An operating method for a full-circular tunnel diameter-changing deformation trolley device
Through the automated design of the fully circular tunnel diameter deformation trolley device, the alternating movement of the needle beam body and the formwork frame body and the accurate positioning of the gradient template are solved, and the problems of slow construction progress and difficult positioning in the existing technology are realized. Efficient and low-cost tunnel diameter construction has been implemented, and the construction quality and progress have been improved.
Patent Information
- Application Number
- CN202110474680.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-04-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2041-04-29
AI Technical Summary
In the construction of existing full-circular tunnels, the speed of manually building the support frame is slow, the materials are numerous, and the labor intensity is high, resulting in slow construction progress and high cost. The positioning support for variable diameter construction is difficult, which is prone to errors and affects the construction quality.
Design a fully circular tunnel diameter deformation trolley device, adopting needle beam body, formwork frame body, screw rod, support cylinder and other components. Through alternating movement and support, the labor intensity is reduced, construction efficiency is improved, and the gradient formwork is used to reduce the intensity of manual labor, improve construction efficiency, and Achieve accurate axial positioning, reduce the use of materials and facilities, and improve construction quality.
By alternating the automatic formwork frame body and the needle beam body, the labor intensity is reduced, the construction progress is improved, the quality of tunnel diameter construction is ensured, the construction cycle is shortened, the cost is reduced, and the efficiency of tunnel engineering construction is improved.
Smart Images

Figure CN113153371B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a full-circle tunnel lining trolley, in particular to an operating method of a full-circle tunnel diameter-changing deformation trolley device. Background Art
[0002] At present, in the existing full-circle tunnel lining pouring construction, most of the full-circle tunnel lining construction formwork is supported by manually building a support frame. Since the speed of manually building a support frame for the full-circle tunnel construction is slow, the materials for construction are large, the labor intensity is large, and it is easy to cause blockage when the construction equipment and materials enter and leave the construction site; in addition, the positioning support for the variable diameter construction of the full-circle tunnel is difficult and prone to errors, which affects the construction quality after the tunnel diameter becomes larger; resulting in high labor costs and slow progress, affecting the progress of construction; in view of the above-mentioned reasons, an operation method of a full-circle tunnel variable diameter deformation trolley device is proposed. Summary of the invention
[0003] The purpose of the present invention is to overcome the existing full-circle tunnel construction, which is slow in speed by manually building a support frame, has a large amount of materials for construction, has a high labor intensity, and is prone to blockage when construction equipment and materials enter and leave the construction site; in addition, the positioning support for the variable diameter construction of the full-circle tunnel is difficult, and errors are prone to occur, which affects the construction quality after the tunnel diameter becomes larger; resulting in high labor costs and slow progress, which affects the progress of construction; now, through reasonable design, an operation method for a full-circle tunnel variable diameter deformation trolley device is provided; a needle beam body is arranged in the template frame of the present invention, and the template frame and the full-circle template are connected by a screw rod and a support cylinder Support or demoulding, remove the screw rod. When removing the screw rod, the top mold and the side mold are supported or contracted for demoulding by the supporting oil cylinder respectively. There is no need to manually build a supporting frame. The template frame and the needle beam body are alternately moved, supported and positioned, which reduces labor intensity and speeds up the construction progress. Gradient template workstations are respectively reserved on the outer sides of the two ends of the needle beam body, and gradient templates are respectively arranged on the gradient template workstations. The gradient template of the present invention has relatively accurate axial positioning, can ensure the quality of the full-circle tunnel diameter change construction, can shorten the construction period, reduce the construction materials and facilities, reduce the construction cost, improve the construction quality, and can speed up the national tunnel engineering construction.
[0004] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: an operation method of a full-circular tunnel diameter-changing deformation trolley device, wherein the full-circular tunnel diameter-changing deformation trolley device is composed of a needle beam body, a track, a template frame body, a door frame, a full-circular template, a first gradual template, a second gradual template, a lifting cylinder mechanism, a rear cylinder seat, a front cylinder seat, a lifting support leg, an anti-floating frame, a gradual template bracket, a walking mechanism, a walking wheel, a screw rod, a supporting cylinder, a top mold, a side mold, a bottom mold, a template interface, a working window, and a template moving mechanism; two pairs of lifting cylinder mechanisms are respectively arranged between the lower part of the two ends of the needle beam body and the ground, and the rear end The lower ends of a pair of lifting cylinder mechanisms are set as rear cylinder seats, and the lower ends of a pair of lifting cylinder mechanisms at the front end are set as front cylinder seats; the outer side of the middle of the needle beam body is set as a template frame, and the outer side of the template frame body is set as a full-circle template, and the full-circle template is provided with a working window; a pair of template moving mechanisms are symmetrically set at both ends of the needle beam body, and pull ropes are respectively set between the pair of template moving mechanisms and the template frame, and a hydraulic pump station is respectively set on one side of the pair of template moving mechanisms; a pair of longitudinal beams are symmetrically set on both sides of the needle beam body, and a pair of rails are set in parallel on the pair of longitudinal beams, and a pair of bottom beams are symmetrically set on both sides of the needle beam body, and a pair of rails are set in parallel under the pair of bottom beams;
[0005] A pair of movable frame longitudinal beams are symmetrically arranged on both sides of the template frame, and a pair of movable frame bottom beams are symmetrically arranged on both sides of the template frame; a pair of movable frame bottom beams and a pair of movable frame longitudinal beams are arranged as a group of movable frame longitudinal beams, and at least three door frames are evenly arranged between a group of movable frame longitudinal beams; corresponding needle beam bodies are reserved in the door frames of at least three door frames as movable channels, and needle beam bodies are arranged in the movable channels;
[0006] The crossbeam at the upper end of the gantry is set as an upper crossbeam, and a lower crossbeam of the gantry is arranged between the lower ends of the door columns of the gantry. A pair of counter-floating frames are arranged on both sides above the front gantry and the rear gantry, and a pair of lifting support legs are arranged on both sides below the front gantry and the rear gantry, and a hydraulic cylinder is arranged in the middle of the lifting support legs; pulleys are arranged above both ends of the front gantry and the rear gantry, and a retractable steel wire rope is arranged between the template moving mechanism and the pulley; two pairs of walking mechanisms are symmetrically arranged on both sides below the upper crossbeam of the front gantry and the rear gantry; two pairs of walking mechanisms are symmetrically arranged on both sides above the lower crossbeam of the front gantry and the rear gantry; the two pairs of walking mechanisms correspond to a pair of tracks under the needle beam body, and a pair of walking wheels are arranged in the walking mechanisms, and wheel grooves are reserved in the middle of the walking wheels, and tracks are respectively arranged in the wheel grooves of the walking wheels;
[0007] The outer sides of the two ends of the needle beam body are symmetrically provided with the first gradient template and the second gradient template, and gradient template brackets are respectively provided between the two sides of the needle beam body and the first gradient template and the second gradient template; the two ends of the first gradient template and the second gradient template are set to different diameters, the small diameter ends of the first gradient template and the second gradient template are set to be the same as the diameter of the full circle template, and the small diameter ends or large diameter ends of the first gradient template and the second gradient template are relatively arranged;
[0008] The top of the template frame is set as a top mold, the bottom of the template frame is set as a bottom mold, the two sides of the template frame are set as side molds, a template interface is reserved between one end of the top mold and the side mold, a screw rod is set between the template frame and the full-circle template, and supporting cylinders are set between the template frame and the top mold and the side mold respectively;
[0009] Before the full-circular variable-diameter deformation trolley enters the tunnel, the full-circular formwork and the lifting cylinder mechanism are in a retracted state; after the full-circular variable-diameter deformation trolley is moved to the entrance of the full-circular tunnel, the formwork frame is supported and axially positioned by hydraulically driving the lifting support legs.
[0010] After the formwork frame is supported and axially positioned, a pair of formwork moving mechanisms are started to rotate synchronously in the same direction. The formwork moving mechanism at the rear end tightens the wire rope, and the formwork moving mechanism at the front end loosens the wire rope. The wire ropes of a pair of formwork moving mechanisms drive the needle beam body to slide forward into the tunnel. After the front section of the needle beam body enters the tunnel construction section, a pair of formwork moving mechanisms are closed and the needle beam body stops moving forward.
[0011] After the needle beam stops moving forward, the needle beam drives the rear cylinder seat and the front cylinder seat to extend and support the ground through the hydraulic rods of the lifting cylinder mechanism at both ends. After the rear cylinder seat and the front cylinder seat are positioned and supported on the ground, they are stable; the lifting support legs at both ends of the template frame are retracted, and a pair of template moving mechanisms are started to rotate synchronously in the same direction. After the front template moving mechanism drives the template frame to move forward along the track to the front section of the needle beam, the pair of template moving mechanisms are closed, the template frame stops moving forward, and the lifting support legs under the two ends of the template frame are extended to support and position the ground of the tunnel;
[0012] After the lifting support legs are extended to support and position the ground of the tunnel, the needle beam body repeats the above process and moves forward to enter the next construction section, and the rear cylinder seat and the front cylinder seat are extended to support the ground; after the needle beam body enters the next construction section again and completes the positioning support; the lifting support legs, the rear cylinder seat and the front cylinder seat at the bottom of the two ends of the formwork frame simultaneously support and position the formwork frame;
[0013] After the support and positioning of the formwork frame is completed, the anti-floating frames above the two ends of the formwork frame extend out to support and position the tunnel top; formwork frame; after the support and positioning of the anti-floating frames are completed, the two sides and top of the formwork frame respectively support the first gradient formwork, the second gradient formwork, and the top formwork outward through the supporting cylinders, and the template interfaces between the second gradient formwork and the top formwork are fixed accordingly to complete the positioning and support of the full-circle formwork; after the positioning and support of the full-circle formwork is completed, the formwork frame and the full-circle formwork are reinforced and supported by screw rods. After the screw rod reinforcement support between the formwork frame and the full-circle formwork is completed, the positioning and support of the full-circle formwork of the trolley device is completed.
[0014] After the full-circle formwork is positioned and supported, the working windows at the bottom, middle and end of the full-circle formwork are opened in sequence to carry out the pouring of the concrete lining; after the concrete on the outside of the full-circle formwork is poured and solidified, the screw rod is removed and the full-circle formwork is demoulded by contracting the supporting cylinder. After the demoulding of the full-circle formwork is completed; the formwork frame and the needle beam are moved, supported and positioned alternately, and the above work process is repeated to carry out the pouring of concrete on the outside of the full-circle formwork.
[0015] When the tunnel is undergoing construction with a larger diameter, the second gradual formwork is used to support and position the concrete pouring construction with the larger diameter; when the tunnel is undergoing construction with a larger diameter, the first gradual formwork is used to support and position the concrete pouring construction with the larger diameter.
[0016] Beneficial effects: a needle beam body is arranged in the template frame of the present invention, and the template frame and the full-circle template are supported or demoulded by means of screw rods and supporting oil cylinders, and the screw rods are removed. When the screw rods are removed, the top template and the side template are supported or contracted for demoulding by the supporting oil cylinders respectively, and there is no need to manually build the supporting frame, and the template frame and the needle beam body are alternately moved, supported and positioned, thereby reducing labor intensity and accelerating the progress of construction; stations for gradual templates are respectively reserved on the outer sides of the two ends of the needle beam body, and gradual templates are respectively arranged on the stations of the gradual templates. The axial positioning of the gradual template of the present invention is relatively accurate, which can ensure the quality of the diameter-changing construction of the full-circle tunnel, shorten the construction period, reduce the materials and facilities for construction, reduce the construction cost, improve the construction quality, and accelerate the national tunnel engineering construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described below in conjunction with the accompanying drawings:
[0018] Figure 1 It is a schematic diagram of the general assembly structure;
[0019] Figure 2 yes Figure 1 Schematic diagram of the local structure of
[0020] Figure 3 yes Figure 2Schematic diagram of the working state structure;
[0021] Figure 4 yes Figure 1 Schematic diagram of the needle beam body and full-circle template structure;
[0022] Figure 5 yes Figure 4 Schematic diagram of the local structure;
[0023] Figure 6 yes Figure 1 Schematic diagram of the template moving frame and template structure;
[0024] Figure 7 yes Figure 6 Schematic diagram of the middle cross-section structure;
[0025] Figure 8 yes Figure 1 Schematic diagram of the beam structure of the needle beam;
[0026] Figure 1 , 2 , 3, 4, 5, 6, 7, 8: needle beam body 1, track 1-1, formwork frame 2, door frame 2-1, full circle formwork 3, first gradual change formwork 4, second gradual change formwork 4-1, lifting cylinder mechanism 5, rear cylinder seat 5-1, front cylinder seat 5-2, lifting support legs 6, anti-floating frame 7, gradual change formwork bracket 8, walking mechanism 9, walking wheel 10, screw 11, supporting cylinder 12, top formwork 13, side formwork 14, bottom formwork 15, formwork interface 16, working window 17, formwork moving mechanism 18. DETAILED DESCRIPTION
[0027] The present invention is further described in detail below in conjunction with embodiments and specific implementation modes:
[0028] Two pairs of lifting cylinder mechanisms 5 are respectively arranged below the two ends of the needle beam body 1 and between the ground, the lower ends of the pair of lifting cylinder mechanisms 5 at the rear end are arranged as rear cylinder seats 5-1, and the lower ends of the pair of lifting cylinder mechanisms 5 at the front end are arranged as front cylinder seats 5-2; the outer side of the middle part of the needle beam body 1 is arranged as a template frame body 2, the outer side of the template frame body 2 is arranged as a full-circle template 3, and the full-circle template 3 is provided with a working window 17; a pair of template moving mechanisms 18 are symmetrically arranged at both ends of the needle beam body 1, and pull ropes are respectively arranged between the pair of template moving mechanisms 18 and the template frame body 2, and a hydraulic pump station is respectively arranged on one side of the pair of template moving mechanisms 18; a pair of longitudinal beams are symmetrically arranged on both sides of the needle beam body 1, and a pair of rails 1-1 are arranged in parallel on the pair of longitudinal beams, and a pair of bottom beams are symmetrically arranged on both sides of the needle beam body 1, and a pair of rails 1-1 are arranged in parallel under the pair of bottom beams;
[0029] A pair of movable frame longitudinal beams are symmetrically arranged on both sides of the template frame 2, and a pair of movable frame bottom beams are symmetrically arranged on both sides of the template frame 2; a pair of movable frame bottom beams and a pair of movable frame longitudinal beams are arranged as a group of movable frame longitudinal beams, and at least three door frames 2-1 are evenly arranged between a group of movable frame longitudinal beams; corresponding needle beam bodies 1 are reserved as movable channels in the door frames of at least three door frames 2-1, and needle beam bodies 1 are arranged in the movable channels;
[0030] The crossbeam at the upper end of the gantry 2-1 is set as an upper crossbeam, and a lower crossbeam of the gantry is arranged between the lower ends of the door columns of the gantry 2-1. A pair of counter-floating frames 7 are arranged on both sides above the front end gantry 2-1 and the rear end gantry 2-1, and a pair of lifting support legs 6 are arranged on both sides below the front end gantry 2-1 and the rear end gantry 2-1, and a hydraulic cylinder is arranged in the middle of the lifting support legs 6; pulleys are arranged above both ends of the front end gantry 2-1 and the rear end gantry 2-1, and a retractable wire rope is arranged between the template moving mechanism 18 and the pulley; two pairs of walking mechanisms 9 are symmetrically arranged on both sides below the upper crossbeam of the front end gantry 2-1 and the rear end gantry 2-1; two pairs of walking mechanisms 9 are symmetrically arranged on both sides above the lower crossbeam of the front end gantry 2-1 and the rear end gantry 2-1; the two pairs of walking mechanisms 9 are arranged corresponding to a pair of tracks 1-1 under the needle beam body 1, and a pair of walking wheels 10 are arranged in the walking mechanisms 9, and wheel grooves are reserved in the middle of the walking wheels 10, and tracks 1-1 are respectively arranged in the wheel grooves of the walking wheels 10;
[0031] The outer sides of the two ends of the needle beam body 1 are configured to symmetrically set the first gradient template 4 and the second gradient template 4-1, and gradient template brackets 8 are respectively set between the two sides of the needle beam body 1 and the first gradient template 4 and the second gradient template 4-1; the two ends of the first gradient template 4 and the second gradient template 4-1 are configured to have different diameters, the small diameter ends of the first gradient template 4 and the second gradient template 4-1 are configured to have the same diameter as the full circle template 3, and the small diameter ends or large diameter ends of the first gradient template 4 and the second gradient template 4-1 are relatively configured;
[0032] The top of the template frame 2 is set as a top mold 13, the bottom of the template frame 2 is set as a bottom mold 15, the two sides of the template frame 2 are set as side molds 14, and a template interface 16 is reserved between one end of the top mold 13 and the side mold 14. A screw rod 11 is set between the template frame 2 and the full-circle template 3, and supporting cylinders 12 are set between the template frame 2 and the top mold 13 and the side mold 14 respectively.
[0033] Before the full-circular variable-diameter deformation trolley enters the tunnel, the full-circular template 3 and the lifting cylinder mechanism 5 are in the retracted state; after the full-circular variable-diameter deformation trolley is moved to the entrance of the full-circular tunnel, the template frame 2 drives the lifting support legs 6 through hydraulic pressure for support and axial positioning.
[0034] Example 2
[0035] After the formwork frame 2 is supported and axially positioned, a pair of formwork moving mechanisms 18 are started to rotate synchronously in the same direction, the formwork moving mechanism 18 at the rear end tightens the wire rope, and the formwork moving mechanism 18 at the front end loosens the wire rope, and the wire ropes of the pair of formwork moving mechanisms 18 drive the needle beam body 1 to slide forward into the tunnel. After the front section of the needle beam body 1 enters the tunnel construction section, the pair of formwork moving mechanisms 18 are closed, and the needle beam body 1 stops moving forward.
[0036] Example 3
[0037] After the needle beam body 1 stops moving forward, the needle beam body 1 drives the rear cylinder seat 5-1 and the front cylinder seat 5-2 to extend and support the ground through the hydraulic rods of the lifting cylinder mechanism 5 at both ends. After the rear cylinder seat 5-1 and the front cylinder seat 5-2 are positioned and supported stably on the ground, the lifting support legs 6 at both ends of the template frame 2 are retracted, and a pair of template moving mechanisms 18 are started to rotate synchronously in the same direction. After the front template moving mechanism 18 drives the template frame 2 to move forward along the track 1-1 to the front section of the needle beam body 1, the pair of template moving mechanisms 18 are closed, the template frame 2 stops moving forward, and the lifting support legs 6 under the two ends of the template frame 2 are extended to support and position the ground of the tunnel;
[0038] After the lifting support legs 6 are extended to support and position with the ground of the tunnel, the needle beam body 1 repeats the above process again and moves forward to enter the next construction section through the rear cylinder seat 5-1 and the front cylinder seat 5-2 to be positioned and supported with the ground; after the needle beam body 1 enters the next construction section again and completes the positioning support; the lifting support legs 6, the rear cylinder seat 5-1, and the front cylinder seat 5-2 under the two ends of the template frame body 2 simultaneously support and position the template frame body 2;
[0039] After the support and positioning of the template frame 2 is completed, the anti-floating frames 7 above the two ends of the template frame 2 extend out to support and position the tunnel top; template frame 2; After the support and positioning of the anti-floating frames 7 are completed, the two sides and the top of the template frame 2 respectively support the first gradient template 4, the second gradient template 4-1, and the top template 13 outward through the supporting cylinders 12, and the template interface 16 between the second gradient template 4-1 and the top template 13 is correspondingly fixed to complete the positioning and support of the full-circle template 3; After the positioning and support of the full-circle template 3 is completed, the template frame 2 and the full-circle template 3 are reinforced and supported by the screw rod 11. After the reinforcement and support of the screw rod 11 between the template frame 2 and the full-circle template 3 is completed, the positioning and support of the full-circle template 3 of the trolley device is completed.
[0040] Example 4
[0041] After the full-circle formwork 3 is positioned and supported, the working windows 17 at the lower, middle and end parts of the full-circle formwork 3 are opened in sequence to carry out the pouring construction of the concrete lining; after the concrete on the outer side of the full-circle formwork 3 is poured and solidified stably, the screw rod 11 is removed, and the full-circle formwork 3 is demoulded by contracting the supporting cylinder 12. After the demoulding of the full-circle formwork 3 is completed; the formwork frame 2 and the needle beam body 1 are alternately moved, supported and positioned, and the above work process is repeated to carry out the pouring construction of the concrete on the outer side of the full-circle formwork 3.
[0042] Example 5
[0043] When the tunnel is undergoing construction with a larger diameter, the second gradual template 4-1 is used to support and position the concrete pouring construction with a larger diameter; when the tunnel is undergoing construction with a larger diameter, the first gradual template 4 is used to support and position the concrete pouring construction with a larger diameter.
Claims
1. An operation method of a full-circular tunnel variable diameter deformation trolley device, wherein the full-circular tunnel variable diameter deformation trolley device is composed of a needle beam body (1), a track (1-1), a template frame body (2), a door frame (2-1), a full-circular template (3), a first gradual change template (4), a second gradual change template (4-1), a lifting cylinder mechanism (5), a rear cylinder seat (5-1), a front cylinder seat (5-2), a lifting support leg (6), an anti-floating frame (7), a gradual change template bracket (8), a walking mechanism (9), a walking wheel (10), a screw rod (11), a supporting cylinder (12), a top mold (13), a side mold (14), a bottom mold (15), a template interface (16), a working window (17), and a template moving mechanism (18); Features: Two pairs of lifting cylinder mechanisms (5) are respectively arranged below the two ends of the needle beam body (1) and between the ground, the lower ends of the pair of lifting cylinder mechanisms (5) at the rear end are arranged as rear cylinder seats (5-1), and the lower ends of the pair of lifting cylinder mechanisms (5) at the front end are arranged as front cylinder seats (5-2); the outer side of the middle part of the needle beam body (1) is arranged as a template frame body (2), the outer side of the template frame body (2) is arranged as a full-circle template (3), and the full-circle template (3) is provided with a working window (17); a pair of template moving mechanisms (18) are symmetrically arranged at the two ends of the needle beam body (1), a pull rope is respectively arranged between the pair of template moving mechanisms (18) and the template frame body (2), and a hydraulic pump station is respectively arranged on one side of the pair of template moving mechanisms (18); a pair of longitudinal beams are symmetrically arranged on both sides of the needle beam body (1), and a pair of rails (1-1) are arranged in parallel on the pair of longitudinal beams; a pair of bottom beams are symmetrically arranged on both sides of the needle beam body (1), and a pair of rails (1-1) are arranged in parallel under the pair of bottom beams; A pair of movable frame longitudinal beams are symmetrically arranged on both sides of the template frame (2), and a pair of movable frame bottom beams are symmetrically arranged on both sides of the template frame (2); the pair of movable frame bottom beams and the pair of movable frame longitudinal beams are arranged as a group of movable frame longitudinal beams, and at least three door frames (2-1) are evenly arranged between the group of movable frame longitudinal beams; the corresponding needle beam bodies (1) in the door frames of the at least three door frames (2-1) are reserved as movable channels, and the needle beam bodies (1) are arranged in the movable channels; The crossbeam at the upper end of the door frame (2-1) is set as an upper crossbeam, and the lower ends of the door columns of the door frame (2-1) are provided with a door frame lower crossbeam. The upper sides of the front door frame (2-1) and the rear door frame (2-1) are provided with a pair of counter-floating frames (7), and the lower sides of the front door frame (2-1) and the rear door frame (2-1) are provided with a pair of lifting support legs (6), and a hydraulic cylinder is provided in the middle of the lifting support legs (6); pulleys are provided above both ends of the front door frame (2-1) and the rear door frame (2-1), and a template moving mechanism (18) is provided between the pulleys. Retracting and releasing the steel wire rope; two pairs of walking mechanisms (9) are symmetrically arranged on both sides below the upper cross beam of the front door frame (2-1) and the rear door frame (2-1); two pairs of walking mechanisms (9) are symmetrically arranged on both sides above the lower cross beam of the front door frame (2-1) and the rear door frame (2-1); the two pairs of walking mechanisms (9) are arranged corresponding to a pair of tracks (1-1) below the needle beam body (1), and a pair of walking wheels (10) are arranged in the walking mechanisms (9), and wheel grooves are reserved in the middle of the walking wheels (10), and the wheel grooves of the walking wheels (10) are respectively provided with tracks (1-1); The outer sides of the two ends of the needle beam body (1) are symmetrically provided with a first gradual template (4) and a second gradual template (4-1), and a gradual template bracket (8) is respectively provided between the two sides of the needle beam body (1) and the first gradual template (4) and the second gradual template (4-1); the two ends of the first gradual template (4) and the second gradual template (4-1) are provided with different diameters, the small diameter ends of the first gradual template (4) and the second gradual template (4-1) are provided with the same diameter as the full-circle template (3), and the small diameter ends or large diameter ends of the first gradual template (4) and the second gradual template (4-1) are provided opposite to each other; The top of the template frame (2) is set as a top mold (13), the bottom of the template frame (2) is set as a bottom mold (15), the two sides of the template frame (2) are set as side molds (14), a template interface (16) is reserved between one end of the top mold (13) and the side mold (14), a screw rod (11) is set between the template frame (2) and the full-circle template (3), and a supporting oil cylinder (12) is set between the template frame (2) and the top mold (13) and the side mold (14). Before the full-circular variable-diameter deformation trolley enters the tunnel, the full-circular template (3) and the lifting cylinder mechanism (5) are in a retracted state; after the full-circular variable-diameter deformation trolley is moved to the entrance of the full-circular tunnel, the template frame (2) drives the lifting support legs (6) through hydraulic pressure to support and axially position.
2. The method for operating the full-circular tunnel diameter-changing deformation trolley device according to claim 1, Features: After the template frame (2) is supported and axially positioned, a pair of template moving mechanisms (18) are started to rotate synchronously in the same direction, the template moving mechanism (18) at the rear end tightens the steel wire rope, and the template moving mechanism (18) at the front end loosens the steel wire rope. The steel wire ropes of the pair of template moving mechanisms (18) drive the needle beam body (1) to slide forward into the tunnel. After the front section of the needle beam body (1) enters the tunnel construction section, the pair of template moving mechanisms (18) are closed, and the needle beam body (1) stops moving forward.
3. The method for operating the full-circular tunnel diameter-changing deformation trolley device according to claim 1, Features: After the needle beam body (1) stops moving forward, the needle beam body (1) drives the rear cylinder seat (5-1) and the front cylinder seat (5-2) to extend and support the ground through the hydraulic rods of the lifting cylinder mechanism (5) at both ends. After the rear cylinder seat (5-1) and the front cylinder seat (5-2) are positioned and supported stably on the ground, the lifting support legs (6) at both ends of the template frame (2) are retracted, and a pair of template moving mechanisms (18) are started to rotate synchronously in the same direction. After the front template moving mechanism (18) drives the template frame (2) to move forward along the track (1-1) to the front section of the needle beam body (1), the pair of template moving mechanisms (18) are closed, the template frame (2) stops moving forward, and the lifting support legs (6) below the two ends of the template frame (2) are extended to support and position the ground of the tunnel; After the lifting support legs (6) are extended to support and position the ground of the tunnel, the needle beam body (1) repeats the above process again and moves forward to enter the next construction section through the rear cylinder seat (5-1) and the front cylinder seat (5-2) to be extended to the ground for positioning support; after the needle beam body (1) enters the next construction section again and completes the positioning support; the lifting support legs (6), the rear cylinder seat (5-1) and the front cylinder seat (5-2) at the lower ends of the template frame body (2) simultaneously support and position the template frame body (2); After the template frame (2) is supported and positioned, the anti-floating frames (7) above the two ends of the template frame (2) extend out to support and position the tunnel top; the template frame (2); after the anti-floating frames (7) are supported and positioned, the two sides and the top of the template frame (2) respectively support the first gradual change template (4), the second gradual change template (4-1), and the top template (13) outwardly through the supporting oil cylinder (12), and after the template interface (16) between the second gradual change template (4-1) and the top template (13) is correspondingly fixed, the positioning support of the full-circle template (3) is completed; after the positioning support of the full-circle template (3) is completed, the template frame (2) and the full-circle template (3) are reinforced and supported by the screw rod (11), and after the reinforcement support of the screw rod (11) between the template frame (2) and the full-circle template (3) is completed, the positioning and support of the full-circle template (3) of the trolley device is completed.
4. The method for operating the full-circular tunnel diameter-changing deformation trolley device according to claim 1, Features: After the positioning and support of the full-circle template (3) are completed, the working windows (17) at the lower, middle and end parts of the full-circle template (3) are opened in sequence to carry out the pouring construction of the concrete lining; after the concrete on the outer side of the full-circle template (3) is poured and solidified stably, the screw rod (11) is removed, and the full-circle template (3) is driven to be demoulded by contraction of the supporting oil cylinder (12), and after the demoulding of the full-circle template (3) is completed; the template frame (2) and the needle beam body (1) are alternately moved, supported and positioned, and the above working process is repeated to carry out the pouring construction of concrete on the outer side of the full-circle template (3).
5. The method for operating the full-circular tunnel diameter-changing deformation trolley device according to claim 1, Features: When the tunnel is undergoing construction with a larger diameter, the second gradual template (4-1) is used to support and position the concrete pouring construction with a larger diameter; when the tunnel is undergoing construction with a larger diameter, the first gradual template (4) is used to support and position the concrete pouring construction with a larger diameter.