A method for treating series and parallel compensation equipment in voltage sag state
By formulating series and parallel compensation equipment management methods for the connection methods of production line equipment under voltage drop, the problems of insufficient adaptability and accuracy in the prior art are solved, and the governance efficiency and use effect are improved.
Patent Information
- Application Number
- CN202110820452.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-07-20
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2041-07-20
AI Technical Summary
The existing treatment methods for voltage drop state compensation equipment are not adaptable and the calculation results are not very accurate, resulting in insufficient understanding of each production line under voltage drop state and poor use effect.
Provide a series-type and parallel-type compensation equipment management method. By determining the power grid status, selecting the target equipment, calculating the equipment size and initial investment, calculating the governance effect and investment recovery period, and formulating targeted according to the connection method of production line equipment to improve adaptability and calculation accuracy.
It improves the governance efficiency and calculation speed, achieves a comprehensive and multi-field understanding of each production line under the voltage drop, and improves the use effect.
Smart Images

Figure CN113659581B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power supply, and in particular to a method for managing series and parallel compensation equipment in a voltage sag state. Background Art
[0002] Voltage sag generally refers to voltage drop. Transient power quality problems mainly include voltage drop, voltage swell and short-term power outage. Voltage sag is defined as the rapid drop of the effective value of the supply voltage to 90%-10% of the rated value, lasting for 0.5 cycles to 1 minute. Under the same duration, if the effective value of the voltage rises rapidly to 110%-180% of the rated value, it is defined as voltage swell. If the duration exceeds 1 minute, it is considered to be low voltage or high voltage. Short-term power outage is defined as a complete loss of power supply, lasting at least 1.5 cycles. Voltage sag is a problem that occurs much more frequently than short-term power outages. Even if the fault is hundreds of kilometers away, it may cause the local voltage amplitude to drop. Once the local voltage sags, it will have an adverse effect on the production line connected to the local power grid. The connection methods of production line equipment and compensation equipment are divided into series and parallel types. The existing voltage sag compensation equipment management method is a universal compensation equipment management method, which cannot be further divided according to the connection method between production line equipment and compensation equipment. The adaptability is not high, and the accuracy of the calculation results in the management process is not high, resulting in the staff's understanding of each production line under the voltage sag state is not accurate enough, and the use effect is not good. Summary of the invention
[0003] The purpose of the present invention is to provide a method for controlling series and parallel compensation equipment in a voltage sag state, which has the advantages of higher pertinence, better adaptability, high control efficiency, faster calculation speed, and convenience for staff to have a comprehensive and multi-field understanding of each production line in the voltage sag state in advance, and poor use effect, so as to solve the problem that the existing voltage sag state compensation equipment control method proposed in the above background technology is a universal compensation equipment control method, which cannot be further divided according to the connection method between the production line equipment and the compensation equipment, has low adaptability, and the accuracy of the calculation results in the control process is not high, resulting in the staff's understanding of each production line in the voltage sag state is not accurate enough and the use effect is poor.
[0004] To achieve the above object, the present invention provides the following technical solution: a method for managing series and parallel compensation equipment in a voltage sag state, comprising the following steps:
[0005] S1: Determine the grid status, read the grid access level of the assessed user in the selected time period, and determine whether there is a voltage sag in the selected time period;
[0006] S2: Select target devices for series compensation devices and parallel compensation devices. In the entire production line, select the target sensitive devices in the production line sensitive device set with the highest expected profit in the next ten years;
[0007] S3: Calculate the equipment size of the series compensation equipment and the parallel compensation equipment. The size calculation method of the series compensation equipment and the parallel compensation equipment is shown in Table 1 and Table 2:
[0008] Table 1. Calculation method of equipment size of series compensation equipment
[0009]
[0010] Table 2. Calculation method of equipment size of parallel compensation equipment
[0011]
[0012] S4: Calculation of initial investment for series compensation equipment and parallel compensation equipment. The one-time purchase price of series compensation equipment is defined as C 串联0 , the one-time purchase price of the parallel compensation equipment is defined as C 并联0 , the following formula is used to calculate the initial investment of series compensation equipment and the initial investment of parallel compensation equipment:
[0013] C 串联 =C 串联0 ×P 串联
[0014] C 并联 =C 并联0 ×P 并联
[0015] Among them, C 串联 is the initial investment of the series compensation equipment, C 串联0 is the one-time purchase price of the series compensation equipment, P 串联 is the total capacity of the target equipment of the series compensation device, C 并联 is the initial investment of the parallel compensation equipment, C 并联0 is the one-time purchase price of the parallel compensation equipment, P 并联 The total capacity of the target equipment for the parallel type compensation equipment;
[0016] S5: The calculation of the treatment effect of the series compensation equipment and the parallel compensation equipment includes the following steps:
[0017] A: Calculate the economic loss that may be caused each year when the selected production line i is not equipped with treatment equipment according to the grid access level, and define it as , the economic loss calculation formula is divided into two modes: mode 1 and mode 2, and the annual economic losses of the selected production line under the two modes are calculated respectively;
[0018] B: Calculate the failure rate of series compensation equipment and parallel compensation equipment;
[0019] C: Set the failure rate of the target equipment of the series compensation equipment to 0, recalculate the failure rate of the target equipment of the parallel compensation equipment and the corresponding production line interruption probability, and use the method in step A to calculate the economic loss after installing the treatment equipment again, and define it as and ;
[0020] D: calculated in step C and Based on the data, the temporary sag loss that can be reduced by installing series compensation equipment and parallel compensation equipment to treat the target equipment each year is calculated. The temporary sag loss that can be reduced by installing series compensation equipment is defined as R 串联0 The annual reduction in temporary sag loss by installing parallel compensation equipment is defined as R 并联0 ;
[0021] S6: Calculation of investment payback period for series compensation equipment and parallel compensation equipment, based on R 串联0 Calculate the annual investment recovery R after installing series compensation equipment to treat the target equipment 串联 , according to R 并联0 Calculate the annual investment recovery R after installing parallel compensation equipment to treat the target equipment 并联 .
[0022] Preferably, the target device selection steps of the series compensation device and the parallel compensation device in S2 are as follows:
[0023] Assume that the decision vector for installing series compensation equipment is:
[0024]
[0025] Among them, x i The value of x is 0 or 1. i =1 means installing series compensation equipment to treat target sensitive equipment i, x i =0 means that no series compensation equipment is installed to treat the target sensitive equipment i, and n is the number of sensitive equipment in the selected production line; then the total power of the target sensitive equipment of the series compensation equipment is:
[0026]
[0027] Among them, P 串联is the total power of the target sensitive equipment of the series compensation equipment of the selected production line, P i is the power of the i-th equipment in the selected production line;
[0028] Assume that the decision vector for installing parallel compensation equipment is:
[0029]
[0030] Among them, x i The value of x is 0 or 1. i =1 means to install parallel compensation equipment to treat the target sensitive device i, x i =0 means that no parallel compensation equipment is installed to treat the target sensitive equipment i, and n is the number of sensitive equipment in the selected production line; then the total power of the target sensitive equipment in the parallel compensation equipment set is:
[0031]
[0032] Among them, P 并联 is the total power of the target sensitive equipment of the selected production line, P i is the power of the i-th equipment in the selected production line.
[0033] Preferably, in step A of S5, the access level of the power grid is counted by software, and the results of the software counting the access level of the power grid are shown in Table 3:
[0034] Table 3. Software statistics on grid access level
[0035]
[0036] Preferably, in step A described in S5, the formula for calculating the economic loss in one year in mode 1 is:
[0037]
[0038] Where i is the name of the selected production line, N(V,T) is the annual frequency of sags with amplitude and duration (V,T), is the probability of interruption of production line i when the voltage sag amplitude and duration are (V, T), is the capacity loss caused by the interruption of production line i, is the raw material loss caused by the interruption of production line i, is the equipment loss caused by the interruption of production line i, and Lenth is the length of the selected time period;
[0039] The formula for calculating economic losses in one year in Model 2 is:
[0040]
[0041] Where i is the name of the selected production line, N(V,T) is the annual frequency of sags with amplitude and duration (V,T), is the probability of interruption of production line i when the voltage sag amplitude and duration are (V, T), is the capacity loss caused by the interruption of production line i, is the probability of failure of sensitive equipment j in production line i that will cause a specific loss of raw materials when the voltage sag amplitude and duration are (V, T), is the corresponding raw material loss, is the probability of failure of electrical equipment k in production line i that will cause a specific equipment loss when the voltage sag amplitude and duration are (V, T), is the corresponding equipment loss, Lenth is the length of the selected time period;
[0042] The calculation formula of Lenth is:
[0043] Lenth=12(year end -year start )+(month end -month start +1)
[0044] where year end The selected end year, month end The selected end month, year start is the selected starting year, month start is the selected starting month.
[0045] Preferably, in step B of S5, the formula for calculating the failure rate of the series compensation device is:
[0046]
[0047] k=1,2,…,r
[0048] Among them, when x k =1 means that a series compensation device is installed to treat the target sensitive device k. At this time, A(x k )=0, then =0; when x k = 0 means that a series compensation device is installed to treat the target sensitive device k. At this time, A(x i )=1, then = ; The above two formulas can be used to set the failure rate of the target device to 0.
[0049] Preferably, in step B described in S5, when calculating the failure rate of the parallel compensation device, for sensitive equipment without compensation device installed, the two knee points (Tmin, Umax) of its tolerance curve, (Tmax, Umin) are used to calculate its failure rate P (V, T) under a certain sag (T0, U0). When the parallel compensation device is installed, the amplitude of the sag input is:
[0050]
[0051] Among them, U is the compensation capacity of the compensation equipment, It is the input amplitude used to calculate the failure rate of sensitive equipment after the parallel compensation equipment is installed. That is, after the parallel compensation equipment is installed, the duration and amplitude of the temporary sag suffered by the sensitive equipment are (T0, ), and then calculate the failure rate P of the equipment ’ (V, T).
[0052] Preferably, in step D described in S5, installing a series compensation device can reduce the temporary sag loss R per year. 串联0 = - , installing parallel compensation equipment can reduce the temporary loss R every year 并联0 = - 。
[0053] Preferably, the investment payback period calculation process of the series compensation equipment in S6 is as follows:
[0054] The following formula is used to calculate the annual investment recovery R after installing series compensation equipment to treat the target equipment: 串联 :
[0055] R 串联 =R 串联0 -Coefficient 串联 *C 串联
[0056] Where R 串联0 The annual reduction in temporary sag loss after installing series compensation equipment to treat the target equipment, Coefficient 串联 is the annual maintenance cost coefficient of the series compensation equipment, C 串联 is the initial investment of the series compensation equipment, then the investment payback period is T 串联 T 串联 =C 串联 / R 串联 , when T 串联 If it is not an integer, round it up;
[0057] The calculation process of the investment payback period of the parallel compensation equipment in S6 is as follows:
[0058] The following formula is used to calculate the annual investment recovery R after installing parallel compensation equipment to treat the target equipment: 并联 :
[0059] R 并联 =R 并联0 -Coefficient 并联 *C 并联
[0060] Where R 并联0 The annual reduction in sag loss after installing parallel compensation equipment to treat the target equipment, Coefficient 并联 is the annual maintenance cost coefficient of the parallel compensation equipment, C 并联 is the initial investment of parallel compensation equipment, and the investment payback period is T 并联 T 并联 =C 并联 / R 并联 , when T 并联 If it is not an integer, round it up.
[0061] The present invention proposes a method for treating series and parallel compensation devices in a voltage sag state, which has the following beneficial effects:
[0062] This method for controlling series and parallel compensation equipment in a voltage sag state formulates control methods for series compensation equipment and parallel compensation equipment according to the different connection methods of production line equipment. Compared with traditional general control methods, this method is more targeted and has better adaptability. The target equipment is selected for the entire production line rather than a single user during control, which effectively improves control efficiency and speeds up calculation. After using software to count the level of grid access, the economic loss is divided into two modes for calculation. Combined with the different failure rates of series and parallel compensation equipment, the control effect calculation of series compensation equipment and parallel compensation equipment is realized, and based on the control effect, the investment payback period of series compensation equipment and parallel compensation equipment is obtained, which is convenient for staff to have a comprehensive and multi-field understanding of each production line under the voltage sag state in advance. BRIEF DESCRIPTION OF THE DRAWINGS
[0063] Figure 1 The present invention is a flowchart of a method for managing a voltage sag state using series and parallel compensation equipment. DETAILED DESCRIPTION
[0064] The technical solutions in the embodiments of the present invention will be explained clearly below in conjunction with the drawings in the embodiments of the present invention; it is obvious that the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0065] See also Figure 1 , a method for managing series and parallel compensation equipment in a voltage sag state, comprising the following steps:
[0066] Step 1: Determine the grid status, read the grid access level of the evaluated user within the selected time period, and determine whether there is a voltage sag within the selected time period. If there is no voltage sag, this algorithm ends directly. If there is a voltage sag, it is managed by using a series compensation device management method or a parallel compensation device management method according to the specific connection method of the equipment.
[0067] Step 2: Select target devices for series compensation devices and parallel compensation devices. In the entire production line, select the target sensitive devices in the production line sensitive device set with the highest expected profit in the next ten years. The target device selection steps for series compensation devices and parallel compensation devices are as follows:
[0068] Assume that the decision vector for installing series compensation equipment is:
[0069]
[0070] Among them, x i The value of x is 0 or 1. i =1 means installing series compensation equipment to treat target sensitive equipment i, x i =0 means that no series compensation equipment is installed to treat the target sensitive equipment i, and n is the number of sensitive equipment in the selected production line; then the total power of the target sensitive equipment of the series compensation equipment is:
[0071]
[0072] Among them, P 串联 is the total power of the target sensitive equipment of the series compensation equipment of the selected production line, P i is the power of the i-th equipment in the selected production line;
[0073] Assume that the decision vector for installing parallel compensation equipment is:
[0074]
[0075] Among them, x iThe value of x is 0 or 1. i =1 means to install parallel compensation equipment to treat the target sensitive device i, x i =0 means that no parallel compensation equipment is installed to treat the target sensitive equipment i, and n is the number of sensitive equipment in the selected production line; then the total power of the target sensitive equipment in the parallel compensation equipment set is:
[0076]
[0077] Among them, P 并联 is the total power of the target sensitive equipment of the selected production line, P i is the power of the i-th equipment in the selected production line.
[0078] Step 3: Calculate the equipment size of the series compensation equipment and the parallel compensation equipment. The size calculation method of the series compensation equipment and the parallel compensation equipment is shown in Table 1 and Table 2:
[0079] Table 1. Calculation method of equipment size of series compensation equipment
[0080]
[0081] Table 2. Calculation method of equipment size of parallel compensation equipment
[0082]
[0083] Step 4: Calculate the initial investment of series compensation equipment and parallel compensation equipment. Define the one-time purchase price of series compensation equipment as C 串联0 , the one-time purchase price of the parallel compensation equipment is defined as C 并联0 , the following formula is used to calculate the initial investment of series compensation equipment and the initial investment of parallel compensation equipment:
[0084] C 串联 =C 串联0 ×P 串联
[0085] C 并联 =C 并联0 ×P 并联
[0086] Among them, C 串联 is the initial investment of the series compensation equipment, C 串联0 is the one-time purchase price of the series compensation equipment, P 串联 is the total capacity of the target equipment of the series compensation device, C 并联 is the initial investment of the parallel compensation equipment, C 并联0 is the one-time purchase price of the parallel compensation equipment, P 并联The total capacity of the target device for the parallel type compensation device.
[0087] Step 5: Calculation of the treatment effect of series compensation equipment and parallel compensation equipment, including the following steps:
[0088] A: Calculate the economic loss that may be caused each year when the selected production line i is not equipped with treatment equipment according to the grid access level, and define it as , the access level of the power grid is counted by software, and the results of the software counting the access level of the power grid are shown in Table 3:
[0089] Table 3. Software statistics on grid access level
[0090]
[0091] The economic loss calculation formula is divided into two modes: mode 1 and mode 2, and the annual economic loss of the selected production line under the two modes is calculated respectively;
[0092] The formula for calculating economic losses in one year in Model 1 is:
[0093]
[0094] Where i is the name of the selected production line, N(V,T) is the annual frequency of sags with amplitude and duration (V,T), is the probability of interruption of production line i when the voltage sag amplitude and duration are (V, T), is the capacity loss caused by the interruption of production line i, is the raw material loss caused by the interruption of production line i, is the equipment loss caused by the interruption of production line i, and Lenth is the length of the selected time period;
[0095] The formula for calculating economic losses in one year in Model 2 is:
[0096]
[0097] Where i is the name of the selected production line, N(V,T) is the annual frequency of sags with amplitude and duration (V,T), is the probability of interruption of production line i when the voltage sag amplitude and duration are (V, T), is the capacity loss caused by the interruption of production line i, is the probability of failure of sensitive equipment j in production line i that will cause a specific loss of raw materials when the voltage sag amplitude and duration are (V, T), is the corresponding raw material loss, is the probability of failure of electrical equipment k in production line i that will cause a specific equipment loss when the voltage sag amplitude and duration are (V, T), is the corresponding equipment loss, Lenth is the length of the selected time period;
[0098] The calculation formula of Lenth is:
[0099] Lenth=12(year end -year start )+(month end -month start +1)
[0100] where year end The selected end year, month end The selected end month, year start is the selected starting year, month start is the selected starting month.
[0101] B: Calculate the failure rate of series compensation equipment and parallel compensation equipment. The formula for calculating the failure rate of series compensation equipment is:
[0102]
[0103] k=1,2,…,r
[0104] Among them, when x k =1 means that a series compensation device is installed to treat the target sensitive device k. At this time, A(x k )=0, then =0; when x k = 0 means that a series compensation device is installed to treat the target sensitive device k. At this time, A(x i )=1, then = ; The above two formulas can set the failure rate of the target device to 0;
[0105] When calculating the failure rate of parallel compensation equipment, for sensitive equipment without compensation devices installed, the two knee points (Tmin, Umax) of the tolerance curve (Tmax, Umin) are used to calculate its failure rate P (V, T) under a certain sag (T0, U0). When the parallel compensation equipment is installed, the amplitude of the sag input is:
[0106]
[0107] Among them, U is the compensation capacity of the compensation equipment, It is the input amplitude used to calculate the failure rate of sensitive equipment after the parallel compensation equipment is installed. That is, after the parallel compensation equipment is installed, the duration and amplitude of the temporary sag suffered by the sensitive equipment are (T0, ), and then calculate the failure rate P of the equipment ’ (V, T).
[0108] C: Set the failure rate of the target equipment of the series compensation equipment to 0, recalculate the failure rate of the target equipment of the parallel compensation equipment and the corresponding production line interruption probability, and use the method in step A to calculate the economic loss after installing the treatment equipment again, and define it as and .
[0109] D: calculated in step C and Based on the data, the temporary sag loss that can be reduced by installing series compensation equipment and parallel compensation equipment to treat the target equipment each year is calculated. The temporary sag loss that can be reduced by installing series compensation equipment is defined as R 串联0 The annual reduction in temporary sag loss by installing parallel compensation equipment is defined as R 并联0 , installing series compensation equipment can reduce the temporary sag loss R every year 串联0 = - , installing parallel compensation equipment can reduce the temporary loss R every year 并联0 = - .
[0110] Step 6: Calculation of the payback period of series compensation equipment and parallel compensation equipment, based on R 串联0 Calculate the annual investment recovery R after installing series compensation equipment to treat the target equipment 串联 , according to R 并联0 Calculate the annual investment recovery R after installing parallel compensation equipment to treat the target equipment 并联 ;
[0111] The calculation process of the investment payback period of series compensation equipment is as follows:
[0112] The following formula is used to calculate the annual investment recovery R after installing series compensation equipment to treat the target equipment: 串联 :
[0113] R 串联 =R 串联0 -Coefficient 串联 *C 串联
[0114] Where R 串联0The annual reduction in temporary sag loss after installing series compensation equipment to treat the target equipment, Coefficient 串联 is the annual maintenance cost coefficient of the series compensation equipment, C 串联 is the initial investment of the series compensation equipment, then the investment payback period is T 串联 T 串联 =C 串联 / R 串联 , when T 串联 If it is not an integer, round it up;
[0115] The calculation process of the investment payback period of the parallel compensation equipment in S6 is as follows:
[0116] The following formula is used to calculate the annual investment recovery R after installing parallel compensation equipment to treat the target equipment: 并联 :
[0117] R 并联 =R 并联0 -Coefficient 并联 *C 并联
[0118] Where R 并联0 The annual reduction in sag loss after installing parallel compensation equipment to treat the target equipment, Coefficient 并联 is the annual maintenance cost coefficient of the parallel compensation equipment, C 并联 is the initial investment of parallel compensation equipment, and the investment payback period is T 并联 T 并联 =C 并联 / R 并联 , when T 并联 If it is not an integer, round it up.
[0119] To sum up, the present method for controlling series and parallel compensation equipment in voltage sag state formulates control methods for series compensation equipment and parallel compensation equipment according to the different connection methods of production line equipment. Compared with the traditional general control method, it is more targeted and has better adaptability. The selection of target equipment during control is for the entire production line rather than a single user, which effectively improves the control efficiency and speeds up the calculation. After using software to count the grid access level, the economic losses are divided into two modes for calculation. Combined with the different failure rates of series and parallel compensation equipment, the control effect calculation of series compensation equipment and parallel compensation equipment is realized, and according to the control effect, the investment payback period of series compensation equipment and parallel compensation equipment is obtained, which is convenient for the staff to have a comprehensive and multi-field understanding of each production line under the voltage sag state in advance, and the use effect is not good.
[0120] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for treating series and parallel compensation equipment in a voltage sag state, characterized in that: The following steps are involved: S1: Determine the grid status, read the grid access level of the assessed user in the selected time period, and determine whether there is a voltage sag in the selected time period; S2: Select target devices for series compensation devices and parallel compensation devices. In the entire production line, select the target sensitive devices in the production line sensitive device set with the highest expected profit in the next ten years; S3: Calculate the equipment size of the series compensation equipment and the parallel compensation equipment. The size calculation method of the series compensation equipment and the parallel compensation equipment is shown in Table 1 and Table 2: Table 1. Calculation method of equipment size of series compensation equipment Table 2. Calculation method of equipment size of parallel compensation equipment S4: Calculation of initial investment for series compensation equipment and parallel compensation equipment. The one-time purchase price of series compensation equipment is defined as C 串联0 , the one-time purchase price of the parallel compensation equipment is defined as C 并联0 , the following formula is used to calculate the initial investment of series compensation equipment and the initial investment of parallel compensation equipment: C 串联 =C 串联0 ×P 串联 C 并联 =C 并联0 ×P 并联 Among them, C 串联 is the initial investment of the series compensation equipment, C 串联0 is the one-time purchase price of the series compensation equipment, P 串联 is the total capacity of the target equipment of the series compensation device, C 并联 is the initial investment of the parallel compensation equipment, C 并联0 is the one-time purchase price of the parallel compensation equipment, P 并联 The total capacity of the target equipment for the parallel type compensation equipment; S5: The calculation of the treatment effect of the series compensation equipment and the parallel compensation equipment includes the following steps: A: Calculate the economic loss that may be caused each year when the selected production line i is not equipped with treatment equipment according to the grid access level, and define it as The economic loss calculation formula is divided into two modes: mode 1 and mode 2, and the annual economic loss of the selected production line under the two modes is calculated respectively; B: Calculate the failure rate of series compensation equipment and parallel compensation equipment; C: Set the failure rate of the target equipment of the series compensation equipment to 0, recalculate the failure rate of the target equipment of the parallel compensation equipment and the corresponding production line interruption probability, and use the method in step A to calculate the economic loss after installing the treatment equipment again, and define it as and D: calculated in step C and Based on the data, the temporary sag loss that can be reduced by installing series compensation equipment and parallel compensation equipment to treat the target equipment each year is calculated. The temporary sag loss that can be reduced by installing series compensation equipment is defined as R 串联0 The annual reduction in temporary sag loss by installing parallel compensation equipment is defined as R 并联0 ; S6: Calculation of investment payback period for series compensation equipment and parallel compensation equipment, based on R 串联0 Calculate the annual investment recovery R after installing series compensation equipment to treat the target equipment 串联 , according to R 并联0 Calculate the annual investment recovery R after installing parallel compensation equipment to treat the target equipment 并联 ; In step A of S5, the formula for calculating the economic loss in one year in model 1 is: Where i is the name of the selected production line, N(V,T) is the annual frequency of sags with amplitude and duration (V,T), is the probability of interruption of production line i when the voltage sag amplitude and duration are (V, T), is the capacity loss caused by the interruption of production line i, is the raw material loss caused by the interruption of production line i, is the equipment loss caused by the interruption of production line i, and Lenth is the length of the selected time period; The formula for calculating economic losses in one year in Model 2 is: Where i is the name of the selected production line, N(V,T) is the annual frequency of sags with amplitude and duration (V,T), is the probability of interruption of production line i when the voltage sag amplitude and duration are (V, T), is the capacity loss caused by the interruption of production line i, is the probability of failure of sensitive equipment j in production line i that will cause a specific raw material loss when the voltage sag amplitude and duration are (V, T), is the corresponding raw material loss, is the probability of failure of electrical equipment k in production line i that will cause a specific equipment loss when the voltage sag amplitude and duration are (V, T), is the corresponding equipment loss, Lenth is the length of the selected time period; The calculation formula of Lenth is: Lenth=12(year end -year start )+(month end -month start +1) where year end The selected end year, month end The selected end month, year start is the selected starting year, month start is the selected starting month.
2. A method for treating series and parallel compensation equipment in a voltage sag state according to claim 1, characterized in that: The target device selection steps for the series compensation device and the parallel compensation device described in S2 are as follows: Assume that the decision vector for installing series compensation equipment is: X UPS =[x1 x2…x n ] Among them, x i The value of x is 0 or 1. i =1 represents the installation of series compensation equipment to treat the target sensitive device i, x i =0 means that no series compensation equipment is installed to treat the target sensitive equipment i, and n is the number of sensitive equipment in the selected production line; then the total power of the target sensitive equipment of the series compensation equipment is: Among them, P 串联 is the total power of the target sensitive equipment of the series compensation equipment of the selected production line, P i is the power of the i-th equipment in the selected production line; Assume that the decision vector for installing parallel compensation equipment is: X 并联 =[x1 x2…x n ] Among them, x i The value of x is 0 or 1. i =1 represents the installation of parallel compensation equipment to treat the target sensitive device i, x i =0 means that no parallel compensation equipment is installed to treat the target sensitive equipment i, and n is the number of sensitive equipment in the selected production line; then the total power of the target sensitive equipment in the parallel compensation equipment set is: Among them, P 并联 is the total power of the target sensitive equipment of the selected production line, P i is the power of the i-th device in the selected production line.
3. A method for treating series and parallel compensation equipment in voltage sag state according to claim 1, characterized in that: In step A of S5, the access level of the power grid is counted by software, and the results of the software counting the access level of the power grid are shown in Table 3: Table 3. Software statistics on grid access level 4. A method for treating series and parallel compensation equipment in a voltage sag state according to claim 1, characterized in that: In step B described in S5, the formula for calculating the failure rate of the series compensation device is: A=[1 0] P k (V,T)=A(x k +1)×P k (V,T)k=1,2,…,r Among them, when x k =1 means that a series compensation device is installed to treat the target sensitive device k. At this time, A(x k )=0, then P k (V,T)=0; when x k = 0 means that no series compensation equipment is installed to treat the target sensitive device k. At this time, A(x i )=1, then P i (V,T)=P i (V,T); The above two formulas can be used to set the failure rate of the target device to 0.
5. A method for treating series and parallel compensation equipment in a voltage sag state according to claim 1, characterized in that: In step B described in S5, when calculating the failure rate of the parallel compensation device, for the sensitive equipment without compensation device installed, the two knee points (Tmin, Umax) and (Tmax, Umin) of its tolerance curve are used to calculate its failure rate P(V, T) under a certain sag (T0, U0). When the parallel compensation device is installed, the amplitude of the sag input is: Among them, U is the compensation capacity of the compensation device, U'0 is the input amplitude used to calculate the failure rate of the sensitive device after the parallel compensation device is installed, that is, after the parallel compensation device is installed, the duration and amplitude of the temporary sag suffered by the sensitive device are (T0, U'0), and then the failure rate P'(V, T) of the device is calculated.
6. A method for treating series and parallel compensation equipment in a voltage sag state according to claim 1, characterized in that: In step D of S5, installing series compensation equipment can reduce the temporary sag loss every year. Installing parallel compensation equipment can reduce temporary sag losses every year 7. A method for treating series and parallel compensation equipment in voltage sag state according to claim 1, characterized in that: The calculation process of the investment payback period of the series compensation equipment described in S6 is as follows: The following formula is used to calculate the annual investment recovery R after installing series compensation equipment to treat the target equipment: 串联 : R 串联 =R 串联0 -Coefficient 串联 *C 串联 Where R 串联0 The annual reduction in temporary sag loss after installing series compensation equipment to treat the target equipment, Coefficient 串联 is the annual maintenance cost coefficient of the series compensation equipment, C 串联 is the initial investment of the series compensation equipment, then the investment payback period is T 串联 T 串联 =C 串联 / R 串联 , when T 串联 If it is not an integer, round it up; The calculation process of the investment payback period of the parallel compensation equipment in S6 is as follows: The following formula is used to calculate the annual investment recovery R after installing parallel compensation equipment to treat the target equipment: 并联 : R 并联 =R 并联0 -Coefficient 并联 *C 并联 Where R 并联0 The annual reduction in sag loss after installing parallel compensation equipment to treat the target equipment, Coefficient 并联 is the annual maintenance cost coefficient of the parallel compensation equipment, C 并联 is the initial investment of parallel compensation equipment, and the investment payback period is T 并联 T 并联 =C 并联 / R 并联 , when T 并联 If it is not an integer, round it up.