A method and device for determining shield machine equipment utilization rate and process time
By counting the time stamps of continuous excavation and assembly periods during the shield construction process, the total excavation, assembly and downtime of the shield machine equipment was calculated, and the problems of low accuracy and low efficiency in the existing technology were solved, achieving more accurate Equipment utilization rate and process time calculation.
Patent Information
- Application Number
- CN202111086341.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-16
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2041-09-16
Smart Images

Figure CN113918887B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method and a device for determining the utilization rate of shield machine equipment and the time required for a process, and belongs to the technical field of production process control at a shield construction site. Background Art
[0002] In the field of shield construction, due to the characteristics of cyclic construction, the industry will basically carry out on-site process construction according to the production industry management model. As the core equipment of shield construction, the shield machine is divided into three major process categories on site according to its status: excavation, assembly, and shutdown. Single-loop production will include excavation, assembly, and shutdown to complete a closed loop. The calculation of shield machine equipment utilization and process time is of great significance for measuring shield construction efficiency, estimating construction costs, and improving project management efficiency.
[0003] The existing equipment utilization rate and process time calculation methods generally record the time spent on excavation, assembly, and shutdown by the on-site shield driver during the construction process, and also use direct feedback from the shield machine to determine the corresponding time of each state. Therefore, the current method relies on on-site statistics by the driver or other engineering personnel, which is highly subjective, has poor calculation accuracy, and is time-consuming and labor-intensive. On the other hand, due to the inconsistent frequency of data collection, the time intervals between the two adjacent excavation data obtained are not equal, which brings certain challenges and difficulties to the automatic calculation of the time spent on each process. In addition, when calculating the time spent on the excavation process, considering that the shield machine discharges slag intermittently through the slag truck, which is different from the TBM discharging slag through the continuous belt, the equipment is not continuously excavated during the construction process, so the calculation of the pure excavation time of the shield machine needs to remove the time spent waiting for the slag truck to enter the hole or pour slag. When calculating the time spent on segment assembly, the equipment is in a state of stopping excavation, and the segments are assembled by grabbing the segments with the help of the grab head. However, considering that during the assembly process, there are abnormal situations such as waiting for segment transportation and damaged segments waiting for replacement, the calculation of shield assembly time needs to exclude the time waiting for segment transportation and damaged segments waiting for replacement.
[0004] Therefore, the current method for determining shield machine equipment utilization and process time cannot accurately determine the time for each process and equipment utilization, and the efficiency is relatively low. Summary of the invention
[0005] The purpose of the present invention is to provide a method and device for determining the utilization rate of shield machine equipment and the time required for a process, so as to solve the problems of low accuracy and low efficiency existing in the current process of determining the utilization rate of shield machine equipment and the time required for a process.
[0006] In order to solve the above technical problems, the present invention provides a method for determining the time taken for a shield machine process, the method comprising the following steps:
[0007] 1) Obtaining tunneling parameters during shield construction, wherein the tunneling parameters include ring number, total thrust, segment assembly mode, tunneling mode and state parameters;
[0008] 2) According to the excavation mode of the current ring, the data of each continuous excavation section is filtered out according to the excavation mode value corresponding to the excavation process, and the start timestamp and end timestamp of each continuous excavation section are obtained to obtain the excavation time of each continuous excavation section of the current ring, and the excavation time of each continuous excavation section is summed to obtain the total excavation time of the current ring;
[0009] 3) According to the segment assembly mode of the current ring, the data of each continuous assembly section is filtered out according to the segment assembly mode value corresponding to the assembly process, and the start timestamp and the end timestamp of each continuous assembly section are obtained to obtain the assembly time of each continuous assembly section of the current ring, and the assembly time of each continuous assembly section is summed to obtain the total assembly time of the current ring;
[0010] 4) Obtain the start timestamp and end timestamp of the shield machine equipment of the current ring number, calculate the total time of the shield machine equipment in the current ring, subtract the total excavation time of the current ring and the total assembly time of the current ring from the total time to obtain the total downtime of the current ring.
[0011] The present invention also provides a device for determining the time required for a shield machine equipment process, characterized in that the device includes a processor and a memory, and the processor executes a computer program stored in the memory to implement the method for determining the time required for a shield machine equipment process described in the present invention.
[0012] The present invention counts the timestamps of each continuous excavation section and assembly section in each ring, thereby calculating the time of each continuous excavation section and the time of each assembly section, and finally counts the total excavation time and total assembly time of each ring, and determines the time of each process of the shield machine equipment of the corresponding ring according to the total time of each ring. The present invention takes into account the situation that the excavation and assembly of each ring in the construction process of the shield machine equipment are not continuous, and the calculated time of each process is closer to the actual construction situation, and the calculated time of each process is high in accuracy and is not affected by the uneven sampling frequency, which provides an important basis for subsequent control and research.
[0013] Furthermore, in order to accurately determine the excavation parameters of each ring, the method also includes determining the excavation parameters of the same ring according to the ring number.
[0014] Furthermore, in order to ensure the accuracy of the tunneling state identification, the method also includes re-inspecting the tunneling state, and the re-inspection process is:
[0015] Get the total thrust parameters under the current ring number conditions. If the total thrust is greater than 0 and the data length of the total thrust is greater than or equal to 5, it means that the excavation re-inspection conditions are met.
[0016] Furthermore, the start timestamp and the end timestamp are obtained according to the corresponding indexes.
[0017] The present invention also provides a method for determining the utilization rate of a shield machine, the method comprising the following steps:
[0018] 1) Obtaining tunneling parameters during shield construction, wherein the tunneling parameters include ring number, total thrust, segment assembly mode, tunneling mode and state parameters;
[0019] 2) According to the excavation mode of the current ring, the data of each continuous excavation section is filtered out according to the excavation mode value corresponding to the excavation process, and the start timestamp and end timestamp of each continuous excavation section are obtained to obtain the excavation time of each continuous excavation section of the current ring, and the excavation time of each continuous excavation section is summed to obtain the total excavation time of the current ring;
[0020] 3) According to the segment assembly mode of the current ring, the data of each continuous assembly section is filtered out according to the segment assembly mode value corresponding to the assembly process, and the start timestamp and the end timestamp of each continuous assembly section are obtained to obtain the assembly time of each continuous assembly section of the current ring, and the assembly time of each continuous assembly section is summed to obtain the total assembly time of the current ring;
[0021] 4) Obtain the start timestamp and end timestamp of the shield machine equipment in the current ring number, calculate the total time of the shield machine equipment in the current ring, and calculate the equipment utilization rate of the shield machine equipment in each ring based on the total excavation time, total assembly time and total time of each ring.
[0022] The present invention counts the timestamps of each continuous excavation section and assembly section in each ring, thereby calculating the time of each continuous excavation section and the time of each assembly section, and finally counts the total excavation time and total assembly time of each ring, and determines the shield machine equipment utilization rate of the corresponding ring according to the total time of each ring. The present invention takes into account the situation that the excavation and assembly of each ring in the shield machine equipment construction process are not continuous, and the calculated equipment utilization rate is closer to the actual construction situation, the calculated equipment utilization rate has high accuracy, and is not affected by the uneven sampling frequency, which provides an important basis for subsequent control and research.
[0023] The present invention also provides a device for determining the utilization rate of a shield machine, which includes a processor and a memory. The processor executes a computer program stored in the memory to implement the method for determining the utilization rate of a shield machine according to the present invention.
[0024] Furthermore, the calculation formula of the equipment utilization rate in step 4) is:
[0025]
[0026] Ttotal is the total duration of the current ring of the device, T ring is the total excavation time of the equipment in the current cycle, T tunnel It is the total assembly time of the current ring of the device.
[0027] Furthermore, in order to ensure the accuracy of the tunneling state identification, the method also includes re-inspecting the tunneling state, and the re-inspection process is:
[0028] Get the total thrust parameters under the current ring number conditions. If the total thrust is greater than 0 and the data length of the total thrust is greater than or equal to the set data length, it means that the excavation re-inspection conditions are met.
[0029] Furthermore, the start timestamp and the end timestamp are obtained according to the corresponding indexes. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a flow chart of the method for determining the utilization rate of shield machine equipment of the present invention;
[0031] Figure 2 It is a flow chart of the method for determining the time taken for a shield machine equipment process of the present invention. DETAILED DESCRIPTION
[0032] The specific implementation of the present invention will be further described below in conjunction with the accompanying drawings.
[0033] Embodiment of the method for determining the utilization rate of shield machine equipment
[0034] In order to reduce the tediousness and subjectivity of on-site manual statistics and the impact of data collection frequency, the present invention provides a method for determining the utilization rate of shield machine equipment. The method obtains the excavation parameters during the construction process, counts the timestamps of each continuous excavation section and assembly section in each ring, calculates the time of each continuous excavation section and the time of each assembly section, and finally counts the total excavation time and total assembly time of each ring, and determines the utilization rate of the shield machine equipment of the corresponding ring according to the total time of each ring. The implementation process of the method is as follows: Figure 1 As shown, the specific implementation process is as follows.
[0035] 1. Obtain the excavation parameters during shield construction.
[0036] The shield machine equipment will upload its own operating parameters to the shield remote monitoring platform during the construction process. Therefore, the present invention obtains the tunneling parameters during the shield construction process through the shield remote monitoring platform. The tunneling parameters include ring number, date, total thrust, segment assembly mode, tunneling mode, status, etc. In addition to recording the received tunneling parameters, the remote monitoring platform will also number the received operating parameters in sequence according to the receiving time, and each sampling time corresponds to a number, also called an index number.
[0037] 2. Determine the working mode of the shield machine based on the excavation parameters such as ring number, segment assembly mode, excavation mode, status, etc. The working modes include excavation, segment assembly and shutdown modes.
[0038] 2.1 Ring excavation parameter extraction: According to the "ring number", read the current excavation ring number of the equipment. If the ring number does not change, it is regarded as the same ring, otherwise it is regarded as the next ring; according to the starting index Index_start and the ending index Index_end of the same excavation ring number, extract the excavation parameters of the current ring number of the equipment.
[0039] 2.2 Ring excavation mode determination: The excavation mode parameters under the current ring number conditions of the equipment extracted in step 2.1 are used as the determination conditions for the ring excavation mode. If the corresponding value of "excavation mode" == 1, the equipment enters the excavation mode, otherwise the equipment is in other working modes.
[0040] 2.3 Ring assembly mode determination: The segment assembly mode parameters under the current ring number conditions of the equipment extracted in step 2.1 are used as the determination conditions for the assembly mode. If the corresponding value of "segment assembly mode" == 2, the equipment enters the segment assembly mode.
[0041] 2.4 Ring shutdown mode determination: According to the state parameters of the device under the current ring number conditions extracted in step 2.1, as the judgment condition of the shutdown mode, if the corresponding value of "state" == 0, the device enters the shutdown mode.
[0042] The mode corresponding values used in the above-mentioned determination of each mode are set by oneself and can be adjusted as needed.
[0043] 3. Determine the total excavation time of each ring according to the determined excavation mode.
[0044] According to step 2.2, when "excavation mode" == 1, select the starting index index_push_start and ending index index_push_end of several continuous excavation segment data, accurately calculate the ring excavation time, and extract the continuous excavation segments by judging whether the excavation parameter indexes corresponding to the excavation mode are continuous. If they are continuous, they are regarded as the same continuous excavation segment, and the starting and ending indexes of the continuous excavation segment are extracted. Otherwise, it is regarded as the next continuous excavation segment. The specific steps are as follows:
[0045] 3.1 According to the starting index index_push_start and the ending index index_push_end of each continuous excavation section, extract the starting timestamp time_push_start and the ending timestamp time_push_end of the corresponding continuous excavation section, and calculate the excavation time of the continuous excavation section.
[0046] 3.2 According to the "total propulsion force" parameter under the current ring number condition of the equipment extracted in step 2.1, determine that "total propulsion force">0. Taking into account the problem of data packet loss due to temporary failure of communication transmission during shield construction, the additional "total propulsion force" data length is greater than or equal to the set data length, in order to ensure that the extracted continuous excavation section is valid as an excavation re-verification condition. The set data length in this embodiment is 5. The above two conditions are used as the re-verification conditions of the "excavation mode" to determine whether the TBM is currently in the excavation state. If it is true, the excavation mark push_label=1, otherwise, push_label=-1.
[0047] 3.3 Extract step 3.2 until the excavation time of all continuous excavation sections of this loop is calculated.
[0048] 3.4 Filter the excavation time of the continuous excavation section with excavation mark push_label = 1, add up and sum them, and get the total excavation time T of the ring tunnel .
[0049] Step 3.2 may also be omitted, and the excavation state can be directly screened according to "excavation mode" == 1. In order to ensure the accuracy of the excavation state judgment, the present invention adds a re-test of step 3.2.
[0050] 4. Determine the total assembly time for each ring.
[0051] According to the excavation parameters of the current ring number of the equipment extracted in step 2.1, according to the corresponding value of "segment assembly mode" == 2, filter the starting index index_ring_start and ending index index_ring_end of several continuous assembly segment data to accurately calculate the ring assembly time. Continuous assembly segments are extracted by judging whether the excavation parameter indexes corresponding to the segment assembly mode are continuous. If they are continuous, they are regarded as the same continuous assembly segment, and the starting and ending indexes of the continuous assembly segment are extracted, otherwise they are regarded as the next assembly segment. The specific steps are as follows:
[0052] 4.1 According to the starting index index_ring_start and the ending index index_ring_end of each continuous assembly segment, extract the starting timestamp time_ring_start and the ending timestamp time_ring_end of the corresponding continuous assembly segment, and calculate the segment assembly time of the continuous assembly segment.
[0053] 4.2 Extract step 4.1 until the segment assembly time of all assembled continuous sections of this ring is calculated.
[0054] 4.3 The segment assembly time of all continuous assembly sections of this ring is accumulated and summed to obtain the total assembly time T of this ring. ring .
[0055] 5. Calculate the utilization rate of shield machine equipment.
[0056] According to the start index Index_start and end index Index_end of the device's current ring number, get the start time T of the device's current ring number start , deadline T end , calculate the total duration of the current ring of the device T total ; Then the total excavation time T of the ring is obtained according to the calculation tunnel , total assembly time T ring And the total ring duration is used to calculate the equipment utilization rate U, and the calculation formula used is as follows:
[0057]
[0058] Where, T total is the total duration of the current ring of the device, T ring is the current ring excavation time of the equipment, T tunnel It is the current segment assembly time of the equipment.
[0059] Through the above process, the present invention takes into account that the excavation and assembly of each link in the construction process of the shield machine equipment are not continuous, and are interrupted by various situations. Therefore, when calculating the duration of each process, it is achieved by counting the sum of the duration of each segment, so that the calculated duration of each process and the equipment utilization rate are closer to the actual construction duration, and the calculated equipment utilization rate is highly accurate, which provides an important basis for subsequent control and research.
[0060] Implementation method for determining time of shield machine equipment process
[0061] The purpose of this embodiment is to obtain the time taken for each process of the shield machine equipment, where each process includes a tunneling process, an assembly process and a shutdown process, wherein the time taken for the tunneling process and the assembly process is the total tunneling time and the total assembly time in each ring. The total tunneling time and the total assembly time of each ring have been described in detail in the embodiment of the method for determining the utilization rate of the shield machine equipment, and specific reference may be made to steps 1-4. The difference of this embodiment is that, on the basis of obtaining the total tunneling time and the total assembly time in each ring, the total shutdown time of each ring needs to be further calculated. The specific implementation process is as follows: Figure 2 shown.
[0062] When calculating the total downtime of the ring, it is necessary to know the total length of the ring. The present invention obtains the start time T of the current ring number of the device according to the start index Index_start and the end index Index_end of the current ring number of the device. start , deadline T end , calculate the total duration of the current ring of the device T total , according to the current ring excavation time T of the equipment obtained previously tunnel, Segment assembly time T ring , calculate the current ring downtime T of the device down :
[0063] T total =T end -T start
[0064] T down =T total -T tunnel -T ring
[0065] Implementation example of device for determining time of shield machine equipment process
[0066] The device for determining the time taken for a shield machine equipment process of the present invention comprises a processor and a memory, wherein the processor executes a computer program stored in the memory to implement the method for determining the time taken for a shield machine equipment process in the above method embodiment of the present invention. That is to say, the method in the above method embodiment should be understood to be a process of the method for determining the time taken for a shield machine equipment process by computer program instructions. These computer program instructions can be provided to the processor so that the processor executes these instructions to generate functions specified by the above method flow.
[0067] The processor referred to in this embodiment refers to a processing device such as a microprocessor MCU or a programmable logic device FPGA; the memory referred to in this embodiment includes a physical device for storing information, which usually digitizes the information and then stores it in a medium using electrical, magnetic or optical methods. For example: various memories that use electrical energy to store information, such as RAM, ROM, etc.; various memories that use magnetic energy to store information, such as hard disks, floppy disks, magnetic tapes, magnetic core memories, magnetic bubble memories, and U disks; various memories that use optical methods to store information, such as CDs or DVDs. Of course, there are other types of memories, such as quantum memories, graphene memories, and so on.
[0068] The device is composed of the above-mentioned memory, processor and computer program, and is implemented by the processor executing corresponding program instructions in the computer. The processor can be equipped with various operating systems, such as Windows operating system, Linux system, Android, iOS system, etc.
[0069] As another embodiment, the device may further include a display, and the display is used to display the diagnosis results for reference by the staff.
[0070] Embodiment of the device for determining the utilization rate of shield machine equipment
[0071] The device for determining the utilization rate of shield machine equipment of the present invention comprises a processor and a memory, wherein the processor executes a computer program stored in the memory to implement the method for determining the utilization rate of shield machine equipment in the above method embodiment of the present invention. That is to say, the method in the above method embodiment should be understood to be a process of the method for determining the utilization rate of shield machine equipment by computer program instructions. These computer program instructions can be provided to the processor so that the processor executes these instructions to generate functions specified by the above method flow.
Claims
1. A method for determining the time required for a shield machine equipment process. It is characterized in that The method comprises the following steps: 1) Obtaining tunneling parameters during shield construction, wherein the tunneling parameters include ring number, total thrust, segment assembly mode, tunneling mode and state parameters; 2) According to the excavation mode of the current ring, the data of each continuous excavation section is filtered out according to the excavation mode value corresponding to the excavation process, and the start timestamp and end timestamp of each continuous excavation section are obtained to obtain the excavation time of each continuous excavation section of the current ring, and the excavation time of each continuous excavation section is summed to obtain the total excavation time of the current ring; 3) According to the segment assembly mode of the current ring, the data of each continuous assembly section is filtered out according to the segment assembly mode value corresponding to the assembly process, and the start timestamp and the end timestamp of each continuous assembly section are obtained to obtain the assembly time of each continuous assembly section of the current ring, and the assembly time of each continuous assembly section is summed to obtain the total assembly time of the current ring; 4) Obtain the start timestamp and end timestamp of the shield machine equipment of the current ring number, calculate the total time of the shield machine equipment in the current ring, subtract the total excavation time of the current ring and the total assembly time of the current ring from the total time to obtain the total downtime of the current ring.
2. The method for determining the time taken for a shield machine process according to claim 1, It is characterized in that The method also includes determining excavation parameters of the same ring according to the ring number.
3. The method for determining the time taken for a shield machine process according to claim 2, It is characterized in that The method also includes re-inspecting the excavation status, and the re-inspection process is: Get the total thrust parameters under the current ring number conditions. If the total thrust is greater than 0 and the data length of the total thrust is greater than or equal to 5, it means that the excavation re-inspection conditions are met.
4. The method for determining the time taken for a shield machine process according to any one of claims 1 to 3, It is characterized in that The start timestamp and end timestamp are obtained based on the corresponding index.
5. A method for determining the utilization rate of shield machine equipment. It is characterized in that The determination method comprises the following steps: 1) Obtaining tunneling parameters during shield construction, wherein the tunneling parameters include ring number, total thrust, segment assembly mode, tunneling mode and state parameters; 2) According to the excavation mode of the current ring, the data of each continuous excavation section is filtered out according to the excavation mode value corresponding to the excavation process, and the start timestamp and end timestamp of each continuous excavation section are obtained to obtain the excavation time of each continuous excavation section of the current ring, and the excavation time of each continuous excavation section is summed to obtain the total excavation time of the current ring; 3) According to the segment assembly mode of the current ring, the data of each continuous assembly section is filtered out according to the segment assembly mode value corresponding to the assembly process, and the start timestamp and the end timestamp of each continuous assembly section are obtained to obtain the assembly time of each continuous assembly section of the current ring, and the assembly time of each continuous assembly section is summed to obtain the total assembly time of the current ring; 4) Obtain the start timestamp and end timestamp of the shield machine equipment in the current ring number, calculate the total time of the shield machine equipment in the current ring, and calculate the equipment utilization rate of the shield machine equipment in each ring based on the total excavation time, total assembly time and total time of each ring.
6. The method for determining the utilization rate of a shield machine according to claim 5, It is characterized in that The calculation formula of the equipment utilization rate in step 4) is: T total is the total duration of the current ring of the device, T ring is the total excavation time of the equipment in the current cycle, T tunnel It is the total assembly time of the current ring of the device.
7. The method for determining the utilization rate of a shield machine according to claim 5, It is characterized in that The method also includes re-inspecting the excavation status, and the re-inspection process is: Get the total thrust parameters under the current ring number conditions. If the total thrust is greater than 0 and the data length of the total thrust is greater than or equal to the set data length, it means that the excavation re-inspection conditions are met.
8. The method for determining the utilization rate of a shield machine according to any one of claims 5 to 7, It is characterized in that The start timestamp and end timestamp are obtained based on the corresponding index.
9. A device for determining the time required for a shield machine process. It is characterized in that The device comprises a processor and a memory, wherein the processor executes a computer program stored in the memory to implement the method for determining the time taken for a shield machine equipment process as described in any one of claims 1 to 4 above.
10. A device for determining the utilization rate of a shield machine. It is characterized in that The device comprises a processor and a memory, wherein the processor executes a computer program stored in the memory to implement the method for determining the utilization rate of a shield machine as described in any one of claims 5 to 8.