Multi-view organization display method and device for nuclear power DCS project function diagram
By obtaining and analyzing the control logic diagram of the design institute in the nuclear power DCS project, converting into the supplier's functional map, and generating the storage organization view under the project manager structure, solving the problem of omissions and multi -view identification of FD pages, and realized the FD map. Convenient display and interpretation.
Patent Information
- Application Number
- CN202111387901.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-22
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2041-11-22
AI Technical Summary
In the prior art, the storage organization form of the FD page is the station-process subsystem-FD page, which causes the FD diagram to be drawn according to the storage organization form of the station. It is easy to cause human errors to cause the CLD missing process subsystem and the FD page is missing. Repair costs and labor investment are huge; at the same time, multiple FD pages on the same CLD page cannot be easily identified and displayed, which affects the inspection of FD by comparing CLD.
The multi -view organization display method of the functional map of the nuclear power DCS project is proposed. By obtaining the control logic diagram of the design institute, the analysis of its attribute information, converting it into the supplier's functional map, and generating a storage organization view under the project manager structure in order Establish a relationship with CLD to reduce the risk of FD pages omissions, and intuitively reflect the process and results of the FD pages allocated to the subsystem.
This method greatly reduces the risk of FD pages omitted from the FD pages under the perspective of the station and storage. It visually display the process and results of the FD pages allocated to the subsystem, which is conducive to interpretation of drawings and conveniently obtain FD pictures that are not assigned to the craft subsystem. Avoid missing.
Smart Images

Figure CN114115149B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of nuclear power DCS technology, and in particular to a multi-view organization display method and device for a nuclear power DCS project function diagram. Background Art
[0002] In nuclear power DCS (Digital Control System) projects, CLD (Controllogic document) and DCS supplier's FD (functional document) are two important documents. Among them, CLD is the basis of FD design. CLD design focuses on the control function from the process perspective, which is relatively abstract and simple. Generally, the control platform implementation is not considered, so it is mainly organized in the form of process system. FD design is more oriented to the control field, and it is necessary to consider the implementation of CLD on a specific control platform, so additional specific design will be added, focusing on the station as the organizational form.
[0003] Currently, the main workflow of FD configuration includes: (1) Analyze and classify the logic of CLD page by page, and form a CLD page structure that can be assigned to a station under the process system, that is, the process subsystem; (2) Summarize the CLD process subsystem information, and after analysis, assign it to the station to form the substation information; (3) According to the substation results, establish the station structure in the FD software; (4) According to the CLD classification, establish the FD page under the corresponding station structure of the FD software, compare the CLD page by page, and draw the FD logic.
[0004] The characteristics of CLD and FD are as follows: (1) FD is derived from CLD. Therefore, when designing FD, the FD page and its corresponding CLD have obvious association marks, such as the page name information of the two must be consistent; (2) One CLD page may correspond to multiple stations, and one CLD page may also correspond to multiple FD pages.
[0005] Based on the above existing working mode, the current storage organization form of FD page is station-process subsystem-FD page, and there is only one display view, that is, the storage organization form remains consistent. Therefore, the following problems exist:
[0006] (1) When drawing the FD diagram, it must be drawn according to the storage organization form of the station, which means that the work must also be allocated according to the storage organization form of the station. For human errors such as missing the CLD process subsystem, resulting in the missing of the corresponding FD page, and the station manager omitting the FD drawing of the process subsystem, it is highly likely that they cannot be discovered in time and effectively in the early stage of the project, and may only be discovered in the subsequent integration and testing stages, so the repair cost and manpower investment are huge;
[0007] (2) In FD, multiple FD pages originating from the same CLD page cannot be conveniently and completely identified and cannot be displayed under one view structure, which is not conducive to checking the FD against the CLD. Summary of the invention
[0008] The purpose of this application is to solve one of the above-mentioned technical problems at least to a certain extent.
[0009] To this end, the first purpose of the present application is to propose a multi-view organization and display method for a nuclear power DCS project functional diagram, which can conveniently establish an association with the CLD by performing detailed structural organization and storage management of the FD diagram from a process perspective in the project manager, greatly reducing the risk of missing FD pages when the FD diagram is directly stored from a station perspective; intuitively reflecting the process and results of allocating FD pages to subsystems, which is conducive to interpreting the drawings; and at the same time, it can also conveniently obtain FD diagrams that are not allocated to process subsystems to avoid omissions.
[0010] The second objective of the present application is to provide a multi-view organization display device for a nuclear power DCS project functional diagram.
[0011] The third object of the present application is to provide a computer device.
[0012] A fourth object of the present application is to provide a non-transitory computer-readable storage medium.
[0013] In order to achieve the above-mentioned purpose, the first embodiment of the present application proposes a multi-view organization display method of a nuclear power DCS project function diagram, comprising:
[0014] Obtain the control logic diagram of the design institute in the nuclear power DCS project;
[0015] Analyzing the attribute information of the design institute control logic diagram, and converting the design institute control logic diagram into a supplier function diagram according to the attribute information;
[0016] Generate a storage organization view of the supplier function diagram under the project manager structure;
[0017] The supplier functional diagram is displayed in the project manager structure.
[0018] Optionally, generating a storage organization view of the supplier function diagram under the project manager structure includes:
[0019] Establishing a project manager infrastructure, wherein the levels of the project manager infrastructure are project, sub-project, functional partition, process system, process sub-system and function page from large to small;
[0020] Establishing a corresponding supplier function diagram under the project manager infrastructure;
[0021] A structure description file corresponding to the supplier function diagram is generated at each level of the project manager infrastructure.
[0022] Optionally, after generating the storage organization view of the supplier function diagram under the project manager structure, the method further includes:
[0023] A station manager index view of the supplier functional diagram is generated.
[0024] Optionally, generating a station manager index view of the supplier functional diagram includes:
[0025] Traverse the structure description files of all process subsystems of each subproject in the project and obtain the station attributes of the process subsystem;
[0026] Determining whether the station attribute of the process subsystem has a corresponding station structure;
[0027] If there is a corresponding station structure, the process subsystem is allocated to the corresponding station;
[0028] If there is no corresponding station structure, the process subsystem is allocated to the preset structure.
[0029] Optionally, the method further includes:
[0030] The process subsystems are manually allocated to corresponding stations from the preset structure based on substation requirements.
[0031] Optionally, the method further includes:
[0032] When a station is deleted, all process subsystems under the station structure are allocated to the preset structure.
[0033] Optionally, the method further includes:
[0034] After generating the storage organization view of the supplier function diagram under the project manager structure, a process system manager index view of the supplier function diagram is generated.
[0035] Optionally, generating a process system manager index view of the supplier function diagram includes:
[0036] Traverse all process systems, process subsystems and function pages of each sub-project in the project;
[0037] Generate the corresponding process system list under the process system manager structure;
[0038] Determine whether the supplier's functional diagram belongs to a certain process system;
[0039] If the supplier function diagram belongs to a process system, the supplier function diagram is assigned to the process system;
[0040] If the supplier function diagram does not belong to the process system, assign the supplier function diagram to Unassigned.
[0041] Optionally, the method further includes:
[0042] In the Project Manager Structure, or Station Manager Structure, or Process System Manager, open and edit the Supplier Function Diagram.
[0043] The multi-view organization and display method of the nuclear power DCS project function diagram of the embodiment of the present application obtains the design institute control logic diagram in the nuclear power DCS project, analyzes the attribute information of the design institute control logic diagram, and converts the design institute control logic diagram into a supplier function diagram according to the attribute information, and then generates a storage organization view of the supplier function diagram under the project manager structure, displays the supplier function diagram with the project manager structure, and performs detailed structural organization and storage management of the FD diagram from the process perspective in the project manager, which can conveniently establish an association with the CLD, greatly reducing the risk of missing FD pages under the perspective and storage mode of the FD diagram directly from the station; intuitively reflects the process and results of the FD page allocation to the subsystem, which is conducive to the interpretation of the drawings; and also conveniently obtains FD diagrams that are not allocated to the process subsystem to avoid omissions.
[0044] In order to achieve the above-mentioned purpose, the second embodiment of the present application proposes a multi-view organization display device for a nuclear power DCS project function diagram, comprising:
[0045] Acquisition module, used to obtain the control logic diagram of the design institute in the nuclear power DCS project;
[0046] An analysis module, used for analyzing the attribute information of the design institute control logic diagram, and converting the design institute control logic diagram into a supplier function diagram according to the attribute information;
[0047] A generating module, used for generating a storage organization view of the supplier function diagram under a project manager structure;
[0048] A display module is used to display the supplier function diagram in the project manager structure.
[0049] Optionally, the generating module is used to:
[0050] Establishing a project manager infrastructure, wherein the levels of the project manager infrastructure are project, sub-project, functional partition, process system, process sub-system and function page from large to small;
[0051] Establishing a corresponding supplier function diagram under the project manager infrastructure;
[0052] A structure description file corresponding to the supplier function diagram is generated at each level of the project manager infrastructure.
[0053] Optionally, the generating module is further used to:
[0054] After generating the storage organization view of the supplier function diagram under the project manager structure, generating the site manager index view of the supplier function diagram.
[0055] Optionally, the generating module is used to:
[0056] Traverse the structure description files of all process subsystems of each subproject in the project and obtain the station attributes of the process subsystem;
[0057] Determining whether the station attribute of the process subsystem has a corresponding station structure;
[0058] If there is a corresponding station structure, the process subsystem is allocated to the corresponding station;
[0059] If there is no corresponding station structure, the process subsystem is allocated to the preset structure.
[0060] Optionally, the generating module is further used to:
[0061] The process subsystems are manually allocated to corresponding stations from the preset structure based on substation requirements.
[0062] Optionally, the generating module is further used to:
[0063] When a station is deleted, all process subsystems under the station structure are allocated to the preset structure.
[0064] Optionally, the generating module is further used to:
[0065] After generating the storage organization view of the supplier function diagram under the project manager structure, a process system manager index view of the supplier function diagram is generated.
[0066] Optionally, the generating module is used to:
[0067] Traverse all process systems, process subsystems and function pages of each sub-project in the project;
[0068] Generate the corresponding process system list under the process system manager structure;
[0069] Determine whether the supplier's functional diagram belongs to a certain process system;
[0070] If the supplier function diagram belongs to a process system, the supplier function diagram is assigned to the process system;
[0071] If the supplier function diagram does not belong to the process system, assign the supplier function diagram to Unassigned.
[0072] Optionally, the device further comprises:
[0073] The editing module is used to open and edit the supplier function diagram in the project manager structure, the station manager structure, or the process system manager.
[0074] The multi-view organization and display device of the nuclear power DCS project function diagram of the embodiment of the present application obtains the design institute control logic diagram in the nuclear power DCS project, analyzes the attribute information of the design institute control logic diagram, and converts the design institute control logic diagram into a supplier function diagram according to the attribute information, and then generates a storage organization view of the supplier function diagram under the project manager structure, displays the supplier function diagram with the project manager structure, and performs detailed structural organization and storage management of the FD diagram from the process perspective in the project manager, which can conveniently establish an association with the CLD, greatly reducing the risk of missing FD pages under the perspective and storage mode of the FD diagram directly from the station; intuitively reflects the process and results of the FD page allocation to the subsystem, which is conducive to the interpretation of the drawings; and can also conveniently obtain FD diagrams that are not allocated to the process subsystem to avoid omissions.
[0075] In order to achieve the above-mentioned purpose, the third aspect embodiment of the present application proposes a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the multi-view organization display method of the nuclear power DCS project functional diagram as described in the first aspect embodiment is implemented.
[0076] In order to achieve the above-mentioned objectives, the fourth aspect embodiment of the present application also proposes a non-temporary computer-readable storage medium, on which a computer program is stored, characterized in that when the computer program is executed by a processor, a multi-view organization display method of a nuclear power DCS project functional diagram as described in the first aspect embodiment is implemented.
[0077] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0078] The drawings constituting part of the present application are used to provide a further understanding of the present application. The exemplary embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0079] Figure 1 It is a flow chart of a multi-view organization display method of a nuclear power DCS project function diagram according to an embodiment of the present application;
[0080] Figure 2 It is a flowchart for generating the storage organization view of the supplier function diagram under the project manager structure;
[0081] Figure 3 It is a flowchart of a specific embodiment of generating a storage organization view of a supplier function diagram under a project manager structure;
[0082] Figure 4 It is a schematic diagram of the project manager structure showing the supplier's functional diagram;
[0083] Figure 5 is a flow chart of a multi-view organization display method of a nuclear power DCS project function diagram according to another embodiment of the present application;
[0084] Figure 6 is a flow chart of the station manager index view that generates the supplier function map;
[0085] Figure 7 is a flowchart of a specific embodiment of generating a storage organization view of a supplier function diagram under a station manager structure;
[0086] Figure 8 It is a schematic diagram of the station manager structure showing the supplier's functional diagram;
[0087] Fig. 9 It is a flowchart of a multi-view organization display method of a nuclear power DCS project function diagram according to another embodiment of the present application;
[0088] Fig.10 is a flowchart of the process system manager index view that generates the supplier function diagram;
[0089] Fig.11 It is a flowchart of a specific embodiment of generating a storage organization view of a supplier function diagram under a process system manager structure;
[0090] Fig.12 It is a schematic diagram of the process system manager structure showing the supplier's functional diagram;
[0091] Fig.13 It is a structural schematic diagram of a multi-view organization display device of an electric DCS project function diagram according to an embodiment of the present application;
[0092] Fig.14 It is a structural schematic diagram of a multi-view organization display device of an electric DCS project function diagram according to another embodiment of the present application. DETAILED DESCRIPTION
[0093] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0094] The present application is further described in detail below in conjunction with specific embodiments. These embodiments should not be construed as limiting the scope of protection claimed in the present application.
[0095] The following describes a method and device for organizing and displaying a multi-view function diagram of a nuclear power DCS project according to an embodiment of the present application with reference to the accompanying drawings.
[0096] Figure 1 FIG. 1 is a flowchart of a multi-view organization display method of a nuclear power DCS project function diagram according to an embodiment of the present application. Figure 1 As shown, the method comprises the following steps:
[0097] S1, obtain the control logic diagram of the design institute in the nuclear power DCS project.
[0098] Among them, the design institute's control logic diagram CLD is the basis for the DCS supplier's function diagram FD design. In nuclear power DCS projects, CLD focuses on control functions from a process perspective, so it is not directly applied to specific projects, so it needs to be converted into a FD that is more suitable for the project.
[0099] S2, analyzing the attribute information of the design institute control logic diagram, and converting the design institute control logic diagram into a supplier function diagram according to the attribute information.
[0100] Analyze and classify the logic of the design institute's control logic diagram CLD page by page to generate a supplier function diagram that conforms to the project manager structure.
[0101] S3, generates a storage organization view of the supplier function diagram under the project manager structure.
[0102] Specifically, Figure 2 As shown, generating a storage organization view of the supplier function diagram under the project manager structure further includes:
[0103] S31, establish a project manager infrastructure.
[0104] Among them, the levels of the project manager infrastructure are project, sub-project, functional partition, process system, process subsystem and function page from large to small.
[0105] S32, establishing a corresponding supplier function diagram under the project manager infrastructure.
[0106] S33, generating a structure description file corresponding to the supplier function diagram at each level of the project manager infrastructure.
[0107] In a specific embodiment, the specific view generation process can be as follows: Figure 3 As shown. (1) Project is the total FD project, which contains a set of FD pages for different platforms and different functions; (2) Sub-project is a set of FD pages that implement a certain function and only contains a unique control platform; (3) Functional partition: contains multiple process systems; (4) Process system: corresponds to the process system of CLD, and contains the same page range as the process system of CLD, and contains the storage organization structure of the process subsystem belonging to this process system; (5) Process subsystem: a subdivision of the process system, and the FD pages it contains can only be allocated to one station; (6) FD page: the smallest storage unit of the FD diagram, and one FD page stores a supplier function diagram FD. Each of the above-mentioned layers of structure has a structure description file, which is used to record and only record its secondary structure and the pages under this layer of structure. According to these structure description files, a FD page storage organization view can be formed in the software.
[0108] FD pages or structures (sub-projects, functional partitions, process systems, process subsystems) can be created, deleted and renamed in the Project Manager, and the structure file contents under their parent structures will also be operated accordingly. In the Project Manager, FD pages can be opened normally for logic editing.
[0109] S4, displays the supplier function diagram in a project manager structure.
[0110] The project manager structure shows the schematic diagram of the supplier function diagram as follows Figure 4 shown.
[0111] The multi-view organization and display method of the nuclear power DCS project function diagram of the embodiment of the present application obtains the design institute control logic diagram in the nuclear power DCS project, analyzes the attribute information of the design institute control logic diagram, and converts the design institute control logic diagram into the supplier function diagram according to the attribute information, and then generates a storage organization view of the supplier function diagram under the project manager structure, displays the supplier function diagram in the project manager structure, and performs detailed structural organization and storage management of the FD diagram from the process perspective in the project manager, which can conveniently establish an association with the CLD, greatly reducing the risk of missing FD pages under the direct station perspective and storage mode of the FD diagram; intuitively reflects the process and results of FD pages being allocated to subsystems, which is conducive to interpreting the drawings; and also conveniently obtains FD diagrams that are not allocated to process subsystems to avoid omissions.
[0112] In another embodiment of the present application, Figure 5 As shown, the method also includes:
[0113] S5, generating a station manager index view of the supplier function map.
[0114] Specifically, Figure 6As shown, generating a station manager index view of a supplier functional diagram further includes:
[0115] S51, traverse the structure description files of all process subsystems of each subproject in the project, and obtain the station attributes of the process subsystem.
[0116] S52, determining whether the station attribute of the process subsystem has a corresponding station structure.
[0117] S53: If there is a corresponding station structure, the process subsystem is allocated to the corresponding station.
[0118] S54: If there is no corresponding station structure, the process subsystem is allocated to the preset structure.
[0119] In a specific embodiment, the specific view generation process can be as follows: Figure 7 Specifically, Figure 8 As shown, the FD page can be displayed in the view according to the structure of project-subproject-station-process subsystem-FD page from large to small. A special station name (preset structure, i.e., unassigned) is fixedly placed under the subproject. Through the refresh operation, the process subsystem (not assigned to the station) and the FD pages under it in the project manager can be placed under unassigned, and the process subsystem with assigned station can be placed under its assigned station.
[0120] A new site structure can be created under a sub-project, and multiple sites can be created.
[0121] In one embodiment, the process subsystems can be manually assigned to the corresponding stations from the preset structure based on the substation requirements. That is, the unassigned process subsystems can be manually dragged into the desired station, and the process subsystems of one station can also be dragged into other stations.
[0122] If the process subsystems in the project manager are increased or decreased, the process subsystems in the station manager will be increased or decreased accordingly after the refresh operation. If a station structure is deleted, the process subsystems under the station will return to the unassigned structure. In the station manager, the FD page can be opened normally for logical editing, but the page cannot be increased or decreased. In the station manager, the process subsystems cannot be increased or decreased.
[0123] The station manager can display the FD page from the station organization perspective, which can completely avoid the omission of sub-stations on the FD page and make the work and allocation work from the station organization perspective more convenient.
[0124] In another embodiment of the present application, Fig. 9 As shown, the method also includes:
[0125] S6, generating a process system manager index view of the supplier function diagram.
[0126] Specifically, Fig.10 As shown, the process system manager index view for generating the supplier function diagram further includes:
[0127] S61, traverse all process systems, process subsystems and function pages of each sub-project in the project.
[0128] S62, generating a corresponding process system list under the process system manager structure.
[0129] S63, determining whether the supplier function diagram belongs to a certain process system.
[0130] S64: If the supplier function diagram belongs to a process system, the supplier function diagram is allocated to the process system.
[0131] S65, if the supplier function diagram does not belong to the process system, the supplier function diagram is allocated to unallocated.
[0132] In a specific embodiment, the specific view generation process can be as follows: Fig.11 Specifically, Fig.12 As shown, the FD page can be displayed in the view according to the structure of project-sub-project-process system-FD page from large to small. In the process system manager, the process system-FD page structure under the sub-project is initially formed and displayed through refresh operation. The page name under each process system is sorted in the order of process subsystem first and then page name, so that multiple FD pages starting from the same CLD page can be displayed side by side. For pages without assigned process subsystems, the corresponding process subsystem is empty.
[0133] In the process system manager, each FD page can be opened normally for logic editing, but pages cannot be added or deleted.
[0134] The process system manager can display the direct relationship between the process system and page of the FD diagram after the substation is completed, penetrates and flattens the subsystem hierarchy in the project manager, facilitates the inspection of multiple FD diagrams from the same CLD page, and also facilitates the acquisition of FD diagrams that are not assigned to process subsystems to avoid omissions.
[0135] In a specific embodiment, three manager structures, namely, the project manager, the station manager, and the process system manager, can be displayed simultaneously.
[0136] Specifically, the following steps can be performed in the project manager:
[0137] 1. Establish sub-projects, functional divisions, and process systems;
[0138] 2. Organize the FD page according to the process system and draw the logic according to the CLD. At this time, the FD page is equivalent to the CLD page;
[0139] 3. Establish process subsystem.
[0140] If the FD page does not need to be split, the entire page is placed in the desired process subsystem; if the FD page needs to be split, a process subsystem is placed in the page before the split, and then a page with the same name is created in another process subsystem, and the logic of the desired split is cut to this page with the same name.
[0141] The following steps can be performed in the Station Manager:
[0142] 1. Carry out sub-station work until there are no unassigned process subsystems, and finally form the station view of the FD page;
[0143] 2. Carry out detailed logic configuration, the same as the previous working method.
[0144] In the Process System Manager, inspection work can be carried out.
[0145] In the project manager process, FD drawing is carried out completely according to the CLD structure, which greatly reduces the probability of FD missing CLD drawing. It can also obtain page adjustments in the process subsystem in real time, accurately and quickly, reducing identification costs.
[0146] In the station manager process, it is possible to effectively ensure that the technological subsystems are allocated to stations.
[0147] In the process system manager process, by confirming whether the page has a process subsystem field, you can easily and intuitively find out whether the FD page is assigned to a process subsystem.
[0148] In order to implement the above-mentioned embodiment, the present application also proposes a multi-view organization display device for a nuclear power DCS project function diagram.
[0149] Fig.13 It is a structural schematic diagram of a multi-view organization display device for a nuclear power DCS project functional diagram in one embodiment of the present application.
[0150] like Fig.13 As shown, the device includes an acquisition module 91 , an analysis module 92 , a generation module 93 and a display module 94 .
[0151] The acquisition module 91 is used to acquire the control logic diagram of the design institute in the nuclear power DCS project.
[0152] The analysis module 92 is used to analyze the attribute information of the design institute control logic diagram and convert the design institute control logic diagram into a supplier function diagram according to the attribute information.
[0153] The generating module 93 is used to generate a storage organization view of the supplier function diagram under the project manager structure.
[0154] The generating module 93 is specifically used for:
[0155] Establish the basic structure of the project manager. The levels of the basic structure of the project manager are project, sub-project, functional partition, process system, process subsystem and function page from large to small.
[0156] Establish corresponding supplier function diagram under the project manager infrastructure;
[0157] Generate structure description files corresponding to the supplier function diagram at each level of the project manager infrastructure.
[0158] The generating module 93 is further used for:
[0159] After generating the storage organization view of the supplier function diagram under the project manager structure, generate the station manager index view of the supplier function diagram.
[0160] The generating module 93 is specifically used for:
[0161] Traverse the structure description files of all process subsystems of each subproject in the project and obtain the station attributes of the process subsystem;
[0162] Determine whether the station attributes of the process subsystem have a corresponding station structure;
[0163] If there is a corresponding station structure, the process subsystem is assigned to the corresponding station;
[0164] If there is no corresponding station structure, the process subsystem is allocated to the preset structure.
[0165] The generating module 93 is further used for:
[0166] Manually assign process subsystems from the preset structure to the corresponding stations based on substation requirements.
[0167] The generating module 93 is further used for:
[0168] When a station is deleted, all process subsystems under the station structure are allocated to the preset structure.
[0169] The generating module 93 is further used for:
[0170] After generating the storage organization view of the supplier function diagram under the project manager structure, generate the process system manager index view of the supplier function diagram.
[0171] The generating module 93 is used for:
[0172] Traverse all process systems, process subsystems and function pages of each sub-project in the project;
[0173] Generate the corresponding process system list under the process system manager structure;
[0174] Determine whether the supplier's functional diagram belongs to a certain process system;
[0175] If the supplier function diagram belongs to a process system, the supplier function diagram is assigned to the process system;
[0176] If the supplier function diagram does not belong to the process system, assign the supplier function diagram to Unassigned.
[0177] The display module 94 is used to display the supplier function diagram in a project manager structure.
[0178] In another embodiment, Fig.14 As shown, the device further includes an editing module 95 .
[0179] The editing module 95 is used to open and edit the supplier function diagram in the project manager structure, the station manager structure, or the process system manager.
[0180] It should be understood that the multi-view organization display device of the nuclear power DCS project function diagram of this embodiment is consistent with the description of the multi-view organization display method of the nuclear power DCS project function diagram of the first embodiment, and will not be repeated here.
[0181] The multi-view organization and display device of the nuclear power DCS project function diagram of the embodiment of the present application obtains the design institute control logic diagram in the nuclear power DCS project, analyzes the attribute information of the design institute control logic diagram, and converts the design institute control logic diagram into the supplier function diagram according to the attribute information, and then generates a storage organization view of the supplier function diagram under the project manager structure, displays the supplier function diagram in the project manager structure, and performs detailed structural organization and storage management of the FD diagram from the process perspective in the project manager, which can conveniently establish an association with the CLD, greatly reducing the risk of missing FD pages under the direct station perspective and storage mode of the FD diagram; intuitively reflects the process and results of allocating FD pages to subsystems, which is conducive to interpreting drawings; and can also conveniently obtain FD diagrams that are not allocated to process subsystems to avoid omissions.
[0182] In order to implement the above embodiments, the present application also proposes a computer device.
[0183] The computer device includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the multi-view organization display method of the nuclear power DCS project function diagram according to the first embodiment is implemented.
[0184] In order to implement the above embodiments, the present application also proposes a non-transitory computer-readable storage medium.
[0185] The non-temporary computer-readable storage medium stores a computer program, which, when executed by a processor, implements the multi-view organization display method of the nuclear power DCS project function diagram as described in the first embodiment.
[0186] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0187] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or otherwise processing in a suitable manner if necessary, and then stored in a computer memory.
[0188] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0189] It should be noted that, in the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
Claims
1. A multi-view organization and display method for a nuclear power DCS project function diagram, characterized in that: The following steps are involved: Obtain the control logic diagram of the design institute in the nuclear power DCS project; Analyzing the attribute information of the design institute control logic diagram, and converting the design institute control logic diagram into a supplier function diagram according to the attribute information; Generate a storage organization view of the supplier function diagram under the project manager structure; displaying the supplier functional diagram in the project manager structure; Generate a storage organization view of the supplier function diagram under the project manager structure, including: Establishing a project manager infrastructure, wherein the levels of the project manager infrastructure are project, sub-project, functional partition, process system, process sub-system and function page from large to small; Establishing a corresponding supplier function diagram under the project manager infrastructure; A structure description file corresponding to the supplier function diagram is generated at each level of the project manager infrastructure.
2. The method according to claim 1, characterized in that After generating the storage organization view of the supplier function diagram under the project manager structure, the method further includes: Generate a storage organization view of the supplier function diagram under the station manager structure.
3. The method according to claim 2, characterized in that Generate a storage organization view of the supplier function diagram under the station manager structure, including: Traverse the structure description files of all process subsystems of each subproject in the project and obtain the station attributes of the process subsystem; Determining whether the station attribute of the process subsystem has a corresponding station structure; If there is a corresponding station structure, the process subsystem is allocated to the corresponding station; If there is no corresponding station structure, the process subsystem is allocated to the preset structure.
4. The method according to claim 3, characterized in that Also includes: The process subsystems are manually allocated to corresponding stations from the preset structure based on substation requirements.
5. The method according to claim 3, characterized in that Also includes: When a station is deleted, all process subsystems under the station structure are allocated to the preset structure.
6. The method according to claim 2, characterized in that After generating the storage organization view of the supplier function diagram under the project manager structure, the method further includes: Generate a storage organization view of the supplier function diagram under the process system manager structure.
7. The method according to claim 2, characterized in that Generate a storage organization view of the supplier function diagram under the process system manager structure, including: Traverse all process systems, process subsystems and function pages of each sub-project in the project; Generate the corresponding process system list under the process system manager structure; Determine whether the supplier's functional diagram belongs to a certain process system; If the supplier function diagram belongs to a process system, the supplier function diagram is assigned to the process system; If the supplier function diagram does not belong to the process system, assign the supplier function diagram to Unassigned.
8. The method according to claim 6, characterized in that Also includes: In the Project Manager Structure, or Station Manager Structure, or Process System Manager, open and edit the Supplier Function Diagram.
9. A multi-view organization display device for a nuclear power DCS project function diagram, characterized in that: include: Acquisition module, used to obtain the control logic diagram of the design institute in the nuclear power DCS project; An analysis module, used for analyzing the attribute information of the design institute control logic diagram, and converting the design institute control logic diagram into a supplier function diagram according to the attribute information; A generating module, used for generating a storage organization view of the supplier function diagram under a project manager structure; Generate a storage organization view of the supplier function diagram under the project manager structure, including: Establishing a project manager infrastructure, wherein the levels of the project manager infrastructure are project, sub-project, functional partition, process system, process sub-system and function page from large to small; Establishing a corresponding supplier function diagram under the project manager infrastructure; generating a structure description file corresponding to a supplier function diagram at each level of the project manager infrastructure; A display module is used to display the supplier function diagram in the project manager structure.
Citation Information
Patent Citations
Method and device for nuclear power station to generate virtual digital control system configuration file
CN101984411A
Process control systems and systems and methods for configuration thereof
CN105589442A