A method, device and storage medium for generating a mixing batching block plan

The optimization algorithm is used to split the overall plan for mixing a large pile into multiple Block plans, which solves the problem of the inability to accurately control the quality of the mixed ore in the existing technology, achieves high-quality Block plan generation, and reduces workload.

CN114118899BActive Publication Date: 2024-10-01WISDRI ENG & RES INC LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111234953.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-22
Publication Date
2024-10-01
Estimated Expiration
2041-10-22

AI Technical Summary

Technical Problem

The existing block plan generation method cannot accurately control the quality of the mixed ore, resulting in a heavy manual calculation workload and inability to meet high quality requirements.

Method used

An optimization algorithm is used to split the master plan of a large mixed pile into multiple block plans. The silicon and iron content of each block plan is as close as possible to the master plan. A genetic algorithm is used for splitting to satisfy the objective function and constraints of multiple constraints. condition.

Benefits of technology

It significantly improves the quality of block plan preparation, reduces the workload of the production organization, and ensures that the ferrosilicon content of each block plan is equal to the overall plan.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114118899B_ABST
    Figure CN114118899B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of smelting batching. The present invention specifically discloses a method for generating a Block plan for mixing and batching, the method comprising: obtaining a master plan for a large mixing pile; obtaining process parameters for mixing and batching; inputting the master plan for the large mixing pile and the process parameters for mixing and batching into a Block splitting model, executing an optimization algorithm, and obtaining all the Block plans after splitting; wherein the Block splitting model is used to split a master plan for a large mixing pile into multiple Block plans. The present invention also proposes a device and a computer-readable storage medium for generating a Block plan for mixing and batching using the above method. The method and device for generating a Block plan for mixing and batching provided by the present invention significantly improve the quality of Block plan compilation under multiple constraints, while greatly reducing the workload of plan compilation in production organization.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of smelting batching, and in particular to a method, device and storage medium for generating a mixing batching Block plan. Background Art

[0002] The mixing of iron-containing raw materials is an important part of the production of steel enterprises. The quality of the mixed ore plays a key role in the quality of sintered ore. The Block batching plan originated in Japan and was first adopted by Baosteel in my country. Due to its strong planning, easy production organization and operation, and quality control, the Block plan has been gradually promoted after its introduction.

[0003] Block plan means splitting the mixing and building plan into multiple block plans, requiring that the ingredients of each block plan should be as similar as possible, the quantity should be as equal as possible, and the composition should be as similar as possible. Since the silicon and iron content have the most significant impact on the sintering quality, the silicon and iron content of each block plan should be as equal as possible.

[0004] To make the composition of each block plan basically the same as that of the bulk pile, and to ensure that the total proportion plan of the bulk pile of mixed ore meets the requirements, tedious calculations are required. At present, the formulation of block plans is done by manual calculation or by solving the linear programming model. Manual calculation is labor-intensive, and linear programming requires the simplification of the model. Both cannot meet the requirements for precise control of the quality of mixed ore. Therefore, it is necessary to develop a set of block plan generation methods and devices using advanced algorithms to reduce the workload of block plan formulation and improve the quality of block plans. Summary of the invention

[0005] In order to overcome the technical problems mentioned above, the present invention proposes a method and device for generating a mixing and batching Block plan, which can automatically split the total plan of a large mixing pile into multiple Block plans under the premise of a known total plan of a large mixing pile, and the silicon and iron content of each Block plan is as close as possible to the silicon and iron content of the total plan of the large mixing pile, and the sum of the material ratios of all Block plans is the same as the material ratio of the total plan.

[0006] The present invention proposes a method for generating a mixing and batching Block plan, and the technical scheme of the method is as follows:

[0007] S1, obtain the overall plan for mixing the large pile;

[0008] S2, obtaining process parameters for mixing ingredients;

[0009] S3, input the overall plan of the mixed bulk and the process parameters of the mixed ingredients into the Block splitting model, execute the optimization algorithm, and obtain the complete Block plan after splitting;

[0010] The Block splitting model is used to split a large mixed pile master plan into multiple Block plans.

[0011] Furthermore, the overall plan of the mixed pile is specifically as follows:

[0012] The overall plan of the mixed pile includes multiple materials, and the parameters of each material include weight value, SiO2 content value, TFe content value and H2O content value; and the SiO2 content value and TFe content value of the overall plan of the mixed pile are calculated based on the parameters of all materials.

[0013] Furthermore, the process parameters of the mixing ingredients are specifically as follows:

[0014] Each mixing ingredient corresponds to a material, and each material is stored in a silo. One material uses at least one silo, and the maximum number of silos used for one material is c, where c ≥ 1; the process parameters of the silo include a first feeding speed value, and the range of the first feeding speed value is set to [α, β], where α is the minimum feeding speed of the silo, and β is the maximum feeding speed of the silo; multiple silos correspond to one mixing trough, and the process parameters of the mixing trough include a second feeding speed value, and the second feeding speed value is set to v.

[0015] Furthermore, the Block splitting model is specifically as follows:

[0016] The Block splitting model splits the total plan of the mixed pile into multiple Block plans. Each Block plan contains multiple materials in the mixed pile. The number of material types contained in each Block plan is limited to the quantity range [a, b], where a is the minimum number of material types contained in the Block plan, and b is the maximum number of material types contained in the Block plan. The objective function of the Block plan in the Block splitting model is established with the maximum total weight of materials contained in each Block plan as the goal. The constraint conditions of the Block plan in the Block splitting model are established with the SiO2 content value and TFe content value of each Block plan and the total plan of the mixed pile satisfying the pre-set conditions and the process parameters of the mixed ingredients as constraints.

[0017] Furthermore, the overall plan of the mixed pile of the Block split model is as follows:

[0018] A large mixed pile is planned to use multiple materials. The number of material types used in the large mixed pile is set to n; each material is numbered in sequence and the number is set to i; the weight value of the i-th material is set to m i , where the weight of the material is mi Including the weight of water; the SiO2 content value, TFe content value and H2O content value of the i-th material are set as According to the weight values, SiO2 content values, TFe content values ​​and H2O content values ​​of all materials, the total planned SiO2 content value and TFe content value of the mixed pile are calculated, and the total planned SiO2 content value and TFe content value of the mixed pile are set as p SiO2 、p TFe , the calculation formula is as follows:

[0019]

[0020]

[0021] The number of all materials, n, and the weight of each material, m i , SiO2 content value TFe content and H2O content The total planned SiO2 content of the mixed pile and TFe content value p TFe The overall plan for forming a mixed pile.

[0022] Furthermore, the objective function of the Block splitting model is specifically:

[0023] The Block splitting model splits the total plan of the mixed pile into multiple Block plans, and numbers the split Block plans in the order of the split time. The number is set to j, and the material weights in the total plan of the mixed pile used in the jth Block plan are Using this as the decision variable, establish the objective function Where z is the total weight of all materials included in the jth Block plan.

[0024] Furthermore, the constraints of the Block splitting model are specifically:

[0025] The constraints that the j-th Block plan needs to meet are as follows:

[0026]

[0027]

[0028]

[0029]

[0030]

[0031]

[0032]

[0033] Among them, constraint (1) means that the number of types of materials used in any Blockj plan must be within the quantity range [a, b]; constraint (2) means that the SiO2 content value of any Blockj plan is equal to the SiO2 content value of the total plan of the mixed pile, that is, the equal silicon constraint; constraint (3) means that the TFe content value of any Blockj plan is equal to the TFe content value of the total plan of the mixed pile, that is, the equal iron constraint; constraint (4) means that the unloading speed of each material used in any Blockj plan is not less than the minimum unloading speed α of the silo, and is not higher than the maximum unloading speed of the silo The product of β and the maximum number of silos c used for a material, i.e., cβ; constraint (5) indicates that any Blockj plan must use up at least one material; constraint (6) indicates the inheritance constraint of adjacent Block plans, i.e., the difference in the number of types of materials used by two adjacent Block plans cannot exceed h; constraint (7) indicates the value range of each material used by the jth Block plan, the minimum value of which is 0, and the maximum value of which is the weight value remaining after deducting the weight value of the corresponding material used by the 1st to j-1th Block plans from the initial weight value of each material, i.e.,

[0034] Furthermore, the optimization algorithm is specifically as follows:

[0035] The optimization algorithm uses a genetic algorithm. First, the optimization algorithm is used to calculate the first Block plan, and then the weight of the material used in the Block plan is deducted from the total plan of the mixed pile to obtain the total plan of the remaining mixed pile. The above optimization algorithm calculation process is repeated until the number of remaining material types in the total plan of the remaining mixed pile is within the preset number of types. The optimization algorithm calculation process ends and all Block plans are obtained.

[0036] Furthermore, the optimization algorithm comprises the steps of:

[0037] Step 1: Set the population size to N, and set j = 1;

[0038] Step 2: Randomly generate N groups of initial solutions according to the constraints Each set of solutions corresponds to an individual in the population, and the individuals in the population correspond to the decision variables in the Block plan. Let the number of iterations g = 0;

[0039] Step 3: Use the following formula to calculate the fitness of each set of solutions. The fitness of each set of solutions corresponds to the objective function of the Block plan.

[0040]

[0041] Step 4: Calculate the degree to which individuals in the population violate the constraints. Convert the inequalities in the constraints (1) to (6) into “≤” form and the equalities into absolute value form. The vector CV of the degree to which individuals violate the constraints is obtained as follows:

[0042]

[0043]

[0044]

[0045]

[0046]

[0047]

[0048]

[0049]

[0050] CV=[CV1,CV2,...,CV8];

[0051] Step 5: Determine whether the number of iterations g reaches the preset maximum number of iterations G. If so, output the vector CV with the maximum individual fitness and the degree of individual violation of constraints. The individual that meets the preset conditions is recorded as the optimal solution of the jth Block plan. Go to step 9; otherwise go to step 6;

[0052] Step 6: Let g = g + 1, and select the surviving N groups of solutions from the N groups of solutions according to the roulette wheel selection method;

[0053] Step 7: Perform a single-point crossover operation on the selected N groups of solutions according to the crossover probability preset in the optimization algorithm;

[0054] Step 8: According to the mutation probability preset in the optimization algorithm, all variables in each of the N groups of solutions after the single-point crossover operation are mutated in turn; go to step 3;

[0055] Step 9: Deduct the weight of the materials used in the jth Block plan from the total plan of the mixed pile to obtain the remaining total plan of the mixed pile. Determine whether the number of material types in the total plan of the remaining mixed pile is within the quantity range [a, b]. If so, take a set of solutions consisting of the weight values ​​of the remaining materials as the optimal solution of the last Block plan, denoted as x j+1* , the set of block plans after the total plan of the mixed large pile is [x1 * ,x2 * ,...,x j * ,x j+1 * ] T , the optimization algorithm calculation process ends and the entire Block plan is obtained; otherwise, let j=j+1 and go to step 2.

[0056] The present invention also proposes a device for generating a mixing and batching Block plan, wherein the device for generating a mixing and batching Block plan stores computer instructions; the computer instructions execute the method for generating a mixing and batching Block plan as described in any of the above items in the device for generating a mixing and batching Block plan.

[0057] The present invention also proposes a computer-readable storage medium, wherein the computer-readable storage medium stores computer instructions, and the computer instructions enable the computer to execute the method for generating a mixing and batching Block plan as described in any one of the above items.

[0058] The beneficial effects brought by the technical solution provided by the present invention are:

[0059] The method and device for generating a mixing and batching Block plan of the present invention can split the overall plan of the entire mixing pile into multiple Block plans according to process requirements, and ensure that the ferrosilicon content of each Block plan is equal to the ferrosilicon content of the overall plan of the mixing pile. This method significantly improves the quality of Block plan preparation under multiple constraints, and greatly reduces the workload of plan preparation in production organization. BRIEF DESCRIPTION OF THE DRAWINGS

[0060] Figure 1 A flowchart of a method for generating a mixing and batching Block plan according to an embodiment of the present invention;

[0061] Figure 2 A flowchart of an optimization algorithm solution process for generating a mixing and batching Block plan according to an embodiment of the present invention;

[0062] Figure 3 The present invention is a schematic diagram of the device structure of a method for generating a mixing and batching Block plan according to an embodiment of the present invention. DETAILED DESCRIPTION

[0063] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0064] Embodiment 1:

[0065] like Figure 1 The flowchart of a method for generating a mixing and batching Block plan according to an embodiment of the present invention is shown, which shows the specific implementation steps of the method, including:

[0066] In step S1, a general plan for mixing a large pile is obtained;

[0067] In one possible implementation, the overall plan of the mixing pile includes the weight of various materials needed for the entire mixing pile, and further, the weight of the materials is in tons; the quantity of all material types, the SiO2 content value, TFe content value and H2O content value of each material; and the SiO2 content value and TFe content value of the mixing pile calculated based on the weight value, SiO2 content value, TFe content value and H2O content value of all materials.

[0068] In step S2, the process parameters for mixing the ingredients are obtained;

[0069] In a possible implementation, taking the process parameters of mixing and batching in a raw material field of a steel enterprise as an example, the parameters include: the maximum number of silos used for a material c = 3, the first material discharge speed value range [α, β] of the silo is [40, 250] t / h, and the second material discharge speed value v of the mixing trough is 1200 t / h;

[0070] It should be noted that: in the present invention, the maximum number of silos used for one material is not c=3, the first material discharge speed value range [α, β] of the silo is [40,250] t / h, and the second material discharge speed value of the mixing trough is v=1200 t / h. It can be adjusted according to specific circumstances in actual applications.

[0071] In step S3, a block splitting model for a large mixed pile is established, specifically:

[0072] In one possible implementation, assume that the total plan for the mixed bulk pile uses n = 15 materials, and the weight value of the i-th material in the total plan for the mixed bulk pile is m i , where the weight of the material is m i Including the weight of water; the SiO2 content value, TFe content value and H2O content value of the i-th material are The total planned SiO2 content and TFe content of the mixed pile are p TFe , and p TFe The calculation formula is as follows:

[0073]

[0074]

[0075] The Block splitting model splits the total plan of the mixed pile into multiple Block plans. Each Block plan contains multiple materials in the mixed pile. The number limit range of the types and quantities of materials contained in each Block plan is set to [8,10]. The split Block plans are numbered in the order of the split time, and the number is set to j. The weight of the materials in the total plan of the pile used in the jth Block is And use this as the decision variable to establish the objective function Where z is the total weight of all materials included in the jth Block plan;

[0076] According to the overall plan of the mixing pile and the process parameters of the mixing ingredients, a set of constraints of the Block splitting model is obtained. The constraints that the j-th Block plan needs to meet are as follows:

[0077]

[0078]

[0079]

[0080]

[0081]

[0082]

[0083]

[0084] Among them, constraint (1) means that the number of types of materials used in any Blockj plan must be within the quantity range [8,10]; constraint (2) means that the SiO2 content value of any Blockj plan is equal to the SiO2 content value of the total plan of the mixed pile, that is, the equal silicon constraint; constraint (3) means that the TFe content value of any Blockj is equal to the TFe content value of the total plan of the mixed pile, that is, the equal iron constraint; constraint (4) means that the unloading speed of each material used in any Blockj plan shall not be lower than the minimum unloading speed of the silo 40t / h, and shall not be higher than the product of the maximum unloading speed of the silo 250t / h and the maximum number of silos used for one material 3, that is, 750t / h. h; constraint (5) indicates that any Blockj plan must use up at least one material; constraint (6) indicates the inheritance constraint of adjacent Block plans, that is, the difference in the number of types of materials used by two adjacent Block plans cannot exceed h types. Furthermore, it can be adjusted according to the number of carts that simultaneously add materials to the mixing trough. Assuming that the number of carts that simultaneously add materials to the mixing trough is 3, h can be set to 3; constraint (7) indicates the value range of each material used by the jth Block. The minimum value of the value range is 0, and the maximum value is the weight value remaining after deducting the weight value of the corresponding material used in the 1st to j-1th Block plans from the initial weight value of each material, that is,

[0085] It should be noted that: in the present invention, the number of material types n is not limited to 15, the number of material types included in each Block plan is limited to [a, b] to [8, 10], and the difference in the number of material types used by two adjacent Block plans is limited to h = 3. In actual applications, it can be adjusted according to specific circumstances.

[0086] It should be noted that the establishment of the Block splitting model in step S3 can also be established in advance before executing step S1. The Block splitting model splits a total plan of a large mixed pile into multiple Block plans.

[0087] In step S4, the optimization algorithm is executed to obtain all the split blocks, specifically:

[0088] The overall plan of the mixing pile described in step S1 and the process parameters of the mixing ingredients described in step S2 are input into the Block splitting model of the mixing pile described in step S3, and the optimization algorithm is executed to obtain the complete Block plan after splitting.

[0089] like Figure 2 The flowchart of the optimization algorithm solution process of the mixing and batching Block plan generation of the embodiment of the present invention is shown. Figure 1 The specific implementation steps of step S4 in the corresponding embodiment include:

[0090] In step 201, set the population size N=200 and set j=1;

[0091] In step 202, 200 sets of initial solutions are randomly generated according to the constraints. As the initial population, each set of solutions corresponds to an individual in the population, and the individuals in the population correspond to the decision variables in the Block plan. Let the number of iterations g = 0;

[0092] In step 203, the fitness of all individuals is calculated using the following formula, and the fitness of each group of solutions corresponds to the objective function of the Block plan;

[0093]

[0094] In step 204, the degree to which all individuals in the population violate the constraints is calculated, and the inequalities in the constraints (1) to (6) are converted into "≤" form, and the equalities are converted into absolute value form, and the vector CV of the degree to which the individuals violate the constraints is obtained as follows:

[0095]

[0096]

[0097]

[0098]

[0099]

[0100]

[0101]

[0102]

[0103] CV=[CV1,CV2,...,CV8];

[0104] In step 205, it is determined whether the number of iterations g reaches the preset maximum number of iterations G. Further, the maximum number of iterations can be adjusted according to the solution situation, and is generally set between 50 and 200. If so, go to step 210, otherwise, go to step 206;

[0105] In step 206, let g=g+1;

[0106] In step 207, 200 solutions are selected from the 200 solutions to enter the next generation according to the roulette wheel selection method;

[0107] In step 208, the selected 200 groups of solutions are subjected to a single-point crossover operation according to the crossover probability preset in the optimization algorithm;

[0108] In step 209, according to the mutation probability preset in the optimization algorithm, mutation operations are sequentially performed on all variables in each of the 200 solutions after the single-point crossover operation is performed, and then the process goes to step 203;

[0109] In step 210, the individual with the largest fitness and the individual whose individual violation constraint degree vector CV satisfies the preset conditions is output as the optimal solution of the jth Block plan.

[0110] In step 211, the weight of the material used in the jth Block plan is deducted from the total plan of the mixed bulk pile to obtain the remaining total plan of the mixed bulk pile, and it is determined whether the number of material types in the remaining total plan of the mixed bulk pile is within the quantity limit range [8,10]. If so, go to step 213; otherwise, go to step 212;

[0111] In step 212, let j=j+1, and go to step 202;

[0112] In step 213, a set of solutions consisting of the weight values ​​of the remaining materials is taken as the optimal solution of the last Block plan, denoted as x j+1 * , the total plan of the mixed large pile is split into a set of blocks [x1 * ,x2 * ,...,x j * ,x j+1 * ] T ;

[0113] In step 214, all block plans calculated by the optimization algorithm are obtained.

[0114] It should be noted that in the present invention, the maximum number of iterations G is not limited to a value range of 50 to 200, and can be adjusted according to specific circumstances in practical applications.

[0115] Embodiment 2:

[0116] The present invention also provides a system / electronic device, such as Figure 3As shown, the device includes a processor 301, a memory 302, a bus 303, and a computer program stored in the memory 302 and executable on the processor 301. The processor 301 includes one or more processing cores. The memory 302 is connected to the processor 301 via the bus 303. The memory 302 is used to store program instructions. When the processor executes the computer program, the steps in the above method embodiment of the first embodiment of the present invention are implemented.

[0117] Further, as an executable solution, the system / electronic device may be a computing device such as a desktop computer, a notebook, a PDA, and a cloud server. The system / electronic device may include, but is not limited to, a processor and a memory. Those skilled in the art will appreciate that the composition structure of the above-mentioned system / electronic device is merely an example of the system / electronic device and does not constitute a limitation on the system / electronic device, and may include more or less components than the above-mentioned, or a combination of certain components, or different components. For example, the system / electronic device may also include input / output devices, network access devices, buses, etc., which are not limited in the embodiments of the present invention.

[0118] Further, as an executable solution, the processor may be a central processing unit (CPU), other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc. The processor is the control center of the system / electronic device, and uses various interfaces and lines to connect various parts of the entire system / electronic device.

[0119] The memory can be used to store the computer program and / or module, and the processor realizes various functions of the system / electronic device by running or executing the computer program and / or module stored in the memory, and calling the data stored in the memory. The memory can mainly include a program storage area and a data storage area, wherein the program storage area can store an operating system and an application required for at least one function; the data storage area can store data created according to the use of the mobile phone, etc. In addition, the memory can include a high-speed random access memory, and can also include a non-volatile memory, such as a hard disk, a memory, a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (SecureDigital, SD) card, a flash card (Flash Card), at least one disk storage device, a flash memory device, or other volatile solid-state storage devices.

[0120] Embodiment three:

[0121] The present invention also provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the above method in the embodiment of the present invention are implemented.

[0122] If the module / unit integrated in the system / electronic device is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present invention implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, U disk, mobile hard disk, disk, optical disk, computer memory, read-only memory (ROM, Read-Onny Memory), random access memory (RAM, Random Access Memory) and software distribution medium, etc. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction.

[0123] Although the present invention has been specifically shown and described in conjunction with the preferred embodiments, it should be understood by those skilled in the art that various changes may be made to the present invention in form and details without departing from the spirit and scope of the present invention as defined by the appended claims, all of which are within the scope of protection of the present invention.

Claims

1. A method for generating a mixing and batching Block plan, characterized in that: Includes steps: S1, obtain the overall plan for mixing the large pile; The overall plan of the mixed pile is as follows: The overall plan of the mixed bulk pile includes multiple materials, and the parameters of each material include weight value, SiO2 content value, TFe content value and H2O content value; and the SiO2 content value and TFe content value of the overall plan of the mixed bulk pile are calculated based on the parameters of all materials; S2, obtaining process parameters for mixing ingredients; The process parameters of the mixing pile are specifically as follows: Each mixing ingredient corresponds to a material, and each material is stored in a silo. At least one silo is used for one material, and the maximum number of silos used for one material is c, where c ≥ 1; the process parameters of the silo include a first feeding speed value, and the range of the first feeding speed value is set to [α, β], where α is the minimum feeding speed of the silo, and β is the maximum feeding speed of the silo; multiple silos correspond to one mixing trough, and the process parameters of the mixing trough include a second feeding speed value, and the second feeding speed value is set to v; S3, input the overall plan of the mixed bulk and the process parameters of the mixed ingredients into the Block splitting model, execute the optimization algorithm, and obtain the complete Block plan after splitting; Wherein, the optimization algorithm comprises the steps of: Step 1: Set the population size to N, and set j = 1; Step 2: Randomly generate N groups of initial solutions according to the constraints Each set of solutions corresponds to an individual in the population, and the individuals in the population correspond to the decision variables in the Block plan. Let the number of iterations g = 0; Step 3: Use the following formula to calculate the fitness of each set of solutions. The fitness of each set of solutions corresponds to the objective function of the Block plan. Step 4: Calculate the degree to which individuals in the population violate the constraints. Convert the inequalities in the constraints (1) to (6) into "≤" form and the equalities into absolute value form. The vector CV of the degree to which individuals violate the constraints is obtained as follows: CV=[CV1,CV2,...,CV8]; Step 5: Determine whether the number of iterations g reaches the preset maximum number of iterations G. If so, output the vector CV with the maximum individual fitness and the degree of individual violation of constraints. The individual that meets the preset conditions is recorded as the optimal solution of the jth Block plan. Go to step 9; otherwise go to step 6; Step 6: Let g = g + 1, and select the surviving N groups of solutions from the N groups of solutions according to the roulette wheel selection method; Step 7: Perform a single-point crossover operation on the selected N groups of solutions according to the crossover probability preset in the optimization algorithm; Step 8: According to the mutation probability preset in the optimization algorithm, all variables in each of the N groups of solutions after the single-point crossover operation are mutated in turn; go to step 3; Step 9: Deduct the weight of the materials used in the jth Block plan from the total plan of the mixed pile to obtain the remaining total plan of the mixed pile. Determine whether the number of material types in the total plan of the remaining mixed pile is within the quantity range [a, b]. If so, take a set of solutions consisting of the weight values ​​of the remaining materials as the optimal solution of the last Block plan, denoted as x j+1 * , the set of block plans after the total plan of the mixed large pile is [x1 * ,x2 * ,...,x j * ,x j+1 * ] T , the optimization algorithm calculation process ends and all block plans are obtained; otherwise, let j = j + 1 and go to step 2; The Block splitting model is used to split the total plan of the mixed pile into multiple Block plans, each Block plan contains multiple materials in the mixed pile, and the number of types of materials contained in each Block plan is limited to the quantity range [a, b], where a is the minimum number of types of materials contained in the Block plan, and b is the maximum number of types of materials contained in the Block plan; the objective function of the Block plan in the Block splitting model is established with the maximum total weight of materials contained in each Block plan as the goal; the SiO2 content value and TFe content value of each Block plan and the total plan of the mixed pile meet the pre-set conditions and the process parameters of the mixed ingredients as constraints, and the constraint conditions of the Block plan in the Block splitting model are established; The objective function of the Block splitting model is as follows: The Block splitting model splits the total plan of the mixed pile into multiple Block plans, and numbers the split Block plans in the order of the split time, and sets the number to j. The weight of the materials in the total plan of the mixed pile used in the jth Block plan is Using this as the decision variable, establish the objective function Where z is the total weight of all materials included in the jth Block plan; The constraints of the Block splitting model are specifically: The constraints that the j-th Block plan needs to meet are as follows: Among them, constraint (1) means that the number of types of materials used in any Block j plan must be within the quantity range [a, b]; constraint (2) means that the SiO2 content value of any Block j plan is equal to the SiO2 content value of the total plan of the mixed pile, that is, the equal silicon constraint; constraint (3) means that the TFe content value of any Block j plan is equal to the TFe content value of the total plan of the mixed pile, that is, the equal iron constraint; constraint (4) means that the unloading speed of each material used in any Block j plan is not less than the minimum unloading speed α of the silo, and is not higher than the product of the maximum unloading speed β of the silo and the maximum number c of silos used for one material, that is, cβ; constraint (5) means that any Block Plan j must use up at least one material. Constraint (6) indicates the inheritance constraint of adjacent block plans, that is, the difference in the number of materials used by two adjacent block plans cannot exceed h. Constraint (7) indicates the value range of each material used by the jth block plan. The minimum value of the value range is 0, and the maximum value is the weight value remaining after deducting the weight value of the corresponding material used by the 1st to j-1th block plans from the initial weight value of each material, that is, The optimization algorithm is specifically as follows: the optimization algorithm uses a genetic algorithm, first using the optimization algorithm to calculate the first Block plan, then deducting the weight of the material used in the Block plan from the total plan of the mixed pile to obtain the total plan of the remaining mixed pile, repeating the above optimization algorithm calculation process until the number of remaining material types in the total plan of the remaining mixed pile is within the preset number of types range, the optimization algorithm calculation process ends, and all Block plans are obtained.

2. The method according to claim 1, characterized in that The block splitting model includes the overall plan of mixing the large pile, specifically: A large mixed pile is planned to use multiple materials. The number of material types used in the large mixed pile is set to n; each material is numbered in sequence and the number is set to i; the weight value of the i-th material is set to m i , where the weight of the material is m i Including the weight of water; the SiO2 content value, TFe content value and H2O content value of the i-th material are set as According to the weight values, SiO2 content values, TFe content values ​​and H2O content values ​​of all materials, the total planned SiO2 content value and TFe content value of the mixed pile are calculated, and the total planned SiO2 content value and TFe content value of the mixed pile are set as p TFe , the calculation formula is as follows: The number of all materials, n, and the weight of each material, m i , SiO2 content value TFe content and H2O content The total planned SiO2 content of the mixed pile and TFe content value p TFe The overall plan for forming a mixed pile.

3. A device for generating a mixing and batching block plan, characterized in that: It includes a memory and a processor, the memory stores at least one program, and the at least one program is executed by the processor to implement the method for generating a mixing and batching Block plan as described in any one of claims 1 to 2.

4. A computer-readable storage medium, characterized in that: The storage medium stores at least one program, and the at least one program is executed by a processor to implement the method for generating a mixing and batching Block plan as described in any one of claims 1 to 2.