A day-ahead economic coordination and dispatching method for integrated energy systems considering multiple uncertainties

By modeling multiple types of uncertainty sources in the integrated energy system and combining electric and thermal resources, a day-ahead economic coordination dispatch model is established, which solves the problem of characterization of multiple uncertainties in the system and realizes the reduction of system operating costs and dispatch strategies. effectiveness improvement.

CN114219221BActive Publication Date: 2024-10-29GUIZHOU POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111373537.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-19
Publication Date
2024-10-29
Estimated Expiration
2041-11-19

AI Technical Summary

Technical Problem

In integrated energy systems, multiple uncertainties (such as energy prices, wind power output and demand response) are difficult to accurately characterize, affecting the flexibility and economy of dispatch models.

Method used

By modeling multiple types of uncertainty sources, combined with electricity-to-hydrogen (PtH), fuel cells and other resources, a day-ahead economic coordination dispatch model of the electric and thermal integrated energy system is established, and a zero-sum game model of uncertainty sources and system operating costs is constructed. , to formulate scheduling strategies that consider multiple uncertainties.

Benefits of technology

It achieves accurate characterization of uncertainty sources in integrated energy systems, reduces system operating costs, and improves the effectiveness and flexibility of dispatch strategies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114219221B_ABST
    Figure CN114219221B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties, including: step S1: constructing uncertainty modeling of multiple types of uncertain sources such as energy price, wind power output, and demand response; step S2: using electric hydrogen production and fuel cells as dispatching models of flexible resources of the integrated energy system; step S3: establishing a day-ahead economic coordination and dispatching model for the electric-thermal integrated energy system, rationalizing the sources of uncertainty as game subjects, and constructing a zero-sum game model of the sources of uncertainty and the operating cost of the integrated energy system. The present invention can accurately characterize the sources of uncertainty and realize day-ahead economic coordination and dispatching of the integrated energy system considering multiple uncertainties.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric power dispatching, and in particular to a day-ahead economic coordination and dispatching method for an integrated energy system taking multiple uncertainties into consideration. Background Art

[0002] With the depletion of fossil energy and the intensification of environmental pollution, vigorously developing renewable energy has become a strategic choice for countries to achieve a low-carbon economy and build a sustainable energy system. However, the load demand does not match the growth rate of concentrated construction of new energy, and the problem of new energy consumption is serious. In addition, the volatility and uncertainty of new energy power generation will have a huge impact on the operation and scheduling of the integrated energy network with a high proportion of new energy. Therefore, it may face multiple uncertainties in terms of electricity storage, heat storage, gas storage, hydrogen storage, pumped storage, etc. This diversified energy storage technology is a major component of the integrated energy network and will also be the key to the development of larger-scale renewable energy in the future. Among the many energy storage methods, hydrogen storage has the advantages of long storage time, large storage scale, environmental protection and pollution-free, and no geographical restrictions. It will play an important role in specific application scenarios.

[0003] In terms of integrated energy system modeling, scholars have been studying integrated energy systems and their uncertainties. A large number of studies have been conducted on source modeling. Some studies have considered the response characteristics of electricity to gas, and used opportunity constraints to consider the uncertainty of wind power output for coordinated scheduling. Referring to the impact of uncertainty in renewable energy output on system planning, some studies have realized the description of uncertain scenarios based on scenario methods, and proposed a multi-objective planning method considering landscape uncertainty with the minimum economic cost, maximum wind and solar energy absorption rate and minimum energy supply as optimization goals. These studies have preliminarily established a scheduling model that considers the uncertainty of the integrated energy system. However, in the process of establishing the integrated energy system model, the combination of PtH and FC technology was not used as a flexibility resource for the integrated energy system, and the uncertainty source representation was not accurate enough. Summary of the invention

[0004] The purpose of the first aspect of the present invention is to provide a method for day-ahead economic coordination and scheduling of an integrated energy system taking into account multiple uncertainties, which can accurately characterize sources of uncertainty and realize strategy formulation for day-ahead economic coordination and scheduling of an integrated energy system taking into account multiple uncertainties.

[0005] To achieve the above object, the present invention adopts the following technical solution:

[0006] A method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties comprises the following steps:

[0007] Step S1: uncertainty modeling of multiple types of uncertainty sources: uncertainty sources of energy prices, wind power output, and demand response are modeled;

[0008] Step S2: Considering power-to-hydrogen (PtH) and fuel cells as flexible resources in the integrated energy system and modeling them;

[0009] Step S3: Combine wind power, photovoltaics, PtH, FC, and gas to establish a day-ahead economic coordination and dispatch model for the electric-thermal integrated energy system, rationalize the sources of uncertainty as game entities, and construct a zero-sum game model of the sources of uncertainty and the operating costs of the integrated energy system. Through model calculation, the strategy formulation of the day-ahead economic coordination and dispatch of the integrated energy system considering multiple uncertainties is completed.

[0010] Furthermore, in step S1, the uncertainty model includes an energy price uncertainty model, a wind power output uncertainty model, and a demand response uncertainty feature modeling.

[0011] Further, in step S3, the objective function is designed as follows:

[0012] The optimization goal of the dispatching model is to minimize the operating cost of the entire system as much as possible under the premise of meeting the regional load and system safe operation. Since the start and stop status of conventional units in the system cannot be adjusted and corrected in real time according to the electricity price of different scenarios after the date is determined, the system operating cost is divided into the start and stop cost of the first stage of conventional units and the second stage of conventional units, and the sum of the operating cost and transaction cost of the power market. The worst objective function F with uncertainty is:

[0013]

[0014]

[0015]

[0016]

[0017]

[0018]

[0019]

[0020]

[0021]

[0022]

[0023]

[0024] Among them, ψ U , M , L are the decision variable sets at the upper, middle and lower levels respectively; N G is the total number of regular units; T is the total number of scheduling cycles; is the fixed operating cost of the i-th conventional unit; is the operating status of the i-th conventional unit at time t, where 0 means the unit is in the shutdown state, and 1 means the unit is in the operating state; and are the start-up and stop costs of the ith unit, respectively; are the start and stop motion variables of the ith conventional unit in time, respectively; Ω is the set of power generation price scenarios; and is the fixed cost of wind power and photovoltaic power; is the fixed operating cost of the electrolyser; is the fixed maintenance cost of hydrogen storage; is the fixed maintenance cost of the fuel cell; It is the fixed maintenance cost of the electric boiler; is the fixed cost of gas turbine operating cost; are the electricity purchased and sold from the electricity market at that time in the scenario respectively; are the corresponding electricity purchase price and electricity sales price respectively; C wt,pv is the cost of wind and photovoltaic power generation; is the penalty cost of abandoning wind and solar power; is the cost of PTH; C HS is the hydrogen storage cost; C FC , C EB , C g and are the operating costs of the fuel cell, electric boiler and gas turbine respectively; λ wt and λ pv are the unit electricity operating costs of wind power and photovoltaic power respectively; P wt (t) and P pv (t) are the output power of wind power and photovoltaic power in period t respectively; and They are the penalty costs for curtailing wind and solar power; are the abandoned wind power and abandoned solar energy during the period; p2h is the cost per unit mass of PTH; HS is the hydrogen storage cost coefficient; FC is the operating cost per unit power of the fuel cell; P FC (t) is the output power of the fuel cell during period t; η FCis the operating efficiency of the fuel cell; EB is the operating cost per unit power of the electric boiler; g It is the operating cost per unit power of the gas turbine.

[0025] Further, in step S3, the constraints of the scheduling model include energy balance constraints, heat load and heat supply balance constraints, wind power and photovoltaic output power balance constraints, controllable device output active power constraints, and controllable device power climbing constraints;

[0026] Furthermore, the constraints of the dispatch model also include: hydrogen production limit constraint; hydrogen storage extreme limit constraint; hydrogen storage balance constraint; power market transaction constraint; price-based demand response constraint;

[0027] The second aspect of the present invention aims to provide a device for day-ahead economic coordination and scheduling of an integrated energy system taking into account multiple uncertainties, comprising a memory, a processor, and a computer program stored in the memory and capable of running on the processor, wherein the processor implements the method described above when executing the computer program.

[0028] The third aspect of the present invention aims to provide a computer-readable storage medium having a computer program stored thereon, wherein the computer program implements the above-mentioned method when executed by a processor.

[0029] The beneficial effects of the present invention are:

[0030] The method of the present invention first models the sources of uncertainty such as energy prices, wind power output, and demand response, takes power-to-hydrogen (PtH) and fuel cells as flexible resources of the integrated energy system and models them, and establishes a day-ahead economic coordination and scheduling model for the electric-thermal integrated energy system by combining wind power, photovoltaics, PtH, FC, gas, etc., rationalizes the sources of uncertainty as game entities, constructs a zero-sum game model of the sources of uncertainty and the operating costs of the integrated energy system, and finally calculates and implements the day-ahead economic coordination and scheduling strategy formulation of the integrated energy system considering multiple uncertainties.

[0031] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description and the preceding claims. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be further described in detail below with reference to the accompanying drawings, in which:

[0033] Figure 1It is a schematic diagram of the wind turbine's available wind power forecast value, fluctuation range and load forecast value;

[0034] Figure 2 This is the power dispatch result diagram;

[0035] Figure 3 This is the thermodynamic equilibrium result diagram. DETAILED DESCRIPTION

[0036] The specific implementation of the present invention will be further described below through specific examples in conjunction with the accompanying drawings.

[0037] The specific steps of the present invention include:

[0038] Step S1: uncertainty modeling of multiple types of uncertainty sources: uncertainty sources of energy prices, wind power output, and demand response are modeled;

[0039] Step S2: Considering power-to-hydrogen (PtH) and fuel cells as flexible resources in the integrated energy system and modeling them;

[0040] Step S3: Combine wind power, photovoltaics, PtH, FC, and gas to establish a day-ahead economic coordination dispatch model for the electric-thermal integrated energy system, rationalize the sources of uncertainty as game entities, and construct a zero-sum game model of the sources of uncertainty and the operating costs of the integrated energy system.

[0041] In step S1, the uncertainty source modeling method of energy price, wind power output and demand response is as follows:

[0042] (1) Energy price uncertainty model

[0043] Within the range of electricity price fluctuations, a limited set of scenarios generated using historical data are used to describe possible implementation scenarios of electricity prices. i Each corresponds to a specific electricity price and scenario probability πω i . As a price acceptor, the virtual power plant establishes a set of corresponding constraints for each scenario, solves the model to obtain the transaction power for each transaction price, and establishes a quotation curve. During day-ahead scheduling, the virtual power plant provides the power market operator with a quotation curve; the power market operator clears the market and determines the hourly day-ahead market price and scheduled transaction power of the virtual power plant the next day based on the quotation curve submitted by the virtual power plant; the power market operator feeds the price back to the virtual power plant. The virtual power plant operator selects the trading right at this time through the real-time electricity price. Comprehensively considering the operating costs of virtual power plants in all scenarios can effectively deal with the uncertainty of electricity prices.

[0044] (2) Wind power output uncertainty model

[0045] Wind power output is uncertain and cannot be accurately predicted. To ensure the safe operation of the system, a certain amount of spinning reserve must be reserved for the unit to deal with the situation where wind power output is overestimated. The expression is as follows:

[0046]

[0047]

[0048] Where: Ω R The coal-fired and gas-fired generating units are shut down; max,i It is the maximum value of the unit's upward rotation reserve; is the upper limit of unit output; is the upward rotation reserve per unit time; P i,t is the output per unit time; Pr{.} represents the probability of occurrence of event {·}; is the actual available output of the wind turbine at that time; C u is the corresponding setting reliability.

[0049] (3) Demand response uncertainty characteristic modeling

[0050] Demand response uncertainty lacks public historical data, and its probability distribution varies greatly in regionalization, so it is impossible to use scenario planning to generate scenarios for modeling. At the same time, demand response directly affects the power balance and spinning reserve constraints of the virtual power plant. Its uncertainty is likely to cause the daily dispatch results to exceed the safe operating limit, affecting operational safety. Therefore, the uncertainty of wind power output can be simulated, and the ARO method can be used to deal with the uncertainty of demand response. Demand response uncertainty value set Λ DR for:

[0051]

[0052]

[0053]

[0054]

[0055] Among them, P t DR is the actual demand response value at that time; is the demand response forecast value at that time; is the demand response forecast error value at the time point; is the indicator variable of time; DR is the demand response uncertainty budget value. satisfy:

[0056]

[0057] Among them, ε t is the time load elastic coefficient; t is the rate of change of electricity price at that time; P 1,t is the load forecast value at time t. Under the time-of-use electricity price environment, the load response forecast problem can be regarded as the load forecast problem under different electricity price environments. Therefore, the maximum error level of demand response is regarded as a two-segment linear model related to load response, self-elasticity coefficient and electricity price incentive level, as shown in the following formula:

[0058]

[0059] Among them, λ Δc,max is the upper limit when the electricity price change rate is greater than 0; Δc,min It is the lower limit when the electricity price change rate is less than 0; It is the inflection point of the rate of change of electricity price where the load response is dominant and the electricity price factor is dominant, and its absolute value is negatively correlated with the degree of electricity price incentive guidance. k1 and k2 are the proportional coefficients of the demand response prediction error and load response before and after the inflection point.

[0060] In step S2, the power-to-hydrogen (PtH) and fuel cells are modeled as flexible resources of the integrated energy system as follows:

[0061] (1) Hydrogen production by water electrolysis

[0062] Hydrogen production by water electrolysis produces hydrogen and oxygen by injecting direct current into the electrolytic cell. The chemical reaction process is 2H2O→O2+H2, and the energy conversion efficiency of this process is 75%-85%. The generated hydrogen is compressed by a compressor and stored in a hydrogen storage tank. The hydrogen production calculation formula is as follows:

[0063] H el (t) = η e2h P el (t)Δt / (3.6L)

[0064] Among them, H el (t) is the mass of hydrogen produced by the electrolyzer at time t; η e2h is the efficiency of hydrogen production by water electrolysis; P el (t) is the active power of water electrolysis to produce hydrogen at that time; Δt is the time step; L is the lower calorific value of hydrogen, which is 119.64MJ / kg.

[0065] The pressure in the hydrogen storage tank can reflect the capacity of hydrogen, and the calculation formula is:

[0066]

[0067] Where, e(t) and e(t-1) are the pressures in the hydrogen storage tank during t and t-1 respectively; R is the general gas constant, which is 8.314 J / (mol*k); is the temperature inside the hydrogen storage tank; V is the volume of the hydrogen storage tank; H s (t) is the amount of hydrogen stored in the electrolyzer during this period.

[0068] (2) Fuel Cell

[0069] Since a single PEMFC can only generate a voltage of 0.5 to 0.9Ω, it is often connected in series and parallel in industrial applications to increase the overall output current and voltage. The formula for calculating the output voltage of a single PEMFC unit is as follows:

[0070] u F =E q -η a -η o -η c

[0071] Among them, u F is the output voltage of PEMFC; E q is the open circuit voltage of PEMFC; η a is the activation polarization loss voltage, used to drive the electrochemical reaction; η o is the ohmic loss voltage, which is determined by the loss caused by the ion flow resistance and contact resistance in the electrolyte; η c It is the concentration polarization loss voltage, which is the loss caused by the rapid consumption of reactants on the electrode to produce a concentration gradient. The total power generated by the chemical reaction of PEMFC is related to the hydrogen consumption rate of the fuel cell and can be expressed as:

[0072]

[0073]

[0074] Among them, P che is the total power generated by the PEMFC chemical reaction; is the hydrogen consumption rate of PEMFC (mol / s); ΔH is the reaction heat of hydrogen, which is 285.83 kJ / mol; F is the Faraday constant, which is 96485 C / mol.

[0075] In step S3, the day-ahead economic coordination dispatch model of the electric-thermal integrated energy system is calculated, and its objective function and constraints are expressed as follows:

[0076] (1) Objective function

[0077] The electric-thermal integrated energy system considered is mainly composed of conventional units, wind turbines, PtH, FC, gas turbines, electric boilers and flexible loads. The system uses conventional units and wind turbines as the main power generation energy sources to supply power to regional loads. The energy storage system and flexible loads provide power compensation for wind turbine output fluctuations. In addition, the system is also interconnected with the external power market for power trading.

[0078] The optimization goal of the dispatch model is to minimize the operating cost of the entire system as much as possible while meeting the regional load and system safety. Since the start and stop status of conventional units in the system cannot be adjusted and corrected in real time according to the electricity price of different scenarios after the date is determined, this paper divides the system operating cost into the start and stop cost of the first phase of conventional units and the second phase of conventional units, and the sum of the operating cost and transaction cost of the power market. The worst objective function F with uncertainty is:

[0079]

[0080]

[0081]

[0082]

[0083]

[0084]

[0085]

[0086]

[0087]

[0088]

[0089]

[0090] Among them, ψ U , M , L are the decision variable sets at the upper, middle and lower levels respectively; N G is the total number of regular units; T is the total number of scheduling cycles; is the fixed operating cost of the i-th conventional unit; is the operating status of the i-th conventional unit at time t, where 0 means the unit is in the shutdown state, and 1 means the unit is in the operating state; and are the start-up and stop costs of the ith unit, respectively; are the start and stop motion variables of the ith conventional unit in time, respectively; Ω is the set of power generation price scenarios; and is the fixed cost of wind power and photovoltaic power; is the fixed operating cost of the electrolyser; is the fixed maintenance cost of hydrogen storage; is the fixed maintenance cost of the fuel cell; It is the fixed maintenance cost of the electric boiler; is the fixed cost of gas turbine operating cost; are the electricity purchased and sold from the electricity market at that time in the scenario respectively; are the corresponding electricity purchase price and electricity sales price respectively; C wt,pv is the cost of wind and photovoltaic power generation; is the penalty cost of abandoning wind and solar power; is the cost of PTH; C HS is the hydrogen storage cost; C FC , C EB , C g and are the operating costs of the fuel cell, electric boiler and gas turbine respectively; λ wt and λ pv are the unit electricity operating costs of wind power and photovoltaic power respectively; P wt (t) and P pv (t) are the output power of wind power and photovoltaic power in period t respectively; and They are the penalty costs for curtailing wind and solar power; are the abandoned wind power and abandoned solar energy during the period; p2h is the cost per unit mass of PTH; HS is the hydrogen storage cost coefficient; FC is the operating cost per unit power of the fuel cell; P FC (t) is the output power of the fuel cell during period t; η FC is the operating efficiency of the fuel cell; EB is the operating cost per unit power of the electric boiler; g It is the operating cost per unit power of the gas turbine.

[0091] (2) Constraints

[0092] a. Energy balance constraints

[0093]

[0094] in, is the electricity required to produce hydrogen during the scenario period; is the amount of electricity purchased from the electricity market during the time period under scenario ω; PELω (t) is the electricity demand during the scenario period; is the demand response load during the period under the scenario; P EBω (t) is the amount of electricity converted into heat energy by using electric boilers during the scenario period; P FCω (t) is the output power of the fuel cell in the scenario over a period of time; P is the amount of electricity provided to the power load from wind power and photovoltaic output power during the scenario period; gω (t) is the power output of the gas turbine during the period in the scenario; is the electricity purchased from the electricity market during the scenario period.

[0095] b. Heat load and heat supply balance constraints

[0096] Q FCω (t)+Q gω (t)+Q EBω (t) = Q HLω (t)

[0097] Among them, Q HLω (t) is the heat load demand during period t; Q FCω (t) is the heat output of the fuel cell during this period.

[0098] c. Power balance constraints of PtH

[0099]

[0100] Among them, in the output power of wind power and photovoltaic power generation, are the electrical energy used for PtH, respectively.

[0101] d. Wind power and photovoltaic output power balance constraints

[0102]

[0103]

[0104] e. Active power constraints of controllable equipment output

[0105]

[0106] Where k = FC, g, EB represent fuel cell, gas turbine, and electric boiler respectively; are the upper and lower limits of the active power output of controllable device k respectively.

[0107] f. Power ramp-up constraints for controllable devices

[0108]

[0109] in, and They are the downward climbing rate and upward climbing rate of the controllable equipment respectively.

[0110] g. Hydrogen production restrictions

[0111]

[0112] in, The maximum hydrogen production

[0113] h. Hydrogen storage limit constraints

[0114]

[0115] in, It is the maximum hydrogen storage capacity of the electrolyzer.

[0116] i. Hydrogen storage balance constraints

[0117] H s (t) = H s (t-1)+H el (t)Δt-H csp (t)Δt

[0118] Among them, H csp (t) is the hydrogen consumption during period t.

[0119] j. Power market transaction constraints

[0120] Maximum trading power limit:

[0121]

[0122]

[0123]

[0124] in, and are variables indicating that the virtual power plant is in the power purchasing state and power selling state respectively; and are the maximum purchasing and selling capabilities of the virtual power plant at time t. The above constraints mean that the virtual power plant cannot be in the state of buying and selling electricity at the same time.

[0125] k. Price-based demand response constraints

[0126] Among the various factors that affect user demand response, price factors have the most significant impact. In the time-of-use electricity price environment, the self-elasticity coefficient is often used to characterize the impact of the electricity price change rate on the load change rate. The self-elasticity coefficient is defined as:

[0127]

[0128] in, is the load response rate at time t.

[0129] Electricity price constraints and demand response quantity balance constraints:

[0130]

[0131]

[0132] The above formula represents the balance of load response during the entire scheduling cycle.

[0133] like Figure 1 As shown, the maximum charging and discharging power of the energy storage device in this embodiment is 20MW, and the maximum energy storage power is 100MW·h; the maximum power sale in the power market is 50MW, the maximum power purchase is 50MW, the electricity price fluctuation range is 50%, and 5 electricity price scenarios are generated based on historical data, and the probability of each scenario is 0.2.

[0134] From the attached Figure 2 It can be seen that during the period of 0-5h and 19-24h, photovoltaic power generation was not generated, and wind power was insufficient to supply the power load. The power consumption of the electric boiler was not much. The electric-heat balance was met. The electric boiler consumed electric energy to supply the heat load, and the balance of electric energy and heat energy constrained each other. Figure 3 It can be seen that during the period from 6h to 18h, the total output of wind and solar energy is much greater than the demand of electricity load. During this period, the heat output of the electric boiler is about twice that of the period from 0h to 5h, which reduces the fuel cost of the gas turbine. However, due to the minimum operating power and climbing restrictions of the gas turbine, the operating cost of the gas turbine during this period did not drop significantly. The PTH cost, hydrogen storage cost, and fuel cell operating cost result in a small proportion of PTH and fuel cells in the integrated energy system, but the total amount is not small. As flexible adjustment devices for energy balance, PTH and fuel cells achieve the effects of absorbing and abandoning wind and solar power, shaving peaks and filling valleys, and alleviating fluctuations in wind and solar output.

[0135] Any process or method description described in the present invention may be understood to represent a module, segment or portion of code including one or more executable instructions for implementing specific logical functions or steps of a process, and the scope of the preferred embodiments of the present invention includes alternative implementations, in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order according to the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present invention belong.

[0136] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.

[0137] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, a plurality of steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

[0138] A person skilled in the art may understand that all or part of the steps of the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.

[0139] In addition, each functional unit in each embodiment of the present invention may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium. The above-mentioned storage medium may be a read-only memory, a disk or an optical disk, etc.

[0140] Although the embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and cannot be understood as limiting the present invention. A person skilled in the art may change, modify, replace and modify the above embodiments within the scope of the present invention without departing from the principles and purpose of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties, characterized in that: Includes steps: Step S1: uncertainty modeling of multiple types of uncertainty sources: modeling of uncertainty sources of energy prices, wind power output, and demand response; Step S2: Modeling hydrogen production by electricity and fuel cells as flexible resources of the integrated energy system, wherein hydrogen production by electricity is PtH; Step S3: Combine wind power, photovoltaic power, PtH, FC, and gas to establish a day-ahead economic coordination dispatch model for the electric-thermal integrated energy system, rationalize the sources of uncertainty as game entities, and construct a zero-sum game model of the sources of uncertainty and the operating costs of the integrated energy system; in step S3, the objective function is designed as follows: The optimization goal of the dispatching model is to minimize the operating cost of the entire system as much as possible under the premise of meeting the regional load and system safe operation. Since the start and stop status of conventional units in the system cannot be adjusted and corrected in real time according to the electricity price of different scenarios after the date is determined, the system operating cost is divided into the start and stop cost of the first stage of conventional units and the second stage of conventional units, and the sum of the operating cost and transaction cost of the power market. The worst objective function F with uncertainty is: Among them, ψ U , M , L are the decision variable sets at the upper, middle and lower levels respectively; N G is the total number of regular units; T is the total number of scheduling cycles; is the fixed operating cost of the i-th conventional unit; is the operating status of the i-th conventional unit at time t, where 0 means the unit is in the shutdown state, and 1 means the unit is in the operating state; and are the start-up and stop costs of the ith unit, respectively; are the start and stop motion variables of the ith conventional unit in time, respectively; Ω is the set of power generation price scenarios; and is the fixed cost of wind power and photovoltaic power; is the fixed operating cost of the electrolyser; is the fixed maintenance cost of hydrogen storage; is the fixed maintenance cost of the fuel cell; It is the fixed maintenance cost of the electric boiler; is the fixed cost of gas turbine operating cost; are the electricity purchased and sold from the electricity market at that time in the scenario respectively; are the corresponding electricity purchase price and electricity sales price respectively; C wt,pv is the cost of wind and photovoltaic power generation; is the penalty cost of abandoning wind and solar power; is the cost of PTH; C HS is the hydrogen storage cost; C FC , C EB , C g and are the operating costs of the fuel cell, electric boiler and gas turbine respectively; λ wt and λ pv are the unit electricity operating costs of wind power and photovoltaic power respectively; P wt (t) and P pv (t) are the output power of wind power and photovoltaic power in period t respectively; and They are the penalty costs for curtailing wind and solar power; are the abandoned wind power and abandoned solar energy during the period; p2h is the cost per unit mass of PTH; HS is the hydrogen storage cost coefficient; FC is the operating cost per unit power of the fuel cell; P FC (t) is the output power of the fuel cell during period t; η FC is the operating efficiency of the fuel cell; EB is the operating cost per unit power of the electric boiler; g is the operating cost per unit power of the gas turbine; In step S3, the constraints of the scheduling model include energy balance constraints, heat load and heat supply balance constraints, wind power and photovoltaic output power balance constraints, controllable device output active power constraints, and controllable device power ramp constraints, which are respectively expressed as follows: (1) Energy balance constraints in, is the electricity required to produce hydrogen during the scenario period; is the amount of electricity purchased from the electricity market during the time period under scenario ω; P ELω (t) is the electricity demand during the scenario period; is the demand response load during the period under the scenario; P EBω (t) is the amount of electricity converted into heat energy by using electric boilers during the scenario period; P FCω (t) is the output power of the fuel cell in the scenario over a period of time; P is the amount of electricity provided to the power load from wind power and photovoltaic output power during the scenario period; gω (t) is the power output of the gas turbine during the scenario period; is the electricity purchased from the electricity market during the scenario period; (2) Heat load and heat supply balance constraints Q FCω (t)+Q gω (t)+Q EBω (t)=Q HLω (t) Among them, Q HLω (t) is the heat load demand during period t; Q FCω (t) is the heat output of the fuel cell during this period; (3) Power balance constraints of PtH Among them, in the output power of wind power and photovoltaic power generation, They are the electrical energy used for PtH; (4) Wind power and photovoltaic output power balance constraints (5) Active power constraints of controllable equipment output Where k = FC, g, EB represent fuel cell, gas turbine, and electric boiler respectively; are the upper and lower limits of the output active power of the controllable device k respectively; (6) Power ramp constraints for controllable devices in, and are the downward climbing rate and upward climbing rate of the controllable equipment respectively; In step S3, the constraints of the scheduling model also include: (7) Hydrogen production restrictions in, is the maximum value of hydrogen production; (8) Hydrogen storage limit constraints in, is the maximum hydrogen storage capacity of the electrolyzer; (9) Hydrogen storage balance constraints H s (t)=H s (t-1)+H el (t)Δt-H csp (t)Δt Among them, H csp (t) is the hydrogen consumption in period t; (10) Power market transaction constraints Maximum trading power limit: in, and are variables indicating that the virtual power plant is in the power purchasing state and power selling state respectively; and are the maximum purchase and sale capacity of the virtual power plant at time t respectively; the above constraints make it impossible for the virtual power plant to be in the state of buying and selling electricity at the same time; (11) Price-based demand response constraints In a time-of-use electricity price environment, the self-elasticity coefficient is often used to characterize the impact of the electricity price change rate on the load change rate. The self-elasticity coefficient is defined as: l Δq,t =e t l Δc,t Among them, λ Δq,t is the load response rate at time t; Electricity price constraints and demand response quantity balance constraints: l Δc,min ≤λ Δc,t ≤λ Δc,max The above formula represents the balance of load response during the entire scheduling cycle.

2. The method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties according to claim 1 is characterized by: In step S1, the uncertainty model includes an energy price uncertainty model, a wind power output uncertainty model, and a demand response uncertainty feature modeling.

3. The method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties according to claim 1 is characterized in that: The energy price uncertainty model refers to a set of limited scenarios generated by historical data to describe the possible implementation scenarios of electricity prices within the range of electricity price fluctuations. i Each corresponds to a specific electricity price and scenario probability πω i ,The virtual power plant acts as a price taker, establishes a set of corresponding constraints for each scenario, solves the model to obtain the transaction power for each transaction price, and establishes the quotation curve.

4. The method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties according to claim 1 is characterized in that: The expression of wind power output uncertainty model is as follows: Where: Ω R The coal-fired and gas-fired generating units are shut down; max, i is the maximum value of the unit's upward rotation reserve; is the upper limit of unit output; is the upward rotation reserve per unit time; P i,t is the output per unit time; Pr{.} represents the probability of occurrence of event {·}; is the actual available output of the wind turbine at that time; C u is the corresponding setting reliability.

5. The method for day-ahead economic coordination and dispatching of an integrated energy system considering multiple uncertainties according to claim 1 is characterized in that: The demand response uncertainty characteristic modeling considers the maximum error level of demand response as a two-segment linear model related to load response, self-elasticity coefficient and electricity price incentive level, as shown in the following formula: Among them, λ Δc,max is the upper limit when the electricity price change rate is greater than 0; Δc,min It is the lower limit when the electricity price change rate is less than 0; It is the inflection point of the electricity price change rate where the load response quantity is dominant and the electricity price factor is dominant, and its absolute value is negatively correlated with the degree of electricity price incentive guidance; k1 and k2 are the proportional coefficients of the demand response prediction error and the load response before and after the inflection point.

6. A device for day-ahead economic coordination and dispatching of an integrated energy system taking into account multiple uncertainties, comprising a memory, a processor, and a computer program stored in the memory and capable of running on the processor, characterized in that: When the processor executes the computer program, the method according to any one of claims 1 to 5 is implemented.

7. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 5 is implemented.