Metal component, processing system and method for manufacturing metal component
By designing coaxial holes and cutting mark chamfers in metal parts, and using an accurate machining system, the problem of low machining accuracy of chamfers is solved, achieving high-precision insertion guidance and aesthetics improvement.
Patent Information
- Application Number
- CN202080064086.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2019-09-17
- Filing Date
- 2020-09-04
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2040-09-04
AI Technical Summary
During the processing of metal parts, especially the chamfered part of the insertion through the penetration is low, which makes it difficult to insert the insertion through the hole part directly, and the fluctuation of the opening edge part causes the chamfered tool position to shift, making it difficult to achieve high precision Chamfering processing.
A metal component is designed, which has a coaxial first hole portion and a second hole portion, and a chamfered portion of cutting marks is provided on the opening edge portion. Through a special processing system and method, the cutting processing of the chamfered portion is ensured. Accuracy: The driving mechanism and control system of the opening tool and the chamfered tool are used to accurately calculate and adjust the position of the opening edge to achieve high-precision chamfering processing.
The guidance accuracy of inserting the penetration is improved, the formation of burrs and notches is avoided, the aesthetics and quality of metal parts are improved, the coaxial accuracy of the holes and the positional accuracy of the chamfered parts are ensured, and the productivity of the processing system is enhanced.
Smart Images

Figure CN114364490B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a metal component, a processing system and a method for manufacturing the metal component.
[0002] This application claims the benefit of priority based on Japanese Patent Application No. 2019-168902 filed on September 17, 2019, and all the contents described in the above-mentioned Japanese application are incorporated herein by reference. Background Art
[0003] Patent Document 1 discloses that a sintered component is subjected to a hole drilling process using a drill.
[0004] Patent Document 1: Japanese Patent Application Publication No. 2006-336078 Summary of the invention
[0005] The metal component of the present invention comprises: a first plate portion having a first surface and a first back surface; a second plate portion having a second surface and a second back surface; and a leg portion for fixing the first plate portion and the second plate portion in a manner that the first back surface and the second back surface are opposed to each other with a gap therebetween.
[0006] The first plate portion has:
[0007] a first hole portion penetrating the first surface and the first back surface;
[0008] a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface, which are opening edge portions constituting the first hole portion; and
[0009] a first chamfered portion provided at least one of the first opening edge portion on the front side and the first opening edge portion on the back side,
[0010] The second plate portion has:
[0011] a second hole portion having at least a second opening edge portion provided on the back side of the second back surface; and
[0012] a second chamfered portion on the back side, which is provided at a second opening edge portion on the back side,
[0013] The axis of the first hole portion and the axis of the second hole portion are coaxial,
[0014] The first chamfered portion of the at least one and the second chamfered portion on the back surface side have cutting marks.
[0015] The processing system involved in the present invention has:
[0016] Hole punching tools and chamfering tools, which process workpieces consisting of metal parts;
[0017] A first drive mechanism for moving the drilling tool and a second drive mechanism for moving the chamfering tool;
[0018] a control unit that controls the first driving mechanism and the second driving mechanism; and
[0019] a measuring unit that obtains a first physical quantity and a second physical quantity related to the control of the first driving mechanism,
[0020] The object to be cut has:
[0021] a first plate portion having a first surface and a first back surface;
[0022] a second plate portion having a second surface and a second back surface; and
[0023] A foot portion that fixes the first plate portion and the second plate portion in a manner that the first back surface and the second back surface are spaced apart and face each other.
[0024] The first driving mechanism operates the drilling tool so as to coaxially process a first hole portion penetrating the first surface and the first back surface and a second hole portion provided in the second plate portion in sequence.
[0025] The first hole portion is a hole portion having a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface.
[0026] The second hole portion is a hole portion having at least a second opening edge portion provided on the back side of the second back surface,
[0027] The second driving mechanism operates the chamfering tool in such a manner that a first chamfered portion is provided at the first opening edge of at least one of the first opening edge on the front side and the first opening edge on the back side, and a second chamfered portion on the back side is provided at the second opening edge on the back side.
[0028] The control unit obtains the position of the first opening edge of the at least one and the position of the second opening edge of the back side based on the first physical quantity and the second physical quantity,
[0029] The second drive mechanism is controlled based on the position of the at least one first opening edge portion and the position of the second opening edge portion on the rear side.
[0030] The method for manufacturing a metal component according to the present invention comprises the following steps:
[0031] preparing a workpiece composed of a metal component;
[0032] Performing a hole drilling process on the workpiece using a drilling tool actuated by a first driving mechanism; and
[0033] The workpiece is chamfered by cutting using a chamfering tool actuated by a second drive mechanism,
[0034] The object to be cut has:
[0035] a first plate portion having a first surface and a first back surface;
[0036] a second plate portion having a second surface and a second back surface; and
[0037] a foot portion that fixes the first plate portion and the second plate portion in a manner that the first back surface and the second back surface face each other with a gap therebetween,
[0038] The step of performing the hole forming process includes the step of coaxially forming a first hole portion penetrating the first surface and the first back surface and a second hole portion provided in the second plate portion in sequence,
[0039] The first hole portion is a hole portion having a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface,
[0040] The second hole portion is a hole portion having at least a second opening edge portion provided on the back side of the second back surface,
[0041] The method for manufacturing the metal component further comprises the following steps:
[0042] Acquiring, by a measuring unit, a first physical quantity and a second physical quantity related to control of the first driving mechanism; and
[0043] Based on the first physical quantity and the second physical quantity, the position of at least one of the first opening edge on the front side and the first opening edge on the back side and the position of the second opening edge on the back side are obtained,
[0044] The chamfering process is based on the position of the first opening edge of the at least one and the position of the second opening edge on the back side, and a first chamfered portion is provided on the first opening edge of the at least one and a second chamfered portion on the back side is provided on the second opening edge on the back side. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 This is a perspective view showing the metal component involved in the first embodiment.
[0046] Figure 2 It means along Figure 1A schematic cross-sectional view of a metal component cut along the cutting line (II) - (II).
[0047] Figure 3 It means along Figure 1 Another schematic cross-sectional view of the metal component cut along the cutting line (II) - (II).
[0048] Figure 4 This is a diagram showing a photograph of a chamfered portion of a metal component according to the first embodiment.
[0049] Figure 5A It is an explanatory diagram showing a drilling process in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0050] Figure 5B This is an explanatory diagram showing a hole drilling process performed on a first plate portion in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0051] Figure 5C This is an explanatory diagram showing the hole drilling process performed on the second plate portion in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0052] Fig. 6A It is an explanatory diagram showing chamfering processing in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0053] Figure 6B It is an explanatory diagram showing the chamfering process performed on the first hole portion in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0054] Figure 6C It is an explanatory diagram showing the chamfering process performed on the first hole portion in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0055] Fig.6D It is an explanatory diagram showing the chamfering process performed on the second hole portion in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0056] Fig. 6E It is an explanatory diagram showing the chamfering process performed on the second hole portion in the processing system and the method for manufacturing a metal component according to the first embodiment.
[0057] Figure 7 This is a graph showing the transition of the load current of the power source for rotating the boring tool obtained by the measuring unit included in the machining system according to the first embodiment.
[0058] Figure 8 This is a flowchart showing the control procedure of the processing system involved in the second embodiment.
[0059] Fig. 9 This is a graph showing the transition of the load current of the power source for rotating the boring tool obtained by the measuring unit included in the machining system according to the second embodiment. DETAILED DESCRIPTION
[0060] [Problems to be Solved by the Invention]
[0061] When an insert through object is inserted into a hole formed in a workpiece by drilling, a chamfer is sometimes provided at the opening edge of the hole. The chamfer is used to guide the insert through object. Examples of the insert through object include cutting tools and shafts. It is desirable that the processing accuracy of the chamfer is high. If the processing accuracy of the chamfer is low, it is difficult to properly guide the insert through object. Therefore, the insert through object is inclined relative to the hole and is difficult to be inserted straight through. From the viewpoint of improving the processing accuracy of the chamfer, it is desirable that the chamfer is processed by cutting rather than grinding.
[0062] However, depending on the shape of the workpiece, it is sometimes difficult to perform cutting processing on the edge of the opening. One of the reasons for this is that there is not enough space to configure a chamfering tool for cutting processing. In addition, as another reason, even if there is space to configure a chamfering tool, the position of the edge of the opening may fluctuate due to the dimensional tolerance of the workpiece. If the position of the edge of the opening fluctuates, the position of the chamfering tool is offset relative to the edge of the opening. Therefore, it is impossible to perform proper chamfering processing on the edge of the opening, and the processing accuracy of the chamfered portion is reduced.
[0063] One object of the present invention is to provide a metal component in which a first hole portion and a second hole portion which are coaxially arranged with a space between them each have chamfered portions formed by cutting at least at opening edges on mutually opposing sides.
[0064] In addition, one of the other objects of the present invention is to provide a processing system and a method for manufacturing a metal part that can manufacture a first hole portion and a second hole portion that are arranged at a distance from each other and have a common axis, and each of the metal parts has a chamfered portion formed by cutting at least on the opening edge portions on the opposite sides of each other.
[0065] [Effects of the Invention]
[0066] The portion of the metal component involved in the present invention where the first plate portion and the second plate portion face each other can be said to be a portion that is difficult to process due to the large restriction on tool operation. Even if the metal component involved in the present invention has a shape with a portion that is difficult to process, it can be a component that has the coaxial accuracy of the axis of the first hole portion and the axis of the second hole portion, the position accuracy of the first hole portion and the first chamfered portion, and the position accuracy of the second hole portion and the second chamfered portion.
[0067] The processing system and the manufacturing method of the metal component involved in the present invention can manufacture a metal component in which a first hole portion and a second hole portion that are separated from each other and have a common axis have chamfered portions formed by cutting at least on the opening edges on the opposite sides.
[0068] <Description of Embodiments of the Invention>
[0069] The present inventors have conducted research to obtain a metal component having coaxial accuracy between the shaft of the first hole portion and the shaft of the second hole portion, positional accuracy between the first hole portion and the first chamfered portion, and positional accuracy between the second hole portion and the second chamfered portion.
[0070] As a raw material for processing the above-mentioned metal parts, it is conceivable that the first plate portion, the second plate portion and the leg portion are integrated. The integrated raw material includes a raw material in which the first plate portion, the second plate portion and the leg portion are joined. In this case, the first hole portion and the second hole portion are continuously processed in the first plate portion and the second plate portion respectively using a hole-making tool, thereby being able to process two holes with high coaxial accuracy. However, it is difficult to chamfer the relative parts of the two plate portions by cutting. For example, even if a tool is introduced between the two plate portions and the leg portion to chamfer the relative opening edges of the first hole portion and the second hole portion, it is actually impossible to perform appropriate processing. The reason is that in order to process without interfering with the leg portion, the tool operation is too restricted. On the other hand, it is conceivable that a tool is introduced between the first plate portion and the second plate portion through the first hole portion, and the first chamfered portion and the second chamfered portion are processed on the relative opening edges of the first hole portion and the second hole portion. In this case, the position accuracy of each chamfered portion in the axial direction of each of the above-mentioned hole portions may be insufficient. The reason is that there is a tolerance in the thickness of each plate portion and the interval between the two plate portions.
[0071] Next, as the raw material for processing the above-mentioned metal parts, it is assumed that the first plate portion, the second plate portion and the leg portion are separated. In this case, each hole portion and each chamfered portion can be processed with high positional accuracy. The reason is that there are few restrictions on the operation of the tool, and each hole portion and each chamfered portion can be processed separately on each plate portion. However, when the first plate portion, the second plate portion and the leg portion are combined, it is difficult to fully ensure the coaxial accuracy of the two hole portions. The reason is that it is difficult for multiple components to be joined to each other with high positional accuracy.
[0072] Based on the above research, the inventors have completed the present invention. Below, embodiments of the present invention are listed for description. In the following description, the first surface and the first back surface of the first plate portion and the second surface and the second back surface of the second plate portion have the following meanings. The first surface and the second surface are the surfaces of the first plate portion and the second plate portion that are located away from each other. The first back surface and the second back surface are the surfaces of the first plate portion and the second plate portion that are located close to each other, and are surfaces that are spaced apart and opposite to each other.
[0073] (1) A metal component according to one embodiment of the present invention comprises: a first plate portion having a first surface and a first back surface; a second plate portion having a second surface and a second back surface; and a leg portion for fixing the first plate portion and the second plate portion so that the first back surface and the second back surface are opposed to each other with a gap therebetween.
[0074] The first plate portion has:
[0075] a first hole portion penetrating the first surface and the first back surface;
[0076] a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface, which are opening edge portions constituting the first hole portion; and
[0077] a first chamfered portion provided at least one of the first opening edge portion on the front side and the first opening edge portion on the back side,
[0078] The second plate portion has:
[0079] a second hole portion having at least a second opening edge portion provided on the back side of the second back surface; and
[0080] a second chamfered portion on the back side, which is provided at a second opening edge portion on the back side,
[0081] The axis of the first hole portion and the axis of the second hole portion are coaxial,
[0082] The first chamfered portion of the at least one and the second chamfered portion on the back surface side have cutting marks.
[0083] Although the above-mentioned metal component has a shape with parts that are difficult to process, it can also be formed into a component that has the coaxial accuracy of the axis of the first hole portion and the axis of the second hole portion, the positional accuracy of the first hole portion and the first chamfered portion, and the positional accuracy of the second hole portion and the second chamfered portion.
[0084] The first chamfered portion on the surface side and the second chamfered portion on the back side have cutting marks, so that when the inserted through-object is inserted through the first hole portion and the second hole portion in the order of the first hole portion and the second hole portion from the first surface side of the first plate portion, the inserted through-object can be properly guided to the first hole portion and the second hole portion. The cutting marks are provided by cutting. Generally, the processing accuracy of the chamfered portion formed by cutting is higher than that of the chamfered portion formed by grinding. Therefore, the chamfered portion with high processing accuracy does not tilt the inserted through-object relative to the first hole portion and the second hole portion, and is easy to insert straight through.
[0085] The first chamfered portion on the back side can suppress the reduction of the aesthetics of the metal component. When the first hole portion is formed by drilling from the first surface of the first plate portion toward the first back side, burrs and notches are sometimes formed at the outlet of the drilling tool, that is, the first opening edge on the back side. The burrs and notches reduce the aesthetics of the metal component. However, the first opening edge on the back side of the metal component is provided with a first chamfered portion on the back side, thereby removing the burrs and notches, so that the aesthetics are good. The burrs and notches are removed, so that the product quality of the metal component is high. In addition, the burrs may become obstacles to the insertion of the through-object, so by removing the burrs, it is easy to insert the through-object into the first hole portion, and it can be suppressed that the inserted through-object is biased to one side in the first hole portion due to the burrs. In addition, the second chamfered portion on the back side has cutting marks, thereby suppressing the reduction of the aesthetics of the metal component.
[0086] (2) As one embodiment of the above-mentioned metal member, there can be mentioned:
[0087] The second hole portion is a through hole penetrating the second surface and the second back surface,
[0088] The first plate portion has:
[0089] a first chamfered portion on the surface side, which is provided at a first opening edge portion on the surface side; and
[0090] a first chamfered portion on the back side, which is provided at the first opening edge portion on the back side,
[0091] The second plate portion has:
[0092] a second opening edge portion on the surface side, which is provided on the second surface; and
[0093] a second chamfered portion on the surface side, which is provided at a second opening edge portion on the surface side,
[0094] The first chamfered portion on the front side, the first chamfered portion on the back side, and the second chamfered portion on the back side have cutting marks.
[0095] When the metal component is inserted through the second hole and the first hole in the order from the second surface side of the second plate portion, the metal component is not inclined relative to the first hole and the second hole and can be inserted straightly and easily. In addition, although the second hole of the metal component is a through hole, the second chamfered portion on the surface side is provided at the second opening edge on the surface side, so that the aesthetics are good.
[0096] (3) A processing system according to one embodiment of the present invention includes:
[0097] Hole punching tools and chamfering tools, which process workpieces consisting of metal parts;
[0098] A first drive mechanism for moving the drilling tool and a second drive mechanism for moving the chamfering tool;
[0099] a control unit that controls the first driving mechanism and the second driving mechanism; and
[0100] a measuring unit that obtains a first physical quantity and a second physical quantity related to the control of the first driving mechanism,
[0101] The object to be cut has:
[0102] a first plate portion having a first surface and a first back surface;
[0103] a second plate portion having a second surface and a second back surface; and
[0104] a foot portion that fixes the first plate portion and the second plate portion in a manner that the first back surface and the second back surface face each other with a gap therebetween,
[0105] The first driving mechanism operates the drilling tool so as to coaxially process a first hole portion penetrating the first surface and the first back surface and a second hole portion provided in the second plate portion in sequence.
[0106] The first hole portion is a hole portion having a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface.
[0107] The second hole portion is a hole portion having at least a second opening edge portion provided on the back side of the second back surface,
[0108] The second driving mechanism operates the chamfering tool in such a manner that a first chamfering portion is provided at a first opening edge portion of at least one of a first opening edge portion on the front side and a first opening edge portion on the back side, and a second chamfering portion on the back side is provided at a second opening edge portion on the back side,
[0109] The control unit obtains the position of the first opening edge of the at least one and the position of the second opening edge of the back side based on the first physical quantity and the second physical quantity,
[0110] The second drive mechanism is controlled based on the position of the at least one first opening edge portion and the position of the second opening edge portion on the rear side.
[0111] The above processing system can manufacture a metal component that has a shape with a difficult-to-process portion but has coaxial accuracy of the axis of the first hole portion and the axis of the second hole portion, positional accuracy of the first hole portion and the first chamfered portion, and positional accuracy of the second hole portion and the second chamfered portion. The reason is as follows.
[0112] The processing system performs coaxial drilling processing on the first and second plates fixed by the legs to drill the first and second holes coaxially. Therefore, the processing system can improve the coaxial accuracy of the axis of the first and second holes.
[0113] Even if the position of the opening edge fluctuates due to the dimensional tolerance of the workpiece, the processing system can accurately obtain the position of the first opening edge and the second opening edge of the at least one of the above-mentioned objects through the control unit. Moreover, the processing system can control the second drive mechanism for each workpiece so that the chamfering tool can appropriately chamfer the first opening edge and the second opening edge of the at least one of the above-mentioned objects based on the position of the first opening edge and the second opening edge of the at least one of the above-mentioned objects obtained by the control unit. Therefore, the processing system can improve the position accuracy of the first hole portion and the first chamfered portion and the position accuracy of the second hole portion and the second chamfered portion.
[0114] (4) As one embodiment of the above-mentioned processing system, the following can be mentioned:
[0115] The first physical quantity is the feed speed of the drilling tool,
[0116] The second physical quantity is a first time from the start of the hole-forming process of the first plate portion to the start of the hole-forming process of the second plate portion.
[0117] The position of the first opening edge of the at least one and the position of the second opening edge of the back side are obtained based on the length of the first hole along the axial direction and the length between the first plate portion and the second plate portion.
[0118] The length of the first hole portion in the axial direction and the length between the first plate portion and the second plate portion are obtained based on the feed speed and the first time.
[0119] The processing system can accurately grasp the position of the first opening edge portion of the at least one and the position of the second opening edge portion on the back side.
[0120] (5) As one embodiment of the above-mentioned processing system, the following can be mentioned:
[0121] The chamfering tool has a columnar body, the outer diameter of which is smaller than the outer diameter of the hole opening tool.
[0122] The front end portion of the main body has a cutting blade whose tip tapers toward the front end side.
[0123] The rear end portion of the main body has a cutting blade whose tip tapers toward the rear end side.
[0124] The processing system can chamfer the first opening edge on the back side by the cutting blade of the rear end. In addition, the processing system can chamfer the first opening edge on the front side and the second opening edge on the back side by the cutting blade of the front end. That is, the processing system can continuously chamfer the first opening edge of at least one of the first opening edge on the front side and the first opening edge on the back side and the second opening edge on the back side by one chamfering tool, thereby achieving excellent productivity of the metal parts.
[0125] (6) As one embodiment of the above-mentioned processing system, the following can be mentioned:
[0126] The first driving mechanism has a power source for self-rotation for rotating the drilling tool.
[0127] The measuring unit obtains the electric quantity of the power source for the rotation,
[0128] The control unit changes the rotation speed of the power source for autorotation based on the difference between the first electric quantity and the second electric quantity,
[0129] The first electric quantity is an electric quantity obtained by the measuring unit during the rotation of the power source for rotation and before the workpiece is processed.
[0130] The second electrical quantity is an electrical quantity acquired by the measuring unit during the hole drilling process of the workpiece.
[0131] The state in which the power source for self-rotation is rotating and before the workpiece is processed refers to a state in which the drilling tool and the workpiece are not in contact with each other while the drilling tool is rotated by the power source for self-rotation under the same cutting conditions as when the workpiece is actually processed. Whether the workpiece is held on the worktable of the processing system or not is not considered. Hereinafter, the state in which the power source for self-rotation is rotating and before the workpiece is processed is sometimes referred to as the state in which the power source for self-rotation is idling.
[0132] The processing system can suppress the production of defective products that are not subjected to the prescribed drilling process by the drilling tool. The reason is that, according to the processing system, the defect of the drilling tool can be detected by comparing the threshold value and the difference as described later, and the rotation speed of the power source for self-rotation can be changed by the control unit when the drilling tool is defective. The defect includes not only the case where the cutting edge of the drilling tool is notched, but also the case where the drilling tool is broken.
[0133] The reason why the defect of the drilling tool can be detected by comparing the above-mentioned threshold value and the above-mentioned difference is as follows. If a defect occurs in the drilling tool, the area of the drilling tool that becomes non-contact with the cutting object increases. If the area of the drilling tool that becomes non-contact becomes too much, the drilling process itself becomes difficult. The state in which the drilling process is difficult can be regarded as a state in which the cutting object and the drilling tool are essentially idling relatively. That is, the first electric quantity approaches the second electric quantity, and the above-mentioned difference becomes smaller. Sometimes the second electric quantity becomes the same as the first electric quantity, and the above-mentioned difference essentially disappears. As a result, the above-mentioned difference changes from exceeding the threshold value to being below the threshold value. Therefore, by calculating the above-mentioned difference, it is possible to grasp whether the above-mentioned difference satisfies the threshold value or not, and it is possible to grasp whether a defect occurs in the drilling tool. The threshold value will be described later.
[0134] (7) As one embodiment of the processing system of (6) above, there can be mentioned:
[0135] The first electric quantity and the second electric quantity are at least one of a magnitude, a differential value, and an integral value of a load current of the power source for the autorotation.
[0136] The machining system can easily detect the defect of the drilling tool because at least one of the load current magnitude, differential value, and integral value of the power source for rotation is correlated with the defect of the drilling tool.
[0137] If a hole punching tool is damaged, the hole punching process itself becomes difficult, so the machining resistance during the machining of the workpiece becomes smaller. If the machining resistance is small, the load torque of the power source for self-rotation becomes smaller, so the load current of the power source for self-rotation becomes smaller. That is, if a hole punching tool is damaged, the load current of the power source for self-rotation during the machining of the workpiece becomes smaller.
[0138] Specifically, when the hole punching tool is defective and the hole punching tool is not in contact with the workpiece, the processing depth is zero (0). The processing depth is zero, so that the magnitude, differential value and integral value of the load current of the power source for self-rotation during the processing of the workpiece become substantially the same as the magnitude, differential value and integral value of the load current of the power source for self-rotation during idling. On the other hand, although the hole punching tool is defective but the hole punching tool is in contact with the workpiece, the processing depth becomes smaller. The processing depth is small, so that the magnitude, differential value and integral value of the load current of the power source for self-rotation during the processing of the workpiece are not as small as when the hole punching tool is not in contact with the workpiece, but are relatively smaller. That is, the magnitude, differential value and integral value of the load current of the power source for self-rotation during the processing of the workpiece are close to the magnitude, differential value and integral value of the load current of the power source for self-rotation during idling. Thus, at least one of the magnitude, differential value, and integral value of the load current of the power source for rotation can be used to understand whether the boring tool has processed the workpiece, that is, whether a defect has occurred in the boring tool.
[0139] (8) As one embodiment of the processing system of (6) or (7), the following can be mentioned:
[0140] The control unit sets the rotation speed of the power source for autorotation to zero when the rotation speed is equal to or less than the difference threshold.
[0141] The machining system can prevent the continuous production of defective products. This is because, when the difference is below the threshold, that is, when the drilling tool is defective, the rotation speed of the power source for self-rotation can be set to zero by the control unit. If the rotation speed of the power source for self-rotation becomes zero, the rotation of the drilling tool or the workpiece stops.
[0142] (9) A method for manufacturing a metal component according to one embodiment of the present invention includes the following steps:
[0143] preparing a workpiece composed of a metal component;
[0144] Performing a hole drilling process on the workpiece using a drilling tool actuated by a first driving mechanism; and
[0145] The workpiece is chamfered by cutting using a chamfering tool actuated by a second drive mechanism,
[0146] The object to be cut has:
[0147] a first plate portion having a first surface and a first back surface;
[0148] a second plate portion having a second surface and a second back surface; and
[0149] a foot portion that fixes the first plate portion and the second plate portion in a manner that the first back surface and the second back surface face each other with a gap therebetween,
[0150] The step of performing the hole forming process includes the step of coaxially forming a first hole portion penetrating the first surface and the first back surface and a second hole portion provided in the second plate portion in sequence,
[0151] The first hole portion is a hole portion having a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface,
[0152] The second hole portion is a hole portion having at least a second opening edge portion provided on the back side of the second back surface,
[0153] The method for manufacturing the metal component further comprises the following steps:
[0154] Acquiring, by a measuring unit, a first physical quantity and a second physical quantity related to control of the first driving mechanism; and
[0155] Based on the first physical quantity and the second physical quantity, the position of at least one of the first opening edge on the front side and the first opening edge on the back side and the position of the second opening edge on the back side are obtained,
[0156] The chamfering process is based on the position of the first opening edge of the at least one and the position of the second opening edge on the back side, and a first chamfered portion is provided on the first opening edge of the at least one and a second chamfered portion on the back side is provided on the second opening edge on the back side.
[0157] The manufacturing method of the above-mentioned metal part can manufacture the following metal part in the same way as the above-mentioned processing system. Although the metal part has a shape with a part that is difficult to process, it has the coaxial accuracy of the axis of the first hole portion and the axis of the second hole portion, the positional accuracy of the first hole portion and the first chamfered portion, and the positional accuracy of the second hole portion and the second chamfered portion.
[0158] (10) One embodiment of the method for manufacturing the metal component includes:
[0159] In the step of providing the chamfered portion, the second drive mechanism is operated so that the chamfered length of the chamfered portion is smaller than the dimensional tolerance of the length between the first plate portion and the second plate portion.
[0160] The manufacturing method of the above-mentioned metal parts is suitable for the case where the chamfer length is smaller than the dimensional tolerance. Usually, when the chamfer length is smaller than the dimensional tolerance, sometimes the chamfering tool cannot properly contact the opening edge, and the opening edge cannot be properly chamfered. However, as described above, the manufacturing method of the above-mentioned metal parts can accurately determine the position of each opening edge and move the chamfering tool corresponding to the position of each opening edge. Therefore, even when the chamfer length is smaller than the dimensional tolerance, the manufacturing method of the above-mentioned metal parts can make the chamfering tool properly contact each opening edge and perform appropriate chamfering.
[0161] <Details of the embodiments of the present invention>
[0162] Hereinafter, embodiments of the present invention will be described in detail.
[0163] Implementation Method 1
[0164] 〔Metal parts〕
[0165] Reference Figures 1 to 4 , the metal component 1 involved in the first embodiment is described. The metal component 1 has a first plate portion 11, a second plate portion 12, and a leg portion 13. The first plate portion 11 has a first surface 111 and a first back surface 112. The second plate portion 12 has a second surface 121 and a second back surface 122. The leg portion 13 fixes the first plate portion 11 and the second plate portion 12 in a manner that the first back surface 112 and the second back surface 122 are spaced apart and face each other. The first plate portion 11 has: a first hole portion 113 that penetrates the first surface 111 and the first back surface 112; a first opening edge portion 114 on the surface side that is an opening edge constituting the first hole portion 113 and is provided on the first surface 111; and a first opening edge portion 115 on the back side that is provided on the first back surface 112. The second plate portion 12 has a second hole portion 123 that has at least a second opening edge portion 125 on the back side provided on the second back surface 122.
[0166] One of the characteristics of the metal component 1 according to the present embodiment is that it has the following important conditions (1) to (4).
[0167] (1) The axis of the first hole portion 113 and the axis of the second hole portion 123 are as follows: Figure 2 or Figure 3 As shown, they are coaxial.
[0168] (2) The first plate portion 11 has the first chamfered portion provided at least at one of the first opening edge portion 114 on the front side and the first opening edge portion 115 on the back side.
[0169] (3) The second plate portion 12 has the second chamfered portion 127 on the rear side provided at the second opening edge portion 125 on the rear side.
[0170] (4) The first chamfered portion of at least one of the above and the second chamfered portion 127 on the back side have Figure 4 Cutting marks 15 as shown.
[0171] Next, each structure is described in detail.
[0172] [First board]
[0173] The material and type of the first plate portion 11 are not particularly limited and can be appropriately selected. Examples of the material of the first plate portion 11 include pure iron, iron alloys, or non-ferrous metals. Examples of the type of the first plate portion 11 include pressed powder molded bodies, sintered bodies, or smelted materials. Pressed powder molded bodies are formed by pressure molding raw material powders. Sintered bodies are formed by sintering pressed powder molded bodies. Smelted materials are formed by solidifying raw material melts. In this embodiment, the first plate portion 11 is composed of a sintered body formed of an iron alloy. The outer shape of the first plate portion 11 is not particularly limited as long as it is a flat shape and can be appropriately selected. The outer shape of the first plate portion 11 is circular in this embodiment. The first surface 111 and the first back surface 112 of the first plate portion 11 are not limited to planes, and may also be provided with depressions and projections.
[0174] (First hole)
[0175] The first hole 113 is Figure 2 or Figure 3 As shown, it is a through hole that penetrates the first plate portion 11 in the thickness direction. The thickness is the length between the first surface 111 and the first back surface 112. That is, the thickness direction of the first plate portion 11 is the direction along the direction in which the first surface 111 and the first back surface 112 are opposite to each other. Figure 2 and Figure 3 , the thickness direction of the first plate portion 11 is the vertical direction of the paper. The first hole portion 113 has a first opening edge portion 114 on the surface side and a first opening edge portion 115 on the back side. The first opening edge portion 114 on the surface side is provided on the first surface 111 of the first plate portion 11. The first opening edge portion 115 on the back side is provided on the first back side 112 of the first plate portion 11.
[0176] The inner peripheral shape of the first hole portion 113 is cylindrical in the present embodiment. That is, the contour shape of the first opening edge portion 114 on the surface side and the first opening edge portion 115 on the back side is circular. The inner peripheral surface of the first hole portion 113 preferably has cutting marks. The cutting marks are formed into a plurality of stripes along the circumference of the first hole portion 113. The number of the first hole portions 113 is not particularly limited and can be appropriately selected. The number of the first hole portions 113 may be single or multiple. The number of the first hole portions 113 in the present embodiment, such as Figure 1The five first holes 113 are shown in FIG. 5 and are arranged in parallel on a circle centered on the center of the first plate 11. The center of the first plate 11 refers to the center of the circumscribed circle of the first plate 11. In this embodiment, the five first holes 113 are substantially evenly spaced on the circle.
[0177] (First chamfer)
[0178] The first plate portion 11 has a first chamfered portion, and the first chamfered portion is provided on at least one of the first opening edge portion 114 on the surface side and the first opening edge portion 115 on the back side. In this embodiment, the first chamfered portion is provided on both the first opening edge portion 114 on the surface side and the first opening edge portion 115 on the back side. Hereinafter, the first chamfered portion provided on the first opening edge portion 114 on the surface side is referred to as the first chamfered portion 116 on the surface side, and the first chamfered portion provided on the first opening edge portion 115 on the back side is referred to as the first chamfered portion 117 on the back side.
[0179] The first chamfered portion 116 on the surface side functions as a guide portion for an inserted through object inserted into the first hole portion 113. Illustration of the inserted through object is omitted. Examples of the inserted through object include cutting tools such as a reamer and accessory parts such as a shaft. Generally, the processing accuracy of a chamfered portion formed by cutting is higher than that of a chamfered portion formed by grinding. A chamfered portion with high processing accuracy can easily guide the inserted through object appropriately. That is, the first chamfered portion 116 on the surface side is formed by cutting, so the inserted through object will not be tilted relative to the first hole portion 113, and it is easy to insert the inserted through object straightly. In the case where the inserted through object is, for example, a reamer, if the reamer is inserted straight through the first hole portion 113, the inner peripheral surface of the first hole portion 113 can be finished with high accuracy by the reamer. As a result, the processing accuracy of the inner peripheral surface of the first hole portion 113 is improved. If the inner peripheral surface of the first hole 113 is processed with high accuracy, when the shaft is inserted into the first hole 113 in the axial direction, the shaft will not be inclined with respect to the first hole 113 and can be easily inserted straightly.
[0180] The first chamfered portion 117 on the back side can suppress the reduction of the aesthetics of the metal component 1. When the first hole portion 113 is formed by drilling from the first surface 111 of the first plate portion 11 toward the first back side 112, burrs and notches are sometimes formed at the outlet of the drilling tool, that is, the first opening edge portion 115 on the back side. The burrs and notches reduce the aesthetics of the metal component 1. However, the metal component 1 of this embodiment is provided with a first chamfered portion 117 on the back side at the first opening edge portion 115 on the back side, thereby removing the burrs and notches, so that the aesthetics are good. By removing the burrs and notches, the product quality of the metal component 1 is high. In addition, the burrs may become obstacles to the insertion of the through-object, so by removing the burrs, the insertion of the through-object is easy to be inserted into the first hole portion 113, and it can be suppressed that the burrs are biased to one side in the first hole portion 113. The second hole portion 123 described later is a through hole. When the above-mentioned insertion object is inserted through the second surface 121 side of the second plate portion 12 in the order of the second hole portion 123 and the first hole portion 113, the first chamfered portion 117 on the back side can easily guide the insertion object appropriately.
[0181] The first chamfered portion 116 on the front side and the first chamfered portion 117 on the back side are formed over the entire circumference of each first opening edge. Figure 4 The cutting marks 15 are formed as shown. The cutting marks 15 are formed in a plurality of stripes along the circumferential direction of each first chamfered portion. The cutting marks 15 are formed by cutting. As the form of the first chamfered portion 116 on the front side and the first chamfered portion 117 on the back side, flat chamfering and R chamfering can be cited. The first chamfered portion 116 on the front side and the first chamfered portion 117 on the back side of this embodiment are flat chamfers.
[0182] [Second board]
[0183] The material and type of the second plate portion 12 can be the same as the material and type of the first plate portion 11 mentioned above. The material and type of the second plate portion 12 are preferably the same as the material and type of the first plate portion 11. In this embodiment, the second plate portion 12 is composed of a sintered body, and the sintered body is formed of an iron alloy, similarly to the first plate portion 11. The outer shape of the second plate portion 12 is not particularly limited as long as it is a flat shape, and can be appropriately selected. The outer shape of the second plate portion 12 of this embodiment is circular. The second surface 121 and the second back surface 122 of the second plate portion 12 are not limited to a plane, similarly to the first plate portion 11, and can be provided with projections and depressions.
[0184] (Second hole portion)
[0185] The axis of the second hole portion 123 is as Figure 2 or Figure 3As shown, the axis of the first hole portion 113 is coaxial. That is, the second hole portion 123 is formed at a position of the second plate portion 12 facing the first hole portion 113. The number of the second hole portions 123 is the same as the number of the first hole portions 113. In this embodiment, as shown in FIG. Figure 1 The number shown is 5. In this embodiment, the five second hole portions 123 are substantially evenly spaced on a circumference centered on the center of the second plate portion 12 .
[0186] The types of the second hole 123 include: Figure 2 The through hole shown or Figure 3 The through hole penetrates the second plate portion 12 in the thickness direction. The thickness is the length between the second surface 121 and the second back surface 122. That is, the thickness direction of the second plate portion 12 is the direction along the direction in which the second surface 121 and the second back surface 122 are opposite to each other. Figure 2 and Figure 3 In the figure, the thickness direction of the second plate portion 12 is the vertical direction of the paper. The through hole has a second opening edge portion 124 on the surface side provided on the second surface 121 of the second plate portion 12 and a second opening edge portion 125 on the back side provided on the second back side 122. On the other hand, the blind hole is a bottomed hole that does not have the second opening edge portion 124 on the surface side but has the second opening edge portion 125 on the back side. The type of the second hole portion 123 of this embodiment is Figure 2 The through hole shown.
[0187] In this embodiment, the inner peripheral shape of the second hole portion 123 is a cylindrical shape that is the same as the inner peripheral shape of the first hole portion 113. That is, the contour shape of the second opening edge portion 124 on the front side and the second opening edge portion 125 on the back side is a circular shape. The inner diameter of the second hole portion 123 is the same diameter as the inner diameter of the first hole portion 113. The inner peripheral surface of the second hole portion 123 preferably has cutting marks. The cutting marks are formed in a plurality of stripes along the circumferential direction of the second hole portion 123.
[0188] (Second chamfer)
[0189] The second plate portion 12 has at least a second chamfered portion 127 on the back side provided at the second opening edge portion 125 on the back side. The second plate portion 12 also has a second chamfered portion 126 on the front side provided at the second opening edge portion 124 on the front side in this embodiment. The second chamfered portion 126 on the front side and the second chamfered portion 127 on the back side are formed over the entire circumference of each second opening edge portion. Each second chamfered portion has the same Figure 4The cutting marks are the same as the cutting marks 15 described above. The cutting marks of the second chamfered portion are formed into a plurality of stripes along the circumferential direction of each second chamfered portion. The cutting marks of the second chamfered portion are formed by cutting. The second chamfered portion is a flat chamfer. The second chamfered portion 127 on the back side is formed by cutting, so the inserted through object passing through the first hole portion 113 will not be tilted relative to the second hole portion 123 and can be easily inserted straight through. The second chamfered portion 126 on the surface side is formed by cutting, so the aesthetics are good, and when the inserted through object is inserted from the second surface 121 side of the second plate portion 12 to the second hole portion 123, the inserted through object will not be tilted relative to the second hole portion 123 and can be easily inserted straight through.
[0190] (Coaxial accuracy)
[0191] The offset between the axis of the first hole 113 and the axis of the second hole 123 is, for example, Φ0.1 mm or less. When the offset between the axes is Φ0.1 mm, the axis of the first hole 113 and the axis of the second hole 123 are assumed to be coaxial. The offset between the axes is further preferably Φ0.05 mm or less, particularly preferably Φ0.03 mm or less, and most preferably zero (0).
[0192] The offset between the axes is calculated as follows. Take an imaginary plane orthogonal to the axis of the first hole portion 113. On the imaginary plane, take a first intersection with the axis of the first hole portion 113 and a second intersection with the axis of the second hole portion 123. The axis of the first hole portion 113 is set to the center of the inscribed circle of the first hole portion 113. The axis of the second hole portion 123 is set to the center of the inscribed circle of the second hole portion 123. Calculate the shortest length between the first intersection and the second intersection. Set the shortest length as the offset between the axes.
[0193] (Position accuracy)
[0194] Preferably, the offset of the chamfer width of the first chamfered portion 116 on the front side and the first chamfered portion 117 on the back side is less than 0.05 mm on one side, and the offset of the chamfer length is less than 0.05 mm on one side. The offset of the chamfer width is more preferably less than 0.025 mm on one side, and particularly preferably less than 0.015 mm on one side. The offset of the chamfer length is more preferably less than 0.025 mm on one side, and particularly preferably less than 0.015 mm on one side.
[0195] Preferably, the offset of the chamfer width of the second chamfered portion 126 on the front side and the second chamfered portion 127 on the back side is less than 0.05 mm on one side, and the offset of the chamfer length is less than 0.05 mm on one side. The offset of the chamfer width is more preferably less than 0.025 mm on one side, and particularly preferably less than 0.015 mm on one side. The offset of the chamfer length is more preferably less than 0.025 mm on one side, and particularly preferably less than 0.015 mm on one side.
[0196] Preferably, the offset of the chamfer width of the first chamfered portion 116 on the surface side and the second chamfered portion 126 on the surface side is less than 0.1 mm on one side, and the offset of the chamfer length is less than 0.1 mm on one side. The offset of the chamfer width is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side. The offset of the chamfer length is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side.
[0197] Preferably, the offset of the chamfer width of the first chamfered portion 117 on the back side and the second chamfered portion 127 on the back side is less than 0.1 mm on one side, and the offset of the chamfer length is less than 0.1 mm on one side. The offset of the chamfer width is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side. The offset of the chamfer length is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side.
[0198] Preferably, the offset of the chamfer width of the first chamfered portion 116 on the front side and the second chamfered portion 127 on the back side is less than 0.1 mm on one side, and the offset of the chamfer length is less than 0.1 mm on one side. The offset of the chamfer width is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side. The offset of the chamfer length is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side.
[0199] Preferably, the offset of the chamfer width of the first chamfered portion 117 on the back side and the second chamfered portion 126 on the front side is less than 0.1 mm on one side, and the offset of the chamfer length is less than 0.1 mm on one side. The offset of the chamfer width is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side. The offset of the chamfer length is more preferably less than 0.05 mm on one side, and particularly preferably less than 0.03 mm on one side.
[0200] When the chamfered portion is a flat chamfer, in a right triangle with the chamfered portion as the hypotenuse, the length of the side in the direction perpendicular to the axial direction of the first hole portion 113 or the second hole portion 123 among the two sides other than the hypotenuse is set as the chamfer width, and the length of the side in the axial direction of the first hole portion 113 or the second hole portion 123 is set as the chamfer length. When the chamfered portion is an R chamfer, in a right triangle with the hypotenuse as the right triangle, the length of the side in the direction perpendicular to the axial direction of the first hole portion 113 and the second hole portion 123 among the two sides other than the hypotenuse is set as the chamfer width, and the length of the side in the axial direction of the first hole portion 113 or the second hole portion 123 is set as the chamfer length.
[0201] [Feet]
[0202] Foot 13 Figure 1 As shown, the first plate portion 11 and the second plate portion 12 are fixed. In this embodiment, the leg portion 13 connects the first back side 112 and the second back side 122. The material and type of the leg portion 13 can be the same as the material and type of the first plate portion 11 and the second plate portion 12 mentioned above. The material and type of the leg portion 13 are preferably the same as the material and type of the first plate portion 11 and the second plate portion 12. The reason is that it is easy to improve the connection strength of the first plate portion 11 and the second plate portion 12. The leg portion 13 of this embodiment is formed in series with the first back side 112 of the first plate portion 11. The front end of the leg portion 13 is connected to the second back side 122 of the second plate portion 12. This connection can be made by an appropriate method such as brazing. The number of the leg portions 13 is not particularly limited and can be appropriately selected. The number of the leg portions 13 can be single or multiple. The number of the leg portions 13 in this embodiment is 5. The 5 leg portions 13 are arranged in parallel on the circumference of the circle centered on the center of the first plate portion 11. In this embodiment, the five legs 13 are substantially evenly spaced on the circumference. Each leg 13 is disposed between the first holes 113 adjacent to each other in the circumferential direction. The shape of each leg 13 is not particularly limited and can be appropriately selected. In this embodiment, the shape of each leg 13 is a trapezoidal column.
[0203] [use]
[0204] The metal member 1 according to the present embodiment can be appropriately used for various general structural members. Examples of general structural members include mechanical members such as planetary carriers.
[0205] 〔Effect〕
[0206] Although the metal component 1 involved in this embodiment has a shape with a difficult-to-process part, it can also be formed into a component that has the coaxial accuracy of the axis of the first hole portion 113 and the axis of the second hole portion 123, the positional accuracy of the first chamfered portion 116 on the surface side and the first chamfered portion 117 on the back side and the first hole portion 113, and the positional accuracy of the second chamfered portion 126 on the surface side and the second chamfered portion 127 on the back side and the second hole portion 123. Therefore, for the metal component 1 involved in this embodiment, the inserted through object will not be tilted relative to the first hole portion 113 and the second hole portion 123, and it is easy to insert and penetrate straight. In addition, the aesthetics of the metal component 1 involved in this embodiment are good. Therefore, the product quality of the metal component 1 involved in this embodiment is high.
[0207] 〔Processing system〕
[0208] Reference FIG. 5A to FIG. 5C , FIG. 6A to FIG. 6E as well as Figure 7 , the processing system 10 involved in this embodiment is described. The processing system 10 involved in this embodiment has Figure 5A The hole cutter 21 and Fig. 6A , etc., the chamfering tool 22, the first drive mechanism 31 and the second drive mechanism 32, the measuring unit 40 and the control unit 50. The drilling tool 21 and the chamfering tool 22 process the workpiece 100. The first drive mechanism 31 operates the drilling tool 21. The second drive mechanism 32 operates the chamfering tool 22. The control unit 50 controls the first drive mechanism 31 and the second drive mechanism 32.
[0209] One of the characteristics of the processing system 10 according to the present embodiment is that it has the following (1) to (6).
[0210] (1) The boring tool 21 forms a specific hole portion in a specific workpiece 100 .
[0211] (2) The chamfering cutter 22 forms a chamfered portion at the opening edge of the hole.
[0212] (3) The first driving mechanism 31 causes the boring tool 21 to perform a predetermined operation.
[0213] (4) The second driving mechanism 32 causes the chamfering tool 22 to perform a predetermined operation.
[0214] (5) The measuring unit 40 acquires the first physical quantity and the second physical quantity related to the control of the first drive mechanism 31. The first physical quantity and the second physical quantity will be described in detail later.
[0215] (6) The control unit 50 obtains the position of the opening edge of the hole, and controls the second drive mechanism 32 based on the position of the opening edge of the hole.
[0216] The processing system 10 involved in this embodiment can produce reference Figures 1 to 4 The following description is made in the order of the outline of the workpiece 100 and the details of each structure of the processing system 10. FIG. 5A to FIG. 5C and FIG. 6A to FIG. 6E The second calculation unit 52 and the second storage unit 56 shown will be described in Embodiment 2 to be described later.
[0217] [Workpiece]
[0218] The object to be cut 100 is a processing object to be processed by the drilling tool 21 and the chamfering tool 22. The object to be cut 100 is processed by the drilling tool 21 and the chamfering tool 22. Figure 5A As shown, the workpiece 100 has a first plate portion 11, a second plate portion 12 and a leg portion 13. The workpiece 100 corresponds to the structure in which the first plate portion 11 does not have the first hole portion 113 and each first chamfered portion, and the second plate portion 12 does not have the second hole portion 123 and each second chamfered portion. The material and type of the workpiece 100 are as described above, and the same material and type as the above-mentioned metal component 1 can be used.
[0219] The workpiece 100 is held on the workbench 200 during processing. The workbench 200 may have a hole 210 that serves as a tool retraction amount for the drilling tool 21 and the chamfering tool 22. The hole 210 is formed by a through hole, but may also be a blind hole. The inner diameter of the hole 210 may be as follows: Fig. 6E As shown, the diameter is set to a degree that the chamfering cutter 22 does not interfere with the inner peripheral surface of the hole 210 when the chamfering cutter 22 processes the second opening edge 124 on the surface side of the second hole 123 .
[0220] [Drilling tool]
[0221] The hole cutting tool 21 is as follows Figure 5B As shown, a first hole portion 113 is formed in the first plate portion 11. Figure 5C As shown, the second hole portion 123 is formed in the second plate portion 12. The first hole portion 113 and the second hole portion 123 in this embodiment are as shown in FIG. Figure 2 The first hole 113 and the second hole 123 of the metal member 1 described above are the same. As the boring tool 21, for example, a drill can be cited.
[0222] [Chamfering tool]
[0223] The chamfering tool 22 forms a chamfering tool on the first plate portion 11. Figure 6B The first chamfered portion 116 on the surface side provided at the first opening edge portion 114 on the surface side and Figure 6CThe chamfering tool 22 is provided on the second plate portion 12, such as Fig.6D As shown, at least the second opening edge 125 on the back side forms the second chamfered portion 127 on the back side. The chamfering tool 22 can form both the first chamfered portion 116 and the first chamfered portion 117 on the back side on the first plate portion 11. The chamfering tool 22 can further be as shown. Fig. 6E As shown in the figure, the second opening edge portion 124 on the surface side of the second plate portion 12 forms a second chamfered portion 126 on the surface side. The formation of each first chamfered portion and each second chamfered portion is performed by cutting. Each first chamfered portion and each second chamfered portion is as shown in FIG. Figure 2 or Figure 3 The first chamfered portions and the second chamfered portions of the metal member 1 described above are similar. As the chamfering tool 22, for example, a chamfering milling cutter can be used.
[0224] In this embodiment, the chamfering tool 22 is Fig. 6A As shown, the main body 23 has an outer diameter smaller than the outer diameter of the drilling tool 21. That is, the outer diameter of the main body 23 is smaller than the inner diameter of the first hole portion 113 and the second hole portion 123. The front end portion of the main body 23 has a cutting blade 24 whose tip becomes thinner toward the front end side. In addition, the rear end portion of the main body 23 has a cutting blade 24 whose tip becomes thinner toward the rear end side. In the following, the cutting blade 24 at the front end portion of the main body 23 is sometimes referred to as the cutting blade 24 on the front end side, and the cutting blade 24 at the rear end portion of the main body 23 is sometimes referred to as the cutting blade 24 on the rear end side. Each cutting blade 24 has the same Figure 2 or Figure 3 The shapes of the first chamfered portion and the second chamfered portion described above correspond to each other. In the case of a chamfering tool for flat chamfering, a straight cutting edge or a spiral cutting edge inclined relative to the axis of the main body 23 can be cited, and in the case of a chamfering tool for R chamfering, an arc-shaped cutting edge can be cited. A plurality of cutting edges 24 are provided in the circumferential direction at the front end and the rear end of the main body 23.
[0225] The cutting edge 24 at the front end of the chamfering tool 22 can process the opening edge of the hole portion of the workpiece 100 located on the side of the chamfering tool 22 in the retreat direction. Figure 6B As shown, the first opening edge portion 114 on the surface side can be cut. Fig.6D As shown in FIG. 1 , the second opening edge 125 on the back side can be cut. The cutting edge 24 on the rear side of the chamfering tool 22 can process the opening edge of the hole portion of the workpiece 100 located on the advancing direction side of the chamfering tool 22. That is, the cutting edge 24 on the rear side is as shown in FIG. Figure 6C As shown, the first opening edge portion 115 on the back side can be cut. Fig. 6EAs shown, the second opening edge 124 on the surface side can be cut. The chamfering tool 22 can continuously chamfer the two first opening edges and the two second opening edges. Therefore, the productivity of the metal component 1 of the above-mentioned processing system 10 is excellent. If the relative interval between the first plate portion 11 and the second plate portion 12 is in a range larger than the axial length of the main body 23, the chamfering tool 22 can form the first chamfered portion 117 on the back side by cutting the first opening edge 115 on the back side, and can form the second chamfered portion 127 on the back side by cutting the second opening edge 125 on the back side.
[0226] [First driving mechanism]
[0227] The first driving mechanism 31 is as follows FIG. 5A to FIG. 5C As shown, the drilling tool 21 is operated to perform the required operation for performing the predetermined drilling process on the first plate portion 11 and the second plate portion 12 of the workpiece 100. As the predetermined drilling process, there can be cited a drilling process that is continuously performed in the order of the first plate portion 11 and the second plate portion 12 by a drilling tool 21. By this drilling process, Figure 5B As shown, a first hole portion 113 is formed in the first plate portion 11. Figure 5C As shown, a second hole portion 123 coaxial with the first hole portion 113 is formed in the second plate portion 12. As the required operation, the boring tool 21 is moved in the axial direction of the boring tool 21 and the boring tool 21 is rotated.
[0228] The first driving mechanism 31 has a power source and a transmission mechanism that transmits the power of the power source to the drilling tool 21. The power source is a component that gives the drilling tool 21 power for the actions required for processing. The power source for the rotation of the drilling tool 21 can be, for example, an electric motor. The transmission mechanism can utilize a known transmission mechanism. As the first driving mechanism 31, for example, an XYZ table, a ball screw, etc. can be utilized. The XYZ table can move the drilling tool 21 to any position on the three-dimensional coordinates. The Z direction is the lifting direction of the drilling tool 21. The XY direction is a direction orthogonal to the lifting direction of the drilling tool 21. As the first driving mechanism 31, it is sufficient to at least enable the drilling tool 21 to be lifted and lowered, but it is preferably also able to move in a direction orthogonal to the lifting direction. The first driving mechanism 31 has a power source 31a for feeding and a power source 31c for rotation. The power source 31a for feeding is a power source for the Z direction.
[0229] The first driving mechanism 31 moves the boring tool 21 in the axial direction of the boring tool 21 by means of a feeding power source 31 a so as to move forward so as to approach the workpiece 100 or to move backward so as to move away from the workpiece 100 . FIG. 5A to FIG. 5CThe arrows along the axial direction of the boring tool 21 in the drawing indicate the forward and backward directions of the boring tool 21. As the type of the power source 31a for feeding, for example, there can be cited an electric motor, a cylinder, a solenoid, etc. The first driving mechanism 31 rotates the boring tool 21 by the power source 31c for rotation. FIG. 5A to FIG. 5C The arrow along the circumferential direction of the boring tool 21 in Graph 1 indicates the rotation direction of the boring tool 21 .
[0230] [Second driving mechanism]
[0231] The second driving mechanism 32 is as follows FIG. 6A to FIG. 6E As shown, the chamfering tool 22 is operated to perform the required operation of performing a predetermined chamfering process on the opening edges of the plurality of holes of the workpiece 100 by cutting. As the predetermined chamfering process, the first plate portion 11 may be chamfered as shown in FIG. Figure 6B The chamfering process performed on the first opening edge portion 114 on the surface side and Figure 6C At least one of the chamfering processes performed on the first opening edge portion 115 on the back side is shown. In addition, as the prescribed chamfering process, the second plate portion 12 can be cited as follows: Fig.6D The chamfering process is performed on at least the second opening edge 125 on the back side. Figure 6B The first chamfered portion 116 on the surface side shown Figure 6C The first chamfered portion of at least one of the first chamfered portions 117 on the back side shown in FIG. Fig.6D The second chamfered portion 127 on the back side is shown. The necessary operation includes moving the chamfering tool 22 in the axial direction of the chamfering tool 22, rotating the chamfering tool 22, and orbiting the chamfering tool 22 along the circumference of the opening edge of the hole.
[0232] The second drive mechanism 32 has a power source and a transmission mechanism that transmits the power of the power source to the chamfering tool 22. The power source is a component that gives the chamfering tool 22 power for the actions required for processing. The power source for the rotation of the chamfering tool 22 is the same as described above, for example, an electric motor can be cited. The transmission mechanism can utilize a known transmission mechanism. As the second drive mechanism 32, for example, an XYZ worktable, a ball screw, etc. can be utilized in the same manner as the first drive mechanism 31. The Z direction is the lifting direction of the chamfering tool 22. The XY direction is a direction orthogonal to the lifting direction of the chamfering tool 22. The second drive mechanism 32 has a power source 32a for feeding, a power source 32c for rotation, and a power source 32d for revolution. The power source 32a for feeding is a power source for the Z direction. The power source 32d for revolution has a power source for the X direction and a power source for the Y direction.
[0233] The second driving mechanism 32 moves the chamfering tool 22 in the axial direction of the chamfering tool 22 by means of a feeding power source 32 a so as to advance the chamfering tool 22 so as to approach the workpiece 100 or to retreat the chamfering tool 22 so as to move away from the workpiece 100 . FIG. 6A to FIG. 6E The arrows along the axial direction of the chamfering tool 22 in 0 indicate the advancing direction and the retreating direction of the chamfering tool 22. The types of the power source 32a for feeding are similar to the types of the power source 31a for feeding, and examples thereof include electric motors, cylinders, solenoids, and the like.
[0234] The second drive mechanism 32 rotates the chamfering tool 22 by the power source 32c for rotation. The second drive mechanism 32 orbits the chamfering tool 22 by the power source 32d for revolution. The cutting edge 24 of the chamfering tool 22 is brought into contact with or away from the opening edge by the power source 32d for revolution. FIG. 6A to FIG. 6E The arrow along the circumferential direction of the chamfering tool 22 in the figure indicates the rotation direction of the chamfering tool 22, and the white arrow along the circumferential direction of the chamfering tool 22 indicates the revolution direction of the chamfering tool 22. The rotation direction and the revolution direction of the chamfering tool 22 may be the same direction or opposite directions.
[0235] In this example, the type of the power source 32c for rotation and the type of the power source 32d for revolution are both electric motors.
[0236] The second drive mechanism 32 may be provided separately from the first drive mechanism 31, or at least a part of the second drive mechanism 32 may be shared with the first drive mechanism 31. For example, the power source 32a for feeding and the power source 32c for rotation of the second drive mechanism 32 may share the power source 31a for feeding and the power source 32c for rotation of the first drive mechanism 31. The second drive mechanism 32 may be a mechanism independent of the first drive mechanism 31.
[0237] [Measurement Department]
[0238] The measuring unit 40 is as follows FIG. 5A to FIG. 5C As shown in FIG. 1 , a first physical quantity and a second physical quantity related to the control of the first drive mechanism 31 are obtained. The first physical quantity obtained by the measuring unit 40 is preferably, for example, the feed speed of the drilling tool 21. The second physical quantity obtained by the measuring unit 40 is preferably Figure 7 Shown first time. Figure 7 This is a graph showing the transition of the load current of the power source 31 c for rotation of the boring blade 21 obtained by the measuring unit 40 . Figure 7The details of the graph are described later. The first time refers to the time from the start of the hole opening process of the first plate portion 11 to the start of the hole opening process of the second plate portion 12. The first time has a first processing time and an intermediate time. The first processing time refers to the time from the start of the hole opening process of the first plate portion 11 to the completion of the hole opening process of the first plate portion 11. The intermediate time refers to the time from the completion of the hole opening process of the first plate portion 11 to the start of the hole opening process of the second plate portion 12. The reason for the preferred feed speed and the first time is that the positions of the first opening edge portion 114 on the surface side of the first hole portion 113 and the first opening edge portion 115 on the back side and the position of the second opening edge portion 125 on the back side of the second hole portion 123 can be easily and accurately calculated by the first calculation unit 51 of the control unit 50 described later.
[0239] The measuring unit 40 preferably also acquires a third physical quantity related to the control of the first drive mechanism 31. The third physical quantity is preferably Figure 7 The second time is the second processing time from the start of the hole-opening process of the second plate portion 12 to the completion of the hole-opening process of the second plate portion 12. The second time is preferred because the position of the second opening edge portion 124 on the surface side of the second hole portion 123 can be easily and accurately calculated by the first calculation unit 51 of the control unit 50 described later.
[0240] The feed speed of the boring tool 21 can be obtained from the set value of the power source 31a for feeding. The first time and the second time can be obtained from the change of the load current of the power source 31c for rotation, for example. The reason is that the load current is correlated with the processing resistance of the boring tool 21. The load current of the power source 31c for rotation can be measured by a current sensor.
[0241] During the drilling process, the machining resistance, i.e., the cutting resistance, of the drilling tool 21 increases, so the load torque of the power source 31c for self-rotation increases, and the load current increases. During the drilling process, the drilling tool 21 is rotated by the power source 31c for self-rotation under the cutting conditions when drilling the workpiece 100, and the state in which the drilling tool 21 and the workpiece 100 are in contact. The drilling process includes the period from the start to the completion of the drilling process of the first plate portion 11 and the period from the start to the completion of the drilling process of the second plate portion 12.
[0242] On the other hand, in the idling of the power source 31c for self-rotation, there is substantially no processing resistance of the drilling tool 21, so the load torque of the power source 31c for self-rotation becomes smaller, and the above-mentioned load current becomes smaller. Therefore, the above-mentioned load current substantially takes a constant value. Regarding the idling of the power source 31c for self-rotation, there can be cited a period until the start of the drilling process of the first plate portion 11, a period from the completion of the drilling process of the first plate portion 11 to the start of the drilling process of the second plate portion 12, and a period from the completion of the drilling process of the second plate portion 12 to the retreat of the drilling tool 21 to the initial position.
[0243] That is, Figure 7 As shown, the time required from the first rise of the load current to the second rise through the fall is the first time. The time required from the first rise of the load current to the fall within the first time is the first processing time. The time required from the first fall of the load current to the second rise within the first time is the intermediate time. The time required from the second rise of the load current to the fall is the second processing time.
[0244] [Control Department]
[0245] The control unit 50 controls the first drive mechanism 31 so that the drilling tool 21 performs the above-specified drilling process, and controls the second drive mechanism 32 so that the chamfering tool 22 performs the above-specified chamfering process. The control unit 50 changes the feed amount of the chamfering tool 22 by the power source 32a for feeding as a control condition of the second drive mechanism 32. The change in feed amount is performed based on the result of the first operation unit 51. The control unit 50 is typically composed of a computer. The computer has a processor, a memory, etc. A program for causing the computer to execute the control sequence described later is stored in the memory. The processor reads out the program stored in the memory and executes it. The program includes program code related to the processing of changing the above-mentioned feed amount based on the calculation result of the first operation unit 51. The control unit 50 is as follows. FIG. 5A to FIG. 5C , FIG. 6A to FIG. 6E As shown, it includes a first computing unit 51 and a first storage unit 55 .
[0246] (First calculation unit)
[0247] The first calculation unit 51 calculates at least one of the position of the first opening edge 114 on the surface side and the position of the first opening edge 115 on the back side, and the position of the second opening edge 125 on the back side, based on the first physical quantity and the second physical quantity obtained by the measuring unit 40. The position of the first opening edge 114 on the surface side and the position of the first opening edge 115 on the back side are obtained by the axial length of the first hole 113. The axial length of the first hole 113 is obtained, for example, based on the feed speed of the drilling tool 21 and the first processing time. The position of the second opening edge 125 on the back side is obtained by the relative interval between the first hole 113 and the second hole 123. The above relative interval is obtained, for example, based on the feed speed of the drilling tool 21 and the intermediate time.
[0248] The first calculation unit 51 can also calculate the position of the second opening edge 124 on the surface side of the second plate portion 12 by using the third physical quantity obtained by the measuring unit 40. The position of the second opening edge 124 on the surface side is obtained by the axial length of the second hole 123. The axial length of the second hole 123 can be calculated based on the feed speed of the drilling tool 21 and the second processing time, for example. The positions of the opening edges are stored in the first storage unit 55.
[0249] [Control order]
[0250] Reference Figure 7 , the control sequence of the control unit 50 is explained. Figure 7 1 is a graph showing the transition of the load current of the power source 31 c for the rotation of the boring cutter 21 . Figure 7 The horizontal axis represents time. Figure 7 The vertical axis represents the current value. Fig. 6 shows the change in the current value when the workpiece 100 is machined using the normal boring tool 21 without any defect. Figure 7 The waveform of the current value is simplified for the sake of convenience and does not necessarily correspond to the actual waveform. In this method, the control sequence of chamfering is described in the order of passing through the first opening edge 114 on the surface side, the first hole 113, the first opening edge 115 on the back side, the second opening edge 125 on the back side, the second hole 123, and reaching the second opening edge 124 on the surface side.
[0251] The measuring unit 40 obtains the feed speed of the boring tool 21 as the first physical quantity from the set value of the power source 31a for feeding the boring tool 21 in advance. In addition, the measuring unit 40 obtains the first processing time and the intermediate time as the second physical quantity, and obtains the second processing time as the third physical quantity during the boring process performed by the boring tool 21. The first processing time is the time required from the start to the completion of the boring process of the first plate part 11. The intermediate time is the time required from the completion of the boring process of the first plate part 11 to the start of the boring process of the second plate part 12. The second processing time is the time required from the start to the completion of the boring process of the second plate part 12. The first processing time, the intermediate time, and the second processing time can be grasped based on the change of the load current value of the power source 31c for rotation.
[0252] If the boring tool 21 is rotated by the power source 31c for self-rotation, the measuring unit 40 obtains the current value of the power source 31c for self-rotation. FIG. 5A to FIG. 5C As shown, the feeding power source 31a is driven to advance, and the hole drilling is performed from the first plate portion 11 side in the order of the first plate portion 11 and the second plate portion 12. By this hole drilling, as shown in FIG. Figure 5B As shown, a first hole portion 113 is formed in the first plate portion 11. Figure 5C As shown, the second hole portion 123 is formed in the second plate portion 12. When the second hole portion 123 is formed, the boring tool 21 is driven by the power source 31a for feeding to retreat and return to the initial position.
[0253] During the process of the drilling tool 21 moving forward and backward, the load current of the drilling tool 21 changes. Figure 5B During the period from the start to the completion of the drilling process of the first plate portion 11 shown in FIG. 1 , the machining resistance of the drilling tool 21 becomes large, so Figure 7 During the period from the completion of the drilling process of the first plate portion 11 to the start of the drilling process of the second plate portion 12, there is substantially no machining resistance of the drilling tool 21, so Figure 7 Specifically, the current value converges to the current value before the start of the hole drilling process. Figure 5C During the period from the start to the completion of the drilling process of the second plate portion 12 shown in FIG. 1 , the machining resistance of the drilling tool 21 becomes large, so Figure 7 The current value shown in the figure becomes larger. There is substantially no machining resistance during the period from the completion of the drilling process of the second plate portion 12 to the return to the initial position, so the current value becomes smaller. Specifically, it converges to the current value before the start of the drilling process. The measuring unit 40 can obtain the first machining time, the intermediate time, and the second machining time based on the change in the current value.
[0254] The first calculation unit 51 calculates the positions of the first opening edge 114 on the front side, the first opening edge 115 on the back side, the second opening edge 124 on the front side, and the second opening edge 125 on the back side based on the feed speed, the first processing time, the intermediate time, and the second processing time of the boring tool 21 obtained by the measuring unit 40. The method of calculating the positions of the first opening edge 114 on the front side, the first opening edge 115 on the back side, the second opening edge 124 on the front side, and the second opening edge 125 on the back side is as described above.
[0255] The control unit 50 controls the second drive mechanism 32 to process each opening edge portion in the order of the first opening edge portion 114 on the surface side, the first opening edge portion 115 on the back side, the second opening edge portion 125 on the back side, and the second opening edge portion 124 on the surface side based on the position of each opening edge portion.
[0256] The control unit 50 drives the power source 32c for rotation. The timing of driving the power source 32c for rotation can be before the cutting blade 24 contacts the edge of the opening. That is, the timing of driving the power source 32c for rotation can be before the driving of the power source 32a for feeding described later, or after the driving of the power source 32a for feeding, or before the driving of the power source 32d for revolution described later.
[0257] The control unit 50 is as follows Fig. 6A As shown, the power source 32a for feeding is driven in such a manner that the chamfering tool 22 in the initial position is advanced. In this embodiment, after the position of the cutting edge 24 on the front end side of the chamfering tool 22 in the axial direction advances to the same position as the first opening edge 114 on the surface side, the control unit 50 stops driving the power source 32a for feeding. By stopping, the cutting edge 24 on the front end side is maintained at a position where the first opening edge 114 on the surface side can be processed.
[0258] After the driving of the power source 32a for feeding stops, the control unit 50 Figure 6B As shown, the power source 32d for revolution is driven in such a manner that the cutting blade 24 on the front end side contacts the first opening edge 114 on the surface side, and the entire circumference of the first opening edge 114 on the surface side is cut to form the first chamfered portion 116 on the surface side. After the cutting process is completed, the control unit 50 drives the power source 32d for revolution in such a manner that the cutting blade 24 on the front end side is separated from the first opening edge 114 on the surface side. After the chamfering tool 22 moves in a direction orthogonal to the axial direction to a position where the main body 23 of the chamfering tool 22 does not contact the inner peripheral surface of the first hole portion 113 even if the chamfering tool 22 is moved forward, the control unit 50 stops driving the power source 32d for revolution.
[0259] After the driving of the power source 32d for revolution stops, the control unit 50 drives the power source 32a for feeding so as to advance the chamfering tool 22. The chamfering tool 22 is inserted through the first hole 113, and the position of the cutting blade 24 on the rear end side of the chamfering tool 22 advances to the same position as the first opening edge 115 on the back side, and then the control unit 50 stops driving the power source 32a for feeding. By stopping, the cutting blade 24 on the rear end side is maintained at a position where it can process the first opening edge 115 on the back side.
[0260] After the power source 32a for feeding stops, the control unit 50 sequentially drives the power source 32d for revolution and stops the driving of the power source 32d for revolution as described above. Figure 6C As shown, the first opening edge portion 115 on the back side is cut by the chamfering cutter 22 to form a first chamfered portion 117 on the back side.
[0261] The control unit 50 drives the power source 32a for feeding so as to advance the chamfering tool 22. After the position of the cutting edge 24 on the front end side of the chamfering tool 22 advances to the same position as the second opening edge 125 on the back side, the control unit 50 stops driving the power source 32a for feeding. By stopping, the cutting edge 24 on the front end side is maintained at a position where the second opening edge 125 on the back side can be processed.
[0262] After the power source 32a for feeding stops, the control unit 50 sequentially drives the power source 32d for revolution and stops the driving of the power source 32d for revolution as described above. Fig.6D As shown, the second opening edge portion 125 on the back side is cut by the chamfering cutter 22 to form a second chamfered portion 127 on the back side.
[0263] The control unit 50 drives the power source 32a for feeding so as to advance the chamfering tool 22. After the position of the cutting blade 24 on the rear end side of the chamfering tool 22 advances to the same position as the second opening edge 124 on the surface side, the control unit 50 stops driving the power source 32a for feeding. By stopping, the cutting blade 24 on the rear end side is maintained at a position where the second opening edge 124 on the surface side can be processed.
[0264] After the feeding power source 32a stops, the control unit 50 sequentially drives the revolution power source 32d and stops the revolution power source 32d as described above. Fig. 6E As shown, the second opening edge portion 124 on the front side is cut by the chamfering cutter 22 to form a second chamfered portion 126 on the front side.
[0265] The control unit 50 drives the power source 32a for feeding so as to retreat the chamfering tool 22. After the chamfering tool 22 retreats to the initial position, the control unit 50 stops driving the power source 32a for feeding.
[0266] When manufacturing a metal component 1 having a plurality of first holes 113 and second holes 123 on a circumference as in the present embodiment described above, the above process is repeated. When the above process is repeated, after one or more processes are performed, before the next process is performed, the boring tool 21 is moved by a predetermined distance in a direction perpendicular to the axial direction of the boring tool 21, or the workpiece 100 is rotated by a predetermined angle.
[0267] When the power source 31c for self-rotation and the power source 32c for self-rotation are a common power source, the hole drilling tool 21 and the chamfering tool 22 are replaced after the hole drilling process is completed and before the chamfering process. When the power source 31c for self-rotation and the power source 32c for self-rotation are independent power sources, the power source 31c for self-rotation and the power source 32c for self-rotation can be still driven when the next object to be cut is being processed, or can be temporarily stopped before the next object to be cut is processed and then driven again. When there is no next object to be cut, the power source 31c for self-rotation and the power source 32c for self-rotation are stopped.
[0268] [use]
[0269] The processing system 10 according to the present embodiment can be suitably used as a processing system for manufacturing various general structural components. The general structural components are as described above.
[0270] 〔Effect〕
[0271] The machining system 10 according to the present embodiment can accurately determine the positions of the first opening edge 114 on the surface side and the first opening edge 115 on the back side of the first hole 113 and the positions of the second opening edge 124 on the surface side and the second opening edge 125 on the back side of the second hole 123, even if the positions of the opening edges fluctuate due to the dimensional tolerance of the workpiece 100. Furthermore, the machining system 10 according to the present embodiment can control the second drive mechanism 32 for each workpiece 100 so that the chamfering tool 22 can appropriately chamfer the first opening edge 114 on the surface side and the first opening edge 115 on the back side and the second opening edge 124 on the surface side and the second opening edge 125 on the back side. Therefore, the machining system 10 according to the present embodiment can manufacture the above-mentioned metal component 1.
[0272] [Method for manufacturing metal parts]
[0273] The method for manufacturing a metal component according to the present embodiment includes the following steps A to C.
[0274] The step A is to prepare the workpiece 100 .
[0275] In step B, the boring tool 21 is operated by the first driving mechanism 31 to perform boring processing on the workpiece 100 .
[0276] In step C, the chamfering tool 22 is operated by the second drive mechanism 32 to chamfer the opening edge of the hole formed by the drilling process.
[0277] Next, each step will be described in detail.
[0278] [Process A]
[0279] The prepared workpiece 100 is a workpiece to be processed by a drilling tool and a chamfering tool. The workpiece 100 is as described in the column of the workpiece 100 of the processing system 10. Figure 5A As shown, there are a first plate portion 11 , a second plate portion 12 and a foot portion 13 .
[0280] [Process B]
[0281] Hole processing Figure 5B As shown, the first hole portion 113 is formed on the first plate portion 11. Figure 5C As shown in FIG. 1 , the second hole 123 is formed in the second plate portion 12. The hole processing of the first plate portion 11 and the second plate portion 12 is as follows: FIG. 5A to FIG. 5C As shown, the first plate portion 11 and the second plate portion 12 are sequentially processed from the first plate portion 11 side so that the axis of the first plate portion 11 and the axis of the second plate portion 12 become coaxial. Step B includes steps B1 and B2 described later.
[0282] (Process B1)
[0283] In step B1, the first physical quantity and the second physical quantity related to the control of the first drive mechanism 31 are measured by the measuring unit 40. As described above, the first physical quantity preferably obtained is the feed speed of the drilling tool 21, and the second physical quantity obtained is the first time. In step B1, it is further preferred to obtain the second time as the third physical quantity. The reason for the preference is as described above.
[0284] (Process B2)
[0285] In step B2, the position of the opening edge of the hole formed by the hole punching process is calculated based on the first physical quantity and the second physical quantity. As the position of the opening edge to be calculated, the position of the first opening edge 115 on the back side of at least the first plate portion 11 and the position of the second opening edge 125 on the back side of the second plate portion 12 can be cited. The method for calculating the position of the first opening edge 115 on the back side and the position of the second opening edge 125 on the back side is as described above. In this step B2, it is further preferred to calculate the position of the first opening edge 114 on the surface side of the first plate portion 11 based on the first physical quantity and the second physical quantity, and it is preferred to calculate the position of the second opening edge 124 on the surface side of the second plate portion 12 based on the first physical quantity, the second physical quantity and the third physical quantity.
[0286] [Process C]
[0287] The chamfering process is to form the first plate portion 11 as shown in FIG. Figure 6B The first chamfered portion 116 on the surface side provided at the first opening edge portion 114 on the surface side and Figure 6C The first chamfering part of at least one of the first chamfering parts 117 on the back side provided at the first opening edge part 115 on the back side is shown. The chamfering process is performed on the second plate part 12 as shown in FIG. Fig.6D As shown in FIG. 1 , at least the second opening edge 125 on the back side forms a second chamfered portion 127 on the back side. The chamfering process may be further as follows: Fig. 6E As shown, a second chamfered portion 126 on the surface side is formed on the second opening edge portion 124 on the surface side. The chamfering process is performed by cutting by the chamfering tool 22. The chamfered portion not only improves the guiding property of the inserted through object, but also can remove the burr formed when the hole forming tool 21 forms the hole portion, and can reliably insert the inserted through object into the hole portion.
[0288] When the first opening edge portion 114 on the surface side is chamfered, as shown in FIG. Figure 6B As shown in FIG. 1 , the chamfering tool 22 is brought closer to the first opening edge 114 on the front side from the first surface 111 side. When the first opening edge 115 on the back side is chamfered, as shown in FIG. Figure 6C As shown, the chamfering tool 22 is inserted from the first opening edge 115 on the front side through the first hole 113 and approaches the first opening edge 115 on the back side. When the second opening edge 125 on the back side is chamfered, as shown in FIG. Fig.6D As shown in FIG. 1 , the chamfering tool 22 is inserted through the first hole 113 and approaches the second opening edge 125 on the back side. When the second opening edge 124 on the front side is chamfered, as shown in FIG. Fig. 6E As shown, the chamfering cutter 22 is inserted through the first hole portion 113 and the second hole portion 123 in this order and approaches the second opening edge portion 124 on the surface side.
[0289] The order of chamfering may be the first opening edge 114 on the front side, the first opening edge 115 on the back side, the second opening edge 125 on the back side, and the second opening edge 124 on the front side, or the reverse order. The cutting process is performed by changing the control conditions of the second drive mechanism 32 in accordance with the position of the first opening edge 115 on the back side and the position of the second opening edge 125 on the back side. The change of the control conditions of the second drive mechanism 32 is as described above.
[0290] The chamfering of the first opening edge 115 on the back side and the second opening edge 125 on the back side is preferably such that the chamfering length of the first chamfered portion 117 on the back side and the second chamfered portion 127 on the back side are smaller than the dimensional tolerance of the relative interval between the first plate portion 11 and the second plate portion 12. The chamfering length is as described above. The dimensional tolerance is the "tolerance" in accordance with "JIS Z8103 (2019) Measurement Terminology".
[0291] When the chamfering length is smaller than the dimensional tolerance, the chamfering tool 22 may not properly contact the first opening edge 115 on the back side of the first plate portion 11 and the second opening edge 125 on the back side of the second plate portion 12, and proper chamfering cannot be performed. However, the manufacturing method of the metal part involved in this embodiment calculates the positions of the first opening edge 115 on the back side of the first plate portion 11 and the second opening edge 125 on the back side of the second plate portion 12, and controls the second drive mechanism 32 corresponding to each position. Therefore, even when the chamfering length is smaller than the dimensional tolerance, the chamfering tool 22 can be properly contacted with the opening edge, and proper chamfering can be performed.
[0292] [use]
[0293] The method for manufacturing a metal component according to the present embodiment can be suitably used in a method for manufacturing various general structural components. The general structural components are as described above.
[0294] 〔Effect〕
[0295] The method for manufacturing a metal component according to the present embodiment can accurately determine the positions of the first opening edge 114 on the front side and the first opening edge 115 on the back side of the first hole 113 and the positions of the second opening edge 124 on the front side and the second opening edge 125 on the back side of the second hole 123, even if the positions of the opening edges fluctuate due to the dimensional tolerance of the workpiece 100. Furthermore, the method for manufacturing a metal component according to the present embodiment can control the second drive mechanism 32 for each workpiece 100 so that the chamfering tool 22 can appropriately cut the first opening edge 114 on the front side and the first opening edge 115 on the back side and the second opening edge 124 on the front side and the second opening edge 125 on the back side. Therefore, the method for manufacturing a metal component according to the present embodiment can manufacture the above-mentioned metal component 1.
[0296] Implementation Method 2
[0297] 〔Processing system〕
[0298] Reference FIG. 5A to FIG. 5C , Figure 8 and Fig. 9 , the processing system 10 according to the second embodiment will be described. The processing system 10 according to this embodiment is different from the processing system 10 according to the first embodiment in the following important condition (1).
[0299] (1) The control unit 50 changes the rotation speed of the power source 31c for rotation based on the difference between the first electric quantity and the second electric quantity obtained by the measuring unit 40. The first electric quantity and the second electric quantity will be described in detail later.
[0300] The following description will focus on the differences from the machining system 10 according to Embodiment 1. Description of the same configuration as that of the machining system 10 according to Embodiment 1 will be omitted.
[0301] [Measurement Department]
[0302] The first electric quantity is the electric quantity of the power source 31c for self-rotation obtained by the measuring unit 40 during the idling of the power source 31c for self-rotation. The second electric quantity is the electric quantity of the power source 31c for self-rotation obtained by the measuring unit 40 during the processing of the workpiece 100. The processing of the workpiece 100 includes the processing of drilling a hole in the first plate portion 11 of the workpiece 100 and the processing of drilling a hole in the second plate portion 12 of the workpiece 100. That is, the second electric quantity refers to the electric quantity of the power source 31c for self-rotation obtained by the measuring unit 40 during the processing of drilling a hole in the first plate portion 11 of the workpiece 100. Alternatively, the second electric quantity refers to the electric quantity of the power source 31c for self-rotation obtained by the measuring unit 40 during the processing of drilling a hole in the second plate portion 12 of the workpiece 100.
[0303] The electric quantity of the power source 31c for self-rotation obtained by the measuring unit 40 includes, for example, the value obtained by the current sensor itself, the value related to the value obtained by the current sensor, and the value obtained by performing a predetermined operation on the value obtained by the current sensor. That is, the first electric quantity and the second electric quantity include the electric quantity itself that drives the power source 31c for self-rotation, the physical quantity related to the electric quantity, or the calculated value calculated based on the electric quantity. As the first electric quantity and the second electric quantity, for example, at least one of the magnitude, differential value, and integral value of the load current of the power source 31c for self-rotation is preferred. The reason is that the magnitude, differential value, and integral value of the load current of the power source 31c for self-rotation are each correlated with the defect of the drilling tool 21, so it is easy to detect the defect of the drilling tool 21. As for the defect, in addition to the case where the blade of the drilling tool 21 is missing, it also includes the case where the drilling tool 21 is bent and broken. The magnitude of the load current of the power source 31c for self-rotation is, for example, the value obtained by the current sensor itself. The differential value and the integrated value of the load current of the power source 31c for rotation are obtained by, for example, calculating the load current value of the power source 31c for rotation obtained by the current sensor. This calculation can be performed by the control unit 50 described later.
[0304] If the hole punching tool 21 is defective, the area of the hole punching tool 21 that is non-contact with the workpiece 100 increases, and the hole punching process itself becomes difficult. If the hole punching process becomes difficult, the processing resistance of the hole punching tool 21 becomes smaller. If the processing resistance of the hole punching tool 21 is small, the load torque of the power source 31c for self-rotation becomes smaller, and thus the magnitude of the load current of the power source 31c for self-rotation in the hole punching process of the workpiece 100 becomes smaller. That is, if the hole punching tool 21 is defective, the magnitude of the load current of the power source 31c for self-rotation becomes smaller.
[0305] Specifically, when the boring tool 21 is broken and does not contact the workpiece 100, the processing depth is zero (0). The processing depth is zero, and thus the magnitude, differential value, and integral value of the load current of the power source 31c for self-rotation in the boring processing of the workpiece 100 are substantially the same as the magnitude, differential value, and integral value of the load current in the idling of the power source 31c for self-rotation. On the other hand, when the boring tool 21 is still in contact with the workpiece 100 despite the occurrence of a notch in the blade portion of the boring tool 21, the processing depth becomes smaller. The processing depth is small, and thus the magnitude, differential value, and integral value of the load current of the power source 31c for self-rotation in the processing of the workpiece 100 are smaller, although not as small as when the boring tool 21 is not in contact with the workpiece 100. That is, the magnitude, differential value, and integral value of the load current of the power source 31c for self-rotation in the processing of the workpiece 100 are close to the magnitude, differential value, and integral value of the load current in the idling of the power source 31c for self-rotation. Thus, at least one of the magnitude, differential value, and integral value of the load current of the rotational power source 31 c can be used to understand whether the boring tool 21 processes the workpiece 100 , that is, whether a defect occurs in the boring tool 21 .
[0306] [Control Department]
[0307] The control unit 50 controls the power source 31c for self-rotation. The control unit 50, for example, drives the power source 31c for self-rotation, or stops the power source 31c for self-rotation. The control unit 50 changes the control conditions of the power source 31c for self-rotation. The change of the control conditions of the power source 31c for self-rotation is representatively based on the first difference and the second difference described later. The control unit 50 is representatively composed of a computer. The computer has a processor, a memory, etc. A program for causing the processor to execute the control sequence described later is stored in the memory. The processor reads out the program stored in the memory and executes it. The program includes a program code related to the process of determining whether the calculation result of the second calculation unit 52 satisfies the threshold value or not, and the process of changing the rotation speed of the power source 31c for self-rotation based on the determination. The control unit 50 has a second calculation unit 52 and a second storage unit 56.
[0308] (Second calculation unit)
[0309] The second calculation unit 52 calculates the difference between the first electric quantity and the second electric quantity. The second electric quantity includes the electric quantity obtained by the measuring unit 40 during the hole drilling process of the first plate portion 11 of the workpiece 100 and the electric quantity obtained by the measuring unit 40 during the hole drilling process of the second plate portion 12 of the workpiece 100. That is, the second calculation unit 52 calculates the first difference between the first electric quantity and the second electric quantity obtained by the measuring unit 40 during the hole drilling process of the first plate portion 11 of the workpiece 100, and the second difference between the first electric quantity and the second electric quantity obtained by the measuring unit 40 during the hole drilling process of the second plate portion 12 of the workpiece 100. As described above, when the first electric quantity and the second electric quantity are at least one of the magnitude, differential value, and integral value of the load current of the power source 31c for rotation, the first difference and the second difference to be calculated can be at least one of the difference between the magnitudes of the load current, the difference between the differential values, and the difference between the integral values. The first difference and the second difference are stored in the second storage unit 56 of the control unit 50.
[0310] When the first electric quantity is at least one of the magnitude, differential value, and integral value of the load current of the power source 31 c for rotation, the first electric quantity takes a substantially constant value. The first electric quantity may be obtained in advance and stored in the second storage unit 56 .
[0311] In addition, the first electric quantity may be obtained for each workpiece 100 during the idling of the power source 31c for self-rotation. When the first electric quantity is obtained for each workpiece 100 during the idling of the power source 31c for self-rotation, the first electric quantity may be, for example, the electric quantity set as follows. Figure 5A As shown, at the initial position where the boring tool 21 is retreated the farthest from the workpiece 100, the boring tool 21 is rotated by the power source 31c for self-rotation under the same cutting conditions as when the workpiece 100 is actually processed. The amount of electricity of the power source 31c for self-rotation obtained by the measuring unit 40 at this time can be cited.
[0312] When the second electric quantity is set to the magnitude of the load current of the power source 31c for rotation, it is as follows. The first electric quantity is set to the average value of the load current obtained from the start of processing of the first plate portion 11 by the drilling cutter 21 to the completion of the processing. Alternatively, the second electric quantity is set to the average value of the load current obtained from the start of processing of the second plate portion 12 by the drilling cutter 21 to the completion of the processing.
[0313] In addition, when the second electric quantity is set to the differential value of the load current of the power source 31c for rotation, it is as follows. The second electric quantity is set to the differential value of the current value immediately after the processing of the first plate portion 11 by the drilling tool 21 is started. Alternatively, the second electric quantity is set to the differential value of the current value immediately after the processing of the second plate portion 12 by the drilling tool 21 is started. Immediately after the processing is started refers to the period from the start of the processing to the current value reaching the maximum value.
[0314] Furthermore, when the second electric quantity is set as the integral value of the load current of the power source 31c for rotation, it is as follows. The second electric quantity is set as the integral value of the load current obtained from the start of processing of the first plate portion 11 by the drilling tool 21 to the completion of the processing. Alternatively, the second electric quantity is set as the integral value of the load current obtained from the start of processing of the second plate portion 12 by the drilling tool 21 to the completion of the processing.
[0315] The start time of each process and the completion time of each process are obtained by, for example, processing a plurality of cut objects in advance using a hole-piercing tool 21 without a defect, and stored in the second storage unit 56. The material, shape and size of the plurality of cut objects processed in advance are set to be the same as the material, shape and size of the cut object 100 used for this process. The processing conditions of the plurality of cut objects processed in advance are set to be the same as the processing conditions of the cut object 100 used for this process. The start time of each process and the completion time of each process can be grasped based on the load current of the power source 31c for rotation. The number of the plurality of cut objects processed in advance can be about 2 to 10.
[0316] The start time of each process to be stored may be the latest start time of the process when processing each plate portion of a plurality of cut objects. The completion time of each process to be stored may be the earliest completion time of the process when processing each plate portion of a plurality of cut objects. Thus, the average value and integral value of the load current obtained from the start of the process of each plate portion of the cut object to the completion of the process and the differential value of the load current just after the start of the process of each plate portion of the cut object are difficult to include the current value of the idling of the power source 31c for rotation. Therefore, the average value and integral value of the load current obtained from the start of the process of each plate portion of the cut object to the completion of the process and the differential value of the load current just after the start of the process of each plate portion of the cut object are equivalent to the average value, integral value and differential value of the load current when each plate portion is actually processed. The start time of each process to be stored may be updated at each delay in the start of the process when processing each plate portion of the cut object 100. Similarly, the stored processing completion time may be updated each time the processing completion time is advanced when processing each plate portion of the workpiece 100 is processed.
[0317] The control unit 50 sets the rotation speed of the power source 31c for rotation to zero when either the first difference is less than the first threshold value or the second difference is less than the second threshold value. The first threshold value and the second threshold value may be, for example, values based on the safety rate of the machining system 10 and whether appropriate machining can be performed by the drilling tool 21. The first threshold value and the second threshold value are pre-stored in the second storage unit 56. The first threshold value and the second threshold value may be the same.
[0318] If the rotation speed of the power source 31c for self-rotation becomes zero, the rotation of the hole-piercing tool 21 stops. The timing of changing the rotation speed of the power source 31c for self-rotation does not depend on the position of the hole-piercing tool 21. After the rotation speed of the power source 31c for self-rotation becomes zero, the power source 31a for feeding can be driven to move the hole-piercing tool 21 to the initial position, or after the power source 31a for feeding is driven to move the hole-piercing tool 21 to the initial position, the rotation speed of the power source 31c for self-rotation can be set to zero. In the case where either of the conditions is met, a defect occurs in the hole-piercing tool 21. Therefore, the control unit 50 sets the rotation speed of the power source 31c for self-rotation to zero, thereby preventing the continuous production of defective products that are not subjected to the prescribed processing by the hole-piercing tool 21.
[0319] When the first difference exceeds the first threshold and the second difference exceeds the second threshold, the control unit 50 does not change the rotation speed of the power source 31c for rotation of the current boring tool 21. In this case, the boring tool 21 rotates at the same rotation speed of the power source 31c for rotation as the immediately preceding boring tool 100 for the next workpiece 100 to be bored.
[0320] [Control order]
[0321] Reference Figure 8 , the control sequence of the control unit 50 will be described. If the boring tool 21 is rotated by the power source 31c for self-rotation, Figure 8 In step S1 shown, the load current of the power source 31c for rotation is obtained by the measuring unit 40.
[0322] As Figure 8 In step S2 shown, the second calculation unit 52 calculates the above-mentioned first difference.
[0323] As Figure 8In step S3 shown, the control unit 50 determines whether the first difference satisfies or is below the first threshold value. Here, the first threshold value is set to the middle value of the difference between the second electric quantity in the processing of the first plate portion 11 and the first electric quantity in the idling of the power source 31c for rotation when the normal drilling tool 21 is used for convenience of explanation. The middle value is set to at least one of the middle value of the difference between the magnitudes of the load currents, the middle value of the difference between the differential values, and the middle value of the difference between the integral values.
[0324] When the first threshold value is satisfied or below in step S3, the control unit 50 sets the rotation speed of the power source 31c for self-rotation to zero as step S4. If the rotation speed of the power source 31c for self-rotation becomes zero, the rotation of the drilling tool 21 stops. And the control ends. The details of the case where step S3 satisfies the threshold value or below are described later, and examples thereof include the case where a drilling tool with a defect that cannot contact the object 100 is used, and the case where a drilling tool with a defect but still able to contact the object 100 is used.
[0325] If the determination in step S3 is negative, Figure 8 In step S5 shown, the load current of the power source 31c for rotation is obtained by the measuring unit 40.
[0326] As Figure 8 In step S6 shown, the second calculation unit 52 calculates the second difference.
[0327] As Figure 8 In step S7 shown, the control unit 50 determines whether the second difference satisfies or is below the second threshold value. Here, the second threshold value is set to the middle value of the difference between the magnitude, differential value, and integral value of the load current in the machining of the second plate portion 12 of the workpiece 100 and the magnitude, differential value, and integral value of the load current in the idling of the power source 31c for rotation when the normal drilling tool 21 is used. The middle value is also set to at least one of the middle value of the difference between the magnitudes of the load currents, the middle value of the difference between the differential values, and the middle value of the difference between the integral values, as with the first threshold value.
[0328] When the second threshold value or less is satisfied in step S7, the control unit 50 sets the rotation speed of the power source 31c for rotation to zero, as in step S4 described above.
[0329] If the determination result in step S7 is negative, the control unit 50 does not change the rotation speed of the power source 31c for self-rotation. That is, the next workpiece 100 is processed at the same rotation speed of the power source 31c for self-rotation as the workpiece 100 immediately before it, and the processing of the next workpiece 100 and steps S1 to S3 are repeated until the determination result in step S3 is below the threshold. The details of the case where the determination result in step S3 is negative will be described later, and an example of the case where a normal drilling tool without a defect is used can be cited.
[0330] Reference Fig. 9 The control sequence of the control unit 50 is described for each of the following cases: using a hole punching tool with a defect that prevents it from contacting the object 100, using a hole punching tool with a defect but still able to contact the object 100, and using a normal hole punching tool without a defect. Fig. 9 The figure shows the change of the load current of the power source 31 c for rotation obtained by the measuring unit 40 when the workpiece 100 is machined using the above-mentioned respective tools. Fig. 9 The horizontal axis represents time. Fig. 9 The vertical axis represents the load current value. Fig. 9 The dotted line shows the change in load current when a boring tool having a defect that makes it impossible to contact the workpiece 100 is used. Fig. 9 The two-dot chain line shows the change in load current when a boring tool that is chipped but still able to contact the workpiece 100 is used. Fig. 9 The solid line shows the change in load current when the first plate portion 11 is processed using a normal boring tool 21 without any defect. Fig. 9 The waveform of the load current is Figure 7 Likewise, the waveforms are simplified for ease of explanation and do not necessarily correspond to actual waveforms.
[0331] (When using an inaccessible hole cutter)
[0332] like Fig. 9As shown by the dotted line, the magnitude, differential value and integral value of the load current in the hole drilling process of the first plate portion 11 of the cut object 100 are substantially the same as the magnitude, differential value and integral value of the load current in the idling of the power source 31c for self-rotation. The reason is that the hole drilling tool that cannot be contacted cannot reach the cut object 100, and the processing itself becomes difficult for the cut object 100, so the processing depth becomes zero. The second calculation unit 52 calculates the above-mentioned first difference. The calculated first difference is substantially close to zero. Therefore, if the above-mentioned first threshold value is compared with the above-mentioned first difference, the above-mentioned first difference satisfies the above-mentioned first threshold value or less. Based on the result of the comparison, the control unit 50 sets the rotation speed of the power source 31c for self-rotation to zero. If the rotation speed of the power source 31c for self-rotation becomes zero, the rotation of the hole drilling tool stops.
[0333] (When using a hole cutter that is damaged but still accessible)
[0334] like Fig. 9 As shown by the double-dotted line, the start of processing of the first plate portion 11 of the cut object 100 is delayed compared to the case where a normal drilling tool 21 is used. The reason is that the drilling tool 21, which is damaged but still accessible, reaches the first plate portion 11, but it takes time to reach it. Moreover, the magnitude, differential value and integral value of the load current in the drilling processing of the first plate portion 11 of the cut object 100 are all smaller than those in the case where a normal drilling tool 21 is used. The reason is that the drilling tool, which is damaged but still accessible, has a smaller processing depth for the first plate portion 11 than the normal drilling tool 21. That is, the cutting resistance of the drilling tool in the drilling processing of the first plate portion 11 is reduced. The second calculation unit 52 calculates the above-mentioned first difference. The calculated first difference becomes smaller. Therefore, if the above-mentioned first threshold value is compared with the above-mentioned first difference, the above-mentioned first difference satisfies the above-mentioned first threshold value or less. Based on the result of the comparison, the control unit 50 sets the rotation speed of the power source 31c for self-rotation to zero.
[0335] (When using a normal hole cutting tool 21)
[0336] like Fig. 9As shown by the solid line, the magnitude, differential value and integral value of the load current in the hole drilling process of the first plate portion 11 of the cut object 100 are greater than the magnitude, differential value and integral value of the load current in the idling of the power source 31c for rotation. The reason is that the contact area between the normal hole drilling tool 21 and the cut object 100 increases, so the cutting resistance increases. Although omitted in the figure, the magnitude, differential value and integral value of the load current in the hole drilling process of the second plate portion 12 of the cut object 100 also produce the same result. The second calculation unit 52 calculates the above-mentioned first difference and the above-mentioned second difference. The calculated first difference and second difference become larger. Therefore, if the above-mentioned first threshold value is compared with the above-mentioned first difference, the above-mentioned first difference does not satisfy the above-mentioned first threshold value or less. In addition, if the above-mentioned second threshold value is compared with the above-mentioned second difference, the above-mentioned second difference does not satisfy the above-mentioned second threshold value or less. That is, the above-mentioned first difference satisfies the above-mentioned first threshold value, and the above-mentioned second difference satisfies the above-mentioned second threshold value or less. Based on the comparison result, the control unit 50 does not change the rotation speed of the power source 31c for rotation. Since the rotation speed of the power source 31c for rotation does not change, the rotation of the boring cutter 21 is maintained.
[0337] For example, the load current when the boring tool 21 is not broken during the boring process of the first plate portion 11 but is broken at the beginning of the boring process of the second plate portion 12 is as follows, although the figure is omitted. Fig. 9 The load current in the hole-opening process of the second plate portion 12 becomes the same as the waveform shown by the solid line. Fig. 9 In this case, the first difference does not satisfy the first threshold value, but exceeds the first threshold value, and the second difference satisfies the second threshold value. Therefore, the control unit 50 stops driving the power source 31c for rotation.
[0338] 〔Effect〕
[0339] The machining system 10 according to the present embodiment can detect a defect of the boring tool 21 , and thus can suppress production of defective products due to the boring tool 21 not performing a predetermined machining.
[0340] [Method for manufacturing metal parts capable of detecting defects in drilling tools]
[0341] The manufacturing method of the metal part of this embodiment is that the above-mentioned step B includes a step of changing the rotation speed of the power source 31c for self-rotation. The change of the rotation speed of the power source 31c for self-rotation is performed based on the difference between the first electric quantity and the second electric quantity. The first electric quantity and the second electric quantity are the electric quantities of the power source 31c for self-rotation of the first driving mechanism 31 that moves the drilling tool 21, and are obtained by the measuring unit 40. The details of this step are described below.
[0342] [Process B]
[0343] The first electric quantity and the second electric quantity obtained are as described above. As the above-mentioned difference, the above-mentioned first difference and the above-mentioned second difference can be cited. Moreover, in this process, the rotation speed of the power source 31c for rotation is changed based on the comparison between the first threshold and the above-mentioned first difference and the comparison between the second threshold and the above-mentioned second difference. The above-mentioned first threshold and the above-mentioned second threshold are as described above.
[0344] When the first difference is below the first threshold value and the second difference is below the second threshold value, the rotation speed of the power source 31c for rotation is set to zero. After the rotation of the power source 31c for rotation stops, the defective drilling tool is replaced with a new drilling tool. After the new drilling tool is replaced, the processing of the next workpiece is repeated until the first difference is below the first threshold value and the second difference is below the second threshold value.
[0345] On the other hand, when the first difference exceeds the first threshold and the second difference exceeds the second threshold, the rotation speed of the power source 31c for rotation is not changed. In this case, the next workpiece 100 is subjected to drilling processing by the drilling tool with the same rotation speed as the immediately preceding workpiece 100. And, until the first difference is less than the first threshold and the second difference is less than the second threshold, the processing of the next workpiece 100 is repeated.
[0346] 〔Effect〕
[0347] The method for manufacturing a metal component can detect the defect of the drilling tool 21, thereby suppressing the production of defective products that are not subjected to the prescribed drilling process by the drilling tool 21. In addition, the method for manufacturing a metal component can improve the productivity of the metal component. This is because it is not necessary to temporarily move the drilling tool 21 to the detector to confirm whether the drilling tool 21 has a defect, so the confirmation operation can be omitted.
[0348] The present invention is not limited to these examples but is shown by the claims, and is intended to include all modifications within the scope of the claims and the equivalents thereof.
[0349] Description of the label
[0350] 1 Metal parts
[0351] 11. First board
[0352] 111 First Surface
[0353] 112 First Back
[0354] 113 First hole
[0355] 114 First opening edge portion on the surface side
[0356] 115 First opening edge portion on the back side
[0357] 116 First chamfered portion on the surface side
[0358] 117 First chamfered portion on the back side
[0359] 12 Second board
[0360] 121 Second Surface
[0361] 122 Second Back
[0362] 123 Second hole
[0363] 124 Second opening edge portion on the surface side
[0364] 125 Second opening edge portion on the back side
[0365] 126 Second chamfered portion on the surface side
[0366] 127 Second chamfered portion on the back side
[0367] 13. Feet
[0368] 15 Cutting marks
[0369] 10 Processing system
[0370] 21 Hole punch
[0371] 22 Chamfering tool
[0372] 23 Subject
[0373] 24 cutting edge
[0374] 31 First drive mechanism
[0375] 31a Power source for feeding
[0376] 31c Power source for self-rotation
[0377] 32 Second driving mechanism
[0378] 32a Power source for feeding
[0379] 32c Power source for self-rotation
[0380] 32d Power source for revolution
[0381] 40 Measurement Department
[0382] 50 Control Department
[0383] 51 First calculation unit
[0384] 52 Second operation unit
[0385] 55 First storage unit
[0386] 56 Second storage unit
[0387] 100 Cutting material
[0388] 200 workbench
[0389] 210 Hole
Claims
1. A processing system comprising: Hole punching tools and chamfering tools, which process workpieces consisting of metal parts; A first drive mechanism for moving the drilling tool and a second drive mechanism for moving the chamfering tool; a control unit that controls the first driving mechanism and the second driving mechanism; and a measuring unit that obtains a first physical quantity and a second physical quantity related to the control of the first driving mechanism, The object to be cut has: a first plate portion having a first surface and a first back surface; a second plate portion having a second surface and a second back surface; and a foot portion that fixes the first plate portion and the second plate portion in a manner that the first back surface and the second back surface face each other with a gap therebetween, The first driving mechanism operates the drilling tool so as to coaxially process a first hole portion penetrating the first surface and the first back surface and a second hole portion provided in the second plate portion in sequence. The first hole portion is a hole portion having a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface. The second hole portion is a hole portion having at least a second opening edge portion provided on the back side of the second back surface, The second driving mechanism operates the chamfering tool in such a manner that a first chamfered portion is provided at the first opening edge of at least one of the first opening edge on the front side and the first opening edge on the back side, and a second chamfered portion on the back side is provided at the second opening edge on the back side. The first physical quantity is the feed speed of the drilling tool, The second physical quantity is a first time from the start of the hole-forming process of the first plate portion to the start of the hole-forming process of the second plate portion. The control unit obtains the position of the first opening edge of the at least one and the position of the second opening edge of the back side based on the first physical quantity and the second physical quantity, The second drive mechanism is controlled based on the position of the first opening edge of the at least one and the position of the second opening edge of the back side, The position of the first opening edge of the at least one and the position of the second opening edge of the back side are obtained based on the length of the first hole along the axial direction and the length between the first plate portion and the second plate portion. The length of the first hole portion in the axial direction and the length between the first plate portion and the second plate portion are obtained based on the feed speed and the first time.
2. The processing system according to claim 1, wherein: The chamfering tool has a columnar body, the outer diameter of which is smaller than the outer diameter of the hole opening tool. The front end portion of the main body has a cutting blade whose tip tapers toward the front end side. The rear end portion of the main body has a cutting blade whose tip tapers toward the rear end side.
3. The processing system according to claim 1 or 2, wherein: The first driving mechanism has a power source for self-rotation for rotating the drilling tool. The measuring unit obtains the electric quantity of the power source for the rotation, The control unit changes the rotation speed of the power source for autorotation based on the difference between the first electric quantity and the second electric quantity, The first electric quantity is an electric quantity obtained by the measuring unit during the rotation of the power source for rotation and before the workpiece is processed. The second electrical quantity is an electrical quantity acquired by the measuring unit during the hole drilling process of the workpiece.
4. The processing system according to claim 3, wherein: The first electric quantity and the second electric quantity are at least one of a magnitude, a differential value, and an integral value of a load current of the power source for the autorotation.
5. The processing system according to claim 3, wherein: The control unit sets the rotation speed of the power source for autorotation to zero when the difference is equal to or smaller than a threshold value.
6. A method for manufacturing a metal part, comprising the following steps: preparing a workpiece composed of a metal component; Performing hole drilling on the workpiece using a drilling tool actuated by a first driving mechanism; and The workpiece is chamfered by cutting using a chamfering tool actuated by a second drive mechanism, The object to be cut has: a first plate portion having a first surface and a first back surface; a second plate portion having a second surface and a second back surface; and a foot portion that fixes the first plate portion and the second plate portion in a manner that the first back surface and the second back surface face each other with a gap therebetween, The step of performing the hole forming process includes the step of coaxially forming a first hole portion penetrating the first surface and the first back surface and a second hole portion provided in the second plate portion in sequence, The first hole portion is a hole portion having a first opening edge portion provided on the front side of the first surface and a first opening edge portion provided on the back side of the first back surface, The second hole portion is a hole portion having at least a second opening edge portion provided on the back side of the second back surface, The method for manufacturing the metal component further comprises the following steps: Acquiring, by a measuring unit, a first physical quantity and a second physical quantity related to control of the first driving mechanism; and Based on the first physical quantity and the second physical quantity, the position of at least one of the first opening edge on the front side and the first opening edge on the back side and the position of the second opening edge on the back side are obtained, The first physical quantity is the feed speed of the drilling tool, The second physical quantity is a first time from the start of the hole-forming process of the first plate portion to the start of the hole-forming process of the second plate portion. The chamfering step is based on the position of the first opening edge of the at least one and the position of the second opening edge of the back side, providing a first chamfered portion at the first opening edge of the at least one and providing a second chamfered portion on the back side at the second opening edge of the back side, The position of the first opening edge of the at least one and the position of the second opening edge of the back side are obtained based on the length of the first hole along the axial direction and the length between the first plate portion and the second plate portion. The length of the first hole portion in the axial direction and the length between the first plate portion and the second plate portion are obtained based on the feed speed and the first time.
7. The method for manufacturing a metal component according to claim 6, wherein: In the step of providing the chamfered portion, the second drive mechanism is operated so that the chamfered lengths of the first chamfered portion and the second chamfered portion are smaller than a dimensional tolerance of a length between the first plate portion and the second plate portion.