Dual-source integrated water source heat pump fresh air unit for data center
By designing a dual-source integrated water source heat pump fresh air unit in the data room, the problems of low space utilization and safety hazards of traditional systems are solved, efficient air filtration and temperature control are achieved, and the temperature and humidity requirements of the data room are met, reducing the temperature and humidity requirements of the data room. The noise and consumables are used to improve the unit's thermal insulation effect and hardness.
Patent Information
- Application Number
- CN202111547795.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-16
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2041-12-16
AI Technical Summary
Traditional data room cooling systems have problems such as low space utilization, large construction volume, high safety hazards, and the need for additional fresh air systems.
A special dual source integrated water source heat pump fresh air unit for data room is designed. The inner cavity of the box is separated by a partition, including a purification chamber, a temperature control chamber and an electrical chamber. It adopts a multi-stage filtration and temperature control and humidity regulating mechanism, and uses a water source heat pump. The module and the inverter realize the integration of fresh air, temperature control and humidity control, reducing the connection between refrigerant pipes, and only the air duct and power cord can operate efficiently.
It realizes efficient air filtration, cooling and temperature control, reduces noise and consumables, improves the unit's thermal insulation effect and hardness, meets the temperature and humidity requirements of the data room, and saves energy and is efficient.
Smart Images

Figure CN114423224B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of cooling down a data room, and in particular to a dual-source integrated water source heat pump fresh air unit dedicated to a data room. Background Art
[0002] With the rapid development of society, the now popular big data has penetrated into applications in all walks of life. "In the era of big data, relevant algorithms are used to process, analyze and store massive amounts of data, discover value from massive amounts of data, and serve life and production. The impact of big data on all walks of life can be felt in the fields of catering, telecommunications, finance, entertainment, sports, etc. Therefore, various places are building or renovating data rooms to meet the needs of reliable operation of servers. Servers will generate a lot of load heat during a large amount of computing and processing, and need to be cooled, otherwise the server will be paralyzed. Traditional data room cooling adopts a decentralized air-conditioning system. The air handling part is mainly a cabinet air-conditioning, and the host and air are connected by chilled water access or refrigerant pipe access. Processing unit. However, placing the air handling unit inside the computer room leads to a decrease in the utilization rate of the computer room space, a decrease in the number of servers placed, and an increase in the amount of engineering construction due to the connection of a large number of water pipes or copper pipes; the leakage of chilled water or Freon pipelines also leads to a relatively large safety hazard in operation; and the daily maintenance work is also quite huge. The latest data room construction requires the configuration of an appropriate amount of fresh air to meet the needs of personnel work, so an additional fresh air system (fresh air host + air duct + fresh air control unit) is required, resulting in a relatively scattered layout of air conditioning equipment. For this reason, we propose a dual-source integrated water source heat pump fresh air unit dedicated to the data room to solve the above problems. Summary of the invention
[0003] The purpose of the present invention is to provide a dual-source integrated water source heat pump fresh air unit dedicated to a data center to solve the problems raised in the above-mentioned background technology.
[0004] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a dual-source integrated water source heat pump fresh air unit dedicated to a data room, comprising a box body, the inner cavity of the box body is divided into a purification chamber, a temperature control chamber and an electrical chamber in sequence by a partition, the bottoms of the purification chamber and the temperature control chamber are connected, an air inlet is provided on the box body at the top of the purification chamber, an air supply outlet is provided on the box body at the top of the temperature control chamber, a purification mechanism is installed in the purification chamber, a temperature control and humidity regulating mechanism is installed in the temperature control chamber, and a blower is installed in the inner cavity of the purification chamber near the air supply outlet.
[0005] In a preferred implementation case, the purification mechanism includes a primary pre-filter, which is fixedly installed at one end of the air inlet away from the purification chamber, a medium-efficiency filter is fixedly installed in the middle of the inner cavity of the purification chamber, and a secondary filter is fixedly installed in the purification chamber between the medium-efficiency filter and the air inlet.
[0006] In a preferred implementation example, an electric regulating valve is fixedly installed in the air inlet, the primary pre-filter and the secondary filter are metal filter structures with gradually decreasing pore sizes, and the medium-efficiency filter is an F8-level bag filter.
[0007] In a preferred implementation case, a water source heat pump module is fixedly installed at the bottom of the inner cavity of the electrical cavity, the water source heat pump module is connected to a compressor, a control box is fixedly installed in the middle of the inner cavity of the electrical cavity, and the compressor and the air blower are both connected to a frequency converter.
[0008] In a preferred implementation case, a vent is opened on the partition between the bottom of the purification chamber and the temperature control chamber, and inspection doors are installed on the boxes on one side of the purification chamber, the temperature control chamber and the electrical chamber. The box is made of polyurethane foam in the middle of a double metal plate.
[0009] In a preferred implementation case, the temperature and humidity control mechanism includes a pre-cooling water coil and a direct expansion coil. The pre-cooling water coil is fixedly installed at the bottom of the temperature control chamber close to the purification chamber, the direct expansion coil is fixedly installed in the temperature control chamber on the top of the pre-cooling water coil, and the condensing reheat coil and the auxiliary heater are fixedly installed in the temperature control chamber between the direct expansion coil and the air supply fan in sequence.
[0010] In a preferred implementation case, the precooling water coil and the direct expansion coil are both installed at an angle, and the precooling water coil and the direct expansion coil are in contact with the bottom inner wall of the temperature control chamber on one side close to the purification chamber, and a condensate tray is fixedly installed on the bottom plate of the temperature control chamber at the bottom of the precooling water coil.
[0011] In a preferred implementation case, the side wall of the temperature control chamber is fixedly sleeved with a cooling water supply and return pipe, a condensing water pipe and a chilled water supply and return pipe, the cooling water supply and return pipe is connected to a pre-cooling water coil, the chilled water supply and return pipe is connected to a direct expansion coil, and the condensing water pipe runs through a condensate tray.
[0012] In a preferred implementation example, the condensing reheat coil is connected to the water source heat pump module and the compressor, and the auxiliary heater is an electric auxiliary heater.
[0013] In a preferred implementation case, the condensing reheat coil and the precooling water coil are both of an upper-in and lower-out type structure, including a bracket, the bracket is fixedly connected to the inner wall of the temperature control chamber by bolts, a water inlet concentrating pipe and a water outlet concentrating pipe are fixedly installed between the brackets, a plurality of heat exchange tubes are fixedly installed between the water inlet concentrating pipe and the water outlet concentrating pipe, a balancing angle valve is fixedly installed on one end of the heat exchange tube close to the water inlet concentrating pipe, a water inlet interface is fixedly installed on one end of the water inlet concentrating pipe, and a water outlet interface is fixedly installed on the end of the water outlet concentrating pipe away from the water inlet interface.
[0014] The beneficial effects of the present invention are:
[0015] 1. The blower works to draw outside air into the purification chamber through the air inlet, and the inhaled air is filtered and purified multiple times through the primary pre-filter, secondary filter and medium-efficiency filter to meet the fresh air standard. The air then flows through the pre-cooling water coil for cooling, and then flows through the direct expansion coil for secondary cooling, so that the water vapor in the air reaches the dew point and condenses and falls into the condensate water tray to achieve dehumidification. The condensed and cooled air then flows through the condensation reheat coil for heating, and finally the auxiliary heater is used for heating fine-tuning, so as to accurately control the air supply temperature. The air is then drawn out by the blower from the air outlet into each machine room that needs to be cooled. The indoor and outdoor parts are integrated structures, and no refrigerant pipe connection is required. Only the air duct and power cord need to be connected to operate efficiently, which is energy-saving and efficient.
[0016] 2. Refrigeration uses high-temperature water to cool down once to meet the temperature requirements in the data room. It cools down to the dew point temperature through direct evaporation, and then starts heating again through condensation to achieve the dehumidification effect. Then, the auxiliary heater ratio is adjusted to play a fine-tuning role to meet the temperature and humidity requirements in the data room. It is easy to use;
[0017] 3. The frequency conversion control fan controls the air supply volume, controls the positive pressure in the data center to be between 5-10Pa, and can accurately control the air supply temperature within ±1℃ by adjusting the compressor frequency, so as to achieve energy-saving control of the temperature and humidity in the data center;
[0018] 4. The box body is made of double metal plate with polyurethane foam in the middle. The sheet metal structure is made of double metal plate with polyurethane foam in the middle, which makes the heat insulation effect of the unit better. The noise of the unit is reduced by 3-4dB(A) compared with the traditional steel plate plus PE insulation cotton. At the same time, the hardness is greatly enhanced and the corresponding plate can be thinned, which not only improves the strength but also reduces consumables. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 A schematic structural diagram of a dual-source integrated water source heat pump fresh air unit dedicated to a data center provided in an embodiment of the present invention.
[0020] Figure 2 It is a schematic diagram of the top structure of the present invention.
[0021] Figure 3 For the present invention Figure 1 Enlarged structural diagram at A in the middle.
[0022] In the figure: 1. Primary pre-filter; 2. Electric regulating valve; 3. Secondary filter; 4. Medium efficiency filter; 5. Pre-cooling water coil; 6. Direct expansion coil; 7. Condensate pan; 8. Condensation reheat coil; 9. Auxiliary heater; 10. Blower; 11. Air supply port; 12. Control box; 13. Box body; 14. Water source heat pump module; 15. Compressor; 16. Cooling water supply and return pipe; 17. Condensate pipe; 18. Chilled water supply and return pipe; 19. Purification chamber; 20. Temperature control chamber; 21. Electrical chamber; 22. Air inlet; 23. Inspection door; 24. Bracket; 25. Water inlet central pipe; 26. Water outlet central pipe; 27. Heat exchange pipe; 28. Water inlet interface; 29. Water outlet interface. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] Example: Figures 1 to 3 As shown, the present invention provides a dual-source integrated water source heat pump fresh air unit dedicated to a data room, comprising a box body 13, the inner cavity of the box body 13 is divided into a purification chamber 19, a temperature control chamber 20 and an electrical chamber 21 in sequence by a partition, the purification chamber 19 and the temperature control chamber 20 are connected at the bottom, an air inlet 22 is opened on the box body 13 at the top of the purification chamber 19, an air supply port 11 is opened on the box body 13 at the top of the temperature control chamber 20, a purification mechanism is installed in the purification chamber 19, a temperature control and humidity regulating mechanism is installed in the temperature control chamber 20, and a blower 10 is installed in the inner cavity of the purification chamber 19 near the air supply port 11. The blower 10 works to draw outside air into the purification chamber 19 through the air inlet 22, filter and purify the air through the purification mechanism, and then cool and control the temperature through the temperature and humidity control mechanism, and finally send it into the machine room from the air outlet 11, realizing the integrated design of fresh air, temperature and humidity control, reducing the size of the device, and integrating the indoor and outdoor structures. There is no need to connect the refrigerant pipe, and only the air duct and the power cord need to be connected to operate efficiently, which is energy-saving and efficient.
[0025] The purification mechanism includes a primary pre-filter 1, which is fixedly installed at one end of the air inlet 22 away from the purification chamber 19, a medium-efficiency filter 4 is fixedly installed in the middle of the inner cavity of the purification chamber 19, and a secondary filter 3 is fixedly installed in the purification chamber 19 between the medium-efficiency filter 4 and the air inlet. The inhaled air is filtered and purified multiple times by the primary pre-filter 1, the secondary filter 3 and the medium-efficiency filter 4 to meet the fresh air standard.
[0026] An electric regulating valve 2 is fixedly installed in the air inlet 22 to control the ventilation flow rate. The primary pre-filter 1 and the secondary filter 3 are metal filter structures with gradually decreasing apertures, and the medium-efficiency filter 4 is an F8-level bag filter.
[0027] A water source heat pump module 14 is fixedly installed at the bottom of the inner cavity of the electrical cavity 21, and the water source heat pump module 14 is connected to a compressor 15. A control box 12 is fixedly installed in the middle of the inner cavity of the electrical cavity 21. The compressor 15 and the air blower 10 are both connected to a frequency converter. The frequency converter controls the air supply fan 10 to control the air supply volume, and the air supply temperature can be accurately controlled within ±1°C by adjusting the frequency of the compressor 15, thereby ensuring temperature control and being more energy-efficient.
[0028] A vent is provided on the partition between the bottom of the purification chamber 19 and the temperature control chamber 20. Inspection doors 23 are installed on the box 13 on one side of the purification chamber 19, the temperature control chamber 20 and the electrical chamber 21. The box 13 is made of polyurethane foam in the middle of a bimetallic plate. The sheet metal structure is made of polyurethane foam in the middle of a bimetallic plate, which makes the heat insulation effect of the unit better. The noise of the unit is reduced by 3 to 4 dB (A) compared with the traditional steel plate plus PE insulation cotton. At the same time, the hardness is greatly enhanced and the corresponding plate can be thinned, which not only improves the strength but also reduces consumables.
[0029] The temperature control and humidity regulating mechanism includes a precooling water coil 5 and a direct expansion coil 6. The precooling water coil 5 is fixedly installed at the bottom of the temperature control chamber 20 close to the purification chamber 19. The direct expansion coil 6 is fixedly installed in the temperature control chamber 20 at the top of the precooling water coil 5. The condensation reheat coil 8 and the auxiliary heater 9 are fixedly installed in the temperature control chamber 20 between the direct expansion coil 6 and the blower 10 in sequence. The precooling water coil 5 and the direct expansion coil 6 are both installed obliquely, and the precooling water coil 5 and the direct expansion coil 6 are attached to the bottom inner wall of the temperature control chamber 20 close to the purification chamber 19. The condensation water pan 7 is fixedly installed on the bottom plate of the temperature control chamber 20 at the bottom of the precooling water coil 5. The side wall of the temperature control chamber 20 is fixedly sleeved with cooling water. The cooling water supply and return pipe 16, the condensing water pipe 17 and the chilled water supply and return pipe 18, the cooling water supply and return pipe 16 is connected to the pre-cooling water coil 5, the chilled water supply and return pipe 18 is connected to the direct expansion coil 6, and the condensing water pipe 17 runs through the condensate pan 7. The air first flows through the pre-cooling water coil 5 for cooling, and then flows through the direct expansion coil 6 for secondary cooling, so that the water vapor in the air reaches the dew point and condenses and falls into the condensate pan 7 to achieve dehumidification. The condensed and cooled air then flows through the condensation reheat coil 8 for heating, and finally is heated and fine-tuned by the auxiliary heater 9, so as to accurately control the supply air temperature. The air is then drawn out by the blower 10 and enters the various machine rooms that need to be cooled from the air supply port 11.
[0030] The condensing reheat coil 8 is connected to the water source heat pump module 14 and the compressor 15, and the auxiliary heater 9 is an electric auxiliary heater.
[0031] The condensing reheat coil 8 and the precooling water coil 5 are both of the upper-in and lower-out type structures, including a bracket 24, which is fixedly connected to the inner wall of the temperature control chamber 20 by bolts, and a water inlet concentrated pipe 25 and a water outlet concentrated pipe 26 are fixedly installed between the brackets 24, and a plurality of heat exchange tubes 27 are fixedly installed between the water inlet concentrated pipe 25 and the water outlet concentrated pipe 26. A balancing angle valve is fixedly installed on one end of the heat exchange tube 27 close to the water inlet concentrated pipe 25, and a water inlet interface 28 is fixedly installed on one end of the water inlet concentrated pipe 25, and a water outlet interface 29 is fixedly installed on the end of the water outlet concentrated pipe 26 away from the water inlet interface 28. The cooling water and the hot water provided by the heat source pump enter the precooling water coil 5 and the condensing reheat coil 8 respectively through the water inlet interface 28, and are evenly distributed to the plurality of heat exchange tubes 27 through the water inlet concentrated pipe 25, and contact with the air through the heat exchange tubes 27, so as to achieve the purpose of heat exchange and temperature control, and finally are concentrated through the water outlet concentrated pipe 26 and discharged through the water outlet interface 29.
[0032] When in use, the blower 10 works to draw outside air into the purification chamber 19 through the air inlet 22, and the inhaled air is filtered and purified multiple times by the primary pre-filter 1, the secondary filter 3 and the medium-efficiency filter 4 to meet the fresh air standard. Then the cooling water supply and return pipe 16 is connected to the pre-cooling water coil 5, the chilled water supply and return pipe 18 is connected to the direct expansion coil 6, and the condensation reheat coil 8 is connected to the water source heat pump module 14. The air first flows through the pre-cooling water coil 5 for cooling, and then flows through the direct expansion coil 6 for secondary cooling, so that the water vapor in the air reaches the dew point and condenses and falls into the condensation water tray 7 to achieve dehumidification. Then the condensed and cooled air flows through the condensation reheat The coil 8 is heated and finally heated and fine-tuned by the auxiliary heater 9, so as to accurately control the supply air temperature. The air is then drawn by the blower 10 and enters the air outlet 11 into each computer room that needs to be cooled. The indoor and outdoor parts are integrated structures, and there is no need to connect refrigerant pipes. Only the air duct and power cord need to be connected to operate efficiently, which is energy-saving and efficient. The refrigeration is cooled once by high-temperature water to meet the temperature requirements in the data room. The dehumidification effect is achieved by directly evaporating and cooling to the dew point temperature, condensing and then starting to heat up. The auxiliary heater 9 is then used for ratio adjustment to play a fine-tuning role to meet the temperature and humidity requirements in the data room. It is easy to use.
[0033] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A dual-source integrated water source heat pump fresh air unit for a data center, comprising a box (13), characterized in that: The box The inner cavity of the air conditioner (13) is divided into a purification cavity (19), a temperature control cavity (20) and an electrical cavity (21) in sequence by a partition, the purification cavity (19) and the temperature control cavity (20) are connected at the bottom, an air inlet (22) is opened on the box body (13) at the top of the purification cavity (19), and an air supply port (11) is opened on the box body (13) at the top of the temperature control cavity (20), a purification mechanism is installed in the purification cavity (19), a temperature control and humidity adjustment mechanism is installed in the temperature control cavity (20), and a blower (10) is installed in the inner cavity of the purification cavity (19) near the air supply port (11); The temperature control and humidity regulating mechanism comprises a precooling water coil (5) and a direct expansion coil (6); the precooling water coil (5) is fixedly installed at the bottom of one side of the temperature control chamber (20) close to the purification chamber (19); the direct expansion coil (6) is fixedly installed in the temperature control chamber (20) at the top of the precooling water coil (5); and a condensing reheating coil (8) and an auxiliary heater (9) are fixedly installed in the temperature control chamber (20) between the direct expansion coil (6) and the air blower (10) in sequence; The precooling water coil (5) and the direct expansion coil (6) are both installed at an angle, and the precooling water coil (5) and the direct expansion coil (6) are in contact with the bottom inner wall of the temperature control chamber (20) on one side close to the purification chamber (19), and a condensate tray (7) is fixedly installed on the bottom plate of the temperature control chamber (20) at the bottom of the precooling water coil (5); The side wall of the temperature control chamber (20) is fixedly sleeved with a cooling water supply and return pipe (16), a condensing water pipe (17) and a chilled water supply and return pipe (18); the cooling water supply and return pipe (16) is connected to the pre-cooling water coil (5); the chilled water supply and return pipe (18) is connected to the direct expansion coil (6); and the condensing water pipe (17) passes through the condensate pan (7); The condensing reheating coil (8) is connected to the water source heat pump module (14) and the compressor (15), and the auxiliary heater (9) is an electric auxiliary heater; The condensing reheat coil (8) and the precooling water coil (5) are both of an upper-in-lower-out type structure, comprising a bracket (24), wherein the bracket (24) is fixedly connected to the inner wall of the temperature control chamber (20) by bolts, and an inlet concentrated pipe (25) and an outlet concentrated pipe (26) are fixedly installed between the brackets (24), and a plurality of heat exchange tubes (27) are fixedly installed between the inlet concentrated pipe (25) and the outlet concentrated pipe (26), and a balancing angle valve is fixedly installed at one end of the heat exchange tube (27) close to the inlet concentrated pipe (25), and a water inlet interface (28) is fixedly installed at one end of the inlet concentrated pipe (25), and a water outlet interface (29) is fixedly installed at one end of the outlet concentrated pipe (26) away from the inlet interface (28).
2. The dual-source integrated water source heat pump fresh air unit for data center as claimed in claim 1, characterized in that: The purification mechanism comprises a primary pre-filter (1), wherein the primary pre-filter (1) is fixedly mounted at one end of the air inlet (22) away from the purification chamber (19), a medium-efficiency filter (4) is fixedly mounted in the middle of the inner cavity of the purification chamber (19), and a secondary filter (3) is fixedly mounted in the purification chamber (19) between the medium-efficiency filter (4) and the air inlet.
3. The dual-source integrated water source heat pump fresh air unit for data center as claimed in claim 2, characterized in that: An electric regulating valve (2) is fixedly installed in the air inlet (22); the primary pre-filter (1) and the secondary filter (3) are metal filter structures with gradually decreasing pore sizes; and the medium-efficiency filter (4) is an F8-grade bag filter.
4. The dual-source integrated water source heat pump fresh air unit for data center as claimed in claim 1, characterized in that: A water source heat pump module (14) is fixedly installed at the bottom of the inner cavity of the electrical cavity (21), and the water source heat pump module (14) is connected to a compressor (15). A control box (12) is fixedly installed in the middle of the inner cavity of the electrical cavity (21), and both the compressor (15) and the air blower (10) are connected to a frequency converter.
5. The dual-source integrated water source heat pump fresh air unit for data center as claimed in claim 1, characterized in that: A vent is provided on the partition between the bottom of the purification chamber (19) and the temperature control chamber (20), and an inspection door (23) is installed on the box (13) on one side of the purification chamber (19), the temperature control chamber (20) and the electrical chamber (21). The box (13) is made of a bimetallic plate with polyurethane foam in the middle.