Project node control method, device, equipment, storage medium and program product

By automatically comparing the current and expected progress of the project, combining project requirements and node requirements, a new project node control plan is generated, which solves the problem of low efficiency in project progress management in the existing technology, and achieves efficient and accurate project progress management.

CN114648309BActive Publication Date: 2024-12-03陕西清水川能源股份有限公司
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202210315586.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-28
Publication Date
2024-12-03
Estimated Expiration
2042-03-28

AI Technical Summary

Technical Problem

In the prior art, project progress management is inefficient, and relying on manual management is time-consuming and labor-intensive and error-prone, and it is impossible to effectively deal with situations where project progress and planned progress are inconsistent.

Method used

By obtaining the current progress information of the project, comparing it with the expected progress, and combining the project requirements and node requirements, a new project node control plan is automatically generated to reduce manual intervention and improve the efficiency of plan generation.

Benefits of technology

It realizes automated project node control plan generation, reduces manual operation time and error rate, and improves the efficiency and accuracy of project progress management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114648309B_ABST
    Figure CN114648309B_ABST
Patent Text Reader

Abstract

The present application provides a project node control method, device, equipment, storage medium and program product. The method includes: obtaining project progress description information, the project progress description information includes the current date, the current node name and the current process name, the project includes at least one node, and a node includes at least one process; querying the project requirements and node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan according to the current node name and the current process name; comparing the current date, the current node name, the current process name with the queried project requirements and node requirements to obtain the comparison result; generating a new project node control plan according to the comparison result. It can be seen that the technical solution improves the efficiency of project management.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of project progress management, and in particular to a project node control method, device, equipment, storage medium and program product. Background Art

[0002] The timely completion of a project may be related to the progress of other projects of the enterprise, and may also be related to the enterprise's cost accounting, development prospects, etc. Therefore, the timely completion of a project is crucial to the enterprise.

[0003] Enterprise project progress management is the key to the timely completion of enterprise projects. Currently, enterprises generally manage project progress manually, changing the project schedule according to personal experience as the project progresses. Obviously, manual management of project progress is time-consuming, labor-intensive, and prone to errors, resulting in low efficiency in current project progress management. Summary of the invention

[0004] The present application provides a project node control method, device, equipment, storage medium and program product to solve the problem of low project management efficiency in the prior art.

[0005] In a first aspect, the present application provides a project node control method, comprising:

[0006] Obtaining project progress description information, which includes the current date, the current node name, and the current process name. A project includes at least one node, and a node includes at least one process.

[0007] According to the current node name and the current process name, query the project requirements and each node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan;

[0008] Compare the current date, current node name, current process name with the queried project requirements and each node requirement to obtain the comparison result;

[0009] Generate a new project node control plan based on the comparison results.

[0010] Optionally, the project requirements include the project cycle, the estimated project start date, the estimated project end date, and whether it can be extended; the node requirements include the node cycle, the estimated node start date, the estimated node end date, the process plan, and whether it can be extended.

[0011] Optionally, after querying the project requirements and node requirements corresponding to the current node name and the current process name from a pre-generated project node control plan according to the current node name and the current process name, the method further includes:

[0012] If the current progress is inconsistent with the expected progress in the project node control plan, determine to generate a new project node control plan.

[0013] Optionally, a new project node control plan is generated based on the comparison results, including:

[0014] Determine schedule solutions based on current dates, project requirements, and milestone requirements;

[0015] Generate a new project node control plan based on the schedule solution.

[0016] Optionally, generate a new project node control plan based on the schedule solution, including:

[0017] Adjust the original project node control plan based on the progress solution to obtain a new project node control plan.

[0018] Optionally, adjust the original project node control plan based on the progress solution, including:

[0019] The completion information of the project and each node before the current time will be recorded in the project node control plan; for the project node control plan after the current time, a new project node control plan will be generated based on the current date, current node name, current process name, project requirements and each node requirements.

[0020] In a second aspect, the present application provides a project node control device, comprising:

[0021] An acquisition module is used to acquire project progress description information, where the project progress description information includes the current date, the current node name and the current process name. A project includes at least one node, and a node includes at least one process.

[0022] A query module is used to query the project requirements and node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan according to the current node name and the current process name;

[0023] The comparison module is used to compare the current date, the current node name, the current process name with the queried project requirements and the requirements of each node to obtain the comparison results;

[0024] The generation module is used to generate a new project node control plan based on the comparison results.

[0025] In a third aspect, an embodiment of the present application provides a computer device, including:

[0026] One or more processors;

[0027] A memory for storing one or more programs;

[0028] When one or more programs are executed by one or more processors, the one or more processors are enabled to execute the method for implementing the above-mentioned first aspect.

[0029] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium on which a computer program is stored, and the computer program is used to implement the method of the first aspect above.

[0030] In a fifth aspect, an embodiment of the present application provides a computer program product, including a computer program, which implements the method of the first aspect when executed by a processor.

[0031] From the above content, it can be seen that the project node control method shown in the embodiment of the present application obtains the current progress of the project, compares the current progress with the expected progress, and combines the project requirements and the requirements of each node included in the project to generate a new project node control plan. Compared with the prior art, project node control plans are manually formulated, and each time the project progress is different from the planned progress, a new project node control plan needs to be manually formulated; the embodiment of the present application can automatically generate a new project node control plan according to the current progress of the project and the original project node control plan, saving time and effort and improving the efficiency of generating project node control plans. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0033] Figure 1 A diagram of an implementation environment of a project node control method provided in one embodiment of the present application;

[0034] Figure 2 A flow chart of a project node control method provided in one embodiment of the present application;

[0035] Figure 3 A flow chart of a project node control method provided by another embodiment of the present application;

[0036] Figure 4 A flow chart of a method for generating a graph project node control plan provided in one embodiment of the present application;

[0037] Figure 5 A schematic diagram of the structure of a project node control device provided in one embodiment of the present application;

[0038] Figure 6A schematic diagram of the structure of a project node control device provided in another embodiment of the present application;

[0039] Figure 7 It is a structural diagram of a computer system according to an embodiment of the present application. DETAILED DESCRIPTION

[0040] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application is clearly and completely described below. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work also belong to the scope of protection of the present application. In addition, it should be noted that the embodiments in the present application and the features in the embodiments can be combined with each other in the absence of conflict. The present application will be described in detail below with reference to the drawings and in combination with the embodiments.

[0041] Figure 1 1 is an implementation environment architecture diagram of a project node control method according to an embodiment of the present application. Figure 1 As shown, the implementation environment architecture includes: a terminal 101 and a server 102 .

[0042] The hardware structure of the terminal 101 includes a processor, a memory and a display device, and the software structure includes a client of an application installed on the terminal 101. For example, a project node control client. When the application client is started, the terminal 101 may display an application interface, through which information input by the user may be obtained, such as a description of the current progress of the project, and the information input by the user may be sent to the server 102, or the terminal 101 may also be used to display one or more messages sent by the server 102.

[0043] The types of terminal 101 include, but are not limited to, smart phones, tablet computers, televisions, laptop computers, desktop computers, etc., and the embodiments of the present application do not specifically limit this.

[0044] The server 102 is used to store project information, such as historical project node control plans, and is also used to receive data requests sent by the terminal 101 , obtain corresponding data according to the data request, and then return the data to the terminal 101 .

[0045] The server 102 may be a single server, or a server cluster consisting of multiple servers, or a cloud computing service center.

[0046] The terminal 101 establishes a communication connection with the server 102 via a wired or wireless network.

[0047] Figure 2It is a flowchart of a project node control method according to an embodiment of the present application. Figure 2 The method shown can be Figure 1 The terminal 101 in the embodiment executes, Figure 2 As shown, the method comprises the following steps:

[0048] Step 201, obtaining project progress description information, the project progress description information includes the current date, the current node name and the current process name.

[0049] Among them, a project includes at least one node, a node is a subtask included in the project, and a node corresponds to at least one process.

[0050] Furthermore, each node name included in a project and the process name corresponding to each node name are all set in advance and stored in the terminal 101 or in the server 102 .

[0051] For example, taking the outsourced project B of Group A as an example, Project B includes 6 nodes, namely the project establishment node, the procurement application node, the procurement result approval node, the bidding node, the contract approval node, and the project implementation and acceptance node.

[0052] Furthermore, taking the bidding node as an example, the bidding node includes the following processes: registration, approval by the bidding leadership group, request from the bidding company, release of the bidding notice, and issuance of the winning notice.

[0053] Further, taking the project implementation and acceptance node as an example, the project implementation and acceptance node includes the following processes: contract signing, determination of the director of the demand department, project start, project completion, first review by the director of the demand department, first review by the director of the responsible department, completion acceptance (general level, key level, limited to upper level), second review by the director of the demand department, second review by the director of the responsible department, settlement registration and financial pre-transfer, review by the director of the enterprise management department, final audit registration, and review by the finance department. Further, assuming that the project is a limited upper level project, the implementation and acceptance node can also include the following processes: group completion acceptance, group audit acceptance, evaluation registration, and review by the biotechnology department.

[0054] In addition, it should be noted that the execution order of the above nodes and processes is not the same as the order of the above description. The specific execution order is subject to the actual operation and is not described here.

[0055] The project progress description information is used to describe the current progress of the project, for example, which node the project has progressed to and which process has progressed to that node.

[0056] For example, taking Project C as an example, the progress description information of Project C includes: the current date is January 3, 2022, the current node name is Node 2, and the current process name is Process N.

[0057] Optionally, the project progress description information may be input into the terminal 101 by the user through a user interface, and the terminal 101 receives and stores the project progress description information.

[0058] Step 202 , query the project requirements and node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan according to the current node name and the current process name.

[0059] Among them, the project node control plan includes the project name and project requirements. Further project requirements include the project cycle, the estimated start date of the project, the estimated end date of the project, and whether the project can be extended.

[0060] Among them, the project node control plan also includes the names of each node corresponding to the project and the requirements of each node. Furthermore, the requirements of each node include the cycle of each node, the expected start date of each node, the expected end date of each node, the process plan of each node and whether the node can be postponed.

[0061] Project requirements and node requirements may also include other information based on the actual situation of the project, and the embodiments of the present application are not limited to this.

[0062] Whether the project can be extended refers to whether the cycle for completing the entire project can be extended, and whether the node can be extended refers to whether the cycle for completing the single node can be extended.

[0063] Furthermore, the initial project node control plan for the project is made based on the initial project requirements and the requirements of each node.

[0064] Exemplarily, still taking Project C as an example, the project node control plans generated in advance are as shown in Tables 1 and 2 below.

[0065] Table 1

[0066]

[0067] Table 2

[0068]

[0069] Step 203 , compare the current date, the current node name, the current process name with the queried project requirements and the requirements of each node to obtain a comparison result.

[0070] During the project, it is very likely that the current progress is inconsistent with the progress of the project node control plan generated in advance due to some reasons, for example, the current progress lags behind the planned progress, or the current progress lags behind the planned progress. Therefore, it is necessary to compare the current progress of the project with the project node control plan generated in advance, and regenerate the project node control plan based on the comparison results.

[0071] Step 204, generating a new project node control plan based on the comparison results.

[0072] When the comparison result shows that the current progress lags behind the previous project node control plan, it is necessary to adjust the period, estimated start time and estimated end time of the later nodes according to the project requirements and node requirements. For example, when the overall project cycle does not allow for extension, it is necessary to speed up the progress of the nodes included in the later stage.

[0073] When the comparison result shows that the current progress is faster than the project node control plan, the cycle of each subsequent node will not be changed, only the expected start date and the expected end date will be adjusted as a whole. For example, when the current progress is 3 days faster than the project node control plan, the expected start date and the expected end date can be adjusted forward by 3 days as a whole.

[0074] Furthermore, when generating a new project node control plan, the completion status of the project and each node of the project before the current time will be recorded in the new project node control plan; for the project node control plan after the current time, it will be generated based on the current date, current node name, current process name, project expected completion date, project requirements, expected completion date of each node and requirements of each node to obtain a new project node control plan.

[0075] From the above content, it can be seen that the project node control method shown in the embodiment of the present application obtains the current progress of the project, compares the current progress with the expected progress, and combines the project requirements and the requirements of each node included in the project to generate a new project node control plan. Compared with the prior art, project node control plans are manually formulated, and each time the project progress is different from the planned progress, a new project node control plan needs to be manually formulated; the embodiment of the present application can automatically generate a new project node control plan according to the current progress of the project and the original project node control plan, saving time and effort and improving the efficiency of generating project node control plans.

[0076] Alternatively, see Figure 3 After step 203, the project node control method further includes the following steps:

[0077] Step 205: When the comparison result shows that the current progress is inconsistent with the project node control plan, determine to generate a new project node control plan.

[0078] Optionally, the current date, current node name, current process name, current node name and current process name are compared with the project node control plan generated in advance to determine whether the current progress is consistent with the planned progress. If they are consistent, a new project node control plan is not generated. If they are inconsistent, a new project node control plan is generated.

[0079] Alternatively, see Figure 4 , step 204 may include the following two steps:

[0080] Step 2041, determine a schedule solution based on the current date, project requirements and node requirements.

[0081] Optionally, the progress solution includes at least one of the following solutions:

[0082] Increase human resources, increase material resources, extend project cycle, extend human working hours, and extend material working hours.

[0083] For example, still taking the above example, assuming that the current time is January 3, 2022, the current progress of the project is that node 2 is not completed, and the project requirement is that the project cannot be postponed, the requirement for node 1 is that it can be postponed for 1 day, the requirement for node 2 is that it can be postponed for 1 day, and the requirement for node 3 is that it can be postponed for 1 day. Then, according to the above requirements, the new solution generated is to postpone node 2 by 1 day and shorten node 3 by 1 day.

[0084] Step 2042, generating a new project node control plan based on the schedule solution.

[0085] Optionally, step 2042 may be: adjusting the original project node control plan based on the progress solution to obtain a new project node control plan.

[0086] That is, on the basis of the original project node control plan, the content of a project requirement and node requirement that are consistent with the original project node can remain unchanged, and only the different content can be modified to obtain a new project node control plan, thereby reducing the workload and improving the efficiency of generating the project node control plan.

[0087] Exemplarily, still taking the example in step 2041 as an example, after adjusting the above table, a new project node control plan is obtained as shown in Table 3 and Table 4 below.

[0088] Table 3

[0089]

[0090] Table 4

[0091]

[0092] Figure 5 A project node control device according to an embodiment of the present application is shown, such as Figure 5 As shown, the device comprises:

[0093] The acquisition module 501 is used to acquire project progress description information, where the project progress description information includes the current date, the current node name and the current process name. A project includes at least one node, and a node includes at least one process.

[0094] A query module 502 is used to query the project requirements and node requirements corresponding to the current node name and the current process name from a pre-generated project node control plan according to the current node name and the current process name;

[0095] The comparison module 503 is used to compare the current date, the current node name, the current process name with the queried project requirements and each node requirement to obtain a comparison result;

[0096] The generation module 504 is used to generate a new project node control plan according to the comparison results.

[0097] Optionally, the project requirements include the project cycle, the estimated project start date, the estimated project end date, and whether it can be extended; the node requirements include the node cycle, the estimated node start date, the estimated node end date, the process plan, and whether it can be extended.

[0098] Alternatively, see Figure 6 , the project node control device also includes:

[0099] The determination module 505 is used to determine to generate a new project node control plan if the current progress is inconsistent with the estimated progress in the project node control plan.

[0100] Optionally, the generating module 504 is further used for:

[0101] Determine schedule solutions based on current dates, project requirements, and milestone requirements;

[0102] Generate a new project node control plan based on the schedule solution.

[0103] Optionally, the generating module 504 is further used for:

[0104] Adjust the original project node control plan based on the progress solution to obtain a new project node control plan.

[0105] Optionally, the generating module 504 is further used for:

[0106] The completion information of the project and each node before the current time will be recorded in the project node control plan; for the project node control plan after the current time, a new project node control plan will be generated based on the current date, current node name, current process name, project requirements and each node requirements.

[0107] In addition, it should be noted that for the relevant contents in the device embodiment, please refer to the method embodiment and will not be repeated here.

[0108] From the above content, it can be seen that the project node control device shown in the embodiment of the present application obtains the current progress of the project, compares the current progress with the expected progress, and combines the project requirements and the requirements of each node included in the project to generate a new project node control plan. Compared with the prior art, project node control plans are manually formulated, and each time the project progress is different from the planned progress, a new project node control plan needs to be manually formulated; the embodiment of the present application can automatically generate a new project node control plan according to the current progress of the project and the original project node control plan, saving time and effort and improving the efficiency of generating project node control plans.

[0109] Figure 7 700 is a schematic diagram of a computer system 700 according to an embodiment of the present application. The computer system includes a central processing unit (CPU) 701, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 702 or a program loaded from a storage portion to a random access memory (RAM) 703. In RAM 703, various programs and data required for system operation are also stored. CPU 701, ROM 702, and RAM 703 are connected to each other via a bus 704. An input / output (I / O) interface 705 is also connected to bus 704.

[0110] The following components are connected to the I / O interface 705: an input section 706 including a keyboard, a mouse, etc.; an output section including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 708 including a hard disk, etc.; and a communication section 709 including a network interface card such as a LAN card, a modem, etc. The communication section 709 performs communication processing via a network such as the Internet. A drive is also connected to the I / O interface 705 as needed. A removable medium 711, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 710 as needed, so that a computer program read therefrom is installed into the storage section 708 as needed.

[0111] In particular, the process described in each flowchart according to the embodiment of the present application can be implemented as a computer software program. For example, each method embodiment of the present application includes a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from the network through a communication part, and / or installed from a removable medium. When the computer program is executed by a central processing unit (CPU) 701, the above-mentioned functions defined in the system of the present application are executed.

[0112] It should be noted that the computer-readable medium shown in the present application may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, device or device. In the present application, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than computer-readable storage media, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wire, optical cable, RF, etc., or any suitable combination of the above.

[0113] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present application. In this regard, each box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the above-mentioned module, program segment or a part of a code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram or flow chart, and the combination of the boxes in the block diagram or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0114] The units involved in the embodiments described in the present application may be implemented by software or hardware, and the units described may also be set in a processor. The names of these units do not constitute limitations on the units themselves in some cases. The units or modules described may also be set in a processor, for example, may be described as: a processor includes an acquisition module 501, a query module 502, a comparison module 503, and a generation module 504. The names of these units or modules do not constitute limitations on the units or modules themselves in some cases.

[0115] As another aspect, the present application also provides a computer-readable medium, which may be included in the electronic device described in the above embodiment; or may exist independently without being assembled into the electronic device. The above computer-readable medium carries one or more programs, and when the above one or more programs are executed by an electronic device, the electronic device implements the project node control method described in the above embodiment.

[0116] For example, the electronic device may implement Figure 1 As shown in: Step 201, obtain project progress description information, the project progress description information includes the current date, the current node name and the current process name, the project includes at least one node, and a node includes at least one process; Step 202, query the project requirements and each node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan according to the current node name and the current process name; Step 203, compare the current date, the current node name, the current process name with the queried project requirements and each node requirements to obtain a comparison result; Step 204, generate a new project node control plan according to the comparison result.

[0117] To summarize, the project node control computer system, computer-readable storage medium, and computer program product provided in the embodiments of the present application obtain the current progress of the project, compare the current progress with the expected progress, and combine the project requirements and the requirements of each node included in the project to generate a new project node control plan. Compared with the prior art, which manually formulates the project node control plan and needs to manually formulate a new project node control plan each time the project progress is different from the planned progress, the embodiments of the present application can automatically generate a new project node control plan based on the current progress of the project and the original project node control plan, saving time and effort and improving the efficiency of generating the project node control plan.

[0118] Finally, it should be noted that all contents not described in the technical solution of this application can be implemented using existing technologies. In addition, the above embodiments are only used to illustrate the technical solution of this application, rather than to limit it; although the application is described in detail with reference to the above embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the above embodiments, or replace some or all of the technical features therein with equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of this application.

Claims

1. A project node control method, characterized in that: include: Acquire project progress description information, wherein the project progress description information includes a current date, a current node name, and a current process name, wherein the project includes at least one node, and the node includes at least one process; According to the current node name and the current process name, query the project requirements and each node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan; Compare the current date, the current node name, and the current process name with the queried project requirements and the node requirements to obtain a comparison result; the project nodes include project establishment nodes, procurement application nodes, procurement result approval nodes, bidding nodes, contract approval nodes, and project implementation and acceptance nodes; the project requirements include project cycle, project estimated start date, project estimated end date, and whether it can be extended; the node requirements include node cycle, node estimated start date, node estimated end date, process plan, and whether it can be extended; Generate a new project node control plan according to the comparison results; Generating a new project node control plan according to the comparison result includes: Determine a schedule solution based on the current date, the project requirements, and the node requirements; A new project node control plan is generated based on the schedule solution.

2. The project node control method according to claim 1, characterized in that: After querying the project requirements and node requirements corresponding to the current node name and the current process name from the pre-generated project node control plan according to the current node name and the current process name, the method further includes: If the current progress is inconsistent with the estimated progress in the project node control plan, determine to generate a new project node control plan.

3. The project node control method according to claim 1, characterized in that: The generating a new project node control plan based on the progress solution includes: The original project node control plan is adjusted based on the progress solution to obtain a new project node control plan.

4. The project node control method according to claim 1, characterized in that: The adjusting the original project node control plan based on the progress solution includes: The completion information of the project and each node before the current time shall be recorded in the project node control plan; for the project node control plan after the current time, a new project node control plan shall be generated according to the current date, the current node name, the current process name, the project requirements and the requirements of each node.

5. A project node control device, characterized in that: include: An acquisition module, used to acquire project progress description information, wherein the project progress description information includes a current date, a current node name, and a current process name, wherein the project includes at least one node, and the node includes at least one process; A query module, used for querying the project requirements and node requirements corresponding to the current node name and the current process name from a pre-generated project node control plan according to the current node name and the current process name; A comparison module is used to compare the current date, the current node name, and the current process name with the queried project requirements and the requirements of each node to obtain a comparison result; the project nodes include project establishment nodes, procurement application nodes, procurement result approval nodes, bidding nodes, contract approval nodes, and project implementation and acceptance nodes; the project requirements include project cycle, project estimated start date, project estimated end date, and whether it can be extended; the node requirements include node cycle, node estimated start date, node estimated end date, process plan, and whether it can be extended; A generation module, used to generate a new project node control plan according to the comparison result; Generating a new project node control plan according to the comparison result includes: Determine a schedule solution based on the current date, the project requirements, and the node requirements; A new project node control plan is generated based on the schedule solution.

6. An electronic device, characterized in that: The device comprises: One or more processors; A memory for storing one or more programs; When the one or more programs are executed by the one or more processors, the one or more processors implement the method according to any one of claims 1 to 4.

7. A computer-readable storage medium, characterized in that: A computer program is stored thereon, the computer program being used to: When the computer program is executed by a processor, the method according to any one of claims 1 to 4 is implemented.

8. A computer program product, comprising a computer program, wherein when the computer program is executed by a processor, the method according to any one of claims 1 to 4 is implemented.