An assembled elevator prefabricated component and its construction method
Through prefabricated elevator prefabricated components and post-casting technology, the long construction cycle of cast-in-place concrete structures and disturbing the public are solved, and rapid installation and efficient construction are achieved.
Patent Information
- Application Number
- CN202210628609.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-06
- Publication Date
- 2025-06-27
- Estimated Expiration
- 2042-06-06
AI Technical Summary
When installing elevators in old communities, the construction period of cast-in-place concrete structures is long, the project volume is large, and the process is complex, which seriously affects residents' lives and leads to obstruction of elevator installation.
Prefabricated elevator prefabricated components are adopted, including prefabricated rafts, prefabricated well walls, prefabricated corridor columns and prefabricated roof panels. The assembly is completed in the factory through post-pouring technology and is quickly installed on site to form a prefabricated elevator structure.
This greatly shortens the construction period, reduces the amount of wet work on site, improves construction efficiency, and reduces disturbances to the public.
Smart Images

Figure CN114809526B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and particularly relates to a prefabricated elevator precast component and a construction method thereof. Background Art
[0002] Foundation engineering is one of the leading projects in building construction. The quality of the foundation engineering construction directly affects the safety of the superstructure.
[0003] For the elevators retrofitted in old communities, the well foundation basically adopts a cast-in-place concrete structure at present. During the construction process, a series of problems such as traffic, fire protection, nuisance to residents, and environmental protection need to be considered simultaneously. At the same time, the construction period of cast-in-place is relatively long, the engineering quantity is large, the construction process is complex, the construction is affected by seasons, and it seriously affects the daily life of residents, resulting in obstacles to the retrofitting of many elevators. Therefore, how to shorten the construction period, reduce the amount of wet work on site, and reduce the nuisance to residents when retrofitting elevators are urgent problems to be solved at present. Summary of the Invention
[0004] In view of this, the present invention provides a prefabricated elevator precast component to solve the problems of long construction period, large engineering quantity, and complex construction process for elevator retrofitting.
[0005] The present invention also provides a construction method for the prefabricated elevator precast component.
[0006] To achieve the above object, the present invention adopts the following technical solutions:
[0007] The prefabricated elevator precast component according to the first aspect embodiment of the present invention includes:
[0008] A plurality of precast raft plates, which are used to form a foundation raft plate by post-cast connection, and the bottom of the foundation raft plate is used to be post-cast connected to the original main foundation;
[0009] A precast well wall, the bottom of which is used to be post-cast connected to the foundation raft plate;
[0010] A precast corridor column, the bottom of which is used to be post-cast connected to the foundation raft plate;
[0011] A precast top plate, which is used to be post-cast connected to the top of the precast corridor column.
[0012] Further, first anchoring steel bars are arranged on the precast raft plate, and the first anchoring steel bars are used for post-cast connection of any two adjacent precast raft plates.
[0013] Furthermore, the upper surface of the foundation raft slab is provided with first extended steel bars, and the bottom of the precast well wall has first grouting sleeves matching the first extended steel bars. The first extended steel bars and the first grouting sleeves are used for grouting connection between the foundation raft slab and the precast well wall.
[0014] Furthermore, the upper surface of the foundation raft slab is also provided with second extended steel bars, and the bottom of the precast corridor column has second grouting sleeves matching the second extended steel bars. The second extended steel bars and the second grouting sleeves are used for grouting connection between the foundation raft slab and the precast corridor column.
[0015] Furthermore, the precast roof slab includes:
[0016] A first roof slab;
[0017] A second roof slab, on which a first through hole is formed. The top of the precast corridor column extends outward to be provided with a steel column, and the steel column is arranged in the first through hole.
[0018] Furthermore, the precast roof slab further includes:
[0019] A connecting piece;
[0020] On one side of the first roof slab, two connecting arms extending towards the second roof slab are formed. On one side of the second roof slab, two flanks extending towards the first roof slab are formed. The connecting piece is used for post-casting connection between the connecting arms and the flanks.
[0021] Furthermore, at the end of the connecting arm towards the second roof slab, second anchoring steel bars are provided, and at the end of the flank towards the first roof slab, third anchoring steel bars are provided;
[0022] The connecting piece has main bars, and the main bars extend out of the connecting piece to be connected with the second anchoring steel bars or the third anchoring steel bars.
[0023] Furthermore, the connecting arm is connected to the flank through two of the connecting pieces;
[0024] The connecting piece further has:
[0025] An end plate, which is located on the side far from the extending end of the main bar;
[0026] Longitudinal bars, the first ends of which are connected to the ends of the end plate, and the second ends of which are connected to the other ends of the main bars;
[0027] A steel plate, which is connected to the end plate;
[0028] Wherein, the two connecting pieces are connected through the end plate.
[0029] Furthermore, a plurality of second through holes are also provided on the base raft, and the second through holes are used to match with the fourth anchor bars implanted on the original main foundation, and the base raft is connected to the original main foundation by post-casting.
[0030] The construction method of the prefabricated elevator precast components according to the second aspect embodiment of the present invention includes the following steps:
[0031] S1, connecting a plurality of precast rafts by post-casting to form a base raft;
[0032] S2, hoisting the base raft and using adjusting shims to adjust the levelness of the base raft;
[0033] S3, connecting the base raft to the pre-treated original main foundation by post-casting;
[0034] S4, connecting the bottom of the precast shaft wall to the base raft by post-casting;
[0035] S5, connecting the bottom of the precast corridor column to the base raft by post-casting;
[0036] S6, connecting the top of the precast corridor column to the precast roof slab by post-casting.
[0037] At least one of the above technical solutions of the present invention has the following beneficial effects:
[0038] 1. The prefabricated elevator precast components according to the embodiments of the present invention include a plurality of precast rafts, a precast shaft wall, precast corridor columns and a precast roof slab. The plurality of precast rafts are used to form a base raft by post-casting connection. An assembled elevator structure is formed by sequentially post-casting the base raft, the precast shaft wall, the precast corridor columns and the precast roof slab on the original main foundation. The elevator components of the embodiments of the present invention are manufactured in the factory, and only the installation and connection operations of each elevator component need to be carried out at the construction site, which greatly shortens the construction period. Compared with the cast-in-place construction, the amount of wet work on site is reduced, and the efficiency of on-site construction is improved.
[0039] 2. The precast roof slab of the prefabricated elevator precast components according to the embodiments of the present invention includes a first roof slab, a second roof slab and two pairs of connecting members. The connecting members are used to connect the connecting arms of the first roof slab and the flanks of the second roof slab by post-casting. Compared with the integral precast roof slab, the first roof slab and the second roof slab are connected by post-casting, which realizes the precise installation of the precast roof slab, ensures the parallelism and perpendicularity of the precast roof slab, and improves the convenience of post-casting construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 It is a schematic diagram of the connection structure between the partial prefabricated elevator precast components and the original main foundation according to the embodiment of the present invention;
[0041] Figure 2 For Figure 1 an enlarged view of A in;
[0042] Figure 3 a schematic diagram of the connection structure between the foundation raft and the precast shaft wall according to an embodiment of the present invention;
[0043] Figure 4 a schematic diagram of the connection structure between the foundation raft and the precast corridor column according to an embodiment of the present invention;
[0044] Figure 5 a schematic diagram of the structure of the precast roof slab according to an embodiment of the present invention;
[0045] Figure 6 a connecting member of the precast roof slab according to an embodiment of the present invention;
[0046] Figure 7 a schematic diagram of the connection structure between the foundation raft and the original main foundation according to an embodiment of the present invention.
[0047] Reference numerals:
[0048] 100. Foundation raft; 110. Precast raft; 111. First protruding steel bar; 112. Second protruding steel bar; 113. Second through hole; 114. First anchoring steel bar; 200. Precast shaft wall; 211. First grouting sleeve; 300. Precast corridor column; 311. Second grouting sleeve; 312. Steel column; 400. Precast roof slab; 410. First roof slab; 411. Connecting arm; 420. Second roof slab; 421. First through hole; 422. Flank; 430. Connecting member; 431. End plate; 432. Steel plate; 433. Longitudinal bar; 434. Main bar; 001. Original main foundation; 001a. Fourth anchoring steel bar; 002. Adjusting gasket. Detailed implementation manners
[0049] In order to make the objectives, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are some, but not all, of the embodiments of the present invention. All other embodiments obtained by those of ordinary skill in the art based on the described embodiments of the present invention fall within the scope of protection of the present invention.
[0050] Unless otherwise defined, technical terms or scientific terms used in the present invention shall have the ordinary meanings understood by those of ordinary skill in the field to which the present invention pertains. The "first", "second" and similar terms used in the present invention do not denote any order, quantity or importance, but are only used to distinguish different components. Similarly, terms such as "a" or "one" do not denote a quantity limitation, but mean that there is at least one. The terms "connected" or "coupled" and the like are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. The terms "upper", "lower", "left", "right" and the like are only used to indicate relative positional relationships, and when the absolute position of the object being described changes, the relative positional relationship also changes accordingly.
[0051] First, the prefabricated elevator components according to the first aspect embodiment of the present invention will be specifically described below with reference to the accompanying drawings.
[0052] As Figure 1-7 shown, the prefabricated elevator components according to the first aspect embodiment of the present invention include a plurality of precast raft plates 110, precast shaft walls 200, precast corridor columns 300, and precast roof plates 400.
[0053] The plurality of precast raft plates 110 are used to form a foundation raft 100 by post-cast connection. The bottom of the foundation raft 100 is used to be post-cast connected to the original main foundation 001. That is to say, by industrially manufacturing a plurality of precast raft plates 110 in the factory and then post-casting to connect the precast raft plates 110 to form the foundation raft 100 on-site, compared with directly casting the foundation raft 100 on-site, the amount of wet work on-site is reduced. And considering the large size of the foundation raft 100, compared with the integral foundation raft 100, the entry and operation of large vehicles and large equipment can be avoided. Specifically, taking Figure 1 the shown foundation raft 100 as an example, the foundation raft 100 can be provided with three precast raft plates 110, for example, and a T-shaped post-cast strip is formed by post-casting. Through this T-shaped post-cast strip, the three precast raft plates 110 can be connected to form the foundation raft 100, and then the foundation raft 100 formed by post-casting is connected to the original main foundation 001, improving the reliability of the prefabricated elevator.
[0054] The bottom of the precast shaft wall 200 is used to be post-cast connected to the foundation raft 100. That is to say, after the precast shaft wall 200 is manufactured in the factory, it is connected to the foundation raft 100 by post-casting, further reducing the amount of wet work on-site and improving the on-site construction efficiency.
[0055] The bottom of the precast corridor column 300 is used for post-casting connection to the foundation raft 100. That is to say, after the precast corridor column 300 is manufactured in the factory, it is connected to the foundation raft 100 through post-casting, further reducing the amount of wet work on site and improving the on-site construction efficiency.
[0056] The precast top plate 400 is used for post-casting connection to the top of the precast corridor column 300. That is to say, after the precast top plate 400 is manufactured in the factory, it is connected to the foundation raft 100 through post-casting, further reducing the amount of wet work on site and improving the efficiency of on-site construction.
[0057] In the embodiment of the present invention, the foundation raft 100, the precast shaft wall 200, the precast corridor column 300, and the precast top plate 400 are post-cast in sequence from bottom to top on the original main body foundation 001 to form an assembled elevator structure. Since the precast components forming the assembled elevator structure are all manufactured in the factory, industrial manufacturing processes can be used to produce elevator components, and conditions such as temperature and humidity can be controlled during the production process to ensure the construction quality of the precast components. Subsequently, only the installation and connection operations of each precast component need to be carried out at the construction site, greatly shortening the construction period. Compared with cast-in-place construction, the amount of wet work on site is reduced, and the on-site construction efficiency is improved.
[0058] Furthermore, the first anchoring steel bars 114 (not shown in the figure) are provided on the precast raft 110. The first anchoring steel bars 114 are used for post-casting connection of any two adjacent precast rafts 110. That is to say, by providing the first anchoring steel bars 114 on each precast raft 110 and connecting two adjacent precast rafts 110 through the first anchoring steel bars 114, usually preferably by welding connection, and then through post-casting, any two adjacent precast rafts 110 are connected to form the foundation raft 100. Specifically, taking Figure 1 the shown foundation raft 100 as an example, during on-site construction, for example, the first anchoring steel bars 114 can be provided on the bottom surface of the first precast raft 110 (corresponding to Figure 1 above the T-shaped post-cast strip), for example, the first anchoring steel bars 114 can also be provided on the top surface and the right side surface of the second precast raft 110 (corresponding to Figure 1 below the left side of the T-shaped post-cast strip), for example, the first anchoring steel bars 114 can also be provided on the top surface and the left side surface of the third precast raft 110 (corresponding to Figure 1 below the right side of the T-shaped post-cast strip), and then through post-casting, the top surface of the second precast raft 110 is connected to the bottom surface of the first precast raft 110; the right side surface of the second precast raft 110 is connected to the left side surface of the third precast raft 110; the top surface of the third precast raft 110 is connected to the bottom surface of the first precast raft 110, that is, it forms Figure 1The shown foundation raft 100. It should be noted that the quantity and combination mode of the precast raft 110 in the embodiment of the present invention include but are not limited to Figure 1 the shown structure.
[0059] Furthermore, a first protruding steel bar 111 is arranged on the upper surface of the foundation raft 100, and the bottom of the precast shaft wall 200 has a first grouting sleeve 211 matching with the first protruding steel bar 111. The first protruding steel bar 111 and the first grouting sleeve 211 are used for grouting connection between the foundation raft 100 and the precast shaft wall 200. That is to say, the foundation raft 100 and the precast shaft wall 200 are connected through the first grouting sleeve 211 to Figure 1 Taking the shown foundation raft 100 as an example, for instance, the precast shaft wall 200 can be connected by post-casting to the upper surface of the third precast raft 110 (corresponding to Figure 1 the lower right side of the T-shaped post-cast strip in). Specifically, as Figure 3 shown, a part of the first protruding steel bar 111 is arranged inside the foundation raft 100, and the other part protrudes from the upper surface of the foundation raft 100. The first grouting sleeve 211 is embedded at the bottom of the precast shaft wall 200. During on-site construction, first, the first grouting sleeves 211 inside the precast shaft wall 200 are connected to the first protruding steel bars 111 on the foundation raft 100 one by one, and then grouting material is injected. The first protruding steel bar 111 and the first grouting sleeve 211 are connected through the bonding and biting action between the grouting materials to realize the connection between the precast shaft wall 200 and the foundation raft 100.
[0060] Furthermore, a first protruding steel bar 112 is also arranged on the upper surface of the foundation raft 100, and the bottom of the precast corridor column 300 has a second grouting sleeve 311 matching with the first protruding steel bar 112. The first protruding steel bar 112 and the second grouting sleeve 311 are used for grouting connection between the foundation raft 100 and the precast corridor column 300. That is to say, the foundation raft 100 and the precast corridor column 300 are connected through the second grouting sleeve 311 to Figure 1 Taking the shown foundation raft 100 as an example, for instance, the precast corridor column 300 can be connected by post-casting to the upper surface of the second precast raft 110 (corresponding to Figure 1 the lower left side of the T-shaped post-cast strip in). Specifically, as Figure 4As shown, a part of the first protruding steel bar 112 is arranged in the foundation raft 100, and the other part protrudes from the upper surface of the foundation raft 100, and the second grouting sleeve 311 is buried in the bottom of the prefabricated corridor column 300. During on-site construction, in order to reduce the workload of on-site construction, the second grouting sleeve 311 on the prefabricated corridor column 300 and the first protruding steel bar 112 on the foundation raft 100 need to be pre-assembled in the factory. During on-site construction, the second grouting sleeve 311 in the prefabricated corridor column 300 is connected to the first protruding steel bar 112 on the foundation raft 100 in a one-to-one correspondence, and then the grouting material is injected, and the first protruding steel bar 112 and the second grouting sleeve 311 are connected through the bonding and biting action between the grouting materials, so as to realize the connection between the prefabricated corridor column 300 and the foundation raft 100.
[0061] Further, the prefabricated top plate 400 includes a first top plate 410 (corresponding to Figure 5 The right side portion) and the second top plate 420 (corresponding to Figure 5 The second top plate 420 is connected to the first top plate 410, a first through hole 421 is formed on the second top plate 420, and a steel column 312 is provided on the top of the prefabricated corridor column 300, the steel column 312 is provided in the first through hole 421, and the steel column 312 is used for post-casting connection between the prefabricated corridor column 300 and the second top plate 420. That is to say, during on-site construction, the second top plate 420 is first connected to the prefabricated corridor column 300, and then the first top plate 410 is connected to the second top plate 420, so that the prefabricated top plate 400 is connected to the prefabricated corridor column 300.
[0062] Furthermore, the prefabricated top plate 400 further includes a connecting member 430, one side of the first top plate 410 (corresponding to Figure 5 The left side of the second top plate 420 is formed with two connecting arms 411 extending toward the second top plate 420. One side of the second top plate 420 (corresponding to Figure 5 The first top plate 410 is formed with two side wings 422 extending toward the first top plate 410 (on the right side in the figure), and the connector 430 is used for post-casting connection of the connecting arm 411 and the side wings 422. That is, the first top plate 410 is connected to the second top plate 420 by post-casting connection of the connecting arm 411 and the side wings 422 through the connector 430. During construction, the second top plate 420 can be first connected to the precast corridor column 300 cast on the foundation raft 100, and then the second top plate 420 and the first top plate 410 are connected by the connector 430. Compared with the integral precast top plate 400, the post-casting connection of the first top plate 410 and the second top plate 420 realizes the precise installation of the precast top plate 400, ensures the parallelism and verticality of the precast top plate 400, and improves the convenience of post-casting construction.
[0063] Further, a second anchoring steel bar (not shown in the figure) is provided at one end of the connecting arm 411 facing the second top plate 420, and a third anchoring steel bar (not shown in the figure) is provided at one end of the flank 422 facing the first top plate 410. The connecting member 430 has a main reinforcement bar 434, and the main reinforcement bar 434 extends out of the connecting member 430 and is connected to the second anchoring steel bar or the third anchoring steel bar. That is to say, the third anchoring steel bar on the flank 422 of the second top plate 420 is connected to the main reinforcement bar 434 of the connecting member 430, and the second anchoring steel bar on the connecting arm 411 of the first top plate 410 is also connected to the main reinforcement bar 434 of the connecting member 430. The first top plate 410 is connected to the second top plate 420 through the connecting arm 411, the second anchoring steel bar, the main reinforcement bar 434, the third anchoring steel bar, and the flank 422 in sequence.
[0064] Further, the connecting arm 411 is connected to the flank 422 through two connecting members 430. As Figure 6 shown, the connecting member 430 further has an end plate 431, longitudinal reinforcement bars 433, and a steel plate 432. The end plate 431 is located on the side away from the extending end of the main reinforcement bar 434. The first end of the longitudinal reinforcement bar 433 is connected to the end of the end plate 431, and the second end is connected to the other end of the main reinforcement bar 434. The steel plate 432 is connected to the end plate 431, and the two connecting members 430 are connected through the end plate 431. That is to say, the first top plate 410 is connected to the second top plate 420 through the connecting arm 411, the second anchoring steel bar, the main reinforcement bar 434 of one of the connecting members, the end plate 431 of one of the connecting members, the end plate 431 of the other connecting member, the main reinforcement bar 434 of the other connecting member, the third anchoring steel bar, and the flank 422 in sequence. During on-site construction, first, the extending end of the main reinforcement bar 434 of one of the connecting members (corresponding to Figure 6 the left end of the left connecting member) is connected to the third anchoring steel bar (not shown in the figure) on the flank 422. This connection method is preferably a welded connection. Then, the extending end of the main reinforcement bar 434 of the other connecting member 430 (corresponding to Figure 6 the right connecting member) (corresponding to Figure 6 the right end of the right connecting member) is connected to the second anchoring steel bar (not shown in the figure) on the connecting arm 411. This connection method is preferably a welded connection. Then, the end plate 431 of one of the connecting members (corresponding to Figure 6 the left connecting member) (corresponding to Figure 6 the right end of the left connecting member) is connected to the end plate 431 of the other connecting member (corresponding to Figure 6 the right connecting member) (corresponding to Figure 6The left end of the right connecting member (), this connection method is preferably a welded connection. During this welded connection process, the relative positions of the two connecting members 430 can be adjusted by stagger-welding the two end plates 431, achieving the precise installation of the first top plate 410, ensuring the parallelism and perpendicularity of the first top plate 410, improving the convenience of post-pouring construction. Finally, pour the connecting member 430, and connect one of the connecting members 430 to the flank 422, and the other connecting member 430 to the connecting arm 411. In addition, by arranging the end plate 431, steel plate 432, longitudinal reinforcement 433 and main reinforcement 434 in the connecting member 430, the mechanical strength of the connecting member 430 is improved.
[0065] A plurality of second through holes 113 are also provided on the foundation raft 100. The second through holes 113 are used to match with the fourth anchor reinforcement 001a implanted on the original main foundation 001, and the foundation raft 100 is connected to the original main foundation 001 through post-pouring. That is, as Figure 7 shown, the foundation raft 100 is connected to the original main foundation 001 through post-pouring, improving the reliability of the prefabricated elevator.
[0066] The construction method of the prefabricated elevator precast component according to the second aspect embodiment of the present invention includes the following steps:
[0067] S1, connect a plurality of precast rafts 110 through post-pouring to form a foundation raft 100;
[0068] S2, hoist the foundation raft 100, and use the adjusting gasket 002 to adjust the levelness of the foundation raft 100;
[0069] S3, connect the foundation raft 100 to the pre-treated original main foundation 001 through post-pouring;
[0070] S4, connect the bottom of the precast shaft wall 200 to the foundation raft 100 through post-pouring;
[0071] S5, connect the bottom of the precast corridor column 300 to the foundation raft 100 through post-pouring;
[0072] S6, connect the top of the precast corridor column 300 to the precast top plate 400 through post-pouring.
[0073] Specifically, the construction process of the prefabricated elevator precast component in the embodiment of the present invention is as follows:
[0074] Fabricate the foundation raft 100. According to the construction drawings, select appropriate precast rafts 110, connect two adjacent precast rafts 110 through the first anchor reinforcement 114, usually preferably a welded connection, and then connect any two adjacent precast rafts 110 through post-pouring to form the foundation raft 100.
[0075] Lift the foundation raft 100. Place the foundation raft 100 into the elevator pit, and use the adjusting shim 002 to adjust the levelness of the foundation raft 100.
[0076] Pour the foundation raft 100. Before pouring, the original main foundation 001 should be pre-treated. The pre-treatment procedures include: roughening the surface of the original main foundation 001, cleaning the roughened original main foundation 001, and grouting the cleaned original main foundation 001. And there is also a fourth anchor bar 001a on the original main foundation 001. At the same time, there are also a plurality of second through holes 113 matching the fourth anchor bar 001a on the foundation raft 100. Place the fourth anchor bar 001a in the second through hole 113, and connect the foundation raft 100 and the original main foundation 001 by post-pouring.
[0077] Pour the precast well wall 200. First, connect the first grouting sleeves 211 in the precast well wall 200 to the first protruding bars 111 on the foundation raft 100 one by one, and then inject grouting material. Connect the first protruding bars 111 and the first grouting sleeves 211 through the bonding and biting action between the grouting materials to realize the connection between the precast well wall 200 and the foundation raft 100.
[0078] Pour the precast corridor column 300. Connect the second grouting sleeves 311 in the precast corridor column 300 to the first protruding bars 112 on the foundation raft 100 one by one, and then inject grouting material. Connect the first protruding bars 112 and the second grouting sleeves 311 through the bonding and biting action between the grouting materials to realize the connection between the precast corridor column 300 and the foundation raft 100.
[0079] Install the precast roof slab 400. First, place the steel column 312 of the precast corridor column 300 in the first through hole 421 of the second roof slab 420, and connect the second roof slab 420 and the precast corridor column 300 by post-pouring. First, connect the protruding end of the main bar 434 of one of the connectors 430 to the third anchor bar on the flank 422. This connection method is preferably a welded connection. Then, connect the protruding end of the main bar 434 of the other connector 430 to the second anchor bar on the connecting arm 411. This connection method is preferably a welded connection. Then, connect the end plate 431 of one of the connectors 430 to the end plate 431 of the other connector 430. This connection method is preferably a welded connection. Finally, pour the connector 430, and connect one of the connectors 430 to the flank 422 and the other connector 430 to the connecting arm 411.
[0080] The above is the preferred embodiment of the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principle of the present invention, several improvements and refinements can be made, and these improvements and refinements should also be regarded as the protection scope of the present invention.
Claims
1. An assembled elevator prefabricated component, characterized in that, Including: Multiple precast raft slabs, which are used to form a foundation raft slab by post-casting connection, and the bottom of the foundation raft slab is used to be connected to the original main foundation by post-casting; A precast well wall, the bottom of which is used to be connected to the foundation raft slab by post-casting; Precast corridor columns, the bottoms of which are used to be connected to the foundation raft slab by post-casting; A precast top slab, which is used to be connected to the top of the precast corridor columns by post-casting; The precast top slab includes: A first top slab; A second top slab, on which a first through hole is formed, and a steel column extends outward from the top of the precast corridor column, and the steel column is arranged in the first through hole; A connecting piece; On one side of the first top slab, two connecting arms extending towards the second top slab are formed, and on one side of the second top slab, two flanks extending towards the first top slab are formed, and the connecting piece is used to connect the connecting arms and the flanks by post-casting; At the end of the connecting arm facing the second top slab, a second anchoring steel bar is arranged, and at the end of the flank facing the first top slab, a third anchoring steel bar is arranged; The connecting piece has a main reinforcement bar, and the main reinforcement bar extends out of the connecting piece and is connected to the second anchoring steel bar or the third anchoring steel bar; The connecting arm connects the flank through two of the connecting pieces; The connecting piece also has: An end plate, which is located on the side far from the extending end of the main reinforcement bar; A longitudinal reinforcement bar, the first end of which is connected to the end of the end plate, and the second end of which is connected to the other end of the main reinforcement bar; A steel plate, which is connected to the end plate; Wherein, the two connecting pieces are connected through the end plate; On the foundation raft slab, a plurality of second through holes are also arranged, and the second through holes are used to match with the fourth anchoring steel bars implanted on the original main foundation, and the foundation raft slab and the original main foundation are connected by post-casting.
2. The prefabricated elevator component according to claim 1, characterized in that, On the precast raft slab, a first anchoring steel bar is arranged, and the first anchoring steel bar is used to connect any two adjacent precast raft slabs by post-casting.
3. The prefabricated elevator precast component according to claim 1, wherein On the upper surface of the foundation raft slab, a first extending steel bar is arranged, and the bottom of the precast well wall has a first grouting sleeve matching with the first extending steel bar, and the first extending steel bar and the first grouting sleeve are used to grout and connect the foundation raft slab and the precast well wall.
4. The prefabricated elevator component according to claim 1, wherein, On the upper surface of the foundation raft slab, a second extending steel bar is also arranged, and the bottom of the precast corridor column has a second grouting sleeve matching with the second extending steel bar, and the second extending steel bar and the second grouting sleeve are used to grout and connect the foundation raft slab and the precast corridor column.
5. A construction method for prefabricated components of an assembled elevator, characterized in that, Applied to the prefabricated elevator precast component according to any one of claims 1 to 4, including the following steps: S1, making multiple precast raft slabs connected to form a foundation raft slab by post-casting; S2, hoisting the foundation raft slab and using adjusting shims to adjust the levelness of the foundation raft slab; S3, making the foundation raft slab connected to the pre-treated original main foundation by post-casting; S4, making the bottom of the precast well wall connected to the foundation raft slab by post-casting; S5, making the bottom of the precast corridor column connected to the foundation raft slab by post-casting; S6. Connect the top of the precast corridor column to the precast roof slab by post-casting.
Citation Information
Patent Citations
Assembly type elevator prefabricated assembly
CN217518056U