Station area identification method, device, electronic equipment and storage medium

By receiving and clustering the voltage, current and power signal characteristics of the user and transformer terminals, the existing station area identification methods are solved, and more accurate and safe station area identification is achieved.

CN114825635BActive Publication Date: 2024-12-03GUANGZHOU YOUDIAN INFORMATION TECH CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202210575966.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-25
Publication Date
2024-12-03
Estimated Expiration
2042-05-25

AI Technical Summary

Technical Problem

The existing station area identification method is inefficient, there are crosstalk and safety hazards for power carrier identification, and the method based on voltage data is not very accurate.

Method used

By receiving voltage, current and power signals from the user and transformer terminals, extracting features and using the transformer terminal as the initial clustering center, clustering the user terminal signals, combining time domain and transform domain features, optimize the clustering algorithm to improve identification accuracy.

Benefits of technology

It improves the accuracy of station area identification, avoids line crosstalk problems, improves identification efficiency, and enhances security.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114825635B_ABST
    Figure CN114825635B_ABST
Patent Text Reader

Abstract

The embodiment of the present invention relates to the technical field of substation identification, and discloses a substation identification method, device, electronic device and storage medium. The method includes: receiving voltage, current and power signals collected by the user end and the transformer end at the same time within a preset time period, and extracting the characteristics of the voltage, current and power signals; clustering the characteristics of the voltage, current and power signals collected by all user ends with the voltage, current and power characteristics of the transformer end as the initial clustering center; and assigning the target user end and the target transformer end to the same substation, and the target user end and the target transformer end belong to the same cluster. By implementing the embodiment of the present invention, the correlation between the voltage, current and power of the user end and the transformer end in the same substation can be considered at the same time, so that the substation identification is more accurate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of substations, and in particular to a method, device, electronic equipment and storage medium for identifying substations based on voltage, current and power characteristics of distribution lines. Background Art

[0002] There are three types of existing area identification: manual detection, user identification through FSK power carrier signal, and meter area identification based on voltage data. Among the above three methods, the manual detection method is inefficient; the power carrier has crosstalk, and the current pulse needs to install a current transformer, which has safety hazards and poor controllability; the correlation method based on voltage data is not accurate because it only considers voltage. Summary of the invention

[0003] In response to the above-mentioned defects, an embodiment of the present invention discloses a substation identification method, device, electronic device and storage medium, which simultaneously considers the correlation between the voltage, current and power at the user end and the transformer end of the same substation, so as to make the substation identification more accurate.

[0004] A first aspect of an embodiment of the present invention discloses a method for identifying a station area, the method comprising:

[0005] Receiving voltage, current and power signals collected simultaneously at the user end and the transformer end within a preset time period, and extracting features of the voltage, current and power signals;

[0006] The voltage, current and power characteristics at the transformer end are used as the initial clustering center to cluster the characteristics of the voltage, current and power signals collected at all user ends;

[0007] The target user end and the target transformer end are classified into the same substation, and the target user end and the target transformer end belong to the same cluster.

[0008] As a preferred embodiment, in the first aspect of the embodiment of the present invention, extracting the characteristics of the voltage, current and power signals includes:

[0009] Using the time domain waveform or transform domain coefficient of the voltage signal as the voltage feature corresponding to the voltage signal;

[0010] The time domain waveforms of the current and power are respectively used as the current feature corresponding to the current signal and the power feature corresponding to the power signal.

[0011] As a preferred embodiment, in the first aspect of the embodiment of the present invention, the time domain waveform feature adopts a combination of dimensional features and dimensionless features; the dimensional time domain feature parameter is one of peak-to-peak value, mean value, variance, standard deviation, and effective value, and the dimensionless time domain feature parameter is one of kurtosis, skewness, waveform factor, peak factor, and pulse factor.

[0012] As a preferred embodiment, in the first aspect of the embodiments of the present invention, when the voltage feature adopts a transform domain coefficient, the voltage feature is a wavelet transform coefficient, a Fourier transform coefficient or a KL transform coefficient.

[0013] As a preferred embodiment, in the first aspect of the embodiment of the present invention, the voltage, current and power characteristics at the transformer end are used as the initial clustering center, and the characteristics of the voltage, current and power signals collected by all user ends are clustered, including:

[0014] Step 21, using the voltage, current and power characteristics at the transformer end as the initial clustering center;

[0015] Step 22: Assign each user-side feature to N classes, where N is the number of initial cluster centers, and minimize the cost function J:

[0016]

[0017] Among them, a1, a2, and a3 are preset weights. is the nth category, O i =[U i , I i , Q i ] is the feature of the i-th user end, U i ,I i , Q i are the voltage, current and power characteristics of the i-th user terminal, is the cluster center of the voltage, current and power characteristics of the nth category;

[0018] Step 23: If the absolute value of J or the change from the previous iteration is less than the preset threshold, the classification ends, otherwise, execute step 24;

[0019] Step 24: Calculate new cluster centers based on the classification results of step 22, and re-execute step 22:

[0020]

[0021]

[0022]

[0023] Among them, c n is the number of elements contained in the nth category.

[0024] As a preferred embodiment, in the first aspect of the embodiment of the present invention, each user terminal feature is assigned to N classes, including:

[0025] calculate The cost function J ni :

[0026]

[0027] Constructing the cost function matrix Where M is the total number of user terminals;

[0028] Defining the selection matrix where x ni =0 or 1;

[0029] Set up an integer programming problem:

[0030]

[0031] Solution When x ni =1,

[0032] A second aspect of an embodiment of the present invention discloses a station area identification device, which includes:

[0033] A receiving unit, used to receive voltage, current and power signals collected simultaneously at the user end and the transformer end within a preset time period, and extract features of the voltage, current and power signals;

[0034] A clustering unit is used to cluster the characteristics of voltage, current and power signals collected by all user terminals using the voltage, current and power characteristics of the transformer terminal as the initial clustering center;

[0035] The identification unit is used to classify the target user end and the target transformer end as belonging to the same substation, and the target user end and the target transformer end belong to the same cluster.

[0036] A third aspect of an embodiment of the present invention discloses an electronic device, comprising: a memory storing executable program code; a processor coupled to the memory; the processor calls the executable program code stored in the memory to execute a station area identification method disclosed in the first aspect of the embodiment of the present invention.

[0037] A fourth aspect of an embodiment of the present invention discloses a computer-readable storage medium storing a computer program, wherein the computer program enables a computer to execute a station area identification method disclosed in the first aspect of an embodiment of the present invention.

[0038] A fifth aspect of an embodiment of the present invention discloses a computer program product. When the computer program product is run on a computer, the computer is enabled to execute a station area identification method disclosed in the first aspect of the embodiment of the present invention.

[0039] A sixth aspect of an embodiment of the present invention discloses an application publishing platform, which is used to publish a computer program product. When the computer program product runs on a computer, the computer executes a station area identification method disclosed in the first aspect of the embodiment of the present invention.

[0040] Compared with the prior art, the embodiments of the present invention have the following beneficial effects:

[0041] The embodiment of the present invention not only considers the information characteristics of voltage or current, but also considers the correlation between voltage, current and power at the user end and transformer end of the substation, thereby improving the accuracy of substation identification. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0043] Figure 1 It is a flow chart of a method for identifying a station area disclosed in an embodiment of the present invention;

[0044] Figure 2 is a schematic diagram of a clustering process disclosed in an embodiment of the present invention;

[0045] Figure 3 It is a flowchart of a method for allocating a user terminal to N classes disclosed in an embodiment of the present invention;

[0046] Figure 4 It is a structural schematic diagram of a station area identification device disclosed in an embodiment of the present invention;

[0047] Figure 5 It is a structural schematic diagram of an electronic device disclosed in an embodiment of the present invention. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] It should be noted that the terms "first", "second", "third", "fourth", etc. in the specification and claims of the present invention are used to distinguish different objects rather than to describe a specific order. The terms "including" and "having" in the embodiments of the present invention and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device including a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0050] The embodiment of the present invention discloses a substation identification method, device, electronic device and storage medium, which simultaneously considers the correlation between voltage, current and power at the user end and transformer end of the substation to improve the accuracy of substation identification, which is described in detail below with reference to the accompanying drawings.

[0051] Embodiment 1

[0052] The distribution substation is a basic element of the power supply system and an important component of the smart grid. The accurate substation topology relationship is of great significance for the information collection of power users. The present invention provides a substation identification method based on the voltage, current and power characteristics of the distribution line, while considering the characteristics of the voltage, current and power of the same substation, avoiding the line crosstalk problem of the power carrier identification method, and the problem of low substation identification accuracy when only using voltage or current information, making substation identification more accurate.

[0053] See also Figure 1 , Figure 1 FIG. 1 is a flow chart of a method for identifying a substation area disclosed in an embodiment of the present invention. Figure 1 As shown, the station area identification method includes the following steps:

[0054] S110, receiving voltage, current and power signals collected simultaneously at the user end and the transformer end within a preset time period, and extracting features of the voltage, current and power signals.

[0055] The voltage feature extracted from the voltage signal is the time domain waveform or transform domain coefficient of the voltage signal, and the current and power features extracted from the current and power signals are the time domain waveforms of the current and power signals. The time domain waveform features of voltage, current and power are combined with dimensional features and dimensionless features. The dimensional time domain feature parameters include peak-to-peak value, average value, variance, standard deviation, effective value, etc., and the dimensionless time domain feature parameters include kurtosis, skewness, waveform factor, peak factor, pulse factor, etc. You can select one or more of the dimensional time domain feature parameters and dimensionless time domain feature parameters as the time domain waveform features of voltage, current and power.

[0056] The transform domain coefficient characteristics of the above voltage, illustratively, can use wavelet transform, Fourier transform or KL transform coefficients as voltage characteristics.

[0057] S120: Taking the voltage, current and power characteristics at the transformer end as the initial clustering center, clustering the characteristics of the voltage, current and power signals collected from all user ends.

[0058] There are many clustering algorithms. In the preferred embodiment of the present invention, please refer to Figure 2 As shown, the clustering process is:

[0059] S121, taking the voltage, current and power characteristics at the transformer end as the initial clustering center;

[0060] S122, assigning each user terminal feature to N classes, where N is the number of initial clustering centers, and minimizing the cost function J:

[0061]

[0062] Among them, a1, a2, and a3 are preset weights. is the nth category, O i =[U i , I i , Q i ] is the feature of the i-th user end, U i ,I i , Q i are the voltage, current and power characteristics of the i-th user terminal, is the cluster center of the voltage, current and power characteristics of the nth category.

[0063] S123. If the absolute value of the minimum cost function J or the change value from the previous iteration is less than a preset threshold, the classification ends, otherwise, execute S124.

[0064] The minimum J value is obtained through step S122. When the absolute value of the minimum J value is less than the preset threshold, or the change value (difference) between the minimum J value obtained in the previous iteration (generally, greater than the minimum J value obtained in step S122) and the minimum J value is less than the preset threshold, the classification ends.

[0065] That is, during the convergence process, if the convergence result, that is, the minimum J value obtained in step S122, is less than the preset threshold, it means that the classification requirements are met, and if the change value is less than the preset threshold, it means that even if the cluster center is recalculated and step S122 is re-executed, the minimum J value obtained will be difficult to reach the corresponding preset threshold.

[0066] It should be noted that the absolute value of the minimum cost function J is less than the preset threshold and is different from the preset threshold in the change value of the previous iteration that is less than the preset threshold. Moreover, the change value that is less than the preset threshold can also be replaced by the number of convergence times, that is, when the number of convergence times reaches the preset number, the classification ends.

[0067] S124. Calculate new cluster centers based on the classification results of S122, and re-execute S122:

[0068]

[0069]

[0070]

[0071] Among them, c n is the number of elements contained in the nth category.

[0072] In step S122, the method of assigning each user terminal feature to N classes is as follows. Figure 3 As shown, it includes the following steps:

[0073] S1221, Calculation The cost function J ni :

[0074]

[0075] S1222. Constructing cost function matrix

[0076] Where M is the total number of user terminals; define the selection matrix where x ni =0 or 1;

[0077] S1223. Establish integer programming problem:

[0078]

[0079] S1224, Solution When x ni =1,

[0080] In step S1224, the constraint condition By solving The minimum value of The value of .

[0081] S130: The target user end and the target transformer end are assigned to the same substation, and the target user end and the target transformer end belong to the same cluster.

[0082] After clustering is completed, the transformer end and user end under the same cluster are recorded as belonging to the same substation. For example, assuming that the target transformer is numbered B05, and the target user ends belonging to the same cluster with the target transformer are numbered Y001, Y007, Y009, and Y012 respectively, then the target user ends numbered Y001, Y007, Y009, and Y012 all belong to the substation corresponding to the target transformer numbered B05.

[0083] Embodiment 2

[0084] See also Figure 4 , Figure 4 Schematic diagram of the structure of a station area identification device disclosed in an embodiment of the present invention. Figure 4 As shown, the station area identification device may include:

[0085] The receiving unit 210 is used to receive the voltage, current and power signals collected by the user end and the transformer end within a preset time period, and extract the characteristics of the voltage, current and power signals;

[0086] The clustering unit 220 is used to cluster the characteristics of the voltage, current and power signals collected by all user terminals using the voltage, current and power characteristics of the transformer terminal as the initial clustering center;

[0087] The identification unit 230 is used to classify the target user end and the target transformer end as belonging to the same substation, and the target user end and the target transformer end belong to the same cluster.

[0088] Preferably, the receiving unit 210 may include:

[0089] Using the time domain waveform or transform domain coefficient of the voltage signal as the voltage feature corresponding to the voltage signal;

[0090] The time domain waveforms of the current and power are respectively used as the current feature corresponding to the current signal and the power feature corresponding to the power signal.

[0091] Wherein, the time domain waveform feature adopts a combination of dimensional features and dimensionless features; the dimensional time domain feature parameter is one of peak-to-peak value, mean value, variance, standard deviation, and effective value, and the dimensionless time domain feature parameter is one of kurtosis, skewness, waveform factor, peak factor, and pulse factor. When the voltage feature adopts transform domain coefficients, the voltage feature is a wavelet transform coefficient, a Fourier transform coefficient, or a KL transform coefficient.

[0092] Preferably, the clustering unit 220 may include:

[0093] An initial setting subunit, used to use the voltage, current and power characteristics at the transformer end as initial clustering centers;

[0094] The calculation subunit is used to assign each user terminal feature to N classes, where N is the number of initial cluster centers, and minimize the cost function J:

[0095]

[0096] Among them, a1, a2, and a3 are preset weights. is the nth category, O i =[U i , I i , Q i ] is the feature of the i-th user end, U i ,I i , Q i are the voltage, current and power characteristics of the i-th user terminal, is the cluster center of the voltage, current and power characteristics of the nth category;

[0097] A judgment subunit is used to terminate the classification if the absolute value of J or the change value from the previous iteration is less than a preset threshold, otherwise the re-execution subunit is executed;

[0098] The re-execution subunit is used to calculate new cluster centers based on the classification results of the calculation subunit and re-execute the calculation subunit:

[0099]

[0100]

[0101]

[0102] Among them, c n is the number of elements contained in the nth category.

[0103] Preferably, the computing subunit may include:

[0104] calculate The cost function J ni :

[0105]

[0106] Constructing the cost function matrix Where M is the total number of user terminals;

[0107] Defining the selection matrix where x ni =0 or 1;

[0108] Set up an integer programming problem:

[0109]

[0110] Solution When x ni =1,

[0111] Embodiment 3

[0112] See also Figure 5 , Figure 5 Schematic diagram of the structure of an electronic device disclosed in an embodiment of the present invention. Figure 5 As shown, the electronic device may include:

[0113] A memory 310 storing executable program codes;

[0114] a processor 320 coupled to the memory 310;

[0115] The processor 320 calls the executable program code stored in the memory 310 to execute part or all of the steps in the station area identification method in the first embodiment.

[0116] An embodiment of the present invention discloses a computer-readable storage medium storing a computer program, wherein the computer program enables a computer to execute part or all of the steps in a station area identification method in the first embodiment.

[0117] The embodiment of the present invention further discloses a computer program product, wherein when the computer program product is run on a computer, the computer is enabled to execute part or all of the steps in the station area identification method in the first embodiment.

[0118] An embodiment of the present invention further discloses an application publishing platform, wherein the application publishing platform is used to publish a computer program product, wherein when the computer program product runs on a computer, the computer executes part or all of the steps in a station area identification method in embodiment one.

[0119] In various embodiments of the present invention, it should be understood that the size of the serial numbers of the processes does not necessarily mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present invention.

[0120] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, i.e., they may be located in one place or distributed over multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0121] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0122] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-accessible memory. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution, can be embodied in the form of a software product, which is stored in a memory and includes several requests for a computer device (which can be a personal computer, a server or a network device, etc., specifically a processor in a computer device) to perform some or all of the steps of the method described in each embodiment of the present invention.

[0123] In the embodiments provided by the present invention, it should be understood that "B corresponding to A" means that B is associated with A, and B can be determined according to A. However, it should also be understood that determining B according to A does not mean determining B only according to A, and B can also be determined according to A and / or other information.

[0124] A person of ordinary skill in the art can understand that some or all of the steps in the various methods of the embodiments can be completed by instructing related hardware through a program, and the program can be stored in a computer-readable storage medium, and the storage medium includes a read-only memory (ROM), a random access memory (RAM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), a one-time programmable read-only memory (OTPROM), an electronically erasable rewritable read-only memory (EEPROM), a compact disc (CD-ROM) or other optical disc storage, magnetic disk storage, magnetic tape storage, or any other computer-readable medium that can be used to carry or store data.

[0125] The above is a detailed introduction to a method, device, electronic device and storage medium for identifying a substation area disclosed in an embodiment of the present invention. Specific examples are used in this article to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea. At the same time, for a person skilled in the art, according to the idea of ​​the present invention, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present invention.

Claims

1. A method for identifying a station area, characterized in that: include: Receiving voltage, current and power signals collected simultaneously at the user end and the transformer end within a preset time period, and extracting features of the voltage, current and power signals; The voltage, current and power characteristics at the transformer end are used as the initial clustering center to cluster the characteristics of the voltage, current and power signals collected at all user ends; The target user end and the target transformer end are assigned to the same substation, and the target user end and the target transformer end belong to the same cluster; The voltage, current and power characteristics at the transformer end are used as the initial clustering center to cluster the characteristics of the voltage, current and power signals collected by all user ends, including: Step 21, using the voltage, current and power characteristics at the transformer end as the initial clustering center; Step 22: Assign each user-side feature to N classes, where N is the number of initial cluster centers, and minimize the cost function J: Among them, a1, a2, and a3 are preset weights. is the nth category, O i =[U i ,I i ,Q i ] is the feature of the i-th user end, U i ,I i , Q i are the voltage, current and power characteristics of the i-th user terminal, is the cluster center of the voltage, current and power characteristics of the nth category; Step 23: If the absolute value of J or the change from the previous iteration is less than the preset threshold, the classification ends, otherwise, execute step 24; Step 24: Calculate new cluster centers based on the classification results of step 22, and re-execute step 22: Among them, c n is the number of elements contained in the nth category.

2. The station area identification method according to claim 1, characterized in that: Extracting characteristics of the voltage, current and power signals, including: Using the time domain waveform or transform domain coefficient of the voltage signal as the voltage feature corresponding to the voltage signal; The time domain waveforms of the current and power are respectively used as the current feature corresponding to the current signal and the power feature corresponding to the power signal.

3. The station area identification method according to claim 2, characterized in that: The time domain waveform feature adopts a combination of dimensional features and dimensionless features; the dimensional time domain feature parameter is one of peak-to-peak value, mean value, variance, standard deviation, and effective value, and the dimensionless time domain feature parameter is one of kurtosis, skewness, waveform factor, peak factor, and pulse factor.

4. The station area identification method according to claim 2, characterized in that: When the voltage feature adopts transformation domain coefficients, the voltage feature is a wavelet transformation coefficient, a Fourier transformation coefficient or a KL transformation coefficient.

5. The station area identification method according to claim 1, characterized in that: Assign each user-side feature to N classes, including: calculate The cost function J ni : Constructing the cost function matrix Where M is the total number of user terminals; Defining the selection matrix where x ni =0 or 1; Set up an integer programming problem: Solution When x ni =1, 6. A station area identification device, characterized in that: It includes: A receiving unit, used to receive voltage, current and power signals collected simultaneously at the user end and the transformer end within a preset time period, and extract features of the voltage, current and power signals; A clustering unit is used to cluster the characteristics of the voltage, current and power signals collected by all user terminals using the voltage, current and power characteristics of the transformer terminal as the initial clustering center; An identification unit, used for classifying a target user end and a target transformer end as belonging to the same substation, wherein the target user end and the target transformer end belong to the same cluster; Clustering units, including: An initial setting subunit, used to use the voltage, current and power characteristics at the transformer end as initial clustering centers; The calculation subunit is used to assign each user terminal feature to N classes, where N is the number of initial cluster centers, and minimize the cost function J: Among them, a1, a2, and a3 are preset weights. is the nth category, O i =[U i ,I i ,Q i ] is the feature of the i-th user end, U i ,I i , Q i are the voltage, current and power characteristics of the i-th user terminal, is the cluster center of the voltage, current and power characteristics of the nth category; A judgment subunit is used to terminate the classification if the absolute value of J or the change value from the previous iteration is less than a preset threshold, otherwise the re-execution subunit is executed; The re-execution subunit is used to calculate new cluster centers based on the classification results of the calculation subunit and re-execute the calculation subunit: Among them, c n is the number of elements contained in the nth category.

7. An electronic device, characterized in that: include: A memory storing executable program code; a processor coupled to the memory; The processor calls the executable program code stored in the memory to execute the station area identification method according to any one of claims 1 to 5.

8. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, wherein the computer program enables a computer to execute the station area identification method according to any one of claims 1 to 5.

Citation Information

Patent Citations

  • Urban low-voltage partitioning method based on spectral clustering algorithm

    CN104952002A

  • Power impedance topological graph generation method and system for power distribution area

    CN112510707A

  • User transformer area analysis method for low-voltage power distribution network

    CN112952828A