An integrated energy system expansion planning method considering flexible electrical loads

By introducing transferable and reducible load models into the integrated energy system, optimizing flexible electric load dispatching solves the problem of failing to effectively consider the impact of flexible electric loads in existing technologies, and achieves the goal of reducing operating costs and improving wind power consumption efficiency. Effect.

CN114936762BActive Publication Date: 2024-10-18YANTAI POWER SUPPLY COMPANY OF STATE GRID SHANDONG ELECTRIC POWER
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210522505.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-14
Publication Date
2024-10-18
Estimated Expiration
2042-05-14

AI Technical Summary

Technical Problem

The existing technology fails to effectively consider the impact of flexible electric loads on comprehensive energy system planning, resulting in high system operating costs, large peak-to-valley differences, and low wind power consumption efficiency.

Method used

Introduce transferable and reducible load models and build a comprehensive energy system expansion planning model. The goal is to minimize system investment, operation, power shortage, wind curtailment costs and flexible electric load compensation costs. The load curve is optimized through flexible electric load dispatching to reduce system operation. cost.

Benefits of technology

Through the introduction of flexible electric loads, the operating costs and power shortage costs of the system are reduced, the economy and reliability of the system are improved, the phenomenon of wind abandonment is reduced, and the wind power consumption capacity is enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114936762B_ABST
    Figure CN114936762B_ABST
Patent Text Reader

Abstract

The present invention relates to a comprehensive energy system expansion planning method taking flexible electric load into account. The present invention first establishes an electricity-gas-heat multi-energy coupling model; then, considering the influence of the regulation of flexible electric load on the planning of the comprehensive energy system, a transferable load and a reducible load model are established; finally, considering the system investment, operation, power shortage, wind abandonment and flexible load scheduling compensation costs, a comprehensive energy system expansion planning model taking flexible electric load into account is constructed. Example analysis shows that the proposed comprehensive energy system expansion planning model taking flexible electric load into account can reduce the operating cost of the comprehensive energy system, reduce power shortage, and improve the system's wind power absorption capacity, which is conducive to improving the economy and reliability of the system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an integrated energy system expansion planning method taking flexible electric load into consideration, belonging to the technical field of integrated energy system expansion planning methods. Background Art

[0002] An integrated energy system (IES) can transform various energy sources such as electricity, gas, and heat in various links of energy production, transmission, storage, and consumption, realize multi-energy complementary utilization and coordinated optimization, and thus significantly improve the operating efficiency of IES. Therefore, issues such as the optimization planning of IES have attracted widespread attention from scholars at home and abroad.

[0003] Considering cogeneration equipment and gas boilers, the prior art discloses an IES extended planning model containing multiple energy systems to carry out the site selection and capacity determination of conventional units, transmission lines, cogeneration and gas boilers. Since power-to-gas equipment can effectively improve energy utilization, the prior art also discloses a power-to-gas combined system optimization planning model that takes into account power-to-gas equipment and gas turbines, and proposes a power-to-gas equipment configuration. The results of the example show that the power-to-gas equipment can improve the system's ability to absorb new energy to a certain extent. The planning model proposed by the prior art considers both the natural gas system and the power system. On the basis of considering the collaborative planning method of the power-gas integrated energy system, the prior art adds research on the energy storage system to better play the role of power storage and gas storage in the planning of the integrated energy system. The prior art coordinates and complements multiple energy sources to carry out optimal capacity planning of the integrated energy system under limited financial constraints to achieve optimal utilization of resources. The prior art takes the minimum fuel cost, wind power abandonment volume and the peak-valley load variance on the end-user side as the objective function, and constructs a multi-objective robust planning model for the integrated energy system. The existing technology considers the intermittent and volatile nature of photovoltaic power generation output, and proposes a capacity planning model for an integrated energy system that takes into account uncertainty and includes multiple energy flows such as cold, heat, electricity, and gas, and its solution method. The existing technology considers the impact of wind power uncertainty on the planning of the integrated energy system, and studies the changes in various system costs under different wind power penetration rates. However, the above studies only consider the impact of different types of energy and their uncertainties on the planning of the integrated energy system from the "source side", and do not consider the impact of different types of loads on the "load side" on the planning of the integrated energy system. Flexible loads can effectively smooth the load curve, reduce the peak-to-valley difference in loads, and promote the consumption of wind power. Therefore, it is necessary to introduce flexible loads and study the expansion planning method of the integrated energy system that takes into account flexible electric loads.

[0004] In the prior art, three different types of flexible load models, namely, curtailable load, shiftable load and transferable load, are established, and it is verified that the participation of flexible load in dispatching can reasonably adjust the load curve and realize the economic operation of the system. In the prior art, a shiftable load model for three loads, namely, cold, heat and electricity, is established, and it is proved that the model can effectively smooth the load curve and reduce the system operation cost. In the prior art, the impact of transferable electric load on the energy interconnected microgrid system is considered, and a multi-energy collaborative optimization strategy model for the supply and demand sides of the energy interconnected microgrid system is constructed, but the model does not consider curtailable load. In the prior art, shiftable load, transferable load and curtailable load are considered, and a mixed integer linear programming method is used to optimize the configuration of the integrated energy system. In the prior art, the basic energy hub is expanded, and various flexible loads such as electricity, gas and heat on the user side are included in the demand side response resources. In the prior art, by constructing flexible electric load and flexible heat load models, the difficulties of integrating wind power generation with cogeneration are alleviated to improve the utilization efficiency of wind power. In the prior art, an electric thermal flexible load model is established, and a low-carbon operation method for an integrated energy system taking into account hydrogen energy and flexible electric thermal loads is proposed. The results show that the scheme considering electric thermal flexible loads can effectively reduce the peak-to-valley difference of the system, while reducing the amount of purchased electricity during the peak load period. In the prior art, flexible load response is introduced, and an optimized scheduling model for an integrated energy system taking into account electric thermal flexible loads is proposed. In the prior art, for the user-side integrated energy system, the seasonal and intraday time series characteristics are fully considered, and a regional system planning model taking into account source-load uncertainty is constructed. The example results show that the model can improve the economy and reliability of system operation. Summary of the invention

[0005] This paper introduces flexible electric loads on the "load side" of the integrated energy system, and proposes an integrated energy system expansion planning method taking flexible electric loads into account. First, a transferable and reducible load model is constructed. Then, the IES expansion optimization planning model is established with the goal of minimizing the sum of system investment, operation, power shortage, wind abandonment cost and flexible electric load compensation cost. Finally, the IEEE14-NGS14 example system is analyzed and verified, and the results show the effectiveness of the constructed model.

[0006] The method for planning the expansion of an integrated energy system taking into account flexible electrical loads is special in that it includes the following steps:

[0007] 1. Establish a flexible electrical load model

[0008] 1.1 Transferable load

[0009] Assume that the acceptable transfer interval of the transferable load is The constraint to ensure that the required power remains unchanged before and after load transfer is:

[0010]

[0011]

[0012] in: and are the power of the transferable load before and after the transfer in period h respectively; and are the minimum load power and maximum load power in each period after transfer, respectively. 0 is the total number of time periods within the day;

[0013] After the load transfer, the economic compensation received by the user is:

[0014]

[0015] Where: λtrans represents the unit compensation price of transferable load;

[0016] For the processing of absolute value terms in formula (3), an auxiliary variable is introduced and And constraint formula (5) and constraint formula (6) transform it into the linearized form shown in formula (4):

[0017]

[0018]

[0019]

[0020] 1.2 Load reduction possible

[0021] The curtailable load refers to the flexible load that keeps the energy consumption period unchanged and reduces the load power to a certain extent under the premise of meeting the energy demand of users. By providing certain economic compensation for the curtailable load to participate in demand response, the enthusiasm of users can be effectively mobilized and users can be guided to reduce part of the load during peak hours. The curtailable load in each period can be expressed as:

[0022]

[0023] Where: η cut Indicates the load reduction rate; β b,d,h,t It is a 0-1 variable. When the value is 1, it means that the load is reduced at this moment, otherwise it is not reduced. and represents the load power before and after the reduction at time h, respectively. The subscript b is the energy center number. The subscripts t, d, and h are the numbers of the year, typical day, and time period, respectively.

[0024] For the load that can be cut, it is also necessary to limit the number of times it can be cut, which can be expressed as

[0025]

[0026]

[0027] Where: β max N is the upper limit of the number of reductions. max Indicates the maximum number of continuous reductions that can be made to the load;

[0028] After load reduction, the compensation fee received by the user is C cut for:

[0029]

[0030] Where: cut Indicates the unit compensation price for load that can be reduced;

[0031] 2. Design of IES expansion planning model considering flexible electrical loads

[0032] 2.1 Objective Function

[0033] The objective function of IES expansion planning taking into account flexible electric loads is to minimize the total cost of the planning scheme, including investment cost, operating cost, power shortage cost, wind curtailment cost and flexible load dispatch compensation cost, which can be expressed as:

[0034]

[0035] Where: Z is the total planning cost; C inv (t) is the investment cost; C op (t) is the operating cost; C eens (t) is the cost of insufficient electricity; C w (t) is the wind curtailment cost; C flex (t) is the total cost of flexible load compensation scheduling; t is the present value coefficient in the tth year; γ is the capital recovery rate;

[0036] The investment cost is expressed as

[0037]

[0038] Where: N i 、N f 、N c 、N p and N l Respectively represent the number of conventional units, gas boilers, CHP units, PTG devices and transmission lines; B i , B l , B f , B c and B pRespectively represent the unit capacity investment costs of conventional units, transmission lines, gas boilers, CHP and PTG; x i,t 、x l,t 、x f,t 、x c,t and x p,t Respectively represent the operation status of conventional units, transmission lines, gas boilers, CHP and PTG; P i max , P l max , and Respectively represent the capacity of the above equipment; and Respectively represent the minimum commissioning years of the above equipment. Considering that the equipment life cycle is usually longer than its planned life, depreciation treatment is adopted, ε i , ε l , ε f , ε c , ε p are the net residual value ratios of conventional units, transmission lines, gas boilers, CHP equipment and PTG devices, respectively. i 、M l 、M f 、M c 、M p They are the service life of conventional units, transmission lines, gas boilers, CHP equipment and PTG devices respectively;

[0039] The operating cost is expressed as:

[0040]

[0041] Where: N gs Indicates the quantity of natural gas source; d 0 is the number of typical days; i , O f , O c , O p and O gs Represent the unit operating costs of conventional units, gas boilers, CHP, PTG and natural gas sources respectively; P i,d,h,t , H f,d,h,t , P c,d,h,t , P p.d.h.t and S gs,d,h,t Respectively represent the output value of the above equipment per hour per typical day per year;

[0042] The cost of insufficient power is expressed as:

[0043]

[0044] in: and ΔLb are the unit power shortage cost and power shortage amount of energy center b respectively;

[0045] The cost of wind curtailment is expressed as:

[0046]

[0047] The present value factor is expressed as

[0048] λ t =1 / (1+τ) t-1 (16)

[0049] The flexible load dispatch compensation cost is expressed as

[0050] C flex (t) = C trans (t)+C cut (t) (17)

[0051] in: is the unit wind curtailment cost; ΔC b is the wind curtailment volume of energy center b; τ is the capital discount rate;

[0052] 2.2 Constraints

[0053] The constraints of the integrated energy system expansion plan include: equipment commissioning status constraints, operation constraints, power system constraints, thermal system constraints, and natural gas system constraints;

[0054] 2.2.1 Equipment Operation Status Constraints

[0055] When the device to be put into operation is put into the integrated energy system, the operation status changes from 0 to 1, and the operation status remains unchanged in the subsequent years. If the year to be put into operation is less than the minimum operation year of the equipment, the device will not participate in the operation. It is expressed as follows

[0056] x a,t-1 ≤x a,t

[0057] x a,t =0

[0058] Where: i + , l + 、f + 、c + 、p + They represent the candidate devices of conventional units, transmission lines, gas boilers, CHP and PTG respectively; x a,t A 0-1 variable representing the operational status of different equipment, where 1 represents operational equipment and 0 represents equipment to be operational; The minimum year in which each equipment can be put into operation;

[0059] 2.2.2 Operational constraints

[0060] The output constraint of conventional units is

[0061]

[0062] The power flow constraint of the transmission line is:

[0063] |P l,d,h,t |≤P l max x l,t ,l∈{L,l +} (twenty one)

[0064]

[0065] Among them: U represents existing conventional units, L represents existing lines, l + represents the candidate line, P l,d,h,t is the line transmission power; B l is the line admittance; θ is the phase angle of the nodes at both ends of the line; M is a large number, here it is 10 15 ;

[0066] The operating constraints of the gas boiler are:

[0067]

[0068]

[0069] Among them: F represents the existing gas boiler, H f,d,h,t Indicates the heating power of the gas boiler, G f,d,h,t is the gas consumption power of the gas boiler, is the thermal efficiency of the gas boiler;

[0070] The operating constraints of the CHP plant are

[0071]

[0072]

[0073]

[0074] Where: P c,d,h,t and H c,d,h,t They represent the power generation and heat generation of the CHP unit, and are the minimum and maximum output of the CHP unit, G c,d,h,t is the gas consumption power of the CHP unit, and are the electrical efficiency and thermal efficiency of CHP respectively;

[0075] The operating constraints of the PTG unit are

[0076] G p,d,h,t =η p P p,d,h,t (28)

[0077]

[0078] Where: η p is the efficiency of PTG, G p,d,h,t is the gas production power of PTG;

[0079] 2.2.3 Power system constraints

[0080] The power supply and demand balance constraint formula and wind abandonment constraint formula are as follows:

[0081]

[0082]

[0083]

[0084] Where: ΔP b,d,h,t represents the power shortage per energy center per year and per hour. is the electric load of the bth energy center. The proportion of electric load of different energy centers is different. p∈b represents the PTG device p located in the bth energy center, and so on. r(l) and k(l) are the terminal node and the starting node of the line respectively. Indicates the maximum output of the wind farm, P w,d,h,t Indicates the actual output of the wind farm, ΔC b,d,h,t represents the abandoned wind power, ρ is the probability of the wind farm output reaching the maximum value, this probability conforms to certain quarterly fluctuation characteristics, and the historical data of a wind farm in northwest my country is selected as a sample, and the corresponding probability curve is obtained by using the non-parametric fitting method;

[0085] 2.2.4 Thermal system constraints

[0086]

[0087] in: is the heat load of the b-th energy center, c∈b represents the CHP unit c located in the b-th energy center, and f∈b represents the gas boiler f located in the b-th energy center;

[0088] 2.2.5 Natural Gas System Constraints

[0089] The natural gas system needs to meet the natural gas supply and demand balance, the upper and lower limits of gas source production, and the upper and lower limits of natural gas flow, as shown below

[0090]

[0091]

[0092]

[0093] in: represents the gas load of energy center b, G pp,d,h,t represents the natural gas flow rate per hour per typical day of the natural gas pipeline pp per year; r(pp) and k(pp) represent the end and start nodes of the natural gas pipeline respectively; Indicates the upper and lower limits of gas production from the gas source; They represent the upper and lower limits of natural gas flow, respectively.

[0094] The above-mentioned IES extended planning model taking into account flexible electric loads is a mixed integer linear programming model, and the optimal solution can be obtained by calling a commercial solver.

[0095] The present invention introduces flexible electric load on the "load side" of the integrated energy system, and constructs an IES expansion planning model by considering the unit investment cost, operation cost, wind curtailment cost, power shortage cost and flexible load scheduling compensation cost. The comparison of the results of four different scenarios shows that after taking the flexible electric load into account, although the investment cost increases slightly, the unit operation cost, power shortage cost and total cost all show a downward trend, indicating that the flexible electric load can effectively improve the economy and reliability of the integrated energy system. At the same time, under the action of the PTG device, the system's wind curtailment phenomenon has been significantly improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0096] Figure 1 : IES basic structure diagram;

[0097] Figure 2 : IEEE 14-NGS14 test system diagram;

[0098] Figure 3 : Output variation curve of conventional units;

[0099] Figure 4 : PTG device power consumption change curve;

[0100] Figure 5 :Annual changes in wind abandonment volume;

[0101] Figure 6 : The annual trend of power shortage;

[0102] Figure 7: The change curve of load reduction in the decoupling and coupling scenarios. DETAILED DESCRIPTION

[0103] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0104] Example 1

[0105] The basic structure of IES is shown in the attached Figure 1 shown.

[0106] On the energy supply side, most of the electricity required by IES is provided by the power grid and wind farms, and the natural gas grid is mainly responsible for the natural gas energy required by IES. In terms of energy coupling, power to gas (PTG) equipment can convert electricity into natural gas energy, improving the system's ability to absorb new energy; combined heat and power (CHP) devices consume natural gas energy in the system to generate electricity and heat energy, maximizing energy utilization efficiency; gas boilers consume natural gas energy and generate heat energy. On the energy demand side, the electric load includes rigid electric load and flexible electric load, and the gas load and heat load mainly provide users with natural gas energy and heat energy.

[0107] IES can also be seen as an energy center, where energy production, transmission, storage and consumption are completed, which can effectively improve the efficiency and flexibility of the integrated energy system.

[0108] 1. Design flexible electrical load model

[0109] 1.1 Transferable load

[0110] Transferable load refers to a flexible load that can be transferred within a specified time period and ensure that the total amount of load remains unchanged before and after the transfer.

[0111] Assume that the acceptable transfer interval of the transferable load is The constraint to ensure that the required power remains unchanged before and after load transfer is:

[0112]

[0113]

[0114] in: and are the power of the transferable load before and after the transfer in period h respectively; and are the minimum load power and maximum load power in each period after transfer, respectively. 0 The total number of time periods in a day.

[0115] After the load transfer, the economic compensation received by the user is

[0116]

[0117] Where: trans Indicates the unit compensation price of the transferable load.

[0118] For the processing of absolute value terms in formula (3), auxiliary variables can be introduced and And the constraint formula (5) and constraint formula (6) transform it into the linear form shown in formula (4)

[0119]

[0120]

[0121]

[0122] 1.2 Load reduction possible

[0123] The curtailable load refers to the flexible load that keeps the energy consumption period unchanged and reduces the load power to a certain extent under the premise of meeting the energy demand of users. By providing certain economic compensation for the curtailable load to participate in demand response, the enthusiasm of users can be effectively mobilized and users can be guided to reduce part of the load during peak hours. The curtailable load in each period can be expressed as

[0124]

[0125] Where: η cut Indicates the load reduction rate; β b,d,h,t It is a 0-1 variable. When the value is 1, it means that the load is reduced at this moment, otherwise it is not reduced. and They represent the load power before and after the reduction at time h. The subscript b is the energy center number; the subscripts t, d, and h are the numbers of the year, typical day, and time period, respectively.

[0126] For the load that can be cut, it is also necessary to limit the number of times it can be cut, which can be expressed as

[0127]

[0128]

[0129] Where: β maxN is the upper limit of the number of reductions. max Indicates the maximum number of continuous reductions that can be made to the load.

[0130] After load reduction, the compensation fee received by the user is C cut for

[0131]

[0132] Where: cut Indicates the unit compensation price for load reduction.

[0133] 2. Design of IES expansion planning model considering flexible electrical loads

[0134] 2.1 Objective Function

[0135] The objective function of the IES expansion planning considering flexible electric load is to minimize the total cost of the planning scheme, including investment cost, operation cost, power shortage cost, wind curtailment cost and flexible load dispatch compensation cost, which is expressed as

[0136]

[0137] Where: Z is the total planning cost; C inv (t) is the investment cost; C op (t) is the operating cost; C eens (t) is the cost of insufficient electricity; C w (t) is the wind curtailment cost; C flex (t) is the total cost of flexible load compensation scheduling; t is the present value coefficient in the tth year; γ is the capital recovery rate.

[0138] The investment cost is expressed as:

[0139]

[0140] Where: N i 、N f 、N c 、N p and N l Respectively represent the number of conventional units, gas boilers, CHP units, PTG devices and transmission lines; B i , B l , B f , B c and B p Respectively represent the unit capacity investment costs of conventional units, transmission lines, gas boilers, CHP and PTG; x i,t 、x l,t 、x f,t 、x c,t and x p,tRespectively represent the operation status of conventional units, transmission lines, gas boilers, CHP and PTG; P i max , P l max , and Respectively represent the capacity of the above equipment; and Respectively represent the minimum commissioning years of the above equipment. Considering that the equipment life cycle is usually longer than its planned life, depreciation treatment is adopted, ε i , ε l , ε f , ε c , ε p are the net residual value ratios of conventional units, transmission lines, gas boilers, CHP equipment and PTG devices, respectively. i 、M l 、M f 、M c 、M p They are the service lives of conventional units, transmission lines, gas boilers, CHP equipment and PTG devices respectively.

[0141] The operating cost is expressed as:

[0142]

[0143] Where: N gs Indicates the quantity of natural gas source; d 0 is the number of typical days; O i , O f , O c , O p and O gs Represent the unit operating costs of conventional units, gas boilers, CHP, PTG and natural gas sources respectively; P i,d,h,t , H f,d,h,t , P c,d,h,t , P p.d.h.t and S gs,d,h,t Respectively represent the output value of the above equipment per hour per typical day per year.

[0144] The cost of insufficient power is expressed as:

[0145]

[0146] in: and ΔL b are the unit power shortage cost and power shortage amount of energy center b respectively;

[0147] The cost of wind curtailment is expressed as:

[0148]

[0149] The present value factor is expressed as:

[0150] λ t =1 / (1+τ) t-1 (52)

[0151] The flexible load dispatch compensation cost is expressed as

[0152] C flex (t) = C trans (t)+C cut (t) (53)

[0153] in: is the unit wind curtailment cost; ΔC b is the wind curtailment volume of energy center b; τ is the capital discount rate;

[0154] 2.2 Constraints

[0155] The constraints of the integrated energy system expansion plan include: equipment commissioning status constraints, operation constraints, power system constraints, thermal system constraints, and natural gas system constraints;

[0156] 2.2.1 Equipment Operation Status Constraints

[0157] When the device to be put into operation is put into the integrated energy system, the operation status changes from 0 to 1, and the operation status remains unchanged in the subsequent years. If the year to be put into operation is less than the minimum operation year of the equipment, the device will not participate in the operation. It is expressed as follows

[0158] x a,t-1 ≤x a,t

[0159] x a,t =0

[0160] Where: i + , l + 、f + 、c + 、p + They represent the candidate devices of conventional units, transmission lines, gas boilers, CHP and PTG respectively; x a,t A 0-1 variable representing the operational status of different equipment, where 1 represents operational equipment and 0 represents equipment to be operational; The minimum year in which each equipment can be put into operation.

[0161] 2.2.2 Operational constraints

[0162] The output constraint of conventional units is

[0163]

[0164] The power flow constraint of the transmission line is

[0165]

[0166]

[0167] Among them: U represents existing conventional units, L represents existing lines, l + Represents candidate line.P l,d,h,t is the line transmission power; B l is the line admittance; θ is the phase angle of the nodes at both ends of the line; M is a large number, here it is 10 15 ;

[0168] The operating constraints of the gas boiler are

[0169]

[0170]

[0171] Among them: F represents the existing gas boiler, H f,d,h,t Indicates the heating power of the gas boiler, G f,d,h,t is the gas consumption power of the gas boiler, is the thermal efficiency of gas boiler.

[0172] The operating constraints of the CHP plant are

[0173]

[0174]

[0175]

[0176] Where: P c,d,h,t and H c,d,h,t They represent the power generation and heat generation of the CHP unit, and are the minimum and maximum output of the CHP unit, G c,d,h,t is the gas consumption power of the CHP unit, and are the electrical efficiency and thermal efficiency of CHP respectively.

[0177] The operating constraints of the PTG unit are:

[0178] G p,d,h,t =η p P p,d,h,t ; (64)

[0179]

[0180] Where: η p is the efficiency of PTG, G p,d,h,t is the gas production power of PTG;

[0181] 2.2.3 Power system constraints

[0182] The power supply and demand balance constraint formula and wind abandonment constraint formula are as follows:

[0183]

[0184]

[0185]

[0186] Where: ΔP b,d,h,t represents the power shortage per energy center per year and per hour. is the electric load of the bth energy center, and the proportion of electric load of different energy centers is different. p∈b represents the PTG device p located in the bth energy center, and so on. r(l) and k(l) are the terminal node and the starting node of the line respectively. Indicates the maximum output of the wind farm, P w,d,h,t Indicates the actual output of the wind farm, ΔC b,d,h,t represents the abandoned wind power. ρ is the probability of the wind farm output reaching the maximum value, which conforms to certain quarterly fluctuation characteristics. [24,25] . Select the historical data of a wind farm in Northwest my country as a sample, and use the non-parametric fitting method to obtain the corresponding probability curve, as shown in the attached figure. Figure 1 shown.

[0187] 2.2.4 Thermal system constraints

[0188]

[0189] in: is the heat load of the b-th energy center, c∈b represents the CHP unit c located in the b-th energy center, and f∈b represents the gas boiler f located in the b-th energy center;

[0190] 2.2.5 Natural Gas System Constraints

[0191] The natural gas system needs to meet the natural gas supply and demand balance, the upper and lower limits of gas source production, and the upper and lower limits of natural gas flow, as shown below

[0192]

[0193]

[0194]

[0195] in: represents the gas load of energy center b, G pp,d,h,t represents the natural gas flow rate per hour per typical day of the natural gas pipeline pp per year; r(pp) and k(pp) represent the end and start nodes of the natural gas pipeline respectively; Indicates the upper and lower limits of gas production from the gas source; Respectively represent the upper and lower limits of natural gas flow;

[0196] The above-mentioned IES extended planning model taking into account flexible electric loads is a mixed integer linear programming model, and the optimal solution can be obtained by calling a commercial solver.

[0197] 3. Example Analysis

[0198] 3.1 Example System

[0199] Take the IEEE 14-NGS14 electrical-gas-thermal coupling system as an example

[13] The effectiveness of the IES expansion planning model considering flexible electric load proposed in this paper is verified. The MIP solver is called by GAMS software for solution. The example system is as follows Figure 2 As shown. The power grid includes 12 conventional units (7 existing units, 5 candidates), 27 transmission lines (20 existing units, 7 candidates), 2 wind farms and 14 electric loads; the natural gas network includes 2 gas sources, 13 natural gas pipelines and 3 gas loads; the heat network includes 12 gas boilers (7 existing units, 5 candidates). The energy is converted between the coupling devices CHP and PTG. The system includes 4 candidate CHP units and 4 candidate PTG devices. Conventional units, transmission lines, gas boilers, CHP The parameters of PTG can be found in the literature

[13] . The nodes where the equipment and loads are located are shown in Appendix 1. The system planning period is 10 years, the capital recovery rate is 10%, the annual discount rate is 5%, and the annual growth rates of electricity, heat and gas loads are 2.5%, 2.5% and 5% respectively. The unit compensation price of transferable load is 12.12USD / MW, and the unit compensation price of curtailable load is 31.82USD / MW. Assume that the unit power shortage cost is 400USD / MWh and the unit wind abandonment cost is 250USD / MWh.

[0200] At the same time, in the four typical days (a total of 96 hours), the transferable load parameters are set within the ranges of [8, 15], [32, 39], [56, 63] and [80, 87] hours, and the user-acceptable load transfer hour ranges are [4, 20], [28, 44], [52, 68] and [76, 92] respectively. At the same time, the reducible load is set in each energy center, and the maximum load reduction times of each energy center in each typical day is set to 20, and the maximum continuous reduction times is set to 3.

[0201] In order to illustrate the effectiveness of the proposed IES extended optimization planning model considering flexible electric loads, the following four typical operation scenarios are set:

[0202] 1) Scenario 1: Without considering the flexible electric load, the system is decoupled and expanded for optimization planning.

[0203] 2) Scenario 2. Considering the access of flexible electric loads, the system is decoupled, expanded and optimized.

[0204] 3) Scenario 3: Without considering the flexible electric load, the system is coupled and expanded for optimization planning.

[0205] 4) Scenario 4. Considering the access of flexible electric loads, the system is coupled and expanded to optimize planning.

[0206] 3.2 Analysis of planning results

[0207] Decoupling planning means not adding coupling devices, such as CHP equipment and PTG devices, to the system and analyzing the changes in various costs in the system; coupling planning means adding CHP, PTG and other energy coupling devices to the system. The specific planning results are shown in Tables 1 and 2.

[0208] As can be seen from Table 1, after adding flexible loads, scenario 2 reduces the commissioning of transmission line L22. Comparing the decoupling and coupling situations, after adding the coupling device, the system reduces the commissioning of gas boilers and is more inclined to commission CHP and PTG devices with high energy conversion efficiency.

[0209] As can be seen from Table 2, after adding flexible electric load, the system's operating cost, wind curtailment cost, power shortage cost and total cost have all decreased significantly, regardless of decoupling or coupling. This shows that flexible electric load can be adjusted in space and time, smooth the load curve, and fill the peak and valley, thereby improving the economy of system operation. At the same time, the PTG device can convert electrical energy into natural gas energy, improve the system's wind power absorption capacity, and make the wind curtailment cost of the coupling planning scheme generally lower than that of the decoupling planning scheme.

[0210] Table 1 Planning results under different scenarios

[0211]

[0212] Note: G, L, F, C and P represent conventional units, transmission lines, gas boilers, CHP units and PTG units in batches, and the numbers in brackets represent the commissioning years of the corresponding equipment.

[0213] Table 2 Costs under different scenarios

[0214]

[0215] 3.3 Analysis of the impact of flexible electrical load on IES

[0216] The impact of flexible electric load on IES is mainly reflected in conventional units, PTG devices, wind abandonment and power shortage.

[0217] 1) Analysis of output status of conventional units

[0218] The output state change curve of conventional units is shown in the attached figure. Figure 3 As shown. It can be seen that the output of conventional units in different scenarios shows different trends. Under scenario 1, the output of conventional units increases year by year. From a general perspective, the upward trend is gentle; from a local perspective, the units in the second and sixth years have a slightly larger increase because conventional units G11 and G10 were put into use in these two years; after adding flexible electric loads, the output of conventional units still shows an upward trend, but it is slightly lower than scenario 1. This is because the addition of flexible electric loads reduces part of the load, resulting in a relative decrease in the output of conventional units. Under scenario 3, the output of conventional units in the second and sixth years increased significantly because PTG devices were put into use in these years, and conventional units needed to generate more electricity to meet system needs. After adding flexible electric loads, the output of conventional units in scenario 4 is less than that in scenario 3. This shows that the addition of flexible electric loads can adjust the distribution of loads in time and improve the economy and reliability of system operation.

[0219] 2) PTG device power consumption analysis

[0220] Attached Figure 4 This is the power consumption curve of the PTG device. Figure 4 It can be seen that after PTG was put into use in the second year, its power consumption showed an increasing trend year by year; Scenario 3 and Scenario 4 both put into use two PTGs in the sixth year, so the power consumption of PTG increased rapidly in these two years. By comparing the two curves, it is found that after the flexible electric load is added, the power consumption of PTG increases. This shows that the addition of flexible electric load can adjust the distribution of load in time and reduce the original load at the same time. The PTG device consumes more electricity and converts it into natural gas energy, which can reduce the output of devices with higher operating costs such as gas sources and improve the economy of system operation.

[0221] 3) Analysis of the trend of wind abandonment

[0222] Attached Figure 5 It is the annual change of wind abandonment. As can be seen from the figure, in the decoupling case, after adding flexible electric load, the wind abandonment is significantly reduced. This shows that the existence of flexible electric load can increase the wind power acceptance capacity, thereby reducing the wind abandonment. In the coupling case, after the PTG was put into use in the second year, there was no wind abandonment phenomenon. This shows that the PTG device can convert excess wind energy into natural gas energy and improve the system's wind power absorption capacity. At the same time, by comparing the wind abandonment in the first year of scenario 3 and scenario 4, it is found that the wind abandonment in scenario 4 is lower than that in scenario 3, which shows the positive effect of flexible electric load on wind power absorption.

[0223] 4) Analysis of the trend of power shortage

[0224] Attached Figure 6 The annual trend of power shortage is shown in the attached figure. Figure 7 The curves of load reduction under the decoupling and coupling scenarios are shown. It can be seen that after the flexible electric load is added, the power shortage is significantly reduced. In scenario 2, the power shortage shows a downward trend in the second and sixth years because one conventional unit G11 was put into operation in the second year, and one conventional unit G10 and one line L24 were put into operation in the sixth year. Therefore, the power shortage has decreased significantly in these two years. In scenario 4, the power shortage increased rapidly in the second year because two new PTG devices P1 and P3 were put into operation in that year, which made the load demand exceed the power supply capacity of the system in certain periods, so the load loss was obvious. At the same time, since lines L24, L25 and one conventional unit G10 were put into operation in the sixth year, the power shortage in the sixth year decreased significantly.

[0225] Compare with Figure 7 and attached Figure 6 It can be seen that in scenario 2, the number of load reductions in the sixth year increased significantly, which reduced the system load. In addition, because the unit G10 and line L24 were newly put into operation in that year, the power shortage decreased significantly. Although the number of load reductions in the seventh year was more than that in the sixth year, because no new units were put into operation in that year, and the power load increased at an annual growth rate of 2.5%, the output of the existing units could not meet the needs of the system power load. Therefore, the power shortage in the seventh year was slightly greater than that in the sixth year. In scenario 4, the number of load reductions in the second year increased significantly, but the power shortage grew rapidly in that year because two PTG devices P1 and P3 were put into operation in that year, which made the load demand exceed the power supply capacity of the system in certain periods, so the load loss was obvious; in the sixth year, the number of load reductions increased significantly, which reduced the system power load. At the same time, lines L24, L25 and a conventional unit G10 were put into operation in that year, which led to a significant decrease in power shortages. This shows that the number of load reductions can affect the reliability of the system to a certain extent.

Claims

1. A method for planning expansion of an integrated energy system taking into account flexible electric loads, characterized by comprising the following steps: 1) Establish a flexible electrical load model 1.1 Transferable load Assume that the acceptable transfer interval of the transferable load is The constraint to ensure that the required power remains unchanged before and after load transfer is: in: and are the power of the transferable load before and after the transfer in period h respectively; and are the minimum load power and maximum load power in each period after transfer, respectively. 0 is the total number of sessions within the day; After the load transfer, the economic compensation received by the user is: Where: trans represents the unit compensation price of the transferable load; To deal with the absolute value term in formula (3), an auxiliary variable is introduced and And constraint formula (5) and constraint formula (6) transform it into the linearized form shown in formula (4): 1.2 Load reduction possible The load that can be reduced in each period can be expressed as: Where: η cut Indicates the load reduction rate; β b,d,h,t It is a 0-1 variable. When the value is 1, it means that the load is reduced at this moment, otherwise it is not reduced. and represents the load power before and after the reduction at time h, respectively. The subscript b is the energy center number. The subscripts t, d, and h are the numbers of the year, typical day, and time period, respectively. 2) Design an IES expansion planning model taking into account flexible electrical loads 2.1 Objective Function The objective function of IES expansion planning taking into account flexible electric loads is to minimize the total cost of the planning scheme, including investment cost, operating cost, power shortage cost, wind curtailment cost and flexible load dispatch compensation cost, which can be expressed as: Where: Z is the total planning cost; C inv (t) is the investment cost; C op (t) is the operating cost; C eens (t) is the cost of insufficient electricity; C w (t) is the wind curtailment cost; C flex (t) is the total cost of flexible load compensation scheduling; t is the present value coefficient in the tth year; γ is the capital recovery rate; The investment cost is expressed as Where: N i 、N f 、N c 、N p and N l Respectively represent the number of conventional units, gas boilers, CHP units, PTG devices and transmission lines; B i , B l , B f , B c and B p Respectively represent the unit capacity investment costs of conventional units, transmission lines, gas boilers, CHP and PTG; x i,t 、x l,t 、x f,t 、x c,t and x p,t Respectively represent the operation status of conventional units, transmission lines, gas boilers, CHP and PTG; P i max , P l max , and Respectively represent the capacity of the above equipment; and They represent the minimum operation years of the above equipment respectively. Considering that the equipment life cycle is longer than its planned life, depreciation treatment is adopted. ε i , ε l , ε f , ε c , ε p are the net residual value ratios of conventional units, transmission lines, gas boilers, CHP equipment and PTG devices, respectively. i 、M l 、M f 、M c 、M p They are the service life of conventional units, transmission lines, gas boilers, CHP equipment and PTG devices respectively; The operating cost is expressed as: Where: N gs Indicates the quantity of natural gas source; d 0 is the number of typical days; O i , O f , O c , O p and O gs Represent the unit operating costs of conventional units, gas boilers, CHP, PTG and natural gas sources respectively; P i,d,h,t , H f,d,h,t , P c,d,h,t , P p.d.h.t and S gs,d,h,t Respectively represent the output value of the above equipment per hour per typical day per year; The cost of insufficient power is expressed as: in: and ΔL b are the unit power shortage cost and power shortage amount of energy center b respectively; The cost of wind curtailment is expressed as: The present value factor is expressed as: l t =1 / (1+τ) t-1 (13) The flexible load dispatch compensation cost is expressed as C flex (t)=C trans (t)+C cut (t) (14) in: is the unit wind curtailment cost; ΔC b is the wind curtailment volume of energy center b; τ is the capital discount rate; 2.2 Constraints The constraints of the integrated energy system expansion plan include: equipment commissioning status constraints, operation constraints, power system constraints, thermal system constraints, and natural gas system constraints; 2.2.1 Equipment Operation Status Constraints When the device to be put into operation is put into the integrated energy system, the operation status changes from 0 to 1, and the operation status remains unchanged in the subsequent years. If the year to be put into operation is less than the minimum operation year of the equipment, the device will not participate in the operation, which is expressed as follows Where: i + , l + 、f + 、c + 、p + They represent the candidate devices of conventional units, transmission lines, gas boilers, CHP and PTG respectively; x a,t A 0-1 variable representing the operational status of different equipment, where 1 represents operational equipment and 0 represents equipment to be operational; The minimum year in which each equipment can be put into operation; 2.2.2 Operational constraints The output constraints of conventional units are: P i min x i,t ≤P i,d,h,t ≤P i max x i,t ,i∈{U,i + } (17) The power flow constraint of the transmission line is: |P l,d,h,t |≤P l max x l,t ,l∈{L,l + } (18) Among them: U represents existing conventional units, L represents existing lines, l + represents the candidate line, P l,d,h,t is the line transmission power; B l is the line admittance; θ is the phase angle of the nodes at both ends of the line; M is a large number, here it is 10 15 ; The operating constraints of the gas boiler are: Among them: F represents the existing gas boiler, H f,d,h,t Indicates the heating power of the gas boiler, G f,d,h,t is the gas consumption power of the gas boiler, is the thermal efficiency of the gas boiler; The operating constraints of the CHP plant are Where: P c,d,h,t and H c,d,h,t Respectively represent the power generation and heat generation of the CHP unit, P c min and are the minimum and maximum output of the CHP unit, G c,d,h,t is the gas consumption power of the CHP unit, and are the electrical efficiency and thermal efficiency of CHP respectively; The operating constraints of the PTG unit are G p,d,h,t =the p P p,d,h,t (25) Where: η p is the efficiency of PTG, G p,d,h,t is the gas production power of PTG; 2.2.3 Power system constraints The power supply and demand balance constraint formula and wind abandonment constraint formula are as follows: Where: ΔP b,d,h,t represents the power shortage per energy center per year and per hour. is the electric load of the bth energy center. The proportion of electric load of different energy centers is different. p∈b represents the PTG device p located in the bth energy center, and so on. r(l) and k(l) are the terminal node and the starting node of the line respectively. Indicates the maximum output of the wind farm, P w,d,h,t Indicates the actual output of the wind farm, ΔC b,d,h,t represents the abandoned wind power, ρ is the probability of the wind farm output reaching the maximum value, this probability conforms to the quarterly fluctuation characteristics, the historical data of a wind farm in northwest my country is selected as a sample, and the corresponding probability curve is obtained by using the non-parametric fitting method; 2.2.4 Thermal system constraints in: is the heat load of the b-th energy center, c∈b represents the CHP unit c located in the b-th energy center, and f∈b represents the gas boiler f located in the b-th energy center; 2.2.5 Natural Gas System Constraints The natural gas system needs to meet the natural gas supply and demand balance, the upper and lower limits of gas source production, and the upper and lower limits of natural gas flow, as shown below in: represents the gas load of energy center b, G pp,d,h,t represents the natural gas flow rate per hour per typical day of the natural gas pipeline pp per year; r(pp) and k(pp) represent the end and start nodes of the natural gas pipeline respectively; Indicates the upper and lower limits of gas production from the gas source; Respectively represent the upper and lower limits of natural gas flow; The above-mentioned IES extended planning model taking into account flexible electric loads is a mixed integer linear programming model, and the optimal solution is obtained by calling a commercial solver.

2. The method for expansion planning of an integrated energy system taking into account flexible electric loads according to claim 1, wherein the load that can be cut also needs to be limited in the number of times it can be cut, which is expressed as: in: β max N is the upper limit of the number of reductions. max Indicates the maximum number of continuous reductions that can be made to the load; After load reduction, the compensation fee received by the user is C cut for: Where: cut Indicates the unit compensation price for load reduction.

Citation Information

Patent Citations

  • Regional integrated energy system capacity configuration method considering electric-thermal flexible load

    CN113690879A

  • Building energy optimization system with capacity market program (CMP) planning

    US20190303830A1