Control method of intelligent positioning and attitude determination device for tunnel boring machine
By installing an intelligent positioning and attitude-setting device on the tunnel boring machine and using laser ranging and angle sensors, the positioning and attitude monitoring of the tunnel boring machine are simplified, the problems of complex operation and low precision in the existing technology are solved, and efficient and accurate tunneling is achieved. Machine positioning and attitude setting.
Patent Information
- Application Number
- CN202210611907.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-05-31
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2042-05-31
AI Technical Summary
The existing tunnel boring machine positioning and attitude-fixing devices are complex to operate, difficult to fuse and analyze data, and have low accuracy. They require frequent corrections and adjustments, making it difficult to meet the needs of intelligent construction of coal mines.
An intelligent positioning and attitude device including a fixed protective shell, a rotating base, a rotating table, a laser ranging transmitter and a signal receiving target is used. Through laser ranging and angle sensor monitoring, the position and attitude of the tunnel boring machine are determined by calculating trigonometric functions. Simplify data collection and precision measurements.
It achieves precise positioning and attitude determination of the tunnel boring machine, reduces operational complexity and data processing difficulty, improves measurement accuracy, and reduces costs and data measurement.
Smart Images

Figure CN115060161B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of coal mining, and in particular to an intelligent positioning and attitude determination device for a roadheader and a control method thereof. Background Art
[0002] Intelligent coal mines are the core technical support for the high-quality development of the coal industry, and intelligent tunneling working faces are an important part of intelligent coal mine construction. Intelligent tunneling requires tunneling machines to be able to achieve autonomous walking and intelligent adaptive cutting, and the precise posture and positioning of tunneling machines are the basis for realizing intelligent tunneling operations such as intelligent adaptive cutting of tunneling machines.
[0003] In the related art, the manufacturing enterprises of tunnel boring machines mainly use total stations, laser targets, ultra-wideband (UWB) and inertial navigation systems to determine the position and attitude of the tunnel boring machine. However, the above methods require the cooperation of multiple measuring equipment, and the time axis unification and fusion analysis of the collected data. There are problems such as complex operation, difficulty in data fusion analysis, low positioning and attitude determination accuracy, and frequent proofreading and adjustment. For example, the related art adopts a method for determining the posture of the tunnel boring machine body based on three laser targets. This method mainly constructs a three-laser point target image, and then uses the machine vision method to establish the posture solution model of the tunnel boring machine body, so as to determine the position and attitude of the tunnel boring machine. However, due to the poor light in the well, this method still has problems such as complex operation process and difficulty in data processing. The related art also proposes a spatial positioning method for the cutting head of a cantilevered tunnel boring machine. This method uses inertial navigation, total stations, etc. to determine the posture of the tunnel boring machine. This method belongs to the traditional method, and there are problems such as large amount of solution data, complex operation, and low positioning and attitude determination accuracy. Related technologies also propose specific spatial measurement methods and systems based on laser pose targets and machine vision. The spatial pose of the tunnel boring machine is solved by measuring the center line and coordinates of the laser pose target and the relative position relationship of each measuring camera. However, the relative positions of each measuring camera in this method are difficult to obtain accurately, and the underground environment has a certain impact on machine vision, resulting in low positioning and pose determination accuracy.
[0004] Based on the above analysis, it can be seen that in the relevant technology, the attitude and positioning devices of the tunnel boring machine mainly use a variety of equipment for mutual calibration and calibration, which has problems such as complex operation, difficulty in data fusion analysis, low positioning and attitude accuracy, and the need for frequent proofreading and adjustment, which urgently need to be improved. Summary of the invention
[0005] The purpose of this application is to solve one of the above-mentioned technical problems at least to a certain extent.
[0006] To this end, the first purpose of this application is to propose an intelligent positioning and attitude determination device for a tunnel boring machine. The positioning and attitude determination device can be used to determine the spatial position and attitude of the tunnel boring machine. The device has a simple structure, convenient data collection, and high measurement accuracy. It solves many problems of traditional positioning and attitude determination devices, such as complex operation, large amount of data calculation, and low positioning and attitude determination accuracy.
[0007] The second purpose of the present application is to provide a control method for an intelligent positioning and attitude determination device of a tunnel boring machine.
[0008] A third object of the present application is to provide a non-transitory computer-readable storage medium.
[0009] To achieve the above-mentioned purpose, the first embodiment of the present application proposes an intelligent positioning and attitude determination device for a roadheader, the device comprising: a fixed protective shell, a rotating base, a rotating table, a first rotation angle sensor, two fixed ear plates, a laser ranging transmitter, a rotating shaft, a second rotation angle sensor, a horizontal reference component, and a signal receiving target, wherein:
[0010] The rotating base is fixedly connected to the fixed protective shell;
[0011] The rotating platform is connected to the rotating base and is used to rotate at a corresponding angle around the vertical axis of the rotating platform;
[0012] The first rotation angle sensor is disposed in the rotating table and is used to monitor the rotation angle of the rotating table;
[0013] The two fixed ear plates are respectively fixed on both sides of the upper surface of the rotating table;
[0014] The laser ranging transmitter is connected to the fixed ear plate through the rotating shaft, and rotates at a corresponding angle through the rotating shaft. The laser ranging transmitter is used to transmit a laser signal to the signal receiving target;
[0015] The second rotation angle sensor is disposed in the rotation shaft and is used to monitor the rotation angle of the rotation shaft;
[0016] The horizontal reference component is fixedly arranged on the inner side of the fixed protective shell, and is used to calibrate the initial rotation position of the rotating table and the rotating shaft;
[0017] The fixed protective shell, the rotating base, the rotating table, the first rotation angle sensor, the fixed ear plate, the laser ranging transmitter, the rotating shaft, the second rotation angle sensor, and the horizontal reference connection constitute a tunneling machine posture sensing device;
[0018] The signal receiving target is arranged at the upper position of the tunnel behind the tunnel boring machine, and is used to receive the laser signal emitted by the laser ranging transmitter, so as to locate and determine the posture of the tunnel boring machine based on the relevant information of the laser signal.
[0019] In addition, the intelligent positioning and attitude determination device for a tunnel boring machine according to the embodiment of the present application also has the following additional technical features:
[0020] Optionally, in some embodiments, the tunnel boring machine posture sensing device is fixedly arranged at the rear middle position of the tunnel boring machine, and the initial values of the first rotation angle sensor and the second rotation angle sensor are pre-calibrated.
[0021] Optionally, in some embodiments, the distances from both sides of the signal receiving target to the walls on both sides of the tunnel are equal, and the signal receiving target is specifically used to sense the landing position of the laser signal emitted by the laser ranging transmitter.
[0022] To achieve the above object, a second embodiment of the present invention provides a control method for an intelligent positioning and attitude determination device for a tunnel boring machine, wherein the intelligent positioning and attitude determination device for a tunnel boring machine is the intelligent positioning and attitude determination device for a tunnel boring machine of the first aspect, and the method comprises:
[0023] The tunnel boring machine posture sensing device is installed at the middle position of the rear part of the tunnel boring machine, and the signal receiving target is set at the upper position of the tunnel behind the tunnel boring machine;
[0024] Establishing a spatial coordinate system for the signal receiving target, and calibrating the initial values of the first rotation angle sensor and the second rotation angle sensor;
[0025] Turn on the laser rangefinder transmitter, obtain the initial landing point A of the laser signal on the signal receiving target, and control the rotating table to rotate at a corresponding angle to obtain the first landing point B corresponding to the shortest distance measured by the laser rangefinder transmitter, and monitor the rotation angle θ of the laser rangefinder transmitter from the initial landing point A to the first landing point B through the first rotation angle sensor;
[0026] Fix the rotating table, control the rotating shaft to rotate 10° to 15° in a direction that gradually increases the distance value measured by the laser ranging transmitter, and obtain the final landing point C of the laser signal on the signal receiving target after the rotating shaft rotates;
[0027] Obtaining the first distance between the signal transmitting point S measured by the laser ranging transmitter and the initial landing point A, the second distance between the signal transmitting point S and the first landing point B, and the third distance between the signal transmitting point S and the second landing point C, respectively, and combining the coordinate values of the initial landing point A, the first landing point B, and the second landing point C, and calculating the position coordinates of the vertical projection point T of the laser ranging transmitter on the signal receiving target, and the fourth distance between the signal transmitting point and the vertical projection point T based on the trigonometric function relationship;
[0028] The position coordinates of the tunnel boring machine in the spatial coordinate system are determined according to the position coordinates of the vertical projection point T and the fourth distance, and the deflection angles in each plane of the spatial coordinate system are used as the posture information of the tunnel boring machine.
[0029] In addition, the control method of the intelligent positioning and posture determination device of the tunnel boring machine in the embodiment of the present application also has the following additional technical features:
[0030] Optionally, in some embodiments, a spatial coordinate system is established for the signal receiving target, including: establishing the spatial coordinate system with the midpoint of the lower edge line of the signal receiving target as the origin, the direction perpendicular to the horizontal ground of the tunnel as the z-axis direction, the direction perpendicular to the side of the tunnel as the x-axis direction, and the direction of the centerline of the tunnel as the y-axis direction.
[0031] Optionally, in some embodiments, the initial values of the first rotation angle sensor and the second rotation angle sensor are calibrated, including: placing the tunnel boring machine on horizontal ground, so that the upper surface of the fixed protective shell is parallel to the horizontal ground and the left and right sides of the fixed protective shell are parallel to the vertical section of the length direction of the tunnel boring machine; controlling the rotating table and the rotating axis to rotate to a corresponding angle, so that the laser emitted by the laser ranging transmitter is aligned with the horizontal reference; maintaining the state of the rotating table, rotating the rotating axis 180°, and calibrating the current angle values of the first rotation angle sensor 4 and the second rotation angle sensor to the initial values.
[0032] Optionally, in some embodiments, the fourth distance between the signal emission point and the vertical projection point T is calculated by the following formula:
[0033]
[0034] Among them, l ST is the fourth distance, l BT is the distance between the first landing point B and the vertical projection point T, l SB is the second distance, l BC is the distance between the first landing point B and the second landing point C, l SC It is the third distance.
[0035] Optionally, in some embodiments, the position coordinates of the tunnel boring machine in the spatial coordinate system are determined by the following formula:
[0036]
[0037] Among them, x T is the value of the vertical projection point T on the x-axis, z T is the value of the vertical projection point T on the z-axis.
[0038] Optionally, in some embodiments, the deflection angles in each plane of the spatial coordinate system are used as the posture information of the roadheader, including:
[0039] Determine a first angle β between a line connecting the initial landing point A and the first landing point B and the x-axis, and determine a second angle γ between a line connecting the signal transmission point S and the first landing point B and a line connecting the signal transmission point S and the vertical projection point T by the following formula:
[0040]
[0041] The rotation angle θ is the deflection angle in the plane where the x-axis and the y-axis are located, the first angle β is the deflection angle in the plane where the x-axis and the z-axis are located, and the second angle γ is the deflection angle in the plane where the y-axis and the z-axis are located.
[0042] To achieve the above-mentioned objectives, the third aspect of the present invention proposes a non-temporary computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, it implements the control method of the intelligent positioning and attitude determination device of the tunnel boring machine as described in any one of the above-mentioned second aspect embodiments.
[0043] The technical solution provided by the embodiments of the present application brings at least the following beneficial effects:
[0044] The present application can monitor the position and attitude information of the tunnel boring machine by installing a tunnel boring machine position and attitude sensing device on the tunnel boring machine and installing a signal receiving target in the tunnel, thereby avoiding the setting of multiple measuring equipment for collaborative detection and eliminating the processing steps such as fusion analysis of multiple collected data, reducing the difficulty of data processing and the complexity of operation, saving the cost of intelligent positioning and attitude determination of the tunnel boring machine, and having significant advantages such as simple structure, convenient data collection, small data measurement and high measurement accuracy. It better solves the problems existing in the positioning and attitude determination scheme of traditional tunnel boring machines, such as complex operation, high difficulty in data fusion analysis, low positioning and attitude determination accuracy and the need for frequent proofreading and adjustment.
[0045] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0046] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0047] Figure 1 A schematic diagram of the structure of an intelligent positioning and posture determination device for a tunnel boring machine proposed in an embodiment of the present application;
[0048] Figure 2 A schematic diagram of the structure of a specific intelligent positioning and posture determination device for a tunnel boring machine proposed in an embodiment of the present application;
[0049] Figure 3 A schematic diagram of the landing point of a laser signal of a laser ranging transmitter on a signal receiving target proposed in an embodiment of the present application;
[0050] Figure 4 This is a flow chart of a control method for an intelligent positioning and attitude determination device of a tunnel boring machine proposed in an embodiment of the present application.
[0051] Figure 5 A schematic diagram of a specific measurement and determination of the attitude information of a roadheader proposed in an embodiment of the present application;
[0052] Figure 6 A schematic diagram of the triangular relationship of the vertical projection of a laser signal on a signal receiving target proposed in an embodiment of the present application. DETAILED DESCRIPTION
[0053] Embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0054] The following describes an intelligent positioning and posture determination device for a tunnel boring machine and a control method thereof in accordance with an embodiment of the present application with reference to the accompanying drawings.
[0055] Figure 1 This is a schematic diagram of the structure of an intelligent positioning and posture determination device for a tunnel boring machine proposed in an embodiment of the present application, such as Figure 1 As shown, the device includes: a fixed protective shell 1, a rotating base 2, a rotating platform 3, a first rotation angle sensor 4, two fixed ear plates 5, a laser ranging transmitter 6, a rotating shaft 7, a second rotation angle sensor 8, a horizontal reference component 9, and a signal receiving target 10. Among them, the second rotation angle sensor 8 and the horizontal reference component 9 Figure 1 In order to more clearly describe the connection relationship and configuration of the above components, the following Figure 1 and Figure 2Provide detailed explanation.
[0056] Wherein, the rotating base 2 is fixedly connected to a fixed protective shell 1.
[0057] The rotating table 3 is connected to the rotating base 2 and is used to rotate a corresponding angle around the vertical axis of the rotating table 3. The rotating table 3 can rotate 360° around its own vertical axis. In the actual measurement process, the rotating table 3 can rotate a corresponding angle according to the measurement needs.
[0058] The first rotation angle sensor 4 is disposed in the rotating table, and is used to monitor the rotation angle of the rotating table 3 .
[0059] The two fixed ear plates 5 are respectively fixed on two sides of the upper surface of the rotating table 3 . The parameters of the two fixed ear plates 5 can be consistent, and they can be symmetrically arranged with respect to the laser ranging transmitter 6 .
[0060] like Figure 2 As shown, the laser rangefinder transmitter 6 is connected to the two fixed ear plates 5 through the rotating shaft 7, and rotates at a corresponding angle through the rotating shaft, that is, the laser rangefinder transmitter 6 can rotate 360° around the rotating shaft 7 driven by the rotating shaft. The laser rangefinder transmitter 6 is used to transmit a laser signal to the signal receiving target 10.
[0061] Continue to refer to Figure 2 As shown, the second rotation angle sensor 8 is disposed in the rotating shaft 7 to monitor the rotation angle of the rotating shaft 7 .
[0062] The horizontal reference component 9 is fixedly disposed on the inner side surface of the fixed protective shell 1 and is used to calibrate the initial rotation position, that is, the initial angle, of the rotating table 3 and the rotating shaft 7 .
[0063] Thus, the fixed protective shell 1, the rotating base 2, the rotating platform 3, the first rotation angle sensor 4, the fixed ear plate 5, the laser ranging transmitter 6, the rotating shaft 7, the second rotation angle sensor 8, and the horizontal reference component 9 are connected in the above-mentioned connection manner to form a tunnel boring machine posture sensing device.
[0064] The signal receiving target 10 is arranged at the upper position of the tunnel behind the tunnel boring machine, and is used to receive the laser signal emitted by the laser ranging transmitter 6, so as to facilitate the subsequent positioning and posture determination of the tunnel boring machine based on the relevant information of the laser signal.
[0065] In one embodiment of the present application, when actually measuring, the tunnel boring machine posture sensing device is fixedly arranged at the middle position of the rear of the tunnel boring machine, and the initial values of the first rotation angle sensor 4 and the second rotation angle sensor 8 are pre-calibrated.
[0066] Specifically, the tunnel boring machine posture sensing device (i.e., components 1 to 9 connected by the above connection method) is fixed at the middle position of the rear of the tunnel boring machine, which is located at the rear of the tunnel boring machine and in the middle position of the width direction of the tunnel boring machine. After the tunnel boring machine posture sensing device is fixed at the middle position of the rear of the tunnel boring machine, it is convenient for the laser ranging transmitter 6 to transmit signals to the signal receiving target 10. In addition, the initial values of the first rotation angle sensor and the second rotation angle sensor are calibrated in advance according to the relevant calibration method, and the first rotation angle sensor 4 and the second rotation angle sensor 8 are adjusted respectively according to the pre-calibrated initial values before measurement.
[0067] In one embodiment of the present application, the distances from both sides of the signal receiving target to the walls on both sides of the tunnel are equal, and the signal receiving target is specifically used to sense the landing position of the laser signal emitted by the laser ranging transmitter.
[0068] Specifically, if Figure 3 As shown, the distances from both sides of the signal receiving target 10 to the walls of both sides of the tunnel 30 are equal, and the surface of the signal receiving target 10 is covered with photosensitive sensors. When the laser beam emitted by the machine posture sensing device 20 hits the surface of the signal receiving target 10, the landing position of the laser beam can be sensed, for example, Figure 3 The position information of landing point A and landing point B in .
[0069] Furthermore, the intelligent positioning and attitude determination device for the tunnel boring machine can perform calculations based on the landing point information and distance information of different laser signals, thereby positioning and determining the attitude of the tunnel boring machine.
[0070] To sum up, the intelligent positioning and attitude determination device for the tunnel boring machine implemented in the present application can monitor the position and attitude information of the tunnel boring machine by installing a tunnel boring machine position and attitude sensing device on the tunnel boring machine and installing a signal receiving target in the tunnel, thereby avoiding the need to set up multiple measuring equipment for collaborative detection. The device has a simple structure, convenient data collection and high accuracy in measuring the position and attitude of the tunnel boring machine.
[0071] In order to more clearly explain the specific implementation process of measuring the position and posture of the tunnel boring machine through the tunnel boring machine intelligent positioning and posture device, a control method for a tunnel boring machine intelligent positioning and posture device proposed in an embodiment of the present application is described in detail below. The method is applied to the tunnel boring machine intelligent positioning and posture device in the above embodiment, that is, the tunnel boring machine intelligent positioning and posture device targeted by the control method of the tunnel boring machine intelligent positioning and posture device is the tunnel boring machine intelligent positioning and posture device described in the above implementation. The components included in the device and the connection method of each component are as described in the above embodiment, and will not be repeated here.
[0072] Figure 4This is a flow chart of a control method for an intelligent positioning and posture determination device for a tunnel boring machine proposed in an embodiment of the present application, such as Figure 4 As shown, the method comprises the following steps:
[0073] Step S401: The tunnel boring machine posture sensing device is set at the middle position of the rear of the tunnel boring machine, and the signal receiving target is set at the upper position of the tunnel behind the tunnel boring machine.
[0074] In this step, the specific configuration of the tunnel boring machine posture sensing device and the signal receiving target can refer to the description in the above device embodiment, which will not be repeated here.
[0075] Step S402: establishing a spatial coordinate system for the signal receiving target, and calibrating the initial values of the first rotation angle sensor and the second rotation angle sensor.
[0076] In one embodiment of the present application, a spatial coordinate system is established for the signal receiving target, including: establishing a spatial coordinate system with the midpoint of the lower edge line of the signal receiving target as the origin, the direction perpendicular to the horizontal ground of the tunnel as the z-axis direction, the direction perpendicular to the side of the tunnel as the x-axis direction and the direction of the center line of the tunnel as the y-axis direction.
[0077] Specifically, if Figure 3 As shown, a coordinate system is established by taking the midpoint of the lower edge line of the signal receiving target 10 as the origin O, the vertical direction as the z-axis direction, the direction perpendicular to the side of the tunnel as the x-axis direction, and the center line direction of the horizontal ground of the tunnel as the y-axis direction. The established spatial coordinate system facilitates the subsequent calibration of the spatial coordinate position and posture of the tunnel boring machine.
[0078] Furthermore, the initial values of the first rotation angle sensor and the second rotation angle sensor are calibrated. In one embodiment of the present application, the initial values of the rotation angle sensor are calibrated including the following steps:
[0079] First, place the tunnel boring machine on horizontal ground, and set the tunnel boring machine position sensing device in the middle position of the rear of the tunnel boring machine, so that the upper surface of the fixed protective shell 1 is parallel to the horizontal ground and the left and right sides of the fixed protective shell 1 are parallel to the vertical section of the length direction of the tunnel boring machine.
[0080] Then, the rotating table 3 and the rotating shaft 7 are controlled to rotate at a corresponding angle, so that after the rotation, the laser emitted by the laser ranging transmitter 6 is aligned with the horizontal reference component 9.
[0081] Finally, the state of the rotating table 3 is maintained, that is, the rotating table 3 is kept stationary, the rotating shaft 7 is rotated 180°, and the angle values of the first rotation angle sensor 4 and the second rotation angle sensor 8 at the current moment are calibrated to their respective initial values, that is, the initial position angles.
[0082] Step S403: Turn on the laser rangefinder transmitter, obtain the initial landing point A of the laser signal on the signal receiving target, and control the rotating table to rotate at a corresponding angle to obtain the first landing point B corresponding to the shortest distance measured by the laser rangefinder transmitter, and monitor the rotation angle θ of the laser rangefinder transmitter from the initial landing point A to the first landing point B through the first rotation angle sensor.
[0083] In the embodiment of the present application, the laser rangefinder transmitter 6 is turned on. At this time, the landing point of the laser beam hitting the signal receiving target 10 is A. Then the rotating table 3 is rotated at a certain angle so that the distance value measured by the laser rangefinder transmitter 6 is minimized. At this time, it is determined that the landing point of the laser beam hitting the signal receiving target 10 is B, and the rotation angle value detected by the first rotation angle sensor 4 is collected as θ.
[0084] Specifically, if Figure 3 As shown, when the measurement starts, the laser rangefinder transmitter 6 is turned on first. At this time, the laser rangefinder transmitter 6 emits a laser beam to the signal receiving target 10, and the landing position of the laser beam received by the signal receiving target 10 is marked as A. Then, the rotating table 3 is rotated horizontally at a small angle, and the direction in which the distance value measured by the laser rangefinder transmitter 6 is reduced is determined by comparison, and the rotation is continued in this direction, so that the distance measured by the laser rangefinder transmitter 6 is the shortest. At this time, the landing position of the laser beam received by the signal receiving target 10 is determined to be marked as B. The rotation angle of the laser rangefinder transmitter 6 from point A to point B is monitored by the first rotation angle sensor 4, and the rotation angle value is recorded as θ.
[0085] It should be noted that, through analysis of the spatial coordinate relationship, the θ value is the deviation angle of the tunnel boring machine in the horizontal direction, and the tunnel boring machine is subsequently required to rotate at an angle of θ in the horizontal direction.
[0086] Step S403: fix the rotating table, control the rotating axis to rotate 10° to 15° in a direction that gradually increases the distance value measured by the laser ranging transmitter, and obtain the final landing point C of the laser signal on the signal receiving target after the rotating axis rotates.
[0087] For details, please refer to Figure 3 As shown, the rotating table 3 is fixed and the rotating shaft 7 is rotated 10-15 degrees in a direction that gradually increases the distance value measured by the laser ranging transmitter 6. The specific rotation angle can be determined according to actual needs. After the rotating shaft finishes rotating, the landing point of the laser beam on the signal receiving target 10 is determined to be C.
[0088] Step S404: Obtain the first distance between the signal transmitting point S and the initial landing point A, the second distance between the signal transmitting point S and the first landing point B, and the third distance between the signal transmitting point S and the second landing point C respectively, and combine the coordinate values of the initial landing point A, the first landing point B, and the second landing point C, and calculate the position coordinates of the vertical projection point T of the laser ranging transmitter on the signal receiving target based on the trigonometric function relationship, as well as the fourth distance between the signal transmitting point and the vertical projection point T.
[0089] Specifically, the laser rangefinder transmitter 6 is approximately regarded as transmitting a laser signal from a signal transmission point S, and the first distance l between the signal transmission point S and the initial landing point A is measured by the ranging function of the laser rangefinder transmitter 6 itself. SA , the second distance l between point S and the first landing point B SB And the third distance l between point S and the second landing point C SC In addition, the signal receiving target 10 can sense the landing point of the laser beam to determine the coordinates of the initial landing point A, the first landing point B, and the second landing point C. The distance l between the first landing point B and the second landing point C on the signal receiving target 10 is calculated according to the distance formula between two points in the plane. BC , the distance between point A and point B on the signal receiving target is 10 AB .
[0090] Furthermore, the edges formed by the above-mentioned points have a spatial position relationship. According to the above-mentioned calculated distance values, the position coordinates of the vertical projection point T of the laser ranging transmitter 6 on the signal receiving target 10 and the fourth distance l between the signal transmitting point S and the vertical projection point T can be calculated through the trigonometric function relationship of each edge. ST .
[0091] Specifically, due to l SB is the shortest distance between the laser ranging transmitter 6 and the signal receiving target 10 obtained by the horizontal rotation of the rotating platform 3. Figure 5 As shown, the line l connecting the vertical projection point T of the laser ranging transmitter 6 on the signal receiving target 10 and point B BT , should be perpendicular to the line connecting point A and point B. AB .
[0092] Then we can construct Figure 6 The trigonometric relationship shown is used to solve the vertical projection point T of the laser ranging transmitter 6 on the signal receiving target 10. Figure 6 It can be seen that the trigonometric relationship between the sides is shown in the following formula:
[0093]
[0094] In the formula, l SB , lSC and l BC All are known values, and the distance l between the first landing point B and the vertical projection point T is calculated by the following formula BT , and the fourth distance between the signal transmission point S and the vertical projection point T can be solved to get l ST :
[0095]
[0096] Among them, l ST is the fourth distance, l BT is the distance between the first landing point B and the vertical projection point T, l SB is the second distance, l BC is the distance between the first landing point B and the second landing point C, l SC It is the third distance.
[0097] Furthermore, SA With l SB The angle between the initial point A and the first point B is θ, and the line connecting the initial point A and the first point B is determined (i.e., l AB ), the first angle β with the x-axis, the line connecting the signal emission point S and the first landing point B (i.e. l SB ), the line connecting the signal emission point S and the vertical projection point T (i.e. l ST ), where γ can be calculated by the following formula:
[0098]
[0099] Then according to the calculated l ST and l BT The coordinate value of the vertical projection point T can be determined based on the position coordinates of each known point in the above spatial coordinate system and the above trigonometric relationship.
[0100] Step S405: Determine the position coordinates of the roadheader in the spatial coordinate system according to the position coordinates of the vertical projection point T and the fourth distance, and use the deflection angles in each plane of the spatial coordinate system as the posture information of the roadheader.
[0101] In one embodiment of the present application, the position coordinates of the tunnel boring machine in the spatial coordinate system are determined by the following formula:
[0102]
[0103] Among them, x T is the value of the vertical projection point T on the x-axis, z T is the value of the vertical projection point T on the z-axis, l ST The fourth distance.
[0104] Furthermore, the deflection angle in each plane of the spatial coordinate system is used as the posture information of the tunnel boring machine. The determined posture information of the tunnel boring machine is: the deflection angle in the plane where the x-axis and the y-axis are located is θ, the deflection angle in the plane where the x-axis and the z-axis are located is β, and the deflection angle in the plane where the y-axis and the z-axis are located is γ.
[0105] Specifically, the coordinate value of the tunnel boring machine on the x-axis is x=x T It indicates that the tunnel boring machine has deviated from the center line of the tunnel, and the deviation distance is the coordinate value of the x-axis; the coordinate value of the tunnel boring machine on the y-axis indicates the distance between the tunnel boring machine and the signal receiving target 10; the coordinate value of the tunnel boring machine on the z-axis indicates the vertical position of the tunnel boring machine, thereby measuring the current position information and posture information of the tunnel boring machine.
[0106] It should be noted that the above-calculated coordinate values are the positions of the tunnel boring machine in the xyz space coordinate system established in the embodiment of the present application. In order to improve the practicality and applicability of the positioning and attitude determination results, in one embodiment of the present application, the absolute position of the tunnel boring machine can also be determined by the coordinate change according to the position of the coordinate origin O of the xyz space coordinate system in the earth coordinate system. In addition, the subsequent deviation correction amount of the tunnel boring machine direction can also be determined according to the measured attitude information of the tunnel boring machine.
[0107] To sum up, the control method of the intelligent positioning and attitude determination device of the tunnel boring machine implemented in the present application only controls one device of the intelligent positioning and attitude determination device of the tunnel boring machine, avoids the setting of multiple measuring devices for collaborative detection, and eliminates the processing steps such as fusion analysis of multiple collected data, reduces the difficulty of data processing and the complexity of operation, saves the cost of intelligent positioning and attitude determination of the tunnel boring machine, reduces the data measurement of positioning and attitude determination, and improves the measurement accuracy.
[0108] In order to implement the above embodiments, the present application also proposes a non-temporary computer-readable storage medium storing a computer program, which, when executed by a processor, implements the control method of the intelligent positioning and attitude determination device of the tunnel boring machine proposed in the aforementioned embodiments of the present application.
[0109] It should be noted that it should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0110] In addition, in the description of the present application, the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0111] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0112] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0113] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0114] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A control method for an intelligent positioning and posture determination device of a tunnel boring machine, characterized in that: The intelligent positioning and attitude determination device of the tunnel boring machine includes: a fixed protective shell, a rotating base, a rotating table, a first rotation angle sensor, two fixed ear plates, a laser ranging transmitter, a rotating shaft, a second rotation angle sensor, a horizontal reference component, and a signal receiving target, wherein: The rotating base is fixedly connected to the fixed protective shell; The rotating platform is connected to the rotating base and is used to rotate at a corresponding angle around the vertical axis of the rotating platform; The first rotation angle sensor is disposed in the rotating table and is used to monitor the rotation angle of the rotating table; The two fixed ear plates are respectively fixed on both sides of the upper surface of the rotating table; The laser ranging transmitter is connected to the fixed ear plate through the rotating shaft, and rotates at a corresponding angle through the rotating shaft. The laser ranging transmitter is used to transmit a laser signal to the signal receiving target; The second rotation angle sensor is disposed in the rotation shaft and is used to monitor the rotation angle of the rotation shaft; The horizontal reference component is fixedly arranged on the inner side of the fixed protective shell, and is used to calibrate the initial rotation position of the rotating table and the rotating shaft; The fixed protective shell, the rotating base, the rotating table, the first rotation angle sensor, the fixed ear plate, the laser ranging transmitter, the rotating shaft, the second rotation angle sensor, and the horizontal reference connection constitute a tunneling machine posture sensing device; The signal receiving target is arranged at the upper position of the tunnel behind the tunnel boring machine, and is used to receive the laser signal emitted by the laser ranging transmitter, so as to locate and determine the posture of the tunnel boring machine based on the relevant information of the laser signal; The control method comprises the following steps: The tunnel boring machine posture sensing device is arranged at the middle position of the rear part of the tunnel boring machine, and the signal receiving target is arranged at the upper position of the tunnel behind the tunnel boring machine; Establishing a spatial coordinate system for the signal receiving target, and calibrating the initial values of the first rotation angle sensor and the second rotation angle sensor; Turn on the laser rangefinder transmitter, obtain the initial landing point A of the laser signal on the signal receiving target, and control the rotating table to rotate at a corresponding angle to obtain the first landing point B corresponding to the shortest distance measured by the laser rangefinder transmitter, and monitor the rotation angle of the laser rangefinder transmitter from the initial landing point A to the first landing point B through the first rotation angle sensor ; Fix the rotating table, control the rotating shaft to rotate 10° to 15° in a direction that gradually increases the distance value measured by the laser ranging transmitter, and obtain the final landing point C of the laser signal on the signal receiving target after the rotating shaft rotates; Obtaining the first distance between the signal transmitting point S measured by the laser ranging transmitter and the initial landing point A, the second distance between the signal transmitting point S and the first landing point B, and the third distance between the signal transmitting point S and the second landing point C, respectively, and combining the coordinate values of the initial landing point A, the first landing point B, and the second landing point C, and calculating the position coordinates of the vertical projection point T of the laser ranging transmitter on the signal receiving target, and the fourth distance between the signal transmitting point and the vertical projection point T based on the trigonometric function relationship; The position coordinates of the tunnel boring machine in the spatial coordinate system are determined according to the position coordinates of the vertical projection point T and the fourth distance, and the deflection angles in each plane of the spatial coordinate system are used as the posture information of the tunnel boring machine.
2. The control method of the intelligent positioning and posture determination device of a tunnel boring machine according to claim 1, characterized in that: The tunnel boring machine posture sensing device is fixedly arranged at the middle position of the rear part of the tunnel boring machine, and the initial values of the first rotation angle sensor and the second rotation angle sensor are pre-calibrated.
3. The control method of the intelligent positioning and posture determination device of a tunnel boring machine according to claim 1, characterized in that: The distances from both sides of the signal receiving target to the walls on both sides of the tunnel are equal, and the signal receiving target is specifically used to sense the landing position of the laser signal emitted by the laser ranging transmitter.
4. The method according to claim 1, characterized in that: The spatial coordinate system is established for the signal receiving target, including: taking the midpoint of the lower edge line of the signal receiving target as the origin, the direction perpendicular to the horizontal ground of the tunnel as the z-axis direction, the direction perpendicular to the side of the tunnel as the x-axis direction, and the direction of the center line of the tunnel as the y-axis direction to establish the spatial coordinate system.
5. The method according to claim 1, characterized in that The calibrating the initial values of the first rotation angle sensor and the second rotation angle sensor includes: The tunnel boring machine is placed on a horizontal ground, so that the upper surface of the fixed protective shell is parallel to the horizontal ground and the left and right side surfaces of the fixed protective shell are parallel to the vertical section of the length direction of the tunnel boring machine; Controlling the rotating table and the rotating axis to rotate at a corresponding angle so that the laser emitted by the laser ranging transmitter is aligned with the horizontal reference; The state of the rotating table is maintained, the rotating shaft is rotated 180 degrees, and the current angle values of the first rotation angle sensor and the second rotation angle sensor are calibrated as the initial values.
6. The method according to claim 1, characterized in that The fourth distance between the signal transmission point and the vertical projection point T is calculated by the following formula: in, is the fourth distance, is the distance between the first landing point B and the vertical projection point T, is the second distance, is the distance between the first landing point B and the second landing point C, It is the third distance.
7. The method according to claim 6, characterized in that The position coordinates of the tunnel boring machine in the spatial coordinate system are determined by the following formula: in, is the value of the vertical projection point T on the x-axis, is the value of the vertical projection point T on the z-axis.
8. The method according to claim 6, characterized in that The deflection angles in each plane of the spatial coordinate system as the posture information of the tunnel boring machine include: Determine the first angle between the line connecting the initial landing point A and the first landing point B and the x-axis , and determine the second angle between the line connecting the signal transmission point S and the first landing point B and the line connecting the signal transmission point S and the vertical projection point T by the following formula: : ; At the rotation angle is the deflection angle in the plane where the x-axis and the y-axis are located, with the first angle is the deflection angle in the plane where the x-axis and the z-axis are located, and the second angle is the deflection angle between the y-axis and the z-axis in the plane.
9. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by the processor, the control method of the intelligent positioning and posture determination device of the tunnel boring machine as described in any one of claims 1-8 is implemented.