A surveying and mapping method based on municipal engineering
Through the measurement method combined with GPS technology and level instruments, the problem of inaccurate and complex measurement of municipal pipeline engineering is solved, and higher accuracy and simplified processes are achieved, saving time and cost.
Patent Information
- Application Number
- CN202210794759.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-05
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2042-07-05
AI Technical Summary
The measurement of municipal pipeline projects is not accurate enough and the process is complicated and cumbersome, resulting in insufficient measurement efficiency and accuracy.
Using GPS technology to establish a control network, use GPS observation calculation and elevation control, combine leveling instruments and leveling rulers to perform measurements, select appropriate concrete markings and control points, convert coordinate systems to improve measurement accuracy, and set elevation wire points outside the line to simplify the process .
Improve the accuracy and simplification of pipeline measurement, save time and economic costs, and facilitate construction work.
Smart Images

Figure CN115164852B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of municipal surveying and mapping, and in particular to a surveying and mapping method based on municipal engineering. Background Art
[0002] Pipeline engineering is the construction of pipelines for transporting oil, natural gas and solid slurry, including pipeline line engineering, station engineering and pipeline ancillary engineering. Pipeline engineering in a broad sense also includes the supply of equipment and facilities. It is a type of municipal engineering.
[0003] However, the current measurement of municipal pipeline projects is very inconvenient, the measurement accuracy is not accurate enough, and the measurement process is complicated and cumbersome. Summary of the invention
[0004] In view of the deficiencies in the prior art, the present invention provides a surveying and mapping method based on municipal engineering, which solves the problems that the current measurement of municipal pipeline engineering is very inconvenient, the measurement accuracy is not accurate enough, and the measurement process is complicated and cumbersome.
[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: A surveying and mapping method based on municipal engineering, comprising the following steps:
[0006] S1. Establish a control network: On the water pipeline, a group of GPS points with mutual visibility are arranged every 10 to 13 km, and then concrete markers are buried to establish a GPS plane control network;
[0007] S2, GPS observation calculation: Use 4 to 6 GPS receivers to measure, then select the coordinate system to convert to Gaussian conformal projection arbitrary band plane rectangular coordinates, then convert the Gaussian plane side length to the ground side length, and then use the inverse calculation of the ground side length;
[0008] S3, elevation control: GPS points, concrete markers and turning points along the joint survey line form a leveling route, and then use a level meter and a level ruler to observe and record;
[0009] S4. Off-line control: Outside the excavation line of the water pipeline, a group of concrete markers are set up every 3 to 5 km as the basis for construction layout, and then joint measurement is carried out using five-level elevation guide wires.
[0010] Furthermore, when the GPD point is selected in step S1, the distance away from the high-voltage line is not less than 80-100m, and the distance away from the high-power transmitting station is not less than 350-400m.
[0011] Furthermore, in the step S1, when the elevation angle of the selected GPS points is 14 to 17 degrees, it is ensured that there are no obstacles between the GPS points that are in sight of each other.
[0012] Furthermore, in step S2, the calculation formula is S=D(Hm / R-Ym 2 / (2R 2 )), where S is the side length, D is the side length of the Gaussian plane of the coordinate system, Hm is the elevation of the GPS side above the geoid, Ym is the average of the horizontal coordinates of the two end points of the GPS side, and R is the average radius of curvature of the midpoint of the GPS side.
[0013] Furthermore, in the step S3, during the elevation control, the fourth-order geometric leveling elevation route is adopted for layout.
[0014] Furthermore, in step S4, 17 to 21 control points are set outside the pipeline, and elevation guide wire points are arranged within the measurement range of the 1:500 topographic map.
[0015] Beneficial Effects
[0016] The present invention provides a surveying and mapping method based on municipal engineering, which has the following beneficial effects compared with the prior art:
[0017] 1. This surveying and mapping method based on municipal engineering selects the coordinate system and converts it into the rectangular coordinates of any plane with Gaussian conformal projection, then converts the side length of the Gaussian plane into the side length of the ground, and then uses the inverse calculation of the side length of the ground, elevation control and off-line control to make the pipeline measurement more accurate, thereby facilitating the corresponding construction work on the pipeline.
[0018] 2. Compared with the traditional surveying method, the surveying method based on municipal engineering of the present invention has simpler steps and higher precision, which saves a lot of time for surveying and mapping, thereby saving economic costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the surveying and mapping process of the present invention. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] See also Figure 1 , the present invention provides three technical solutions:
[0022] Embodiment 1
[0023] A surveying and mapping method based on municipal engineering includes the following steps:
[0024] S1. Establish a control network: On the water pipeline, a group of GPS points with mutual visibility are arranged every 10km, and then concrete markers are buried to establish a GPS plane control network;
[0025] S2, GPS observation calculation: Use 4 GPS receivers to measure, then select the coordinate system to convert to Gaussian orthogonal projection arbitrary band plane rectangular coordinates, then convert the Gaussian plane side length to the ground side length, and then use the inverse calculation of the ground side length;
[0026] S3, elevation control: GPS points, concrete markers and turning points along the joint survey line form a leveling route, and then use a level meter and a level ruler to observe and record;
[0027] S4. Off-line control: A group of concrete markers are set up every 3 km outside the excavation line of the water pipeline as the basis for construction layout, and then joint measurement is carried out using five-level elevation guide wires.
[0028] In the embodiment of the present invention, when the GPD point is selected in step S1, the distance away from the high-voltage line is not less than 80m, and the distance away from the high-power transmitting station is not less than 350m.
[0029] In the embodiment of the present invention, among the GPS points selected in step S1, when the elevation angle is 14 degrees, it is ensured that there are no obstacles between the GPS points that are in sight of each other.
[0030] In the embodiment of the present invention, in step S2, the calculation formula is S=D(Hm / R-Ym 2 / (2R 2 )), where S is the side length, D is the side length of the Gaussian plane of the coordinate system, Hm is the elevation of the GPS side above the geoid, Ym is the average of the horizontal coordinates of the two end points of the GPS side, and R is the average radius of curvature of the midpoint of the GPS side.
[0031] In the embodiment of the present invention, in step S3, during elevation control, the fourth-order geometric leveling elevation route is used for layout.
[0032] In the embodiment of the present invention, in step S4, 17 control points are set outside the pipeline, and elevation guide points are arranged within the measurement range of the 1:500 topographic map.
[0033] Embodiment 2
[0034] A surveying and mapping method based on municipal engineering includes the following steps:
[0035] S1. Establish a control network: On the water pipeline, a group of GPS points with mutual visibility are arranged every 13km, and then concrete markers are buried to establish a GPS plane control network;
[0036] S2, GPS observation calculation: Use 6 GPS receivers to measure, then select the coordinate system to convert to Gaussian conformal projection arbitrary band plane rectangular coordinates, then convert the Gaussian plane side length to the ground side length, and then use the inverse calculation of the ground side length;
[0037] S3, elevation control: GPS points, concrete markers and turning points along the joint survey line form a leveling route, and then use a level meter and a level ruler to observe and record;
[0038] S4. Off-line control: Outside the excavation line of the water pipeline, a group of concrete markers are set up every 5 km as the basis for construction layout, and then a five-level elevation guide wire is used for joint measurement.
[0039] In the embodiment of the present invention, when the GPD point is selected in step S1, the distance away from the high-voltage line is not less than 100m, and the distance away from the high-power transmitting station is not less than 400m.
[0040] In the embodiment of the present invention, among the GPS points selected in step S1, when the elevation angle is 17 degrees, it is ensured that there are no obstacles between the GPS points that are in sight of each other.
[0041] In the embodiment of the present invention, in step S2, the calculation formula is S=D(Hm / R-Ym 2 / (2R 2 )), where S is the side length, D is the side length of the Gaussian plane of the coordinate system, Hm is the elevation of the GPS side above the geoid, Ym is the average of the horizontal coordinates of the two end points of the GPS side, and R is the average radius of curvature of the midpoint of the GPS side.
[0042] In the embodiment of the present invention, in step S3, during elevation control, the fourth-order geometric leveling elevation route is used for layout.
[0043] In the embodiment of the present invention, in step S4, 21 control points are set outside the pipeline, and elevation guide wire points are arranged within the measurement range of the 1:500 topographic map.
[0044] Embodiment 3
[0045] A surveying and mapping method based on municipal engineering includes the following steps:
[0046] S1. Establish a control network: On the water pipeline, a group of GPS points with mutual visibility are arranged every 12km, and then concrete markers are buried to establish a GPS plane control network;
[0047] S2, GPS observation calculation: Use 5 GPS receivers to measure, then select the coordinate system to convert to Gaussian orthogonal projection arbitrary band plane rectangular coordinates, then convert the Gaussian plane side length to the ground side length, and then use the inverse calculation of the ground side length;
[0048] S3, elevation control: GPS points, concrete markers and turning points along the joint survey line form a leveling route, and then use a level meter and a level ruler to observe and record;
[0049] S4. Off-line control: Outside the excavation line of the water pipeline, a group of concrete markers are set up every 4 km as the basis for construction layout, and then a five-level elevation guide wire is used for joint measurement.
[0050] In the embodiment of the present invention, when the GPD point is selected in step S1, the distance away from the high-voltage line is not less than 90m, and the distance away from the high-power transmitting station is not less than 370m.
[0051] In the embodiment of the present invention, among the GPS points selected in step S1, when the elevation angle is 15 degrees, it is ensured that there is no obstacle between the GPS points that are in sight of each other.
[0052] In the embodiment of the present invention, in step S2, the calculation formula is S=D(Hm / R-Ym 2 / (2R 2 )), where S is the side length, D is the side length of the Gaussian plane of the coordinate system, Hm is the elevation of the GPS side above the geoid, Ym is the average of the horizontal coordinates of the two end points of the GPS side, and R is the average radius of curvature of the midpoint of the GPS side.
[0053] In the embodiment of the present invention, in step S3, during elevation control, the fourth-order geometric leveling elevation route is used for layout.
[0054] In the embodiment of the present invention, in step S4, 19 control points are set outside the pipeline, and elevation guide wire points are arranged within the measurement range of the 1:500 topographic map.
[0055] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0056] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
Claims
1. A surveying and mapping method based on municipal engineering, characterized in that: The following steps are involved: S1. Establish a control network: On the water pipeline, a group of GPS points with mutual visibility are arranged every 10km, and then concrete markers are buried to establish a GPS plane control network; S2, GPS observation calculation: Use 4 GPS receivers to measure, then select the coordinate system to convert to Gaussian orthogonal projection arbitrary band plane rectangular coordinates, then convert the Gaussian plane side length to the ground side length, and then use the inverse calculation of the ground side length; S3, elevation control: GPS points, concrete markers and turning points along the joint survey line form a leveling route, and then use a level meter and a level ruler to observe and record; S4, off-line control: Along the excavation line of the water pipeline, a group of concrete markers are set aside every 3km as the basis for construction layout, and then joint measurement is carried out using the five-level elevation guide wire; When selecting the GPS point in step S1, the distance from the high-voltage line is not less than 80m, and the distance from the high-power transmitter is not less than 350m; In the step S1, when the elevation angle is 14 degrees, the GPS points selected are guaranteed to be unobstructed with respect to each other; In the step S3, when controlling the elevation, the fourth-order geometric level elevation route is used for layout; In step S4, 17 control points are set outside the pipeline, and elevation wire points are arranged within the measurement range of the 1:500 topographic map; In step S2, the calculation formula is S=D(H m / RY m 2 / (2R 2 )), where S is the side length, D is the side length of the Gaussian plane of the coordinate system, and H m Y is the elevation of the GPS side above the geoid, m is the average value of the horizontal coordinates of the two end points of the GPS edge, and R is the average radius of curvature of the midpoint of the GPS edge.