An adaptive linkage method for pipeline internal and external inspection robots based on ELF attenuation field

Through the adaptive linkage method of pipeline internal and external inspection robots based on the ELF attenuation field, the problem in the existing technology that is difficult to achieve dynamic high-precision tracer positioning and adapt to complex environments is solved, and high-precision detection of pipeline thickness and corrosion and fault points are achieved. identification to ensure detection accuracy and reliability.

CN115201320BInactive Publication Date: 2024-10-25NORTHEASTERN UNIV CHINA
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210829342.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-15
Publication Date
2024-10-25
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing signal transmission technology within pipelines is difficult to achieve dynamic high-precision tracking and positioning, and is difficult to adapt to complex environmental factors such as changes in pipe wall thickness. Existing algorithms are difficult to distinguish the causes of signal intensity changes and cannot flexibly adjust model parameters, resulting in poor detection results.

Method used

The adaptive linkage method of internal and external pipeline detection robots based on ELF attenuation field is adopted. Through mutual perception and collaboration between internal and external detection robots, model parameters are adjusted, changes in signal strength are used to detect changes in pipeline thickness, and obstacle avoidance paths are planned when obstacles exist to ensure detection. Accuracy and reliability.

Benefits of technology

It achieves high-precision detection of pipeline thickness and corrosion, can quickly adjust model parameters in complex environments, ensures detection accuracy and credibility, and can promptly identify fault points and conduct comprehensive detection to avoid the impact of obstacles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115201320B_ABST
    Figure CN115201320B_ABST
Patent Text Reader

Abstract

A method for adaptive linkage of internal and external pipeline detection robots based on ELF attenuation field belongs to the field of automated pipeline detection technology. The external detection robot sends a signal to the internal detection robot to control the internal detection robot to adjust the working mode, and complete the adaptive linkage of the internal and external detection robots; it includes the following steps: judging whether the pipeline thickness changes at each moment, when the pipeline thickness changes, the corresponding model parameters need to be adjusted; when the pipeline thickness does not change, the original parameters are maintained to continue the detection. An extremely low frequency electromagnetic signal attenuation field is constructed, and actual data is used for simulation. The sensitivity difference between the pipeline thickness and the horizontal deviation and vertical deviation of the internal and external detection robots is proved to be significant enough through the change of the field strength signal of the magnetic field. The change of pipeline thickness can be detected by detecting the sudden change of signal intensity, and it can be used to detect partial pipeline corrosion.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of automated pipeline detection, and in particular relates to an adaptive linkage method of pipeline internal and external detection robots based on an ELF attenuation field. Background Art

[0002] Due to the metal shielding problem, the current signal transmission technology in pipelines mainly uses extremely low frequency electromagnetic signals. Such signals are mainly used to design corresponding transmitting and receiving coils. Such signals are often used for tracing and positioning research of pipeline detection or cleaning robots. For example, Qi Haiming of Harbin Institute of Technology has conducted research on the design of tracing and positioning models for mobile robots in pipelines, and Chen Juan of Huazhong University of Science and Technology has built an ultra-low frequency magnetic induction communication system. The main existing problem is that it is difficult to achieve dynamic high-precision tracing and positioning, and tracing inversion can only be performed for specific environmental conditions. Most of the tracing and positioning robots for pipeline detection or cleaning focus on a fixed base station. When the internal detection or cleaning robot arrives near it, it is located and traced. There are few related studies that analyze complex environmental factors such as changes in pipe wall thickness.

[0003] Because the distribution and attenuation of extremely low frequency electromagnetic fields are greatly affected by the environment and there are many influencing factors, and the pipeline laying environment is complex, changeable and unevenly distributed, the existing algorithms are difficult to distinguish the causes of changes in signal strength and perform high-confidence position inversion. At the same time, it is also difficult to adjust model parameters when environmental factors change, and it is impossible to flexibly adapt to different environments to give results. Even if it is possible, it can only give an idealized and complex calculus equation relationship.

[0004] There is no research on the control of collaborative robot groups in the pipeline field. The present invention uses the characteristics of mutual cooperation, mutual perception and linkage of internal and external detection robots. On the basis of the original fixed transmitting and receiving ends, mobile transmitting and receiving ends are designed to regulate the motion state of the carrier, and it has a strong adaptive characteristic. Summary of the invention

[0005] In order to realize mutual perception and work coordination between the internal and external pipeline inspection robots, comprehensively improve the inspection effect, and maintain pipeline energy security, it is necessary to propose a theory of signal excitation reception and robot linkage inside and outside buried metal pipelines that guarantees accuracy and credibility, and provide a method for detecting changes in pipe wall thickness and pipe wall corrosion based on signal strength. Expand the fixed base station into a robot that can move continuously to perform real-time positioning and analysis. In the face of complex and changing environments: changes in pipe wall thickness, soil changes, displacement deviations, and obstacles, etc. - Provide an adaptive linkage method for pipeline internal and external inspection robots based on the ELF attenuation field.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] A method for adaptive linkage of internal and external pipeline detection robots based on ELF attenuation field, wherein an external detection robot sends a signal to an internal detection robot to control the internal detection robot to adjust the working mode, thereby completing the adaptive linkage of the internal and external detection robots; the method comprises the following steps:

[0008] The internal detection robot determines whether the pipeline thickness changes at each moment. When the pipeline thickness changes, the corresponding model parameters need to be adjusted; when the pipeline thickness does not change, the original parameters are maintained to continue the detection.

[0009] The process of adjusting the corresponding model parameters is as follows:

[0010] (1) Detect the change in pipeline thickness and adjust the corresponding model parameters to ensure that the horizontal distance between the internal and external inspection robots remains unchanged during the inspection process;

[0011] (2) When the inner and outer detection robots maintain a constant horizontal distance while walking, when the outer detection robot reaches a possible fault point on the pipeline, a hysteresis mileage calculation is performed to calculate the signal sending time for the outer detection robot to adjust the working mode of the inner detection robot, so that the inner detection robot can switch power and conduct a comprehensive inspection around the fault point.

[0012] The ELF attenuation field-based pipeline internal and external detection robot adaptive linkage method also includes:

[0013] Obstacle avoidance path planning process: When the external inspection robot avoids obstacles above the pipeline, the motion trajectory will deviate from the central axis of the pipeline. At this time, the motion trajectory on the xy plane is rotated to the yz plane with the central axis of the pipeline as the rotation axis. The moving path planned by the external inspection robot when avoiding obstacles in the xy plane is calculated, and it returns to the top of the central axis of the pipeline after the obstacle avoidance is completed.

[0014] The internal detection robot can be selected to be an internal detection robot that can be adjusted in two modes: low power and high power. Internal detection robots with different powers can also be selected. When an internal detection robot with adjustable power is selected, the external detection robot sends signals of different magnitudes to control the internal detection robot to adjust to different working modes.

[0015] The method for detecting the change of pipeline thickness and adjusting the corresponding model parameters comprises the following steps:

[0016] Step 1: Calculate the changed thickness of the pipeline based on the initial value of the pipeline thickness and the horizontal distance maintained by the internal and external detection robots; Calculate the changed soil thickness based on the vertical distance between the centers of the internal and external detection robots' coils, the inner diameter of the pipeline, and the thickness of the pipeline;

[0017] Step 2: After knowing the current pipe thickness change value and soil thickness change value, in order to keep the internal and external detection robots at a suitable horizontal distance, the pipe thickness and soil thickness are updated to the changed pipe thickness and soil thickness.

[0018] Calculating the signal sending time of the external detection robot adjusting the working mode of the internal detection robot comprises the following steps:

[0019] Step 1: Calculate the corresponding speed according to the corresponding inclination angle, rotation speed and wheel radius of the external detection robot when the pipeline external detection robot climbs or descends, and then calculate the vertical and horizontal component speeds of the external detection robot; obtain the vertical distance between the coil center of the pipeline internal detection robot and the coil center of the pipeline external detection robot at the corresponding moment through the vertical component speed of the external detection robot and the initial vertical distance between the coil center of the pipeline internal detection robot and the coil center of the pipeline external detection robot;

[0020] Step 2: Integrate the horizontal velocity of the external detection robot to obtain the horizontal distance traveled by the external detection robot after passing the fault point and the signal sending time of the external detection robot to adjust the working mode of the internal detection robot; after receiving the signal, the internal detection robot conducts a comprehensive inspection around the fault point.

[0021] The obstacle avoidance path planning process includes the following steps:

[0022] Step 1: Establish xyz three-dimensional coordinates; when the external inspection robot avoids obstacles above the pipeline, the motion trajectory will deviate from the central axis of the pipeline. At this time, the external inspection robot rotates the motion trajectory on the xy plane to the yz plane with the central axis of the pipeline as the rotation axis. It only needs to find the equation of z with respect to y in the yz plane to obtain the equation of x with respect to y by substitution;

[0023] Step 2: Based on the xyz three-dimensional coordinates, define the length of the pipe wall through which the electromagnetic wave signal passes and the rate of change of the speed of the external detection robot with the distance;

[0024] Step 3: Add constraints: Make the component v of the velocity in the y direction at each point during obstacle avoidance y The speed is equal to the initial speed v0 when obstacle avoidance is not performed, which ensures that the direction of the pipeline can be maintained without additional adjustment when obstacle avoidance ends;

[0025] Step 4: According to the xyz three-dimensional coordinates, the length of the pipe wall through which the electromagnetic wave signal passes, the rate of change of the external detection robot's speed with the distance, and the constraints, a differential equation is constructed and solved to obtain the moving path planned by the external detection robot when avoiding obstacles in the xy plane.

[0026] The technical effects of the present invention are:

[0027] 1. An extremely low frequency electromagnetic signal attenuation field was constructed and simulated with actual data. The sensitivity difference between pipeline thickness and the horizontal and vertical deviations of the internal and external detection robots was proved to be significant enough through the change of magnetic field strength signal. The change of pipeline thickness can be detected by detecting the sudden change of signal strength, and it can be used to detect partial pipeline corrosion.

[0028] 2. Adaptive communication is achieved. When the thickness of the pipeline changes, the calculated pipeline thickness can be used in time to quickly adjust the model parameters. When obstacles appear, the strength of the signal can be used to carry out appropriate path planning to ensure that the external inspection robot returns to the pipeline in time and maintains the original collaborative mode.

[0029] 3. To ensure the accuracy and timeliness of mode changes, the external detection robot can estimate when the internal detection robot reaches the suspected fault point through its own data and the received signal strength, and switch modes in time to achieve reasonable distribution of energy. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is the ratio of the change in pipe wall thickness to the horizontal deviation under different attenuation indexes;

[0031] Figure 2 is the ratio of the change in pipe wall thickness to the vertical deviation under different attenuation indices;

[0032] Figure 3 It is a schematic diagram of sending a signal using delayed mileage;

[0033] Figure 4 It is a schematic diagram of obstacle avoidance path planning.

[0034] Figure 5 It is a flow chart of the adaptive linkage method of pipeline internal and external inspection robots based on the ELF attenuation field; DETAILED DESCRIPTION

[0035] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments.

[0036] The present invention can identify the changes in the ELF attenuation quasi-static field when factors such as pipe wall thickness, burial depth, robot motion posture, soil composition, etc. change by performing sensitivity correlation verification, change model parameters, and realize adaptive characteristics; utilize the real-time inversion relationship between magnetic field intensity and distance, and combine multiple sensors to obtain the motion state, so as to ensure that the distance between the pipeline internal detection robot and the external detection robot is maintained within a certain range during the detection process, and define the "lag mileage" at the same time, so as to realize that signals can be sent to each other to trigger events of the other party; through the equivalent transformation of the spatial trajectory, the differential equation is solved to give the obstacle avoidance trajectory.

[0037] like Figure 5As shown, a method for adaptive linkage of internal and external pipeline detection robots based on ELF attenuation field is provided. When the internal and external detection robots are put into use, the internal and external pipeline detection robots operate normally, and the transmitting coil of the external detection robot is adjusted to send signals of different strengths to the receiving coil of the internal detection robot, thereby controlling the internal detection robot to adjust the working mode, and completing the adaptive linkage of the internal and external detection robots; the method comprises the following steps:

[0038] Step S1: Calculate the sensitivity ratio of pipeline thickness change to horizontal deviation and vertical deviation, and prove the difference in the influence of error and pipeline thickness change on the signal according to the horizontal deviation and vertical deviation generated in different environments; the internal detection robot determines whether the pipeline thickness changes at each moment;

[0039] Step S2: When the pipe thickness changes, the corresponding model parameters need to be adjusted;

[0040] Step S3: When the pipe thickness does not change, the original parameters are maintained and the detection is continued.

[0041] The process of adjusting the corresponding model parameters is as follows:

[0042] (1) Detect the change in pipeline thickness and adjust the corresponding model parameters to ensure that the horizontal distance between the internal and external inspection robots remains unchanged during the inspection process;

[0043] (2) When the inner and outer detection robots maintain a constant horizontal distance while walking, when the outer detection robot reaches a possible fault point on the pipeline, a hysteresis mileage calculation is performed to calculate the signal sending time for the outer detection robot to adjust the working mode of the inner detection robot, so that the inner detection robot switches the low power mode to the high power mode and starts a comprehensive inspection around the fault point to determine the specific location of the fault point. The low power is 30% detection power, the high power is 100% detection power, and the detection power is 100% power.

[0044] The ELF attenuation field-based pipeline internal and external detection robot adaptive linkage method also includes:

[0045] Obstacle avoidance path planning process: When the external inspection robot avoids obstacles above the pipeline, the motion trajectory will deviate from the central axis of the pipeline. At this time, the motion trajectory on the xy plane is rotated to the yz plane with the central axis of the pipeline as the rotation axis. The moving path planned by the external inspection robot when avoiding obstacles in the xy plane is calculated, and it returns to the top of the central axis of the pipeline after the obstacle avoidance is completed.

[0046] The method of detecting the pipeline thickness and determining whether the pipeline thickness changes at each moment includes the following steps:

[0047] Step 1: Analyze the basic principles of ELF:

[0048] The extremely low frequency electromagnetic signal attenuation equation group is, that is, in the ELF electromagnetic signal, its extremely low frequency electromagnetic signal can be equivalent to the ELF attenuation static magnetic field analysis:

[0049]

[0050]

[0051]

[0052] Where: H is the magnetic field strength received by the receiving coil end; H0 is the distribution of the magnetic field strength amplitude on the axis of the transmitting coil in the magnetic dipole model; μ i is the magnetic permeability of different media; ω is the angular frequency of electromagnetic waves; σ i is the conductivity of different media; ε is the dielectric constant of soil; l p is the pipe thickness; l d is the soil thickness; M is the magnetic dipole moment; r is the unit vector in the r direction; θ is the unit vector in the θ direction; N is the number of coil turns; I is the effective value of the current; R is the equivalent radius of the coil; x is the horizontal distance between the coil centers of the internal and external pipeline detection robots, and the horizontal distance is determined when the internal and external detection robots are initially placed;

[0053] sinθ is the sine value of the angle between the line connecting the inner and outer detection robots and the horizontal direction, and the calculation formula is: Where L is the vertical distance difference between the centers of the detection robot coils inside and outside the pipeline;

[0054] In actual applications, the magnetic field strength H received by the corresponding receiving coil is also related to the height of the coil from the ground. Here, for the convenience of calculation, its height is set to 0. If the actual height needs to be applied, it can be regarded as the corresponding value of the expansion of the inner diameter of the pipeline;

[0055] Step 2: Compare the sensitivity ratio η1 of the pipe thickness change and the horizontal deviation, and substitute formula (1) into the sensitivity ratio formula (4). The common situation is that the horizontal distance increases, as follows:

[0056]

[0057] in:

[0058] sinθ′ is the sine value of the angle change caused by the horizontal deviation, and the calculation formula is: dh is the horizontal distance between the inner and outer detection robots, which is set by the signal strength that can be received by the receiving coil and the requirement for signal transmission; Δd is the horizontal displacement change value;

[0059] By changing the signal attenuation and horizontal deviation under normal conditions, several groups of sensitivity ratios η1 are calculated; the signal attenuation is calculated to be the original signal strength e under normal internal and external detection robot collaborative operation. -1 , e -2 , e -3 The sensitivity ratio of

[0060] The selected parameters are:

[0061]

[0062] μ1=100μ0,μ2=μ0=4π×10 -7

[0063] ω=2πf=46π

[0064]

[0065]

[0066] ε=4

[0067] l p =4mm

[0068] Δ p =1mm

[0069] l d =1.25m

[0070] Δ d =1~50cm

[0071] D=0.3m

[0072] like Figure 1 As shown in Figure 2, image analysis shows that, under different operating attenuation ratios, corresponding to various vertical deviations, a higher sensitivity ratio can be achieved; in particular, when the operating attenuation ratio is e -3 When faced with a horizontal deviation of 50 cm, it still has a high sensitivity ratio; therefore, it can be seen that in the face of the wax deposition problem that is difficult to deal with in oil and gas pipelines in actual situations, the external inspection robot can also distinguish between the change in pipeline thickness and the wax deposition point;

[0073] Step 3: Compare the sensitivity ratio η2 of the pipe thickness change and the vertical deviation, and substitute formula (1) into the sensitivity ratio formula (5). Common situation: the vertical distance becomes smaller, as follows:

[0074]

[0075] in:

[0076] sinθ′ is the sine value of the angle change caused by the horizontal deviation, and the calculation formula is:

[0077] By changing the signal attenuation and vertical deviation under normal conditions, several sets of sensitivity ratios η2 can be obtained; when the internal and external detection robots are running in coordination, the signal attenuation is e of the original signal strength. -1 , e -2 , e -3 The sensitivity ratios are shown below:

[0078] The selected parameters are:

[0079] L=1.404m

[0080] μ1=100μ o

[0081] μ2=μ0=4π×10 -7

[0082] ω=2πf=46π

[0083] σ1=5×10 6

[0084] σ2=10 -5

[0085] ε=4

[0086] l p =4mm

[0087] Δ p =1mm

[0088] l d =1.25m

[0089] Δ d =1~50cm

[0090] like Figure 2 As shown in the figure, through image analysis, it can be seen that under different signal attenuation, corresponding to various vertical deviations, it still has a high sensitivity ratio; in the face of various climbing and descending problems in actual situations, the external detection robot can effectively distinguish between height changes and pipe thickness changes;

[0091] through Figure 2 Analysis shows that the larger the horizontal distance between the internal and external detection robots, the greater the tolerance of the external detection robot to horizontal deviations and the smaller the tolerance to vertical deviations. Therefore, it is necessary to conduct a comprehensive analysis based on the horizontal deviations and numerical deviations that may occur in different environments to determine the horizontal distance x maintained by the internal and external detection robots.

[0092] Step 4: Determine whether the pipe thickness changes at each moment. According to step 1, substitute the actual value to obtain the magnetic field intensity change ratio. Where H pipe thickness change min is the minimum scale of pipe thickness change. in is the ratio of the magnetic field strength at the current moment, indicating that the pipeline thickness has changed. When the pipeline thickness changes, the corresponding model parameters need to be adjusted; when the actual value changes This indicates that the pipe thickness has not changed. If the pipe thickness has not changed, the original parameters are maintained and the test is continued.

[0093] The method for detecting the change of pipeline thickness and adjusting the corresponding model parameters comprises the following steps:

[0094] Step 1: When initially deploying the pipeline internal and external inspection robots, set the initial values ​​of the relevant models:

[0095] Initial value of pipe thickness l p0 ;

[0096] Set the pipeline inspection robot to emit an electromagnetic signal with a constant intensity and a frequency of 23Hz; and according to the requirements, set the inner and outer inspection robots to maintain a horizontal distance x of Set the initial value of the pipe thickness to l p0 And horizontal distance Substituting into formula (1) in step 1, the initial value of the magnetic field strength is calculated as follows:

[0097]

[0098] Since the influence of soil and air, two media with poor conductivity, on magnetic field attenuation differs by more than 5 orders of magnitude, the attenuation of electromagnetic signals passing through soil and air can be ignored, so the above formula (6) can be simplified to:

[0099]

[0100] Step 2: When the pipeline internal and external inspection robots are operating normally, the angle between the line connecting the pipeline internal inspection robot and the pipeline external inspection robot and the horizontal direction is θ0, and θ0 is known. When the angle between the line connecting the pipeline internal inspection robot and the pipeline external inspection robot and the horizontal direction becomes θ 变化值 , the change in magnetic field intensity can be calculated by formula (1), as follows:

[0101]

[0102] Since the influence of soil and air, two media with poor conductivity, on magnetic field attenuation differs by more than 5 orders of magnitude, the attenuation of electromagnetic signals passing through soil and air can be ignored, so the above formula (8) can be simplified to:

[0103]

[0104] Known θ 变化值 and H 变化值 We can find:

[0105]

[0106] If the value of H0 cannot be accurately known, 初始值 , H 初始值 Substituting into formula (1), we get formula (11), and then comparing formula (9) with formula (11), we get the following relationship:

[0107]

[0108]

[0109] We can further find:

[0110]

[0111] Using this method, the change in pipe thickness is measured instantaneously, which can be extended to measure the degree of corrosion above the pipe;

[0112] At the same time, according to the formula: Calculate l d变化值 , where D is the inner diameter of the pipe;

[0113] Step 3: After knowing the current l p变化值 and l d变化值 Afterwards, in order to keep the inner and outer detection robots at an appropriate horizontal distance, they are updated to l p变化值 and l d变化值 , that is, H 变化值 =g(d h正常 , l p变化值 , l d变化值 ).

[0114] Calculating the signal sending time of the external detection robot adjusting the working mode of the internal detection robot comprises the following steps:

[0115] Step 1: Install an electronic level on the pipeline external inspection robot to obtain the corresponding inclination angle α when the pipeline external inspection robot climbs or descends; use the external inspection robot speed n and the external inspection robot wheel radius R o , we can find the corresponding velocity v = 2πR on; thus the vertical and horizontal velocities of the external detection robot can be calculated as:

[0116] v 竖直 = sinα (14)

[0117] v 水平 =vcosα (15)

[0118] Then through the formula: Calculate the vertical distance h between the center of the detection robot coil inside the pipeline and the center of the detection robot coil outside the pipeline at the corresponding time.

[0119] Among them, the initial vertical distance difference h0 between the center of the coil of the detection robot inside the pipeline and the center of the coil of the detection robot outside the pipeline;

[0120] Step 2: On the basis that the external detection robot can obtain the horizontal distance x between itself and the internal detection robot in real time, when the external detection robot reaches the suspected fault point, the lag mileage calculation is performed; the lag mileage is defined as the horizontal distance s traveled by the external detection robot after passing the fault point, and the calculation formula is:

[0121]

[0122] While calculating the horizontal distance s, the horizontal distance d between the inner and outer detection robots is also calculated in real time. h For comparison, When h When it is equal to s, it means that the internal detection robot has also driven to the corresponding fault point, and the corresponding time t2 is the time when the signal is sent. Figure 3 As shown, at this time, the external detection robot sends a signal to the receiving coil of the internal detection robot through the transmitting coil thereon. When the internal detection robot receives the signal, it converts the low-power mode into the high-power mode, performs a comprehensive detection of the fault point, and determines whether the possible fault point preliminarily determined by the external detection robot is the fault point; it can also be expanded to an internal detection robot with multiple power modes, namely high power, relatively high power, medium power, and low power. The high power is 100% detection power, the relatively high power is 80% detection power, the medium power is 50% detection power, and the low power is 30% detection power. The internal detection robot can be controlled to adjust to different modes by adjusting the signal with different intensities emitted by the external detection robot to achieve reasonable energy distribution.

[0123] The speed regulation and obstacle avoidance path planning includes the following steps:

[0124] Step 1: Establish xyz three-dimensional coordinates; when the external inspection robot avoids obstacles above the pipeline, the motion trajectory will deviate from the central axis of the pipeline. At this time, the external inspection robot rotates the motion trajectory on the xy plane to the yz plane with the central axis of the pipeline as the rotation axis, such as Figure 4 As shown, the position of the internal detection robot is assumed to be (0, -y0, z0). The magnetic field strength received here is obtained by the formula of the ELF attenuation quasi-static field. The geometric relationship can be used to derive the equation relationship before and after rotation:

[0125] (z+z0) 2 -x 2 =z0 2 (17)

[0126] We only need to find the equation of z with respect to y in the yz plane, and we can get the equation of x with respect to y by substitution;

[0127] Step 2: Define the length of the pipe wall through which the electromagnetic wave signal passes as l ps , the external detection robot speed changes with the distance a s With △ l ps Proportional, coefficient is k, the relationship is as follows:

[0128] l ps = l p / sinθ (18)

[0129]

[0130] Step 3: Add constraints: Make the component v of the velocity in the y direction at each (0, y, z) during obstacle avoidance y The speed is equal to the initial speed v0 when obstacle avoidance is started, which ensures that the horizontal distance of the original position can be maintained without additional adjustment when obstacle avoidance ends;

[0131] v y =v0 (20)

[0132]

[0133]

[0134] The differential equation is as follows:

[0135]

[0136] By simplifying the second-order differential equation using the Taylor expansion method, we can obtain:

[0137]

[0138] f=Z(y) (25)

[0139] Initial condition expression:

[0140] f(0) = initial position

[0141] f'(0) = obstacle avoidance turning coefficient, related to motion control

[0142] MATLAB can be used to find a numerical solution within a certain range, and multiple polynomial fitting can be performed to obtain Z(y); or the analytical solution of Z(y) can be obtained through functional analysis; then the equations of x and y can be expressed as

[0143]

[0144] The above formula is the moving path planned by the external inspection robot when avoiding obstacles in the xy plane. On this path, there is no need to design an additional algorithm for speed adjustment during obstacle avoidance. The algorithm for adjusting the speed according to the distance when not avoiding obstacles is still maintained. When the obstacle avoidance is completed and the robot returns to the top of the pipeline centerline, the original horizontal distance can be maintained to continue the inspection operation. By reasonably sensing the changes in signal strength, the external inspection robot can avoid obstacles better, return to the pipeline in time, and maintain the original collaborative mode.

[0145] In the pipeline detection, the present invention uses a pipeline internal and external detection robot group to cooperate with each other and sense linkage; uses the ELF electromagnetic attenuation quasi-static field model to set a suitable horizontal distance d h , considering the changes in pipeline thickness and the sensitivity of horizontal and vertical deviations, and working together through signal strength. Considering the changes in factors such as pipeline thickness, buried depth, robot motion state, soil composition, etc., adjust the model parameters to achieve adaptive adaptation to multiple environments.

Claims

1. An adaptive linkage method for pipeline internal and external detection robots based on ELF attenuation field, characterized in that: The external detection robot sends a signal to the internal detection robot, controls the internal detection robot to adjust the working mode, and completes the adaptive linkage between the internal and external detection robots; including the following steps: The internal inspection robot determines whether the pipeline thickness has changed at each moment. If the pipeline thickness has changed, the corresponding model parameters need to be adjusted; if the pipeline thickness has not changed, the original parameters are maintained to continue the inspection; The process of adjusting the corresponding model parameters is as follows: (1) Detect the change in pipeline thickness and adjust the corresponding model parameters to ensure that the horizontal distance between the internal and external inspection robots remains unchanged during the inspection process; (2) When the inner and outer detection robots maintain a constant horizontal distance while walking, when the outer detection robot reaches a possible fault point on the pipeline, the hysteresis mileage calculation is performed to calculate the signal sending time for the outer detection robot to adjust the working mode of the inner detection robot, so that the inner detection robot can switch power and conduct a comprehensive inspection around the fault point; The method for detecting the change of pipeline thickness and adjusting the corresponding model parameters comprises the following steps: Step 1: Calculate the changed thickness of the pipeline according to the initial value of the pipeline thickness and the horizontal distance maintained by the internal and external detection robots; Calculate the changed soil thickness according to the vertical distance between the centers of the internal and external detection robots' coils, the inner diameter of the pipeline and the thickness of the pipeline; Step 2: After knowing the current pipe thickness change value and soil thickness change value, in order to keep the internal and external detection robots at a suitable horizontal distance, the pipe thickness and soil thickness are updated to the changed pipe thickness and soil thickness.

2. The method of adaptive linkage of pipeline internal and external detection robots based on ELF attenuation field according to claim 1 is characterized in that: Also includes: Obstacle avoidance path planning process: When the external inspection robot avoids obstacles above the pipeline, the motion trajectory will deviate from the central axis of the pipeline. At this time, the motion trajectory on the xy plane is rotated to the yz plane with the central axis of the pipeline as the rotation axis. The moving path planned by the external inspection robot when avoiding obstacles in the xy plane is calculated, and it returns to the top of the central axis of the pipeline after the obstacle avoidance is completed.

3. The method of adaptive linkage of pipeline internal and external detection robots based on ELF attenuation field according to claim 1 is characterized by: The internal inspection robot can be selected to have two modes of adjustment: low power and high power. It is also possible to select internal inspection robots with different powers. When an internal inspection robot with adjustable power is selected, the external inspection robot sends signals of different magnitudes to control the internal inspection robot to adjust to different working modes.

4. The method of adaptive linkage of pipeline internal and external detection robots based on ELF attenuation field according to claim 1 is characterized by: Calculating the signal sending time of the external detection robot adjusting the working mode of the internal detection robot comprises the following steps: Step 1: Calculate the corresponding speed according to the corresponding inclination angle, rotation speed and wheel radius of the external detection robot when the pipeline external detection robot climbs or descends, and then calculate the vertical and horizontal component speeds of the external detection robot; obtain the vertical distance between the coil center of the pipeline internal detection robot and the coil center of the pipeline external detection robot at the corresponding moment through the vertical component speed of the external detection robot and the initial vertical distance between the coil center of the pipeline internal detection robot and the coil center of the pipeline external detection robot; Step 2: Integrate the horizontal velocity of the external detection robot to obtain the horizontal distance traveled by the external detection robot after passing the fault point and the signal sending time of the external detection robot to adjust the working mode of the internal detection robot; after receiving the signal, the internal detection robot conducts a comprehensive inspection around the fault point.

5. The method of adaptive linkage of pipeline internal and external detection robots based on ELF attenuation field according to claim 2 is characterized by: The obstacle avoidance path planning process includes the following steps: Step 1: Establish xyz three-dimensional coordinates; when the external inspection robot avoids obstacles above the pipeline, the motion trajectory will deviate from the central axis of the pipeline. At this time, the external inspection robot rotates the motion trajectory on the xy plane to the yz plane with the central axis of the pipeline as the rotation axis. It only needs to find the equation of z with respect to y in the yz plane to obtain the equation of x with respect to y by substitution; Step 2: Based on the xyz three-dimensional coordinates, define the length of the pipe wall through which the electromagnetic wave signal passes and the rate of change of the speed of the external detection robot with the distance; Step 3: Add constraints: Make the component v of the velocity in the y direction at each point during obstacle avoidance y The speed is equal to the initial speed v0 when obstacle avoidance is started, which ensures that the direction of the pipeline can be maintained without additional adjustment when obstacle avoidance is ended; Step 4: According to the xyz three-dimensional coordinates, the length of the pipe wall through which the electromagnetic wave signal passes, the rate of change of the external detection robot's speed with the distance, and the constraints, a differential equation is constructed and solved to obtain the moving path planned by the external detection robot when avoiding obstacles in the xy plane.