Detachable pipe jacking work pit support and its construction technology

By adopting a detachable pipe jacking working well support system during pipe jacking construction, including steel sheet piles, purlins, arc-shaped enclosures and support structures, the existing technology problems of multiple materials, complex construction and environmental damage are solved. Improved construction efficiency and environmental protection.

CN115233703BActive Publication Date: 2024-10-18CHINA MCC5 GROUP CORP LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202210965000.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-12
Publication Date
2024-10-18
Estimated Expiration
2042-08-12

AI Technical Summary

Technical Problem

The existing pipe jacking construction methods contain many types and quantities of materials that cannot be recycled, the construction process is complicated, quality control is difficult, and the environment is severely damaged.

Method used

A detachable pipe jacking working well support system is adopted, including steel sheet piles, purlins, arc-shaped enclosures and support structures. Steel sheet piles are driven into the foundation. The purlins and arc-shaped enclosures form a frame structure, and the support structure provides support. It saves unnecessary pouring process, simplifies the construction process, and realizes the recycling of materials.

Benefits of technology

It simplifies the construction process, shortens the construction period, reduces material waste, meets green construction requirements, and improves construction efficiency and finished product quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115233703B_ABST
    Figure CN115233703B_ABST
Patent Text Reader

Abstract

The present invention provides a detachable pipe jacking work pit support and a construction process thereof, wherein the detachable pipe jacking work pit support includes steel sheet piles; purlins connected to the steel sheet piles, wherein the purlins are in a plurality and constitute a frame structure, and an opening structure is formed on one side of the frame structure; an arc-shaped enclosure connected to the opening of the frame structure, and the arc-shaped enclosure is used for casting a back wall; a support structure is connected between the opposite purlins to support the purlins. The present invention adopts Larsen steel sheet piles, and adjacent Larsen steel sheet piles can engage with each other when driven into the foundation; the side Larsen steel sheet piles are supported by internal supports, which can effectively reduce the bending moment at the top of the steel support; the back wall is in an arc shape, which can effectively reduce the tensile stress and make full use of the compressive strength of concrete; the internal structure of the present invention can make full use of the structure and performance of the component itself, and requires fewer types of work and workers.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipe jacking working shaft support, and in particular to a detachable pipe jacking working shaft support and a construction process thereof. Background Art

[0002] Before pipe jacking construction, a working pit needs to be built. The existing technology generally uses the caisson method to make the working pit. This caisson working pit is to excavate a layer, cast a layer of support; then excavate again, and then support again, and continue the cycle until the excavation reaches the bottom of the well. This method has the following main shortcomings: 1. The types and quantities of materials required are large, and the materials cannot be recycled, which damages the environment; 2. The construction process requires the cooperation of multiple types of workers such as reinforcement workers, formwork workers, and welders, which is time-consuming and labor-intensive; 3. The quality is difficult to control. Summary of the invention

[0003] The present invention aims to solve at least one of the technical problems existing in the prior art.

[0004] To this end, a first aspect of the present invention provides a detachable pipe jacking work pit support.

[0005] A second aspect of the present invention provides a construction process for detachable pipe jacking work pit support.

[0006] The present invention provides a detachable pipe jacking work well support, comprising:

[0007] Steel sheet piles;

[0008] A perimeter purlin is connected to the steel sheet pile, wherein the perimeter purlin is in a certain number and forms a frame structure, and an opening structure is formed on one side of the frame structure;

[0009] An arc-shaped enclosure connected to the opening of the frame structure, the arc-shaped enclosure being used for pouring the back wall;

[0010] The supporting structure is connected between the opposite purlins to support the purlins.

[0011] The detachable pipe jacking working shaft support proposed by the present invention includes steel sheet piles, purlins, arc-shaped enclosures and support structures. Among them, the steel sheet piles are first driven into the set elevation according to the design size and shape of the working shaft. In addition, the steel sheet piles adopt Larsen steel sheet piles to ensure the overall strength. The purlins are connected to the steel sheet piles to form a frame structure, and the interior of the frame structure is the working shaft. On the basis of the above, an arc-shaped enclosure is added to the opening of the frame structure, and the arc-shaped enclosure is used to lean against the wall after pouring for the installation of the main top oil cylinder. In order to further improve the strength of the frame structure, a support structure is set inside the frame structure, and the support structure can provide support for the purlins to prevent the purlins from tilting or collapsing under force. Compared with the traditional caisson method, the present invention not only has a simple structure and eliminates unnecessary pouring process, thereby shortening the construction period, but also the entire device can be recycled, reducing material waste and meeting green construction requirements.

[0012] The detachable jacking work well support according to the above technical solution of the present invention may also have the following additional technical features:

[0013] In the above technical solution, the number of the steel sheet piles is several and they are installed according to the set shape and size of the working well.

[0014] In this technical solution, the number of steel sheet piles is set in multiple groups and adjusted according to actual working conditions.

[0015] In the above technical solution, the steel sheet piles form a tightly fitting structure, and the surrounding purlins form a tightly fitting structure.

[0016] In this technical solution, the steel sheet piles are interlocked and tightly connected to avoid the existence of connection gaps, thereby ensuring the overall strength and improving the molding quality of the working well. The surrounding purlins are tightly fitted to each other, thereby further ensuring the connection strength and reducing the connection gaps.

[0017] The above technical solution also includes:

[0018] A reserved opening is formed on one side of the frame structure.

[0019] In the technical solution, a reserved opening is also included, which is used for manual passage and for the driving end of the main top oil cylinder to pass through, providing an operating channel for it.

[0020] In the above technical solution, the reserved opening is sealed by a sealing plate.

[0021] In this technical solution, the reserved opening is sealed by a sealing plate, which can be a steel plate, so as to ensure the strength of the reserved opening and prevent the reserved opening from collapsing.

[0022] In the above technical solution, opening concrete is poured along the inner wall surface of the reserved opening.

[0023] In this technical solution, the hole opening concrete is used to improve the strength of the reserved opening to prevent the reserved opening from being deformed due to stress and affecting the operation of the main top oil cylinder.

[0024] In the above technical solution, the support structure includes:

[0025] Support columns, each end of which is connected to the opposite perimeter purlin;

[0026] The corbel is connected to the bottom of the support column and provides support for the support column.

[0027] In the technical solution, the support structure is composed of support columns and corbels. The number of support columns is several and is adjusted according to the length of the frame structure. The support columns are supported between the purlins and can provide sufficient support for the purlins to prevent them from tilting or collapsing under force. The corbels are used to provide support for the support columns. In addition, the support columns and corbels can be connected by bolts, which is convenient for disassembly and installation.

[0028] The above technical solution also includes:

[0029] The bottom plate is cast and formed at the bottom of the frame structure.

[0030] In this technical solution, a bottom plate is cast at the bottom of the frame structure, which is used to ensure the flatness of the bottom of the working well, thereby facilitating the installation of machinery such as the main top oil cylinder.

[0031] The above technical solution also includes:

[0032] Reinforcement ribs are connected between the purlins.

[0033] In this technical solution, reinforcing ribs are also included. The reinforcing ribs are used to improve the connection force between the surrounding purlins.

[0034] The present invention also provides a construction process for detachable pipe jacking work pit support as described in any one of the above technical solutions, comprising the following steps:

[0035] Drive steel sheet piles and arc-shaped enclosures to the designed elevation;

[0036] Excavate the foundation pit to 0.5m below the designed purlin height;

[0037] Weld the corbels to the designed position on the steel sheet piles;

[0038] Weld the purlins to the steel sheet piles, continue excavation and repeat the above steps;

[0039] Install the inner bracing to the perimeter purlins;

[0040] Cast the back wall, weld the steel plate opposite to the back wall, drill a reserved hole, and cast the annular support concrete;

[0041] Maintenance is completed.

[0042] Compared with the prior art, the detachable jacking shaft support and construction process thereof proposed in the present invention have the following beneficial effects:

[0043] 1. The present invention adopts Larsen steel sheet piles, and adjacent Larsen steel sheet piles can interlock with each other when driven into the foundation;

[0044] 2. The side Larsen steel sheet piles use internal support to effectively reduce the bending moment at the top of the steel support;

[0045] 3. The back wall is arc-shaped, which can effectively reduce the tensile stress and make full use of the compressive capacity of concrete;

[0046] 4. The internal structure of the present invention can fully utilize the structure and performance of the components themselves, and fewer types of work and workers are required.

[0047] Additional aspects and advantages of the present invention will become apparent from the following description or may be learned by practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0049] Figure 1 It is a top view of the detachable jacking pipe working well support of the present invention;

[0050] Figure 2 It is a front view of the detachable jacking pipe working well support of the present invention;

[0051] Figure 3 It is a side view of the detachable jacking pipe working well support of the present invention;

[0052] Figure 4 It is a structural schematic diagram of the support column and the corbel in the detachable jacking pipe working shaft support of the present invention.

[0053] in, Figures 1 to 4 The corresponding relationship between the reference numerals and the component names is as follows:

[0054] 1. Steel sheet piles; 2. Purlins; 3. Curved enclosures; 4. Back walls; 5. Reserved openings; 6. Sealing plates; 7. Opening concrete; 8. Support columns; 9. Corbels; 10. Bottom plates; 11. Reinforcement ribs. DETAILED DESCRIPTION

[0055] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0056] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.

[0057] Refer to the following Figures 1 to 4 To describe the detachable pipe jacking work shaft support and its construction process provided according to some embodiments of the present invention.

[0058] Some embodiments of the present application provide a detachable pipe jacking work well support.

[0059] like Figures 1 to 4 As shown, the first embodiment of the present invention provides a detachable jacking work well support, comprising:

[0060] Steel sheet pile 1;

[0061] A perimeter purlin 2 is connected to the steel sheet pile 1, wherein the perimeter purlin 2 is in a certain number and forms a frame structure, and an opening structure is formed on one side of the frame structure;

[0062] An arc-shaped enclosure 3 connected to the opening of the frame structure, and the arc-shaped enclosure 3 is used for pouring a back wall 4;

[0063] The supporting structure is connected between the opposite purlins 2 to support the purlins 2.

[0064] The detachable pipe jacking working shaft support proposed by the present invention includes a steel sheet pile 1, a purlin 2, an arc-shaped enclosure 3 and a supporting structure. Among them, the steel sheet pile 1 is first driven into the set elevation according to the design size and shape of the working shaft. In addition, the steel sheet pile 1 adopts Larsen steel sheet pile 1 to ensure the overall strength. The purlin 2 is connected to the steel sheet pile 1 to form a frame structure, and the interior of the frame structure is the working shaft. On the basis of the above, an arc-shaped enclosure 3 is added to the opening of the frame structure, and the arc-shaped enclosure 3 is used to lean against the wall after pouring for the installation of the main top oil cylinder. In order to further improve the strength of the frame structure, a supporting structure is set inside the frame structure, and the supporting structure can provide support for the purlin 2 to prevent the purlin 2 from tilting or collapsing due to force. Compared with the traditional caisson method, the present invention not only has a simple structure and eliminates unnecessary pouring process, thereby shortening the construction period, but also the entire device can be recycled, reducing material waste and meeting green construction requirements.

[0065] The second embodiment of the present invention proposes a detachable jacking pipe working shaft support, and on the basis of the first embodiment, the number of the steel sheet piles 1 is several and they are installed according to the set shape and size of the working shaft.

[0066] In this embodiment, the number of steel sheet piles 1 is set in multiple groups and is adjusted according to actual working conditions.

[0067] The third embodiment of the present invention proposes a detachable jacking pipe working shaft support, and on the basis of any of the above embodiments, the steel sheet piles 1 form a tightly fitting structure, and the surrounding purlins 2 form a tightly fitting structure.

[0068] In this embodiment, the steel sheet piles 1 are interlocked and tightly connected to avoid the existence of connection gaps, thereby ensuring the overall strength and improving the molding quality of the working well. The surrounding purlins 2 are tightly fitted to each other, thereby further ensuring the connection strength and reducing the connection gaps.

[0069] A fourth embodiment of the present invention provides a detachable pipe jacking work well support, and based on any of the above embodiments, further includes:

[0070] The reserved opening 5 is formed on one side of the frame structure.

[0071] In this embodiment, a reserved opening 5 is also included. The reserved opening 5 is used for manual passage and for the passage of the driving end of the main top oil cylinder to provide an operating channel for it.

[0072] The fifth embodiment of the present invention proposes a detachable jacking pipe working shaft support, and on the basis of any of the above embodiments, the reserved opening 5 is sealed by a sealing plate 6.

[0073] In this embodiment, the reserved opening 5 is sealed by a sealing plate 6. The sealing plate 6 can be a steel plate to ensure the strength of the reserved opening 5 and prevent the reserved opening 5 from collapsing.

[0074] The sixth embodiment of the present invention proposes a detachable jacking pipe working shaft support, and on the basis of any of the above embodiments, a hole concrete 7 is poured along the inner wall surface of the reserved opening 5.

[0075] In this embodiment, the hole opening concrete 7 is used to improve the strength of the reserved opening 5 to prevent the reserved opening 5 from being deformed by force and affecting the operation of the main jacking cylinder.

[0076] The seventh embodiment of the present invention provides a detachable pipe jacking work pit support, and based on any of the above embodiments, the support structure includes:

[0077] A support column 8, with both ends connected to the opposite purlins 2;

[0078] The corbel 9 is connected to the bottom of the support column 8 and provides support for the support column 8 .

[0079] In this embodiment, the support structure is composed of support columns 8 and corbels 9. The number of support columns 8 is several and is adjusted according to the length of the frame structure. The support columns 8 are supported between the purlins 2 and can provide sufficient support for the purlins 2 to prevent them from tilting or collapsing under force. The corbels 9 are used to provide support for the support columns 8. In addition, the support columns 8 and the corbels 9 can be connected by bolts, which is convenient for disassembly and installation.

[0080] The eighth embodiment of the present invention provides a detachable pipe jacking work well support, and based on any of the above embodiments, further includes:

[0081] The bottom plate 10 is cast and formed at the bottom of the frame structure.

[0082] In this embodiment, a bottom plate 10 is cast at the bottom of the frame structure. The bottom plate 10 is used to ensure the flatness of the bottom of the working well, so as to facilitate the installation of machinery such as the main top oil cylinder.

[0083] The ninth embodiment of the present invention provides a detachable pipe jacking work well support, and based on any of the above embodiments, further includes:

[0084] The reinforcing ribs 11 are connected between the surrounding purlins 2.

[0085] In this embodiment, reinforcing ribs 11 are also included. The reinforcing ribs 11 are used to improve the connection force between the surrounding purlins 2.

[0086] The tenth embodiment of the present invention proposes a construction process for detachable pipe jacking work pit support as described in any one of the above technical solutions, comprising the following steps:

[0087] Drive steel sheet piles and arc-shaped enclosures to the designed elevation;

[0088] Excavate the foundation pit to 0.5m below the designed purlin height;

[0089] Weld the corbels to the designed position on the steel sheet piles;

[0090] Weld the purlins to the steel sheet piles, continue excavation and repeat the above steps;

[0091] Install the inner bracing to the perimeter purlins;

[0092] Cast the back wall, weld the steel plate opposite to the back wall, drill a reserved hole, and cast the annular support concrete;

[0093] Maintenance is completed.

[0094] In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0095] Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction process for detachable pipe jacking work pit support, characterized in that: The pipe jacking work well support includes: Steel sheet piles; A perimeter purlin is connected to the steel sheet pile, wherein the perimeter purlin is in a certain number and forms a frame structure, and an opening structure is formed on one side of the frame structure; An arc-shaped enclosure connected to the opening of the frame structure, the arc-shaped enclosure being used for pouring the back wall; A supporting structure connected between the opposite purlins to support the purlins; The support structure comprises: Support columns, each end of which is connected to the opposite perimeter purlin; A corbel, connected to the bottom of the support column and providing support for the support column; The construction process includes the following steps: Drive steel sheet piles and arc-shaped enclosures to the designed elevation; Excavate the foundation pit to 0.5m below the designed purlin height; Weld the corbels to the designed position on the steel sheet piles; Weld the purlins to the steel sheet piles, continue excavation and repeat the above steps; Install the support posts to the purlins; Cast the back wall, weld the steel plate at the opposite side of the back wall, punch a reserved hole, form a reserved opening, and cast the annular support concrete; Maintenance is completed.

2. The construction process according to claim 1, characterized in that: The steel sheet piles are provided in a plurality of numbers and are installed according to the set shape and size of the working well.

3. The construction process according to claim 2, characterized in that: The steel sheet piles form a tightly fitting structure, and the surrounding purlins form a tightly fitting structure.

4. The construction process according to claim 3, characterized in that: A reserved opening is formed on one side of the frame structure.

5. The construction process according to claim 4, characterized in that: The reserved opening is sealed by a sealing plate.

6. The construction process according to claim 5, characterized in that: Hole concrete is poured along the inner wall surface of the reserved opening.

7. The construction process according to any one of claims 1 to 5, characterized in that: Also includes: The bottom plate is cast and formed at the bottom of the frame structure.

8. The construction process according to any one of claims 1 to 5, characterized in that: Also includes: Reinforcement ribs are connected between the purlins.

Citation Information

Patent Citations

  • Top tube well structure, and construction method thereof

    CN111851588A

  • Water-stopping structure for reserved hole of pipe-jacking working well

    CN204000963U

  • Detachable pipe jacking working well support

    CN217923645U