A method for calculating the discharge flow rate of coal storage gate without time lag
By establishing a mathematical model based on fluid flow calculation, combining bulk material particle size and gate opening, the problem of real-time measurement of unloading flow of coal storage bin is solved, and the time-delay calculation of unloading flow of coal storage bin is realized, and intelligence is improved Efficiency and control accuracy of the cosmetic truck system.
Patent Information
- Application Number
- CN202210904980.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-29
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2042-07-29
AI Technical Summary
The problem of real-time measurement of unloading flow of the coal storage bin gate. The existing indirect measurement methods have a large time lag, which leads to slow adjustment of unloading speed during loading, and cannot meet the buffer bin level control in time, resulting in insufficient supply of quantitative bins, affecting Loading efficiency.
By establishing a coal bin unloading flow calculation model based on fluid flow calculation, introducing bulk material particle size and gate opening, establishing a mathematical mapping relationship, calculating unloading speed and flow, real-time unloading flow calculation, and adjusting the gate opening to match Loading needs.
It realizes direct calculation of the unloading flow of the coal storage bin gate without delay, improves the operating efficiency of the intelligent loading system, and ensures real-time control and efficiency of the loading process.
Smart Images

Figure CN115290147B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for calculating the discharge flow of a coal storage bin gate without time lag. Background Art
[0002] The instantaneous changes of some detection data in the intelligent control system of rapid quantitative loading are extremely drastic. At present, the measurement accuracy of sensors is low or there is no effective measurement method, which sets a huge obstacle to the intelligent upgrade of loading stations. Among them, since the flow data indirectly measured by the belt scale of the transport belt under the coal storage bin has a time lag, it is not the real-time gate flow data directly obtained, resulting in delayed control. Therefore, the real-time measurement problem of the coal storage bin gate discharge flow is particularly prominent. Since it is impossible to realize the real-time direct measurement of the instantaneous gate discharge flow, and the indirect measurement method has the defect of large time lag, the adjustment of the coal storage bin discharge speed during the loading process lacks timely basis, and the belt conveyor feeding speed is not adjusted in time, which cannot meet the actual requirements of the buffer bin material level control. In the end, the quantitative bin may be under-fed, and the loading carriage has to stop moving to wait for the material in the quantitative bin to reach the rated weight, so the expected loading efficiency is often not achieved. Summary of the invention
[0003] The purpose of the present invention is to provide a method for calculating the unloading flow of a coal storage bin gate without time lag. It is a mathematical calculation method for the unloading flow that introduces fluid flow calculation and takes into account the particle size of bulk materials. A mathematical mapping relationship between the opening of the unloading bin gate, the measured particle size of bulk materials and the unloading flow at the gate is established to reduce the control error in the intelligent loading process and effectively improve the actual operating efficiency of the intelligent loading system.
[0004] In order to achieve the above object, the scheme of the present invention is:
[0005] A method for calculating the discharge flow of a coal storage bin gate without time lag is provided. A coal storage bin discharge flow calculation model is established based on a fluid flow calculation formula. The discharge speed v of the coal storage bin discharge flow calculation model is used as a to-be-determined discharge speed variable. The coal storage bin discharge flow is finally obtained by determining the discharge speed variable. The coal storage bin discharge flow calculation model is:
[0006] Q=3600γ·ω0·v Formula 1
[0007] Where:
[0008] Q represents the discharge flow at the gate, in t / h, tons / hour;
[0009] γ represents bulk density, unit is T / m 3 , tons / cubic meter;
[0010] ω0 represents the actual unloading area formed by the gate opening, in m 2;
[0011] v represents the discharge speed at the gate, in m / s, meters per second;
[0012] The calculation process of the discharge flow is:
[0013] Step 1: First, a database of particle diameters of different unloaded bulk materials is established, and the belt weighing sensor under the gate is used to experimentally obtain the time-delay flow weighing data of different unloaded bulk materials after they fall onto the belt weighing sensor at different openings of the coal storage bin gate;
[0014] Step 2: Introduce the calculation formula 2 in the fluid flow calculation method, which states that the equivalent diameter value is 4 times the hydraulic radius value, and introduce the calculation formula for the coal preparation discharge speed, that is, convert the calculation of the discharge speed v in formula 1 into formula 3.
[0015] A=4R H Formula 2
[0016]
[0017] in:
[0018] λ represents the discharge coefficient, which is used to correct the discharge speed;
[0019] g represents the acceleration due to gravity;
[0020] A represents the equivalent diameter;
[0021] R H It represents the hydraulic radius, where the hydraulic radius is the ratio of the geometric area of a certain opening of the coal storage bin gate to the perimeter: Where: Π is the perimeter;
[0022] Step 3: Calculate the equivalent diameter A based on the ratio of the hydraulic radius to the perimeter of the geometric figure with a certain opening of the coal storage bin gate.
[0023]
[0024] Step 4: Based on Formula 1, we can get the coal storage bin gate discharge flow expression formula 5:
[0025]
[0026] The other parameters other than the known gate opening values ω0 and equivalent diameter A on the left and right sides in formula 5 are extracted and combined to be recorded as the parameter k represented by formula 6,
[0027]
[0028] For the discharge coefficient λ, formula 5 and formula 6, the different discharge coefficients λ corresponding to different parameter k values are calculated based on the lag flow of different unloaded bulk materials at different coal storage bin gate openings, forming a database of different coal storage bin gate openings corresponding to different parameter k values, and then the discharge speeds at different coal storage bin gate openings are obtained by formula 3, so that the coal storage bin gate discharge flow can be finally obtained by determining the discharge speed.
[0029] The scheme further includes: the parameter k value is a multiple set of k corresponding to formula 7 under a series of gate opening conditions j The fitted calculation value of the value;
[0030]
[0031] In the formula,
[0032] m1, m2, and m3 represent the coefficients fitted when the total gate opening is less than the threshold;
[0033] n1, n2, n3 represent the coefficients fitted when the total gate opening is greater than the threshold;
[0034] l represents the total gate opening threshold;
[0035] a′=d′ / 2 is the radius of the particles of the unloaded bulk material.
[0036] The scheme further includes: the multiple groups k j The value should be no less than 5 groups.
[0037] Compared with the prior art, the advantages of the present invention are as follows: the relationship between the unloading area and the unloading speed of the coal storage bin gate of the loading station is given, and the calculation method of the parameter k is given in combination with the indirect hysteresis measurement data, thereby completely establishing a real-time calculation model for the unloading flow of the coal storage bin gate, wherein: the introduced fluid flow calculation method and the coal preparation discharge speed calculation formula provide a theoretical basis for the establishment of the calculation model, and the present invention realizes the direct calculation of the gate unloading flow without hysteresis, and then realizes the real-time gate opening adjustment during the loading process, that is: there is a known mathematical mapping relationship between the gate opening and the unloading flow, and given the gate opening, the unloading flow can be directly obtained accordingly. During the loading operation, if the amount of material is insufficient, the gate unloading flow is increased to the specified value by adjusting the coal storage bin gate opening; if the amount of material is too much, the gate unloading flow is reduced to the specified value by adjusting the coal storage bin gate opening. The calculation method of the present invention provides a solid theoretical basis for intelligent loading control.
[0038] The present invention is described in detail below with reference to the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 This is a schematic diagram of the unloading area of the circular gate of the coal storage bin. DETAILED DESCRIPTION
[0040] A method for calculating the discharge flow of a coal storage bin gate without time lag, the method establishes a coal storage bin discharge flow calculation model based on a fluid flow calculation formula, takes the discharge speed v of the coal storage bin discharge flow calculation model as a to-be-determined discharge speed variable, and finally obtains the coal storage bin discharge flow by determining the discharge speed variable. The coal storage bin discharge flow calculation model is:
[0041] Q=3600γ·ω0·v Formula 1
[0042] Where:
[0043] Q represents the discharge flow at the gate, in t / h, tons / hour;
[0044] γ represents bulk density, unit is T / m 3 , tons / cubic meter;
[0045] ω0 represents the actual unloading area formed by the gate opening, in m 2 ;
[0046] v represents the discharge speed at the gate, in m / s, meters per second;
[0047] The calculation process of the discharge flow is:
[0048] Step 1: First, establish a database of particle diameters of different unloaded bulk materials, and use the belt weighing sensor under the gate to experimentally obtain the flow weighing data of different unloaded bulk materials when they fall to the belt weighing sensor at different openings of the coal storage bin gate;
[0049] Step 2: Introduce the calculation formula 2 in the fluid flow calculation method, which states that the equivalent diameter value is 4 times the hydraulic radius value, and introduce the calculation formula for the coal preparation discharge speed, that is, convert the calculation of the discharge speed v in formula 1 into formula 3.
[0050] A=4R H Formula 2
[0051]
[0052] in:
[0053] λ represents the discharge coefficient, which is used to correct the discharge speed;
[0054] g represents the acceleration due to gravity;
[0055] A represents the equivalent diameter;
[0056] R H It represents the hydraulic radius, where the hydraulic radius is the ratio of the geometric area of a certain opening of the coal storage bin gate to the perimeter: Where: Π is the perimeter;
[0057] Step 3: Calculate the equivalent diameter A based on the ratio of the hydraulic radius to the perimeter of the geometric figure with a certain opening of the coal storage bin gate.
[0058]
[0059] Step 4: Based on Formula 1, we can get the coal storage bin gate discharge flow expression formula 5:
[0060]
[0061] The other parameters other than the known gate opening values ω0 and equivalent diameter A on the left and right sides in formula 5 are extracted and combined to be recorded as the parameter k represented by formula 6,
[0062]
[0063] For the discharge coefficient λ, Formula 5 and Formula 6, the different discharge coefficients λ corresponding to different parameter k values are calculated and determined based on the time-delayed flow rates of different unloaded bulk materials at different coal storage bin gate openings, forming a database of different coal storage bin gate openings corresponding to different parameter k values. The real-time unloading speeds at different coal storage bin gate openings are then obtained from Formula 3, so that the real-time coal storage bin gate unloading flow can be finally obtained by determining the unloading speed.
[0064] The coal storage bin gate in the embodiment can be rectangular (square) or circular. The area calculation of gates of different shapes is different. The following takes the circular gate of the coal storage bin as an example to illustrate the calculation. Figure 1 The unloading area of the circular gate of the coal storage bin is shown in the figure. The circular area in the figure is the circular gate of the coal storage bin. In the closed state, the left and right gates are located at the dotted line position in the figure. In the open state, the maximum opening position of the gate is the left and right sides of the square, respectively. Among them: r represents the radius of the circular gate, x1 represents the opening of the left gate, x2 represents the opening of the right gate, α1 and α2 are radian values, both of which are known quantities. In order to prevent excessive falling impact, it is usually Figure 1 The opening of the left gate and the opening of the right gate are asymmetrical, so that the coal falls in a sliding manner.
[0065] by Figure 1 As an example, the coal storage bin gate discharge flow rate without time lag calculation method includes: establishing a coal bin discharge flow rate calculation model based on the fluid flow rate calculation formula (flow rate equals cross-sectional area multiplied by speed, Q=Sv). Since the discharge speed depends on the properties of bulk materials (such as dryness and wetness, particle size, etc.) and is related to the size of the gate opening, it is a variable; therefore, this method uses the discharge speed v of the coal bin discharge flow rate calculation model as the undetermined discharge speed variable, and finally obtains the coal bin discharge flow rate by determining the discharge speed variable. The coal bin discharge flow rate calculation model is:
[0066] Q=3600γ·ω0·v Formula 1
[0067] Where:
[0068] Q represents the discharge flow at the gate, in t / h, tons / hour;
[0069] γ represents bulk density, unit is t / m 3 , tons / cubic meter, can be obtained by looking up the table based on bulk materials;
[0070] ω0 represents the actual unloading area at the gate, in m 2 ;
[0071] v represents the discharge speed at the gate, in m / s, meters per second;
[0072] The calculation process of the discharge flow is:
[0073] Step 1: First, establish a database of particle diameters of different unloaded bulk materials (obtained through sample measurement), and use the existing belt weighing sensor under the gate (the current general weighing system) to experimentally obtain the flow weighing data of different unloaded bulk materials falling to the belt weighing sensor at different openings of the coal storage bin gate;
[0074] Step 2: Introduce the calculation formula 2 in the fluid flow calculation method, which states that the equivalent diameter value is 4 times the hydraulic radius value, and introduce the calculation formula for the coal preparation discharge speed, that is, convert the calculation of the discharge speed v in formula 1 into formula 3.
[0075] A=4R H Formula 2
[0076]
[0077] in:
[0078] λ represents the discharge coefficient, which is used to correct the discharge speed;
[0079] g represents the acceleration due to gravity;
[0080] A represents the equivalent diameter;
[0081] R H It represents the hydraulic radius, where the hydraulic radius is the ratio of the area to the perimeter of the geometric figure of a certain opening of the coal storage bin gate;
[0082] The calculation formula of coal preparation discharge speed is selected from the Coal Preparation Manual of Book No. 3472E0151 Coal Industry Press, Chapter 7 Auxiliary Equipment of Coal Preparation Plant, Chapter 3 Conveying Equipment, Section 6 Gate;
[0083] Step 3: Based on the hydraulic radius, the area-to-perimeter ratio of the geometric figure with a certain opening of the coal storage bin gate is obtained, and then the equivalent diameter formula 4 is obtained from formula 2:
[0084]
[0085] Where:
[0086]
[0087] r represents the radius of the circular gate;
[0088] x1 represents the opening of the left gate;
[0089] x2 represents the opening of the right gate;
[0090] d′ represents the particle diameter of the unloaded bulk material;
[0091] Step 4: Based on formula 1, we can get the formula 5 for the discharge flow of the circular gate of the coal storage bin:
[0092]
[0093] Figure 1 In the formula, r represents the radius of the circular gate, x1 represents the opening of the left gate, and x2 represents the opening of the right gate, all of which are known quantities. Based on the above known quantities, the length values of a1 and a2, as well as the arc values of α1 and α2 are obtained respectively (already expressed in formula 4 of step 3). Here, the bulk material is simplified to spherical particles, and the measured value of the bulk material particle size, i.e., the bulk material diameter, is d', then the bulk material radius is:
[0094] a′=d′ / 2
[0095] Among them, in order to ensure the accuracy of calculation, in the calculation of the area and perimeter of the unloading area, the radius of the material is subtracted in the radial direction as the calculation basis, that is, the opened gate area through which the geometric center of the particle can pass is taken as the actual unloading area.
[0096] Due to the huge number of bulk particles, it is impossible to complete the particle size measurement of all particles, so the gradation method is used to measure the average particle size of bulk materials. That is, a certain mass of bulk material to be loaded is selected, a series of particle size intervals are set, and the proportion of the mass of particles in each particle size interval to the total mass of the bulk material is obtained. The sieving method is further used to measure the particle size of complex bulk materials, and the mass percentage of bulk materials in each particle size interval is obtained, and then the average particle size value of the bulk materials is calculated.
[0097] The area of the unloading area is calculated in four parts, namely, the areas of two triangles and two sectors are calculated separately:
[0098] ω0=a1(x1-a′sinα1)+α1(ra′) 2+a2(x2-a′sinα2)+α2(ra′) 2
[0099] The perimeter of the unloading area is also calculated in four parts, namely, the lengths of the two straight sides and the two arc sides are calculated separately:
[0100] Π=2((a1-a′cosα1)+α1(ra′)+(a2-a′cosα2)+α2(ra′))
[0101] The hydraulic radius is the ratio of the discharge area to its perimeter:
[0102]
[0103] The corresponding equivalent diameter is:
[0104]
[0105] The other parameters except the gate opening values on the left and right sides and the particle diameter of the unloaded bulk material known in Formula 5 are extracted and combined to be recorded as the parameter k represented by Formula 6.
[0106]
[0107] For the discharge coefficient λ, formula 5 and formula 6, the different discharge coefficients λ corresponding to different parameter k values are calculated and determined based on the hysteresis flow of different unloaded bulk materials at different coal storage bin gate openings. The range is usually between 0 and 1, forming a database of different coal storage bin gate openings corresponding to different parameter k values. Then, the discharge speed at different coal storage bin gate openings is obtained by formula 3, so that the discharge flow rate can be finally obtained by determining the discharge speed.
[0108] In addition to the known fixed items such as material density and gravity acceleration, parameter k also includes the discharge coefficient λ related to bulk material viscosity, humidity, fluidity and other parameters, that is, the size of the discharge coefficient is related to different bulk material types and batches. In addition, the discharge coefficient also needs to consider the calculation error caused by the uneven bulk material particle size. Under the combined effect of these factors, the discharge coefficient cannot be taken as a fixed value in advance, and needs to be calculated differently according to the on-site material conditions. The calculation method is:
[0109]
[0110] Here, the indirect flow measurement method (through-belt scale weighing method) is used for hysteresis calculation. In the above formula, the material particle size, gate opening and other geometric parameters contained in the numerator are all known, and the denominator is the discharge flow obtained by the indirect hysteresis measurement of the belt scale, recorded as Q jAccording to the above formula, the indirect hysteresis measurement value of parameter k under different gate opening conditions can be obtained under the condition that the material particle size is known, which is recorded as k j Although the indirect measurement method has the disadvantage of large delay, it can provide data support for the fitting calculation of parameter k, and then realize the direct mathematical calculation of the unloading flow rate based on parameter k, and finally complete the timely adjustment of the unloading flow rate at the gate of the coal storage bin during the loading process.
[0111] In actual tests, when the sum of the gate openings on both sides (total gate opening) is large, the effect of bulk material size on parameter k is significantly reduced, so a reasonable total gate opening threshold can be selected. When the total gate opening is less than the threshold, the corresponding k under a series of smaller gate opening conditions is j Calculate the value and complete the coefficient fitting calculation; when the total gate opening is greater than the threshold, according to the corresponding k under a series of larger gate opening conditions j Calculate the value and complete the coefficient fitting calculation. To ensure the accuracy of fitting, the gate opening and the corresponding k under two conditions are j The calculated data should not be less than 5 groups.
[0112] Therefore: The parameter k value is a multiple set of k corresponding to formula 7 under a series of gate opening conditions. j The fitted calculation value of the value;
[0113]
[0114] In the formula,
[0115] m1, m2, and m3 represent the coefficients fitted when the total gate opening is less than the threshold;
[0116] n1, n2, n3 represent the coefficients fitted when the total gate opening is greater than the threshold;
[0117] l represents the total gate opening threshold;
[0118] a′=d′ / 2 is the radius of the particles of the unloaded bulk material.
[0119] The coefficients are fitted and calculated based on the above flow lag measurement data: the order of magnitude of the quadratic term coefficient of material particle size is 10-2, and its contribution to the parameter k value is very small, indicating that the selection of a quadratic polynomial can fit the parameter k curve more accurately; the linear term coefficient of material particle size is distributed between 1 and 20, indicating that the linear term coefficient has a significant influence on the parameter k value; the order of magnitude of the constant term coefficient is 103, which has the greatest influence on the parameter k value, indicating that the viscosity, humidity, fluidity and other properties of the material affect the discharge flow at the gate mainly through the constant term coefficient.
[0120] The above embodiment provides a calculation method for the unloading area and unloading speed of the coal storage bin gate of the loading station, and provides a calculation method for the parameter k in combination with the indirect hysteresis measurement data, thereby completely establishing a real-time calculation model for the unloading flow of the coal storage bin gate, wherein: the introduced fluid flow calculation method and the coal preparation discharge speed calculation formula provide a theoretical basis for the establishment of the calculation model, and the present invention realizes the direct calculation of the gate unloading flow without hysteresis, and then realizes the real-time gate opening adjustment during the loading process, that is: there is a known mathematical mapping relationship between the gate opening and the unloading flow, and given the gate opening, the unloading flow can be directly obtained accordingly. During the operation, if the feeding amount is insufficient, the gate unloading flow is increased to the specified value by adjusting the gate opening; if the feeding amount is too much, the gate unloading flow is reduced to the specified value by adjusting the gate opening. The calculation method of the present invention provides a solid theoretical basis for intelligent loading control.
Claims
1. A method for calculating the discharge flow rate of a coal storage bin gate without time lag, characterized in that: A coal bunker unloading flow calculation model is established based on the fluid flow calculation formula. The unloading speed v of the coal bunker unloading flow calculation model is used as the unloading speed variable to be determined. The coal bunker unloading flow is finally obtained by determining the unloading speed variable. The coal bunker unloading flow calculation model is: Q=3600γ·ω0·v Formula 1 Where: Q represents the discharge flow at the gate, in t / h, tons / hour; γ represents bulk density, unit is t / m 3 , tons / cubic meter; ω0 represents the actual unloading area formed by the gate opening, in m 2 ; v represents the discharge speed at the gate, in m / s, meters per second; The calculation process of the discharge flow is: Step 1: First, a database of particle diameters of different unloaded bulk materials is established, and the belt weighing sensor under the gate is used to experimentally obtain the time-delay flow weighing data of different unloaded bulk materials after they fall onto the belt weighing sensor at different openings of the coal storage bin gate; Step 2: Introduce the calculation formula 2 in the fluid flow calculation method, which states that the equivalent diameter value is 4 times the hydraulic radius value, and introduce the calculation formula for the coal preparation discharge speed, that is, convert the calculation of the discharge speed v in formula 1 into formula 3. A=4R H Formula 2 in: λ represents the discharge coefficient, which is used to correct the discharge speed; g represents the acceleration due to gravity; A represents the equivalent diameter; R H It represents the hydraulic radius, where the hydraulic radius is the ratio of the geometric area of a certain opening of the coal storage bin gate to the perimeter: Where: Π is the perimeter; Step 3: Calculate the equivalent diameter A based on the ratio of the hydraulic radius to the perimeter of the geometric figure with a certain opening of the coal storage bin gate. Step 4: Based on Formula 1, we can get the coal storage bin gate discharge flow expression formula 5: The other parameters other than the known gate opening values ω0 and equivalent diameter A on the left and right sides in formula 5 are extracted and combined to be recorded as the parameter k represented by formula 6, For the discharge coefficient λ, formula 5 and formula 6, the different discharge coefficients λ corresponding to different parameter k values are calculated based on the lag flow of different unloaded bulk materials at different coal storage bin gate openings, forming a database of different coal storage bin gate openings corresponding to different parameter k values, and then the discharge speeds at different coal storage bin gate openings are obtained by formula 3, so that the coal storage bin gate discharge flow can be finally obtained by determining the discharge speed.
2. The method for calculating the discharge flow rate of a coal storage bin gate without time lag according to claim 1 is characterized in that: The parameter k value is a multiple set of k corresponding to formula 7 under a series of gate opening conditions. j The fitted calculation value of the value; In the formula, m1, m2, and m3 represent the coefficients fitted when the total gate opening is less than the threshold; n1, n2, n3 represent the coefficients fitted when the total gate opening is greater than the threshold; l represents the total gate opening threshold; a′=d′ / 2 is the radius of the particles of the unloaded bulk material.
3. The method for calculating the discharge flow rate of the coal storage bin gate without time lag according to claim 2 is characterized in that: The multiple groups k j The value is not less than 5 groups.