A concrete anti-cracking construction method based on temperature control and a construction device thereof
By installing heat exchange pipes of multiple unit sections in the concrete to be poured area and injecting heat exchange medium, the problem of concrete temperature control is solved, the construction of water source stations and human resources consumption is reduced, and more efficient concrete crack-proof construction is achieved.
Patent Information
- Application Number
- CN202211483468.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-24
- Publication Date
- 2025-04-15
- Estimated Expiration
- 2042-11-24
AI Technical Summary
The prior art is difficult to effectively control the temperature during concrete pouring, resulting in temperature cracks. At the same time, the transportation and installation of condensate pipes are inconvenient, and the construction of water source stations also consumes a lot of manpower and material resources.
The concrete crack-proof construction method based on temperature control is adopted. By installing a heat exchange pipe in the area to be poured, the heat exchange pipe consists of multiple unit sections, the medium inlet and outlet are located outside the area to be poured, and the concrete temperature is controlled by injecting the heat exchange medium to reduce the construction of the water source station.
Effectively reduce the temperature of concrete structures, reduce the occurrence of temperature cracks, simplify the transportation and installation of condensate pipes, reduce the construction of water source stations, and save manpower and resources.
Smart Images

Figure CN115853274B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of concrete crack prevention, and in particular to a concrete crack prevention construction method based on temperature control and a construction device thereof. Background Art
[0002] Concrete releases a large amount of heat during the solidification process, but concrete itself is a poor conductor of heat, which causes heat to accumulate inside the concrete, resulting in a large temperature difference between the inside and outside. As a result, temperature cracks are likely to occur after the concrete solidifies. Temperature cracks seriously affect the integrity and durability of the concrete structure.
[0003] In the related art, before pouring concrete, a spiral condenser is buried in the concrete. The condenser is provided with a medium inlet and a medium outlet, and a water source station is built at the medium inlet of the condenser. When the concrete needs to be cooled, condensed water is circulated and injected into the condenser through the water source station to achieve the purpose of cooling.
[0004] For some longer pouring areas, such as roads, when laying condenser pipes, if the condenser pipes are too long, it is not convenient to transport and lay them. When the condenser pipes are shorter, more condenser pipes will be needed for the longer pouring area, which requires the construction of more water source stations and consumes more manpower and material resources. Summary of the invention
[0005] In order to facilitate the installation and transportation of condenser pipes while reducing the construction of water source stations, the present application provides a concrete anti-cracking construction method based on temperature control.
[0006] In the first aspect, the present application provides a concrete crack prevention construction method based on temperature control, which adopts the following technical solution:
[0007] A method for constructing a concrete crack-proof heat exchange tube based on temperature control comprises the following steps: step 1, installing a heat exchange tube in an area to be poured, wherein a medium inlet and a medium outlet of the heat exchange tube are both located outside the area to be poured; the heat exchange tube comprises a plurality of unit sections, wherein the unit sections comprise a starting section, a finishing section and a plurality of connecting sections, the medium inlet of the heat exchange tube is arranged on the starting section, the medium outlet of the heat exchange tube is arranged on the finishing section, one end of the starting section and the connecting section are both connected with a connecting tube 1, and the other end of the finishing section and the connecting section are both connected with a connecting tube 2, wherein the connecting tube 1 is used to be connected with the connecting tube 2; step 2, pouring concrete in the area to be poured; step 3, controlling the concrete temperature by injecting a heat exchange medium into the heat exchange tube.
[0008] By adopting the above technical solution, before pouring concrete, heat exchange tubes are arranged in the area to be poured. Therefore, after pouring concrete, if the temperature in the concrete structure is too high, a cooling medium (such as condensed water) can be injected into the heat exchange tubes. The cooling medium flows along the heat exchange tubes and flows out from the medium outlet, thereby taking out the heat in the concrete structure, thereby reducing the temperature of the concrete structure and improving the problem of temperature cracks easily generated in the concrete. In addition, for roads, in winter, the roads are prone to ice. At this time, a heating medium (such as steam) can be injected into the heat exchange tubes to heat the concrete structure, so as to melt the ice and snow on the road and make the road passable normally. By setting up heat exchange tubes and in the exchange The temperature of the concrete structure can be controlled by injecting heat exchange medium into the heat pipe; for the construction of a longer area to be poured (such as a road), the heat exchange pipe is arranged into multiple unit sections, and the unit section is composed of a starting section, a finishing section and multiple connecting sections, so that the heat exchange pipe can be installed section by section during construction, which is convenient for the transportation and installation of the heat exchange pipe. At the same time, the setting of multiple connecting sections is convenient for controlling the length of the unit section, and each unit section has a medium inlet and a medium outlet, which is convenient for the subsequent supply of heat exchange medium and the recovery of heat exchange medium; in addition, the starting section, the finishing section and multiple connecting sections can be connected through connecting pipe 1 and connecting pipe 2, so that the unit section forms a whole, reducing the medium inlet and the medium outlet, so as to reduce the construction of the water source station.
[0009] Optionally, the connecting tube 2 is used to be inserted into the connecting tube 1, an air ring is fixed on the inner wall of the connecting tube 1, the air ring is used to be sleeved on the connecting tube 2, and the connecting tube 1 is provided with an inflation component for inflating the air ring, and the air ring is inflated to press against the connecting tube 2.
[0010] By adopting the above technical solution, after connecting tube 2 is inserted into connecting tube 1, the air ring is inflated through the inflation component, so that the air ring can be expanded and pressed against connecting tube 2. Through the arrangement of the air ring and the inflation component, the connection between connecting tube 1 and connecting tube 2 has good sealing performance.
[0011] Optionally, the inflation component includes a piston block and a spring. An air groove is opened on the inner wall of the connecting tube one, and the piston block is inserted into the air groove. The spring has a tendency to cause the piston block to partially extend out of the air groove and enter the connecting tube one. The connecting tube two is inserted into the connecting tube one to push the piston block into the air groove, and the air groove is connected to the air ring.
[0012] By adopting the above technical solution, when connecting tube 2 is inserted into connecting tube 1, the piston will be pushed to move, so that the piston is inserted into the air groove, so that under the action of air pressure, the gas in the air groove enters the air ring, causing the air ring to expand; the inflation component has a simple structure and is easy to operate.
[0013] Optionally, a limiting rod is inserted into the inner wall of the connecting tube, and a limiting groove is provided on the inner wall of the connecting tube for the limiting rod to be fully inserted into. The limiting groove is connected to the air groove, and when the spring is not deformed, the limiting rod is completely located in the limiting groove; a slot is provided on the outer wall of the connecting tube for the limiting rod to be inserted into.
[0014] By adopting the above technical solution, during the process of connecting tube 2 being inserted into connecting tube 1, since the limiting rod is blocked by the outer wall of connecting tube 2 and will not move, the gas in the air groove will preferentially enter the air ring until the groove on the outer wall of connecting tube 2 moves to the position of the limiting rod. Then the limiting rod can move, so that the gas in the air ring will partially overflow, pushing the limiting rod into the groove, making it impossible for connecting tube 2 to separate from connecting tube 1, thereby enhancing the connection stability between connecting tube 2 and connecting tube 1.
[0015] In a second aspect, the present application provides a construction device using a concrete anti-cracking construction method based on temperature control, which adopts the following technical solution:
[0016] Optionally, a construction device adopting a concrete anti-cracking construction method based on temperature control includes an installation mechanism and at least two installation rails, the installation mechanism is used to install the unit segment between two adjacent installation rails, the installation mechanism includes a mobile frame used to be installed on the installation rail and move along the length direction of the installation rail, the mobile frame is provided with a bearing plate for carrying the unit segment, the mobile frame is provided with a conveying mechanism, the conveying mechanism is used to install the unit segment on the bearing plate between two adjacent installation rails and insert the connecting pipe 2 into the connecting pipe 1 to connect the connecting pipe 1.
[0017] By adopting the above technical solution, when installing the unit segment, the starting segment, the ending segment and the multiple connecting segments are placed on the supporting plate in the vertical direction according to the installation sequence, and then the starting segment, the ending segment and the multiple connecting segments are installed between two adjacent installation rails according to the installation sequence through the conveying mechanism. Through the setting of the installation mechanism, the supporting plate can carry the unit segment, and the conveying mechanism can install the unit segment on the supporting plate between two adjacent slide rails, which can reduce manpower and is a prerequisite for realizing automated construction. The setting of the installation rail is convenient for the sliding of the mobile frame on the one hand, and for the positioning of the unit segment on the other hand.
[0018] Optionally, the transport mechanism includes a slide seat which is arranged on a mobile frame and can move in a vertical direction, the mobile frame is provided with a driving component 1 for driving the slide seat to slide, the slide seat is rotatably connected to a material picking rack, the rotating axis of the material picking rack is arranged in a vertical direction, the slide seat is provided with a driving component 2 for driving the material picking rack to rotate, the material picking rack is provided with a cylinder, the telescopic end of the cylinder is fixedly connected to an electromagnetic suction cup, and the cylinder is telescopic so that the electromagnetic suction cup can grab the unit segment on the carrying plate.
[0019] By adopting the above technical solution, when installing the unit segment, the unit segment on the supporting plate is grabbed by the cylinder and the electromagnetic suction cup, and then the material picking rack is rotated by the driving component 2 to drive the cylinder to rotate, so that the unit segment grabbed by the cylinder is located above the two adjacent slide rails, and then the slide seat is driven downward by the driving component 1 to install the unit segment between the two installation rails; the transport mechanism has a simple structure and is easy to operate.
[0020] Optionally, the carrying plate is rotatably connected to the mobile frame, the rotation axis of the carrying plate is arranged along the vertical direction, and the mobile frame is provided with a driving component three for driving the carrying plate to rotate.
[0021] By adopting the above technical solution, since some wider concrete construction areas need to install multiple installation rails, for example, when installing three installation rails, the mobile frame is installed on the middle installation rail, the conveying mechanism can first install the unit segment on the bearing plate between the middle installation rail and the installation rail on one side, and then rotate the bearing plate to a suitable position, the conveying mechanism can install the unit segment on the bearing plate between the middle installation rail and the installation rail on the other side, without removing the mobile frame from the middle installation rail, which is simple and convenient.
[0022] Optionally, the starting section, the ending section and the plurality of connecting sections are all fixedly connected with a card block, and the mounting track is provided with a slot for the card block to be vertically inserted.
[0023] By adopting the above technical solution, it is convenient to prevent the unit segment from being displaced in the horizontal direction.
[0024] In summary, this application includes the following beneficial technical effects:
[0025] 1. In the present application, when transporting and installing the unit segment, the unit segment can be split to reduce the length of the unit segment, thereby facilitating the transportation and installation of the unit segment. When installing the unit segment, the unit segment can be installed segment by segment, and during the installation process, the starting segment, the ending segment and multiple connecting segments are connected into a whole through the connecting pipe 1 and the connecting pipe 2, so as to facilitate the introduction of heat exchange medium into the entire unit segment, thereby reducing the construction of the water source station;
[0026] 2. This application facilitates the installation of the heat exchange tube unit section by setting up the construction device, saves manpower, and is a prerequisite for realizing the automated construction of the heat exchange tube. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a schematic diagram of the overall structure of a concrete anti-cracking construction method based on temperature control in the present application;
[0028] Figure 2 yes Figure 1 Schematic diagram of the local structure;
[0029] Figure 3 yes Figure 2 A schematic diagram of the connection structure of the middle connecting pipe 1 and the connecting pipe 2;
[0030] Figure 4 yes Figure 3 A cross-sectional view of
[0031] Figure 5 It is a schematic diagram of the overall structure of the construction process of a construction device of a concrete anti-cracking construction method based on temperature control in the present application;
[0032] Figure 6 yes Figure 5 Schematic diagram of the overall structure of the construction device.
[0033] Description of reference numerals:
[0034] 1. Road; 2. Medium supply box; 3. Medium recovery box; 4. Delivery pump; 5. Heat exchange tube; 6. Delivery tube; 7. Medium inlet; 8. Medium outlet; 9. Water pump; 10. Medium inlet tube; 11. Medium outlet tube; 12. Starting section; 13. Ending section; 14. Connecting section; 15. Connecting tube 1; 16. Connecting tube 2; 17. Annular groove; 18. Air ring; 19. Rubber pad; 20. Piston block; 21. Spring; 22. Air groove; 23. Air pipe; 24. Gear ring; 25. Limiting groove; 26. Limit rod; 27. Slot; 28. Pipe; 29. Slider; 30. T-slot; 31. Guide plate; 32. Roller; 33. Motor 1; 34. Mounting seat; 35. Slide seat; 36. Motor 2; 37. Screw; 38. Material rack; 39. Motor 3; 40. Cylinder; 41. Electromagnetic suction cup; 42. Adsorption plate; 43. Loading plate; 44. Motor 4; 45. Fixed block; 46. Slot; 47. Transmission gear; 48. Mounting track; 49. Unit segment; 50. Slot. DETAILED DESCRIPTION
[0035] The following is combined with Figure 1-6 This application is described in further detail.
[0036] The present application discloses a concrete crack prevention construction method based on temperature control. Figure 1 and Figure 2 , including the following steps:
[0037] Step 1: Level the area to be poured (in this embodiment, the area to be poured is road 1).
[0038] Step 2: construct multiple medium supply boxes 2 and medium recovery boxes 3 on both sides of the road 1. Adjacent medium supply boxes 2 and medium recovery boxes 3 are connected by a delivery pipe 6. A delivery pump 4 is installed on the delivery pipe 6. The delivery pump 4 is used to transport the medium in the medium recovery box 3 to the medium supply box 2.
[0039] Step 3, install the heat exchange tube 5 in the area to be poured, the medium inlet 7 and the medium outlet 8 of the heat exchange tube 5 are both located outside the area to be poured, the heat exchange tube 5 is wavy, the heat exchange tube 5 includes multiple unit sections 49, each unit section 49 is provided with a medium inlet 7 and a medium outlet 8, the number of medium supply boxes 2 and medium inlets 7 is the same, the number of medium recovery boxes 3 and medium outlets 8 is the same, the medium supply box 2 is connected to the medium inlet 7 through the medium inlet pipe 10, the medium recovery box 3 is connected to the medium outlet 8 through the medium outlet pipe 11, and a water pump 9 is installed on the medium inlet pipe 10, and the water pump 9 is used to transport the medium in the medium supply box 2 to the heat exchange tube 5.
[0040] The unit section 49 includes a starting section 12, a tail section 13 and multiple connecting sections 14. The medium inlet 7 of the heat exchange tube 5 is arranged on the starting section 12, and the medium outlet 8 of the heat exchange tube 5 is arranged on the tail section 13. One end of the starting section 12 and one end of the connecting section 14 are both connected with a connecting pipe 15, and one end of the tail section 13 and one end of the connecting section 14 away from the connecting pipe 15 are both connected with a connecting pipe 2 16. The connecting pipe 2 16 is used to be inserted into the connecting pipe 15 in the vertical direction, and the outer wall of the connecting pipe 2 16 is adapted to the inner wall of the connecting pipe 15.
[0041] When installing the heat exchange tube 5, first install the starting section 12, then install the connecting section 14, select a suitable number of connecting sections 14 as needed, install multiple connecting sections 14 one by one, and finally install the ending section 13. During this installation process, the connecting pipe 2 16 must be inserted into the connecting pipe 1 15 in the vertical direction.
[0042] The unit segment 49 is divided into a starting segment 12, an ending segment 13 and a plurality of connecting segments 14. When transporting and installing the unit segment 49, the unit segment 49 can be split to reduce the length of the unit segment 49, thereby facilitating the transportation and installation of the unit segment 49. When installing the unit segment 49, the unit segment 49 can be installed segment by segment, and during the installation process, the starting segment 12, the ending segment 13 and the plurality of connecting segments 14 are connected into a whole through connecting pipe 1 15 and connecting pipe 2 16, so as to facilitate the introduction of heat exchange medium into the entire unit segment 49.
[0043] Reference Figure 3 and Figure 4In order to make the connected unit segment 49 have better sealing performance, an annular groove 17 is opened on the inner wall of the connecting pipe 15, and an air ring 18 is fixed in the annular groove 17 (the air ring 18 can be fixed by gluing). The air ring 18 is used to be sleeved on the connecting pipe 2 16, and a rubber pad 19 is fixed inside the air ring 18 (the rubber pad 19 can be fixed by gluing). The connecting pipe 15 is provided with an inflation component for inflating the air ring 18, and the air ring 18 is inflated to make the rubber pad 19 press against the connecting pipe 2 16.
[0044] The inflatable assembly includes a piston block 20 and a spring 21. A fixing block 45 is fixedly connected to the outer wall of the connecting pipe 15 (the fixing method of the fixing block 45 can be welding). An air groove 22 is opened on the fixing block 45. The air groove 22 is connected to the inside of the connecting pipe 15. The air groove 22 is connected to the air ring 18 through the air pipe 23. The piston block 20 can be completely inserted into the air groove 22. The length direction of the spring 21 is arranged along the insertion direction of the piston block 20. When the spring 21 is not deformed, the piston block 20 is partially located in the connecting pipe 15, and the piston block 20 faces the connecting pipe 15. The portion of the opening located in the connecting tube 15 is an arc-shaped convex surface; due to the setting of the arc-shaped convex surface, when the connecting tube 16 is inserted into the connecting tube 15, the connecting tube 16 pushes the piston block 20 to completely enter the air groove 22, and the air groove 22 is connected to the air ring 18. When the piston block 20 enters the air groove 22, under the action of air pressure, the gas in the air groove 22 enters the air ring 18, causing the air ring 18 to expand, so that the rubber pad 19 is pressed against the connecting tube 15, thereby realizing the sealing of the connecting tube 15 and the connecting tube 2 16.
[0045] In order to prevent the connecting pipe 2 16 from being separated from the connecting pipe 1 15 before pouring concrete, a limiting rod 26 is inserted into the inner wall of the connecting pipe 1 15, and a limiting groove 25 (the limiting groove 25 is relatively small) is provided on the inner wall of the connecting pipe 15 for the limiting rod 26 to be fully inserted into. The limiting groove 25 is connected to the connecting pipe 15, and the limiting groove 25 is connected to the air groove 22 through the pipeline 28. When the spring 21 is not deformed, the limiting rod 26 is completely located in the limiting groove 25; a card slot 27 is provided on the outer wall of the connecting pipe 2 16 for the limiting rod 26 to be inserted into.
[0046] During the process of inserting the connecting tube 16 into the connecting tube 1 15 , the connecting tube 16 pushes the piston block 20 to completely enter the air groove 22 , and the gas in the air groove 22 first enters the air ring 18 , and the air ring 18 expands, causing the rubber pad 19 to press against the outer wall of the connecting tube 16 , until the groove 27 on the outer wall of the connecting tube 16 moves to the position of the limiting rod 26 . Under the action of air pressure, a very small part of the gas in the air ring 18 will enter the limiting groove 25 (without affecting the sealing effect of the air ring 18 ), pushing the limiting rod 26 in the limiting groove 25 to extend out of the limiting groove 25 and be inserted in the groove 27 , thereby completing the limiting of the connecting tube 16 and preventing the connecting tube 16 from being separated from the connecting tube 1 15 .
[0047] The implementation principle of the temperature-controlled concrete crack prevention construction method of the present application is as follows: before pouring concrete, a heat exchange tube 5 is arranged in the area to be poured. After pouring concrete, if the temperature inside the concrete structure is too high, a cooling medium (such as condensed water) can be injected into the heat exchange tube 5 through the medium supply box 2. The cooling medium flows along the heat exchange tube 5 and flows out from the medium outlet 8 to the medium recovery box 3, thereby taking out the heat in the concrete structure, thereby reducing the temperature of the concrete structure and improving the problem of temperature cracks easily occurring in the concrete.
[0048] The present application also discloses a construction device for a concrete crack prevention construction method based on temperature control, referring to Figure 5 and Figure 6 The construction device includes a mounting mechanism and at least two mounting rails 48 (in this embodiment, the mounting rails 48 are set to three), the mounting mechanism is used to install the unit segment 49 between two adjacent mounting rails 48, the mounting mechanism includes a mobile frame used to be installed on the mounting rail 48 and move along the length direction of the mounting rail 48, the mobile frame is provided with a bearing mechanism for bearing the unit segment 49, the mobile frame is provided with a conveying mechanism, the conveying mechanism is used to install the unit segment 49 on the bearing mechanism between two adjacent mounting rails 48 and to insert the connecting pipe 2 16 into the connecting pipe 1 15 along the vertical direction to connect the connecting pipe 1 15.
[0049] In this embodiment, the movable frame is arranged on the mounting track 48 located in the middle, and the movable frame includes a slider 29, a guide plate 31 and a roller 32. The slider 29 is T-shaped, and a T-slot 30 for the slider 29 to slide along its own path direction is provided on the mounting track 48 located in the middle. The slider 29 is inserted into the T-slot 30, and the guide plate 31 is fixedly connected to the slider 29. The guide plate 31 is vertically arranged, and the roller 32 is rotatably connected to the slider 29. The roller 32 is used to abut against the upper surface of the mounting track 48 located in the middle. A motor 33 is fixedly connected to the slider 29, and the motor 33 drives the roller 32 to rotate through a belt.
[0050] The transport mechanism includes a slide 35 and a material picking rack 38. The slide 35 is slidably connected to the guide plate 31 in the vertical direction. The guide plate 31 is provided with a driving component 1 for driving the slide 35 to slide. The driving component 1 includes a motor 2 36 and a screw 37. The screw 37 is rotatably connected to the guide plate 31, and the rotation axis and length direction of the screw 37 are both arranged in the vertical direction. The screw 37 is threaded through the slide 35, and the motor 2 36 is fixedly connected to the guide plate 31, and the output shaft of the motor 2 36 is coaxially fixedly connected to the screw 37.
[0051] The material picking rack 38 is rotatably connected to the slide 35, and the rotation axis of the material picking rack 38 is arranged in the vertical direction. The slide 35 is fixedly connected with a motor 39 for driving the material picking rack 38 to rotate (the motor 39 can drive the material picking rack 38 to rotate through a gear transmission member and a belt transmission member). The end of the material picking rack 38 away from the slide 35 is fixedly connected with a cylinder 40, and the length direction of the cylinder 40 is arranged in the vertical direction. The telescopic rod of the cylinder 40 is fixedly connected with an electromagnetic suction cup 41, and adsorption plates 42 are welded on the starting section 12, the ending section 13 and multiple connecting sections 14, and the adsorption plates 42 are adsorbed by the electromagnetic suction cup 41.
[0052] The bearing mechanism includes a bearing plate 43, and the thickness direction of the bearing plate 43 is arranged along the vertical direction. The slider 29 is fixedly connected to a mounting seat 34, and a gear ring 24 is sleeved on the outer wall of the mounting seat 34 and rotatably connected. The rotation axis of the gear ring 24 is arranged along the vertical direction. The bearing plate 43 is fixedly connected to the gear ring 24, and the slider 29 is fixedly connected to a motor four 44. The output shaft of the motor four 44 is coaxially fixedly connected to a transmission gear 47, and the transmission gear 47 is meshingly connected to the gear ring 24 (the motor four 44 can also drive the guide plate 31 to rotate through a gear transmission member and a belt transmission member).
[0053] In order to prevent the unit segment 49 from moving in the horizontal direction, a clamping block 50 is welded on the starting segment 12 , the ending segment 13 and the plurality of connecting segments 14 , and a slot 46 for vertically inserting the clamping block 50 is provided on the mounting track 48 .
[0054] The implementation principle of the construction device of the temperature-controlled concrete anti-cracking construction method of the present application is as follows: after the slider 29 is installed on the middle mounting track 48, the bearing plate 43 is adjusted to a suitable position by the motor four 44, and the starting section 12, the ending section 13 and the plurality of connecting sections 14 are placed on the bearing plate 43 in the vertical direction according to the installation sequence, and then the motor two 36 drives the slide 35 to move up, and then the material picking rack 38 is rotated so that the cylinder 40 is located above the uppermost unit section 49, and then the cylinder 40 is turned on to make the electromagnetic suction cup 41 grab the unit section 49, and then the motor three 39 drives the material picking rack 38 to rotate between the two mounting tracks 48, and then the motor two 36 drives the slide 35 to move down until the fixed block 45 on the unit section 49 is inserted into the slot 46, and the roller 32 drives the moving rack to move, so that the unit sections 49 can be installed sequentially along the length direction of the mounting track 48.
[0055] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A concrete anti-cracking construction method based on temperature control, characterized in that: The steps include: Step 1: Install a heat exchange tube (5) in the area to be poured, wherein the medium inlet (7) and the medium outlet (8) of the heat exchange tube (5) are both located outside the area to be poured; the heat exchange tube (5) comprises a plurality of unit sections (49), wherein the unit sections (49) comprise a starting section (12), a finishing section (13) and a plurality of connecting sections (14); the medium inlet (7) of the heat exchange tube (5) is arranged on the starting section (12), and the medium outlet (8) of the heat exchange tube (5) is arranged on the finishing section (13); one end of the starting section (12) and the connecting section (14) are both connected to a connecting tube 1 (15), and the other end of the finishing section (13) and the connecting section (14) are both connected to a connecting tube 2 (16); the connecting tube 1 (15) is used to be connected to the connecting tube 2 (16); the connecting tube 2 (16) is used to be inserted into the connecting tube 1 (15); 5), an air ring (18) is fixed on the inner wall of the connecting tube 1 (15), the air ring (18) is used to be sleeved on the connecting tube 2 (16), and the connecting tube 1 (15) is provided with an inflation component for inflating the air ring (18), and the air ring (18) is inflated to press against the connecting tube 2 (16); the inflation component includes a piston block (20) and a spring (21), an air groove (22) is opened on the inner wall of the connecting tube 1 (15), the piston block (20) is inserted into the air groove (22), and the spring (21) has a tendency to make the piston block (20) partially extend out of the air groove (22) and enter the connecting tube 1 (15), and the connecting tube 2 (16) is inserted into the connecting tube 1 (15) to push the piston block (20) into the air groove (22), and the air groove (22) is connected to the air ring (18); Step 2, pouring concrete in the area to be poured; Step 3: Control the temperature of the concrete by injecting heat exchange medium into the heat exchange tube (5).
2. A concrete crack prevention construction method based on temperature control according to claim 1, characterized in that: A limiting rod (26) is inserted on the inner wall of the connecting tube 1 (15); a limiting groove (25) is provided on the inner wall of the connecting tube 1 (15) for the limiting rod (26) to be fully inserted into; the limiting groove (25) is connected to the air groove (22); when the spring (21) is not deformed, the limiting rod (26) is completely located in the limiting groove (25); and a clamping groove (27) is provided on the outer wall of the connecting tube 2 (16) for the limiting rod (26) to be inserted into.
3. A construction device using the temperature-controlled concrete anti-cracking construction method according to any one of claims 1 to 2, characterized in that: The invention comprises a mounting mechanism and at least two mounting rails (48), wherein the mounting mechanism is used to mount a unit segment (49) between two adjacent mounting rails (48), wherein the mounting mechanism comprises a movable frame used to be mounted on the mounting rail (48) and move along the length direction of the mounting rail (48), wherein the movable frame is provided with a carrying plate (43) used to carry the unit segment (49), and wherein the movable frame is provided with a conveying mechanism, wherein the conveying mechanism is used to mount the unit segment (49) on the carrying plate (43) between two adjacent mounting rails (48) and to insert the second connecting pipe (16) into the first connecting pipe (15) to connect the first connecting pipe (15).
4. The construction device of the temperature-controlled concrete crack prevention construction method according to claim 3 is characterized in that: The transport mechanism comprises a slide (35) which is arranged on a mobile frame and can move in a vertical direction, the mobile frame is provided with a driving component 1 for driving the slide (35) to slide, the slide (35) is rotatably connected with a material picking frame (38), the rotation axis of the material picking frame (38) is arranged in the vertical direction, the slide (35) is provided with a driving component 2 for driving the material picking frame (38) to rotate, the material picking frame (38) is provided with a cylinder (40), the telescopic end of the cylinder (40) is fixedly connected with an electromagnetic suction cup (41), and the cylinder (40) is telescopic so that the electromagnetic suction cup (41) can grab the unit segment (49) on the carrying plate (43).
5. The construction device of the temperature-controlled concrete crack prevention construction method according to claim 3 is characterized in that: The bearing plate (43) is rotatably connected to the mobile frame, the rotation axis of the bearing plate (43) is arranged along the vertical direction, and the mobile frame is provided with a driving component three for driving the bearing plate (43) to rotate.
6. The construction device of the temperature-controlled concrete crack prevention construction method according to claim 3 is characterized in that: The starting section (12), the ending section (13) and the plurality of connecting sections (14) are all fixedly connected with a card block (50), and the mounting track (48) is provided with a slot (46) for vertically inserting the card block (50).
Citation Information
Patent Citations
Control bulky concrete crack's water cooling circulation heat sink
CN208718384U