A pile structure and a pile supplementing method for supplementing piles at a few-pile position of an engineering pile
By erecting transverse ground beams and reinforcing bars between the offset engineering pile position and the adjacent conventional pile position, the support force is distributed, which solves the problem of insufficient support caused by the offset of the engineering pile and ensures that the supplementary pile has sufficient support strength. This method is suitable for building construction in silty environments.
Patent Information
- Application Number
- CN202310022660.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-01-08
- Publication Date
- 2025-11-21
- Estimated Expiration
- 2043-01-08
AI Technical Summary
During the construction of engineering piles, the silty geological environment and construction conditions are highly variable, which can cause the pile positions to shift, making it impossible to find the corresponding stress points of the pile positions. This affects the support effect of the building and the construction progress, and it is difficult to effectively supplement the piles at the locations where there are few piles to ensure sufficient support capacity.
By erecting a transverse ground beam between the offset engineering pile position and the adjacent conventional engineering pile position, and setting up supplementary piles on top of it, the supporting force is distributed to multiple engineering pile positions using the transverse ground beam and through reinforcement, forming a stable foundation and enhancing the supporting strength of the supplementary piles.
It enables the distribution of support force to ensure sufficient support capacity for the supplementary piles in the event of pile displacement, thereby reducing construction difficulty and saving construction time. It is suitable for load-bearing foundations of buildings in silty environments.
Smart Images

Figure CN116043933B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of building construction, in particular to a structure and method for supplementing a pile at a position with few piles. BACKGROUND
[0002] An engineering pile is a pile used in an engineering entity, which is a permanent pile constructed for building foundation treatment, and its construction quality and layout position directly affect the service life of a building. During building construction, the design and construction of an engineering pile need to be completed in a foundation pit, and after the construction of the engineering pile is completed, a bottom plate is laid and an upper building is constructed, and the position of the engineering pile cannot be moved or adjusted after the construction of the engineering pile is completed.
[0003] However, during the construction of the engineering pile, the actual construction position of the pile position occasionally deviates from the design position due to the influence of silt geological environment interference and variable site construction conditions, which results in the inability to find a corresponding pile position stress point during the construction of the upper building, so that there is no engineering pile to support at a position that needs to bear weight, which seriously affects the progress of the later construction and also affects the support effect of the building.
[0004] Therefore, how to timely and effectively supplement a pile when the position of the engineering pile deviates is a major test. After the construction of the foundation pit is completed, it is difficult to construct a new engineering pile, and it is also difficult to ensure that the supplement of the pile at the position with few piles has sufficient supporting capacity.
[0005] The above-mentioned defects are worth solving. SUMMARY
[0006] In order to solve the defect that there is no engineering pile to bear weight when the existing engineering pile deviates, and to enable the supplement of the pile at the position with few piles to have sufficient supporting strength, the present application provides a structure and method for supplementing a pile at a position with few piles.
[0007] The technical scheme of the present application is as follows:
[0008] A structure for supplementing a pile at a position with few piles, characterized in that it comprises an offset engineering pile position and a first conventional engineering pile position adjacent to the offset engineering pile position, a transverse ground beam is arranged between the offset engineering pile and the first conventional engineering pile position, and the transverse ground beam spans the position with few piles,
[0009] A rear supplement pile is arranged on the upper side of the transverse ground beam, and the rear supplement pile is located directly above the position with few piles.
[0010] According to the application of the above scheme, characterized in that, the bottom plate is laid between the offset engineering pile position and the first regular engineering pile position, and in the bottom plate above the offset engineering pile position and the first regular engineering pile position.
[0011] According to the application of the above scheme, characterized in that, the through bar is arranged in the transverse ground beam, and two ends of the through bar are connected with the offset engineering pile body of the offset engineering pile position and the regular engineering pile body of the first regular engineering pile position respectively.
[0012] According to the application of the above scheme, characterized in that, one end of the transverse ground beam extends to the second regular engineering pile position adjacent to the other side of the offset engineering pile, and the other end of the transverse ground beam extends to the third regular engineering pile position on the other side of the first regular engineering pile after passing through the first regular engineering pile.
[0013] According to the application of the above scheme, characterized in that, the offset engineering pile position comprises an offset engineering pile body, the offset engineering pile body is arranged in the offset engineering pile cap, and the post-pile is fixedly connected with the steel bar assembly in the offset engineering pile cap.
[0014] Further, the steel bar assembly comprises side longitudinal bars, side transverse bars, top transverse bars, bottom transverse bars and bottom longitudinal bars, the side longitudinal bars are arranged on the left and right sides in the offset engineering pile cap, the side transverse bars are arranged on the front and back sides in the offset engineering pile cap and are fixedly connected with the side longitudinal bars on the front and back sides, the top transverse bars are arranged on the top of the offset engineering pile cap and are fixedly connected with the through bar in the transverse ground beam, and the bottom transverse bars and the bottom longitudinal bars are arranged on the bottom of the offset engineering pile cap, and the bottom longitudinal bars are fixedly connected with the bottom transverse bars and the side longitudinal bars on the left and right sides.
[0015] On the other hand, a method for filling piles in a pile-scarce position, characterized in that, the method comprises the following steps:
[0016] S1, obtaining a pile-scarce position, and determining the positions of an offset engineering pile position and a first regular engineering pile position, so that the offset engineering pile position and the first regular engineering pile position are arranged on the left and right sides of a post-pile to be filled;
[0017] S2, erecting a transverse ground beam between the offset engineering pile position and the first regular engineering pile position, so that the transverse ground beam spans the pile-scarce position;
[0018] S3, erecting a post-pile on the transverse ground beam, so that the post-pile is arranged directly above the pile-scarce position.
[0019] The application according to the above scheme is characterized in that, in step S2, a through bar is erected between the offset engineering pile position and the first regular engineering pile position, and then concrete is poured on the through bar to form the transverse beam.
[0020] Further, the application further comprises a process of erecting an auxiliary bar after the through bar is erected, the auxiliary bar is erected so as to cross the through bar, and two ends of the auxiliary bar are connected to fourth regular engineering piles on the sides of the offset engineering pile position.
[0021] The application according to the above scheme is characterized in that, in step S2, two ends of the transverse beam pass through the offset engineering pile position and the first regular engineering pile position respectively, so that one end of the transverse beam extends to a second regular engineering pile position adjacent to the other side of the offset engineering pile position, and the other end of the transverse beam extends to a third regular engineering pile position on the other side of the first regular engineering pile position after passing through the first regular engineering pile position.
[0022] The application has the beneficial effect that, by using the offset engineering pile position and the adjacent regular engineering pile position, the support force of the newly supplemented engineering pile is shared in the engineering pile position, so that the supplemented pile can have a more stable foundation, even if it is applied to a silt environment, the supplemented pile can also provide a load-bearing foundation for the upper building, and the defect of the few piles caused by the offset of the existing engineering pile construction is solved.
[0023] The application realizes force dispersion in a sharing manner, ensures the structural strength of the supplemented pile, and the supplemented pile is constructed on the upper side of the bottom plate, so that the process is simpler, the construction difficulty is reduced, and the construction period is saved. BRIEF DESCRIPTION OF DRAWINGS
[0024] Figure 1 It is a schematic view of the supplemented pile position in the application;
[0025] Figure 2 It is a partial enlarged view in Figure 1
[0026] Figure 3 It is a side view of the binding of the supplemented pile position in the application;
[0027] Figure 4 It is a schematic view of the binding of the bottom transverse bar in the application;
[0028] Figure 5 It is a schematic view of the binding of the side longitudinal bar and the bottom longitudinal bar in the application.
[0029] In the drawings, various reference numerals are:
[0030] 10a. First conventional engineering pile location; 10b. Second conventional engineering pile location; 10c. Third conventional engineering pile location; 10d. Fourth conventional engineering pile location; 11. Main body of conventional engineering pile; 12. Pile cap of conventional engineering pile; 13. Support body of conventional engineering pile;
[0031] 20. Offset of the engineering pile position; 21. Offset of the main body of the engineering pile; 22. Offset of the pile cap of the engineering pile;
[0032] 30. Post-construction pile main body; 31. Post-construction reinforcement;
[0033] 41. Lateral longitudinal reinforcement; 42. Continuous reinforcement; 43. Lateral transverse reinforcement; 44. Top transverse reinforcement; 45. Bottom transverse reinforcement; 46. Bottom longitudinal reinforcement;
[0034] 50. Horizontal ground beam;
[0035] 60. Base plate. Detailed Implementation
[0036] The present invention will now be further described with reference to the accompanying drawings and embodiments:
[0037] like Figures 1 to 5 As shown, in order to solve the problem of missing piles caused by the offset of existing engineering piles, and to enable the supplementary piles to have sufficient support strength and reduce the construction difficulty of the supplementary piles, the present invention provides a pile supplementary structure for the missing pile location of engineering piles and a construction method for the structure.
[0038] like Figure 1 As shown, this invention utilizes the offset engineering pile position 20 with a deviation in construction location and the adjacent conventional engineering pile to achieve the distribution of the supporting force of the supplementary engineering pile, ensuring the supporting foundation and strength of the supplementary engineering pile. Specifically, the supplementary pile structure at the location of the missing engineering pile includes the offset engineering pile position 20 and the first conventional engineering pile position 10a adjacent to the offset engineering pile position 20. A transverse ground beam 50 is erected between the offset engineering pile and the first conventional engineering pile position 10a, and the transverse ground beam 50 spans the location of the missing engineering pile. At the same time, the supplementary pile is erected on the upper side of the transverse ground beam 50, so that the supplementary pile is located directly above the location of the missing engineering pile.
[0039] The supplementary pile includes a supplementary pile body 30, with supplementary reinforcing bars 31 on both the left and right sides of the supplementary pile body 30. The distribution direction of the supplementary reinforcing bars 31 is consistent with the extension direction of the transverse ground beam 50. In addition, the supplementary reinforcing bars on the left and right sides are tied together by reinforcing bars with a zigzag bend. For example, 6ΦZ 16@50 (8) reinforcing bars are added to the left and right sides of the supplementary pile body 30 as supplementary reinforcing bars, and the supplementary reinforcing bars on both sides are connected by 8ΦZ25. In this embodiment, supplementary reinforcing bars are provided on the left and right sides of the supplementary pile body 30, and the left and right sides of the supplementary pile body 30 are respectively the offset engineering pile position 20 and the first conventional engineering pile position 10a obtained from the actual construction on site.
[0040] To increase the structural strength and support capacity of the transverse ground beam 50, a through-beam 42 is provided inside the transverse ground beam 50 of this invention. The two ends of the through-beam 42 are respectively connected to the offset engineering pile body 21 of the offset engineering pile position 20 and the conventional engineering pile body 11 of the first conventional engineering pile position 10a. Concrete is poured after the through-beam 42 is tied to the offset engineering pile position 20 and the first conventional engineering pile position 10a, which increases the structural strength and support capacity of the transverse ground beam 50.
[0041] Please see Figure 1 , Figure 2 The offset piles here are shifted to the left compared to the original designed pile positions, resulting in no piles supporting the superstructure at the designed pile positions. Therefore, the force distribution of the supplementary piles is achieved using the offset pile position 20 shifted to the left and the first conventional pile position 10a located to the right of the offset pile position 20. When this building structure is applied in a silty geological environment, the support effect of the supplementary piles will not be affected by the silty geological conditions. The first conventional pile here refers to the pile with an appropriate construction location, and the same applies to other subsequent conventional piles.
[0042] A base plate 60 is laid between the offset engineering pile position 20 and the first conventional engineering pile position 10a, and within the pile cap of the offset engineering pile position. The ground beam is located on the upper side of the base plate 60 between the offset engineering pile position 20 and the first conventional engineering pile position 10a. In this invention, the post-construction piles are installed on the base plate 60, making the construction process more convenient and unaffected by the underlying silty environment. In this embodiment, the thickness of the base plate 60 is 100mm.
[0043] exist Figure 1In the shown embodiment, the transverse beam 50 is not only supported on the offset pile site 20 and the first regular pile site 10a, but also extends to more regular pile sites to further distribute the support force of the post-pile. Specifically, one end of the transverse beam 50 extends to the second regular pile site 10b adjacent to the other side of the offset pile site 20, and the other end of the transverse beam 50 extends to the third regular pile site 10c beyond the first regular pile site 10a. Correspondingly, the through bar 42 also extends to the second regular pile site 10b and the third regular pile site 10c.
[0044] In the above embodiment, the support force of the post-pile is linearly distributed, i.e. the support force of the post-pile is distributed to the offset pile site 20, the first regular pile site 10a, and even the second regular pile site 10b and the third regular pile site 10c. In other embodiments, the support force of the post-pile can also be distributed in a plane. Specifically, the transverse beam 50 also intersects with one or more auxiliary beams (not shown in the figure, the same below), and the two ends of the auxiliary beam are connected to the fourth regular pile site 10d adjacent to the offset pile site 20. By intersecting the transverse beam 50 with the auxiliary beam, a support plane is formed, which can further distribute the support force of the post-pile to other regular piles.
[0045] In a specific implementation process, the auxiliary beam and the transverse beam 50 can intersect to form a cross, a T or a rice character. The auxiliary beam and the transverse beam 50 can also intersect to form a T, a factory character, etc. (at this time, one end of the auxiliary beam is connected with the transverse beam 50, and the other end is connected with the fourth regular pile site 10d adjacent to the offset pile site 20), which can distribute the support force of the post-pile in a plane using the surrounding regular piles.
[0046] Please refer to Figures 2 to 5 , the offset pile site 20 includes an offset pile body 21, which is located inside the offset pile pile cap 22, and the post-pile is fixed with the reinforcement assembly in the offset pile pile cap 22. In this embodiment, the surface of the offset pile pile cap 22 is calibrated with concrete to form an offset pile support body. In a specific embodiment, the offset pile support body is additionally provided with X-direction bottom reinforcement (such as Φ14@150 steel bars) and Y-direction bottom reinforcement (such as Φ12@150 steel bars).
[0047] In the implementation process, the steel bar assembly includes side longitudinal bars 41, side transverse bars 43, top transverse bars 44, bottom transverse bars 45, and bottom longitudinal bars 46. The side longitudinal bars 41 are distributed on the left and right sides inside the offset engineering pile cap 22. The side transverse bars 43 are distributed on the front and rear sides inside the offset engineering pile cap 22 and are tied and connected with the side longitudinal bars 41 on the front and rear side edges. The top transverse bars 44 are distributed on the top of the offset engineering pile cap 22 and are tied and connected with the through bars 42 inside the transverse girder 50. The bottom transverse bars 45 and the bottom longitudinal bars 46 are both distributed on the bottom of the offset engineering pile cap 22, and the bottom longitudinal bars 46 are tied and connected with the bottom transverse bars 45 and the side longitudinal bars 41 on the left and right side edges.
[0048] In the embodiment, the top end of the offset engineering pile body 21 is higher than the inner bottom wall of the offset engineering pile cap 22 by 100 mm. The force transmission between the support capacity of the offset engineering pile body 21 and the steel bar assembly inside the offset engineering pile cap 22 can make the offset engineering pile body 21 have a corresponding support capacity.
[0049] In the above structure, each conventional engineering pile position includes a conventional engineering pile body 11 located inside a conventional engineering pile cap 12, and the inside and surface of the conventional engineering pile cap 12 are poured with concrete to form a conventional engineering pile support body 13. The conventional engineering pile support body 13 here includes concrete forming part of the bottom plate 60. In one specific embodiment, the conventional engineering pile support body 13 is additionally provided with X-direction bottom bars (for example, Φ14@150 steel bars) and Y-direction bottom bars (for example, Φ12@150 steel bars).
[0050] The application also provides an engineering pile few-pile position pile supplementing method for realizing the above engineering pile few-pile position pile supplementing structure. The pile supplementing method specifically includes the following steps:
[0051] S1, first, an engineering pile few-pile position is obtained, and the reason for the few-pile position is determined according to the engineering pile few-pile position, and then an offset engineering pile position 20 is determined. Then, the position of a first conventional engineering pile position 10a is determined according to the position of the offset engineering pile position 20 and the position of the engineering pile few-pile position, so that the offset engineering pile position 20 and the first conventional engineering pile position 10a are distributed on the left and right sides of the to-be-supplemented pile.
[0052] In the specific construction design process, whether to perform horizontal expansion sharing or plane sharing of the support force of the to-be-supplemented pile is determined according to the engineering pile few-pile position, the design requirements of the upper building, and the design of the surrounding conventional engineering piles. If horizontal expansion sharing is required, a conventional engineering pile position on the left side of the offset engineering pile position is further selected as a second conventional engineering pile position 10b, and a conventional engineering pile on the right side of the first conventional engineering pile position 10a is further selected as a third conventional engineering pile position 10c. If plane sharing is required, a fourth conventional engineering pile position 10d (a conventional engineering pile position on the front and rear sides of the transverse girder 50) is further determined.
[0053] S2, erecting a transverse ground beam 50 between the offset engineering pile position 20 and the first conventional engineering pile position 10a, so that the transverse ground beam 50 spans the engineering pile less pile position.
[0054] In the specific construction process, the through bar 42 is first erected between the offset engineering pile position 20 and the first conventional engineering pile position 10a, and then the concrete is poured on the through bar 42 to form the transverse ground beam 50. Of course, when the through bar 42 is erected here, the through bar 42 needs to be bound to the reinforcement assembly in the offset engineering pile position 20 to realize the support transmission effect of the offset engineering pile position 20.
[0055] If the extension construction involving the second conventional engineering pile position 10b and the third conventional engineering pile position 10c is involved, the two ends of the transverse ground beam 50 need to pass through the offset engineering pile position 20 and the first conventional engineering pile position 10a respectively, so that one end of the transverse ground beam 50 extends to the second conventional engineering pile position 10b adjacent to the other side of the offset engineering pile, and the other end of the transverse ground beam 50 extends to the third conventional engineering pile position 10c on the other side of the first conventional engineering pile position 10a after passing through the first conventional engineering pile position 10a.
[0056] In addition, if the planar distribution needs to be carried out by using the fourth conventional engineering pile position 10d, after the transverse through bar 42 is erected, the erection process of the auxiliary bar is also included: specifically, the auxiliary bar is erected so that the auxiliary bar intersects with the through bar 42, and the two ends of the auxiliary bar are connected to the fourth conventional engineering pile on the side of the offset engineering pile position 20.
[0057] S3, erecting a post-pile on the transverse ground beam 50, so that the post-pile is located directly above the engineering pile less pile position.
[0058] The specific construction process of the post-pile is similar to that of the engineering pile structure on the side of the conventional engineering pile position, which will not be described here.
[0059] The present application utilizes the first conventional engineering pile position 10a (and possibly the second conventional engineering pile position 10b, the third conventional engineering pile position 10c, and the fourth conventional engineering pile position 10d) and the construction offset offset engineering pile position 20 to horizontally distribute (and possibly planarly distribute) the support force of the post-pile, which not only solves the problem of engineering pile less pile, but also reduces the construction difficulty of the post-pile and saves the construction period.
[0060] It should be understood that those skilled in the art can make improvements or changes according to the above description, and all these improvements and changes shall belong to the protection scope of the appended claims of the present application.
[0061] The patent of the application is exemplarily described above in combination with the drawings, and it is obvious that the implementation of the patent of the application is not limited by the above-mentioned mode, as long as various improvements are made by adopting the method concept and technical scheme of the patent of the application, or the concept and technical scheme of the patent of the application is directly applied to other occasions without improvement, which are all within the protection scope of the patent of the application.
Claims
1. A structure for supplementing piles in locations with insufficient piles in engineering projects, characterized in that, It includes an offset engineering pile position and a first conventional engineering pile position adjacent to the offset engineering pile position. A transverse ground beam is erected between the offset engineering pile position and the first conventional engineering pile position. The transverse ground beam spans the position of the fewest engineering piles. A through bar is provided in the transverse ground beam. The two ends of the through bar are respectively connected to the offset engineering pile body of the offset engineering pile position and the conventional engineering pile body of the first conventional engineering pile position. A base plate is laid between the offset engineering pile position and the first conventional engineering pile position, and inside the pile cap of the offset engineering pile position. The transverse ground beam is located on the upper side of the base plate between the offset engineering pile position and the first conventional engineering pile position. A supplementary pile is erected on the upper side of the transverse ground beam, and the supplementary pile is located directly above the position where the engineering pile is missing. The offset engineering pile position includes the offset engineering pile body, which is located inside the offset engineering pile cap. The supplementary pile is tied and fixed to the steel reinforcement components inside the offset engineering pile cap.
2. The pile replacement structure for locations with insufficient piles in engineering piles according to claim 1, characterized in that, One end of the transverse ground beam extends to the second conventional engineering pile position adjacent to the other side of the offset engineering pile, and the other end of the transverse ground beam extends to the third conventional engineering pile position on the other side of the first conventional engineering pile position after passing the first conventional engineering pile position.
3. The pile replacement structure for locations with insufficient piles according to claim 1, characterized in that, The steel reinforcement assembly includes side longitudinal bars, side transverse bars, top transverse bars, bottom transverse bars, and bottom longitudinal bars. The side longitudinal bars are distributed on the left and right sides of the offset pile cap. The side transverse bars are distributed on the front and rear sides of the offset pile cap and are tied to the side longitudinal bars at the front and rear edges. The top transverse bars are distributed on the top of the offset pile cap and are tied to the through bars in the transverse ground beam. The bottom transverse bars and the bottom longitudinal bars are both distributed at the bottom of the offset pile cap, and the bottom longitudinal bars are tied to the bottom transverse bars and the side longitudinal bars located at the left and right edges.
4. A method for supplementing piles at locations with insufficient engineering piles, characterized in that, To implement the pile supplementation structure for locations with insufficient piles as described in any one of claims 1-3, the following steps are included: S1. Obtain the location of the missing engineering piles and determine the position of the offset engineering pile position and the first regular engineering pile position, so that the offset engineering pile position and the first regular engineering pile position are distributed on the left and right sides of the subsequent piles to be supplemented. S2. A transverse ground beam is erected between the offset engineering pile position and the first conventional engineering pile position, so that the transverse ground beam spans the position of the few engineering piles. S3. Install supplementary piles on the transverse ground beam, so that the supplementary piles are located directly above the position of the missing pile in the engineering pile.
5. The method for supplementing piles at locations with insufficient piles according to claim 4, characterized in that, In step S2, a through-beam is first erected between the offset engineering pile position and the first conventional engineering pile position, and then concrete is poured on the through-beam to form the transverse ground beam.
6. The method for supplementing piles at locations with insufficient piles according to claim 5, characterized in that, After the main reinforcement is erected, the process of erecting auxiliary reinforcement is also included. The auxiliary reinforcement is erected so that it intersects with the main reinforcement, and the two ends of the auxiliary reinforcement are respectively connected to the fourth conventional engineering pile next to the offset engineering pile position.
7. The method for supplementing piles at locations with insufficient piles according to claim 4, characterized in that, In step S2, both ends of the transverse ground beam cross the offset engineering pile position and the first conventional engineering pile position respectively, so that one end of the transverse ground beam extends to the second conventional engineering pile position adjacent to the other side of the offset engineering pile, and the other end of the transverse ground beam crosses the first conventional engineering pile position and extends to the third conventional engineering pile position on the other side of the first conventional engineering pile position.
Citation Information
Patent Citations
High pile beam plate type dock remedy structure with malposed sunk piles
CN202148513U
Pile repairing structure for less pile position of engineering pile
CN219508630U
Basic structure of independent pile without basic beam
JP2006265999A