Modular embankment construction method for retaining spoil during tower foundation construction of power transmission and transformation projects
Through the modular fort construction method, combined with terrain parameters and earthwork quantity, dry-stacked chain concrete blocks and permeable concrete layers were used to treat the abandoned soil, which solved the problems of abandoned soil disposal and fort stability in power grid tower foundation construction, and realized the earthwork and stone flow Balance and cost reduction effects.
Patent Information
- Application Number
- CN202211563827.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-07
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2042-12-07
AI Technical Summary
During the power grid construction, the tower foundation construction in the hilly area has large amount of soil abandoned due to excavation and backfilling. The existing temporary barrier and mortar stone fort barrier methods have unfavorable vegetation restoration, unstable barriers, and large project volume. For problems with difficult transportation and poor landscape effects, we need to seek technologies to reasonably dispose of abandoned soil, improve the reliability of the fortress and reduce costs.
The modular fort construction method is adopted. By obtaining the topographic parameters and earthwork around the tower foundation, the construction parameters and masonry methods of the fortress are determined, and the dry-stack chain concrete blocks are used to build the fortress, and a permeable concrete layer is formed as needed. Accommodate discarded soil and combine plant greening to improve stability and landscape effect.
The earth and stone balance within the base of the tower is achieved, reducing the difficulty and construction cost of transporting materials of the burgundy, improving the reliability and landscape effect of the burgundy, and reducing the construction complexity and environmental impact.
Smart Images

Figure CN116180802B_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of earthwork construction, and specifically relates to a modular embankment construction method for retaining abandoned soil during tower foundation construction of a power transmission and transformation project. Background Art
[0002] During the construction of the power grid, the excavation and backfilling disturbance area in the hilly area is large, and the amount of excavation and backfilling of the high and low leg tower foundations in the hilly area and the tower leg foundations with large slopes is large, so certain blocking measures are needed. At present, there are two main blocking methods, temporary blocking with vegetation bags and mortar-laid stone embankments, that is, building walls to block the abandoned soil. When using temporary blocking with vegetation bags, vegetation recovery may be unfavorable, the vegetation bags will gradually weather, the blocking will gradually disintegrate, and the blocking effect will be lost; when using mortar-laid stone embankments, the project volume is large, the stone specifications are large, and it is difficult to transport in the hilly area, and the landscape effect of large-area mortar-laid stone walls is poor.
[0003] Therefore, the technical problem of how to reasonably dispose of the waste soil generated during construction while improving the reliability of the embankment and reducing the construction cost needs to be solved urgently. Summary of the invention
[0004] In order to solve the technical problem of how to reasonably dispose of the waste soil generated during construction, improve the reliability of the embankment and reduce the construction cost as described in the above background technology, this application proposes a modular embankment construction method for blocking waste soil during tower foundation construction of power transmission and transformation projects.
[0005] According to a first aspect of the present application, a modular embankment construction method for blocking waste soil during tower foundation construction of a power transmission and transformation project is proposed, comprising: obtaining terrain parameters and the amount of waste soil within a preset range centered on the tower foundation; determining the construction parameters and masonry method of the embankment based on the terrain parameters and the amount of earthwork, the construction parameters including the construction height and the inclination angle of the embankment facade, and the masonry method including cross-laying of blocks in different masonry layers; based on the construction parameters, the embankment is constructed by masonry of dry-laid interlocking concrete blocks to form a waste soil accommodating area for accommodating waste soil; when the construction height is less than the preset height and / or the inclination angle of the embankment facade is less than the preset inclination angle, the waste soil is recovered in layers in the waste soil accommodating area; when the construction height is greater than the preset height and / or the inclination angle of the embankment facade is greater than the preset inclination angle, a permeable concrete layer is first formed in the waste soil accommodating area, and then the waste soil is recovered.
[0006] Optionally, the permeable concrete layer has a thickness of 30-70 cm.
[0007] Optionally, the method further comprises: laying a drainage pipe at the bottom of the permeable concrete layer.
[0008] Optionally, the method further comprises: laying a geotextile on top of the permeable concrete layer as a filter layer to prevent abandoned soil from clogging the permeable layer.
[0009] Optionally, the building blocks include main building blocks and secondary building blocks, and the masonry method also includes: each masonry layer constituting the embankment is composed of main building blocks and secondary building blocks cross-laid, and the main building blocks and secondary building blocks in adjacent masonry layers correspond one-to-one to the main building blocks and secondary building blocks of adjacent masonry layers.
[0010] Optionally, the masonry method includes cross-laying of blocks in different masonry layers, including: filling plants between the main blocks and the secondary blocks.
[0011] Optionally, a crushed stone cushion layer is provided below the embankment and is built in close contact with the embankment.
[0012] Optionally, the method further includes: when building the embankment, building a preset number of masonry layers, and recovering the abandoned soil, and repeating the process in sequence until the building height of the embankment reaches the required construction height.
[0013] Optionally, the method further includes: in the tower foundation construction area where the abandoned soil is recovered, the exposed height of the tower foundation is greater than or equal to 0.2 m.
[0014] Optionally, it also includes: the vertical inclination angle of the embankment is less than or equal to 18% slope, and the building height is less than or equal to 1.5m.
[0015] The invention proposes a modular embankment construction method for retaining excess soil during tower foundation construction of a power transmission and transformation project, which has the following beneficial effects:
[0016] This application determines the building parameters and methods of the embankment through terrain parameters and earthwork volume, and determines the corresponding embankment building height, inclination angle and other parameters based on the construction site. The construction of the embankment can be determined in combination with the construction site, while achieving earthwork balance within the range of a single tower base, reducing the transportation difficulty and construction cost of the embankment building materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic flow chart of a modular embankment construction method for blocking waste soil during tower foundation construction of a power transmission and transformation project in one embodiment of the present application;
[0018] Figure 2 This is a schematic diagram of an interlocking building block with a stopper in one embodiment of the present application;
[0019] Figure 3 This is a schematic diagram of an interlocking building block without a stopper in an embodiment of the present application;
[0020] Figure 4 This is a schematic diagram of interlocking blocks constructed with the same blocks on the facade of the embankment in one embodiment of the present application;
[0021] Figure 5 This is a schematic diagram of interlocking blocks in which different blocks are used to cross-build the facade of the embankment in one embodiment of the present application;
[0022] Figure 6 This is a schematic diagram of a second construction structure of the fortress in one embodiment of the present application;
[0023] Figure 7 This is a schematic diagram of a first construction structure of a fortress in one embodiment of the present application;
[0024] Figure 8 This is a schematic diagram of a fortress in an embodiment of the present application. DETAILED DESCRIPTION
[0025] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and preferred embodiments. However, it should be noted that many details listed in the specification are only for the purpose of enabling the reader to have a thorough understanding of one or more aspects of the present invention, and these aspects of the present invention can be implemented even without these specific details.
[0027] As described in the background technology, during the construction of power grids, the excavation and backfilling disturbance area in hilly areas is large, and the amount of excavation and backfilling of high and low leg tower foundations and tower leg foundations with larger slopes in hilly areas is large, so certain blocking measures are needed. At present, there are two main blocking methods: temporary blocking with vegetation bags and mortar-laid stone embankments, that is, building walls to block the abandoned soil. When using vegetation bags for temporary blocking, vegetation recovery may be unfavorable, the vegetation bags will gradually weather, the blocking will gradually disintegrate, and the blocking effect will be lost; when using mortar-laid stone embankments for blocking, the project volume is large, the stone specifications are large, and transportation in hilly areas is more difficult, and the landscape effect of large-area mortar-laid stone walls is poor.
[0028] Therefore, according to one aspect of the present application, a modular embankment construction method for blocking spoil during tower foundation construction of a power transmission and transformation project is provided, see Figure 1 As shown, including:
[0029] S10: Obtaining terrain parameters and the volume of abandoned soil within a preset range centered on the tower base.
[0030] In the initial stage of the project, after the construction workers obtain the installation site of the tower, they need to survey the terrain within a certain range centered on the tower to obtain terrain parameters, such as the slope of the mountain and the terrain structure parameters that can form a ridge. At the same time, they need to fully consider the differences between mechanized construction and conventional construction methods, and comprehensively evaluate the line selection, mountain slope and other parameters of temporary roads passed by transportation tools and construction tools, so as to avoid terrain that is not conducive to construction as much as possible.
[0031] S20: Determine the building parameters and the laying method of the embankment based on the terrain parameters and the earthwork volume, wherein the building parameters include the building height and the inclination angle of the embankment facade, and the laying method includes cross-laying of blocks in different laying layers.
[0032] S30: Based on the construction parameters, the embankment is constructed by using dry-laid interlocking concrete blocks to form a waste soil accommodating area for accommodating waste soil.
[0033] S40: When the building height is less than a preset height and / or the inclination angle of the embankment facade is less than a preset inclination angle, recovering the waste soil in layers in the waste soil accommodating area.
[0034] S50: When the building height is greater than a preset height and / or the slope angle of the embankment facade is greater than a preset slope angle, a permeable concrete layer is first formed in the waste soil accommodating area, and then the waste soil is covered.
[0035] The construction parameters of the embankment may include the height of the embankment, the inclination angle, the distance from the tower base and other parameters. The imitation stone barrier material is light in weight, at 5kg-10kg. Compared with the larger amount of work and large-sized stones of the mortar-laid stone embankment, it is less difficult to transport and has a higher construction efficiency, while also having a better landscape effect.
[0036] The abandoned soil will be returned to the abandoned soil storage area to achieve the balance of earth and stone within the scope of a single tower base, while improving the reliability of the embankment and reducing the construction cost.
[0037] In this embodiment, the building parameters and construction method of the embankment are determined by terrain parameters and earthwork volume. Based on the construction site, the corresponding embankment construction height, inclination angle and other parameters are determined. The construction of the embankment can be determined in combination with the construction site. While achieving earthwork balance within the range of a single tower base, the transportation difficulty and construction cost of the embankment materials are reduced.
[0038] The building materials of the embankment can be imitation stone barrier materials. Imitation stone barrier materials are relatively light and convenient for modular construction. At the same time, their appearance has external features similar to natural rocks or local characteristic landscape stones, which is conducive to improving the landscape effect of engineering measures. In addition, as an engineering measure with simple construction, low material and construction costs, good durability, and better barrier effect than temporary barriers of vegetation bags, dry masonry technology is adopted and the blocks can be dismantled and reused.
[0039] As an exemplary embodiment, the determining of the construction parameters of the embankment based on the terrain structure parameters and the earthwork volume includes: determining the slope of the tower base setting position based on the terrain structure parameters; determining the construction parameters based on the slope and the earthwork volume. The construction parameters include: the construction position, construction height, embankment inclination angle and construction structure of the embankment.
[0040] In the present embodiment, in the construction of some tower bases, the location of the tower base may be set on a mountain with a slope, resulting in the high and low legs of the tower base, which makes the tower base unstable. In the process of building the tower base, the greater the slope of the location where the tower base is built, the more waste soil will be excavated. Therefore, when determining how to build the embankment, it is necessary to determine the slope of the mountain where the tower base is built, and the amount of earthwork generated by the excavation. The construction parameters of the embankment are determined according to the amount of earthwork. The higher the construction height of the embankment and the longer the construction length, the more waste soil can be accommodated. However, if the construction height of the embankment is too high, there may be a risk of the embankment being unstable and leading to collapse. Therefore, the construction height of the embankment should not be too high. In actual construction, the construction height of the embankment can be 1-3m.
[0041] For example, see Figure 2-5 As shown, the embankment can be divided into two types: main blocks and secondary blocks. The main blocks are quadrilaterals, with the dimensions of 468mm, 362mm and 250mm in length, width and height, 4.5cm in thickness and 8-10kg in weight; the secondary blocks are octagonal, with the dimensions of 362mm, 362mm and 250mm in length, width and height, 4.5cm in thickness and 5-7kg in weight. The main blocks and secondary blocks are small in size and easy to carry. The facade can be designed to have interlocking blocks with stoppers and interlocking blocks without stoppers, wherein the height of the stoppers is 1-2 cm, and 1.5 cm is taken as an example in this application. When the built sill needs a certain tilt angle, interlocking blocks with stoppers can be selected, and the built sill is more stable. When the built sill is at a vertical angle to the horizontal line, interlocking blocks without stoppers can be selected, and interlocking blocks without stoppers and interlocking blocks with stoppers can also be selected according to construction requirements. Interlocking blocks with different blocks cross-laid and interlocking blocks with two configurations can also be designed. When the facade is cross-laid with different blocks, a certain angle gap can be generated to facilitate drainage, and planting soil can be filled to plant herbaceous plants to vertically green the wall. Plant seeds can be filled in the gap, which has the advantages of greening, high overall strength, low cost and easy construction. Among them, the building blocks can be hollow blocks or solid blocks. Compared with solid blocks, hollow blocks are lighter and easier to transport. In addition, crushed stone, abandoned soil, etc. can be added to the hollow cavity of the hollow blocks to increase the stability of the blocks.
[0042] As an exemplary embodiment, the building structure includes a first building structure and a second building structure; when the building structure is the first building structure, the embankment includes an embankment body; when the building structure is the second building structure, the embankment includes an embankment body and a permeable structure.
[0043] In this embodiment, due to the different construction sites, the drainage difficulty of the completed embankment construction area is different. For the area with greater drainage difficulty, a reasonable design is required to make the area with embankment construction easier to drain. Therefore, for the area with greater drainage difficulty in the construction site, refer to Figure 6 As shown, the sill can be composed of the sill body and the permeable structure. The permeable structure can be composed of a permeable concrete wall or a permeable concrete wall and a drainage pipe, so as to avoid the problem that the water diversion in the area with greater drainage difficulty is difficult to discharge, resulting in the sill being corroded, or the soil moisture content is high and the soil is loose, resulting in the sill being unreliable. It should be noted that since the block sill does not use a complex reinforcement structure, the height is set to the common height of the sill of 1-3m, and 10-20cm graded crushed stone is used as the cushion layer at the bottom of the sill. The thickness of the block sill is 36.2cm, and the thickness of the permeable concrete on the back is 30-70cm. The permeable concrete can be made of crushed stone coarse aggregate with a diameter of not less than 2cm and mixed with concrete. It depends on the height of the sill. The higher the height of the sill, the more abandoned soil it can accommodate, so the required permeability needs to be stronger. Therefore, in areas with greater drainage difficulty, the height of the sill is proportional to the thickness of the permeable concrete wall. When the first building structure is used to build the sill, the sill is built in the form of modules. First, the cushion layer of the sill module is built, then the wall of the sill farthest from the tower base is built, and finally the two sides of the sill module are built; when the second building structure is used to build the sill, the sill is built in the form of modules. First, the cushion layer of the sill module is built, and after the cushion layer is built, the wall and the permeable structure of the sill farthest from the tower base are built at the same time, and finally the two sides of the sill module are built.
[0044] As an exemplary embodiment, when the building structure is the first building structure, the waste soil disposal method further includes: determining a first building height and a first ridge tilt angle of the ridge based on the first building structure, the earthwork volume and the slope, and the first building height and the first ridge tilt angle are positively correlated. When the building structure is the second building structure, the waste soil disposal method further includes: determining a second building height and a second ridge tilt angle of the ridge based on the second building structure, the earthwork volume and the slope, and the second building height and the second ridge tilt angle are positively correlated.
[0045] In this embodiment, see Figure 6-7 As shown, Figure 6For the sill that includes a permeable structure, when the height of the sill exceeds 1.5m, the back of the sill structure needs to be compacted with crushed stones with a particle size of 2 to 5cm and mixed with a small amount of cement to form a permeable concrete wall as a permeable layer on the back of the block to reduce the difficulty of drainage. Geotextile is used as a filter layer on the top of the permeable concrete wall to prevent soil from clogging the permeable concrete wall. At the same time, a drainage pipe with a diameter of 10 to 15cm is laid at the bottom of the permeable layer to form a good drainage measure. At the same time, it can form a whole with the masonry of the poured crushed stone blocks, promoting the stability of the wall force. Due to the use of interlocking blocks and reinforced permeable concrete wall water-repellent layer structure, the construction can greatly reduce the amount of engineering work caused by setting geogrids and backfilling soil during the construction of traditional dry-stack block retaining wall structures. Especially in hilly areas, the impact of masonry engineering on the slope can be reduced. Table 1 shows the relationship between the interlocking block masonry method and masonry height, as shown in Table 1:
[0046] Table 1
[0047] Tilt parameters of the embankment The structure of the fortress Height limit Vertical interlocking block ridge Baokan body 1.00m Interlocking block embankment with 9% slope Baokan body 1.25m Interlocking block embankment with 9% slope Permeable structure and embankment body 2.25m Interlocking block embankment with 18% slope Baokan body 1.50m Interlocking block embankment with 18% slope Permeable structure and embankment body 3.00m
[0048] In an actual construction scheme based on this application, see Figure 8 As shown, the terrain slope is 15° to 25°, and some tower legs are located in low-lying areas or the tower position is loose and unstable. It is necessary to set a certain height of interlocking block sills at a certain distance from the downhill position of the tower position in the vertical line direction, and pile the abandoned soil inside the tower base and a certain range outside the tower base to prevent sliding and ensure stability. The distance between the interlocking block sill and the outer edge of the foundation, as well as the height, slope, and length of the sill are determined according to the amount of abandoned soil. The interlocking block sill is preferably controlled within 1.5m in height with a slope of 18%. It can save the backfill of permeable concrete, reduce the construction volume, and make the barrier more stable. If the amount of earthwork is large, the length of the sill can be appropriately increased to increase the earthwork capacity. During construction, it is necessary to build a sill of 2 module height first, then backfill and compact, and then build a sill of 2 module height for backfilling. While digging, backfill layer by layer to ensure stability. Finally, after backfilling, it should be ensured that the top surface of the foundation is exposed by at least 0.2m.
[0049] It should be noted that the parameters of the building blocks and related parameters of the embankment exemplified in the embodiments of the present application can be adaptively changed according to the actual construction area and construction requirements, and are not intended to limit the embodiments of the present application.
[0050] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any modification, equivalent substitution and improvement made by any technician familiar with the technical field within the technical scope disclosed by the present invention and within the spirit and principle of the present invention should be covered within the protection scope of the present invention.
Claims
1. A modular embankment construction method for blocking spoil during tower foundation construction of a power transmission and transformation project, characterized in that: include: Obtain terrain parameters and the volume of abandoned earth within a preset range centered on the tower base; Determine the construction parameters and masonry method of the embankment based on the terrain parameters and the earthwork volume, the construction parameters include the construction height and the inclination angle of the embankment facade, the masonry method includes cross-laying of blocks in different masonry layers, the blocks include main blocks and secondary blocks, each masonry layer constituting the embankment is composed of cross-laying of main blocks and secondary blocks, and the main blocks and secondary blocks in adjacent masonry layers correspond to the main blocks and secondary blocks in adjacent masonry layers respectively, build a preset number of masonry layers, and perform multiple soil recovery, cycle in sequence, until the construction height of the embankment reaches the required construction height, in the tower base construction area where the soil recovery is completed, the exposed height of the tower base is greater than or equal to 0.2m, and fill plants between the main blocks and the secondary blocks; A crushed stone cushion layer is arranged below the embankment and is built in close contact with the embankment; The vertical inclination angle of the embankment is less than or equal to 18% slope, and the building height is less than or equal to 1.5m; Based on the construction parameters, the embankment is constructed by using dry-laid interlocking concrete blocks to form a waste soil accommodating area for accommodating waste soil; When the building height is less than the preset height and / or the inclination angle of the embankment facade is less than the preset inclination angle, the waste soil is recovered in layers in the waste soil accommodation area; When the building height is greater than the preset height and / or the inclination angle of the embankment facade is greater than the preset inclination angle, a permeable concrete layer is first formed in the waste soil accommodating area, and then the waste soil is covered.
2. The modular embankment construction method for blocking spoil during tower foundation construction of a power transmission and transformation project as claimed in claim 1, characterized in that: The thickness of the permeable concrete layer is 30-70 cm.
3. The modular embankment construction method for blocking spoil during tower foundation construction of a power transmission and transformation project as claimed in claim 2, characterized in that: Also includes: A drainage pipe is laid at the bottom of the permeable concrete layer.
4. The modular embankment construction method for blocking spoil during tower foundation construction of a power transmission and transformation project as claimed in claim 3, characterized in that: Also includes: A geotextile is laid on the top of the permeable concrete layer as a filter layer to prevent the abandoned soil from clogging the permeable layer.
Citation Information
Patent Citations
power transmission line tower foundation construction residual soil treatment method
CN109800467A
The versatile retaining wall
GB0408004D0
Reinforced banking wall method using channel type wall surface material