Elevator installation method and elevator installation
By installing hoisting equipment at the top of the elevator shaft, the modular assembly and layer-by-layer hoisting of the equipment frame can be achieved, solving the problem of shaft structural strength caused by the large weight of the elevator equipment, reducing costs and accelerating the construction progress.
Patent Information
- Application Number
- CN202310317320.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-28
- Publication Date
- 2025-12-05
- Estimated Expiration
- 2043-03-28
AI Technical Summary
The large weight of elevator equipment during hoisting leads to excessively high requirements for the structural strength of the elevator shaft, increasing costs and affecting the construction schedule.
At least two hoisting devices are installed at the top of the elevator shaft to stack and fix the equipment frame from bottom to top in the shaft. The hoisting devices are used to lift and fix the equipment layer by layer to achieve modular assembly.
The construction strength requirements for elevator shafts have been reduced, construction costs have been decreased, and overweight hoisting reviews are no longer required, thus improving construction progress.
Smart Images

Figure CN116216460B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the elevator technical field, and in particular to an elevator equipment hoisting method and an elevator equipment. BACKGROUND
[0002] In the elevator installation process, some equipment needs to be installed or transported in the elevator shaft. Since the specifications of these equipment are relatively heavy, the overall hoisting form requires higher building strength, and additionally increases the building cost of the elevator shaft. Moreover, hoisting exceeding a certain weight needs to be reviewed, thereby affecting the elevator installation progress. SUMMARY
[0003] The present application aims to provide an elevator equipment hoisting method and an elevator equipment to alleviate the technical problem that the hoisting weight of the elevator equipment is too large, and the building strength requirement of the elevator shaft is too high.
[0004] In a first aspect, the present application provides an elevator equipment hoisting method, comprising the following steps:
[0005] At least two hoisting equipment are arranged at the top of the elevator shaft;
[0006] A plurality of equipment frames are stacked from bottom to top, so that the plurality of equipment frames are arranged inside the elevator shaft, and the plurality of equipment frames are arranged below the hoisting equipment;
[0007] Elevator components are installed in the plurality of equipment frames, respectively;
[0008] The plurality of equipment frames are hoisted by the at least two hoisting equipment, and the hoisted equipment frames are fixed in the elevator shaft.
[0009] In combination with the first aspect, the present application provides a first possible implementation manner of the first aspect, wherein the step of stacking the plurality of equipment frames from bottom to top so that the plurality of equipment frames are arranged inside the elevator shaft comprises:
[0010] One of the equipment frames is installed at a first installation position inside the elevator shaft;
[0011] The remaining equipment frames are stacked and placed on the equipment frame installed at the first installation position, and the stacking layer number of the equipment frames is greater than 2.
[0012] In combination with the first aspect, the present application provides a second possible implementation manner of the first aspect, wherein the step of hoisting the plurality of equipment frames by the at least two hoisting equipment and fixing the hoisted equipment frames in the elevator shaft comprises:
[0013] using at least two of the lifting devices to connect the equipment frame at the top layer, hoist the equipment frame, and fix it in the elevator shaft;
[0014] hoist and fix the remaining equipment frames in order from top to bottom, and fix the lowest equipment frame at the second installation position;
[0015] release the equipment frames above the second installation position layer by layer from bottom to top, so that the multiple equipment frames are stacked from bottom to top.
[0016] In combination with the first aspect, the present application provides a third possible implementation of the first aspect, wherein the step of hoisting the multiple equipment frames using at least two of the lifting devices and fixing the hoisted equipment frames in the elevator shaft comprises:
[0017] using at least two of the lifting devices to connect the equipment frame at the top layer, hoist the equipment frame, and fix it in the elevator shaft;
[0018] divide the multiple equipment frames into at least one group from top to bottom, hoist and fix each group in the elevator shaft until the lowest equipment frame is hoisted and fixed at the second installation position.
[0019] In combination with the first aspect, the present application provides a fourth possible implementation of the first aspect, wherein the step of fixing the hoisted equipment frames in the elevator shaft comprises:
[0020] equipping the equipment frame with a support device, and clamping the elevator shaft guide rail by the support device;
[0021] Alternatively, connecting the equipment frame to the shaft ring beam.
[0022] The second aspect of the present application provides an elevator equipment, comprising:
[0023] at least two lifting devices installed at the top of the elevator shaft;
[0024] multiple equipment frames stacked inside the elevator shaft from bottom to top, with the lowest equipment frame connected to the elevator shaft;
[0025] and elevator components installed inside the equipment frame.
[0026] In combination with the second aspect, the present application provides a first possible implementation of the second aspect, wherein the equipment frame is equipped with a support device that clamps the elevator shaft guide rail;
[0027] Alternatively, the lifting point on the equipment frame is connected to the shaft ring beam.
[0028] In combination with the second aspect, the present application provides a second possible implementation manner of the second aspect, wherein the equipment frame has a gap space with the sidewall of the elevator shaft.
[0029] The embodiment of the present application has the following beneficial effects: by arranging at least two hoisting devices on the top of the elevator shaft, stacking the plurality of equipment frames from bottom to top, placing the plurality of equipment frames inside the elevator shaft, and locating the plurality of equipment frames below the hoisting devices, installing the elevator components in the plurality of equipment frames respectively, hoisting the plurality of equipment frames by using the at least two hoisting devices, and fixing the hoisted equipment frames in the elevator shaft, the modularization and hoisting of the elevator components can be realized, the hoisting can be performed once or multiple times according to the weight bearing capacity, the technical problem that the building strength requirement of the elevator shaft is too high due to the too large hoisting weight of the elevator is solved, and the building cost of the elevator shaft is reduced.
[0030] In order to make the above objectives, characteristics and advantages of the present application more apparent, comprehensible and easy to understand, the following preferred embodiments are specifically described below, and the accompanying drawings are referred to for detailed description. BRIEF DESCRIPTION OF DRAWINGS
[0031] In order to more clearly illustrate the technical solutions in the specific embodiments or the related art, the following will briefly introduce the drawings needed to be used in the specific embodiments or the related art description. Obviously, the drawings in the following description are some embodiments of the present application, and for those skilled in the art, other drawings can also be obtained without creative labor.
[0032] Figure 1 A schematic view of a first elevator equipment provided by the embodiment of the present application in an initial state;
[0033] Figure 2 A schematic view of a second elevator equipment provided by the embodiment of the present application in an initial state;
[0034] Figure 3 A schematic view of the first elevator equipment provided by the embodiment of the present application when hoisting the top layer equipment frame;
[0035] Figure 4 A schematic view of the first elevator equipment provided by the embodiment of the present application when hoisting the next top layer equipment frame;
[0036] Figure 5 A schematic view of the second elevator equipment provided by the embodiment of the present application when hoisting the next top layer equipment frame.
[0037] Icon: 001 - hoisting equipment; 101 - top hoisting point; 102 - equipment hoisting point; 002 - equipment frame; 003 - bottom support; 004 - support device. DETAILED DESCRIPTION
[0038] The technical solutions of the present application will be described clearly and completely below in conjunction with the drawings. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.
[0039] In the description of the present application, it should be noted that the orientations or positional relationships indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and therefore cannot be understood as indicating or implying that the devices or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as limiting the present application. In addition, the terms "first", "second", "third" are only for descriptive purposes and cannot be understood as indicating or implying relative importance. Physical quantities in formulas, such as basic quantities of International System of Units, or derived quantities derived from basic quantities by mathematical operations such as multiplication, division, differentiation or integration, should be understood as basic quantities of International System of Units, or derived quantities derived from basic quantities by mathematical operations such as multiplication, division, differentiation or integration.
[0040] In the description of the present application, it should be noted that unless otherwise explicitly specified and limited, the terms "mounting", "connection", "connection" should be understood broadly, for example, it can be fixedly connected, or it can be detachably connected, or integrally connected; it can be mechanically connected, or it can be electrically connected; it can be directly connected, or it can be indirectly connected through an intermediate medium; it can be the communication inside two elements. For those skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.
[0041] As shown in Figure 1 and Figure 2 The elevator equipment hoisting method provided by the embodiments of the present application comprises the following steps:
[0042] At least two hoisting equipment 001 are arranged at the top of the elevator shaft;
[0043] A plurality of equipment frames 002 are stacked from bottom to top, so that the plurality of equipment frames 002 are placed inside the elevator shaft and located below the hoisting equipment 001;
[0044] The elevator components are respectively mounted in the plurality of equipment frames 002;
[0045] The plurality of equipment frames 002 are hoisted by at least two hoisting devices 001, and the hoisted equipment frames 002 are fixed in the elevator shaft.
[0046] The elevator equipment hoisting method can realize the modularization of elevator components, and the elevator components can be divided and loaded on the plurality of equipment frames 002, so that the shaft side bearing capacity during hoisting can be reduced, and the building strength requirement of the elevator shaft is reduced, which is beneficial to reducing the building cost of the elevator shaft. In addition, the elevator equipment hoisting can distribute the hoisting weight according to the building bearing capacity, and can be hoisted in modules without the need for overweight hoisting, so that hoisting review is no longer needed, and the construction progress of the elevator can be accelerated.
[0047] In the embodiment of the present application, the step of stacking the plurality of equipment frames 002 from bottom to top and placing the plurality of equipment frames 002 inside the elevator shaft includes: installing one equipment frame 002 at a first installation position inside the elevator shaft, as shown in Figure 1 and Figure 2 The equipment frame 002 is placed on the bottom support 003, and the bottom support 003 is fixed to the side wall of the elevator shaft, the equipment frame 002 is supported by the bottom support 003, and is kept at the first installation position. Then, the remaining equipment frames 002 are stacked on the equipment frame 002 installed at the first installation position, and the number of stacked equipment frames 002 is greater than 2. The elevator components are respectively installed in the plurality of equipment frames 002, and can be hoisted separately during hoisting, which realizes the modularization of the equipment and reduces the requirement of the building strength of the elevator shaft during hoisting of the elevator.
[0048] As shown in Figure 3 , Figure 4 and Figure 5 The step of hoisting the plurality of equipment frames 002 by at least two hoisting devices 001 and fixing the hoisted equipment frames 002 in the elevator shaft includes:
[0049] The top equipment frame 002 is hoisted and fixed in the elevator shaft by using at least two hoisting devices 001 to connect the top equipment frame 002;
[0050] The remaining equipment frames 002 are hoisted and fixed layer by layer in the order from top to bottom, and the lowest equipment frame 002 is fixed at a second installation position;
[0051] The equipment frames 002 above the second installation position are released layer by layer from bottom to top, so that the plurality of equipment frames 002 are stacked from bottom to top.
[0052] Specifically, the lifting process adopts the lifting method, the center of gravity of the hoisted equipment frame 002 and the elevator components is located inside the figure formed by the connecting line of the lifting points, the top of the lifting equipment 001 is connected to the top lifting point 101, the lower end of the lifting equipment 001 is connected to the equipment lifting point 102, the equipment frame 002 is hoisted by at least two lifting equipment 001, the connecting line of the plurality of lifting equipment 001 from the top lifting point 101 to the equipment lifting point 102 is symmetrical relative to the longitudinal center line of the elevator shaft, so as to avoid the deflection of the equipment frame 002 in the elevator shaft. In addition, after the equipment frame 002 is hoisted layer by layer from top to bottom by the lifting equipment 001, the lowermost equipment frame 002 is first fixed to the second installation position, and then the equipment frame 002 above is released in turn from bottom to top, so that the plurality of equipment frames 002 can be stacked.
[0053] In an optional embodiment, the step of hoisting the plurality of equipment frames 002 by at least two lifting equipment 001 and fixing the hoisted equipment frames 002 in the elevator shaft comprises:
[0054] The equipment frame 002 below the top layer or the top layer is connected by at least two lifting equipment 001, hoisted and fixed in the elevator shaft;
[0055] The plurality of equipment frames 002 are divided into at least one group from top to bottom, and are hoisted and fixed in the elevator shaft respectively until the lowermost equipment frame 002 is hoisted and fixed to the second installation position.
[0056] Under the condition that the lifting load is allowed, a plurality of equipment frames 002 can be lifted at a time, and at least two lifting equipment 001 can be connected to the bottom layer of the equipment frame 002, so as to reduce the number of hoisting operations. When a plurality of equipment frames 002 are lifted at a time, the lifting equipment 001 is connected to the bottom layer of the group of equipment frames 002, so that the hoisting of the group of equipment frames 002 can be realized quickly. In the lifting process, the bottom layer of each group of equipment frames 002 is connected to the elevator shaft, and after the bottom layer of the lowermost group of equipment frames 002 is fixed, each group of equipment frames 002 is released in turn from bottom to top, so that the hoisted plurality of equipment frames 002 can be stacked again.
[0057] As shown in Figure 1 , Figure 3 and Figure 4 , the step of fixing the hoisted equipment frame 002 in the elevator shaft comprises: providing a supporting device 004 on the equipment frame 002, clamping the elevator shaft guide rail by the supporting device 004, and locking the equipment frame 002 in the corresponding installation position inside the elevator shaft.
[0058] In addition, the equipment frame 002 can be connected to the hoistway ring beam, and when connected, the lifting point on the equipment frame 002 can be connected to the hoistway ring beam through a lifting belt, so as to fix the equipment frame 002 in the absence of the default support device 004.
[0059] As shown in Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 , the elevator equipment provided by the embodiment of the present application comprises: at least two lifting devices 001 installed on the top of the elevator hoistway; a plurality of equipment frames 002 stacked from bottom to top inside the elevator hoistway, the lowermost equipment frame 002 being connected to the elevator hoistway; and elevator components installed inside the equipment frame 002.
[0060] In the above-mentioned elevator equipment, the elevator components are respectively loaded by the plurality of equipment frames 002, and according to the building load capacity of the elevator hoistway, the plurality of equipment frames 002 can be lifted one by one or in groups, which can alleviate the technical problem that the overall weight of the elevator equipment is too large, resulting in too high a requirement for the building strength of the elevator hoistway, which is not only beneficial to reduce the construction cost of the elevator hoistway, but also avoids the delay of the construction period due to the review of the overloading lifting.
[0061] In the embodiment of the present application, the equipment frame 002 is provided with a support device 004 clamping the elevator hoistway guide rail, or the lifting point on the equipment frame 002 is connected to the hoistway ring beam. The plurality of support devices 004 can be respectively fixed relative to the elevator hoistway, so as to reduce the load bearing of the bottom equipment frame 002, and further reduce the gravity borne by the bottom support 003.
[0062] In addition, the equipment frame 002 has a gap space with the side wall of the elevator hoistway, and the lifting device 001 can pass through the gap space to be connected to any equipment frame 002 below the next top layer, so that the number of single lifting equipment frames 002 can be reasonably arranged according to the building strength of the elevator hoistway and the load capacity of the lifting device 001, without requiring too high a requirement for the building strength of the elevator hoistway, thereby reducing the construction cost of the hoistway.
[0063] Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present application, but not to limit them; although the present application has been described in detail with reference to the above embodiments, those skilled in the art should understand that: the technical solutions recorded in the above embodiments can still be modified, or some or all of the technical features can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present application.
Claims
1. A hoisting method of an elevator installation, characterized in that, The method comprises the following steps: providing at least two hoisting devices (001) at the top of an elevator shaft; stacking a plurality of equipment frames (002) from bottom to top, placing the plurality of equipment frames (002) inside the elevator shaft, and locating the plurality of equipment frames (002) below the hoisting devices (001); installing elevator components in the plurality of equipment frames (002) respectively; hoisting the plurality of equipment frames (002) by using the at least two hoisting devices (001) and fixing the hoisted equipment frames (002) in the elevator shaft; the step of stacking the plurality of equipment frames (002) from bottom to top and placing the plurality of equipment frames (002) inside the elevator shaft comprises: installing one of the equipment frames (002) at a first installation position inside the elevator shaft; and stacking the remaining equipment frames (002) on the equipment frame (002) installed at the first installation position, and making the number of stacked layers of the equipment frames (002) greater than 2; the step of hoisting the plurality of equipment frames (002) by using the at least two hoisting devices (001) and fixing the hoisted equipment frames (002) in the elevator shaft comprises: connecting the equipment frame (002) at the top layer by using the at least two hoisting devices (001), hoisting the equipment frame (002), and fixing the equipment frame (002) in the elevator shaft; hoisting and fixing the remaining equipment frames (002) in order from top to bottom layer by layer, and fixing the equipment frame (002) at the bottom layer in a second installation position; and releasing the equipment frames (002) above the second installation position layer by layer from bottom to top, so that the plurality of equipment frames (002) are stacked from bottom to top.
2. The hoisting method of an elevator installation according to claim 1, characterized in that, the step of fixing the hoisted equipment frames (002) in the elevator shaft comprises: providing support devices (004) on the equipment frames (002), and clamping the elevator shaft guide rails by the support devices (004); or connecting the equipment frames (002) to the shaft ring beam.
Citation Information
Patent Citations
Arrangement and a method for parallel transport and installation of elevator components
US20160332845A1