A large concrete steel-clad column construction method and auxiliary collection mechanism
By presetting the assembly of the insertion ribs and using the introduction cone and auxiliary collection mechanism in the large concrete steel column, the installation difficulties caused by small clearance in the embedded insertion rib hook and small bolt hole gap are solved, and the smooth installation and construction efficiency of the steel structure columns are achieved.
Patent Information
- Application Number
- CN202310133951.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-02-20
- Publication Date
- 2025-05-20
- Estimated Expiration
- 2043-02-20
AI Technical Summary
The empty size inside the embedded reinforcement hook of large concrete steel columns is small, which makes the steel structure column unable to be installed directly in place. The introduction of the embedded bolt cone causes a small gap between the bolt holes and the bolts on the steel column foot of the steel structure column, making it difficult to install.
The assembled insert is adopted, and the lower insert is preset in the base to reduce the height of the insert so that the steel structure base plate can enter from above; the introduction cone and auxiliary collection mechanism are used to assist in the installation and recovery of the introduction cone to ensure that the bolt hole is aligned with the anchor bolts and penetrate.
It solves the problem that steel structure columns cannot be installed directly, simplifies the installation process, avoids the problem of small internal space of the insertion reinforcement and the inability to enter, and improves construction efficiency.
Smart Images

Figure CN116290808B_ABST
Abstract
Claims
1. A large concrete steel-clad column construction method, characterized in that: The specific steps include: S1: prefabricated integral dowel bars (211), lower dowel bars (212), upper dowel bars (213) and an introduction cone (44); S2: pre-embed the anchor bolts (4), the whole dowel bars (211) and the lower dowel bars (212), and then inject concrete to complete the construction of the base (1); S3: After the surface of the base (1) is subjected to a pitting treatment and a washer group is provided, a guide cone (44) is installed on the top of the straight rod (41) of the anchor bolt; S4: hoisting the steel structure (3) so that the steel structure (3) enters the base (1) from one side of the lower dowel (212) and then moves the steel structure (3) downward so that the anchor bolts (4) pass through the bolt holes on the bottom plate (31). The auxiliary collection mechanism is then used to recover the guide cone (44) and then the bottom plate (31) is fixed. S5: After inspecting the installed steel structure (3), the grouting layer (5) is constructed; S6: Using a connector (214), the upper dowel bar (213) is installed on the lower dowel bar (212), and stirrups (22) are installed; S7: Supporting the formwork of the concrete-encased steel column (2) on the outer side of the whole dowel (211) and the lower dowel (212), and pouring concrete into the formwork, and after the concrete solidifies, removing the formwork and cleaning; The auxiliary collection mechanism comprises: a support rod (6), a mounting frame (8) which moves along the length direction of the support rod (6) and an elastic element connected to the mounting frame (8) are slidably provided on the support rod (6), a winding mechanism (10) is provided at one end of the support rod (6) away from the mounting frame (8), a pull rope (9) is provided between the mounting frame (8) and the winding mechanism (10), an electromagnet (16) is provided on the mounting frame (8), and a collection box (7) for collecting the introduction cone (44) is provided on the support rod (6); A mounting member (15) is rotatably arranged inside the mounting frame (8), and the electromagnets (16) are provided in a plurality of groups. The plurality of groups of electromagnets (16) are evenly distributed on the outside of the mounting member (15). A driving member is connected to the mounting member (15) to drive the mounting member (15) to rotate.
2. A large concrete steel-clad column construction method according to claim 1, characterized in that: The upper part of the introduction cone (44) is conical, and the lower part is a sleeve, and the inner diameter of the sleeve is equal to the outer diameter of the thread of the anchor bolt straight rod (41).
3. A large concrete steel-clad column construction method according to claim 1, characterized in that: The concrete-coated steel column (2) has at least one surface with lower inserted reinforcement (212).
4. A large concrete steel-clad column construction method according to claim 1, characterized in that: The support rod (6) is provided with a first touch switch (14) located on the moving path of the mounting frame (8), and the first touch switch (14) is electrically connected to the electromagnet (16) to control the electromagnet (16) to cut off power.
5. A large concrete steel-clad column construction method according to claim 4, characterized in that: The support rod (6) is provided with a slot (12), a reel (13) and a torsion spring connected to the reel (13) are rotatably provided in the slot (12), a pipe (11) connected to the mounting frame (8) is wound around the reel (13), and a connecting cable between the electromagnet (16) and the first touch switch (14) is located in the pipe (11).
6. A large concrete steel-clad column construction method according to claim 1, characterized in that: A mounting groove (17) is provided at the connection portion between the mounting member (15) and the electromagnet (16), the electromagnet (16) is slidably inserted into the mounting groove (17), an elastic member (18) is provided between the electromagnet (16) and the mounting groove (17), a second touch switch (20) electrically connected to the driving member is provided in the mounting groove (17), and the electromagnet (16) is provided with a pressing block (19) located inside the second touch switch (20).
7. A large concrete steel-clad column construction method according to claim 1, characterized in that: The collecting box (7) is detachably mounted on the support rod (6), and an elastic spacer is arranged inside the collecting box (7).
Citation Information
Patent Citations
Huge steel reinforced concrete combined column structure and construction method thereof
CN105178510A
Method for mounting steel-structure module in place
CN107327023A
Construction waste land remediation device
CN112403650A
Connecting joint of assembly type column base
CN217630436U