A full-circle synchronous lining trolley for TBM tunnel construction and construction method
By designing a full circle synchronous lining trolley for the TBM construction tunnel, using an integral frame and an inflatable airbag formwork, the problems of complicated and difficult processes in traditional TBM construction are solved, and efficient tunnel lining construction is achieved.
Patent Information
- Application Number
- CN202310106408.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-02-13
- Publication Date
- 2025-08-29
- Estimated Expiration
- 2043-02-13
AI Technical Summary
The traditional TBM method has complicated construction processes for secondary lining of tunnels, high cross interference, high construction difficulty, and hydraulic components occupy space, resulting in a large number of internal poles of the trolley, making on-site operation inconvenient.
A fully circular synchronous lining trolley of TBM construction tunnel was designed, adopting an integral frame design, and the trolley structure does not need to be shrinked. The template is supported and removed through an inflatable airbag formwork. Combined with needle beams, steel bar trolleys, maintenance trolleys and other components, the construction process is simplified and a full circle is achieved.
The construction process is simplified, the construction difficulty is reduced, the construction efficiency is improved, and the efficient operation of lining construction is achieved.
Smart Images

Figure CN116357341B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel construction, in particular to a TBM (Transport Block Machine) tunnel full-circle synchronous lining trolley and a construction method. Background Art
[0002] In traditional TBM construction, the secondary lining of tunnels is constructed only after the tunnel is fully penetrated, and the secondary lining adopts a construction mode in which the invert arch and the arch wall lining are constructed separately, which has a great impact on the project schedule.
[0003] The simultaneous construction of secondary lining and TBM excavation requires effective solutions for transport track dismantling and conversion, ventilation, slag conveyors, high-voltage cables, and rail-mounted material transport, all crossing the lining operation area. The lining operation area is complex, with significant cross-interference and construction difficulties. Traditional lining trolleys use hydraulic components (or screws) to control the retraction and contraction of the trolley panels, enabling the erection and removal of lining formwork. Because the hydraulic components (or screws) and the retraction of the panels require a certain amount of space, the trolley's internal rods are numerous, making on-site operations inconvenient. Summary of the Invention
[0004] The object of the present invention is to provide a TBM construction tunnel full-circle synchronous lining trolley and construction method with convenient operation and efficient construction.
[0005] To achieve the above-mentioned object, the present invention provides the following technical solutions: a TBM construction tunnel full-circle synchronous lining trolley and construction method, the TBM construction tunnel full-circle synchronous lining trolley comprises a needle beam, a steel bar trolley is provided at the front end of the needle beam; a lining trolley is provided on the needle beam and at the rear side of the steel bar trolley; a maintenance trolley is provided on the needle beam and at the rear side of the lining trolley; cantilever beams are provided at both ends of the needle beam; lifting devices are symmetrically provided below the top of the frame of the needle beam and the cantilever beam; floating trolleys are provided at the front and rear ends of the needle beam. A Y-type turnout, and the floating Y-type turnout is connected to the end of the needle beam through a hinged ear plate, a spring group is provided under the needle beam side rail of the floating Y-type turnout, a wheelset is provided at the bottom of the floating Y-type turnout, and the wheelset is provided below the spring group; a shifting device is provided between the needle beam and the steel bar trolley, lining trolley and maintenance trolley; bottom supports A are provided at both ends of the bottom of the steel bar trolley and the lining trolley, and anti-floating supports are provided at both ends of the top of the lining trolley; bottom supports B are provided at both ends of the bottom of the needle beam.
[0006] Among them, in the present invention, the lining trolley includes a lining trolley gantry arranged outside the needle beam, and horizontal rollers A and vertical limiting wheels A are provided between the lining trolley gantry and the needle beam and at the four corners; a cylindrical ring beam is connected to the outside of the lining trolley gantry, and the lining trolley gantry and the cylindrical ring beam are connected by support columns, and both ends of the lining trolley gantry extend 40 cm to 60 cm outside the cylindrical ring beam; a template device is provided outside the cylindrical ring beam; a flat barrel-type hard air duct is provided above the lining trolley gantry, a support pipe is provided in the flat barrel-type hard air duct, and a hanging ring is connected to the top of the support pipe.
[0007] Among them, in order to ensure that the lining trolley can successfully complete the demoulding, the template device includes air bags densely arranged on the periphery of the cylindrical ring beam, and the air bags are fixed to the outer surface of the cylindrical ring beam by anchor nails; an inflation valve is provided on the air bag, and a fiber rope is provided inside the air bag; a hard plastic panel is provided on the outer surface of the air bag; a plurality of feeding ports with handles are evenly arranged in the cylindrical ring beam and the template device, a clamping plate is provided on the side wall of the feeding port, a steel seal is installed on the feeding port, a reinforcement ring is provided on the outer periphery of the feeding port, and an L-shaped pressure plate is symmetrically provided on the reinforcement ring.
[0008] Among them, the rebar trolley includes a rebar trolley gantry mounted outside the needle beam, and a telescopic working platform is arranged on both sides of the rebar trolley gantry; horizontal rollers B and vertical limiting wheels B are arranged between the rebar trolley gantry and the needle beam and at the four corners; a ventilation hose passage is arranged on the rebar trolley gantry, and a ventilation hose is arranged in the ventilation hose passage.
[0009] Among them, in order to facilitate the maintenance of the tunnel after lining, a maintenance trolley is arranged behind the lining trolley, and the maintenance trolley includes a maintenance trolley gantry arranged outside the needle beam, and horizontal rollers C and vertical limiting wheels C are arranged between the maintenance trolley gantry and the needle beam and at the four corners; an air film maintenance cover is arranged on the maintenance trolley gantry, and the air film maintenance cover is supported on the maintenance trolley gantry by an annular square steel frame, and the air film maintenance cover is arranged along the inner surface of the lining, and the air film maintenance cover is arranged as an air film cylindrical structure, and air film plugs are arranged at both ends of the air film maintenance cover; a spray device is arranged on one side of the maintenance trolley gantry.
[0010] Among them, in order to facilitate the adjustment of the position of the trolley, the shifting device includes an upper rack and a lower rack respectively arranged on the upper and lower surfaces of the needle beam, and two upper racks and two lower racks are symmetrically arranged. A hydraulic motor is arranged on the inner wall of the steel bar trolley gantry, lining trolley gantry and maintenance trolley gantry and at a position corresponding to the upper rack and the lower rack, and a gear is connected to the hydraulic motor.
[0011] Among them, in order to facilitate the adjustment of the height of the needle beam and the trolley and ensure the accuracy of the lining size, the bottom support A includes a telescopic cylinder A arranged at both ends of the bottom of the steel bar trolley gantry and the lining trolley gantry, and a support block A is arranged at the other end of the telescopic cylinder A; the bottom support B includes a telescopic cylinder B arranged at both ends of the bottom of the needle beam, and a support block B is arranged at the other end of the telescopic cylinder B; the anti-floating support includes a telescopic cylinder C arranged at both ends of the top of the lining trolley gantry, and a support block C is arranged at the other end of the telescopic cylinder C.
[0012] In order to facilitate the removal of the front rail system and transfer it to the rear for installation, the lifting device includes a hanging rail symmetrically arranged below the top of the needle beam, and a crane is slidably arranged on the hanging rail.
[0013] Among them, since the continuous belt conveyor needs to change the support mode when passing through the lining trolley and the maintenance trolley, in order to ensure the smooth passage of the continuous belt conveyor, a bracket is provided on one side of the lining trolley gantry and the maintenance trolley gantry, and support rollers and vertical limit rollers are provided on the bracket.
[0014] Among them, in order to ensure smooth cable sliding, a support frame is provided on the outer wall of one side of the reinforcement trolley gantry, lining trolley gantry and maintenance trolley gantry, and a cable sliding channel is provided on the support frame; a tunnel wall cable is provided on one side of the tunnel, and a continuous belt conveyor is provided on the tunnel wall and opposite to the tunnel wall cable.
[0015] The TBM tunnel full-circle synchronous lining construction method includes the following steps: 1) moving the front floating Y-type turnout forward; 2) removing the original track under the turnout and cleaning the tunnel bottom; 3) moving the needle beam forward; 4) installing the rear track; 5) moving the rear floating Y-type turnout forward; 6) moving the steel bar trolley forward and installing the steel bar; 7) moving the lining trolley and the maintenance trolley forward and synchronously maintaining the rear lining; 8) lining construction.
[0016] Wherein, in said step 8), the lining trolley is moved to the lining pouring position, the bottom support A and the anti-floating support are adjusted, and the lining trolley is put into place; the airbag is inflated to the specified value from bottom to top, so that the airbag panel expands to the designed lining surface, the inflation valve is closed to maintain pressure, and then the lining end is sealed, and the lining concrete is poured from the feeding port from bottom to top. When the lining concrete pouring surface is almost at the feeding port, the steel seal is installed, and the feeding port is sealed with an L-shaped pressure plate and the steel seal, and the concrete is continued to be poured from the upper feeding port until the lining pouring is completed; after the lining concrete pouring is completed, when the concrete strength reaches the specified value, the steel seal is removed. There is a steel seal. Open the inflation valve of each airbag from top to bottom in turn to release the air in the airbag, pull the feeding port back and fix it, and then use the vacuum pump to completely exhaust the air in the airbag. The airbag is retracted, compressed and adsorbed on the cylindrical ring beam. At this time, the trolley demoulding is completed; retract the bottom support B at the bottom of the needle beam, so that the needle beam falls on the roller at the bottom of the lining trolley, and the hydraulic motor is turned to move the needle beam forward. After the needle beam moves into place, lower the bottom supports B at both ends of the needle beam to support the needle beam, and lift the lining trolley on the needle beam. Start the hydraulic motor on the lining trolley to move the lining trolley forward to the next lining construction position.
[0017] Wherein, in step 6) and step 7), the moving method of the reinforcement trolley and the maintenance trolley is the same as that of the lining trolley in step 8).
[0018] Among them, in the step 7), when the lining trolley moves forward, the ventilation hose is untied from the tunnel arch in the forward direction of the trolley, and as the trolley moves, the ventilation hose in the forward direction is retracted and put on the flat barrel-type rigid air duct, and the ventilation hose on the end of the flat barrel-type rigid air duct is pulled out from the rear of the gantry and re-hung on the wire rope of the tunnel arch. After the gantry moves into place, the ventilation hose is fastened and fixed to the flat barrel-type rigid air duct with a tightening tie to restore normal ventilation. If the ventilation efficiency is low, a pressurized fan is added to the flat barrel-type rigid air duct to assist ventilation.
[0019] Due to the adoption of the above technical solution, the present invention has the advantages of simple construction process and low construction difficulty. The internal frame of the device is an integral design, the trolley structure does not need to be retracted, and an inflatable airbag template is set on the outside of the trolley panel. The trolley template is supported and removed by inflating and deflating the airbag. The use of this invention can realize the one-time casting of the entire circle of lining construction, simplifying the construction process and improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The accompanying drawings of the present invention are as follows:
[0021] Figure 1 This is a longitudinal section diagram of the full-circle synchronous lining construction;
[0022] Figure 2This is an enlarged view of the front half of the longitudinal section of the full-circle synchronous lining construction;
[0023] Figure 3 This is an enlarged view of the middle part of the longitudinal section of the full-circle synchronous lining construction;
[0024] Figure 4 This is an enlarged view of the second half of the longitudinal section of the full-circle synchronous lining construction;
[0025] Figure 5 This is a schematic diagram of the tunnel cross-section layout;
[0026] Figure 6 This is a schematic diagram of the bottom support and anti-floating structure of the full-section lining trolley;
[0027] Figure 7 This is a schematic diagram of the full-section lining trolley frame structure;
[0028] Figure 8 This is a schematic diagram of the full-section lining trolley panel structure;
[0029] Figure 9 This is a schematic diagram of the cross section of the steel bar trolley;
[0030] Figure 10 This is a schematic diagram of the cross section of the needle beam;
[0031] Figure 11 This is a schematic diagram of the cross section of the maintenance trolley. DETAILED DESCRIPTION
[0032] The specific embodiments of the present invention are further described in detail below with reference to the accompanying drawings, but the present invention is not limited to these embodiments. Any improvement or substitution based on the basic spirit of the present embodiment still falls within the scope of protection required by the claims of the present invention.
[0033] Example 1: Figure 1 、 2, 3, 4, 5, 6, 7, 8, 9, 10 or 11, a TBM construction tunnel full-circle synchronous lining trolley, comprising a needle beam 12, a steel bar trolley 17 is provided at the front end of the needle beam 12; a lining trolley 7 is provided on the needle beam 12 and at the rear side of the steel bar trolley 17; a maintenance trolley 18 is provided on the needle beam 12 and at the rear side of the lining trolley 7; cantilever beams 1201 are provided at both ends of the needle beam 12; a lifting device 16 is symmetrically provided below the top of the frame of the needle beam 12 and the cantilever beam 1201; and a lifting device 16 is provided at the front and rear ends of the needle beam 12. A floating Y-type turnout 19 is provided, and the floating Y-type turnout 19 is connected to the end of the needle beam 12 through a hinged ear plate 1904, a spring group 1902 is provided under the needle beam side rail of the floating Y-type turnout 19, a wheelset 1901 is provided at the bottom of the floating Y-type turnout 19, and the wheelset 1901 is provided below the spring group 1902; a shifting device 15 is provided between the needle beam 12 and the steel bar trolley 17, the lining trolley 7, and the maintenance trolley 18; bottom supports A 20 are provided at both ends of the bottom of the steel bar trolley 17 and the lining trolley 7, and anti-floating supports 701 are provided at both ends of the top of the lining trolley 7; bottom supports B 1203 are provided at both ends of the bottom of the needle beam 12.
[0034] Further description, in the present invention, the lining trolley 7 includes a lining trolley gantry 702 which is mounted outside the needle beam 12, and horizontal rollers A 703 and vertical limiting wheels A 704 are provided between the lining trolley gantry 702 and the needle beam 12 and at the four corners; a cylindrical ring beam 8 is connected to the outside of the lining trolley gantry 702, and the lining trolley gantry 702 and the cylindrical ring beam 8 are connected by support columns 707, and both ends of the lining trolley gantry 702 extend out of the cylindrical ring beam 8; a template device 9 is provided outside the cylindrical ring beam 8; a flat barrel-type hard air duct 201 is provided above the lining trolley gantry 702, a support pipe 202 is provided in the flat barrel-type hard air duct 201, and a lifting ring 203 is connected to the top of the support pipe 202.
[0035] In order to avoid adverse effects on the quality of concrete caused by vibrations from passing vehicles during lining operations, the frames of the lining trolley portal frame 702 and the needle beam 12 are designed to be separated, with sufficient clearance between the frames. During the lining operations, the bottom support B 1203 of the needle beam 12 is adjusted to ensure that the frame of the needle beam 12 does not come into contact with the lining trolley portal frame 702 when the rail transport formation passes.
[0036] Further description, the template device 9 includes air bags 904 densely arranged on the periphery of the cylindrical ring beam 8, and the air bags 904 are fixed to the outer surface of the cylindrical ring beam 8 by anchor nails 902; an inflation valve 903 is provided on the air bag 904, and a fiber rope 901 is provided inside the air bag 904; a hard plastic panel 10 is provided outside the air bag 904; a plurality of feeding ports 11 with handles 1101 are evenly provided in the cylindrical ring beam 8 and the template device 9, a clamping plate 1102 is provided on the side wall of the feeding port 11, a steel seal 1103 is installed on the feeding port 11, a reinforcement ring 1104 is provided on the outer periphery of the feeding port 11, and an L-shaped pressure plate 1105 is symmetrically provided on the reinforcement ring 1104.
[0037] The trolley template is erected and dismantled by inflating and deflating the air bag 904 in the template device.
[0038] Further description, the rebar trolley 17 includes a rebar trolley gantry 1701 which is mounted outside the needle beam 12, and a telescopic working platform 1705 is provided at the upper ends of both sides of the rebar trolley gantry 1701; horizontal rollers B 1703 and vertical limiting wheels B 1704 are provided between the rebar trolley gantry 1701 and the needle beam 12 and at the four corners; a ventilation hose passage 1702 is provided on the rebar trolley gantry 1701, and a ventilation hose 2 is provided in the ventilation hose passage 1702.
[0039] Further description, the maintenance trolley 18 includes a maintenance trolley gantry 1803 which is mounted outside the needle beam 12, and horizontal rollers C 1806 and vertical limiting wheels C1807 are provided between the maintenance trolley gantry 1803 and the needle beam 12 and at the four corners; an air film maintenance cover 1805 is provided on the maintenance trolley gantry 1803, and the air film maintenance cover 1805 is supported on the maintenance trolley gantry 1803 by a ring-shaped square steel frame 1802, and the air film maintenance cover 1805 is arranged along the inner surface of the lining, and the air film maintenance cover 1805 is arranged as an air film cylindrical structure, and air film plugs 1804 are provided at both ends of the air film maintenance cover 1805; a spray device 1801 is provided on one side of the maintenance trolley gantry 1803.
[0040] The air film curing cover 1805 is inflated to seal the lining surface to be cured, and then the spraying device 1801 sprays water to cure the lining structure; after the curing is completed, the air in the air film curing cover 1805 is released.
[0041] Further description, the shifting device 15 includes an upper rack 1502 and a lower rack 1503 respectively arranged on the upper and lower surfaces of the needle beam 12, and two upper racks 1502 and two lower racks 1503 are symmetrically arranged, and a hydraulic motor 1504 is arranged on the inner wall of the steel bar trolley gantry 1701, the lining trolley gantry 702 and the maintenance trolley gantry 1803 and at a position corresponding to the upper rack 1502 and the lower rack 1503, and a gear 1501 is connected to the hydraulic motor 1504.
[0042] The steel bar trolley 17 and the curing trolley 18 can move back and forth on the needle beam 12 under the joint action of the shifting device 15 and the horizontal rollers and the vertical limiting rollers.
[0043] Further description, the bottom support A 20 includes a telescopic cylinder A 2001 arranged at both ends of the bottom of the steel bar trolley gantry 1701 and the lining trolley gantry 702, and a support block A 2002 is arranged at the other end of the telescopic cylinder A 2001; the bottom support B 1203 includes a telescopic cylinder B 1204 arranged at both ends of the bottom of the needle beam 12, and a support block B1205 is arranged at the other end of the telescopic cylinder B 1204; the anti-floating support 701 includes a telescopic cylinder C 705 arranged at both ends of the top of the lining trolley gantry 702, and a support block C 706 is arranged at the other end of the telescopic cylinder C 705.
[0044] To further describe, the lifting device 16 includes a hanging rail 1601 symmetrically arranged below the top of the needle beam 12 , and a crane 1602 is slidably arranged on the hanging rail 1601 .
[0045] By setting up the lifting device 16, the crane 1602 lifts the track removed in front and slides it from the front end to the rear end of the hanging rail 1601, thereby completing the transfer of the track.
[0046] Further description is given, a bracket 301 is provided on one side of the lining trolley portal frame 702 and the maintenance trolley portal frame 1803 , and a supporting roller 302 and a vertical limiting roller 303 are provided on the bracket 301 .
[0047] When the continuous belt conveyor 3 passes through the lining trolley 7 and the maintenance trolley 18, it is necessary to change the support mode. By setting the support roller 302 and the vertical limit roller 303, the continuous belt conveyor 3 can ensure that the continuous belt conveyor 3 passes through the lining trolley 7 and the maintenance trolley 18.
[0048] Further description is given, a support frame 401 is provided on the outer wall of one side of the reinforcement trolley gantry 1701, the lining trolley gantry 702 and the maintenance trolley gantry 1803, and a cable sliding channel 402 is provided on the support frame 401; a tunnel wall cable 4 is provided on one side of the tunnel, and a continuous belt conveyor 3 is provided on the tunnel wall and at a position opposite to the tunnel wall cable 4.
[0049] Before the reinforcement work, all the tunnel wall cables 4 are untied and placed in the cable sliding channel 402 on the trolley. After the lining construction is completed, the tunnel wall cables 4 are restored to the lined tunnel wall.
[0050] Further description, the TBM construction method for full-circle synchronous lining of a tunnel includes the following steps: 1) moving the front floating Y-type turnout forward; 2) removing the original track under the turnout and cleaning the tunnel bottom at the same time; 3) moving the needle beam forward; 4) installing the rear track; 5) moving the rear floating Y-type turnout forward; 6) moving the steel bar trolley forward and installing the steel bar; 7) moving the lining trolley and the maintenance trolley forward and synchronously maintaining the rear lining; 8) lining construction.
[0051] Further description, in said step 8), the lining trolley 7 is moved to the lining pouring position, the bottom support A20 and the anti-floating support 701 are adjusted, and the lining trolley 7 is put into place; the air bag 904 is inflated to the specified value from bottom to top, so that the air bag 904 panel is expanded to the designed lining surface, the inflation valve 903 is closed to maintain the pressure, and then the lining end is sealed, and the lining concrete is poured from the feeding port 11 from bottom to top. When the lining concrete pouring surface is about to reach the feeding port 11, the steel seal 1103 is installed, and the L-shaped pressure plate 1105 and the steel seal 1103 are used to press the lining. The feeding port 11 is sealed, and concrete pouring continues from the feeding port 11 of the upper layer until the lining pouring is completed; after the lining concrete pouring is completed, when the concrete strength reaches the specified value, all steel seals 1103 are removed, and the inflation valve 903 of each air bag 904 is opened from top to bottom, the air in the air bag 904 is released, and the feeding port 11 is pulled back and fixed, and then the air in the air bag 904 is completely exhausted by using the vacuum pump, and the air bag 904 is retracted, compressed and adsorbed on the cylindrical ring beam 8, and the trolley demoulding is completed at this time; the bottom support B at the bottom of the needle beam 12 is retracted 1203, so that the needle beam 12 falls on the roller at the bottom of the lining trolley 7, and the needle beam 12 is moved forward by rotating the hydraulic motor 1504. After the needle beam 12 moves into place, the bottom supports B 1203 at both ends of the needle beam 12 are lowered to prop up the needle beam 12, and the lining trolley 7 is lifted on the needle beam 12, and the hydraulic motor 1504 set on the lining trolley 7 is started to move the lining trolley 7 forward to the next lining construction position.
[0052] To further describe, in step 6) and step 7), the moving method of the reinforcement trolley 17 and the curing trolley 18 is the same as that of the lining trolley 7 in step 8).
[0053] Further description, in the step 7), when the lining trolley 7 moves forward, the ventilation hose 2 is untied from the tunnel arch in the forward direction of the trolley, and as the trolley moves, the ventilation hose 2 in the forward direction is retracted and put on the flat barrel-type hard air duct 201, and the ventilation hose 2 on the end of the flat barrel-type hard air duct 201 is pulled out from the rear of the stand and re-hung on the wire rope of the tunnel arch. After the stand moves into place, the ventilation hose 2 is fastened and fixed to the flat barrel-type hard air duct 201 with a tightening tie to restore normal ventilation; if the ventilation efficiency is low, a pressurized fan is added to the flat barrel-type hard air duct 201 to assist ventilation.
[0054] In the present invention, steel sleepers 5 are provided at both ends of the needle beam, and double-track tracks are provided on the steel sleepers; a single-track track 1202 is provided at the bottom of the needle beam, and the double-track track 501 is connected to the single-track track 1202 through a floating Y-shaped branch 19.
Claims
1. A TBM construction tunnel full-circle synchronous lining trolley, comprising a needle beam (12), characterized in that: A steel bar trolley (17) is provided at the front end of the needle beam (12); a lining trolley (7) is provided on the needle beam (12) and located at the rear side of the steel bar trolley (17); a maintenance trolley (18) is provided on the needle beam (12) and located at the rear side of the lining trolley (7); a cantilever beam (1201) is provided at both ends of the needle beam (12), and a lifting device (16) is symmetrically provided below the top of the frame of the needle beam (12) and the cantilever beam (1201); a floating Y-type turnout (19) is provided at the front and rear ends of the needle beam (12), and the floating Y-type turnout (19) is connected to the end of the needle beam (12) through a hinged ear plate (1904). A spring group (1902) is provided below the needle beam side rail of the floating Y-type turnout (19); a wheel pair (1901) is provided at the bottom of the floating Y-type turnout (19), and the wheel pair (1901) is provided below the spring group (1902); a shifting device (15) is provided between the needle beam (12) and the steel bar trolley (17), the lining trolley (7), and the maintenance trolley (18); bottom supports A (20) are provided at both ends of the bottom of the steel bar trolley (17) and the lining trolley (7), and anti-floating supports (701) are provided at both ends of the top of the lining trolley (7); and bottom supports B (1203) are provided at both ends of the bottom of the needle beam (12).
2. The TBM tunnel full-circle synchronous lining trolley according to claim 1, characterized in that: The lining trolley (7) comprises a lining trolley portal frame (702) sleeved on the outside of the needle beam (12); horizontal rollers A (703) and vertical limiting wheels A (704) are provided between the lining trolley portal frame (702) and the needle beam (12) and at four corners; a cylindrical ring beam (8) is connected to the outside of the lining trolley portal frame (702); a support is provided between the lining trolley portal frame (702) and the cylindrical ring beam (8). The lining trolley portal frame (702) is connected to a column (707), and both ends of the lining trolley portal frame (702) extend outside the cylindrical ring beam (8); a template device (9) is provided outside the cylindrical ring beam (8); a flat barrel-shaped hard air duct (201) is provided above the lining trolley portal frame (702), a support pipe (202) is provided in the flat barrel-shaped hard air duct (201), and a lifting ring (203) is connected to the top of the support pipe (202).
3. The TBM tunnel full-circle synchronous lining trolley according to claim 2, characterized in that: The template device (9) includes air bags (904) densely arranged on the periphery of the cylindrical ring beam (8), and the air bags (904) are fixedly arranged on the outer surface of the cylindrical ring beam (8) by anchor nails (902); an inflation valve (903) is arranged on the air bag (904), and a fiber rope (901) is arranged inside the air bag (904); a hard plastic panel (10) is arranged on the outer surface of the air bag (904); a plurality of feeding ports (11) with handles (1101) are evenly arranged in the cylindrical ring beam (8) and the template device (9), a clamping plate (1102) is arranged on the side wall of the feeding port (11), a steel seal (1103) is installed on the feeding port (11), a reinforcement ring (1104) is arranged on the outer periphery of the feeding port (11), and an L-shaped pressure plate (1105) is symmetrically arranged on the reinforcement ring (1104).
4. The full-circle synchronous lining trolley for TBM tunnel construction according to claim 3, characterized in that: The steel bar trolley (17) includes a steel bar trolley gantry (1701) mounted outside the needle beam (12), and a telescopic working platform (1705) is provided on both sides of the steel bar trolley gantry (1701); horizontal rollers B (1703) and vertical limiting wheels B (1704) are provided between the steel bar trolley gantry (1701) and the needle beam (12) and at the four corners; a ventilation hose passage (1702) is provided on the steel bar trolley gantry (1701), and a ventilation hose (2) is provided in the ventilation hose passage (1702).
5. The TBM tunnel full-circle synchronous lining trolley according to claim 4, characterized in that: The maintenance trolley (18) includes a maintenance trolley door frame (1803) which is sleeved on the outside of the needle beam (12), and horizontal rollers C (1806) and vertical limiting wheels C (1807) are provided between the maintenance trolley door frame (1803) and the needle beam (12) and at the four corners; an air film maintenance cover (1805) is provided on the maintenance trolley door frame (1803), and the air film maintenance cover (1805) is supported on the maintenance trolley door frame (1803) through an annular square steel frame (1802), and the air film maintenance cover (1805) is provided along the inner surface of the lining, and the air film maintenance cover (1805) is provided as an air film cylindrical structure, and air film plugs (1804) are provided at both ends of the air film maintenance cover (1805); a spray device (1801) is provided on one side of the maintenance trolley door frame (1803).
6. The TBM tunnel full-circle synchronous lining trolley according to claim 5, characterized in that: The shifting device (15) includes an upper rack (1502) and a lower rack (1503) respectively arranged on the upper and lower surfaces of the needle beam (12), and two upper racks (1502) and two lower racks (1503) are symmetrically arranged. A hydraulic motor (1504) is arranged on the inner wall of the steel bar trolley gantry (1701), the lining trolley gantry (702) and the maintenance trolley gantry (1803) at a position corresponding to the upper rack (1502) and the lower rack (1503), and a gear (1501) is connected to the hydraulic motor (1504).
7. The TBM tunnel full-circle synchronous lining trolley according to claim 6, characterized in that: The bottom support A (20) comprises a telescopic oil cylinder A (2001) arranged at both ends of the bottom of the reinforcement trolley portal frame (1701) and the lining trolley portal frame (702), and a support block A (2002) is arranged at the other end of the telescopic oil cylinder A (2001); the bottom support B (1203) comprises a telescopic oil cylinder B (1204) arranged at both ends of the bottom of the needle beam (12), and a support block B (1205) is arranged at the other end of the telescopic oil cylinder B (1204); the anti-floating support (701) comprises a telescopic oil cylinder C (705) arranged at both ends of the top of the lining trolley portal frame (702), and a support block C (706) is arranged at the other end of the telescopic oil cylinder C (705).
8. The full-circle synchronous lining trolley for TBM tunnel construction according to claim 7, characterized in that: The lifting device (16) comprises a hanging rail (1601) symmetrically arranged below the top of the needle beam (12), and a crane (1602) is slidably arranged on the hanging rail (1601).
9. The TBM construction tunnel full circle synchronous lining trolley as claimed in claim 8, characterized in that: A bracket (301) is provided on one side of the lining trolley portal frame (702) and the maintenance trolley portal frame (1803), and a supporting roller (302) and a vertical limiting roller (303) are provided on the bracket (301).
10. The TBM tunnel full-circle synchronous lining trolley according to claim 9, characterized in that: A support frame (401) is provided on one side outer wall of the reinforcement trolley gantry (1701), the lining trolley gantry (702) and the maintenance trolley gantry (1803), and a cable sliding channel (402) is provided on the support frame (401); a tunnel wall cable (4) is provided on one side of the tunnel, and a continuous belt conveyor (3) is provided on the tunnel wall and at a position opposite to the tunnel wall cable (4).
11. A method for constructing a full-circle synchronous lining of a TBM-constructed tunnel using the full-circle synchronous lining trolley for TBM-constructed tunnel according to any one of claims 1 to 10, characterized in that: The method comprises the following steps: 1) moving the front floating Y-type turnout forward; 2) removing the original track under the turnout and simultaneously cleaning the tunnel bottom; 3) moving the needle beam forward; 4) installing the rear track; 5) moving the rear floating Y-type turnout forward; 6) moving the steel bar trolley forward and installing the steel bar; 7) moving the lining trolley and the maintenance trolley forward and simultaneously maintaining the rear lining; 8) lining construction.
12. The TBM tunnel full-circle synchronous lining construction method according to claim 11, characterized in that: In the step 8), the lining trolley (7) is moved to the lining pouring position, the bottom support A (20) and the anti-floating support (701) are adjusted, and the lining trolley (7) is put into place; the air bag (904) is inflated to the specified value from bottom to top, so that the air bag (904) panel expands to the designed lining surface, the inflation valve (903) is closed to maintain pressure, and then the lining end is sealed, and the lining concrete is poured from the feeding port (11) from bottom to top. When the lining concrete pouring surface is almost at the feeding port (11), the steel seal (1103) is installed, and the feeding port (11) is sealed using the L-shaped pressure plate (1105) and the steel seal (1103), and the concrete is continued to be poured from the upper feeding port (11) until the lining pouring is completed; after the lining concrete pouring is completed, when the concrete strength reaches the specified value, all the steel seals (1103) are removed, and each is opened from top to bottom. The inflation valve (903) of the airbag (904) releases the air in the airbag (904), and the feeding port (11) is pulled back and fixed, and then the air in the airbag (904) is completely exhausted by using the vacuum pump. The airbag (904) is retracted, compressed and adsorbed on the cylindrical ring beam (8), and the trolley demoulding is completed at this time; the bottom support B (1203) at the bottom of the needle beam (12) is retracted, so that the needle beam (12) falls on the roller at the bottom of the lining trolley (7), and the needle beam (12) is moved forward by rotating the hydraulic motor (1504). After the needle beam (12) moves into place, the bottom supports B (1203) at both ends of the needle beam (12) are lowered to support the needle beam (12), and the lining trolley (7) is lifted on the needle beam (12), and the hydraulic motor (1504) set on the lining trolley (7) is started to move the lining trolley (7) forward to the next lining construction position.
13. The TBM tunnel full-circle synchronous lining construction method according to claim 12, wherein: In step 6) and step 7), the movement method of the steel bar trolley (17) and the maintenance trolley (18) is the same as that of the lining trolley (7) in step 8).
14. The TBM tunnel full-circle synchronous lining construction method according to claim 13, wherein: In the step 7), when the lining trolley (7) moves forward, the ventilation hose (2) is untied from the tunnel arch in the forward direction of the trolley. As the trolley moves, the ventilation hose (2) in the forward direction is retracted and sleeved on the flat barrel-shaped hard air duct (201). The ventilation hose (2) sleeved on the end of the flat barrel-shaped hard air duct (201) is pulled out from the rear of the trolley and re-suspended on the wire rope of the tunnel arch. After the trolley moves into place, the ventilation hose (2) is fastened and fixed to the flat barrel-shaped hard air duct (201) using a fastening tie, and normal ventilation can be restored. If the ventilation efficiency is low, a pressurized fan is added to the flat barrel-shaped hard air duct (201) to assist ventilation.
Citation Information
Patent Citations
Inverted arch synchronous lining trolley for TBM construction and inverted arch synchronous lining construction method
CN114233331A
Inverted arch lining trolley and synchronous tunnel operating system
CN203809016U