Steel tower circumferential joint construction platform
By designing a combination of main hanging basket, tail hanging basket, slide and guardrail, the problems of low construction efficiency and insufficient safety caused by the change of steel tower cross-section were solved, and efficient and stable support and safe operation of variable cross-section steel tower were achieved.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-29
- Publication Date
- 2026-03-06
AI Technical Summary
Existing circumferential joint construction platforms cannot adapt to changes in the cross-sectional size of steel towers, resulting in low construction efficiency and insufficient safety.
A steel tower circumferential joint construction platform was designed, comprising a main hanging basket, a tail hanging basket, a slide, and guardrails. The main hanging basket is fixed to the steel tower, the tail hanging basket is connected to the main hanging basket, the slide is slidable, and guardrails are set on the inner and outer sides to form a U-shaped corridor. Stable support and convenient movement are achieved through tie rods and pulleys.
This improves the adaptability and safety of steel tower construction, ensuring that workers can stably support and safely operate the tower when its cross-section changes.
Smart Images

Figure CN116623558B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of bridge construction platform technology, and in particular to a steel tower circumferential joint construction platform. Background Technology
[0002] Modern bridges, while prioritizing practicality, also place great emphasis on aesthetics. The main bridge towers employ a teardrop-shaped steel-concrete composite structure, with the lower tower column made of concrete and the upper tower column of steel. A steel-concrete joint connects the upper and lower tower columns. During construction of the upper tower column's steel structure, a construction platform was required. However, the cross-sectional size of the steel tower varies, and existing circumferential joint construction platforms could not accommodate the changing cross-section of the steel tower. Summary of the Invention
[0003] The purpose of this application is to provide a steel tower circumferential joint construction platform, which can improve the construction efficiency and safety of variable cross-section steel towers.
[0004] Other features and advantages of this application will become apparent from the following detailed description, or may be learned in part from practice of this application.
[0005] According to one aspect of the embodiments of this application, a steel tower circumferential joint construction platform is provided. The steel tower circumferential joint construction platform includes a main hanging basket, a tail hanging basket, a slide, and a guardrail. The main hanging basket surrounds the steel tower and is fixed to the steel tower, and is used to support workers to work on the steel tower. The tail hanging basket is connected to the main hanging basket and is used to support workers to work on the steel tower. The slide is disposed on the tail hanging basket and can slide along the tail hanging basket. The slide and the main hanging basket surround the steel tower. The guardrail is disposed on the inner and outer sides of the main hanging basket and the tail hanging basket. The main hanging basket, the tail hanging basket, and the guardrail surround the steel tower to form a U-shaped corridor for workers to walk through.
[0006] In one embodiment of this application, based on the aforementioned scheme, a tie rod is provided between the main hanging basket and the steel tower, main hanging ears are distributed on the inner side of the main hanging basket, and auxiliary hanging ears are provided on the steel tower at positions corresponding to the main hanging ears. One end of the tie rod is connected to the main hanging ear, and the other end of the tie rod is connected to the auxiliary hanging ear.
[0007] In one embodiment of this application, based on the aforementioned scheme, the angle between the pull rod and the horizontal plane is 60-70°.
[0008] In one embodiment of this application, based on the aforementioned scheme, a plurality of pulleys are provided on the inner side of the main hanging basket, and the pulleys are used to slide up and down the steel tower when the main hanging basket is hoisted.
[0009] In one embodiment of this application, based on the aforementioned scheme, the pulley is an industrial pulley with a diameter of 130-160mm, a thickness of 60-70mm, and a load capacity of 50-60kg.
[0010] In one embodiment of this application, based on the aforementioned scheme, the main hanging basket includes a first hanging basket layer and a second hanging basket layer, a connecting member is provided between the first hanging basket layer and the second hanging basket layer, and the pulley is disposed on the inner side of the first hanging basket layer and the second hanging basket layer.
[0011] In one embodiment of this application, based on the aforementioned scheme, the first hanging basket layer is located above the second hanging basket layer in terms of horizontal height, and the first hanging basket layer extends outward to form the second hanging basket layer. The first hanging basket layer is used to support workers operating on the steel tower.
[0012] In one embodiment of this application, based on the foregoing scheme, the angle between the plane where the main hanging basket is located and the plane where the tail hanging basket is located is 20-30°.
[0013] In one embodiment of this application, based on the aforementioned scheme, an anti-slip layer is provided on the upper surface of the first hanging basket layer.
[0014] In one embodiment of this application, based on the aforementioned scheme, the anti-slip layer includes a plurality of angle irons, and the plurality of angle irons are evenly distributed on the first hanging basket layer.
[0015] In the technical solution of this application embodiment, the main hanging basket is lifted to a suitable position on the steel tower by a crane and fixed to the steel tower. The steel tower's cross-section changes direction, and the main hanging basket slides towards the main hanging basket via a slide at the rear. The main hanging basket and the slide encircle the steel tower, forming stable support for the workers. This design can be used when the steel tower's cross-section changes continuously in a certain direction, improving the installation adaptability of the main hanging basket. Simultaneously, guardrails are installed on the inner and outer sides of the main hanging basket and the rear hanging basket. The main hanging basket, the rear hanging basket, and the guardrails form a U-shaped corridor for workers to walk through, effectively ensuring their operational safety.
[0016] It should be understood that the above general description and the following detailed description are exemplary and explanatory only, and do not limit this application. Attached Figure Description
[0017] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0018] Figure 1This is a structural schematic diagram of a steel tower circumferential joint construction platform according to an embodiment of this application;
[0019] Figure 2 This is a schematic cross-sectional view of the installation of the steel tower circumferential joint construction platform according to an embodiment of this application;
[0020] Figure 3 This is a front view of the steel tower circumferential joint construction platform shown according to an embodiment of this application;
[0021] Figure 4 This is a schematic diagram illustrating the installation of a steel tower circumferential joint construction platform according to an embodiment of this application;
[0022] Figure 5 This is a schematic diagram of the tie rod installation of a steel tower circumferential joint construction platform according to an embodiment of this application.
[0023] Attached reference numerals: 10, main hanging basket; 101, first hanging basket layer; 102, second hanging basket layer; 11, pulley; 12, main hanging lug; 20, tail hanging basket; 30, slide; 40, guardrail; 50, anti-slip layer; 60, tie rod; 70, steel tower; 71, auxiliary hanging lug. Detailed Implementation
[0024] Exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, these exemplary embodiments can be implemented in many forms and should not be construed as limited to the examples set forth herein; rather, these embodiments are provided to make this application more comprehensive and complete, and to fully convey the concept of the exemplary embodiments to those skilled in the art.
[0025] It should be noted that "multiple" in this article refers to two or more. "And / or" describes the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can represent: A alone, A and B simultaneously, or B alone. The character " / " generally indicates that the preceding and following related objects have an "or" relationship.
[0026] The implementation details of the technical solutions in the embodiments of this application are described in detail below:
[0027] First, it should be noted that the steel tower circumferential joint construction platform proposed in this application can be applied to the field of bridge construction platform technology. For example, for novel teardrop-shaped steel-concrete composite towers, the cross-sectional size of the steel tower varies. Existing steel tower circumferential joint construction platforms cannot change according to the cross-sectional size of the steel tower. Therefore, it is particularly important that the steel tower circumferential joint construction platform can adjust its distance from the steel tower according to the change in the cross-section of the steel tower.
[0028] According to one aspect of this application, a steel tower circumferential joint construction platform is provided. Figure 1This is a structural schematic diagram of a steel tower circumferential joint construction platform according to an embodiment of this application. Figure 2 This is a schematic cross-sectional view of the installation of the steel tower circumferential joint construction platform according to an embodiment of this application. Figure 3 This is a front view of the steel tower circumferential joint construction platform shown according to an embodiment of this application. Figure 4 This is a schematic diagram illustrating the installation of a steel tower circumferential joint construction platform according to an embodiment of this application. Figure 5 The following is a detailed description of the tie rod installation of the steel tower circumferential joint construction platform according to an embodiment of this application:
[0029] Please refer to Figures 1-4 According to one aspect of the embodiments of this application, a steel tower circumferential joint construction platform is provided. The steel tower circumferential joint construction platform includes a main hanging basket 10, a tail hanging basket 20, a slide 30, and a guardrail 40. The main hanging basket 10 surrounds the steel tower 70 and is fixed to the steel tower 70. The main hanging basket 10 is used to support workers to work on the steel tower 70. The tail hanging basket 20 is connected to the main hanging basket 10 and is used to support workers to work on the steel tower 70. The slide 30 is disposed on the tail hanging basket 20 and can slide along the tail hanging basket 20. The slide 30 and the main hanging basket 10 surround the steel tower 70. The guardrail 40 is disposed on the inner and outer sides of the main hanging basket 10 and the tail hanging basket 20. The main hanging basket 10, the tail hanging basket 20, and the guardrail 40 surround the steel tower 70 to form a U-shaped corridor for workers to walk on.
[0030] In this application, the main hanging basket 10 and the tail hanging basket 20 are used to support workers standing during construction. To accommodate changes in the cross-section of the steel tower 70, the slides 30 of the main hanging basket 10 and the tail hanging basket 20 can surround the steel tower 70 to form a stable support. Furthermore, through the guardrails 40 installed on the main hanging basket 10 and the tail hanging basket 20 respectively, the main hanging basket 10, the tail hanging basket 20, and the guardrails 40 form a U-shaped corridor, allowing workers to safely perform construction within this corridor. When the cross-section of the steel tower 70 changes, the slides 30 are first moved away from the main hanging basket 10. After the main hanging basket 10 is raised to the corresponding height using a crane, it is fixed to the steel tower 70. Then, the slides 30 slide towards the main hanging basket 10, with the main hanging basket 10 and the slides 30 surrounding the steel tower 70. This effectively improves the adaptability of the steel tower circumferential joint construction platform to variable cross-section steel towers 70.
[0031] It should be emphasized that the main hanging basket 10 and the tail hanging basket 20 brackets can be connected by bolts, which facilitates assembly and disassembly.
[0032] Please refer to Figure 5 In one embodiment of this application, a tie rod 60 is provided between the main hanging basket 10 and the steel tower 70. Main hanging ears 12 are distributed on the inner side of the main hanging basket 10, and auxiliary hanging ears 71 are provided on the steel tower 70 at the corresponding positions of the main hanging ears 12. One end of the tie rod 60 is connected to the main hanging ear 12, and the other end of the tie rod 60 is connected to the auxiliary hanging ear 71.
[0033] In this application, the main hanging ear 12 of the main hanging basket 10 and the auxiliary hanging ear 71 of the steel tower 70 are fixed by a tie rod 60. The tie rod 60 is connected to the main hanging ear 12 and the auxiliary hanging ear 71 respectively by a cotter pin. The tie rod 60 is firmly connected and easy to disassemble, which improves the convenience of moving the main hanging basket 10.
[0034] In one embodiment of this application, the angle between the pull rod 60 and the horizontal plane is 60-70°.
[0035] When the angle between the tie rod 60 and the horizontal plane is 60-70°, the tie rod 60 is subjected to uniform force, the tie rod 60 exerts sufficient tension on the main hanging basket 10, and the stability between the steel tower 70 and the main hanging basket 10 is strong, effectively ensuring the construction safety of the workers.
[0036] In one embodiment of this application, a plurality of pulleys 11 are provided on the inner side of the main hanging basket 10, and the pulleys 11 are used to slide up and down the steel tower 70 when the main hanging basket 10 is hoisted.
[0037] In this application, when the main hanging basket 10 is moved relative to the steel tower 70, it is lifted by a crane. The main hanging basket 10 and the steel tower 70 are subjected to rolling friction through pulleys 11, which reduces the wear of the main hanging basket 10 on the steel tower 70 and improves the moving efficiency of the main hanging basket 10.
[0038] In one embodiment of this application, the pulley 11 is an industrial pulley 11 with a diameter of 130-160mm, a thickness of 60-70mm, and a load capacity of 50-60kg.
[0039] In this application, the pulley 11 has a diameter of 130-160mm, a thickness of 60-70mm, and a load capacity of 50-60kg. The specifications of the pulley 11 determine its load-bearing capacity, and the large contact surface between the pulley 11 and the steel tower 70 effectively reduces damage to the steel tower 70 when the main hanging basket 10 moves.
[0040] Please refer to Figure 3 In one embodiment of this application, the main hanging basket 10 includes a first hanging basket layer 101 and a second hanging basket layer 102, a connecting member is provided between the first hanging basket layer 101 and the second hanging basket layer 102, and a pulley 11 is provided on the inner side of the first hanging basket layer 101 and the second hanging basket layer 102.
[0041] In this application, the first hanging basket layer 101 and the second hanging basket layer 102 are connected and fixed by connectors, which can be steel bars, steel pipes, or angle iron. The first hanging basket layer 101 and the second hanging basket layer 102 have a certain height, ensuring sufficient contact area between the main hanging basket 10 and the steel tower 70, making it easier for the main hanging basket 10 to maintain stability after fixation. Furthermore, the layered, perforated structure effectively reduces the weight of the main hanging basket 10 itself, lowering the pressure exerted by the main hanging basket 10 on the steel tower 70.
[0042] In one embodiment of this application, the first hanging basket layer is located above the second hanging basket layer 102 in terms of horizontal height, and the first hanging basket layer 101 extends outward from the second hanging basket layer 102. The first hanging basket layer 101 is used to support workers to operate on the steel tower 70.
[0043] In this application, the spatial positions of the first hanging basket layer 101 and the second hanging basket layer 102 are staggered. While ensuring the safety of construction workers, the materials of the second hanging basket layer 102 are saved, the cost is reduced, and the overall weight of the main hanging basket 10 is reduced, thus reducing the pressure of the main hanging basket 10 on the steel tower 70.
[0044] In one embodiment of this application, the angle between the plane where the main hanging basket 10 is located and the plane where the tail hanging basket 20 is located is 20-30°.
[0045] In this application, due to the structural influence of the teardrop-shaped steel tower 70 itself, after the main hanging basket 10 is fixed to the steel tower 70, the main hanging basket 10 is not placed horizontally. The angle between the plane where the main hanging basket 10 is located and the plane where the tail hanging basket 20 is located is 20-30°. The tail hanging basket 20 is basically parallel to the horizontal plane, which facilitates the construction convenience of the staff on the tail hanging basket 20.
[0046] In one embodiment of this application, an anti-slip layer 50 is provided on the upper surface of the first hanging basket layer 101.
[0047] In this application, due to the structural influence of the teardrop-shaped steel tower 70 itself, after the main hanging basket 10 is fixed to the steel tower 70, the main hanging basket 10 is not placed horizontally, that is, the first hanging basket layer 101 has a certain angle with the horizontal plane. The anti-slip layer 50 can improve the stability of the workers when standing on the first hanging basket layer 101 and improve the safety of the workers during construction.
[0048] In one embodiment of this application, the anti-slip layer 50 includes a plurality of angle irons, which are evenly distributed on the first hanging basket layer 101.
[0049] In this application, the angle irons are staggered and irregular, which can play a good anti-slip role, and the angle irons can also play a reinforcing role, providing stability to the first hanging basket layer 101.
[0050] Please refer to Figure 4This application has been applied to the construction of the teardrop-shaped steel-concrete composite tower of the Ziyun Bridge, which has effectively improved the construction efficiency of the teardrop-shaped steel-concrete composite tower and ensured the safety of construction personnel.
[0051] In the technical solution of this application embodiment, the main hanging basket 10 is lifted to a suitable position on the steel tower 70 by a crane, and the main hanging basket is fixed to the steel tower 70. The cross-section of the steel tower 70 changes direction and slides to the main hanging basket 10 via the slide 30 of the tail hanging basket 20. The main hanging basket 10 and the slide 30 surround the steel tower 70, forming a stable support for the workers. This can be applied to situations where the cross-section of the steel tower 70 changes continuously in a certain direction, improving the installation adaptability of the main hanging basket 10. At the same time, guardrails 40 are set on the inner and outer sides of the main hanging basket 10 and the tail hanging basket 20. The main hanging basket 10, the tail hanging basket 20 and the guardrails 40 form a U-shaped corridor for workers to walk through, effectively ensuring the operational safety of the workers.
[0052] It should be understood that this application is not limited to the precise structures described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from its scope. The scope of this application is limited only by the appended claims.
Claims
1. A steel tower girth weld construction platform, characterized by, The utility model relates to a steel tower ring seam construction platform, comprising: a main hanging basket, which is arranged around the steel tower and fixed to the steel tower, and is used for supporting workers to work on the steel tower; a tail hanging basket, which is connected to the main hanging basket and is used for supporting workers to work on the steel tower; a slide, which is arranged on the tail hanging basket and can slide along the tail hanging basket, and is arranged around the steel tower together with the main hanging basket; a guardrail, which is arranged on the inner side and the outer side of the main hanging basket and the tail hanging basket, and forms a U-shaped corridor for the workers to walk around the steel tower together with the main hanging basket, the tail hanging basket and the guardrail; the main hanging basket comprises a first hanging basket layer and a second hanging basket layer, and a connecting piece is arranged between the first hanging basket layer and the second hanging basket layer; the first hanging basket layer and the second hanging basket layer have a certain height; the angle between the plane of the main hanging basket and the plane of the tail hanging basket is 20-30°; a pull rod is arranged between the main hanging basket and the steel tower, main hanging ears are arranged on the inner side of the main hanging basket, vice hanging ears are arranged at positions corresponding to the main hanging ears on the steel tower, one end of the pull rod is connected to the main hanging ear, and the other end of the pull rod is connected to the vice hanging ear; the angle between the pull rod and the horizontal plane is 60-70°.
2. The steel tower ring seam construction platform according to claim 1, wherein a plurality of pulleys are arranged on the inner side of the main hanging basket, and the pulleys are used for sliding on the steel tower when the main hanging basket is hoisted.
3. The steel tower ring seam construction platform according to claim 2, wherein the pulleys are industrial pulleys, the diameter of the pulleys is 130-160 mm, the thickness of the pulleys is 60-70 mm, and the load of the pulleys is 50-60 kg.
4. The steel tower ring seam construction platform according to claim 3, wherein the pulleys are arranged on the inner side of the first hanging basket layer and the second hanging basket layer.
5. The steel tower ring seam construction platform according to claim 4, wherein the first hanging basket layer is located above the second hanging basket layer in the horizontal height, the first hanging basket layer extends outward beyond the second hanging basket layer, and the first hanging basket layer is used for supporting workers to work on the steel tower.
6. The steel tower ring seam construction platform according to any one of claims 4 or 5, wherein an anti-slip layer is arranged on the upper surface of the first hanging basket layer.
7. The steel tower ring seam construction platform according to claim 6, wherein the anti-slip layer comprises a plurality of angle irons, and the plurality of angle irons are uniformly distributed on the first hanging basket layer.
Citation Information
Patent Citations
Construction method of in-air connection universal mobile platform of curved surface leaning tower
CN104499432A
Climbing-up type platform device for torsional special-shaped continuous variable cross-section steel tower structures
CN111691661A
Bridge pier column construction step ladder attachment device
CN115075136A