A composite top hugging and pressing integrated static pressure pile construction equipment and construction method

Through the integrated static pressing pile construction equipment of composite top pressing, the problems of insufficient clamping force and adaptive construction of static pressing pile equipment are solved, efficient pressing and low clearance construction of steel pipe piles are achieved, and construction efficiency and space utilization are improved.

CN117188455BActive Publication Date: 2025-07-22CHINA ACAD OF BUILDING RES +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202311240265.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-25
Publication Date
2025-07-22
Estimated Expiration
2043-09-25

AI Technical Summary

Technical Problem

Existing static pile equipment is prone to pulling when the clamping force is insufficient, and it cannot be adaptively constructed according to the diameter of the pile body, resulting in low construction efficiency and requiring coordinated operation of large-scale machinery, which makes the space use insufficient.

Method used

The integrated static pressure pile construction equipment of composite top-held pressing is adopted. Through the design of moving components, tightening components and chain rails, the adaptive clamping and pressing of steel pipe piles is achieved, and the frame system provides a stressed frame for low clearance construction.

Benefits of technology

It realizes efficient pressing of steel pipe piles, adapts to different pipe diameters, reduces construction time, avoids dependence on large machinery, and improves construction efficiency and space utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117188455B_ABST
    Figure CN117188455B_ABST
Patent Text Reader

Abstract

The present invention discloses a composite top hugging and pressing integrated static pressure pile construction device, which includes a moving component slidably connected to a guide rod at the middle of a frame system, a top pressing oil cylinder component detachably connected to a top plate component at the top of the frame system, a hugging component connected to the inner side of the moving component, a hugging adjusting oil cylinder component and a hugging cover plate connected below the hugging component, a crawler connected to the moving component, and a top pressing plate correspondingly connected to the top of the crawler. Through the setting of the moving component in the present invention, it is beneficial to clamp the inclined block component and ensure the downward pressing of the steel pipe pile; through the setting of the hugging component, it is beneficial to ensure hugging of steel pipe piles with different diameters; and through the setting of the inclined pressing block and cooperation with the moving body, it presses downward while hugging the steel pipe pile; through the setting of the chain ear plate and the crawler, the steel pipe pile can be further pressed downward through the crawler; through the setting of the frame system, it is beneficial to form a force-bearing frame to provide a site for pressing, and installation and construction can be carried out with a low clearance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of pile construction, and particularly relates to a composite top-holding and pressing integrated static pressure pile construction equipment and construction method. Background Art

[0002] The existing foundation reinforcement is a technical requirement widely applied in the domestic and foreign construction industries in recent years. When carrying out foundation treatment under an existing building, not only should the foundation bearing capacity of the original building be improved by means such as pile driving, but also it is necessary to ensure that during construction, the soil body is not disturbed and the bearing capacity of the original building is not reduced. When constructing in the underground space of an existing building, due to the limitation of space size, the construction equipment cannot be made very large. However, the diameter requirements of the pile holes are getting larger and the construction depth is getting deeper, which requires very high requirements for mechanical equipment, otherwise construction cannot be carried out. When the existing static pressure pile equipment clamps the drilling tool and presses it into the ground, the clamping force is often insufficient, resulting in the phenomenon of pulley, and repeated clamping and pressing are required, increasing the construction time and reducing the efficiency; there are also equipment that can be used for both top pressing and holding pressing, which requires the combined action of large machinery such as large spaces, gantry cranes and cranes; moreover, it cannot carry out adaptive construction according to the size of the pile body diameter. Summary of the Invention

[0003] The present invention provides a composite top-holding and pressing integrated static pressure pile construction equipment and construction method to solve technical problems such as the adaptive clamping, holding and pressing integration design of steel pipe piles and the overall combined top pressing design.

[0004] To achieve the above object, the present invention adopts the following technical solutions:

[0005] A composite top-holding and pressing integrated static pressure pile construction equipment includes a frame system formed by a bottom plate assembly, a guide rod and a top plate assembly, a moving assembly slidably connected to the guide rod in the middle of the frame system, a top pressing oil cylinder assembly detachably connected to the top plate assembly at the top of the frame system, a holding assembly connected to the inner side of the moving assembly, a holding adjustment oil cylinder assembly and a holding cover plate connected below the holding assembly, a chain track connected to the moving assembly, and a top pressing plate correspondingly connected to the top of the chain track;

[0006] The moving assembly includes a moving main body, a moving sleeve connecting piece integrally connected to the outside of the moving main body and sleeved on the guide rod, and a moving top connecting piece connected to the top of the moving main body; the moving main body is an annular piece, and a frustum-shaped hole is provided inside the annular piece, and the vertical section of the frustum-shaped hole is a trapezoid with a smaller upper part and a larger lower part;

[0007] The clamping assembly includes a set of inclined pressure blocks corresponding to the moving body, an inclined pressure block bottom plate connected to the lower part of the inclined pressure blocks, inclined pressure block connecting holes arranged on the bottom surface of the inclined pressure bottom plate, an inclined pressure block gap arranged between the set of inclined pressure blocks, and an inclined pressure pipe-clamping hole formed by the inner sides of the set of inclined pressure blocks; the inclined pressure pipe-clamping hole corresponds to the connection of the steel pipe pile; the inclined pressure block connecting holes correspond to the connection with the clamping adjustment oil cylinder assembly;

[0008] The inclined pressure blocks are arc-shaped fan-shaped sheets, and there is an inclined pressure block gap between the set of inclined pressure blocks, and the outer side surfaces of the inclined pressure blocks enclose a frustum shape corresponding to the frustum-shaped hole of the moving body.

[0009] Further, for the base, the bottom plate assembly includes two parallel bottom longitudinal plates and a bottom transverse plate vertically connected between the bottom longitudinal plates, and the long ends of the bottom longitudinal plates are connected to the base through anchor bolts.

[0010] Further, the guide rod includes a rod body and a fixing nut connected to the top of the rod body, and there are four rod bodies arranged in a rectangle; the bottom of the rod body is fixedly connected to the bottom transverse plate.

[0011] Further, the top plate assembly includes a top main plate and top plate connecting ears connected to the side edges of the top main plate, and the top plate connecting ears are arranged in an X shape; the top plate connecting ears correspond to the guide rods, and fixing nuts are detachably connected to the top and bottom of the top plate connecting ears respectively;

[0012] Grooves for installing the top pressing oil cylinder assembly are symmetrically arranged on the top main plate.

[0013] Further, the moving sleeve connecting part is a C-shaped part, the vertical part is a sleeve-shaped socket for the rod body, and the two parallel horizontal parts are integrally connected to the moving body;

[0014] The moving top connecting part is an inverted T-shaped part, the horizontal part is pin-connected to the moving body, and the vertical part corresponds to the connection of the top pressing oil cylinder assembly;

[0015] The bottom of the moving body is pin-connected to the clamping cover plate, and a groove for installing the clamping adjustment oil cylinder assembly is also arranged on the clamping cover plate.

[0016] Further, there are four inclined pressure blocks, and a cross-shaped inclined pressure block gap is arranged between the four inclined pressure blocks; the bottoms of the four inclined pressure blocks are fixedly connected to a circular inclined pressure block bottom plate.

[0017] Further, two chain ear plates are arranged in the vertical direction of the connection line of the two top pressing oil cylinder assemblies; a chain track is detachably connected to the chain ear plates; a top pressing plate is movably connected corresponding to the top of the chain track.

[0018] Further, a construction method of a composite top-clamping and pressing integrated static pile driving construction equipment is as follows:

[0019] Step 1: First, form a framework with the bottom plate assembly, top plate assembly, and guide rods. Among them, the bottom longitudinal plate is connected to the base through anchor bolts; the guide rods are fixed on the bottom transverse plate and the top plate assembly is adjusted and fixed through fixing nuts;

[0020] Step 2: Slide and install a moving assembly on the guide rods in advance, and install a top pressing oil cylinder assembly on the top plate assembly; among them, the top pressing oil cylinder assembly includes a clamping oil cylinder installed on the top main plate and a clamping oil cylinder piston rod extending from the bottom of the clamping oil cylinder; the clamping oil cylinder piston rod is correspondingly connected to the top groove of the moving top connecting part;

[0021] Step 3: Install a clamping assembly inside the moving body and install a clamping cover plate at the bottom of the moving body. Among them, a clamping adjustment oil cylinder assembly is pre-installed on the clamping cover plate; the clamping adjustment oil cylinder assembly includes a clamping oil cylinder installed in the groove of the clamping cover plate and a clamping oil cylinder piston rod extending from the top of the clamping oil cylinder; the clamping oil cylinder piston rod is correspondingly connected to the inclined pressure block connecting hole;

[0022] Step 4: Then drive the clamping oil cylinder to move up and down to drive the inclined pressure block to move; provide a horizontal component force through the inclined surface of the inclined pressure block and at the same time close the divided inclined pressure blocks towards the center to clamp the steel pipe pile; then drive the top pressing main oil cylinder, and the moving assembly drives the inclined block assembly to act together to press the steel pipe pile into the ground;

[0023] Step 5: At the same time, place a top pressing plate on the top of the steel pipe pile, and connect the top pressing plate and the moving body with a segmented spliced track chain; when the moving body presses the steel pipe pile downward, the track chain pulls the top pressing plate to press the steel pipe pile into the ground at the same time. The top pressing main oil cylinder acts for one stroke, and one segment of the track chain is removed. Repeat this process until the steel pipe pile is completely pressed into the ground and the construction is completed.

[0024] Furthermore, the inclined pressure block is equally divided into several segments according to the diameter of the steel pipe pile, and there is enough gap between adjacent segments; stress measurement points are arranged on the inner side of the inclined pressure block, and stress sensors and strain sensors are arranged at the stress measurement points; the stress and strain data of the stress measurement points are connected to the control terminal in real time; by setting the stress and strain, the up and down movement of the clamping oil cylinder is controlled to meet the design requirements for clamping the steel pipe pile.

[0025] Furthermore, during the process of pressing the steel pipe pile downward, the clamping assembly is driven reciprocally to clamp or loosen the steel pipe pile, and cooperate with the downward movement of the top pressing oil cylinder assembly and the disassembly and assembly of the track chain, so as to continuously press the steel pipe pile without replacing the clamping assembly until the pressing length of the steel pipe pile reaches the design requirements.

[0026] The beneficial effects of the present invention are reflected in:

[0027] 1) Through the setting of the moving assembly, on the one hand, the downward pressing of the moving assembly is beneficial to clamping the inclined block assembly, and on the other hand, it cooperates with the top pressing oil cylinder assembly to ensure the downward pressing of the steel pipe pile;

[0028] 2) The present invention, through the setting of the clamping assembly, is conducive to ensuring the clamping of steel pipe piles with different pipe diameters; and through the setting of the inclined pressing block, it cooperates with the moving body to press down while clamping the steel pipe pile.

[0029] 3) The present invention, through the setting of the chain ear plate and the chain track, can further press the steel pipe pile downward through the chain track.

[0030] 4) The present invention, through the combined setting of the bottom plate assembly, the guide rod and the top plate assembly, etc., is conducive to forming a force-bearing framework to provide a site for the pressing-in, and can be installed and constructed with a low clearance.

[0031] Other features and advantages of the present invention will be described in the subsequent specification, and will be partially obvious from the specification, or understood by implementing the present invention; the main purpose and other advantages of the present invention can be achieved and obtained through the solutions specifically pointed out in the specification. Brief Description of the Drawings

[0032] Figure 1 is the vertical section of the composite top-clamping and pressing integrated static pile construction equipment Figure 1 ;

[0033] Figure 2 is the partial schematic diagram of the composite top-clamping and pressing integrated static pile construction equipment;

[0034] Figure 3 is the vertical section schematic diagram of the structure of the clamping assembly;

[0035] Figure 4 is the top view of the clamping assembly;

[0036] Figure 5 is the vertical section of the composite top-clamping and pressing integrated static pile construction equipment Figure 2 ;

[0037] Figure 6 is the top view schematic diagram of the composite top-clamping and pressing integrated static pile construction equipment.

[0038] Reference Signs: 1 - Base, 2 - Anchor Bolt, 3 - Bottom Plate Assembly, 31 - Bottom Longitudinal Plate, 32 - Bottom Transverse Plate, 4 - Guide Rod, 41 - Rod Body, 42 - Fixed Nut, 5 - Top Plate Assembly, 51 - Top Main Plate, 52 - Top Plate Link Ear, 6 - Moving Assembly, 61 - Moving Body, 62 - Moving Sleeve Link, 63 - Moving Top Link, 7 - Clamping Assembly, 71 - Inclined Pressing Block, 72 - Inclined Pressing Block Bottom Plate, 73 - Inclined Pressing Block Connecting Hole, 74 - Inclined Pressing Block Gap, 75 - Inclined Pressing Pipe-Clamping Hole, 8 - Clamping Adjusting Oil Cylinder Assembly, 81 - Clamping Oil Cylinder, 82 - Clamping Oil Cylinder Piston Rod, 9 - Clamping Cover Plate, 10 - Top Pressing Oil Cylinder Assembly, 101 - Top Pressing Main Oil Cylinder, 102 - Top Pressing Oil Cylinder Piston Rod, 11 - Steel Pipe Pile, 12 - Top Pressing Plate, 13 - Chain Ear Plate, 14 - Chain Track. Specific embodiments

[0039] Taking the construction of a basement with low headroom and the driving of steel pipe piles as an example, as Figures 1 to 6 shown, the composite top hugging and pressing integrated static pile construction equipment includes a frame system formed by a bottom plate assembly 3, a guide rod 4, and a top plate assembly 5, a moving assembly 6 slidably connected to the guide rod 4 at the middle of the frame system, a top pressing oil cylinder assembly 10 detachably connected to the top plate assembly 5 at the top of the frame system, a hugging assembly 7 connected to the inner side of the moving assembly 6, a hugging adjustment oil cylinder assembly 8 and a hugging cover plate 9 connected below the hugging assembly 7, a track 12 connected to the moving assembly 6, and a top pressing plate 12 correspondingly connected to the top of the track 12.

[0040] In this embodiment, the moving assembly 6 includes a moving main body 61, a moving sleeve connecting member 62 integrally connected to the outer side of the moving main body 61 and sleeved on the guide rod 4, and a moving top connecting member 63 connected to the top of the moving main body 61; the moving main body 61 is a ring-shaped steel member, and a frustum-shaped hole is provided inside the ring member, and the vertical section of the frustum-shaped hole is a trapezoid with a smaller upper part and a larger lower part.

[0041] In this embodiment, the hugging assembly 7 includes a group of inclined pressing blocks 71 corresponding to the moving main body 61, an inclined pressing block bottom plate 72 connected to the lower part of the inclined pressing blocks 71, an inclined pressing block connecting hole 73 provided on the bottom surface of the inclined pressing bottom plate, an inclined pressing block gap 74 provided between a group of inclined pressing blocks 71, and an inclined pressing pipe hugging hole 75 surrounded by the inner sides of a group of inclined pressing blocks 71; the inclined pressing pipe hugging hole 75 is correspondingly connected to the steel pipe pile 11; the inclined pressing block connecting hole 73 is correspondingly connected to the hugging adjustment oil cylinder assembly 8; four inclined pressing blocks 71 are provided, and a cross-shaped inclined pressing block gap 74 is provided between the four inclined pressing blocks 71; the bottoms of the four inclined pressing blocks 71 are fixedly connected to a circular inclined pressing block bottom plate 72.

[0042] In this embodiment, the inclined pressing block 71 is an arc-shaped fan-shaped steel member, a group of inclined pressing blocks 71 are provided with an inclined pressing block gap 74 between each other, and the outer side surfaces of the inclined pressing blocks 71 enclose a frustum shape corresponding to the frustum-shaped hole of the moving main body 61.

[0043] In this embodiment, for the base 1 and the bottom plate assembly 3, it includes two parallel bottom longitudinal plates 31 and a bottom transverse plate 32 vertically connected between the bottom longitudinal plates 31, and the long ends of the bottom longitudinal plates 31 are connected to the base 1 through anchor bolts 2. Among them, both the bottom longitudinal plates 31 and the bottom transverse plate 32 are shaped steel plates.

[0044] In this embodiment, the guide rod 4 includes a steel rod body 41 and a fixing nut 42 connected to the top of the rod body 41, and four rod bodies 41 are provided and arranged in a rectangle; the bottom of the rod body 41 is fixedly connected to the bottom transverse plate 32.

[0045] In this embodiment, the top plate assembly 5 includes a top main plate 51 and top plate connecting ears 52 connected to the sides of the top main plate 51. The top plate connecting ears 52 are arranged in an X shape. The top plate connecting ears 52 are arranged corresponding to the guide rods 4, and fixing nuts 42 are detachably connected to the top and bottom of the top plate connecting ears 52 respectively. Grooves for installing the top pressing oil cylinder assembly 10 are symmetrically arranged on the top main plate 51. Among them, the top main plate 51 is a circular steel plate.

[0046] In this embodiment, the moving sleeve connecting part 62 is a C-shaped part. The vertical part is a sleeve-shaped socket rod body 41, and the two parallel horizontal parts are integrally connected to the moving body 61. The moving top connecting part 63 is an inverted T-shaped part. The horizontal part is pin-connected to the moving body 61, and the vertical part is correspondingly connected to the top pressing oil cylinder assembly 10. The bottom of the moving body 61 is pin-connected to the clamping cover plate 9, and a groove for installing the clamping adjusting oil cylinder assembly 8 is also arranged on the clamping cover plate 9.

[0047] In this embodiment, two chain ear plates 13 are arranged vertically on the vertical line connecting the two top pressing oil cylinder assemblies 10. A chain track 12 is detachably connected to the chain ear plates 13. The top of the chain track 12 is movably connected to a top pressing plate 12 correspondingly.

[0048] Combined Figures 1 to 6 As shown, a construction method of a composite top clamping and pressing integrated comprehensive static pressure pile construction equipment is as follows:

[0049] Step 1: First, form a framework with the bottom plate assembly 3, the top plate assembly 5 and the guide rods 4. Among them, the bottom longitudinal plate 31 is connected to the base 1 through anchor bolts 2. The guide rods 4 are fixed on the bottom transverse plate 32 and the top plate assembly 5 is adjusted and fixed through the fixing nuts 42.

[0050] Step 2: Slide and install the moving assembly 6 on the guide rods 4 in advance, and install the top pressing oil cylinder assembly 10 on the top plate assembly 5. Among them, the top pressing oil cylinder assembly 10 includes a clamping oil cylinder 81 installed on the top main plate 51 and a clamping oil cylinder piston rod 82 extending from the bottom of the clamping oil cylinder 81. The clamping oil cylinder piston rod 82 is correspondingly connected to the top groove of the moving top connecting part 63.

[0051] Step 3: Install the clamping assembly 7 inside the moving body 61, and install the clamping cover plate 9 at the bottom of the moving body 61. Among them, the clamping adjusting oil cylinder assembly 8 is installed on the clamping cover plate 9 in advance. The clamping adjusting oil cylinder assembly 8 includes a clamping oil cylinder 81 installed in the groove of the clamping cover plate 9 and a clamping oil cylinder piston rod 82 extending from the top of the clamping oil cylinder 81. The clamping oil cylinder piston rod 82 is correspondingly connected to the inclined pressure block connecting hole 73.

[0052] In this embodiment, the inclined pressure block 71 is equally divided into several segments according to the diameter of the steel pipe pile 11, and there is enough gap between adjacent segments; stress measurement points are arranged on the inner side of the inclined pressure block 71, and stress sensors and strain sensors are arranged at the stress measurement points; the stress and strain data of the stress measurement points are connected to the control terminal in real time; by setting the stress and strain, the up and down movement of the clamping oil cylinder 81 is controlled to meet the design requirements for clamping the steel pipe pile 11.

[0053] Step Four: Then drive the clamping oil cylinder 81 to move up and down to drive the inclined pressure block 71 to move; the inclined surface of the inclined pressure block 71 provides a horizontal component force and at the same time closes the segmented inclined pressure blocks 71 towards the center to clamp the steel pipe pile 11; then drive the top pressure main oil cylinder 101, and the moving assembly 6 drives the inclined block assembly to act together to press the steel pipe pile 11 into the ground.

[0054] Step Five: At the same time, place a top pressure plate 12 on the top of the steel pipe pile 11, and connect the top pressure plate 12 and the moving main body 61 with the segmented spliced track chain 12; when the moving main body 61 drives the steel pipe pile 11 to press down, the track chain 12 pulls the top pressure plate 12 to press the steel pipe pile 11 into the ground at the same time. When the top pressure main oil cylinder 101 moves one stroke, remove one segment of the track chain 12, and repeat this process until the steel pipe pile 11 is completely pressed into the ground and the construction is completed.

[0055] During the process of pressing the steel pipe pile 11 into the ground, the clamping assembly 7 is driven reciprocally to clamp or release the steel pipe pile 11, and cooperate with the downward movement of the top pressure oil cylinder assembly 10 and the disassembly and assembly of the track chain 12, so as to continuously press the steel pipe pile 11 without replacing the clamping assembly 7 until the pressing length of the steel pipe pile 11 reaches the design requirements.

[0056] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be thought of by those skilled in the art within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.

Claims

1. A composite top-holding and pressing integrated static pressure pile construction equipment, comprising a frame system formed by a bottom plate assembly (3), guide rods (4) and a top plate assembly (5), a moving assembly (6) slidably connected to the guide rods (4) at the middle of the frame system, a top pressing oil cylinder assembly (10) detachably connected to the top plate assembly (5) at the top of the frame system, a holding assembly (7) connected to the inner side of the moving assembly (6), a holding adjustment oil cylinder assembly (8) and a holding cover plate (9) connected below the holding assembly (7), a track chain (12) connected to the moving assembly (6), and a top pressing plate (12) correspondingly connected to the top of the track chain (12); The moving assembly (6) comprises a moving main body (61), a moving sleeve connecting piece (62) integrally connected to the outer side of the moving main body (61) and sleeved on the guide rod (4), and a moving top connecting piece (63) connected to the top of the moving main body (61); the moving main body (61) is an annular piece, and a frustum-shaped hole is arranged inside the annular piece, and the vertical section of the frustum-shaped hole is a trapezoid with a smaller upper part and a larger lower part; The holding assembly (7) comprises a group of inclined pressing blocks (71) correspondingly arranged with the moving main body (61), an inclined pressing block bottom plate (72) connected below the inclined pressing blocks (71), inclined pressing block connecting holes (73) arranged on the bottom surface of the inclined pressing bottom plate, an inclined pressing block gap (74) arranged between the group of inclined pressing blocks (71), and an inclined pressing pipe-holding hole (75) formed by enclosing the inner sides of the group of inclined pressing blocks (71); the inclined pressing pipe-holding hole (75) is correspondingly connected to a steel pipe pile (11); the inclined pressing block connecting holes (73) are correspondingly connected to the holding adjustment oil cylinder assembly (8); The inclined pressing blocks (71) are arc-shaped fan-shaped pieces, and an inclined pressing block gap (74) is arranged between the group of inclined pressing blocks (71), and the outer side surfaces of the inclined pressing blocks (71) enclose a frustum shape corresponding to the frustum-shaped hole of the moving main body (61).

2. A composite top-holding and pressing integrated static pressure pile construction equipment as described in claim 1, a base (1), the bottom plate assembly (3) comprises two parallel bottom longitudinal plates (31) and a bottom transverse plate (32) vertically connected between the bottom longitudinal plates (31), and the long ends of the bottom longitudinal plates (31) are connected to the base (1) through anchor bolts (2).

3. A composite top-holding and pressing integrated static pressure pile construction equipment as described in claim 1, the guide rod (4) comprises a rod body (41) and a fixing nut (42) connected to the top of the rod body (41), and there are four rod bodies (41) arranged in a rectangle; the bottom of the rod body (41) is fixedly connected to the bottom transverse plate (32).

4. A composite top-holding and pressing integrated static pressure pile construction equipment as described in claim 1, the top plate assembly (5) comprises a top main plate (51) and top plate connecting ears (52) connected to the side edges of the top main plate (51), and the top plate connecting ears (52) are arranged in an X shape; the top plate connecting ears (52) are correspondingly arranged with the guide rods (4), and fixing nuts (42) are detachably connected to the top and bottom of the top plate connecting ears (52) respectively; Grooves for installing the top pressing oil cylinder assembly (10) are symmetrically arranged on the top main plate (51).

5. The construction equipment for a composite top hugging and pressing integrated static pressure pile as described in claim 1, wherein The movable sleeve connecting piece (62) is a C-shaped piece, the vertical part is a sleeve-shaped socket rod body (41), and the two parallel horizontal parts are integrally connected to the movable main body (61); The movable top connecting piece (63) is an inverted T-shaped piece, the horizontal part is pin-connected to the movable main body (61), and the vertical part is correspondingly connected to the top pressing oil cylinder assembly (10); The bottom of the movable main body (61) is pin-connected to the clamping cover plate (9), and a groove for installing the clamping adjustment oil cylinder assembly (8) is also provided on the clamping cover plate (9).

6. For a composite top-clamping and pressing integrated static pressure pile construction equipment according to claim 1, four inclined pressing blocks (71) are provided, and a cross-shaped inclined pressing block gap (74) is provided between the four inclined pressing blocks (71); the bottoms of the four inclined pressing blocks (71) are fixedly connected to a circular inclined pressing block bottom plate (72).

7. For a composite top-clamping and pressing integrated static pressure pile construction equipment according to claim 1, two chain ear plates (13) are provided in the vertical direction perpendicular to the connection line of the two top pressing oil cylinder assemblies (10); a chain track (12) is detachably connected to the chain ear plate (13); a top pressing plate (12) is correspondingly movably connected to the top of the chain track (12).

8. A construction method for a composite top-clamping and pressing integrated static pressure pile construction equipment according to any one of claims 1 to 7, the specific steps are as follows: Step 1: First, form a framework with the bottom plate assembly (3), the top plate assembly (5) and the guide rod (4), wherein the bottom longitudinal plate (31) is connected to the base (1) through anchor bolts (2); the guide rod (4) is fixed on the bottom transverse plate (32) and the top plate assembly (5) is adjusted and fixed through a fixing nut (42); Step 2: The movable assembly (6) is pre-slidingly installed on the guide rod (4), and the top pressing oil cylinder assembly (10) is installed on the top plate assembly (5); wherein the top pressing oil cylinder assembly (10) includes a clamping oil cylinder (81) installed on the top main plate (51) and a clamping oil cylinder piston rod (82) extending from the bottom of the clamping oil cylinder (81); the clamping oil cylinder piston rod (82) is correspondingly connected to the top groove of the movable top connecting piece (63); Step 3: The clamping assembly (7) is installed inside the movable main body (61), and the clamping cover plate (9) is installed at the bottom of the movable main body (61), wherein the clamping adjustment oil cylinder assembly (8) is pre-installed on the clamping cover plate (9); the clamping adjustment oil cylinder assembly (8) includes a clamping oil cylinder (81) installed in the groove of the clamping cover plate (9) and a clamping oil cylinder piston rod (82) extending from the top of the clamping oil cylinder (81); the clamping oil cylinder piston rod (82) is correspondingly connected to the inclined pressing block connecting hole (73); Step 4: Then drive the clamping oil cylinder (81) to move up and down to drive the inclined pressing block (71) to move; provide a horizontal component force through the inclined surface of the inclined pressing block (71) and at the same time close the divided inclined pressing blocks (71) towards the center to clamp the steel pipe pile (11); then drive the top pressing main oil cylinder (101), and the movable assembly (6) drives the inclined block assembly to act together to press the steel pipe pile (11) into the ground; Step 5. Meanwhile, place a top pressing plate (12) on the top of the steel pipe pile (11), and connect the top pressing plate (12) and the moving body (61) with a segmented track chain (12); when the moving body (61) presses down with the steel pipe pile (11), the track chain (12) pulls the top pressing plate (12) to press the steel pipe pile (11) into the ground simultaneously. After the top pressing main oil cylinder (101) moves one stroke, remove one segment of the track chain (12), and repeat this process until the steel pipe pile (11) is completely pressed into the ground, and the construction is completed.

9. For the construction method of a composite top-holding and pressing integrated static pressure pile construction device as described in claim 8, the inclined pressing block (71) is equally divided into several segments according to the diameter of the steel pipe pile (11), and there is enough gap between adjacent segments; stress and strain sensors are arranged at the measurement and control points on the inner side of the inclined pressing block (71); the stress and strain data of the measurement and control points are connected to the control terminal in real time; By setting the stress and strain, control the up and down movement of the clamping oil cylinder (81) to meet the design requirements for clamping the steel pipe pile (11).

10. For the construction method of a composite top-holding and pressing integrated static pressure pile construction device as described in claim 8, during the process of pressing down the steel pipe pile (11), the clamping assembly (7) is reciprocally driven to clamp or release the steel pipe pile (11), and cooperate with the downward movement of the top pressing oil cylinder assembly (10) and the disassembly and assembly of the track chain (12), so as to continuously press the steel pipe pile (11) without replacing the clamping assembly (7) until the pressing length of the steel pipe pile (11) reaches the design requirements.