A method for troubleshooting on-board chargers for electric vehicles
By combining software optimization and hardware improvements, the problem of batch failures of on-board chargers was solved, the troubleshooting time was shortened, costs were reduced, and the efficiency of vehicle recalls was improved.
Patent Information
- Application Number
- CN202311153656.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-07
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-09-07
AI Technical Summary
Massive failures of on-board chargers have resulted in high costs and long cycles for replacing parts, making it impossible to resolve existing faults in a timely and effective manner, thus affecting vehicle recalls and user experience.
The fault was resolved by optimizing the on-board charger startup process and the PFC circuit software startup process through software optimization, and replacing the front-end drive circuit resistor of the MOSFET in some vehicles, combining software and hardware improvements.
It shortened the troubleshooting time, reduced costs, avoided the need for large-scale parts replacement, saved resources and manpower, and enabled timely and effective fault repair.
Smart Images

Figure CN117284116B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of electric vehicle technology, and in particular to a method for handling faults in an on-board charger for electric vehicles. Background Technology
[0002] With the booming development of electric vehicles and the continuous increase in market stock, the high-voltage three-electric system, including battery systems, drive systems, and power systems, is accelerating its integration. In recent years, recalls of entire vehicles due to mass failures have become increasingly common. Vehicle recalls not only damage the brand image of automakers but also cause significant economic losses, making them a necessary but unavoidable solution to market problems. As component integration continues to advance, vehicle fault repair is becoming increasingly important. There are two main directions for fault repair: reducing the failure rate and reducing repair costs. Reducing the failure rate mainly relies on the early-stage product development of each component, demonstrating a strong proactive approach. Reducing repair costs requires comprehensive consideration, as different fault solutions have different costs.
[0003] The on-board charger (OBC), installed in an electric vehicle, is a crucial component. Currently, integrated on-board power supplies are primarily two-in-one products combining DC / DC converters and an OBC. However, the OBC is also one of the components with the highest failure rate in electric vehicles. The high replacement costs of integrated products negatively impact the healthy development of electric vehicles and user experience. Especially when a large number of OBC failures occur, and the root cause is a hardware problem, a large number of parts need to be replaced. This requires automakers and parts manufacturers to invest significant financial and human resources, resulting in high costs and long lead times. Summary of the Invention
[0004] This invention addresses the problem of high cost and long cycle time for replacing parts when on-board chargers fail in batches, which cannot effectively and promptly resolve existing faults. It provides a fault handling method for on-board chargers in electric vehicles.
[0005] To solve the above problems, the present invention adopts the following technical solution:
[0006] A method for handling faults in an on-board charger for an electric vehicle, the method comprising the following steps:
[0007] Step 1: Perform fault diagnosis on the on-board charger to determine the cause of the fault. The cause of the fault is that the MOSFET in the PFC circuit of the on-board charger is damaged.
[0008] Step 2: For vehicles that urgently need troubleshooting in the market, optimize the software startup process of the on-board charger and the PFC circuit software startup process respectively;
[0009] Step 3: For existing vehicles and vehicles to be produced, not only are the on-board charger startup process and PFC circuit software startup process optimized respectively, but the resistor in the front-end drive circuit of the MOS transistor in the PFC circuit is also replaced with a resistor with a larger resistance value.
[0010] The beneficial effects of this invention are:
[0011] This invention addresses the problems of excessively long modification and verification times (approximately four months) when on-board chargers experience batch hardware problems requiring component replacement. This hinders timely and effective resolution of existing market malfunctions, necessitates complete vehicle replacement, incurs high costs, and necessitates substantial resource and manpower investment. The invention proposes a novel method for resolving on-board charger malfunctions through a combination of software and hardware. Firstly, it optimizes the on-board charger startup process and the PFC circuit software startup process to address on-board charger malfunctions in vehicles urgently requiring troubleshooting. Because the software modification and verification time is relatively short (approximately one month), and it only requires software updates instead of complete vehicle replacement, it not only saves significant time and effectively resolves existing vehicle malfunctions but also reduces costs. Secondly, after hardware verification is completed, the invention further optimizes the on-board charger startup process and the PFC circuit software startup process for both existing and upcoming vehicles, and modifies the hardware across all vehicles. This invention combines software optimization and hardware improvement, with the two approaches complementing each other. The time advantage of software optimization compensates for the time shortness of hardware improvement. Compared to hardware improvement alone, this invention uses a combination of software optimization and hardware improvement to significantly shorten the problem-solving time while ensuring that the fault is effectively resolved, and at the same time reduce after-sales costs. Attached Figure Description
[0012] Figure 1 This is a flowchart of a method for handling faults in an on-board charger for electric vehicles, as described in an embodiment of the present invention.
[0013] Figure 2 This is a flowchart of the software startup process of the optimized PFC circuit in an embodiment of the present invention;
[0014] Figure 3 This is a circuit diagram of the MOSFET drive loop in a PFC circuit. Detailed Implementation
[0015] The technical solution of the present invention will now be described in detail with reference to the accompanying drawings and preferred embodiments.
[0016] This invention provides a method for handling faults in on-board chargers for electric vehicles. This method addresses the problem of high component replacement costs and long lead times when on-board chargers experience mass failures, thus failing to provide timely and effective solutions to existing faults. Figure 1 As shown, the method specifically includes the following steps 1 to 3.
[0017] Step 1: Perform fault diagnosis on the on-board charger to determine the cause of the fault.
[0018] The vehicle failed to charge during AC charging. Fault diagnosis and analysis of the on-board charger determined the cause to be a damaged MOSFET in the power factor correction (PFC) circuit. Testing revealed that during AC charging, the voltage at the GS pins of the PFC MOSFET oscillated under narrow pulse conditions at the moment of heavy load switching (from small to large current), causing the MOSFET to fail. Testing the oscillation waveform under different combinations of drive resistor values showed that when the drive resistor R05 was 10Ω (in the faulty circuit), the MOSFET's GS pin voltage oscillated, while when R05 was 24Ω (after modification), there was no oscillation. Therefore, the root cause of the on-board charger failure was that the resistance value of R05 in the MOSFET's front-end drive circuit of the PFC circuit was too small.
[0019] Because replacing hardware circuits is costly and time-consuming in the back-end market, a detailed analysis of the fault process revealed that the fault occurred during a heavy-load switching process. This invention addresses the oscillation problem by optimizing the slope of the switching current through software to meet the requirements of both the market and production ends. Simultaneously, the drive circuit resistor R05 was changed to 24Ω, and switching was performed after testing and verification. In other words, software optimization and hardware improvement were carried out simultaneously.
[0020] Step 2: Optimize the startup strategy using software for vehicles that urgently need troubleshooting in the market.
[0021] The software optimization of the startup strategy is carried out in two aspects: software optimization of the on-board charger startup process and software optimization of the PFC circuit startup process.
[0022] Under normal circumstances, the on-board charger will reach the charging request current within 3 seconds during the startup process, which is fast and efficient. However, according to the above analysis, the MOSFET failure mainly occurs during the heavy load switching process. Therefore, this invention implements step-by-step current limiting during the on-board charger startup process, that is, limiting the output current of the on-board charger step by step. Specifically, the software-optimized on-board charger startup process includes the following steps:
[0023] After the on-board charger receives a charging request and powers on, within 0-5 seconds, if the charging request current is greater than 5A, the output current is limited to no more than 5A; if the charging request current is less than or equal to 5A, the output current is equal to the charging request current. Within 5-10 seconds, if the charging request current is greater than 7A, the output current is limited to no more than 7A; if the charging request current is less than or equal to 7A, the output current is equal to the charging request current. After 10 seconds, the output current is equal to the charging request current, thereby suppressing short-term high current operation.
[0024] The fault analysis revealed that the voltage oscillation at the GS pins of the MOSFET was caused by the undersized resistance of R05 in the MOSFET drive circuit. The oscillation voltage amplitude was V = L × di / dt, where L represents the parasitic inductance in the MOSFET drive circuit, and di / dt represents the derivative of current with respect to time, i.e., the change in current per unit time. With the hardware circuit unchanged, L is a constant; the greater the current change (di) per unit time (dt), the greater the voltage V. Therefore, the larger di is, the greater the oscillation amplitude. Since Vgs and Vds share the same S pin, an increase in the oscillation amplitude of Vds will exacerbate the oscillation of Vgs. Therefore, by optimizing the software startup strategy and reducing current changes, the voltage oscillation at the GS pins caused by software startup can be effectively suppressed. The optimized PFC circuit startup process is as follows: Figure 2 As shown, it includes the following steps:
[0025] S1: The AC input of the MOSFET in the PFC circuit is greater than 80V and the PFC is fault-free. Upon receiving the power-on command, it enters the soft-start state. The MOSFET is a switch that is controlled to turn on and off by low voltage (3V-5V). After being turned on, it can withstand high voltage (200V-450V) and high current (0-32A).
[0026] S2: Determine if the output bus voltage of the MOSFET in the PFC circuit is greater than 8V. If yes, proceed to S3; otherwise, report a soft start fault.
[0027] S3: Close the pre-charge relay. If the output bus voltage is greater than 0.6 times the peak value of the AC input voltage within 3 seconds, proceed to S4; otherwise, report a soft start fault.
[0028] S4: Close the output relay, open the pre-charge relay, and use the current bus voltage as the initial value for soft start to gradually perform closed-loop soft start towards the final desired output.
[0029] S5: If phase locking is successful within 7 seconds and the AC input frequency is greater than 43Hz and the bus voltage is higher than the final expected output minus 10V, then the soft start is successful; otherwise, a soft start fault is reported.
[0030] In this embodiment, the software-optimized PFC circuit startup process can reduce current changes and avoid voltage changes and oscillations in the GS pin caused by startup current variations.
[0031] This embodiment first optimizes the on-board charger startup process and PFC circuit software startup process to solve the on-board charger failure problem of vehicles that urgently need troubleshooting in the market. Since the software modification and verification time is relatively short (about one month) and there is no need to replace the whole vehicle parts, only to update the software, it can not only save a lot of time and solve the vehicle's failure in a timely and effective manner, but also avoid a large number of parts replacements, saving resources and manpower investment, and reducing costs.
[0032] Step 3: For both existing vehicles in the market and vehicles to be produced, simultaneously optimize the software and improve the hardware circuitry.
[0033] like Figure 3 As shown, when R05 = 10Ω, with OBC output at 330V and load at 10A, the oscilloscope shows oscillation at the Vgs terminals of the MOSFET during the instantaneous load change. When R05 = 24Ω, with OBC output at 330V and load at 10A, the oscilloscope shows no oscillation at the Vgs terminals of the MOSFET during the instantaneous load change. The experiment indicates that the oscillation during the heavy load change is caused by the parasitic capacitance of the PFC MOSFET. According to the damping condition, to prevent oscillation of the drive current, the drive resistor must reach a certain value. Therefore, increasing the drive resistor can prevent oscillation. Thus, changing the value of R05 in the MOSFET drive circuit to 24Ω can solve the problem of MOSFET damage due to oscillating voltage at the pins from a hardware perspective.
[0034] After the hardware verification is completed, for both existing vehicles in the market and vehicles to be produced, not only will the on-board charger startup process and the PFC circuit software startup process be optimized respectively, but the hardware will also be changed on all vehicles.
[0035] This invention combines software optimization and hardware improvement, with the two approaches complementing each other. The time advantage of software optimization compensates for the time shortness of hardware improvement. Compared to hardware improvement alone, this invention uses a combination of software optimization and hardware improvement to significantly shorten the problem-solving time while ensuring that the fault is effectively resolved, and at the same time reduce after-sales costs.
[0036] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0037] The embodiments described above are merely illustrative of several implementations of the present invention, and while the descriptions are relatively specific and detailed, they should not be construed as limiting the scope of the invention patent. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of the present invention, and these all fall within the protection scope of the present invention. Therefore, the protection scope of this invention patent should be determined by the appended claims.
Claims
1. A method for handling faults in an electric vehicle on-board charger, characterized in that, Includes the following steps: Step 1: Perform fault diagnosis on the on-board charger to determine the cause of the fault. The cause of the fault is that the MOSFET in the PFC circuit of the on-board charger is damaged. Step 2: For vehicles that urgently need troubleshooting in the market, optimize the software startup process of the on-board charger and the PFC circuit software startup process respectively; The optimized on-board charger startup process includes the following steps: After the on-board charger receives a charging request and powers on, within 0-5 seconds, if the requested charging current is greater than 5A, the output current is limited to no more than 5A; if the requested charging current is less than or equal to 5A, the output current is equal to the requested charging current. Within 5-10 seconds, if the requested charging current is greater than 7A, the output current is limited to no more than 7A; if the requested charging current is less than or equal to 7A, the output current is equal to the requested charging current. After 10 seconds, the output current is equal to the requested charging current. The optimized PFC circuit software startup process includes the following steps: S1: The AC input of the MOSFET in the PFC circuit is greater than 80V and the PFC is fault-free. Upon receiving the power-on command, it enters the soft-start state. S2: Determine if the output bus voltage of the MOSFET in the PFC circuit is greater than 8V. If yes, proceed to S3; otherwise, report a soft start fault. S3: Close the pre-charge relay. If the output bus voltage is greater than 0.6 times the peak value of the AC input voltage within 3 seconds, proceed to S4; otherwise, report a soft start fault. S4: Close the output relay, open the pre-charge relay, and use the current bus voltage as the initial value for soft start to gradually perform closed-loop soft start towards the final desired output. S5: If phase locking is successful within 7 seconds and the AC input frequency is greater than 43Hz and the bus voltage is higher than the final expected output minus 10V, then the soft start is successful; otherwise, a soft start fault is reported. Step 3: For inventory vehicles and vehicles to be produced, not only are the on-board charger startup process and PFC circuit software startup process optimized respectively, but the resistor in the front-end drive circuit of the MOS transistor in the PFC circuit is also replaced with a resistor with a larger resistance value.
2. The method for handling faults in an electric vehicle on-board charger according to claim 1, characterized in that, In step 3, the resistor in the front-end drive circuit of the MOS transistor in the PFC circuit is replaced from a 10Ω resistor to a 24Ω resistor.
Citation Information
Patent Citations
DC distribution line protection method based on control and protection cooperation
CN114977137A
Panic protection from fault conditions in power converters
US20020141128A1