A hierarchically tensioned double-circle continuous arch beam lattice shell structure and its construction method
Through the hierarchical tensioning double-circle arch beam mesh shell structure, combined with the damping ball hinge support and cable bearing structure, the problems of mid-stiffness and support difficulty of stadium roof design are solved, efficient construction and visual effects are achieved, and cost and Difficulty.
Patent Information
- Application Number
- CN202311480264.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-08
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2043-11-08
AI Technical Summary
The open-air site design in the middle of the stadium roof is difficult to achieve sufficient stiffness and bearing capacity, and it is difficult to support, resulting in challenges in the visual effect and construction difficulty of the mesh shell structure.
The grid shell structure of the graded tensioned double-ring connected arch beam includes outer steel ring beam, inner steel ring beam, ring aluminum structure, steel arch beam and crescent aluminum structure, and supports it through damping ball hinge support and cable bearing structure. Combining finite element analysis and hierarchical tensioning methods, structural layout and construction steps are optimized.
The overall load-bearing force of the multi-system special-shaped space structure is realized, which reduces the construction difficulty and cost, improves the visual effect and structural stability, and ensures the stability and construction efficiency of the roof.
Smart Images

Figure CN117328558B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of lattice shell building construction, and particularly relates to a graded tensioned double-circle continuous arch beam lattice shell structure and a construction method thereof. Background Art
[0002] The grid shell structure is a typical spatial structure. Reasonable curved surfaces can make the structural force flow uniform, the structure has greater rigidity, less structural deformation, high stability, and save materials. The grid shell structure has a beautiful architectural shape, and can give designers full creative freedom in terms of architectural plane, appearance and shape. The grid shell structure can achieve almost all the forms that thin shell structures and grid structures cannot achieve. It can express static beauty, and can also express dynamic beauty through the cutting of planes and facades and the changes of grids, supports and rods.
[0003] For stadiums, the middle is often an open-air venue, so the middle of the roof is a curved surface with a large opening. The multi-system special-shaped space structure needs to have sufficient visual effects. In addition, due to the difficulty of supporting the middle of the stadium, it is very difficult to design the lattice shell structure to meet sufficient rigidity and bearing capacity. Therefore, targeted design is needed. Summary of the invention
[0004] The invention provides a graded tensioned double-circle continuous arch beam lattice shell structure and a construction method thereof, which are used to solve the technical problems mentioned in the background technology.
[0005] To achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a graded tensioned double-ring continuous arch beam lattice shell structure, comprising an outer steel ring beam, an inner steel ring beam, an annular aluminum structure, a steel arch beam, a crescent-shaped aluminum structure and a cable-supported structure, the outer steel ring beam and the inner steel ring beam are concentrically arranged, the outer steel ring beam is installed on the steel structure, the outer steel ring beam is fixed to the steel structure through a number of damping ball hinge supports, the annular aluminum structure is installed between the outer steel ring beam and the inner steel ring beam, the steel arch beam is an arch with an opening downward, two steel arch beams are arranged in parallel and are symmetrically arranged at the center position of the inner steel ring beam, the two ends of the steel arch beam are respectively welded to the inner side surface of the outer steel ring beam and the steel arch beam is welded to the top of the inner steel ring beam, the crescent-shaped aluminum structure is arranged between the steel arch beam and the inner steel ring beam, the outer steel ring beam, the inner steel ring beam and the steel The arch beams are all circular steel beams. On the vertical plane in the length direction of the steel arch beam, the inner steel ring beam and the outer steel ring beam are both in an arch shape with an opening downward, and the inner steel ring beam is higher than the outer steel ring beam. On the vertical plane in the length direction of the steel arch beam, the inner steel ring beam and the outer steel ring beam are both in an arch shape with an opening upward, and the inner steel ring beam is higher than the outer steel ring beam. The cable-supporting structure includes a ring cable, a cable clamp, an outer diameter cable, an inner diameter cable, an outer steel strut, and a tree-shaped strut. The ring cable includes an inner elliptical segment and outer arc segments on both sides. The center point of the inner elliptical segment is concentrically arranged with the outer steel ring beam and the inner steel ring beam. The long axis of the inner elliptical segment is parallel to the steel arch beam. The two ends of the long axis of the inner elliptical segment are respectively located between the outer steel ring beam and the inner steel ring beam, and the two ends of the short axis of the inner elliptical segment are respectively located between the inner steel ring beam and the steel arch beam. The inner elliptical segment passes through the inner steel ring The intersection of the beam and the steel arch beam, the outer arc segment is located directly below the inner steel ring beam on the outside of the two steel arch beams, the intersection of the inner elliptical segment and the outer arc segment is located directly below the intersection of the inner steel ring beam and the steel arch beam, on the vertical plane in the length direction of the steel arch beam, the inner elliptical segment and the outer arc segment are both arcs with an opening upward, the outer arc segment is lower than the corresponding part of the inner elliptical segment, on the vertical plane in the length direction of the steel arch beam, the inner elliptical segment and the outer arc segment are both arcs with an opening upward, the corresponding parts of the outer arc segment and the inner elliptical segment are the same height, and a number of cable clamps are arranged on the inner elliptical segment and the outer arc segment, the cable clamp includes an upper clamp and a lower clamp clamped on the ring cable, the upper clamp and the lower clamp are connected by bolts, and the top of the upper clamp is fixedly provided with a steel cable ear plate and a steel strut ear The outer steel ring beam is provided with a plurality of outer cable ear plates, and the inner steel ring beam is provided with a plurality of outer support rod ear plates. The two ends of the outer diameter cable are respectively connected to the outer cable ear plate and the ring cable through a pin shaft and a joint bearing node. The outer diameter cable is connected to the two end sections of the outer arc segment and the inner elliptical segment. The two ends of the outer steel support rod are respectively connected to the outer support rod ear plate and the steel support rod ear plate through a pin shaft and a joint bearing node. The outer steel support rod between the two steel arch beams is inclined, and the outer steel support rods outside the two steel arch beams are vertical. The inner steel ring beam is also provided with an inner cable ear plate. The node of the annular aluminum structure and the crescent-shaped aluminum structure includes an aluminum rod and an aluminum alloy node plate. The aluminum rod is an H-shaped structure. The node plate has two nodes and is respectively arranged at the top and bottom ends of the aluminum rod. The aluminum rod is fixed to the node plate by stainless steel rivets.The bottom ends of several node plates are provided with inner support rod ear plates, the two ends of the inner diameter cable are respectively connected to the inner cable ear plates and the ring cable through pins and joint bearing nodes, the inner diameter cable is connected to the middle section of the inner elliptical section, the lower half of the tree-shaped support rod is a vertical rod, the upper half of the tree-shaped support rod is a plurality of branch rods, the bottom ends of the tree-shaped support rods are connected to the steel support rod ear plates through pins and joint bearing nodes, the upper half of the tree-shaped support rods are respectively connected to the inner support rod ear plates at different positions through pins and joint bearing nodes, the damping ball joint support comprises a base, a lower support plate, a ball joint plate, an upper support plate and a limiting graded unloading device, the base is fixed on the steel structure, the lower support plate is placed on the base, several springs are arranged on the side of the lower support plate, the lower support plate and the upper support plate are embedded, the ball joint plate is located between the lower support plate and the upper support plate, and the periphery of the upper support plate is provided with The graded limit ring, the lower support plate and the upper support plate are rectangular plates, and the limit graded unloading device includes a support plate fixed on the steel structure, the support rod is located on the side of the damping ball joint support close to the inner steel ring beam, and a plurality of reinforcing inclined plates located away from the damping ball joint support are also arranged between the support plate and the steel structure. The top end of the support plate close to the damping ball joint support is threadedly connected with an adjusting screw, and the end of the adjusting screw close to the upper support plate is rotatably connected with a rotating seat, and a plurality of rotating seats are fixed on the U-shaped top support, and the U-shaped top support opening faces the upper support plate and is adapted to the graded limit ring, and the graded limit ring is embedded in the U-shaped top support, and a mounting seat is also fixedly arranged on the top end of the support plate close to the damping ball joint support, and a jack is fixedly installed between the mounting seat and the upper support plate, and the mounting seat is arranged along the width direction of the support plate, and the jack is located in the middle of the mounting seat.
[0006] Preferably, 36 damping ball joint supports are evenly distributed.
[0007] Preferably, the outer diameter cables are evenly distributed at 36 locations, the inner diameter cables are evenly distributed at 18 locations, the outer steel struts are correspondingly arranged at 36 locations, and the tree-shaped struts are correspondingly arranged at 18 locations.
[0008] Preferably, both ends of the outer diameter rope and the inner diameter rope are fork-ear type anchor heads.
[0009] Preferably, the ring rope is divided into four sections for splicing, and the segmentation position is located at the intersection of the inner elliptical section and the outer arc section, offset a distance toward the two ends of the inner elliptical section. The two ends of the ring rope after segmentation are conical anchor heads, and adjacent conical anchor heads are connected by a joint device. The joint device includes two clamping plates located outside the two conical anchor heads, and the two clamping plates are fixedly connected by screws and bolts.
[0010] Preferably, the cable-supporting structure also includes four V-cables, two outer diameter cables on the vertical plane of the vertical plane in the longitudinal direction of the steel arch beam are weak diameter cables, and a reinforcing cable ear plate 1 is also provided on the cable clamp below the weak diameter cable, and a reinforcing cable ear plate 2 is provided on the outer steel ring beam of the weak diameter cable adjacent to the weak diameter cable, and the two ends of the V-cable are respectively connected to the reinforcing cable ear plate 1 and the reinforcing cable ear plate 2 through a pin shaft and a joint bearing node.
[0011] Preferably, the annular aluminum structure is a lattice shell structure with prismatic holes intersecting in an X-shape, and the crescent-shaped aluminum structure is a lattice shell structure with triangular holes intersecting in a rice-shape.
[0012] Preferably, the nodes of the annular aluminum structure and the crescent-shaped aluminum structure include an aluminum rod and an aluminum alloy node plate, the aluminum rod is an H-shaped structure, the node plates have two and are respectively arranged at the top and bottom ends of the aluminum rod, and the aluminum rod is fixed to the node plate by stainless steel rivets.
[0013] Preferably, H-shaped steel corbels are welded to the outer steel ring beam, the inner steel ring beam and the steel arch beam, respectively, the annular aluminum structure and the crescent-shaped aluminum structure are respectively connected to the steel corbels, and the steel corbels are fully bolted to the node plates.
[0014] A construction method for a graded tensioned double-circle continuous arch beam lattice shell structure comprises the following steps:
[0015] Step 1: Use finite element analysis software to establish a construction simulation analysis model, analyze the stress of the overall structure and determine the specifications of parts that meet the structural strength;
[0016] Step 2: Install the damping ball joint support on the steel structure, hoist the outer steel ring beam in sections, and assemble it at high altitude;
[0017] Step 3: Arrange support measures for the inner steel ring beam on the steel structure, use portal support, divide the working surface into four fan-shaped areas, and construct temporary support measures for the outer steel ring beam and the inner steel ring beam in each area in a counterclockwise direction;
[0018] Step 4: Install the inner steel ring beam, hoist the inner steel ring beam in sections, and assemble it at high altitude;
[0019] Step 5: Install the annular aluminum structure, divide it into units, assemble the units on the ground and then hoist them, then assemble them in the air and connect them with the inner steel ring beam or the outer steel ring beam through steel brackets;
[0020] Step 6: Install the support measures of the steel arch beam on the steel structure, using single-point support;
[0021] Step 7: Hoist the steel arch beam, hoist in sections, and assemble at high altitude;
[0022] Step 8: Install the crescent-shaped aluminum structure, divide it into units, assemble the units on the ground and then hoist them, then assemble them in the air and connect them with the inner steel ring beam or steel arch beam through steel brackets;
[0023] Step 9: Lay out the hoop cable frame, which is offset 2.0m inward to facilitate the loosening and docking of the hoop cable;
[0024] Step 10: Lift the slings in sections, and arrange multiple lifting points on each section of the slings for lifting. After all the slings are lifted, adjust them. After all the slings are adjusted and aligned, tighten the cable clamps;
[0025] Step 11: Install outer diameter rope, inner diameter rope and V rope;
[0026] The outer diameter cables and inner diameter cables are hoisted by graded tensioning.
[0027] First, it is necessary to calculate and determine the appropriate tensioning force, and perform tensioning according to the tensioning force of each stage calculated by construction simulation. Use the cable tension oil pressure gauge + monitoring value to calibrate the cable tension value, and use the total station to measure the deformation value to check the quality of the tensioning process. The tensioning equipment uses a jack and a matching oil pump and pressure gauge. A precision oil pressure gauge is used during tensioning. Before tensioning, the equipment and instruments of the tensioning system should be calibrated. During calibration, the jack should actively load the test equipment and draw a chart for on-site use. During the tensioning process, the corresponding oil pressure is adjusted according to the internal force required by the construction process to accurately tension the cable to the required force.
[0028] In the first stage of tensioning, the outer diameter cable and the inner diameter cable are tensioned in sequence to 30% of the total tensioning force, and the adjusting screw is rotated at the same time with the auxiliary support of the jack so that the adjusting screw releases the displacement and stress of the lower support plate, the ball joint plate, the upper support plate and the adjusting screw together;
[0029] In the second stage of tensioning, the outer diameter cable and the inner diameter cable are tensioned in sequence to 60% of the total tensioning force, and the adjusting screw is rotated at the same time with the auxiliary support of the jack so that the adjusting screw releases the displacement and stress of the lower support plate, the ball joint plate, the upper support plate and the adjusting screw together;
[0030] The third stage tensioning is to tension the outer diameter cable and the inner diameter cable in sequence to 90% of the total tensioning force, and rotate the adjusting screw at the same time with the auxiliary support of the jack so that the adjusting screw can release the displacement and stress of the lower support plate, the ball joint plate, the upper support plate and the adjusting screw together;
[0031] The fourth stage of tensioning is to tension the outer diameter cable and the inner diameter cable in sequence to 100% of the total tensioning force, and rotate the adjusting screw at the same time with the auxiliary support of the jack so that the adjusting screw can release the displacement and stress of the lower support plate, the ball joint plate, the upper support plate and the adjusting screw together;
[0032] Step 12: Remove the supporting measures of the inner steel ring beam and steel arch beam.
[0033] The beneficial effects of the present invention are as follows: 1. The structural system is a new type of combined structural system with a single-layer aluminum alloy lattice shell on the upper layer and a cable-supported string system on the lower layer. Through the unique arrangement of the ring cables and the unique arrangement of the radial cables, it is supported on the outer ring steel lattice shell structure to form a multi-system special-shaped space structure, so that the inner ring aluminum alloy lattice shell of the integral roof is a self-supporting integral force system, and only the damping ball hinge bearing arranged on the inner ring beam of the outer ring steel lattice shell of the roof can complete the support;
[0034] 2. This structure is designed to create a double-ring continuous arch beam structure, cleverly arrange the positions of the two steel arch beams, and match the two steel arch beams with the outer steel ring beam and the inner steel ring beam in terms of structural shape, achieving the effect of convenient construction and good appearance. A circular aluminum structure is arranged between the outer steel ring beam and the inner steel ring beam, and two steel arch beams are symmetrically erected on the outer steel ring beam and the inner steel ring beam. A crescent-shaped aluminum structure is arranged between the inner steel ring beam and the steel arch beam, forming an outer ring and inner double arc structure as a whole, which not only improves the visual effect but also reduces the cost and construction difficulty. In addition, the inner steel ring beam, the outer steel ring beam and the inner steel ring beam are connected to form a stable structure to support and install the aluminum structure, and the stability of the overall lattice shell is greatly improved;
[0035] 3. Based on the structural form of double-ring continuous arch beams, the double rings of this structure are in the form of curves, so that the continuity of the annular aluminum structure and the crescent-shaped aluminum structure can be achieved after the steel arch beams, which are both curved, are welded. It not only has sufficient visual effects on multi-system special-shaped space structures, but also has a small overall inflection point angle and good continuity. The stability of the structure reduces the cost and construction difficulty. The inner steel ring beam and the outer steel ring beam are both circular steel beams, which are connected to the inner steel ring beam to form a stable structure to support and install the aluminum structure. The stability of the overall lattice shell is greatly improved, which has pioneered the double-ring continuous arch beam lattice shell structure and has important significance in the field of construction.
[0036] 4. The double-circle continuous arch beam structure, unique ring cable arrangement, unique radial cable arrangement and V-cable design at the weak stress point greatly reduce the overall project cost and construction difficulty;
[0037] 5. Install a limited graded unloading device on the inner side of the damping ball joint support on the steel structure, and use a graded tensioning method to unload the stress of the radial cable in grades, which are 30%, 60%, 90% and 100% of the total tensioning force respectively, to maintain the stability of the structure and ensure that the structure does not deform or damage excessively during the construction process. The limited graded unloading device is coordinated by the top support and the jack. During the unloading process, the jack assists in the release of stress and facilitates the rotation adjustment of the adjustment screw after support, which not only ensures the stability of the stress released structure and is conducive to operation, achieving multiple effects and ensuring structural stability and construction efficiency.
[0038] Other features and advantages of the present invention will be set forth in the following description, and in part will become apparent from the description, or may be understood by practicing the present invention; the main purpose and other advantages of the present invention may be realized and obtained through the solutions particularly pointed out in the description. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 is a schematic diagram of the overall structure of an embodiment of the present invention;
[0040] Figure 2 is a front view of a vertical plane in the length direction of a steel arch beam according to an embodiment of the present invention;
[0041] Figure 3 It is a front view of a vertical plane of a vertical plane in the length direction of a steel arch beam according to an embodiment of the present invention;
[0042] Figure 4 is a top view of a sling according to an embodiment of the present invention;
[0043] Figure 5 1 is a schematic structural diagram of a cable clamp of a loop cable according to an embodiment of the present invention;
[0044] Figure 6 is a schematic diagram of a cable support structure on both sides of a steel arch beam according to an embodiment of the present invention;
[0045] Figure 7 is a structural diagram of the cable support structure on both sides of the steel arch beam according to an embodiment of the present invention;
[0046] Figure 8 is a schematic diagram of a cable support structure between steel arch beams according to an embodiment of the present invention;
[0047] Fig. 9 is a schematic structural diagram of a damping ball joint support according to an embodiment of the present invention;
[0048] Fig.10 2 is a schematic structural diagram of a position-limiting and graded unloading device according to an embodiment of the present invention;
[0049] Fig.11 is a schematic diagram of the structure of a node disk according to an embodiment of the present invention;
[0050] Fig.12 Schematic diagram of the structure of a steel corbel according to an embodiment of the present invention.
[0051] Figure numerals: 1, outer steel ring beam; 2, inner steel ring beam; 3, annular aluminum structure; 4, steel arch beam; 5, crescent-shaped aluminum structure; 6, cable support structure; 61, ring cable; 611, inner elliptical segment; 612, outer arc segment; 62, cable clamp; 621, upper clamp; 622, lower clamp; 623, steel cable ear plate; 624, steel support rod ear plate; 63, outer diameter cable; 64, inner diameter cable; 65, outer steel support rod; 66, tree-shaped support Rod; 67, weak diameter cable; 68, V cable; 7, damping ball joint support; 71, base; 72, lower support plate; 73, ball joint plate; 74, upper support plate; 75, limited graded unloading device; 751, supporting vertical plate; 752, reinforcing inclined plate; 753, adjusting screw; 754, rotating seat; 755, U-shaped top support; 756, mounting seat; 757, jack; 8, aluminum rod; 9, node plate; 10, steel corbel. DETAILED DESCRIPTION
[0052] The technical solution of the present invention is described in detail below through examples. The following examples are merely exemplary and can only be used to explain and illustrate the technical solution of the present invention, but cannot be interpreted as limiting the technical solution of the present invention.
[0053] Combination Figure 1-12A graded tensioned double-ring continuous arch beam lattice shell structure comprises an outer steel ring beam 1, an inner steel ring beam 2, an annular aluminum structure 3, a steel arch beam 4, a crescent-shaped aluminum structure 5 and a cable-supported structure 6. The outer steel ring beam 1 and the inner steel ring beam 2 are concentrically arranged, the outer steel ring beam 1 is installed on the steel structure, the outer steel ring beam 1 is fixed to the steel structure through a plurality of damping ball joint supports 7, the annular aluminum structure 3 is installed between the outer steel ring beam 1 and the inner steel ring beam 2, the steel arch beam 4 is an arch with an opening downward, two steel arch beams 4 are arranged in parallel and are symmetrically arranged at the center position of the inner steel ring beam 2, the two ends of the steel arch beam 4 are respectively welded to the inner side surface of the outer steel ring beam 1 and the steel arch beam 4 is welded to the top of the inner steel ring beam 2, the crescent-shaped aluminum structure 5 is arranged between the steel arch beam 4 and the inner steel ring beam 2, the outer steel ring beam 1. The inner steel ring beam 2 and the steel arch beam 4 are both circular steel beams. On the vertical plane in the length direction of the steel arch beam 4, the inner steel ring beam 2 and the outer steel ring beam 1 are both arched with an opening downward, and the inner steel ring beam 2 is higher than the outer steel ring beam 1. On the vertical plane of the vertical plane in the length direction of the steel arch beam 4, the inner steel ring beam 2 and the outer steel ring beam 1 are both arched with an opening upward, and the inner steel ring beam 2 is higher than the outer steel ring beam 1. The cable support structure 6 includes a ring cable 61, a cable clamp 62, an outer diameter cable 63, an inner diameter cable 64, an outer steel strut 65, and a tree-shaped strut 66. The ring cable 61 includes an inner elliptical segment 611 and outer arc segments 612 on both sides. The center point of the inner elliptical segment 611 is concentrically arranged with the outer steel ring beam 1 and the inner steel ring beam 2. The major axis of the inner elliptical segment 611 is parallel to the steel arch beam 4. The two ends of the major axis are respectively located between the outer steel ring beam 1 and the inner steel ring beam 2, the two ends of the minor axis of the inner elliptical segment 611 are respectively located between the inner steel ring beam 2 and the steel arch beam 4, the inner elliptical segment 611 passes through the intersection of the inner steel ring beam 2 and the steel arch beam 4, the outer arc segment 612 is respectively located directly below the inner steel ring beam 2 on the outsides of the two steel arch beams 4, the intersection of the inner elliptical segment 611 and the outer arc segment 612 is located directly below the intersection of the inner steel ring beam 2 and the steel arch beam 4, on the vertical plane in the longitudinal direction of the steel arch beam 4, the inner elliptical segment 611 and the outer arc segment 612 are both in an arc shape with an opening upward, the outer arc segment 612 is lower than the corresponding part of the inner elliptical segment 611, and on the vertical plane in the longitudinal direction of the steel arch beam 4, the inner elliptical segment 611 and the outer arc segment 612 are 2 are both in an arc shape with an opening upward, and the corresponding parts of the outer arc segment 612 and the inner elliptical segment 611 are at the same height. The inner elliptical segment 611 and the outer arc segment 612 are both provided with a plurality of cable clamps 62, and the cable clamp 62 comprises an upper clamping plate 621 and a lower clamping plate 622 clamped on the ring cable 61, and the upper clamping plate 621 and the lower clamping plate 622 are connected by bolts, and a steel cable ear plate 623 and a steel strut ear plate 624 are fixedly provided on the top of the upper clamping plate 621, and a plurality of outer cable ear plates are provided on the outer steel ring beam 1, and a plurality of outer strut ear plates are provided on the inner steel ring beam 2, and the two ends of the outer diameter cable 63 are respectively connected to the outer cable ear plate and the ring cable 61 through a pin shaft and a joint bearing node, and the outer diameter cable 63 is connected to the two end sections of the outer arc segment 612 and the inner elliptical segment 611,The two ends of the outer steel strut 65 are connected to the outer strut ear plate and the steel strut ear plate 624 through a pin shaft and a joint bearing node, respectively. The outer steel strut 65 between the two steel arch beams 4 is inclined, and the outer steel strut 65 outside the two steel arch beams 4 is vertical. An inner cable ear plate is also provided on the inner steel ring beam 2. The node of the annular aluminum structure 3 and the crescent-shaped aluminum structure 5 includes an aluminum rod 8 and an aluminum alloy node plate 9. The aluminum rod 8 is an H-shaped structure. The node plate 9 has two nodes and is respectively arranged at the top and bottom of the aluminum rod 8. The aluminum rod 8 is fixed to the node plate 9 by stainless steel rivets. The bottom ends of several node plates 9 are provided with inner strut ear plates. The two ends of the inner diameter cable 64 are respectively connected by a pin shaft and a joint bearing node. The inner cable ear plate and the ring cable 61 are connected, the inner diameter cable 64 is connected to the middle section of the inner elliptical section 611, the lower half of the tree-shaped support rod 66 is a vertical rod, and the upper half of the tree-shaped support rod 66 is a plurality of branch rods. The bottom end of the tree-shaped support rod 66 is connected to the steel support rod ear plate 624 through a pin shaft and a joint bearing node, and the upper half of the tree-shaped support rod 66 is connected to the inner support rod ear plate at different positions through a pin shaft and a joint bearing node. The damping ball joint support 7 includes a base 71, a lower support plate 72, a ball joint plate 73, an upper support plate 74 and a limit-grading unloading device 75. The base 71 is fixed on the steel structure, and the lower support plate 72 is placed on the base 71. The side of the lower support plate 72 Several springs are arranged on the side, and the spring support limit is the internal structure of the damping ball joint support 7, which belongs to the prior art and will not be described again here. The lower support plate 72 and the upper support plate 74 are interlocked, and the ball joint plate 73 is located between the lower support plate 72 and the upper support plate 74. The periphery of the upper support plate 74 is provided with graded limit rings. The lower support plate 72 and the upper support plate 74 are rectangular plates. The limit graded unloading device 75 includes a support vertical plate 751 fixed to the steel structure, and the support vertical rod is located on the side of the damping ball joint support 7 close to the inner steel ring beam 2. A plurality of reinforcing inclined plates 752 are also arranged between the support vertical plate 751 and the steel structure, which are located away from the damping ball joint support 7. The top of one side of the ball joint support 7 is threadedly connected with an adjusting screw 753, and one end of the adjusting screw 753 close to the upper support plate 74 is rotatably connected with a rotating seat 754. A number of rotating seats 754 are fixed on a U-shaped top support 755. The U-shaped top support 755 opens toward the upper support plate 74 and is adapted to the graded limiting ring. The graded limiting ring is embedded in the U-shaped top support 755. A mounting seat 756 is also fixedly arranged at the top of the support vertical plate 751 close to the damping ball joint support 7. A jack 757 is fixedly installed between the mounting seat 756 and the upper support plate 74. The mounting seat 756 is arranged along the width direction of the support vertical plate 751, and the jack 757 is located in the middle of the mounting seat 756.
[0054] The damping ball joint bearings 7 are evenly arranged in 36 pieces, which has a suitable number, a good supporting effect and a short construction period.
[0055] The outer diameter cables 63 are evenly distributed at 36 locations, the inner diameter cables 64 are evenly distributed at 18 locations, the outer steel support rods 65 are correspondingly arranged at 36 locations, and the tree-shaped support rods 66 are correspondingly arranged at 18 locations. The quantity is appropriate, the supporting effect is good, and the construction period is short.
[0056] Both ends of the outer diameter rope 63 and the inner diameter rope 64 are fork-ear type anchor heads, which is convenient for construction.
[0057] The ring rope 61 is divided into four sections for splicing. The section position is located at a distance offset from the intersection of the inner elliptical section 611 and the outer arc section 612 to the two ends of the inner elliptical section 611. The two ends of the ring rope 61 after the section are conical anchor heads. The adjacent conical anchor heads are connected by a joint device. The joint device includes two clamping plates located outside the two conical anchor heads. The two clamping plates are fixedly connected by screws and bolts, which is convenient for construction.
[0058] The cable-supporting structure 6 also includes four V-cables 68. The two outer diameter cables 63 on the vertical plane of the longitudinal vertical plane of the steel arch beam 4 are weak diameter cables 67. A reinforcing cable ear plate 1 is also provided on the cable clamp 62 below the weak diameter cable 67. A reinforcing cable ear plate 2 is provided on the outer steel ring beam 1 of the weak diameter cable 67 adjacent to the weak diameter cable 67. The two ends of the V-cable 68 are respectively connected to the reinforcing cable ear plate 1 and the reinforcing cable ear plate 2 through a pin shaft and a joint bearing node.
[0059] The annular aluminum structure 3 is a lattice shell structure with prismatic holes intersecting in an X shape, and the crescent-shaped aluminum structure 5 is a lattice shell structure with triangular holes intersecting in a rice shape.
[0060] The nodes of the annular aluminum structure 3 and the crescent-shaped aluminum structure 5 include an aluminum rod 8 and an aluminum alloy node plate 9. The aluminum rod 8 is an H-shaped structure. The node plates 9 have two nodes and are respectively arranged at the top and bottom ends of the aluminum rod 8. The aluminum rod 8 is fixed to the node plate 9 by stainless steel rivets.
[0061] H-shaped steel corbels 10 are welded to the outer steel ring beam 1 , the inner steel ring beam 2 and the steel arch beam respectively, the annular aluminum structure 3 and the crescent-shaped aluminum structure 5 are respectively connected to the steel corbels 10 , and the steel corbels 10 are fully bolted to the node plate 9 .
[0062] A construction method for a graded tensioned double-circle continuous arch beam lattice shell structure comprises the following steps:
[0063] Step 1: Use finite element analysis software to establish a construction simulation analysis model, analyze the stress of the overall structure and determine the specifications of parts that meet the structural strength;
[0064] Step 2: Install the damping ball joint support 7 on the steel structure, and hoist the outer steel ring beam 1 in sections and assemble it at high altitude;
[0065] Step 3: Arrange support measures for the inner steel ring beam 2 on the steel structure, use portal support, divide the working surface into four fan-shaped areas, and construct temporary support measures for the outer steel ring beam 1 and the inner steel ring beam 2 in each area in a counterclockwise direction;
[0066] Step 4: Install the inner steel ring beam 2, the inner steel ring beam 2 is hoisted in sections and assembled at high altitude;
[0067] Step 5: Install the annular aluminum structure 3, divide it into units, assemble the units on the ground and then hoist them, then assemble them in the air and connect them with the inner steel ring beam or the outer steel ring beam through steel brackets;
[0068] Step 6: Install the steel arch beam 4 on the steel structure by using single-point support;
[0069] Step 7: hoist the steel arch beam 4, hoist in sections, and assemble at high altitude;
[0070] Step 8: Install the crescent-shaped aluminum structure 5, divide it into units, assemble the units on the ground and then hoist them, then assemble them in the air and connect them with the inner steel ring beam or steel arch beam through steel brackets;
[0071] Step 9: Lay out the tire frame of the ring rope 61, and the tire frame of the ring rope 61 is offset 2.0m inward to facilitate the loosening and docking of the ring rope 61;
[0072] Step 10: hoist the sling 61 in sections, arrange multiple hoisting points on each section of the sling 61 for hoisting, adjust the slings 61 after all the hoisting is completed, and tighten the cable clamps 62 after all the slings 61 are adjusted and aligned;
[0073] Step 11: hoist the outer diameter rope 63, the inner diameter rope 64 and the V rope 68;
[0074] The outer diameter cable 63 and the inner diameter cable 64 are hoisted by staged tensioning.
[0075] First, it is necessary to calculate and determine the appropriate tensioning force, and perform tensioning according to the tensioning force of each stage calculated by construction simulation. Use the cable tension oil pressure gauge + monitoring value to calibrate the cable tension value, and use the total station to measure the deformation value to check the quality of the tensioning process. The tensioning equipment uses jack 757 and the matching oil pump and pressure gauge. A precision oil pressure gauge is used during tensioning. Before tensioning, the equipment and instruments of the tensioning system should be calibrated. During calibration, the jack 757 should actively load the test equipment and draw a chart for on-site use. During the tensioning process, the corresponding oil pressure is adjusted according to the internal force required by the construction process to accurately tension the cable to the required force.
[0076] In the first stage of tensioning, the outer diameter cable 63 and the inner diameter cable 64 are tensioned in sequence to 30% of the total tensioning force, and the adjusting screw 753 is rotated simultaneously with the auxiliary support of the jack 757 so that the adjusting screw 753 releases the displacement and stress of the lower support plate 72, the ball joint plate 73, the upper support plate 74 and the adjusting screw 753 together;
[0077] The second stage tensioning is to tension the outer diameter cable 63 and the inner diameter cable 64 in sequence to 60% of the total tensioning force, and the adjusting screw 753 is rotated at the same time with the auxiliary support of the jack 757 so that the adjusting screw 753 releases the displacement and stress of the lower support plate 72, the ball joint plate 73, the upper support plate 74 and the adjusting screw 753 together;
[0078] The third stage tensioning is to tension the outer diameter cable 63 and the inner diameter cable 64 in sequence to 90% of the total tensioning force, and the adjusting screw 753 is rotated at the same time with the auxiliary support of the jack 757 so that the adjusting screw 753 releases the displacement and stress of the lower support plate 72, the ball joint plate 73, the upper support plate 74 and the adjusting screw 753 together;
[0079] The fourth stage of tensioning is to tension the outer diameter cable 63 and the inner diameter cable 64 in sequence to 100% of the total tensioning force, and the adjusting screw 753 is rotated at the same time with the auxiliary support of the jack 757 so that the adjusting screw 753 releases the displacement and stress of the lower support plate 72, the ball joint plate 73, the upper support plate 74 and the adjusting screw 753 together;
[0080] Step 12: Remove the supporting measures of the inner steel ring beam 2 and the steel arch beam 4.
[0081] The beneficial effects of the present invention are as follows: 1. The structural system is a new type of combined structural system in which the upper layer is a single-layer aluminum alloy lattice shell and the lower layer is a cable-supported string system. Through the unique arrangement of the ring cable 61 and the unique arrangement of the radial cable, it is supported on the outer ring steel lattice shell structure to form a multi-system special-shaped space structure, so that the inner ring aluminum alloy lattice shell of the integral roof is a self-supporting integral force system, and only the damping ball hinge support 7 arranged on the inner ring beam of the outer ring steel lattice shell of the roof is required to complete the support;
[0082] 2. This structure is designed to create a double-ring continuous arch beam structure, cleverly arrange the positions of the two steel arch beams, and match the two steel arch beams with the outer steel ring beam and the inner steel ring beam in terms of structural shape, so as to achieve the effect of convenient construction and good appearance. A circular aluminum structure is arranged between the outer steel ring beam 1 and the inner steel ring beam 2, two steel arch beams 4 are symmetrically arranged on the outer steel ring beam 1 and the inner steel ring beam 2, and a crescent-shaped aluminum structure is arranged between the inner steel ring beam 2 and the steel arch beam 4, so as to form a structural form with an outer ring and an inner double arc as a whole, which not only improves the visual effect but also reduces the cost and construction difficulty. In addition, the inner steel ring beam 2, the outer steel ring beam 1 and the inner steel ring beam 2 are connected to form a stable structure to support and install the aluminum structure, so that the stability of the overall lattice shell is greatly improved.
[0083] 3. Based on the structural form of double-circle continuous arch beam, the double circles of this structure are in the form of curves, so that the steel arch beam 4, which is also a curve, realizes the continuity of the ring-shaped aluminum structure and the crescent-shaped aluminum structure after welding, which not only has sufficient visual effects on the multi-system special-shaped space structure, but also has a small overall inflection point angle and good continuity. The stability of the structure reduces the cost and construction difficulty. In addition, the inner steel ring beam 2 and the outer steel ring beam 1 are all circular steel beams, and the three are connected with the inner steel ring beam 2 to form a stable structure to support and install the aluminum structure. The stability of the overall lattice shell is greatly improved, which has opened up a precedent for the double-circle continuous arch beam lattice shell structure and has important significance in the field of building construction.
[0084] 4. The double-circle continuous arch beam structure and the unique arrangement of the ring cable 61, the unique arrangement of the radial cable and the design of the V cable 68 at the weak stress point greatly reduce the overall project cost and construction difficulty;
[0085] 5. A limit-limiting graded unloading device 75 located on the inner side of the damping ball joint support 7 is installed on the steel structure, and a graded tensioning method is used to perform graded stress unloading on the radial cable, which are 30%, 60%, 90% and 100% of the total tensioning force respectively, to maintain the stability of the structure and ensure that the structure does not deform or damage excessively during the construction process. The limit-limiting graded unloading device 75 is cooperated by the top support and the jack 757. During the unloading process, the jack 757 assists in the release of stress and facilitates the rotation adjustment of the adjustment screw after support, which not only ensures the structural stability of the stress release and is conducive to operation, but also achieves multiple effects and ensures structural stability and construction efficiency.
[0086] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that a technician familiar with the technical field can think of within the technical scope disclosed in the present invention should be covered within the protection scope of the present invention.
Claims
1. A graded tensioned double-circle continuous arch beam lattice shell structure, characterized in that: The invention comprises an outer steel ring beam (1), an inner steel ring beam (2), an annular aluminum structure (3), a steel arch beam (4), a crescent-shaped aluminum structure (5) and a cable-supported structure (6). The outer steel ring beam (1) and the inner steel ring beam (2) are arranged concentrically. The outer steel ring beam (1) is installed on the steel structure. The outer steel ring beam (1) is fixed on the steel structure through a plurality of damping ball joint supports (7). The annular aluminum structure (3) is installed between the outer steel ring beam (1) and the inner steel ring beam (2). The steel arch beam (4) is in an arch shape with an opening facing downward. Two steel arch beams (4) are arranged in parallel and are arranged symmetrically at the center of the inner steel ring beam (2). The two ends of the steel arch beam (4) are respectively welded to the inner side surface of the outer steel ring beam (1) and the steel arch beam (4) is welded to the top of the inner steel ring beam (2). The crescent-shaped aluminum structure (5) is provided at the center of the inner steel ring beam (2). The aluminum structure (5) is arranged between the steel arch beam (4) and the inner steel ring beam (2); the outer steel ring beam (1), the inner steel ring beam (2) and the steel arch beam (4) are all circular steel beams; on the vertical plane in the longitudinal direction of the steel arch beam (4), the inner steel ring beam (2) and the outer steel ring beam (1) are both in the shape of an arch with an opening downward; the inner steel ring beam (2) is higher than the outer steel ring beam (1); on the vertical plane in the longitudinal direction of the steel arch beam (4), the inner steel ring beam (2) and the outer steel ring beam (1) are both in the shape of an arch with an opening upward; the inner steel ring beam (2) is higher than the outer steel ring beam (1); the cable support structure (6) comprises a ring cable (61), a cable clamp (62), an outer diameter cable (63), an inner diameter cable (64), an outer steel support rod (65), and a tree-shaped support rod (66); the ring cable (61) comprises an inner elliptical segment (611) and outer arc segments (612) on both sides, the center point of the inner elliptical segment (611) is concentrically arranged with the outer steel ring beam (1) and the inner steel ring beam (2), the major axis of the inner elliptical segment (611) is parallel to the steel arch beam (4), the two ends of the major axis of the inner elliptical segment (611) are respectively located between the outer steel ring beam (1) and the inner steel ring beam (2), the two ends of the minor axis of the inner elliptical segment (611) are respectively located between the inner steel ring beam (2) and the steel arch beam (4), the inner elliptical segment (611) passes through the intersection of the inner steel ring beam (2) and the steel arch beam (4), the outer arc segments (612) are respectively located directly below the inner steel ring beam (2) outside the two steel arch beams (4), and the intersection of the inner elliptical segment (611) and the outer arc segment (612) is located at the inner Directly below the intersection of the steel ring beam (2) and the steel arch beam (4), on the vertical plane in the longitudinal direction of the steel arch beam (4), the inner elliptical segment (611) and the outer arc segment (612) are both in an arc shape with an opening upward, and the outer arc segment (612) is lower than the corresponding part of the inner elliptical segment (611). On the vertical plane of the vertical plane in the longitudinal direction of the steel arch beam (4), the inner elliptical segment (611) and the outer arc segment (612) are both in an arc shape with an opening upward, and the corresponding parts of the outer arc segment (612) and the inner elliptical segment (611) are at the same height. A plurality of cable clamps (62) are provided on the inner elliptical segment (611) and the outer arc segment (612), and the cable clamp (62) includes an upper clamping plate (621) and a lower clamping plate (622) clamped on the ring cable (61).The upper clamping plate (621) and the lower clamping plate (622) are connected by bolts. A steel cable ear plate (623) and a steel strut ear plate (624) are fixedly arranged on the top of the upper clamping plate (621). A plurality of outer cable ear plates are arranged on the outer steel ring beam (1). A plurality of outer strut ear plates are arranged on the inner steel ring beam (2). The two ends of the outer diameter cable (63) are respectively connected to the outer cable ear plate and the ring cable (61) through a pin shaft and a joint bearing node. The outer diameter cable (63) is connected to the two end sections of the outer arc section (612) and the inner elliptical section (611). The two ends of the outer steel strut (65) are respectively connected to the outer strut ear plate and the steel strut ear plate (624) through a pin shaft and a joint bearing node. The outer steel strut (65) between the two steel arch beams (4) is inclined. The outer steel support rod (65) on the outer side of the steel arch beam (4) is vertically connected, and an inner cable ear plate is also arranged on the inner steel ring beam (2). The nodes of the annular aluminum structure (3) and the crescent-shaped aluminum structure (5) include an aluminum rod (8) and an aluminum alloy node plate (9). The aluminum rod (8) is an H-shaped structure. The node plate (9) has two nodes which are respectively arranged at the top and bottom ends of the aluminum rod (8). The aluminum rod (8) is fixed to the node plate (9) by stainless steel rivets. The bottom ends of several node plates (9) are provided with inner support rod ear plates. The two ends of the inner diameter cable (64) are respectively connected to the inner cable ear plate and the ring cable (61) by a pin shaft and a joint bearing node. The inner diameter cable (64) is connected to the middle section of the inner elliptical section (611). The lower half of the tree-shaped support rod (66) is The upper part of the tree-shaped support rod (66) is a plurality of branch rods. The bottom end of the tree-shaped support rod (66) is connected to the steel support rod ear plate (624) through a pin shaft and a joint bearing node. The upper part of the tree-shaped support rod (66) is connected to the inner support rod ear plates at different positions through a pin shaft and a joint bearing node. The damping ball joint support (7) includes a base (71), a lower support plate (72), a ball joint plate (73), an upper support plate (74) and a limit-grading unloading device (75). The base (71) is fixed on the steel structure, the lower support plate (72) is placed on the base (71), and a plurality of springs are arranged on the side of the lower support plate (72). The lower support plate (72) and the upper support plate (74) are engaged, and the ball joint plate (73) is located at Between the lower support plate (72) and the upper support plate (74), a graded limiting ring is arranged on the periphery of the upper support plate (74); the lower support plate (72) and the upper support plate (74) are rectangular plates; the limiting graded unloading device (75) comprises a supporting vertical plate (751) fixed on the steel structure; the supporting vertical rod is located on the side of the damping ball joint support (7) close to the inner steel ring beam (2); a plurality of reinforcing inclined plates (752) located away from the damping ball joint support (7) are also arranged between the supporting vertical plate (751) and the steel structure; the top end of the supporting vertical plate (751) close to the damping ball joint support (7) is threadedly connected to an adjusting screw rod (753); one end of the adjusting screw rod (753) close to the upper support plate (74) is rotatably connected to a rotating seat (754);A plurality of rotating seats (754) are fixed on the U-shaped top support (755). The opening of the U-shaped top support (755) faces the upper support plate (74) and is matched with the graded limiting ring. The graded limiting ring is embedded in the U-shaped top support (755). A mounting seat (756) is fixedly arranged at the top of the support vertical plate (751) near the damping ball joint support (7). A jack (757) is fixedly installed between the mounting seat (756) and the upper support plate (74). The mounting seat (756) is arranged along the width direction of the support vertical plate (751). The jack (757) is located in the middle of the mounting seat (756).
2. The hierarchical tensioned double-circle continuous arch beam lattice shell structure according to claim 1, characterized in that: The damping ball joint supports (7) are evenly distributed in 36 pieces.
3. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 2, characterized in that: The outer diameter cables (63) are evenly distributed at 36 locations, the inner diameter cables (64) are evenly distributed at 18 locations, the outer steel support rods (65) are correspondingly arranged at 36 locations, and the tree-shaped support rods (66) are correspondingly arranged at 18 locations.
4. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 3, characterized in that: Both ends of the outer diameter rope (63) and the inner diameter rope (64) are fork-ear type anchor heads.
5. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 4, characterized in that: The ring rope (61) is divided into four sections for splicing, and the section positions are located at the intersection of the inner elliptical section (611) and the outer arc section (612) and offset a distance toward the two ends of the inner elliptical section (611). The two ends of the ring rope (61) after the sections are conical anchor heads, and the adjacent conical anchor heads are connected by a joint device. The joint device includes two clamping plates located outside the two conical anchor heads, and the two clamping plates are fixedly connected by screws and bolts.
6. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 5, characterized in that: The cable support structure (6) also includes four V-cables (68), two outer diameter cables (63) on the vertical plane of the longitudinal vertical plane of the steel arch beam (4) are weak diameter cables (67), a reinforcing cable ear plate 1 is also provided on the cable clamp (62) below the weak diameter cable (67), and a reinforcing cable ear plate 2 is provided on the outer steel ring beam (1) of the weak diameter cable (67) adjacent to the weak diameter cable (67), and two ends of the V-cable (68) are respectively connected to the reinforcing cable ear plate 1 and the reinforcing cable ear plate 2 through a pin shaft and a joint bearing node.
7. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 6, characterized in that: The annular aluminum structure (3) is a lattice shell structure with prismatic holes intersecting in an X shape, and the crescent-shaped aluminum structure (5) is a lattice shell structure with triangular holes intersecting in a rice shape.
8. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 7, characterized in that: The nodes of the annular aluminum structure (3) and the crescent-shaped aluminum structure (5) include an aluminum rod (8) and an aluminum alloy node plate (9); the aluminum rod (8) is an H-shaped structure; the node plates (9) have two nodes and are respectively arranged at the top and bottom ends of the aluminum rod (8); the aluminum rod (8) is fixed to the node plate (9) by stainless steel rivets.
9. The step-by-step tensioned double-circle continuous arch beam lattice shell structure according to claim 8, characterized in that: H-shaped steel brackets (10) are welded to the outer steel ring beam (1), the inner steel ring beam (2) and the steel arch beam respectively, the annular aluminum structure (3) and the crescent-shaped aluminum structure (5) are respectively connected to the steel brackets (10), and the steel brackets (10) are fully bolted to the node plate (9).
10. A construction method for a graded tensioned double-circle continuous arch beam lattice shell structure according to any one of claims 1 to 9, characterized in that: The following steps are included: Step 1: Use finite element analysis software to establish a construction simulation analysis model, analyze the stress of the overall structure and determine the specifications of parts that meet the structural strength; Step 2: Install the damping ball joint support (7) on the steel structure, and hoist the outer steel ring beam (1) in sections and assemble them at high altitude; Step 3: Arrange support measures for the inner steel ring beam (2) on the steel structure, use portal support, divide the working surface into four sector-shaped areas, and construct temporary support measures for the outer steel ring beam (1) and the inner steel ring beam (2) in each area in a counterclockwise direction; Step 4: Install the inner steel ring beam (2), the inner steel ring beam (2) is hoisted in sections and assembled at high altitude; Step 5: Install the annular aluminum structure (3), divide it into units, assemble the units on the ground and then hoist them, and then assemble them in the air and connect them with the inner steel ring beam or the outer steel ring beam through steel brackets; Step 6: Install the steel arch beam (4) on the steel structure, using single-point support; Step 7: hoisting the steel arch beam (4), hoisting in sections, and assembling at high altitude; Step 8: Install the crescent-shaped aluminum structure (5), divide it into units, assemble the units on the ground and then hoist them, and then assemble them in the air and connect them with the inner steel ring beam or steel arch beam through steel brackets; Step 9: Laying out the tire frame of the hoop rope (61), the tire frame of the hoop rope (61) is offset 2.0m inward to facilitate the loosening and docking of the hoop rope (61); Step 10, hoisting the sling (61) in sections, arranging multiple hoisting points on each section of the sling (61) for hoisting, adjusting the slings (61) after all the hoisting is completed, and tightening the cable clamp (62) after all the slings (61) are adjusted and aligned; Step 11: hoisting the outer diameter rope (63), the inner diameter rope (64) and the V rope (68); The outer diameter cable (63) and the inner diameter cable (64) are hoisted by staged tensioning. First, it is necessary to calculate and determine the appropriate tensioning force, and tensioning is performed according to the tensioning force of each stage calculated by the construction simulation. The cable force value is calibrated using a cable force oil pressure gauge + monitoring value, and the deformation value is measured using a total station to check the quality of the tensioning process. The tensioning equipment uses a jack (757) and a matching oil pump and pressure gauge. A precision oil pressure gauge is used during tensioning. Before tensioning, the equipment and instruments of the tensioning system should be calibrated. During calibration, the jack (757) should actively load the test equipment, and a chart should be drawn for on-site use. During the tensioning process, the corresponding oil pressure is adjusted according to the internal force required by the construction process to accurately tension the cable to the required force. In the first stage of tensioning, the outer diameter cable (63) and the inner diameter cable (64) are tensioned in sequence to 30% of the total tensioning force, and the adjusting screw (753) is rotated simultaneously with the auxiliary support of the jack (757) so that the adjusting screw (753) releases the displacement and stress of the lower support plate (72), the ball joint plate (73), the upper support plate (74) and the adjusting screw (753) together; In the second stage of tensioning, the outer diameter cable (63) and the inner diameter cable (64) are tensioned in sequence to 60% of the total tensioning force, and the adjusting screw (753) is rotated simultaneously with the auxiliary support of the jack (757) so that the adjusting screw (753) releases the displacement and stress of the lower support plate (72), the ball joint plate (73), the upper support plate (74) and the adjusting screw (753) together; The third stage of tensioning is to tension the outer diameter cable (63) and the inner diameter cable (64) in sequence to 90% of the total tensioning force, and to rotate the adjusting screw (753) at the same time with the auxiliary support of the jack (757) so that the adjusting screw (753) releases the displacement and stress of the lower support plate (72), the ball joint plate (73), the upper support plate (74) and the adjusting screw (753) together; The fourth stage of tensioning is to tension the outer diameter cable (63) and the inner diameter cable (64) in sequence to 100% of the total tensioning force, and to rotate the adjusting screw (753) at the same time with the auxiliary support of the jack (757) so that the adjusting screw (753) releases the displacement and stress of the lower support plate (72), the ball joint plate (73), the upper support plate (74) and the adjusting screw (753) together; Step 12: Remove the support measures of the inner steel ring beam (2) and the support measures of the steel arch beam (4).