A method for constructing a fabricated concrete wall

By using prefabricated construction methods, including 3D model segmentation, foundation pit excavation and base material filling, and concrete grouting, the problems of large site occupation and low efficiency in concrete wall construction have been solved, improving construction efficiency and shortening drying time.

CN117364963BActive Publication Date: 2026-02-06CHINA CONSTRUCTION INDUSTRIAL & ENERGY ENGINEERING GROUP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311316702.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-11
Publication Date
2026-02-06
Estimated Expiration
2043-10-11

AI Technical Summary

Technical Problem

The construction of concrete walls as a whole results in a large construction site occupation and low construction efficiency. Large-area concrete pouring leads to long drying time and complicated curing process.

Method used

The prefabricated construction method involves measuring and marking the location and dimensions of the wall, constructing a three-dimensional model to divide the wall, excavating the foundation pit and filling it with base material, fixing the wall components, adjusting them with a level, and pouring concrete grout to fill the gaps, thereby increasing strength and sealing.

Benefits of technology

It solves the problems of large construction site occupation and low construction efficiency, shortens the drying time of concrete walls, and simplifies the curing process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117364963B_ABST
    Figure CN117364963B_ABST
Patent Text Reader

Abstract

The application provides a prefabricated concrete wall construction method, and belongs to the technical field of building construction. The prefabricated concrete wall construction method comprises the following steps: constructing a three-dimensional model according to the size of a wall and the distance between the wall and surrounding objects, and segmenting the wall according to the three-dimensional model; constructing wall components according to the size of the three-dimensional model; excavating a foundation pit at a construction site of the wall, and filling a base material; fixing the wall components in the foundation pit, and pouring a concrete base; connecting and fixing the wall components and the components in the foundation pit; adjusting the wall plates horizontally and vertically by using a level; and filling the gaps between and around the wall plates by pouring concrete slurry after the installation of the wall plates is completed. The method can solve the problems that the overall construction of a concrete wall occupies a large construction site, has low construction efficiency, and a long drying time of the concrete wall and a complex maintenance process caused by large-area concrete pouring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of building construction technology, and more specifically, relates to a method for constructing prefabricated concrete walls. Background Technology

[0002] The construction of concrete walls is inseparable from the selection and use of concrete materials. Concrete is a building material composed of cement, aggregates, water, and admixtures mixed in a certain proportion. In concrete wall construction, it is necessary to understand the concrete mix proportions, strength, and other performance indicators, as well as the construction techniques and conditions. Concrete wall construction requires structural design, including the wall's height, thickness, and the location of openings. The structural design of the wall must consider factors such as load-bearing capacity, seismic performance, and temperature deformation to ensure the safety and stability of the wall during use. Formwork is often used in concrete wall construction to fix and shape the concrete. Formwork technology includes the selection and installation of formwork, the design and construction of support systems, and the removal and recycling of formwork. The quality and installation accuracy of the formwork directly affect the quality of the wall's formation. The construction of concrete walls requires the selection of appropriate construction techniques based on specific circumstances. This includes the processes of concrete pouring, vibration, and curing. A reasonable selection of construction techniques can improve construction efficiency and ensure the quality and strength of the wall. Concrete wall construction requires the use of a series of construction equipment and tools, such as concrete mixers, cranes, formwork support systems, electric vibrators, and levels. Safety management and quality control are crucial in concrete wall construction. Construction workers must adhere to relevant safety operating procedures to ensure site safety and personnel health. Simultaneously, rigorous quality control is essential, including quality inspection of concrete materials and verification of wall dimensions and flatness, to ensure the wall quality meets design requirements.

[0003] However, the overall construction of concrete walls will result in a large construction site occupation and low construction efficiency. Large-area concrete pouring will lead to a long drying time for concrete walls and a complicated curing process. Summary of the Invention

[0004] In view of this, the present invention provides a prefabricated concrete wall construction method, which can solve the problems of large construction site occupation and low construction efficiency caused by the overall construction of concrete walls, as well as the long drying time and complicated curing process caused by large-area concrete pouring.

[0005] This invention is implemented as follows:

[0006] This invention provides a method for constructing prefabricated concrete walls, comprising the following steps:

[0007] S10: Measure and mark the position and dimensions of the wall, and measure the distance and angle between the surrounding objects and the wall;

[0008] S20: Construction workers construct a three-dimensional model based on the dimensions of the wall and its distance from surrounding objects, and then divide the wall according to the three-dimensional model;

[0009] S30: Construction workers construct the wall components according to the dimensions divided by the three-dimensional model;

[0010] S40: Excavate a foundation pit at the construction site of the wall and fill it with base material;

[0011] S50: Fix the wall components in the foundation pit and pour a concrete foundation;

[0012] S60: Connect and fix the wall components to the components in the foundation pit in sequence;

[0013] S70: Use a level to adjust the wall panels horizontally and vertically;

[0014] S80: After the wall panels are installed, the gaps between and around the wall panels are filled with concrete grout to increase the strength and sealing of the wall.

[0015] S90: After the wall panel installation and fixing are completed, subsequent processing work is carried out.

[0016] The technical advantages of the prefabricated concrete wall construction method provided by this invention are as follows: The method involves measuring and marking the wall's position and dimensions, and measuring the distances and angles between the wall and surrounding objects; constructing a three-dimensional model based on the wall's dimensions and distances to surrounding objects, and then segmenting the wall according to the three-dimensional model; constructing wall components based on the dimensions of the segmented three-dimensional model; excavating a foundation pit at the construction site of the wall and filling it with base material; fixing the wall components in the foundation pit and pouring a concrete foundation; sequentially connecting and fixing the wall components to the components in the foundation pit; using a level to adjust the wall panels horizontally and vertically; after the wall panels are installed, filling the gaps between and around the wall panels with concrete grout to increase the wall's strength and sealing; and performing subsequent processing after the wall panels are installed and fixed. This method solves the problems of large construction site occupation and low construction efficiency caused by overall concrete wall construction, as well as the long drying time and complex curing process resulting from large-area concrete pouring.

[0017] Based on the above technical solution, the prefabricated concrete wall construction method of the present invention can be further improved as follows:

[0018] The construction workers construct a three-dimensional model of the wall based on its dimensions and distances from surrounding objects. The specific steps for dividing the wall using this three-dimensional model include:

[0019] The first step involves the construction workers using SolidWorks software to build a 3D model of the wall based on its dimensions and distance from surrounding objects. The 3D model of the wall is then scanned to generate a point cloud map.

[0020] The second step is for the construction workers to voxelize the initial point cloud to obtain multiple voxel cubes;

[0021] The third step involves the construction personnel selecting any of the aforementioned voxel cubes as the center cube, calculating the fitting plane normal vector in each adjacent cube adjacent to the center cube, and calculating the angle between each fitting plane normal vector and the center fitting plane normal vector of the center cube. When the angle is less than a set angle threshold, it is determined that the center cube and the adjacent cube can be fitted to form a cube fitting plane, and the preliminary point cloud of the cube fitting plane is determined.

[0022] The fourth step involves the construction personnel projecting the three-dimensional data of the cube fitting plane onto the cube fitting plane to form two-dimensional data. The two-dimensional data is then divided into grids, and the number of points in each grid is compared with a set point count threshold. Grids with a number of points greater than the threshold are numbered as new data points. These new data points are then numbered and classified based on a clustering algorithm to obtain the finely segmented plane of the cube fitting plane.

[0023] Fifth, the construction personnel repeat the steps of the third and fourth steps until the initial point cloud is traversed, all the fine segmentation planes are obtained, and the over-segmented planes in the fine segmentation planes are optimized;

[0024] The sixth step is for the construction workers to divide the three-dimensional model into planes.

[0025] Furthermore, the specific steps of excavating a foundation pit at the construction site of the wall and filling it with base material include:

[0026] The first step is to clean the construction area of ​​the wall;

[0027] The second step is to mark the dimensions of the wall on the construction site of the wall;

[0028] The third step is to determine the size and depth of the foundation pit based on the soil conditions and dimensional requirements of the construction site of the wall.

[0029] The fourth step is to use an excavator to excavate at the determined location of the foundation pit according to its size and depth;

[0030] Fifth, after excavation is completed, thoroughly clean the foundation pit;

[0031] The sixth step is to take appropriate measures based on the condition of the bottom of the foundation pit and the soil conditions.

[0032] Step 7: After treating the bottom of the foundation pit, begin filling with the base material;

[0033] Step 8: During the filling of the base material, ensure that the base material is filled evenly and densely.

[0034] Furthermore, the specific steps for determining the size and depth of the foundation pit based on the soil conditions and dimensional requirements of the construction site of the wall include:

[0035] The first step is to conduct a soil strength survey in the foundation pit to determine the soil type, water content, stability, and bearing capacity.

[0036] The second step is to determine the height, width, and thickness parameters of the wall based on the engineering design requirements and the wall size requirements.

[0037] The third step is to determine the depth of the foundation pit based on the soil survey and wall size requirements.

[0038] The fourth step is to determine the width of the foundation pit based on soil surveys, engineering requirements, and safety considerations.

[0039] Fifth, based on the soil conditions and the depth of the foundation pit, a support structure is installed at the bottom of the foundation pit to stabilize the pit wall.

[0040] The sixth step is to optimize the construction plan based on the obtained dimensions and depth of the foundation pit;

[0041] The depth of the foundation pit is greater than the height of the wall plus the thickness of the foundation bottom, in order to provide sufficient depth for construction and to ensure the stability of the foundation pit;

[0042] The width of the foundation pit is 1.5 to 2 times the height of the wall;

[0043] The length of the foundation pit is determined based on the required construction work space and surrounding environmental conditions.

[0044] Furthermore, the specific steps for taking corresponding treatment measures based on the condition of the bottom of the foundation pit and the soil conditions include:

[0045] The first step is to analyze the soil at the bottom of the foundation pit to determine its properties, thickness, and bearing capacity.

[0046] The second step is to determine the treatment method based on the soil conditions at the bottom of the foundation pit.

[0047] The third step is to carry out the construction according to the treatment method;

[0048] The method for determining the treatment based on the soil conditions at the bottom of the foundation pit includes:

[0049] For deeper foundation pits, the bearing capacity can be improved by reinforcing the fences and reinforcing the concrete pouring.

[0050] For shallower foundation pits, high-pressure jet grouting and cement mortar grouting are used to increase the bearing capacity.

[0051] For foundation pit bottoms with low bearing capacity, the bearing capacity can be improved by replacing with sand and gravel or cement concrete.

[0052] For foundation pits with poor soil quality, the soil quality can be improved through excavation and filling.

[0053] Furthermore, the specific steps for filling the base material after treating the bottom surface of the foundation pit include:

[0054] The first step is to prepare the base material;

[0055] The second step is to lay a layer of waterproof cloth at the bottom of the foundation pit and then pour the base material in layers to fix it on top of the waterproof cloth.

[0056] The third step is to compact the base material to ensure uniform filling.

[0057] Furthermore, the specific steps of laying a layer of waterproof fabric at the bottom of the foundation pit and then pouring and fixing the base material in layers on top of the waterproof fabric include:

[0058] The first step is to cut the waterproof fabric so that the cut waterproof fabric is larger than the bottom of the foundation pit;

[0059] The second step is to lay the waterproof cloth at the bottom of the pit, so that the reserved length around it fits tightly against the side wall of the pit.

[0060] The third step is to use a scraper to fix and compact the waterproof cloth along the bottom of the pit;

[0061] Fourth step, pour the adhesive onto the waterproof cloth and use the scraper to spread the adhesive evenly along the bottom of the pit;

[0062] Fifth step: Use a scraper to scrape off the adhesive on the waterproof cloth, so that the waterproof cloth is fixed to the bottom of the pit;

[0063] Step 6: Evenly lay a layer of limestone on the waterproof cloth, the thickness of which is 3-5cm;

[0064] Step 7: Pour waterproof adhesive onto the limestone to evenly fill and fix the gaps in the limestone.

[0065] Step 8: While the adhesive is not completely dry, lay a layer of fiberglass cloth on top of the adhesive so that the fiberglass cloth is fixedly connected to the limestone through the adhesive.

[0066] Furthermore, the adhesive is one of polyvinyl alcohol, epoxy resin, polyurethane, silane, polyacrylate, polyvinyl acetate, acrylate, polyurethane waterproof adhesive, epoxy resin waterproof adhesive, polyethylene waterproof adhesive, and polyurethane waterproof adhesive.

[0067] Furthermore, the specific steps for increasing the strength and sealing of the wall by filling the gaps between and around the wall panels with concrete grout after the wall panels are installed include:

[0068] The first step is to fix a template around the gaps between and around the wall panels, the template securing the wall tightly.

[0069] The second step is to use a pouring machine to pour concrete inside the template, maintaining a uniform pouring speed during the pouring process.

[0070] The third step is to process the poured concrete and wait for it to solidify.

[0071] Fourth step, remove the template;

[0072] The fifth step is to cure the surface of the concrete wall.

[0073] Furthermore, the specific steps for treating the poured concrete and waiting for it to solidify include:

[0074] The vibrator is attached to the formwork of the poured concrete. The angle and position of the vibrator are adjusted as needed. During the concrete pouring process, the vibrator is used to perform directional vibration to lift air bubbles in the concrete from the flow area of ​​the concrete to the pouring surface and expel the air from the concrete.

[0075] The specific steps for curing the surface of the concrete wall include:

[0076] Within 24 hours after the concrete is poured, water is sprayed onto the concrete multiple times to keep the surface of the mixed soil moist. The water spraying process is repeated 3 to 5 times a day for 7 to 10 days.

[0077] Compared with existing technologies, the beneficial effects of the prefabricated concrete wall construction method provided by this invention are as follows: The method involves measuring and marking the wall's position and dimensions, and measuring the distance and angle between the wall and surrounding objects; constructing a three-dimensional model based on the wall's dimensions and distances to surrounding objects, and then segmenting the wall according to the three-dimensional model; constructing wall components based on the dimensions of the segmented three-dimensional model; excavating a foundation pit at the construction site of the wall and filling it with base material; fixing the wall components in the foundation pit and pouring a concrete foundation; sequentially connecting and fixing the wall components to the components in the foundation pit; using a level to adjust the wall panels horizontally and vertically; after the wall panels are installed, filling the gaps between and around the wall panels with concrete grout to increase the wall's strength and sealing; and performing subsequent processing work after the wall panels are installed and fixed. This method solves the problems of large construction site occupation and low construction efficiency caused by overall concrete wall construction, as well as the long drying time and complex curing process resulting from large-area concrete pouring. Attached Figure Description

[0078] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments of the present invention will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0079] Figure 1 This is a flowchart illustrating the operation of a prefabricated concrete wall construction method. Detailed Implementation

[0080] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings.

[0081] like Figure 1 The diagram shows an operation flowchart of a prefabricated concrete wall construction method provided by the present invention, which includes the following steps:

[0082] S10: Measure and mark the location and dimensions of the wall, and measure the distance and angle between the surrounding objects and the wall;

[0083] S20: Construction workers construct a three-dimensional model based on the dimensions of the wall and its distance from surrounding objects, and then divide the wall according to the three-dimensional model;

[0084] S30: Construction workers construct wall components based on the dimensions divided from the 3D model;

[0085] S40: Excavate a foundation pit at the construction site of the wall and fill it with base material;

[0086] S50: Fix the wall components in the foundation pit and pour the concrete foundation;

[0087] S60: Connect and fix the wall components to the components in the foundation pit in sequence;

[0088] S70: Use a level to adjust the wall panels horizontally and vertically;

[0089] S80: After the wall panels are installed, concrete grout is poured to fill the gaps between and around the wall panels, increasing the strength and sealing of the wall.

[0090] S90: After the wall panel installation and fixing are completed, proceed with the follow-up processing.

[0091] During use, measure and mark the wall's location and dimensions, and measure the distances and angles between the wall and surrounding objects; construct a 3D model based on the wall's dimensions and distances to surrounding objects, and then segment the wall according to the 3D model; construct wall components based on the dimensions of the segmented 3D model; excavate foundation pits at the construction sites of the wall and fill them with base material; fix the wall components in the foundation pits and pour concrete foundations; connect and fix the wall components to the components in the foundation pits in sequence; use a level to adjust the wall panels horizontally and vertically; after the wall panels are installed, fill the gaps between and around the wall panels with concrete grout to increase the wall's strength and sealing; after the wall panels are installed and fixed, proceed with subsequent processing work.

[0092] In the aforementioned technical solution, the construction workers construct a three-dimensional model based on the dimensions of the wall and its distance from surrounding objects. The specific steps for dividing the wall based on the three-dimensional model include:

[0093] The first step is for construction workers to use SolidWorks software to build a 3D model based on the dimensions of the wall and its distance from surrounding objects, and then scan the 3D model of the wall to form a point cloud map.

[0094] The second step is for the construction workers to voxelize the initial point cloud to obtain multiple voxel cubes;

[0095] The third step involves the construction personnel selecting any voxel cube as the center cube, calculating the fitting plane normal vector in each adjacent cube of the center cube, and calculating the angle between each fitting plane normal vector and the center fitting plane normal vector of the center cube. When the angle is less than the set angle threshold, it is determined that the center cube and the adjacent cube can be fitted to form a cube fitting plane, and the preliminary point cloud of the cube fitting plane is determined.

[0096] The fourth step involves the construction workers projecting the three-dimensional data of the cube fitting plane onto the cube fitting plane to form two-dimensional data. The two-dimensional data is then divided into grids, and the number of points in each grid is compared with a set point count threshold. Grids with a number of points greater than the threshold are numbered as new data points. These new data points are then numbered and classified based on a clustering algorithm to obtain a finely segmented plane for the cube fitting plane.

[0097] Fifth, the construction workers repeat the steps of the third and fourth steps until they have traversed the initial point cloud, obtained all the fine segmentation planes, and optimized the over-segmented planes in the fine segmentation planes;

[0098] The sixth step is for the construction workers to divide the 3D model into planar sections.

[0099] Furthermore, in the above technical solution, the specific steps for excavating a foundation pit at the construction site of the wall and filling it with base material include:

[0100] The first step is to clean the construction area of ​​the wall;

[0101] The second step is to mark the dimensions of the wall on the construction site of the wall;

[0102] The third step is to determine the size and depth of the foundation pit based on the soil conditions and dimensional requirements of the construction site of the wall.

[0103] The fourth step is to use an excavator to excavate at the determined location of the foundation pit, according to the size and depth of the pit.

[0104] Fifth, after excavation is completed, thoroughly clean the foundation pit;

[0105] The sixth step is to take appropriate measures based on the condition of the bottom of the foundation pit and the soil conditions.

[0106] Step 7: After treating the bottom of the foundation pit, begin filling with the base material;

[0107] Step 8: During the filling of the base material, ensure that the base material is filled evenly and densely.

[0108] Furthermore, in the above technical solution, the specific steps for determining the size and depth of the foundation pit based on the soil conditions and dimensional requirements of the construction site of the wall include:

[0109] The first step is to conduct a soil strength survey in the foundation pit to determine the soil type, moisture content, stability, and bearing capacity.

[0110] The second step is to determine the height, width, and thickness parameters of the wall based on the engineering design requirements and wall size requirements.

[0111] The third step is to determine the depth of the foundation pit based on the soil survey and wall size requirements.

[0112] The fourth step is to determine the width of the foundation pit based on soil surveys, engineering requirements, and safety considerations.

[0113] The fifth step is to set up a support structure at the bottom of the pit to stabilize the pit walls, based on the soil conditions and the depth of the pit.

[0114] The sixth step is to optimize the construction plan based on the obtained dimensions and depth of the foundation pit;

[0115] The depth of the foundation pit is greater than the height of the wall plus the thickness of the foundation bottom, in order to provide sufficient depth for construction and to ensure the stability of the foundation pit;

[0116] The width of the foundation pit is 1.5 to 2 times the height of the wall;

[0117] The length of the foundation pit is determined based on the required construction work space and the surrounding environmental conditions.

[0118] Furthermore, in the above technical solution, the specific steps for taking corresponding treatment measures based on the condition of the bottom of the foundation pit and the soil conditions include:

[0119] The first step is to analyze the soil at the bottom of the foundation pit to determine its properties, thickness, and bearing capacity.

[0120] The second step is to determine the treatment method based on the soil conditions at the bottom of the foundation pit;

[0121] The third step is to carry out the construction according to the treatment method;

[0122] Based on the soil conditions at the bottom of the foundation pit, the treatment methods include:

[0123] For deeper foundation pits, the bearing capacity can be improved by reinforcing the fences and reinforcing the concrete pouring.

[0124] For shallower foundation pits, high-pressure jet grouting and cement mortar grouting are used to increase the bearing capacity.

[0125] For foundation pit bottoms with low bearing capacity, the bearing capacity can be improved by replacing with sand and gravel or cement concrete.

[0126] For foundation pits with poor soil quality, the soil quality can be improved through excavation and filling.

[0127] Furthermore, in the above technical solution, the specific steps for filling the base material after treating the bottom surface of the foundation pit include:

[0128] The first step is to prepare the base material;

[0129] The second step is to lay a layer of waterproof cloth at the bottom of the foundation pit and then pour the base material in layers and fix it on top of the waterproof cloth.

[0130] The third step is to vibrate the base material to ensure uniform filling.

[0131] Furthermore, in the above technical solution, the specific steps of laying a layer of waterproof fabric at the bottom of the foundation pit and then pouring and fixing the base material on top of the waterproof fabric in layers include:

[0132] The first step is to cut the waterproof fabric so that the cut fabric is larger than the bottom of the pit.

[0133] The second step is to lay the waterproof cloth at the bottom of the pit, ensuring that the reserved length around it fits tightly against the side wall of the pit.

[0134] The third step is to use a scraper to fix and compact the waterproof fabric along the bottom of the pit;

[0135] Fourth step: Pour the adhesive onto the waterproof cloth and use a scraper to spread the adhesive evenly along the bottom of the pit;

[0136] Fifth step: Use a scraper to scrape off the adhesive on the waterproof cloth, so that the waterproof cloth is fixed to the bottom of the pit;

[0137] Step 6: Evenly lay a layer of limestone on the waterproof cloth, with a thickness of 3-5cm.

[0138] Step 7: Pour waterproof adhesive onto the limestone, ensuring the adhesive evenly fills and secures the limestone crevices.

[0139] Step 8: Before the adhesive is completely dry, lay a layer of fiberglass cloth on top of the adhesive so that the fiberglass cloth is fixedly connected to the limestone by the adhesive.

[0140] Furthermore, in the above technical solution, the adhesive is one of polyvinyl alcohol, epoxy resin, polyurethane, silane, polyacrylate, polyvinyl acetate, acrylate, polyurethane waterproof adhesive, epoxy resin waterproof adhesive, polyethylene waterproof adhesive, and polyurethane waterproof adhesive.

[0141] Furthermore, in the above technical solution, after the wall panels are installed, the specific steps for filling the gaps between and around the wall panels with concrete grout to increase the strength and sealing of the wall include:

[0142] The first step is to fix the template around the gaps between and around the wall panels, so that the template can tightly fix the wall.

[0143] The second step is to use a pouring machine to pour concrete inside the formwork, maintaining a uniform pouring speed during the pouring process.

[0144] The third step is to treat the poured concrete and wait for it to solidify.

[0145] Step four: Remove the formwork;

[0146] The fifth step is to cure the surface of the concrete wall.

[0147] Furthermore, in the above technical solution, the specific steps for treating the poured concrete and waiting for it to solidify include:

[0148] The vibrator is attached to the formwork of the poured concrete. The angle and position of the vibrator are adjusted as needed. During the concrete pouring process, the vibrator is used to perform directional vibration to lift air bubbles in the concrete from the flow area to the pouring surface and expel the air from the concrete.

[0149] The specific steps for curing the surface of a concrete wall include:

[0150] Within 24 hours after the concrete is poured, spray water on the concrete multiple times to keep the surface of the mixed soil moist. Spray water 3 to 5 times a day for 7 to 10 days.

[0151] Example:

[0152] Construction workers measure and mark the location and dimensions of the wall, and measure the distances and angles between the wall and surrounding objects; leave a 1-2m distance around the wall; construct a 3D model based on the wall's dimensions and distances to surrounding objects, and then divide the wall according to the 3D model; construct wall components based on the dimensions of the 3D model; the wall components are concrete blocks with length, width, and height of 1-3m; clean the construction area of ​​the wall; mark the wall dimensions on the construction area; determine the size and depth of the foundation pit based on the soil conditions and dimensional requirements of the construction area; the foundation pit depth is greater than the wall height plus the thickness of the foundation bottom to provide sufficient depth for construction and ensure the stability of the foundation pit; the foundation pit width is 1.5 to 2 times the wall height; the foundation pit length is determined based on the required construction work space and surrounding environmental conditions; use an excavator to excavate at the determined foundation pit location according to the dimensions and depth of the foundation pit; after excavation, [the foundation pit is then inspected]. The pit is thoroughly cleaned; appropriate treatment measures are taken based on the condition of the pit bottom and the soil quality; for deeper pits, the bearing capacity is improved by reinforcing the fence and pouring reinforced concrete; for shallower pits, the bearing capacity is increased by high-pressure jet grouting and cement mortar grouting; for pits with low bearing capacity, the bearing capacity is improved by sand and gravel replacement and cement concrete replacement; for pits with poor soil quality, the soil quality is improved by excavation and filling; after treating the pit bottom, the base material is filled; during the filling process, the base material is ensured to be filled evenly and densely; the wall components are fixed in the pit, and the concrete foundation is poured; the wall components are connected and fixed to the components in the pit in sequence; the wall panels are adjusted horizontally and vertically using a level; after the wall panels are installed, the gaps between and around the wall panels are filled with concrete grout to increase the strength and sealing of the wall; after the wall panels are installed and fixed, subsequent treatment work is carried out.

[0153] Specifically, the principle of this invention is as follows: Measuring and marking the position and dimensions of the wall; measuring the distance and angle between the wall and surrounding objects; constructing a three-dimensional model based on the wall's dimensions and distances to surrounding objects; segmenting the wall based on the three-dimensional model; constructing wall components based on the dimensions of the segmented three-dimensional model; excavating a foundation pit at the construction site of the wall and filling it with base material; fixing the wall components in the foundation pit and pouring a concrete foundation; sequentially connecting and fixing the wall components to the components in the foundation pit; using a level to adjust the wall panels horizontally and vertically; after the wall panels are installed, filling the gaps between and around the wall panels with concrete grout to increase the wall's strength and sealing; and performing subsequent processing work after the wall panels are installed and fixed.

Claims

1. A method of constructing a fabricated concrete wall, characterised by, The method comprises the following steps: S10: measuring and marking the wall position and size, measuring the distance and angle of the surrounding objects to the wall; S20: the construction personnel constructs a three-dimensional model according to the size of the wall and the distance of the surrounding objects to the wall, and divides the wall according to the three-dimensional model; S30: the construction personnel constructs the wall components according to the size of the three-dimensional model division; S40: excavate the foundation pit at the construction site of the wall, and fill the base material; S50: fix the wall components in the foundation pit, and pour the concrete foundation; S60: sequentially connect and fix the wall components and the components in the foundation pit; S70: use the level to adjust the wallboard horizontally and vertically; S80: after the wallboard installation is completed, fill the gaps between and around the wallboard with grouting concrete slurry to increase the strength and sealing performance of the wall; S90: after the wallboard installation and fixation are completed, carry out subsequent processing work; The specific operation steps of the construction personnel constructing a three-dimensional model according to the size of the wall and the distance of the surrounding objects to the wall, and dividing the wall according to the three-dimensional model include: First step, the construction personnel uses SolidWorks software to construct a three-dimensional model according to the size of the wall and the distance of the surrounding objects to the wall, scans the three-dimensional graph of the wall, and forms a point cloud graph; Second step, the construction personnel voxelizes the initial point cloud to obtain a plurality of voxel cubes; Third step, the construction personnel selects any voxel cube as a center cube, calculates the fitting plane normal vector in each adjacent cube adjacent to the center cube, and calculates the included angle between each fitting plane normal vector and the center fitting plane normal vector of the center cube. When the included angle is less than a set included angle threshold, it is determined that the center cube and the adjacent cube can be fitted to form a cube fitting plane, and the preliminary point cloud of the cube fitting plane is determined; Fourth step, the construction personnel projects the three-dimensional data of the cube fitting plane to the cube fitting plane to form two-dimensional data, divides the grid of the two-dimensional data, and compares the number of grid points with a set point number threshold. The grid number with a point number greater than the point number threshold is formed as a new data point, and the new data point is numbered and classified based on a clustering algorithm to obtain the fine division plane of the cube fitting plane; Fifth step, the construction personnel repeats the third and fourth steps until the initial point cloud is traversed, and obtains all the fine division planes, and optimizes the over-division planes in the fine division planes; Sixth step, the construction personnel performs plane division on the three-dimensional model.

2. The method of claim 1, wherein, The specific steps of excavating the foundation pit at the construction site of the wall and filling the base material include: First step, clean the construction site of the wall; Second step, mark the size of the wall on the construction site of the wall; Third step, determine the size and depth of the foundation pit according to the soil conditions and size requirements of the construction site of the wall; The fourth step is to use the excavator to excavate according to the size and depth of the foundation pit at the determined position of the foundation pit; The fifth step is to thoroughly clean the foundation pit after excavation; The sixth step is to take appropriate treatment measures according to the condition of the bottom surface of the foundation pit and the soil condition; The seventh step is to start filling the base material after the bottom surface of the foundation pit is treated; The eighth step is to ensure uniform and dense filling of the base material during the filling process.

3. The method of claim 2, wherein the method further comprises: The specific steps for determining the size and depth of the foundation pit according to the soil condition and size requirement of the construction site of the wall include: The first step is to investigate the soil strength in the foundation pit to determine the type, water content, stability, and bearing capacity of the soil in the foundation pit; The second step is to determine the height, width, and thickness parameters of the wall according to the engineering design requirements and the size requirements of the wall; The third step is to determine the depth of the foundation pit based on the soil investigation and size requirements of the wall; The fourth step is to determine the width of the foundation pit based on the soil investigation, engineering requirements, and safety considerations; The fifth step is to set up a support structure at the bottom of the foundation pit to stabilize the foundation pit wall according to the soil condition and depth of the foundation pit; The sixth step is to optimize the construction plan according to the obtained size and depth of the foundation pit; The depth of the foundation pit is greater than the height of the wall plus the thickness of the foundation bottom, which provides sufficient depth for construction and ensures the stability of the foundation pit; The width of the foundation pit is 1.5 to 2 times the height of the wall; The length of the foundation pit is determined according to the required construction operation space and surrounding environmental conditions.

4. The method of claim 3, wherein the method further comprises: The specific steps for taking appropriate treatment measures according to the condition of the bottom surface of the foundation pit and the soil condition include: The first step is to analyze the soil quality of the bottom surface of the foundation pit to determine the properties, thickness, and bearing capacity of the soil at the bottom of the foundation pit; The second step is to determine the treatment method according to the soil condition of the bottom surface of the foundation pit; The third step is to perform construction according to the treatment method; Determining the treatment method according to the soil condition of the bottom surface of the foundation pit includes: For deeper foundation pit bottoms, reinforce the fence and pour concrete to increase the bearing capacity; For shallower foundation pit bottoms, use high-pressure jet grouting and cement mortar grouting treatment to increase the bearing capacity; For foundation pit bottoms with low bearing capacity, use sand replacement and cement concrete replacement treatment to improve the bearing capacity; For poor soil foundation pit bottoms, use excavation and filling treatment to improve the soil quality.

5. The method of claim 4, wherein the method further comprises: The specific steps for filling the base material after treating the bottom surface of the foundation pit include: The first step is to prepare the base material; The second step is to lay a layer of waterproof cloth at the bottom of the foundation pit and then pour and fix the base material layer by layer on top of the waterproof cloth; The third step is to vibrate the base material to ensure uniform filling of the base material.

6. The method of claim 5, wherein the method further comprises: The specific steps for laying a layer of waterproof cloth at the bottom of the foundation pit and then pouring and fixing the base material layer by layer on top of the waterproof cloth include: The first step is to cut the waterproof cloth so that the cut waterproof cloth is larger than the size of the bottom of the foundation pit; The second step is to lay the waterproof cloth at the bottom of the foundation pit so that the reserved length around the side wall of the foundation pit tightly fits the side wall. Third step, the waterproof cloth is fixed and compacted along the bottom of the foundation pit by a scraper; Fourth step, the adhesive is poured on the waterproof cloth, and the scraper is used to evenly spread the adhesive along the bottom of the foundation pit; Fifth step, the adhesive on the waterproof cloth is scraped off by the scraper, so that the waterproof cloth is fixed on the bottom of the foundation pit; Sixth step, a layer of limestone with a thickness of 3-5 cm is evenly laid on the waterproof cloth; Seventh step, waterproof adhesive is poured on the limestone, so that the adhesive evenly fills the gaps of the limestone and fixes it; Eighth step, when the adhesive is not completely dry, a layer of glass fiber cloth is laid on the top of the adhesive, so that the glass fiber cloth is fixedly connected with the limestone through the adhesive.

7. The method of claim 6, wherein the method further comprises: The adhesive is one of polyvinyl alcohol, epoxy resin, polyurethane, silane, polyacrylate, polyvinyl acetate, acrylate, polyurethane waterproof adhesive, epoxy resin waterproof adhesive, polyethylene waterproof adhesive, and polyurethane waterproof adhesive.

8. The method of claim 7, wherein the method further comprises: After the wallboard is installed, the specific steps for filling the gaps between and around the wallboard with concrete slurry to increase the strength and sealing performance of the wall body include: First step, fix the formwork around the gaps between and around the wallboard, which tightly fixes the wall body; Second step, use a pouring machine to pour concrete inside the formwork, and keep the pouring speed uniform during pouring; Third step, treat the poured concrete and wait for it to solidify; Fourth step, remove the formwork; Fifth step, maintain the surface of the concrete wall.

9. The method of claim 8, wherein the method further comprises: The specific steps for treating the poured concrete and waiting for it to solidify include: Attach a vibrator to the formwork of the poured concrete, adjust the angle and position of the vibrator as needed, and use the vibrator for directional vibration during concrete pouring to make the air bubbles in the concrete rise from the flowing area of the concrete to the pouring surface, and discharge the air in the concrete; The specific steps for maintaining the surface of the concrete wall include: Within 24 hours after the completion of concrete pouring, spray water on the concrete several times to keep the surface of the mixed soil moist, and the spraying process is 3 to 5 times a day for 7 to 10 days.

Citation Information

Patent Citations

  • Architectural engineering construction device based on 3D printing technology and application method

    CN103967276A

  • BIM (building information modeling)-based block standardized construction method

    CN104314310A