A monitoring system for floating mortise and tenon type segments in shield tunnels
By setting up monitoring units and data models in the shield tunnel to identify and analyze the floating situation of the pipe sheet, the problems of upload monitoring delay and construction accuracy deviation caused by changes in working conditions in the existing technology are solved, and more efficient monitoring is achieved and construction operations.
Patent Information
- Application Number
- CN202410710935.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-04
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing shield tunnel mortise and tenon pipe sheets are difficult to accurately identify when working conditions change, resulting in monitoring delays or construction accuracy deviations.
A shield tunnel mortise and tenon type pipe sheet floating monitoring system is designed, including monitoring unit, data acquisition and conversion module, data model establishment module, data result feedback module and early warning processing module. Through multi-condition analysis and mathematical calculation model, Identify the static and dynamic pressure rise situations, and promptly feedback and adjustments.
The accuracy and efficiency of pipe sheet floating monitoring are improved, problems during construction are discovered in a timely manner, and construction accuracy and safety are ensured.
Smart Images

Figure CN118292948B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shield tunnel segment monitoring, and in particular to a shield tunnel mortise and tenon type segment floating monitoring system. Background Art
[0002] The reference patent name is: A shield tunnel segment floating monitoring equipment, monitoring system and monitoring method (patent publication number: CN114370857A, patent publication date: 2022-04-19), including a reference water tank for being set in a stable reference position, a floating monitoring device and a connecting hose for being set on the segment to be monitored. The reference liquid level tank and multiple floating monitoring devices are connected in series through a connecting hose. The liquid level sensor is arranged in each floating monitoring device to detect the liquid level of the monitoring liquid, the wireless sensor node is connected to the liquid level sensor, and multiple wireless transmission nodes are communicated and connected to the data acquisition node. Multiple data acquisition nodes are communicated and connected to the monitoring terminal through communication equipment, providing a complete, efficient, convenient and automated monitoring device and monitoring method, which does not require line of sight conditions and can perform high-precision, real-time and continuous monitoring of multi-ring segments and automatically transmit records and early warnings, which plays a positive role in understanding the floating laws and monitoring and early warning of segments in shield tunnel construction and operation.
[0003] Based on the description in the above-mentioned documents, the existing mortise and tenon type segments of shield tunnels float due to changes in working conditions. If the current floating is simply observed through images, it cannot be identified as static pressure floating or dynamic pressure floating, so that the floating problem cannot be discovered in time during the monitoring process, or the floating problem continues to accumulate and causes deviations in subsequent construction accuracy. For this reason, the present invention provides a shield tunnel mortise and tenon type segment floating monitoring system. Summary of the invention
[0004] In view of the shortcomings of the prior art, the present invention provides a shield tunnel mortise and tenon segment flotation monitoring system, which solves the problem that the existing shield tunnel mortise and tenon segment flotation occurs due to changes in working conditions. If the current flotation is simply observed through images, it cannot be identified as static pressure flotation or dynamic pressure flotation, so that the flotation problem cannot be discovered in time during the monitoring process, or the flotation problem continues to accumulate, resulting in deviations in subsequent construction accuracy.
[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: A shield tunnel mortise and tenon type segment floating monitoring system, comprising:
[0006] The monitoring unit includes a variety of measuring and monitoring instruments, which are used to measure the position and various parameter data of the mortise and tenon type segments in the shield tunnel, and transmit them to the segment floating monitoring system for processing;
[0007] The segment floating monitoring system receives and classifies the parameters, and completes the establishment of the monitoring model based on the required data analysis, and records and displays the floating conditions generated by the data-adjusted model, and includes:
[0008] The data acquisition and conversion module collects and receives the segment shape data, segment parameter data, unit type, unit constant, and material parameters in the tunnel, and stores them in the monitoring database after classification;
[0009] The data model building module sets up a simulation model, and uses numerical simulation and theoretical calculation methods to conduct multi-condition analysis on the floating of the pipe segments, establish a mathematical calculation model, and calculate and verify the floating of the pipe segments;
[0010] The data result feedback module generates instructions for segment repair or operation adjustment prevention based on the calculation results and the floating situation of the segment, and provides feedback to the display panel and early warning processing module;
[0011] The real-time update module updates parameters and completes the model update based on the data replacement at the monitoring location or based on instructions for segment repair or operation adjustment prevention;
[0012] The early warning processing module notifies personnel to carry out special construction according to actual on-site working conditions and parameters when the pipe segment floats and the floating displacement distance exceeds the early warning range;
[0013] The display panel presents the data generated by data collection, monitoring, updating and early warning in the form of data and charts, and completes the output of commands through human control.
[0014] Preferably, the measuring method of the monitoring unit is:
[0015] A1. First, plan the tunnel centerline according to the construction guide wire, and determine the centerline elevation according to the plane. Then, use a total station to measure the actual clearance parameters in the tunnel and compare them with the tunnel design section to obtain the shape of the segment after construction.
[0016] A2. Use a level, a level, an aluminum ruler, and a reflective sheet. Stick a reflective sheet at the midpoint of the level and measure the three-dimensional coordinates of the segment. Then calculate the distance from the reflective sheet to the center of the circle based on the segment radius and the length of the level, which is the measured three-dimensional coordinates of the center of the circle. Then compare the measured coordinates with the designed coordinates to determine the displacement of the segment in all directions.
[0017] A3. Continue to use sensors and high-definition cameras to complete the collection of unit types, unit constants, and material parameters in the tunnel.
[0018] Preferably, the data model building module performs the following analysis operations on the building of the simulation model:
[0019] B1. Complete the simplified construction of the simulation model based on the collected segment parameters and tunnel parameters, and meet the following model simplification conditions:
[0020] The soil layer is simplified to 6 layers, and the soil parameters are taken as the average value within the tunnel depth range. The tunnel slope and the connection of the segments are set to be flat slopes. The segments are taken as a whole ring, and the bolt joint effect between the segments is ignored. The groundwater seepage is simplified to buoyancy, and the extrusion force of the segments on the overburden acts on the contact surface between the segments and the soil.
[0021] B2. Then, based on the model, select the area to be analyzed, perform mesh refinement, and analyze the effects of slurry properties, soil properties, and the distance of the segment from the shield tail on the floating deformation of the segment.
[0022] B3. Set multiple monitoring nodes on the simulation model, and perform result analysis operations based on the data changes obtained from the monitoring nodes of the model by changing different working conditions.
[0023] Preferably, the operation steps of performing mesh refinement on the analysis area in B2 are:
[0024] b21. Perform mesh division on the analysis area, find the part that needs to be meshed, and refine the local structure;
[0025] b22. The explicit integral solver is used to automatically increase the time increment step to track the propagation of stress waves in the regional elastic body, thereby amplifying the quality of the grid and refining the specific structure of the grid part. The time taken by the stress wave to pass through the minimum grid unit, that is, the time increment step, is calculated as follows:
[0026] ;
[0027] and ;
[0028] Finally we get: ;
[0029] in, represents the time increment step; represents the propagation speed of stress wave in the unit cell; Represents the minimum grid unit length; Represents the elastic modulus of the material; Represents the material density; stands for Poisson's ratio.
[0030] Preferably, the setting for the working condition in B3 is:
[0031] b31. Three basic working conditions are set, I, II and III, and the data of Young's modulus of slurry, elastic modulus of soil layer and distance of segment from shield tail are the same for the three basic working conditions;
[0032] b32. Analyze the changes of the model by adjusting the working conditions, which includes the following 3 types:
[0033] The basic working condition of group I was selected as a reference, and the slurry Young's modulus was used as a variable, and the slurry Young's modulus value was continuously increased to obtain the floating data of the segment and make an analysis;
[0034] The II group of basic working conditions was selected as a reference, and the floating data of the pipe segment was obtained and analyzed by taking the elastic modulus of the soil layer as a variable and continuously reducing the value of the elastic modulus of the soil layer;
[0035] The basic working condition of group III was selected as a reference, and by taking the distance of the segment from the shield tail as a variable and continuously reducing the value of the distance of the segment from the shield tail, the floating data of the segment was obtained and analyzed.
[0036] Preferably, the step of performing force analysis on the segment after the parameter change in b32 is:
[0037] C1. First, analyze the corresponding cross-sectional image data in the simulation model, overlay the changed image data onto the image before the change for comparison, mark the feature data of the pipe segment in the changed image, and make other background features transparent;
[0038] C2. Observe whether the features of the pipe segment in the image after the change coincide with the features of the pipe segment in the image before the change. If they coincide, continue to measure whether the pipe segment is subjected to static pressure. If they do not coincide, the pipe segment is affected by dynamic pressure.
[0039] C3. After decomposing the forces on the segment, the forces on the segment in the vertical direction include buoyancy. Foundation resilience , Segment gravity , Slurry Gravity , viscous resistance and overburden pressure , and the vertical force calculation formula of the segment floating position is: .
[0040] Preferably, when the segment is in a balanced state in steps C2 to C3, the buoyancy calculation formula of the static pressure generated by the grouting slurry is:
[0041] ;
[0042] in It is the static pressure generated by the grouting slurry; is the outer diameter of the segment; is the segment width; is the bulk density of slurry.
[0043] Preferably, when the segment is in a dynamic state in steps C2 to C3, the floating calculation formula of the dynamic pressure generated by the slurry during diffusion is:
[0044] ;
[0045] in, It is the dynamic pressure generated by the grouting slurry; is the width of the dynamic buoyancy; The grouting pressure used in construction; It is the angle between the boundary of the grouting slurry distribution area and the vertical direction.
[0046] Preferably, the steps of establishing the mathematical calculation model are:
[0047] D1. Based on the force calculation data of the vertical position of the pipe segment, and under the adjustment of different working conditions, the floating data of static pressure and dynamic pressure are obtained;
[0048] D2. Establish a mathematical calculation model for the floating changes of the pipe segments, and introduce the calculated data into a training set to the mathematical calculation model for training optimization;
[0049] D3. After optimization, the mathematical calculation model is applied to the installation of pipe segments in the actual monitoring area. After the actual parameters change, the floating threshold range data is introduced to provide timely warning feedback when the threshold range is exceeded.
[0050] Preferably, the data result feedback module generates adjustment and prevention instructions based on the results of the monitored data, and performs segment installation and standardized operations of influencing factors after knowing the data of the current working conditions in advance.
[0051] The present invention provides a shield tunnel mortise and tenon type segment floating monitoring system. Compared with the prior art, it has the following beneficial effects:
[0052] (1) The shield tunnel mortise and tenon type pipe segment floating monitoring system is provided with a pipe segment floating monitoring system, which receives and classifies the parameters, completes the establishment of the monitoring model according to the required data analysis, and records and feedbacks the floating conditions generated by the model after data adjustment, thereby optimizing the floating monitoring data model, effectively monitoring the static pressure floating or dynamic pressure floating caused by the change of working conditions, improving the monitoring accuracy, and timely knowing the impact of problems in the construction process, thereby improving the monitoring efficiency.
[0053] (2) The shield tunnel mortise and tenon segment floating monitoring system establishes a simplified simulation model through a data model building module, so as to conduct experiments on changing the numerical values of the working conditions based on the model, obtain the data changes of the segment floating from the monitoring nodes of the model, analyze the impact of the working condition changes on the floating situation, and obtain a variety of data for subsequent training operations, so as to achieve better monitoring operations during the construction of the shield tunnel mortise and tenon segment, and solve possible problems in advance based on the collected data.
[0054] (3) The shield tunnel mortise and tenon segment floating monitoring system uses a data model building module to analyze and process the static pressure floating data and dynamic pressure floating data, which are then introduced into the mathematical calculation model for training and optimization. This allows the system to timely predict and feedback the results of data changes when applied to actual operations, supporting personnel to conduct early problem detection and making the monitoring effect more obvious and the results more accurate. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] Figure 1 It is a principle block diagram of the pipe segment floating monitoring system of the present invention;
[0056] Figure 2 This is a measurement flow chart of the monitoring unit of the present invention;
[0057] Figure 3 A flow chart of the establishment of a simulation model by a data model establishment module of the present invention;
[0058] Figure 4 It is a schematic diagram of a model of vertical force on a pipe segment of the present invention;
[0059] Figure 5 It is a schematic diagram of the positional relationship between the pipe segment and the grouting layer of the present invention. DETAILED DESCRIPTION
[0060] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0061] See also Figure 1-Figure 5 , the present invention provides a technical solution:
[0062] A shield tunnel mortise and tenon segment floating monitoring system, comprising:
[0063] The monitoring unit includes a variety of measuring and monitoring instruments, which are used to measure the position and various parameter data of the mortise and tenon type segments in the shield tunnel, and transmit them to the segment floating monitoring system for processing;
[0064] The segment floating monitoring system receives and classifies the parameters, and completes the establishment of the monitoring model based on the required data analysis, and records and displays the floating conditions generated by the data-adjusted model, and includes:
[0065] The data acquisition and conversion module collects and receives the segment shape data, segment parameter data, unit type, unit constant, and material parameters in the tunnel, and stores them in the monitoring database after classification;
[0066] The data model building module sets up a simulation model, and uses numerical simulation and theoretical calculation methods to conduct multi-condition analysis on the floating of the pipe segments, establish a mathematical calculation model, and calculate and verify the floating of the pipe segments;
[0067] The data result feedback module generates instructions for segment repair or operation adjustment prevention based on the calculation results and the floating situation of the segment, and provides feedback to the display panel and early warning processing module;
[0068] The real-time update module updates parameters and completes the model update based on the data replacement at the monitoring location or based on instructions for segment repair or operation adjustment prevention;
[0069] The early warning processing module notifies personnel to carry out special construction according to actual on-site working conditions and parameters when the pipe segment floats and the floating displacement distance exceeds the early warning range;
[0070] The display panel presents the data generated by data collection, monitoring, updating and early warning in the form of data and charts, and completes the output of commands through human control.
[0071] By setting up a segment flotation monitoring system, the parameters are received and classified, and the monitoring model is established based on the required data analysis. The flotation situation generated by the data-adjusted model is recorded and feedback is displayed, so as to optimize the flotation monitoring data model, effectively monitor the static pressure flotation or dynamic pressure flotation caused by changes in working conditions of the segment, improve the monitoring accuracy, and promptly know the impact of problems in the construction process, so as to improve the monitoring efficiency.
[0072] In the embodiment of the present invention, the measurement method of the monitoring unit is:
[0073] A1. First, plan the tunnel centerline according to the construction guide wire, and determine the centerline elevation according to the plane. Then, use a total station to measure the actual clearance parameters in the tunnel and compare them with the tunnel design section to obtain the shape of the segment after construction.
[0074] A2. Use a level, a level, an aluminum ruler, and a reflective sheet. Stick a reflective sheet at the midpoint of the level and measure the three-dimensional coordinates of the segment. Then calculate the distance from the reflective sheet to the center of the circle based on the segment radius and the length of the level, which is the measured three-dimensional coordinates of the center of the circle. Then compare the measured coordinates with the designed coordinates to determine the displacement of the segment in all directions.
[0075] A3. Continue to use sensors and high-definition cameras to complete the collection of unit types, unit constants, and material parameters in the tunnel.
[0076] During measurement, an aluminum ruler is placed horizontally at the bottom of the segment, a level is used to correct the deviation, and a reflective sheet is attached to the center of the aluminum ruler. A level is used to measure the elevation of the reflective sheet 45 hours after the assembled segment is removed from the shield tail. At the same time, the vertical deviation of the shield tail of the shield machine is monitored. By comparing the data of the two, the floating amount of the segment can be obtained.
[0077] In the embodiment of the present invention, the data model building module performs the following analysis operations on the building of the simulation model:
[0078] B1. Complete the simplified construction of the simulation model based on the collected segment parameters and tunnel parameters, and meet the following model simplification conditions:
[0079] The soil layer is simplified to 6 layers, and the soil parameters are taken as the average value within the tunnel depth range. The tunnel slope and the connection of the segments are set to be flat slopes. The segments are taken as a whole ring, and the bolt joint effect between the segments is ignored. The groundwater seepage is simplified to buoyancy, and the extrusion force of the segments on the overburden acts on the contact surface between the segments and the soil.
[0080] B2. Then, based on the model, select the area to be analyzed, perform mesh refinement, and analyze the effects of slurry properties, soil properties, and the distance of the segment from the shield tail on the floating deformation of the segment.
[0081] B3. Set multiple monitoring nodes on the simulation model, and perform result analysis operations based on the data changes obtained from the monitoring nodes of the model by changing different working conditions.
[0082] In the embodiment of the present invention, the operation steps of performing mesh refinement on the analysis area in B2 are:
[0083] b21. Perform mesh division on the analysis area, find the part that needs to be meshed, and refine the local structure;
[0084] b22. The explicit integral solver is used to automatically increase the time increment step to track the propagation of stress waves in the regional elastic body, thereby amplifying the quality of the grid and refining the specific structure of the grid part. The time taken by the stress wave to pass through the minimum grid unit, that is, the time increment step, is calculated as follows:
[0085] ;
[0086] and ;
[0087] Finally we get: ;
[0088] in, represents the time increment step; represents the propagation speed of stress wave in the unit cell; Represents the minimum grid unit length; Represents the elastic modulus of the material; Represents the material density; stands for Poisson's ratio.
[0089] In the embodiment of the present invention, the setting for the working condition in B3 is:
[0090] b31. Three basic working conditions are set, I, II and III, and the data of Young's modulus of slurry, elastic modulus of soil layer and distance of segment from shield tail are the same for the three basic working conditions;
[0091] b32. Analyze the changes of the model by adjusting the working conditions, which includes the following 3 types:
[0092] The basic working condition of group I was selected as a reference, and the slurry Young's modulus was used as a variable, and the slurry Young's modulus value was continuously increased to obtain the floating data of the segment and make an analysis;
[0093] The II group of basic working conditions was selected as a reference, and the floating data of the pipe segment was obtained and analyzed by taking the elastic modulus of the soil layer as a variable and continuously reducing the value of the elastic modulus of the soil layer;
[0094] The basic working condition of group III was selected as a reference, and by taking the distance of the segment from the shield tail as a variable and continuously reducing the value of the distance of the segment from the shield tail, the floating data of the segment was obtained and analyzed.
[0095] Among them, a simplified simulation model is established through the data model building module, so as to conduct experiments on changing the numerical values of the working conditions based on the model, obtain the data changes of the floating of the pipe segments from the monitoring nodes of the model, analyze the impact of the changes in the working conditions on the floating conditions, and obtain a variety of data for subsequent training operations, so as to achieve better monitoring operations during the construction of the mortise and tenon type pipe segments of the shield tunnel, and solve possible problems in advance based on the collected data.
[0096] In the embodiment of the present invention, the steps of performing force analysis on the segment after the parameter change in b32 are:
[0097] C1. First, analyze the corresponding cross-sectional image data in the simulation model, overlay the changed image data onto the image before the change for comparison, mark the feature data of the pipe segment in the changed image, and make other background features transparent;
[0098] C2. Observe whether the features of the pipe segment in the image after the change coincide with the features of the pipe segment in the image before the change. If they coincide, continue to measure whether the pipe segment is subjected to static pressure. If they do not coincide, the pipe segment is affected by dynamic pressure.
[0099] C3. After decomposing the forces on the segment, the forces on the segment in the vertical direction include buoyancy. Foundation resilience , Segment gravity , Slurry Gravity , viscous resistance and overburden pressure , and the vertical force calculation formula of the segment floating position is: .
[0100] In the embodiment of the present invention, when the segment is in a balanced state in steps C2 to C3, the floating calculation formula of the static pressure generated by the grouting slurry is:
[0101] ;
[0102] in It is the static pressure generated by the grouting slurry; is the outer diameter of the segment; is the segment width; is the bulk density of slurry.
[0103] In the embodiment of the present invention, when the segment is in a dynamic state in steps C2 to C3, the floating calculation formula of the dynamic pressure generated by the slurry during diffusion is:
[0104] ;
[0105] in, It is the dynamic pressure generated by the grouting slurry; is the width of the dynamic buoyancy; The grouting pressure used in construction; It is the angle between the boundary of the grouting slurry distribution area and the vertical direction.
[0106] Among them, the vertical force component of the segment ring microelement is integrated throughout the ring to obtain the foundation rebound force on the entire ring segment:
[0107] ;
[0108] is the foundation resilience; is the static earth pressure coefficient; is the outer diameter of the grouting layer; is the average formation weight;
[0109] , ,and is the segment gravity; is the slurry gravity; is the weight of the segment; is the inner diameter of the segment ring;
[0110] Viscous resistance is a variable value, and its magnitude is related to the floating displacement and the properties of the slurry. When a single-liquid inert slurry is used, the viscous resistance The grouting pipe is not easy to be blocked, and the grouting effect is good. However, the initial setting time of the slurry is long, and the pipe segments are immersed in the slurry for a long time. In addition, the dilution effect of the seepage water in the water-rich soft soil layer increases the floating of the pipe segments. The viscous resistance of the single-liquid hard slurry is moderate, and the grouting pipe is blocked from time to time. The grouting effect is general, the initial setting time is controllable, and the floating of the pipe segments is controllable. The viscous resistance of the double-liquid instantaneous slurry is large, and the grouting pipe is very easy to be blocked, but it can be initially set within a few seconds.
[0111] The overburden pressure obtained by Terzaghi relaxation theory is:
[0112] ;
[0113] is the overlying soil pressure; Half of the sliding soil mass; is the cohesion of soil; is the lateral pressure coefficient on the sliding surface; is the friction angle; is the ground load; is the thickness of the overlying soil.
[0114] In the embodiment of the present invention, the steps of establishing the mathematical calculation model are:
[0115] D1. Based on the force calculation data of the vertical position of the pipe segment, and under the adjustment of different working conditions, the floating data of static pressure and dynamic pressure are obtained;
[0116] D2. Establish a mathematical calculation model for the floating changes of the pipe segments, and introduce the calculated data into a training set to the mathematical calculation model for training optimization;
[0117] D3. After optimization, the mathematical calculation model is applied to the installation of pipe segments in the actual monitoring area. After the actual parameters change, the floating threshold range data is introduced to provide timely warning feedback when the threshold range is exceeded.
[0118] Among them, the static pressure buoyancy data and dynamic pressure buoyancy data obtained through data model building module analysis and processing are introduced into the mathematical calculation model for training and optimization, so that when applied to actual operations, timely prediction and feedback of the results of data changes can be given, supporting personnel to conduct early problem troubleshooting, while making the monitoring effect more obvious and the results more accurate.
[0119] In the embodiment of the present invention, the data result feedback module generates adjustment and prevention instructions based on the results generated by the monitored data, and performs segment installation and standardized operations of influencing factors after knowing the data of the current working conditions in advance.
[0120] Among them, for the floating process of the segment, Figure 4 As shown, The upward displacement of the pipe segment to release the soil stress is is the deformation displacement of the slurry that changes with time and finally causes flow and volume compression. is the floating displacement of the segment, and the slurry elastic modulus increases, and the slurry flow and volume compression capacity weakens. decreases, the bottom of the segment floats up This is consistent with the displacement curve of the bottom of the segment.
[0121] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0122] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0123] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A shield tunnel mortise and tenon segment floating monitoring system, characterized in that: include: The monitoring unit includes a variety of measuring and monitoring instruments, which are used to measure the position and various parameter data of the mortise and tenon type segments in the shield tunnel, and transmit them to the segment floating monitoring system for processing; The segment floating monitoring system receives and classifies the parameters, and completes the establishment of the monitoring model based on the required data analysis, and records and displays the floating conditions generated by the data-adjusted model, and includes: The data acquisition and conversion module collects and receives the segment shape data, segment parameter data, unit type, unit constant, and material parameters in the tunnel, and stores them in the monitoring database after classification; The data model building module sets up a simulation model, and uses numerical simulation and theoretical calculation methods to conduct multi-condition analysis on the floating of the pipe segments, establish a mathematical calculation model, and calculate and verify the floating of the pipe segments; The data result feedback module generates instructions for segment repair or operation adjustment prevention based on the calculation results and the floating situation of the segment, and provides feedback to the display panel and early warning processing module; Real-time update module, which updates parameters according to the monitored data and completes the model update; The early warning processing module notifies personnel to carry out special construction according to actual on-site working conditions and parameters when the pipe segment floats and the floating displacement distance exceeds the early warning range; The display panel displays the data generated by data collection, monitoring, updating and early warning in the form of data and charts, and completes the output of commands through human control; The data model building module performs the following analysis operations on the building of the simulation model: B1. Complete the simplified construction of the simulation model based on the collected segment parameters and tunnel parameters, and meet the following model simplification conditions: The soil layer is simplified to 6 layers, and the soil parameters are taken as the average value within the tunnel depth range. The tunnel slope and the connection of the segments are set to be flat slopes. The segments are taken as a whole ring, and the bolt joint effect between the segments is ignored. The groundwater seepage is simplified to buoyancy, and the extrusion force of the segments on the overburden acts on the contact surface between the segments and the soil. B2. Then, based on the model, select the area to be analyzed, perform mesh refinement, and analyze the effects of slurry properties, soil properties, and the distance of the segment from the shield tail on the floating deformation of the segment. B3. Set multiple monitoring nodes on the simulation model, and perform result analysis based on the data changes obtained from the monitoring nodes of the model by changing different working conditions; The steps of establishing the mathematical calculation model are: D1. Based on the force calculation data of the vertical position of the pipe segment, and under the adjustment of different working conditions, the floating data of static pressure and dynamic pressure are obtained; D2. Establish a mathematical calculation model for the floating changes of the pipe segments, and introduce the calculated data into a training set to the mathematical calculation model for training optimization; D3. After optimization, the mathematical calculation model is applied to the installation of pipe segments in the actual monitoring area. After the actual parameters change, the floating threshold range data is introduced to provide timely warning feedback when the threshold range is exceeded.
2. A shield tunnel mortise and tenon segment floating monitoring system according to claim 1, characterized in that: The measuring method of the monitoring unit is: A1. First, plan the tunnel centerline according to the construction guide wire, and determine the centerline elevation according to the plane. Then, use a total station to measure the actual clearance parameters in the tunnel and compare them with the tunnel design section to obtain the shape of the segment after construction. A2. Use a level, a level, an aluminum ruler, and a reflective sheet. Stick a reflective sheet at the midpoint of the level and measure the three-dimensional coordinates of the segment. Then calculate the distance from the reflective sheet to the center of the circle based on the segment radius and the length of the level, which is the measured three-dimensional coordinates of the center of the circle. Then compare the measured coordinates with the designed coordinates to determine the displacement of the segment in all directions. A3. Continue to use sensors and high-definition cameras to complete the collection of unit types, unit constants, and material parameters in the tunnel.
3. A shield tunnel mortise and tenon segment floating monitoring system according to claim 1, characterized in that: The steps for performing mesh refinement on the analysis area in B2 are as follows: b21. Perform mesh division on the analysis area, find the part that needs to be meshed, and refine the local structure; b22. The explicit integral solver is used to automatically increase the time increment step to track the propagation of stress waves in the regional elastic body, thereby amplifying the quality of the grid and refining the specific structure of the grid part. The time taken by the stress wave to pass through the minimum grid unit, that is, the time increment step, is calculated as follows: ; and ; Finally we get: ; in, represents the time increment step; represents the propagation speed of stress wave in the unit cell; Represents the minimum grid unit length; Represents the elastic modulus of the material; Represents the material density; stands for Poisson's ratio.
4. A shield tunnel mortise and tenon segment floating monitoring system according to claim 1, characterized in that: The setting for the working condition in B3 is: b31. Three basic working conditions are set, I, II and III, and the data of Young's modulus of slurry, elastic modulus of soil layer and distance of segment from shield tail are the same for the three basic working conditions; b32. Analyze the changes of the model by adjusting the working conditions, which includes the following 3 types: The basic working condition of group I was selected as a reference, and the slurry Young's modulus was used as a variable, and the slurry Young's modulus value was continuously increased to obtain the floating data of the segment and make an analysis; The II group of basic working conditions was selected as a reference, and the floating data of the pipe segment was obtained and analyzed by taking the elastic modulus of the soil layer as a variable and continuously reducing the value of the elastic modulus of the soil layer; The basic working condition of group III was selected as a reference, and by taking the distance of the segment from the shield tail as a variable and continuously reducing the value of the distance of the segment from the shield tail, the floating data of the segment was obtained and analyzed.
5. A shield tunnel mortise and tenon segment floating monitoring system according to claim 4, characterized in that: In b32, the steps of performing stress analysis on the segment after the parameter change are as follows: C1. First, analyze the corresponding cross-sectional image data in the simulation model, overlay the changed image data onto the image before the change for comparison, mark the feature data of the pipe segment in the changed image, and make other background features transparent; C2. Observe whether the features of the pipe segment in the image after the change coincide with the features of the pipe segment in the image before the change. If they coincide, continue to measure whether the pipe segment is subjected to static pressure. If they do not coincide, the pipe segment is affected by dynamic pressure. C3. After decomposing the forces on the segment, the forces on the segment in the vertical direction include buoyancy. Foundation resilience , Segment gravity , Slurry Gravity , viscous resistance and overburden pressure , and the vertical force calculation formula of the segment floating position is: .
6. A shield tunnel mortise and tenon segment floating monitoring system according to claim 5, characterized in that: When the segment is in a balanced state in steps C2 to C3, the floating calculation formula of the static pressure generated by the grouting slurry is: ; in It is the static pressure generated by the grouting slurry; is the outer diameter of the segment; is the segment width; is the bulk density of slurry.
7. A shield tunnel mortise and tenon segment floating monitoring system according to claim 5, characterized in that: When the segment is in a dynamic state in steps C2 to C3, the floating calculation formula of the dynamic pressure generated by the slurry during diffusion is: ; in, It is the dynamic pressure generated by the grouting slurry; is the width of the dynamic buoyancy; The grouting pressure used in construction; It is the angle between the boundary of the grouting slurry distribution area and the vertical direction.
8. The shield tunnel mortise and tenon segment floating monitoring system according to claim 1 is characterized by: The data result feedback module generates adjustment and prevention instructions based on the results of the monitored data, and performs segment installation and standardized operations of influencing factors after knowing the working condition data in advance.
Citation Information
Patent Citations
Establishment method of floating and slab staggering refined model of segment ring separated from shield tail