Method and device for controlling the assembly welding dimensions of external suction pump skid structural components on mooring suction anchor

By using the control device on the suction anchor top cover to accurately position and adjust the suction hole flange and lifting lugs, the problem of low accuracy of traditional assembly welding is solved, and the accuracy and connection stability of the assembly welding on the suction anchor top cover are achieved.

CN118321776BActive Publication Date: 2024-10-11OFFSHORE OIL ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410759272.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2024-10-11
Estimated Expiration
2044-06-13

AI Technical Summary

Technical Problem

The traditional manual assembly and welding method cannot meet the dimensional accuracy requirements for the assembly and welding of the suction pump skid structural components on the suction anchor top cover, resulting in excessive dimensional deviation of the suction hole flange and lifting lug set, severe welding deformation, and inability to connect with the external suction pump skid. Connection installation.

Method used

Design a method and device for group welding size control. The suction hole flange positioning component of the control device is attached to the inner wall of the top cover, and the lifting lug positioning component is connected to the pin to achieve precise position and size adjustment of the suction hole flange and lifting lug. , to ensure the accuracy of assembly welding.

Benefits of technology

The suction hole flange and lifting lugs are accurately assembled and welded on the suction anchor top cover, reducing welding deformation and improving the connection and installation accuracy with the external suction pump skid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118321776B_ABST
    Figure CN118321776B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for controlling the size of an external suction pump skid structure component on a mooring suction anchor. The control method comprises the following steps: placing a suction hole flange, a first lifting ear and a second lifting ear in pairs on the suction anchor top cover; placing a control device on the suction anchor top cover, inserting the suction hole flange positioning assembly of the control device into the suction hole flange; inserting the first lifting ear and the second lifting ear into the lifting ear positioning assembly of the control device respectively; fine-tuning the spacing and position of the first lifting ear and the second lifting ear; welding the suction hole flange, the first lifting ear and the second lifting ear to the suction anchor top cover. Also disclosed is a device for controlling the size of an external suction pump skid structure component on a mooring suction anchor. The method and device for controlling the size of an external suction pump skid structure component on a mooring suction anchor provided by the present invention can accurately control the position and accuracy of the suction hole flange, the first lifting ear and the second lifting ear on the suction anchor top cover, thereby achieving accurate welding.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of the manufacture of suction anchors, and particularly relates to a method and a control device for controlling the welding and assembly dimensions of structural components of an external suction pump skid on a mooring suction anchor. Background Art

[0002] With the improvement of the development capacity of deep - sea oil and gas fields, a new technology of using a suction anchor to sink piles into the seabed mud layer to moor a floating production, storage and offloading unit (FPSO) has been widely applied. The mooring suction anchor is a circular steel cylinder with a closed top and an open bottom. A structural component for connecting an external suction pump skid, namely a suction hole flange and a lifting lug, is provided on its top cover. Mooring anchor ears are provided in the middle and lower parts of the steel cylinder and are connected to the FPSO facility through anchor chains to form an anchor mooring system. The structural components of the external suction pump skid on the top cover of the mooring suction anchor include a suction hole flange located at the center of the top cover and two lifting lugs symmetrically arranged on the same axis on both sides thereof. When the suction pump skid is connected and assembled with the structural components, the suction pump skid and the two lifting lugs are connected and fixed to the top cover of the suction anchor through a pin shaft combination, and the suction pump on the suction pump skid is hermetically connected to the suction hole flange through bolts.

[0003] The structural components of the external suction pump skid are the key core components of the suction anchor. The welding and assembly dimension accuracy requirements of its suction hole flange and two lifting lugs on the top cover of the suction anchor are relatively high. The traditional manual welding and assembly method and dimension control method cannot meet the strict requirements of the welding and assembly dimension accuracy, often resulting in too large deviation in the alignment dimensions of the suction hole flange and the two lifting lugs. At the same time, welding deformation will also occur during the joint welding, and the phenomenon that it cannot be connected and installed with the external suction pump skid will occur.

[0004] Therefore, it is urgent to design a method and a control device for controlling the welding and assembly dimensions of structural components of an external suction pump skid on a mooring suction anchor to solve the problems of too large deviation in the alignment dimensions of the installed suction hole flange and the two lifting lugs, low accuracy, welding deformation during joint welding, and inability to be connected and installed with the external suction pump skid mentioned above. Summary of the Invention

[0005] To solve the technical problems mentioned in the background art, such as too large deviation in the alignment dimensions of the installed suction hole flange and the two lifting lugs, low accuracy, welding deformation during joint welding, and inability to be connected and installed with the external suction pump skid, a method and a control device for controlling the welding and assembly dimensions of structural components of an external suction pump skid on a mooring suction anchor are provided to solve the above problems.

[0006] To achieve the above object, the specific technical solutions of the method and the control device for controlling the welding and assembly dimensions of structural components of an external suction pump skid on the mooring suction anchor of the present invention are as follows:

[0007] A method for controlling the welding and assembly dimensions of structural components of an external suction pump skid on a mooring suction anchor includes the following steps:

[0008] S1. Place the suction hole flange, the first lifting lug, and the second lifting lug onto the suction anchor top cover respectively for pairing.

[0009] S2. Place the control device onto the suction anchor top cover, insert the suction hole flange positioning component of the control device into the suction hole flange, and adjust the suction hole flange so that the suction hole flange positioning component fits against the inner wall of the suction hole flange.

[0010] S3. Insert the first lifting lug and the second lifting lug into the lifting lug positioning components at both ends of the control device respectively, and adjust the first lifting lug and the second lifting lug so that the first lifting lug is connected to the lifting lug positioning component at one end of the control device through the first pin shaft, and the second lifting lug is connected to the lifting lug positioning component at the other end of the control device through the second pin shaft.

[0011] S4. Fine-tune the distance and position of the first lifting lug and the second lifting lug, and fix the positioning welding points of the first lifting lug and the second lifting lug on the suction anchor top cover.

[0012] S5. Weld the suction hole flange, the first lifting lug, and the second lifting lug to the suction anchor top cover.

[0013] S6. Remove the control device.

[0014] Furthermore, place the suction hole flange, the first lifting lug, and the second lifting lug onto the suction anchor top cover respectively for pairing, and the suction hole flange, the first lifting lug, and the second lifting lug are not fixed to the suction anchor top cover.

[0015] A welding dimension control device for external suction pump skid structure components on a mooring suction anchor, comprising a main frame assembly. A suction hole flange positioning component is arranged on the main frame assembly, and lifting lug positioning components are respectively arranged at both ends of the main frame assembly. The suction hole flange positioning component is inserted into the suction hole flange, and the suction hole flange positioning component fits against the inner wall of the suction hole flange to position the suction hole flange. The lifting lug positioning component at one end of the main frame assembly is connected to the first lifting lug through the first pin shaft, and the lifting lug positioning component at the other end of the main frame assembly is connected to the second lifting lug through the second pin shaft to position the first lifting lug and the second lifting lug.

[0016] Furthermore, the main frame assembly includes a front beam and a rear beam, which are arranged in parallel. A first cross beam, a second cross beam, a third cross beam, a fourth cross beam, a fifth cross beam, and a sixth cross beam are sequentially connected between the front beam and the rear beam. The first cross beam and the sixth cross beam are respectively connected to both ends of the front beam and the rear beam.

[0017] Furthermore, it further includes a first forklift sleeve beam and a second forklift sleeve beam. First through holes and second through holes are respectively opened on the front beam and the rear beam. The first forklift sleeve beam passes through the two first through holes and is fixedly arranged on the front beam and the rear beam, and the second forklift sleeve beam passes through the two second through holes and is fixedly arranged on the front beam and the rear beam.

[0018] Further, frame lifting lugs are provided at the four included angles formed by the connection between the third cross beam, the fourth cross beam, the front beam, and the rear beam.

[0019] Further, bolt through holes are provided on the side of the front beam, the rear beam, the third cross beam, and the fourth cross beam close to the suction hole flange, and are fixedly connected to the suction hole flange positioning assembly through bolts.

[0020] Further, the suction hole flange positioning assembly includes 4 positioning pads and a positioning steel ring. The 4 positioning pads are evenly distributed on the positioning steel ring. Through holes are provided on the 4 positioning pads and the positioning steel ring. The bolts pass through the 4 positioning pads and the positioning steel ring and are respectively fixedly connected to the front beam, the rear beam, the third cross beam, and the fourth cross beam.

[0021] Further, the lifting lug positioning assembly includes a first lifting lug positioning frame and a second lifting lug positioning frame. The first lifting lug positioning frame is arranged on the first cross beam and the second cross beam, and the second lifting lug positioning frame is arranged on the fifth cross beam and the sixth cross beam.

[0022] Further, the lifting lug positioning assembly further includes a first pin shaft. A first inner plate and a first outer plate are spaced on the first lifting lug positioning frame. The first lifting lug is placed between the first inner plate and the first outer plate. Through holes are provided on both the first inner plate and the first outer plate. A first lifting lug hole is provided on the first lifting lug. The first pin shaft sequentially passes through the through hole of the first inner plate, the first lifting lug hole, and the through hole of the first outer plate to connect the first lifting lug between the first inner plate and the first outer plate.

[0023] The method and device for controlling the welding dimensions of the structural components of the external suction pump skid on the mooring suction anchor of the present invention have the following advantages:

[0024] By placing the control device on the suction anchor top cover, inserting the suction hole flange positioning assembly of the control device into the suction hole flange, adjusting the suction hole flange to make the suction hole flange positioning assembly fit the inner wall of the suction hole flange, inserting the first lifting lug and the second lifting lug into the lifting lug positioning assemblies at both ends of the control device respectively, adjusting the first lifting lug and the second lifting lug to connect the first lifting lug with the lifting lug positioning assembly at one end of the control device through the first pin shaft, and connecting the second lifting lug with the lifting lug positioning assembly at the other end of the control device through the second pin shaft, the relative positions and dimensional accuracies of the suction hole flange, the first lifting lug, and the second lifting lug on the suction anchor top cover can be accurately controlled, precise welding is achieved, welding deformation is reduced, and thus the connection and installation accuracies of the suction hole flange, the first lifting lug, and the second lifting lug with the external suction pump skid are improved. Description of the Drawings

[0025] Figure 1 is a flow chart of the method for controlling the welding dimensions of the structural components of the external suction pump skid on the mooring suction anchor of the present invention;

[0026] Figure 2This is a schematic structural diagram of the assembly welding dimension control device for the structural components of the external suction pump skid on the mooring suction anchor of the present invention and the suction anchor top cover;

[0027] Figure 3 This is a schematic structural diagram of the assembly welding dimension control device for the structural components of the external suction pump skid on the mooring suction anchor of the present invention;

[0028] Figure 4 This is a schematic structural diagram of the suction hole flange positioning assembly of the present invention.

[0029] Description of the markings in the figure:

[0030] 100. Suction anchor top cover; 200. Control device; 300. Support beam; 1. Main body frame assembly; 11. Front beam; 12. Rear beam; 13. First cross beam; 14. Second cross beam; 15. Third cross beam; 16. Fourth cross beam; 17. Fifth cross beam; 18. Sixth cross beam; 19. Frame lifting lug; 2. Suction hole flange positioning assembly; 21. Positioning pad; 22. Positioning steel ring; 3. Lifting lug positioning assembly; 31. First lifting lug positioning frame; 32. Second lifting lug positioning frame; 33. First pin shaft; 34. Second pin shaft; 35. First inner side plate; 36. First outer side plate; 37. Second inner side plate; 38. Second outer side plate; 39. Rib plate; 4. Suction hole flange; 5. First lifting lug; 6. Second lifting lug; 7. Leg; 8. First forklift sleeve beam; 9. Second forklift sleeve beam. Detailed implementation manners

[0031] To make the objectives, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are some, but not all, of the embodiments of the present invention. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts fall within the scope of protection of the present invention.

[0032] Those skilled in the art can understand that although some embodiments herein include some features included in other embodiments but not other features, the combination of features of different embodiments means that it is within the scope of the present invention and forms different embodiments. For example, in the claims, any one of the claimed embodiments can be used in any combination.

[0033] Next, refer to the attached Figure 1 to the attached Figure 4 Describe the assembly welding dimension control method and control device for the structural components of the external suction pump skid on the mooring suction anchor of the present invention.

[0034] As Figure 1As shown in the figure, the method for controlling the welding dimensions of the structural components of the mooring suction anchor with an externally connected suction pump skid in the present invention includes the following steps:

[0035] S1. Respectively place the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 in alignment on the suction anchor top cover 100;

[0036] S2. Place the control device 200 on the suction anchor top cover 100, insert the suction hole flange positioning component 2 of the control device 200 into the suction hole flange 4, and adjust the suction hole flange 4 so that the suction hole flange positioning component 2 fits against the inner wall of the suction hole flange 4;

[0037] S3. Insert the first lifting lug 5 and the second lifting lug 6 into the lifting lug positioning components 3 at both ends of the control device 200 respectively, and adjust the first lifting lug 5 and the second lifting lug 6 so that the first lifting lug 5 is connected to the lifting lug positioning component 3 at one end of the control device 200 through the first pin shaft 33, and the second lifting lug 6 is connected to the lifting lug positioning component 3 at the other end of the control device 200 through the second pin shaft 34;

[0038] S4. Fine-tune the distance and position between the first lifting lug 5 and the second lifting lug 6, and fix the positioning welds of the first lifting lug 5 and the second lifting lug 6 on the suction anchor top cover 100;

[0039] S5. Weld the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 to the suction anchor top cover 100;

[0040] S6. Remove the control device 200.

[0041] By placing the control device 200 on the suction anchor top cover 100, inserting the suction hole flange positioning component 2 of the control device 200 into the suction hole flange 4, adjusting the suction hole flange 4 so that the suction hole flange positioning component 2 fits against the inner wall of the suction hole flange 4, inserting the first lifting lug 5 and the second lifting lug 6 into the lifting lug positioning components 3 at both ends of the control device 200 respectively, and adjusting the first lifting lug 5 and the second lifting lug 6 so that the first lifting lug 5 is connected to one lifting lug positioning component 3 through the first pin shaft 33, and the second lifting lug 6 is connected to the other lifting lug positioning component 3 through the second pin shaft 34, the relative positions and dimensional accuracies of the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 on the suction anchor top cover 100 can be accurately controlled, precise welding is achieved, welding deformation is reduced, and thus the connection and installation accuracies of the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 with the externally connected suction pump skid are improved.

[0042] Specifically, as Figures 1 to 3 shown, first use the cooperation method of a crane and manual labor, and use the alignment inserts to respectively place the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 in the corresponding positions of the openings on the suction anchor top cover 100. The suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 are not welded and fixed to the suction anchor top cover 100.

[0043] Positioning pads 21 and positioning steel rings 22 of the suction hole flange positioning assembly 2 of the control device 200 are inserted into the non-fixed suction hole flange 4 by a hoisting crane, and are fitted with its inner wall to achieve rigid fixation with clearance fit. The clearance in the fitting state is 1-2 mm. During the insertion process, the position of the suction hole flange 4 needs to be adjusted. The levelness of the flange surface should be ensured, and its deviation shall not exceed 1% of its outer diameter and shall not be greater than 3 mm. After the position dimensions meet the requirements, it is spot-welded to the suction anchor top cover 100.

[0044] Specifically, the positioning pads 21 and positioning steel rings 22 of the suction hole flange positioning assembly 2 of the control device 200 are first inserted into the holes of the non-welded suction hole flange 4 by a hoisting crane, so that there is a relative rigid fit with a clearance of 1-2 mm between the outer walls of the positioning pads 21 and positioning steel rings 22 and the inner wall of the suction hole flange 4. Then, the orientation and position dimensions of the suction hole flange 4 on the suction anchor top cover 100 are finely adjusted manually. After its relative position, protruding height, the orientation of the flange hole bolt holes, and the levelness of the flange surface all meet the requirements, it is spot-welded to the suction anchor top cover 100, but the joint welding is not carried out. In this embodiment, the 1-2 mm fitting clearance between the suction hole flange positioning assembly 2 and the inner wall of the suction hole flange 4 can ensure that the suction hole flange positioning assembly 2 plays a role in fitting and rigidly fixing the suction hole flange 4, so that no excessive angular deformation occurs after the final joint welding, and the deviation of the flange surface levelness does not exceed 1% of its outer diameter and is not greater than 3 mm. At the same time, this fitting clearance can also ensure that the orientation and position dimensions of the suction hole flange 4 can be finely adjusted during precise alignment. In this embodiment, the 1-2 mm fitting clearance between the suction hole flange positioning assembly 2 and the inner wall of the suction hole flange 4 is within a reasonable range, and a fitting within a reasonable range can ensure welding accuracy.

[0045] At the same time, the first lifting lug 5 and the second lifting lug 6 will also be inserted into the first lifting lug positioning frame 31 and the second lifting lug positioning frame 32 of the lifting lug positioning assembly 3 at both ends of the control device 200 respectively, so that the first lifting lug 5 is connected to a lifting lug positioning assembly 3 through a first pin shaft 33, and the second lifting lug 6 is connected to another lifting lug positioning assembly 3 through a second pin shaft 34. In this embodiment, the rigid fixation of the suction hole flange positioning assembly 2 to the suction hole flange 4 must form mutual constraints simultaneously with the rigid fixation of the first lifting lug positioning frame 31 to the first lifting lug 5 and the rigid fixation of the second lifting lug positioning frame 32 to the second lifting lug 6 before it can play a role, so as to ensure the precise orientation and position dimensions of the suction hole flange 4, the first lifting lug 5, and the second lifting lug 6 after welding on the suction anchor top cover 100.

[0046] The control device 200 is used to connect the first lifting lug 5 and the second lifting lug 6 through a pin shaft. According to the suction hole flange 4 that is group-point-fixed, the positions and spacings of the first lifting lug 5 and the second lifting lug 6 are respectively finely adjusted. After they meet the requirements of the drawing dimensions, they are positioned and welded to the suction anchor top cover 100 at the groove.

[0047] Under the die-type rigid fixing effect of the control device 200 on the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6, the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 are welded to the suction anchor top cover 100 according to the welding process and with a reasonable welding sequence.

[0048] After the welding operation is completed and cooled, the control device 200 is removed by using a crane, that is, the dimensional control of the group welding of the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 of the external suction pump skid structure components on the mooring suction anchor is completed.

[0049] As Figures 2 to 4 shown, the present invention also provides a dimensional control device for the group welding of the external suction pump skid structure components on the mooring suction anchor, including a main frame assembly 1. A suction hole flange positioning assembly 2 is arranged on the main frame assembly 1. Lifting lug positioning assemblies 3 are respectively arranged at both ends of the main frame assembly 1. The suction hole flange positioning assembly 2 is inserted into the suction hole flange 4, and the inner wall of the suction hole flange positioning assembly 2 is attached to the inner wall of the suction hole flange 4 to position the suction hole flange 4. The lifting lug positioning assembly 3 at one end of the main frame assembly 1 is connected to the first lifting lug 5 through a first pin shaft 33, and the lifting lug positioning assembly 3 at the other end of the main frame assembly 1 is connected to the second lifting lug 6 through a second pin shaft 34 to position the first lifting lug 5 and the second lifting lug 6.

[0050] Further, as Figures 2 to 4 shown, the main frame assembly 1 includes a front beam 11 and a rear beam 12. The front beam 11 and the rear beam 12 are arranged in parallel. A first cross beam 13, a second cross beam 14, a third cross beam 15, a fourth cross beam 16, a fifth cross beam 17 and a sixth cross beam 18 are sequentially connected between the front beam 11 and the rear beam 12. The first cross beam 13 and the sixth cross beam 18 are respectively connected to both ends of the front beam 11 and the rear beam 12. The present invention also provides that the dimensional control device for the group welding of the external suction pump skid structure components on the mooring suction anchor further includes legs 7. The legs 7 are arranged at the four right angles of the main frame assembly 1 to support the main frame assembly 1.

[0051] Further, as Figures 2 to 4As shown in the figure, the present invention also provides a welding dimension control device for external suction pump skid structural components on a mooring suction anchor, which further includes a first forklift sleeve beam 8 and a second forklift sleeve beam 9. The front beam 11 and the rear beam 12 are both provided with a first through hole and a second through hole. The first forklift sleeve beam 8 passes through the two first through holes and is fixedly arranged on the front beam 11 and the rear beam 12. The second forklift sleeve beam 9 passes through the two second through holes and is fixedly arranged on the front beam 11 and the rear beam 12. It is convenient for the forklift to be inserted into the first forklift sleeve beam 8 and the second forklift sleeve beam 9 to realize the overall transportation of the forklift for the control device 200.

[0052] Furthermore, as Figures 2 to 4 shown in the figure, frame lifting lugs 19 are provided at the four included angles formed by the connection between the third cross beam 15, the fourth cross beam 16, the front beam 11 and the rear beam 12. There are 4 groups of 8 stiffening plates 39. The 4 groups of stiffening plates 39 are respectively fixed in pairs on the open sides of the first cross beam 13 and the second cross beam 14, the fifth cross beam 17 and the sixth cross beam 18. Bolt through holes are provided on the sides of the front beam 11, the rear beam 12, the third cross beam 15 and the fourth cross beam 16 close to the suction hole flange 4, and they are fixedly connected to the suction hole flange positioning assembly 2 through bolts.

[0053] Furthermore, as Figures 2 to 4 shown in the figure, the suction hole flange positioning assembly 2 includes 4 positioning pads 21 and a positioning steel ring 22. The 4 positioning pads 21 are evenly distributed on the positioning steel ring 22. Through holes are provided on the 4 positioning pads 21 and the positioning steel ring 22. Bolts pass through the 4 positioning pads 21 and the positioning steel ring 22 and are respectively fixedly connected to the front beam 11, the rear beam 12, the third cross beam 15 and the fourth cross beam 16. The positioning pads 21 and the positioning steel ring 22 are inserted into the suction hole flange 4 and fit with its inner wall to achieve clearance fit and rigid fixation, so as to ensure the welding dimension accuracy of the suction hole flange 4.

[0054] Furthermore, as Figure 1 and Figure 2As shown in the figure, the lug positioning assembly 3 includes a first lug positioning frame 31 and a second lug positioning frame 32. The first lug positioning frame 31 is arranged on the first cross beam 13 and the second cross beam 14, and the second lug positioning frame 32 is arranged on the fifth cross beam 17 and the sixth cross beam 18. The lug positioning assembly 3 further includes a first pin shaft 33. The first lug positioning frame 31 is provided with a first inner side plate 35 and a first outer side plate 36 at intervals. The first lug 5 is placed between the first inner side plate 35 and the first outer side plate 36. Through holes are provided on both the first inner side plate 35 and the first outer side plate 36. A first lug hole is formed on the first lug 5. The first pin shaft 33 sequentially passes through the through hole of the first inner side plate 35, the first lug hole, and the through hole of the first outer side plate 36, connecting the first lug 5 between the first inner side plate 35 and the first outer side plate 36. The lug positioning assembly 3 further includes a second pin shaft 34. The second lug positioning frame 32 is provided with a second inner side plate 37 and a second outer side plate 38 at intervals. The second lug 6 is placed between the second inner side plate 37 and the second outer side plate 38. Through holes are provided on both the second inner side plate 37 and the second outer side plate 38. A second lug hole is formed on the second lug 6. The second pin shaft 34 sequentially passes through the through hole of the second inner side plate 37, the second lug hole, and the through hole of the second outer side plate 38, connecting the second lug 6 between the second inner side plate 37 and the second outer side plate 38. The lug positioning assembly 3 further includes a support beam 300. One end of the support beam 300 is connected to the first inner side plate 35, and the other end of the support beam 300 is connected to the second inner side plate 37 to realize the overall reinforcement of the first lug positioning frame 31 and the second lug positioning frame 32.

[0055] The control device 200 is used to connect the first lug 5 and the second lug 6 respectively through the first pin shaft 33 and the second pin shaft 34. According to the suction hole flange 4 for group point fixation, the first pin shaft 33 and the second pin shaft 34 are respectively connected to the first lug positioning frame 31 and the second lug positioning frame 32. The height, angle, spacing and other position dimensions of the unfixed first lug 5 and second lug 6 are manually adjusted to meet the requirements of the drawing dimensions. After that, the positioning welds are fixed to the suction anchor top cover 100 at the groove, but the joint welding is not carried out.

[0056] In this embodiment, the rigid fixation of the first lug 5 and the second lug 6 by the first lug positioning frame 31 and the second lug positioning frame 32 is realized by the clearance fit of 0 - 1 mm between the outer wall surfaces of the first pin shaft 33 and the second pin shaft 34 and the inner wall surfaces of the lug holes of the first lug 5 and the second lug 6, as well as the joint welds. The first lug 5 and the second lug 6 are lugs with large wall thickness. The inner wall surfaces of the lug holes of the first lug 5 and the second lug 6 can achieve a clearance fit of 0 - 1 mm with the first pin shaft 33 and the second pin shaft 34, and are rigidly fixed under the action of the joint welds.

[0057] The spacing between the first inner plate 35 and the first outer plate 36, and between the second inner plate 37 and the second outer plate 38 is only for the convenience of inserting the first lifting lug 5 and the second lifting lug 6, and has no function of rigidly clamping and fixing the first lifting lug 5 and the second lifting lug 6. The rigid fixation of the first lifting lug 5 and the second lifting lug 6 is respectively carried out through the first pin shaft 33 and the second pin shaft 34. That is, the first pin shaft 33 is fixed between the first inner plate 35 and the first outer plate 36, the first lifting lug 5 is fixed on the first pin shaft 33, the second pin shaft 34 is fixed between the second inner plate 37 and the second outer plate 38, and the second lifting lug 6 is fixed on the second pin shaft 34.

[0058] Moreover, the rigid fixation of the first lifting lug positioning frame 31 to the first lifting lug 5 and the rigid fixation of the second lifting lug positioning frame 32 to the second lifting lug 6 must form mutual constraints simultaneously with the rigid fixation of the suction hole flange positioning assembly 2 to the suction hole flange 4 before they can play a role, so as to ensure the precise orientation and position dimensions among the suction hole flange 4, the first lifting lug 5, and the second lifting lug 6 after welding on the suction anchor top cover 100.

[0059] The present invention also provides the working process of the welding dimension control device for the structural components externally connected to the mooring suction anchor and the suction pump skid as follows:

[0060] During use, first use the cooperation method of a crane and manual labor, and use the assembly block to assemble and place the structural component suction hole flange 4, the first lifting lug 5, and the second lifting lug 6 at the corresponding positions on the suction anchor top cover 100 but without tack welding;

[0061] Lift the control device 200 above the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 of the suction anchor top cover 100 by means of a crane and using the frame lifting lug 19. Align the positioning steel ring 22 of the suction hole flange positioning assembly 2 with the suction hole flange 4, and align the first lifting lug positioning frame 31 and the second lifting lug positioning frame 32 of the lifting lug positioning assembly 3 with the first lifting lug 5 and the second lifting lug 6 respectively, and then slowly lower it. Insert the positioning cushion block 21 and the positioning steel ring 22 into the suction hole flange 4, and fit them with the inner wall of the suction hole flange 4 to achieve clearance fit and rigid fixation. During the insertion process, adjust the position of the suction hole flange 4 that has been paired but not tack-welded. After meeting the dimensional requirements, tack-weld it to the suction anchor top cover 100. At the same time, insert the first lifting lug 5 between the first inner plate 35 and the first outer plate 36 of the first lifting lug positioning frame 31, and adjust the through holes of the first inner plate 35, the first lifting lug hole, and the through holes of the first outer plate 36 to be aligned on the same axis. The first pin shaft 33 passes through the through holes of the first inner plate 35, the first lifting lug hole, and the through holes of the first outer plate 36 in sequence to connect the first lifting lug 5 between the first inner plate 35 and the first outer plate 36. Insert the second lifting lug 6 between the second inner plate 37 and the second outer plate 38 of the second lifting lug positioning frame 32, and adjust the through holes of the second inner plate 37, the second lifting lug hole, and the through holes of the second outer plate 38 to be aligned on the same axis. The second pin shaft 34 passes through the through holes of the second inner plate 37, the second lifting lug hole, and the through holes of the second outer plate 38 in sequence to connect the second lifting lug 6 between the second inner plate 37 and the second outer plate 38. Then, finely adjust the positions of the first lifting lug 5 and the second lifting lug 6 that have been paired but not tack-welded. After their dimensions meet the requirements, tack-weld them to the suction anchor top cover 100;

[0062] Remove the hook of the crane and move it away, and continue to install the control device 200 on the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 to maintain rigid fixation; weld the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 to the suction anchor top cover 100 according to the welding process and using a reasonable welding sequence;

[0063] After the welding operation is completed and cooled, use the crane to lift the device again. Remove the first pin shaft 33 and the second pin shaft 34 on the lifting lug positioning assembly 3 respectively, and then remove the device, completing the precise group welding of the rigid fixation of the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 on the suction anchor top cover 100, so as to improve the connection and installation accuracy with the suction pump skid.

[0064] The method and device for controlling the group welding dimensions of the structural components of the external suction pump skid on the mooring suction anchor of the present invention form a die-type group welding mode, ensuring the relative position and dimensional control accuracy of the structural components such as the suction hole flange 4, the first lifting lug 5 and the second lifting lug 6 on the suction anchor top cover 100, realizing precise group welding, reducing welding deformation, and thus improving the connection and installation accuracy with the external suction pump skid.

[0065] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, rather than limitations on the implementation manners of the present invention. For those of ordinary skill in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all implementation manners here. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the claims of the present invention.

Claims

1. A device for controlling the size of the welding of the external suction pump skid structure components on a mooring suction anchor, characterized in that: It includes a main frame assembly, a suction hole flange positioning assembly is arranged on the main frame assembly, ear positioning assemblies are arranged at both ends of the main frame assembly, the suction hole flange positioning assembly is inserted into the suction hole flange, the suction hole flange positioning assembly is fitted with the inner wall of the suction hole flange to position the suction hole flange, the ear positioning assembly at one end of the main frame assembly is connected to the first ear through a first pin shaft, and the ear positioning assembly at the other end of the main frame assembly is connected to the second ear through a second pin shaft to position the first ear and the second ear; The main frame assembly includes a front beam and a rear beam, the front beam and the rear beam are arranged in parallel, the front beam and the rear beam are sequentially connected with a first cross beam, a second cross beam, a third cross beam, a fourth cross beam, a fifth cross beam, and a sixth cross beam, and the first cross beam and the sixth cross beam are respectively connected to both ends of the front beam and the rear beam; Bolt through holes are provided on one side of the front beam, the rear beam, the third cross beam and the fourth cross beam close to the suction hole flange, and are fixedly connected to the suction hole flange positioning assembly by bolts; The suction hole flange positioning assembly includes 4 positioning pads and a positioning steel ring. The 4 positioning pads are evenly distributed on the positioning steel ring. Through holes are provided on the 4 positioning pads and the positioning steel ring. Bolts pass through the 4 positioning pads and the positioning steel ring and are fixedly connected to the front beam, the rear beam, the third cross beam and the fourth cross beam respectively. The lifting ear positioning assembly comprises a first lifting ear positioning frame and a second lifting ear positioning frame, the first lifting ear positioning frame is arranged on the first cross beam and the second cross beam, and the second lifting ear positioning frame is arranged on the fifth cross beam and the sixth cross beam; The ear positioning assembly also includes a first pin shaft, and a first inner plate and a first outer plate are arranged at intervals on the first ear positioning frame, the first ear is placed between the first inner plate and the first outer plate, and through holes are arranged on the first inner plate and the first outer plate, and a first ear hole is opened on the first ear, and the first pin shaft passes through the through hole of the first inner plate, the first ear hole and the through hole of the first outer plate in sequence to connect the first ear between the first inner plate and the first outer plate.

2. The device for controlling the welding dimensions of the external suction pump skid structural components on the mooring suction anchor according to claim 1, characterized in that: It also includes a first forklift sleeve beam and a second forklift sleeve beam. The front beam and the rear beam are both provided with a first through hole and a second through hole. The first forklift sleeve beam passes through the two first through holes and is fixedly arranged on the front beam and the rear beam. The second forklift sleeve beam passes through the two second through holes and is fixedly arranged on the front beam and the rear beam.

3. The device for controlling the welding dimensions of the external suction pump skid structural components on the mooring suction anchor according to claim 1, characterized in that: Frame hanging ears are arranged at four angles formed by the third cross beam, the fourth cross beam, the front beam and the rear beam.

4. A method for controlling the size of the assembly welding of a suction pump skid structure component connected to a mooring suction anchor, applied to the device for controlling the size of the assembly welding of a suction pump skid structure component connected to an mooring suction anchor as claimed in any one of claims 1 to 3, characterized in that: The following steps are involved: S1, assembling the suction hole flange, the first lifting ear and the second lifting ear in pairs and placing them on the suction anchor top cover; S2. Place the control device on the suction anchor top cover, insert the suction hole flange positioning assembly of the control device into the suction hole flange, and adjust the suction hole flange so that the suction hole flange positioning assembly fits with the inner wall of the suction hole flange; S3, insert the first lifting ear and the second lifting ear into the lifting ear positioning components at both ends of the control device respectively, adjust the first lifting ear and the second lifting ear, so that the first lifting ear is connected to the lifting ear positioning component at one end of the control device through the first pin shaft, and the second lifting ear is connected to the lifting ear positioning component at the other end of the control device through the second pin shaft; S4, fine-adjusting the distance and position between the first lifting ear and the second lifting ear, and fixing the first lifting ear and the second lifting ear positioning welding points on the suction anchor top cover; S5, welding the suction hole flange, the first lifting ear and the second lifting ear to the suction anchor top cover; S6. Remove the control device.

5. The method for controlling the assembly welding dimensions of the external suction pump skid structural component on the mooring suction anchor according to claim 4, characterized in that: The suction hole flange, the first lifting ear and the second lifting ear are respectively placed in pairs on the suction anchor top cover, and the suction hole flange, the first lifting ear and the second lifting ear are not fixed to the suction anchor top cover.