Distributed water level data analysis method and system
Through the distributed water level data analysis method, we build a water level analysis model and a real-time warning module, which solves the problems of incomplete reservoir management of hydropower stations and difficult to predict water level changes, and realizes the intelligentization of water level monitoring and the improvement of early warning capabilities.
Patent Information
- Application Number
- CN202410603596.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-15
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2044-05-15
AI Technical Summary
Reservoir management of hydropower stations is imperfect, reservoir dispatching and flood control measures are unscientific, and river water level changes are difficult to predict, resulting in property losses downstream when water is released. Moreover, existing technology is difficult to achieve distributed water level monitoring and intelligent management and control, and lacks forward-looking early warning capabilities.
Based on the distributed water level data analysis method, by obtaining historical water release data from hydropower stations, we build a water level analysis model, intelligently select water level monitoring points, and build a real-time warning calculation module to monitor and issue warning messages in real time to prevent potential risks caused by water level changes.
It realizes the rapid and intelligent search for water level monitoring points in the inflection point area during the water release process upstream of the hydropower station, timely feedback of water level data, improves early warning capabilities, and effectively prevents risks caused by natural factors and changes in field conditions.
Smart Images

Figure CN118364206B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of distributed water level data analysis, and in particular to a distributed water level data analysis method and system. Background Art
[0002] As equipment integrating power generation, flood control and water supply, hydropower stations have always occupied an important position in the process of scientific and technological development. In the current technology, due to the imperfect management system of some hydropower station reservoirs, unscientific reservoir scheduling and flood control measures, and imperfect early warning facilities, there are still major safety hazards in the safe operation of hydropower station reservoirs.
[0003] Moreover, due to the geographical characteristics of the river, it is often difficult to predict the water level changes caused by natural factors such as river turning points and reefs during the water release process. Sometimes, the upstream sluice gates are opened to release water, causing property losses to the people downstream. At the same time, in the existing technology, the river water level is limited by field conditions, and distributed collection is difficult. The setting of water level monitoring points lacks intelligent and digital management and control. The monitored water level data cannot be fed back in time, and there is a lack of ability to evaluate water level risk changes based on historical data, and there is a lack of forward-looking warning measures and means. Summary of the invention
[0004] The purpose of the present invention is to provide a distributed water level data analysis method and system to solve the problems raised in the above background technology.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a distributed water level data analysis method, the method comprising the following steps:
[0006] S1. Acquire historical data of water discharge from a hydropower station, wherein the historical data includes water level monitoring data of inflection points of each river channel on the river discharged by the hydropower station;
[0007] S2. Obtain the water level data upstream of the hydropower station and the water level monitoring data of the first channel inflection point area on the released river from the historical data, build a water level analysis model, and output the functional relationship between the water level data upstream of the hydropower station and the water level data of the first channel inflection point area on the released river;
[0008] S3. Build a water level monitoring point analysis model for each channel turning point area on the released river, and intelligently select water level monitoring points based on real-time water level height data and feed them back to the system administrator port;
[0009] S4. Construct a real-time warning calculation module, based on the real-time monitoring data of the turning point areas of each river channel on the hydropower station's water discharge river, and send real-time warning information to the downstream of the water discharge river when the system preset value is not met.
[0010] According to the above technical solution, the river channel turning point area includes:
[0011] The straight line where the current river channel is located forms an angle θ with the straight line where the hydropower station discharges water. When the angle θ is greater than the angle threshold set by the system, the vertex position of the angle θ is recorded as the river channel turning point, and the area formed with the river channel turning point as the center and R as the radius is recorded as the river channel turning point area, where R is a constant set by the system.
[0012] According to the above technical solution, the water level analysis model includes:
[0013] Obtain the historical data of water release from the hydropower station. In the historical data of single water release, the water level height data upstream of the hydropower station is used as the horizontal coordinate, and the water level monitoring data of the first river channel turning point area on the released river is used as the vertical coordinate to form the coordinate base point of the single water release data;
[0014] The water level monitoring data of the first river channel turning point area on the released water river refers to: obtaining the monitoring data of all monitoring points in the first river channel turning point area, calculating the average value A0, and taking A0 as the water level monitoring data of the first river channel turning point area on the released water river; performing monitoring point analysis on the first river channel turning point area, and the monitoring point analysis includes:
[0015] Take |A0-B i The monitoring point corresponding to the minimum value of | is recorded as the monitoring point of the first river turning point area this time, where B i Refers to the water level height data monitored at the ith monitoring point in the first river channel turning point area;
[0016] Create a data set and form a water level analysis model based on the different coordinate base points in the data set:
[0017] A0=k1*K0+ω
[0018] Among them, K0 refers to the water level data upstream of the hydropower station; k1 refers to the regression coefficient; ω refers to the residual term;
[0019] Based on the real-time water level height data, the predicted water level height data of the first river channel turning point area is obtained.
[0020] According to the above technical solution, the intelligent selection of water level monitoring points includes:
[0021] According to the water level analysis model, between the inflection point areas of the river channel, the water level monitoring data of the previous inflection point area of the river channel is used as the new horizontal coordinate each time, and the water level monitoring data of the current inflection point area of the river channel is used as the new vertical coordinate, and the water level analysis model is continuously constructed to realize the functional relationship between the water level monitoring data of the previous inflection point area of the river channel and the water level monitoring data of the next inflection point area of the river channel;
[0022] Based on the functional relationship between the water level monitoring data of the previous river channel turning point area and the water level monitoring data of the next river channel turning point area, the predicted water level height data of the next river channel turning point area can be formed according to the predicted water level height data of the previous river channel turning point area, and the water level monitoring point can be intelligently selected based on the predicted water level height data of each river channel turning point area;
[0023] include:
[0024] Obtain each water level height data under historical data and the selected water level monitoring point for any river turning point area;
[0025] All water level height data are written into a sample set. The water level height data of the same water level monitoring point use the same mark to form a data sample set, and each sample is numbered;
[0026] Calculate the distance between samples to form a sample distance matrix;
[0027]
[0028] Among them, D1,2,D2,1 refers to the distance between sample 1 and sample 2; D n , 1 refers to the distance between sample n and sample 1; n represents the total number of samples;
[0029] The system sets a threshold and selects neighboring samples based on the threshold. The point with more neighboring samples is used as the geometric center of the representative point, including:
[0030] Take each row of the sample distance matrix as the selection basis, calculate the number of data in each row that is less than the threshold, select the row with the largest number of data as the selection row, select another row corresponding to the data less than the threshold on the selection row, and form a set of matrix rows with all the selected rows, which is recorded as the first discarded row;
[0031] In the sample distance matrix, all rows of the first discarded row are deleted, and rows are selected from the remaining rows again, and rows are discarded according to the new selected rows. The discarded rows are not counted in the new discarded rows, until only one row is left in the sample distance matrix;
[0032] Divide all discarded rows into ranges, take the maximum and minimum values of the data in any discarded row as the two ends of the range, and form the range of each discarded row;
[0033] Get real-time water level data and perform range selection, which includes:
[0034] The absolute value of the difference between the midpoint of the range and the water level data is selected. The real-time water level data belongs to the discarded row with the smallest absolute value of the difference. According to the mark, the number of water level data of each monitoring point in the discarded row is obtained, and the corresponding monitoring point with the highest proportion is used as the water level monitoring point in the current river turning point area.
[0035] According to the above technical solution, in step S4, it also includes:
[0036] A real-time warning calculation module is constructed. According to the output of the water level monitoring points in the turning point area of each river channel, during the real-time water release process of the hydropower station, if the difference between the predicted data values of any two water level heights exceeding the water level monitoring points is greater than the system threshold, a real-time warning message will be issued to the downstream of the released river.
[0037] Based on a distributed water level data analysis system, the system includes: a water level monitoring module, a distributed water level analysis module, an intelligent point feedback module and a real-time warning calculation module;
[0038] The water level monitoring module is used to monitor the water release data of the hydropower station and obtain the historical data of the water release of the hydropower station; the distributed water level analysis module is used to obtain the water level height data of the upstream of the hydropower station and the water level monitoring data of the first river channel turning point area on the water release river from the historical data, build a water level analysis model, and output the functional relationship between the water level height data of the upstream of the hydropower station and the water level height data of the first river channel turning point area on the water release river; the intelligent point feedback module is used to build a water level monitoring point analysis model for each river channel turning point area on the water release river, and based on the real-time water level height data, intelligently select the water level monitoring point to feedback to the system administrator port; the real-time warning calculation module is based on the real-time monitoring data of each river channel turning point area on the water release river of the hydropower station, and when the system preset value is not met, the real-time warning calculation module sends real-time warning information to the downstream of the water release river;
[0039] The output end of the water level monitoring module is connected to the input end of the distributed water level analysis module; the output end of the distributed water level analysis module is connected to the input end of the intelligent point feedback module; the output end of the intelligent point feedback module is connected to the input end of the real-time warning calculation module.
[0040] According to the above technical solution, the distributed water level analysis module includes a distributed arrangement unit and a water level analysis unit;
[0041] The distributed arrangement unit is used to arrange sensors at monitoring points, and arranges a number of monitoring points at each river channel turning point; the water level analysis unit is used to obtain water level height data upstream of the hydropower station and water level monitoring data of the first river channel turning point area on the released river, build a water level analysis model, and output a functional relationship between the water level height data upstream of the hydropower station and the water level height data of the first river channel turning point area on the released river;
[0042] The output end of the distributed arrangement unit is connected to the input end of the water level analysis unit.
[0043] According to the above technical solution, the intelligent point feedback module includes a water level monitoring point analysis unit and a selection unit;
[0044] The water level monitoring point analysis unit is used to construct a water level monitoring point analysis model for each channel turning point area on the released river; the selection unit intelligently selects water level monitoring points based on real-time water level height data and feeds them back to the system administrator port;
[0045] The output end of the water level monitoring point analysis unit is connected to the input end of the selection unit.
[0046] According to the above technical solution, the real-time warning calculation module includes a real-time monitoring unit and a warning unit;
[0047] The real-time monitoring unit is used to monitor the real-time monitoring data of each river channel turning point area on the water discharge river of the hydropower station; the warning unit is used to send real-time warning information to the downstream of the water discharge river when the real-time monitoring data does not meet the system preset value;
[0048] The output end of the real-time monitoring unit is connected to the input end of the warning unit.
[0049] Compared with the prior art, the beneficial effects achieved by the present invention are: the present invention can quickly and intelligently find water level monitoring points in various inflection point areas during the water release process upstream of the hydropower station, and the use of a distributed approach can effectively prevent changes in natural factors and field conditions. The monitored water level data can be fed back in a timely manner to improve the early warning capability. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0051] Figure 1 It is a flow chart of the distributed water level data analysis method of the present invention. DETAILED DESCRIPTION
[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] See also Figure 1 In the first embodiment, a distributed water level data analysis method is provided, the method comprising:
[0054] Acquire historical data of water release from a hydropower station, wherein the historical data includes water level monitoring data of inflection points of each river channel on the river released by the hydropower station;
[0055] In the historical data, the water level data upstream of the hydropower station and the water level monitoring data of the first channel turning point area on the released river are obtained, a water level analysis model is constructed, and the functional relationship between the water level data upstream of the hydropower station and the water level data of the first channel turning point area on the released river is output;
[0056] The river channel inflection point area includes:
[0057] The straight line where the current river channel is located forms an angle θ with the straight line where the hydropower station discharges water. When the angle θ is greater than the angle threshold set by the system, the vertex position of the angle θ is recorded as the river channel turning point, and the area formed with the river channel turning point as the center and R as the radius is recorded as the river channel turning point area, where R is a constant set by the system.
[0058] The water level analysis model includes:
[0059] Obtain the historical data of water release from the hydropower station. In the historical data of single water release, the water level height data upstream of the hydropower station is used as the horizontal coordinate, and the water level monitoring data of the first river channel turning point area on the released river is used as the vertical coordinate to form the coordinate base point of the single water release data;
[0060] The water level monitoring data of the first river channel turning point area on the released water river refers to: obtaining the monitoring data of all monitoring points in the first river channel turning point area, calculating the average value A0, and taking A0 as the water level monitoring data of the first river channel turning point area on the released water river; performing monitoring point analysis on the first river channel turning point area, and the monitoring point analysis includes:
[0061] Take |A0-B i The monitoring point corresponding to the minimum value of | is recorded as the monitoring point of the first river turning point area this time, where B i Refers to the water level height data monitored at the ith monitoring point in the first river channel turning point area;
[0062] Create a data set and form a water level analysis model based on the different coordinate base points in the data set:
[0063] A0=k1*K0+ω
[0064] Among them, K0 refers to the water level data upstream of the hydropower station; k1 refers to the regression coefficient; ω refers to the residual term;
[0065] Based on the real-time water level height data, the predicted water level height data of the first river channel turning point area is obtained.
[0066] The intelligent selection of water level monitoring points includes:
[0067] According to the water level analysis model, between the inflection point areas of the river channel, the water level monitoring data of the previous inflection point area of the river channel is used as the new horizontal coordinate each time, and the water level monitoring data of the current inflection point area of the river channel is used as the new vertical coordinate, and the water level analysis model is continuously constructed to realize the functional relationship between the water level monitoring data of the previous inflection point area of the river channel and the water level monitoring data of the next inflection point area of the river channel;
[0068] Construct a water level monitoring point analysis model for each channel turning point area on the released river, and intelligently select water level monitoring points based on real-time water level height data and feed them back to the system administrator port;
[0069] Based on the functional relationship between the water level monitoring data of the previous river channel turning point area and the water level monitoring data of the next river channel turning point area, the predicted water level height data of the next river channel turning point area can be formed according to the predicted water level height data of the previous river channel turning point area, and the water level monitoring point can be intelligently selected based on the predicted water level height data of each river channel turning point area;
[0070] include:
[0071] Obtain each water level height data under historical data and the selected water level monitoring point for any river turning point area;
[0072] All water level height data are written into a sample set. The water level height data of the same water level monitoring point use the same mark to form a data sample set, and each sample is numbered;
[0073] For example, the sample set is (the data is for reference only):
[0074] a1: 0.5; 1; 1; 1.5; 1;
[0075] a2: 0; 0; 0; 1; 0;
[0076] a3:1;0;1;2;0;
[0077] Calculate the distance between samples to form a sample distance matrix;
[0078]
[0079] Among them, D1,2,D2,1 refers to the distance between sample 1 and sample 2; D n , 1 refers to the distance between sample n and sample 1; n represents the total number of samples;
[0080] Then the sample distance matrix is:
[0081] a1: 0.0; 1.5; 1.1;
[0082] a2: 1.5; 0.0; 1.0;
[0083] a3: 1.1; 1.0; 0.0;
[0084] The system sets the threshold to 1.2, selects neighbor samples based on the threshold, and uses the point with more neighbor samples as the geometric center of the representative point, including:
[0085] Take each row of the sample distance matrix as the selection basis, calculate the number of data in each row that is less than the threshold, select the row with the largest number of data as the selection row, select another row corresponding to the data less than the threshold on the selection row, and form a set of matrix rows with all the selected rows, which is recorded as the first discarded row;
[0086] Then the selected selection behavior is the third row, and the first discard behavior is [a1, a2];
[0087] In the sample distance matrix, all rows of the first discarded row are deleted, and rows are selected from the remaining rows again, and rows are discarded according to the new selected rows. The discarded rows are not counted in the new discarded rows, until only one row is left in the sample distance matrix;
[0088] Divide all discarded rows into ranges, take the maximum and minimum values of the data in any discarded row as the two ends of the range, and form the range of each discarded row;
[0089] Get real-time water level data and perform range selection, which includes:
[0090] The absolute value of the difference between the midpoint of the range and the water level data is selected. The real-time water level data belongs to the discarded row with the smallest absolute value of the difference. According to the mark, the number of water level data of each monitoring point in the discarded row is obtained, and the corresponding monitoring point with the highest proportion is used as the water level monitoring point in the current river turning point area.
[0091] In step S4, it also includes:
[0092] A real-time warning calculation module is constructed. According to the output of the water level monitoring points in the turning point area of each river channel, during the real-time water release process of the hydropower station, if the difference between the predicted data values of any two water level heights exceeding the water level monitoring points is greater than the system threshold, a real-time warning message will be issued to the downstream of the released river.
[0093] In the second embodiment, a distributed water level data analysis system is provided, which includes: a water level monitoring module, a distributed water level analysis module, an intelligent point feedback module and a real-time warning calculation module;
[0094] The water level monitoring module is used to monitor the water release data of the hydropower station and obtain the historical data of the water release of the hydropower station; the distributed water level analysis module is used to obtain the water level height data of the upstream of the hydropower station and the water level monitoring data of the first river channel turning point area on the water release river from the historical data, build a water level analysis model, and output the functional relationship between the water level height data of the upstream of the hydropower station and the water level height data of the first river channel turning point area on the water release river; the intelligent point feedback module is used to build a water level monitoring point analysis model for each river channel turning point area on the water release river, and based on the real-time water level height data, intelligently select the water level monitoring point to feedback to the system administrator port; the real-time warning calculation module is based on the real-time monitoring data of each river channel turning point area on the water release river of the hydropower station, and when the system preset value is not met, the real-time warning calculation module sends real-time warning information to the downstream of the water release river;
[0095] The output end of the water level monitoring module is connected to the input end of the distributed water level analysis module; the output end of the distributed water level analysis module is connected to the input end of the intelligent point feedback module; the output end of the intelligent point feedback module is connected to the input end of the real-time warning calculation module.
[0096] The distributed water level analysis module includes a distributed arrangement unit and a water level analysis unit;
[0097] The distributed arrangement unit is used to arrange sensors at monitoring points, and arranges a number of monitoring points at each river channel turning point; the water level analysis unit is used to obtain water level height data upstream of the hydropower station and water level monitoring data of the first river channel turning point area on the released river, build a water level analysis model, and output a functional relationship between the water level height data upstream of the hydropower station and the water level height data of the first river channel turning point area on the released river;
[0098] The output end of the distributed arrangement unit is connected to the input end of the water level analysis unit.
[0099] The intelligent point feedback module includes a water level monitoring point analysis unit and a selection unit;
[0100] The water level monitoring point analysis unit is used to construct a water level monitoring point analysis model for each channel turning point area on the released river; the selection unit intelligently selects water level monitoring points based on real-time water level height data and feeds them back to the system administrator port;
[0101] The output end of the water level monitoring point analysis unit is connected to the input end of the selection unit.
[0102] The real-time warning calculation module includes a real-time monitoring unit and a warning unit;
[0103] The real-time monitoring unit is used to monitor the real-time monitoring data of each river channel turning point area on the water discharge river of the hydropower station; the warning unit is used to send real-time warning information to the downstream of the water discharge river when the real-time monitoring data does not meet the system preset value;
[0104] The output end of the real-time monitoring unit is connected to the input end of the warning unit.
[0105] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0106] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. Based on distributed water level data analysis method, Features: The method comprises the following steps: S1. Acquire historical data of water discharge from a hydropower station, wherein the historical data includes water level monitoring data of inflection points of each river channel on the river discharged by the hydropower station; S2. Obtain the water level data upstream of the hydropower station and the water level monitoring data of the first channel inflection point area on the released river from the historical data, build a water level analysis model, and output the functional relationship between the water level data upstream of the hydropower station and the water level data of the first channel inflection point area on the released river; S3. Build a water level monitoring point analysis model for each channel turning point area on the released river, and intelligently select water level monitoring points based on real-time water level height data and feed them back to the system administrator port; S4. Construct a real-time warning calculation module, based on the real-time monitoring data of the turning point area of each river channel on the water discharge river of the hydropower station, and send real-time warning information to the downstream of the water discharge river when the system preset value is not met; The water level analysis model includes: Obtain the historical data of water release from the hydropower station. In the historical data of single water release, the water level height data upstream of the hydropower station is used as the horizontal coordinate, and the water level monitoring data of the first river channel turning point area on the released river is used as the vertical coordinate to form the coordinate base point of the single water release data; The water level monitoring data of the first river channel inflection point area on the released river refers to: obtaining the monitoring data of all monitoring points in the first river channel inflection point area, and calculating the average value A 0 , with A 0 The water level monitoring data of the first river channel turning point area on the released river; the monitoring point analysis is performed on the first river channel turning point area, and the monitoring point analysis includes: Take |A 0 -B i The monitoring point corresponding to the minimum value of | is recorded as the monitoring point of the first river channel turning point area this time, where B i Refers to the water level height data monitored by the ith monitoring point in the first river channel turning point area; Create a data set and form a water level analysis model based on the different coordinate base points in the data set: A 0 =k 1 *K 0 +oh Among them, K 0 Refers to the water level data upstream of the hydropower station; k 1 refers to the regression coefficient; ω refers to the residual term; Based on the real-time water level data, the predicted water level data of the first river channel turning point area is obtained; The intelligent selection of water level monitoring points includes: According to the water level analysis model, between the inflection point areas of the river channel, the water level monitoring data of the previous inflection point area of the river channel is used as the new horizontal coordinate each time, and the water level monitoring data of the current inflection point area of the river channel is used as the new vertical coordinate, and the water level analysis model is continuously constructed to realize the functional relationship between the water level monitoring data of the previous inflection point area of the river channel and the water level monitoring data of the next inflection point area of the river channel; Based on the functional relationship between the water level monitoring data of the previous river channel turning point area and the water level monitoring data of the next river channel turning point area, the predicted water level height data of the next river channel turning point area can be formed according to the predicted water level height data of the previous river channel turning point area, and the water level monitoring point can be intelligently selected based on the predicted water level height data of each river channel turning point area; include: Obtain each water level height data under historical data and the selected water level monitoring point for any river turning point area; All water level height data are written into a sample set. The water level height data of the same water level monitoring point use the same mark to form a data sample set, and each sample is numbered; Calculate the distance between samples to form a sample distance matrix; Among them, D 1、2 , D 2、1 Refers to the distance between sample 1 and sample 2; D n、1 Refers to the distance between sample n and sample 1; n represents the total number of samples; The system sets a threshold and selects neighboring samples based on the threshold. The point with more neighboring samples is used as the geometric center of the representative point, including: Take each row of the sample distance matrix as the selection basis, calculate the number of data in each row that is less than the threshold, select the row with the largest number of data as the selection row, select another row corresponding to the data less than the threshold on the selection row, and form a set of matrix rows with all the selected rows, which is recorded as the first discarded row; In the sample distance matrix, all rows of the first discarded row are deleted, and rows are selected from the remaining rows again, and rows are discarded according to the new selected rows. The discarded rows are not counted in the new discarded rows, until only one row is left in the sample distance matrix; Divide all discarded rows into ranges, take the maximum and minimum values of the data in any discarded row as the two ends of the range, and form the range of each discarded row; Get real-time water level data and perform range selection, which includes: The absolute value of the difference between the midpoint of the range and the water level data is selected. The real-time water level data belongs to the discarded row with the smallest absolute value of the difference. According to the mark, the number of water level data of each monitoring point in the discarded row is obtained, and the corresponding monitoring point with the highest proportion is used as the water level monitoring point in the current river turning point area.
2. The distributed water level data analysis method according to claim 1, Features: The river channel inflection point area includes: The straight line where the current river channel is located forms an angle θ with the straight line where the hydropower station discharges water. When the angle θ is greater than the angle threshold set by the system, the vertex position of the angle θ is recorded as the river channel turning point, and the area formed with the river channel turning point as the center and R as the radius is recorded as the river channel turning point area, where R is a constant set by the system.
3. The distributed water level data analysis method according to claim 2, Features: In step S4, it also includes: A real-time warning calculation module is constructed. According to the output of the water level monitoring points in the turning point area of each river channel, during the real-time water release process of the hydropower station, if the difference between the predicted data values of any two water level heights exceeding the water level monitoring points is greater than the system threshold, a real-time warning message will be issued to the downstream of the released river.
4. A distributed water level data analysis system, using the distributed water level data analysis method as claimed in claim 1, Features: The system includes: water level monitoring module, distributed water level analysis module, intelligent point feedback module and real-time warning calculation module; The water level monitoring module is used to monitor the water release data of the hydropower station and obtain the historical data of the water release of the hydropower station; the distributed water level analysis module is used to obtain the water level height data of the upstream of the hydropower station and the water level monitoring data of the first river channel turning point area on the water release river from the historical data, build a water level analysis model, and output the functional relationship between the water level height data of the upstream of the hydropower station and the water level height data of the first river channel turning point area on the water release river; the intelligent point feedback module is used to build a water level monitoring point analysis model for each river channel turning point area on the water release river, and based on the real-time water level height data, intelligently select the water level monitoring point to feedback to the system administrator port; the real-time warning calculation module is based on the real-time monitoring data of each river channel turning point area on the water release river of the hydropower station, and when the system preset value is not met, the real-time warning calculation module sends real-time warning information to the downstream of the water release river; The output end of the water level monitoring module is connected to the input end of the distributed water level analysis module; the output end of the distributed water level analysis module is connected to the input end of the intelligent point feedback module; the output end of the intelligent point feedback module is connected to the input end of the real-time warning calculation module.
5. The distributed water level data analysis system according to claim 4, Features: The distributed water level analysis module includes a distributed arrangement unit and a water level analysis unit; The distributed arrangement unit is used to arrange sensors at monitoring points, and arranges a number of monitoring points at each river channel turning point; the water level analysis unit is used to obtain water level height data upstream of the hydropower station and water level monitoring data of the first river channel turning point area on the released river, build a water level analysis model, and output a functional relationship between the water level height data upstream of the hydropower station and the water level height data of the first river channel turning point area on the released river; The output end of the distributed arrangement unit is connected to the input end of the water level analysis unit.
6. The distributed water level data analysis system according to claim 4, Features: The intelligent point feedback module includes a water level monitoring point analysis unit and a selection unit; The water level monitoring point analysis unit is used to construct a water level monitoring point analysis model for each channel turning point area on the released river; the selection unit intelligently selects water level monitoring points based on real-time water level height data and feeds them back to the system administrator port; The output end of the water level monitoring point analysis unit is connected to the input end of the selection unit.
7. The distributed water level data analysis system according to claim 4, Features: The real-time warning calculation module includes a real-time monitoring unit and a warning unit; The real-time monitoring unit is used to monitor the real-time monitoring data of each river channel turning point area on the water discharge river of the hydropower station; the warning unit is used to send real-time warning information to the downstream of the water discharge river when the real-time monitoring data does not meet the system preset value; The output end of the real-time monitoring unit is connected to the input end of the warning unit.
Citation Information
Patent Citations
Precipitation forecasting and support vector machine coupled real-time river flood peak water level forecasting method
CN108921345A
Rapid water quality forecasting and early warning method and system based on distributed computing
CN111310976A
Hydrology and water resource monitoring method and system based on machine learning
CN114118754A
Distributed power supply integrated monitoring system and method based on fusion terminal
CN115296424A
Disaster degree identification method and device based on multi-source information, equipment and medium
CN116485614A