A method, system and storage medium for generating a construction inspection sheet
By establishing the correlation between the task feature atomic database and the inspection feature atomic database, construction inspection orders are generated, which solves the problems of low efficiency and poor accuracy in the generation of construction inspection orders in the existing technology, and achieves efficient and flexible construction management.
Patent Information
- Application Number
- CN202410869145.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-01
AI Technical Summary
The generation of existing construction inspection orders requires manual operations, resulting in low information processing efficiency, poor accuracy, and difficulty in flexibly responding to different working conditions.
By obtaining the task characteristic atom library and the inspection characteristic atom library, the correlation between the two is established, the target task characteristic atom and the inspection characteristic atom are determined, and the target inspection order is generated, including determining the target construction site, inspection personnel, and inspection frequency.
It achieves efficient, accurate and flexible generation of construction inspection orders, reduces the impact of human factors, improves construction management efficiency, and has traceability to facilitate subsequent analysis and control.
Smart Images

Figure CN118411126B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of construction inspection, and in particular to a method, system and storage medium for generating a construction inspection sheet. Background Art
[0002] In the construction industry, inspection sheets are standardized documents used to record and track construction site conditions. In order to ensure that the quality, safety and progress of the construction process are effectively controlled, quality, safety and progress inspections are usually used. In this way, the main problems of monitoring, early warning and prediction of the construction site are solved. Through real-time monitoring and data analysis, construction efficiency and quality can be improved, and risks and costs can be reduced.
[0003] Currently, the generation of inspection task orders needs to be done manually. However, due to the large amount of information in construction projects and the complexity of construction areas, it is a huge challenge for humans to distinguish valid information from the massive amount of content and generate task orders.
[0004] Therefore, it is desired to provide a method, system and storage medium for generating a construction inspection sheet, so as to generate the construction inspection sheet efficiently, accurately and flexibly. Summary of the invention
[0005] One or more embodiments of this specification provide a method for generating a construction inspection list. The method includes: obtaining a task feature atom library and an inspection feature atom library; establishing an association relationship between the task feature atoms in the task feature atom library and the inspection feature atoms in the inspection feature atom library; obtaining a task list, and determining the target construction site to be inspected and the target task feature atom based on the task list; determining the target inspection feature atom corresponding to the target task feature atom based on the target task feature atom and the association relationship; determining the target inspection personnel and the target inspection frequency based on the target construction site; and generating a target inspection list based on the target inspection feature atom, the target inspection personnel and the target inspection frequency.
[0006] One or more embodiments of the present specification provide a system for generating a construction inspection form. The system includes: an acquisition module for acquiring a task feature atom library and an inspection feature atom library; an establishment module for establishing an association relationship between task feature atoms in the task feature atom library and inspection feature atoms in the inspection feature atom library; a determination module for: acquiring a task form, and determining the target construction site and target task feature atoms to be inspected based on the task form; determining the target inspection feature atoms corresponding to the target task feature atoms based on the target task feature atoms and the association relationship; and determining the target inspection personnel and the target inspection frequency based on the target construction site; a generation module for generating a target inspection form based on the target inspection feature atoms, the target inspection personnel and the target inspection frequency.
[0007] One or more embodiments of the present specification provide a computer-readable storage medium, wherein the storage medium stores computer instructions. When a computer reads the computer instructions in the storage medium, the computer executes the method for generating a construction inspection sheet.
[0008] The embodiments of this specification include at least the following beneficial effects: (1) High efficiency: Flexible assembly of inspection sheets based on task feature atoms and inspection feature atoms can ensure the consistency and accuracy of inspection information, reduce the impact of human factors on inspections, and improve efficiency; (2) High flexibility: The complete inspection content cannot be reused, but the inspection information at the atomic level can be reused. Flexible assembly of inspection feature atoms according to different working conditions can construct inspection sheets more flexibly; (3) Automation: The human brain cannot remember such a large amount of information, but computers can. The flexible assembly of inspection sheets based on feature atoms or codes can ensure the consistency and accuracy of inspection information, reduce the impact of human factors on inspections, and improve efficiency; (4) Traceability: Recording and tracking the transmission process and results of inspection information is convenient for subsequent query and analysis, which is conducive to pre-control and preventive maintenance, and later tracing and analysis of the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] Figure 1 It is a module schematic diagram of a system for generating a construction inspection sheet according to some embodiments of this specification;
[0010] Figure 2 is an exemplary flow chart of a method for generating a construction inspection sheet according to some embodiments of this specification;
[0011] Figure 3 is an exemplary schematic diagram of a task feature atom library according to some embodiments of this specification;
[0012] Figure 4is an exemplary schematic diagram of patrolling a characteristic atom library according to some embodiments of this specification;
[0013] Figure 5 It is an exemplary schematic diagram of a tree structure according to some embodiments of the present specification. DETAILED DESCRIPTION
[0014] In order to more clearly illustrate the technical solutions of the embodiments of this specification, the following is a brief introduction to the drawings required for the description of the embodiments. Obviously, the drawings described below are only some examples or embodiments of this specification. For ordinary technicians in this field, this specification can also be applied to other similar scenarios based on these drawings without creative work. Unless it is obvious from the language environment or otherwise explained, the same reference numerals in the figures represent the same structure or operation.
[0015] It should be understood that the "system", "device", "unit" and / or "module" used herein are a method for distinguishing different components, elements, parts, portions or assemblies at different levels. However, if other words can achieve the same purpose, the words can be replaced by other expressions.
[0016] As shown in this specification and claims, unless the context clearly indicates an exception, the words "a", "an", "an" and / or "the" do not refer to the singular and may also include the plural. Generally speaking, the terms "comprise" and "include" only indicate the inclusion of the steps and elements that have been clearly identified, and these steps and elements do not constitute an exclusive list. The method or device may also include other steps or elements.
[0017] Flowcharts are used in this specification to illustrate the operations performed by the system according to the embodiments of this specification. It should be understood that the preceding or following operations are not necessarily performed precisely in order. Instead, the steps may be processed in reverse order or simultaneously. At the same time, other operations may also be added to these processes, or one or more operations may be removed from these processes.
[0018] Figure 1 1 is a schematic diagram of a module of a system for generating a construction inspection form according to some embodiments of this specification. Figure 1 As shown, the construction inspection form generation system 100 may include an acquisition module 110 , an establishment module 120 , a determination module 130 , and a generation module 140 .
[0019] In some embodiments, the acquisition module 110 may acquire a task feature atom library and a patrol feature atom library.
[0020] In some embodiments, the acquisition module 110 may acquire multiple historical task orders, extract at least one construction feature point from each of the multiple historical task orders, and determine at least one corresponding task feature atom based on the at least one construction feature point to construct a task feature atom library. For more information on acquiring a task feature atom library, see Figure 2 and its related description.
[0021] In some embodiments, the acquisition module 110 may acquire multiple historical inspection orders, extract at least one inspection feature point from each of the multiple historical inspection orders, and determine at least one corresponding inspection feature atom based on the at least one inspection feature point to construct an inspection feature atom library. For more information on acquiring the inspection feature atom library, see Figure 2 and its related description.
[0022] In some embodiments, the establishing module 120 may establish an association relationship between the task feature atoms in the task feature atom library and the patrol feature atoms in the patrol feature atom library.
[0023] In some embodiments, the establishment module 120 can arbitrarily select a task feature atom in the task feature atom library as a query item, match it one by one in the patrol feature atom library based on a preset matching model, and determine the matching item, where the preset matching model is a machine learning model; establish an association relationship between the query item and the matching item, and obtain the association relationship between the task feature atom in the task feature atom library and the patrol feature atom in the patrol feature atom library.
[0024] In some embodiments, in response to the matching item being a parent atom including multiple patrol feature atoms, the establishing module 120 may establish an association relationship between the multiple patrol feature atoms included in the parent atom and the query item. For more information on establishing an association relationship, see Figure 2 , Figure 5 and its related description.
[0025] In some embodiments, the determination module 130 can obtain a task order, and determine the target construction site to be inspected and the target task feature atoms based on the task order; determine the target inspection feature atoms corresponding to the target task feature atoms based on the target task feature atoms and the association relationship; and determine the target inspection personnel and target inspection frequency based on the target construction site.
[0026] In some embodiments, the determination module 130 may determine the inspection type based on the target construction site; and determine the target inspection personnel and the target inspection frequency based on the inspection type.
[0027] In some embodiments, the determination module 130 can obtain acceptance information of similar construction sites outside the task list based on the target construction site; in response to the acceptance information satisfying the first preset condition, the inspection type is determined as a regular inspection; in response to the acceptance information not satisfying the first preset condition, the inspection type is determined as a special inspection.
[0028] In some embodiments, the determination module 130 can obtain construction safety information of similar construction sites outside the task list based on the target construction site; in response to the construction safety information satisfying the second preset condition, determine the inspection type as a regular inspection; in response to the construction safety information not satisfying the second preset condition, determine the inspection type as a special inspection.
[0029] In some embodiments, the determination module 130 can determine the reference inspection frequency in response to the inspection type being a routine inspection by querying the inspection orders of the task orders corresponding to the same type of construction sites, and determine the target inspection frequency corresponding to the routine inspection based on the reference inspection frequency; and query the management personnel of the target construction site and determine the management personnel as the target inspection personnel corresponding to the routine inspection.
[0030] In some embodiments, the determination module 130 can query the construction cycle of the target construction site in response to the inspection type being a special inspection, and determine the target inspection frequency corresponding to the special inspection based on the construction cycle; and query the acceptance personnel of the target construction site, and determine the acceptance personnel as the target inspection personnel corresponding to the special inspection.
[0031] In some embodiments, the determination module 130 can determine the inspection intensity based on the construction safety information in response to the inspection type being a special inspection, and determine the target inspection frequency corresponding to the special inspection based on the inspection intensity; and query the management personnel of the target construction site and determine the management personnel as the target inspection personnel corresponding to the special inspection.
[0032] For more information on determining target task characteristics, target patrol characteristic atoms, target patrol personnel, and target patrol frequency, see Figure 2 and its related description.
[0033] In some embodiments, the generation module 140 may generate a target inspection list based on the target inspection feature atoms, target inspection personnel, and target inspection frequency.
[0034] In some embodiments, the generation module 140 can obtain an inspection order template; generate an initial inspection order based on the target inspection feature atoms and the inspection order template; and in response to receiving user confirmation feedback on the initial inspection order, generate a target inspection order based on the initial inspection order, target inspection personnel and target inspection frequency.
[0035] For more information on generating a target inspection list, see Figure 2and its related description.
[0036] In some embodiments, the system 100 for generating a construction inspection form may further include a rectification module (not shown in Figure 1 In some embodiments, the rectification module can obtain the inspection results corresponding to the target inspection form; based on the inspection results, a rectification form is generated. For more information on generating rectification forms, see Figure 2 and its related description.
[0037] Figure 2 This is an exemplary flow chart of a method for generating a construction inspection form according to some embodiments of this specification. In some embodiments, process 200 can be executed by a processor. For example, process 200 can be stored in a storage device in the form of a program or instruction, and when the processor executes the program or instruction, process 200 can be implemented. The operational diagram of process 200 presented below is illustrative. In some embodiments, the process can be completed using one or more additional operations not described and / or one or more operations not discussed. Figure 2 As shown, the method for generating a construction inspection form includes the following steps. In addition, Figure 2 The order in which the operations of process 200 are illustrated and described below is not intended to be limiting.
[0038] S210, obtaining a task feature atom library and an inspection feature atom library.
[0039] The task feature atom library is a database used to store task feature atoms.
[0040] Task feature atoms refer to data obtained by splitting relevant information of construction tasks level by level. In some embodiments, task feature atoms may include one or any combination of task item atoms, engineering category atoms, construction phase atoms, construction location atoms, construction progress atoms, construction cost atoms, and construction material atoms.
[0041] Task item atoms refer to the data obtained by splitting the task items contained in the task list level by level.
[0042] In some embodiments, the processor may decompose the task list level by level to determine the task items at each level, until the lower-level task item obtained by decomposition cannot be decomposed any further, and then the lower-level task item may be determined as the last-level task item.
[0043] A super-level task item may contain one or more subordinate tasks. For example, when a super-level task item is to build a wall, its subordinate tasks may include: cleaning and leveling the wall location, watering and moistening the bricks, marking the wall location with ink lines, preparing cement mortar, applying cement mortar on the ground foundation, placing the first layer of bricks, applying cement mortar on the first layer of bricks, placing the second layer of bricks, scraping the cement mortar, correcting the bricks, installing the wall corner line, etc.
[0044] The final task item refers to the task at the lowest and most detailed level after the construction task is decomposed. The final task item does not include the lower-level task items, that is, the final task item is the lowest-level task item among all task items. For example, when a task item is to install a window, the final task items obtained by disassembling it may include cleaning the wall, installing the window frame, etc.
[0045] It should be noted that the "divisible" and "indivisible" referred to in the embodiments of this specification refer to whether the task item can be further divided in terms of the construction skills required to complete the task item. Specifically, a type of work includes at least one construction skill under the type of work, and a worker can only belong to the type of work corresponding to the construction skill if he possesses any one of the construction skills.
[0046] Taking the type of work as a rebar worker as an example, the construction skills under this type of work may include rebar rust removal, rebar straightening, rebar connection, etc., and rebar rust removal, rebar straightening, and rebar connection cannot be further divided into lower-level construction skills, so rebar rust removal, rebar straightening, and rebar connection each correspond to a final-level task item atom. It should be understood that some construction skills may also have multiple levels, and the construction skills corresponding to the final-level task item are the final-level construction skills.
[0047] In some embodiments, Figure 3 As shown, after splitting the task items level by level, multiple levels of task item atoms can be obtained. For example, the upper-level task item atom can be further split into one or more lower-level task item atoms. When the task items are split into the smallest atomic level, the final-level task item atom can be obtained. The final-level task item atom refers to the task item atom corresponding to the final-level task item. The final-level task item atom cannot be split any further.
[0048] Taking the task list of a construction project of a housing construction project as an example, the first-level task item atom may include "building a building", and the second-level task item atom may include "building a wall". When building a wall, sub-task items such as "cleaning and leveling the wall location", "watering the bricks", and "laying out the wall location with an ink line" are required. If these sub-task items cannot be split any further, they can be considered as the last-level task item atom.
[0049] In some embodiments, the relevant production information of the task item atom may include the task content of the task item (e.g., cleaning and leveling the wall-building position, watering and moistening the bricks, etc.), task time (e.g., planned start time, planned end time, planned duration, etc.), required resources, etc. For example, if the task item is to install windows, the relevant production information of the task item atom corresponding to the task item may include: task name—install windows; estimated duration—2 days; required resources—2 workers, some materials.
[0050] In some embodiments, the relevant production information of the task item atom can be stored after being bound to the name or code of the task item atom, and the relevant production information of the task item atom can be obtained by retrieving the name or code of the task item atom. The name of the task item atom can be preset. For more information about the code, see the relevant description below.
[0051] Engineering category atoms refer to the data obtained by splitting the engineering categories contained in the task order level by level.
[0052] The project category refers to the category to which the task order belongs. In some embodiments, the project category can be divided into categories including housing construction projects, power projects, highway projects, municipal public works projects, electromechanical installation projects, decoration and renovation projects, and landscaping projects according to the project field, construction purpose, etc. These project categories can be further divided. For example, housing construction projects can be divided into civil buildings, industrial buildings and structures, etc., and civil buildings can be further divided into hospitals, office buildings, and teaching buildings, etc.
[0053] In some embodiments, Figure 3 As shown, after the engineering category is split level by level, multiple levels of engineering category atoms can be obtained. For example, the upper-level engineering category atom can be further split into one or more lower-level engineering category atoms. When the engineering category is split into the smallest atomic level, the final-level engineering category atom can be obtained. The final-level engineering category atom refers to the engineering category at the lowest and most detailed level after the task order is decomposed. The final-level engineering category atom cannot be split any further.
[0054] Taking the task list of splitting the construction project of housing construction engineering as an example, the first-level engineering category atom can include "civil building" and the second-level task item atom can include "hospital". Among them, the hospital can be further split into inpatient building, outpatient building, etc. If these engineering categories cannot be split any further, they can be considered as the final engineering category atom.
[0055] In some embodiments, the relevant production information of the engineering category atom may include the engineering time corresponding to the engineering category to which the task order belongs (for example, the planned start time, planned end time, planned duration, etc.), the engineering contractor, etc.
[0056] In some embodiments, the relevant production information of the engineering category atom can be stored after being bound to the name or code of the engineering category atom, and the relevant production information of the engineering category atom can be obtained by retrieving the name or code of the engineering category atom. The name of the engineering category atom can be preset. For more information about the code, see the relevant description below.
[0057] Construction phase atoms refer to the data obtained by splitting the construction phases contained in the task order level by level.
[0058] In some embodiments, the construction phase may include a foundation engineering phase and a main engineering phase. The foundation engineering phase refers to the phase of building infrastructure. For example, the infrastructure may include a foundation pit, pile foundation, foundation, etc. The main engineering phase refers to the phase of building the main facilities. For example, the main facilities may include walls, stairs, columns, ceilings, etc.
[0059] In some embodiments, Figure 3 As shown, after the construction phases are split level by level, multiple levels of construction phase atoms can be obtained. For example, the upper construction phase atom can be further split into one or more lower construction phase atoms. When the construction phase is split into the smallest atomic level, the final construction phase atom can be obtained. The final construction phase atom refers to the construction phase at the lowest and most detailed level after the task order is decomposed. The final construction phase atom cannot be split any further.
[0060] Taking the construction project of housing construction as an example, the first-level construction stage atom can be the foundation engineering stage, and the second-level construction stage atom can be the foundation construction stage. Among them, the foundation construction stage can be further divided into measurement, line laying, pit digging, cleaning, etc. These construction stages cannot be divided any further and can be considered as the final construction stage atoms.
[0061] In some embodiments, the relevant production information of the construction phase atom may include the task items belonging to the construction phase, time information of the construction phase (for example, the planned start time, planned end time, planned duration, etc. of the construction phase), acceptance information (for example, whether it has been accepted), etc.
[0062] In some embodiments, the relevant production information of the construction phase atom can be stored after being bound to the name or code of the construction phase atom, and the relevant production information of the construction phase atom can be obtained by searching the name or code of the construction phase atom. The name of the construction phase atom can be preset. For more information about the code, see the relevant description below.
[0063] Construction site atoms refer to the data obtained by splitting the construction sites included in the task order level by level.
[0064] The construction site refers to the construction object corresponding to the task item. In some embodiments, the construction site can be divided into basements, main bodies, master plans, foundations, etc. according to the structure and composition of the building. These construction parts can be further divided. For example, the main body can be further divided into 1st floor, 2nd floor, etc., and 1st floor can be further divided into room levels, such as bedrooms, bathrooms, etc. At the room level, it can also be further divided into component levels, such as walls, beams, slabs, columns, etc.
[0065] In some embodiments, Figure 3 As shown, after the construction site is split level by level, multiple levels of construction site atoms can be obtained. For example, the upper construction site atom can be further split into one or more lower construction site atoms. When the construction site is split into the smallest atomic level, the final construction site atom can be obtained. The final construction site atom refers to the construction site at the lowest and most detailed level after the task list is decomposed. The final construction site atom cannot be split any further.
[0066] Taking the task list of splitting a construction project of a house construction project as an example, the first-level construction part atom can be the main part, and the second-level construction part atom can be the floor. Among them, the floor can be further split into the room level, such as bedroom and bathroom. The room level can be further split into the component level, such as wall, beam, plate, column, etc. The construction part corresponding to the component level cannot be split any further and can be considered as the last-level construction part atom.
[0067] In some embodiments, the relevant production information of the construction site atom may include the task item to which the construction site belongs, time information of the construction site (for example, the planned start time, planned end time, estimated construction period, etc. of the construction phase), acceptance information (for example, whether it has been accepted), etc.
[0068] In some embodiments, the relevant production information of the construction site atom can be stored after being bound to the name or code of the construction site atom, and the relevant production information of the construction site atom can be obtained by searching the name or code of the construction site atom. The name of the construction site atom can be preset. For more information about the code, please refer to the relevant description below.
[0069] Construction progress atoms refer to the data obtained by splitting the construction progress management method contained in the task order level by level.
[0070] In some embodiments, the construction progress management method may include a progress report, a construction log, etc. The progress report may be further divided into a monthly progress report and a weekly progress report.
[0071] In some embodiments, Figure 3As shown, after the construction progress management method is split, multiple levels of construction progress atoms can be obtained. For example, the upper construction progress atom can be further split into one or more lower construction progress atoms. When the construction progress management method is split into the smallest atomic level, the final construction progress atom can be obtained. The final construction progress atom refers to the construction progress management method of the task item at the lowest and most detailed level after the construction progress management method is decomposed. The final construction progress atom cannot be split any further.
[0072] Taking the task list of a housing construction project as an example, the first-level construction progress atom may include a "progress report", which may be further divided into a monthly progress report and a weekly progress report. If the monthly progress report and the weekly progress report cannot be divided any further, they may be considered as the final-level construction progress atom.
[0073] In some embodiments, the relevant production information of the construction progress atom may include the specific contents of the task items, progress reports or construction logs belonging to the construction progress management method.
[0074] In some embodiments, the relevant production information of the construction progress atom can be stored after being bound to the name or code of the construction progress atom, and the relevant production information of the construction progress atom can be obtained by retrieving the name or code of the construction progress atom. The name of the construction progress atom can be preset. For more information about the code, please refer to the relevant description below.
[0075] Construction cost atoms refer to the data obtained by splitting the construction costs of the task items contained in the task order according to the task item level. A task order can correspond to a total construction cost. Multiple levels of task items contained in the task order can each correspond to a construction cost. The construction cost corresponding to the last level task item cannot be divided any further.
[0076] In some embodiments, Figure 3 As shown in the figure, after the construction cost is split according to the task items, multiple levels of construction progress atoms can be obtained. For example, the upper construction cost atom can be further split into one or more lower construction cost atoms. When the construction cost is split into the smallest atomic level according to the task items, the final construction cost atom can be obtained. The final construction cost atom refers to the construction cost at the lowest and most detailed level after the task order is decomposed. The final construction cost atom cannot be split any further.
[0077] Taking the task list of splitting a construction project of a house construction project as an example, the first-level construction cost atom can be the construction cost corresponding to building a building, and the second-level construction cost atom can be the construction cost corresponding to building a wall. When building a wall, it is necessary to perform subtasks such as "cleaning and leveling the wall position", "watering and moistening the bricks", and "laying out the wall position with ink lines". These subtasks cannot be split any further, so the construction costs corresponding to these subtasks can be considered as the final-level construction cost atom.
[0078] In some embodiments, the relevant production information of the construction cost atom may include the expected cost of the corresponding task item, the actual consumed cost, etc. The expected cost is a measure of the cost that is expected to be consumed by the task item.
[0079] In some embodiments, the relevant production information of the construction cost atom can be stored after being bound to the name or code of the construction cost atom, and the relevant production information of the construction cost atom can be obtained by searching the name or code of the construction cost atom. The name of the construction cost atom can be preset. For more information about the code, see the relevant description below.
[0080] Construction material atoms refer to the data obtained by splitting the construction materials contained in the task items level by level.
[0081] In some embodiments, the categories of construction materials may include structural materials, decorative materials, special materials, etc. Structural materials can be further divided into steel, wood, bamboo, stone, cement, concrete, metal, bricks and tiles, ceramics, glass, engineering plastics, composite materials, etc. Among them, steel can be further divided into primary steel, secondary steel, tertiary steel, threaded steel, round steel, pipe angle steel, channel steel, I-beam, special-shaped steel, etc. Other structural materials can also be further divided, which will not be repeated here. Decorative materials can be further divided into coatings, paints, coatings, veneers, tiles, glass, etc. Among them, special materials refer to materials used for waterproofing, moisture-proofing, anti-corrosion, fireproofing, flame retardancy, sound insulation, heat insulation, thermal insulation, sealing, etc.
[0082] In some embodiments, Figure 3 As shown, after decomposing the construction materials level by level, multiple levels of construction material atoms can be obtained. For example, the upper-level construction material atom can be further decomposed into one or more lower-level construction material atoms. When the construction materials are decomposed into the smallest atomic level, the final-level construction material atom can be obtained. The final-level construction material atom refers to the category of the construction material at the lowest and most detailed level after the construction materials are decomposed. The final-level construction material atom cannot be decomposed any further.
[0083] Taking the construction project of housing construction as an example, the first-level construction material atom can be structural material, and the second-level construction material atom can be steel. Among them, steel can be further divided into first-level steel, second-level steel, third-level steel, threaded steel, round steel, pipe angle steel, channel steel, I-beam, special-shaped steel, etc. These construction materials cannot be further divided and can be considered as the final-level construction material atoms.
[0084] In some embodiments, the relevant production information of the construction material atom may include the task item to which the construction material belongs, the type, quantity, supplier information, etc. of the construction material.
[0085] In some embodiments, the relevant production information of the construction material atom can be stored after being bound to the name or code of the construction material atom, and the relevant production information of the construction material atom can be obtained by searching the name or code of the construction material atom. The name of the construction material atom can be preset. For more information about the code, please refer to the relevant description below.
[0086] In some embodiments, task feature atoms may also include construction area atoms.
[0087] Construction area atoms refer to data obtained by splitting the construction area included in the task list level by level. In some embodiments, multiple levels of construction area atoms can be obtained after splitting the construction area. For example, the upper-level construction area atom can be further split into one or more lower-level construction area atoms. When the construction area is split into the smallest atomic level, the final-level construction area atom can be obtained. The final-level construction area atom refers to the construction area at the bottom and most detailed level after the construction area is decomposed. The final-level construction area atom cannot be split any further.
[0088] In some embodiments, the processor can split the task list layer by layer from multiple directions to the smallest atomic level based on prior knowledge, thereby determining multiple task feature atoms and storing them in the task feature atom database. For example, the processor can split the construction task to the smallest atomic level according to the task item, thereby determining multiple task item atoms; split the construction task to the smallest atomic level according to the engineering category, thereby determining multiple engineering category atoms, and so on. For more descriptions on splitting, please refer to the above.
[0089] In some embodiments, the processor may obtain multiple historical task orders, and extract at least one construction feature point from each of the multiple historical task orders; determine at least one corresponding task feature atom based on the multiple construction feature points to construct a task feature atom library.
[0090] Historical task list refers to the task list assigned historically. Task list refers to the task list assigned to the construction party for construction.
[0091] In some embodiments, the processor may obtain the historical task list according to the user's input. For example, the user may upload the historical task list of the historical construction project through the terminal device.
[0092] In some embodiments, the processor can read the historical task list of the historical construction project from the storage device. The storage device can be a storage device of the construction inspection sheet generation system 100, or an external storage device that does not belong to the construction inspection sheet generation system 100, such as a hard disk, an optical disk, etc.
[0093] In some embodiments, the processor can read the historical task list of the historical construction project through an interface, and the interface includes but is not limited to a program interface, a data interface, a transmission interface, etc. In some embodiments, when the system 100 for generating the construction inspection form is working, the construction plan of the construction project can be automatically extracted from the interface. In some embodiments, the system 100 for generating the construction inspection form can be called by other external devices or systems, and the above data is passed to the system 100 for generating the construction inspection form when the call is made. In some embodiments, the construction plan of the construction project can also be obtained by any method well known to those skilled in the art, and this specification does not limit this.
[0094] A construction feature point is a node used to classify task feature atoms contained in a task feature atom library. For example, a task feature atom library may include one or more types of task feature atoms, and task feature atoms of the same type may be classified under a construction feature point. This is equivalent to a construction feature point being the highest-level general node of a class of task feature atoms.
[0095] As an example only, multiple task item atoms contained in the task feature atom library can be classified into the feature points corresponding to the task items. Task item atoms at different levels can be classified into the feature points corresponding to the task items in turn to obtain a tree structure. Among them, the total node at the highest level of the tree structure is the feature point corresponding to the task item, the first-level task item atom is the child node of the total node, the second-level task item atom is the child node of the first-level task item atom, and so on.
[0096] In some embodiments, the construction feature points include at least one of task item feature points, project category feature points, construction site feature points, construction cost feature points, and construction material feature points.
[0097] The task item feature point refers to the total node corresponding to the task item atoms at each level when the task list is split according to the level of the task item. In some embodiments, the processor can split the task list level by level to the smallest atomic level according to the task item feature point to obtain task item atoms at multiple levels. Figure 3As shown, the task item feature point may be a top-level master node including multiple levels of sub-nodes. A sub-node of one level corresponds to a task item atom of one level.
[0098] In some embodiments, the feature classification corresponding to the task item feature point is a task item. Accordingly, the feature classifications of the multiple levels of task item atoms contained below the task item feature point are all task items, and different task item atoms may correspond to different task items. For more information about the multiple levels of task item atoms, see the related description above.
[0099] The engineering category feature point refers to the total node corresponding to the engineering category atoms at each level when the task order is split according to the level of the engineering category. In some embodiments, the processor can split the task order level by level to the smallest atomic level according to the engineering category feature point to obtain engineering category atoms at multiple levels. Figure 3 As shown, the engineering category feature point may be a top-level master node including multiple levels of sub-nodes. A sub-node of one level corresponds to an engineering category atom of one level.
[0100] In some embodiments, the feature classification corresponding to the engineering category feature point is the engineering category. Accordingly, the feature classifications of the multiple levels of engineering category atoms contained under the engineering category feature point are all engineering categories, and different engineering category atoms may correspond to different engineering categories. For more information about the multiple levels of engineering category atoms, please refer to the relevant description above.
[0101] The construction site feature point refers to the total node corresponding to the construction site atoms at each level when the task list is split according to the level of the construction site. In some embodiments, the processor can split the task list level by level to the smallest atomic level according to the construction site feature point to obtain construction site atoms at multiple levels. Figure 3 As shown, the construction site feature point can be a top-level general node including multiple levels of sub-nodes. A sub-node of one level corresponds to a construction site atom of one level.
[0102] In some embodiments, the feature classification corresponding to the construction site feature point is the construction site. Correspondingly, the feature classifications of the multiple levels of construction site atoms contained under the construction site feature point are all construction sites, and different construction site atoms may correspond to different construction sites. For more information about the multiple levels of construction site atoms, please refer to the relevant description above.
[0103] The construction cost feature point refers to the total node corresponding to the construction cost atoms at each level when the task order is split according to the level of construction cost. In some embodiments, the processor can split the task order level by level to the smallest atomic level according to the construction cost feature point to obtain construction cost atoms at multiple levels. Figure 3As shown, the construction cost feature point may be a top-level master node including multiple levels of sub-nodes. A sub-node of one level corresponds to a construction cost atom of one level.
[0104] In some embodiments, the feature classification corresponding to the construction cost feature point is construction cost. Accordingly, the feature classifications of the multiple levels of construction cost atoms contained under the construction cost feature point are all construction costs, and different construction cost atoms may correspond to different construction costs. For more information about the multiple levels of construction cost atoms, please refer to the relevant description above.
[0105] The construction material feature point refers to the total node corresponding to the construction material atoms at each level when the task list is split according to the level of the construction material. In some embodiments, the processor can split the task list level by level to the smallest atomic level according to the construction material feature point to obtain construction material atoms at multiple levels. Figure 3 As shown, the construction material feature point may be a top-level master node including multiple levels of sub-nodes. A sub-node of one level corresponds to a construction material atom of one level.
[0106] In some embodiments, the feature classification corresponding to the construction material feature point is construction material. Accordingly, the feature classifications of the multiple levels of construction material atoms contained under the construction material feature point are all construction materials, and different construction material atoms may correspond to different construction materials. For more information about the multiple levels of construction material atoms, please refer to the relevant description above.
[0107] In some embodiments, the construction feature points also include at least one of construction stage feature points and construction progress feature points.
[0108] The construction phase feature point refers to the total node corresponding to the construction phase atoms at each level when the construction project is split according to the level of the construction phase. In some embodiments, the processor can split the task order level by level to the smallest atomic level according to the construction phase feature point to obtain multiple levels of construction phase atoms. Figure 3 As shown, the construction stage feature point can be a top-level master node including multiple levels of sub-nodes. A sub-node of one level corresponds to a construction stage atom of one level.
[0109] In some embodiments, the feature classification corresponding to the construction stage feature point is the construction stage. Accordingly, the feature classifications of the multiple levels of construction stage atoms contained under the construction stage feature point are all construction stages, and different construction stage atoms may correspond to different construction stages. For more information about the multiple levels of construction stage atoms, please refer to the relevant description above.
[0110] The construction progress feature point refers to the total node corresponding to the construction progress atoms at each level when the task list is split according to the level of the construction progress of the task item. In some embodiments, the processor can split the task list level by level to the smallest atomic level according to the construction progress feature point to obtain construction progress atoms at multiple levels. Figure 3 As shown, the construction progress feature point may be a top-level master node including multiple levels of sub-nodes. A sub-node of one level corresponds to a construction progress atom of one level.
[0111] In some embodiments, the feature classification corresponding to the construction progress feature point is construction progress. Accordingly, the feature classifications of the multiple levels of construction progress atoms contained under the construction progress feature point are all construction progress, and different construction progress atoms may correspond to different construction progresses. For more information about the multiple levels of construction progress atoms, please refer to the relevant description above.
[0112] In some embodiments, the processor may extract at least one construction feature point from each of the plurality of historical task orders based on the content information in the historical task order. For example, the corresponding construction feature point is determined according to the content information contained in the historical task order. As an example only, if the historical task order contains the engineering category of the construction project, it may be determined that the construction feature point includes the engineering category feature point; if the historical task order contains multiple task items, it may be determined that the construction feature point includes the task item feature point, and so on.
[0113] In some embodiments, the processor may determine at least one corresponding task feature atom based on at least one construction feature point to construct a task feature atom library. For example, the processor may split the current task list based on at least one construction feature point, determine the task feature atom corresponding to each construction feature point, and then construct a task feature atom library.
[0114] In some embodiments, the processor may further bind at least one task feature atom with corresponding relevant production information and store the resultant information in a task feature atom library.
[0115] In some embodiments of the present specification, by splitting the task order into task feature atoms, the task information can be deconstructed into highly flexible and easy-to-manage atomic-level data, which helps to flexibly assemble task feature atoms according to different working conditions to obtain task orders under different working conditions.
[0116] In some embodiments, the processor may further encode each task feature atom in the task feature atom library. The encoding may be performed based on a preset encoding rule. In some embodiments, the preset encoding rule may include provisions for the length, character set, encoding structure, etc. of the encoding to ensure the uniqueness and readability of the encoding.
[0117] For example, for the engineering category atom, the preset coding rule may be to encode "housing construction project" as "FWJZ". For the construction site atom, the preset coding rule may be to encode "basement" as "DSX", "main structure" as "ZTJG", "first floor" as "F01", "column" as "Z", "wall" as "Q", "beam" as "L", etc. For the task item atom, the preset coding rule may be to encode "task item for masonry wall" as "QZQT". For the construction stage atom, the preset coding rule may be to encode "foundation engineering stage" as "JCGC", "main engineering stage" as "ZTGC", etc.
[0118] In some embodiments, the processor may encode the task feature atoms based on the correspondence between different task feature atoms and different codes. The correspondence between different task feature atoms and different codes may be preset by the system or manually.
[0119] In some embodiments, the task feature atom library may include multiple task feature atoms and their corresponding codes.
[0120] In some embodiments, the codes of different construction feature points and their corresponding multiple levels of task feature atoms in the task feature atom library can be stored separately. For example, the codes of task item feature points and their corresponding multiple levels of task item atoms can be combined into a coding table and stored independently. For another example, the codes of engineering category feature points and their corresponding multiple levels of engineering category atoms can be combined into a coding table and stored independently, and so on. The structure of the coding table can be a tree structure.
[0121] In some embodiments, the code tables corresponding to different construction feature points can be superimposed. For example, the code "FWJZ" of "housing construction project", the code "DSX" of "basement", and the code "Z" of "pillar" can be superimposed to obtain the code "FWJZ-DSX-Z".
[0122] In some embodiments of the present specification, the information contained in the task list can be converted into a computer-readable form based on coding technology, and assembled quickly and accurately by a computer, thereby improving the efficiency of searching and assembling data and reducing the time and labor costs of manual recording and sorting of data.
[0123] The patrol feature atom library is a database used to store patrol feature atoms.
[0124] Inspection feature atoms refer to the data obtained by splitting the contents contained in the inspection list and inspection materials level by level. The inspection list is a list of multiple inspection items for the inspection of the construction project. For example, the inspection items may include construction process inspection and safety measures inspection. Different inspection items may correspond to different inspection standards. Inspection materials include specifications, atlases, construction manuals and other materials corresponding to the inspection items or inspection objects. Specifications may include requirements for compliance construction of inspection items or inspection objects. For example, concrete construction specifications, etc. Atlases may include image data when the inspection items or inspection objects meet the specifications. Construction manuals may include construction processes and requirements for inspection items or inspection objects.
[0125] Construction process inspection refers to the inspection of the construction process. For example, the process of earth excavation includes: determining the order and slope of excavation, cutting the contour line of the trench along the gray line, layered excavation, trimming the trench edge, and cleaning the bottom. The inspection of this process includes: inspecting whether the order of excavation complies with regulations, inspecting whether the slope of excavation complies with regulations, inspecting whether the contour line of the trench complies with regulations, etc.
[0126] Safety measures inspection refers to the inspection of construction safety measures. For example, safety measures may include the installation of protection, insurance, signal and other devices, the structure of the construction device meets the requirements, the operation status of the construction device meets the requirements, and the installation of personal protective equipment (for example, wearing a safety helmet, etc.). The content of the safety measures inspection includes: checking whether the installation of protection, insurance, signal and other devices, checking whether the structure of the construction device meets the requirements, checking whether the operation status of the construction device meets the requirements, and checking whether personal protective equipment is installed.
[0127] Inspection standards can be used to measure whether the inspection results of the inspection items are compliant. When the inspection items meet the inspection standards, the inspection results of the inspection items can be determined to be compliant; otherwise, the inspection results of the inspection items are determined to be non-compliant. For example, when the quality of the construction process meets the set quality requirements, the construction process inspection meets the inspection standards, and the inspection results of the construction process inspection are compliant.
[0128] For inspection items, different inspection objects or inspection contents in the inspection items may correspond to different inspection standards. For example, for the inspection item of safety measures inspection, the inspection standards for the two inspection contents of "determining whether protection, insurance, signal and other devices are equipped" and "whether personal protective equipment is equipped" are different.
[0129] In some embodiments, the inspection standards corresponding to different inspection items and the inspection standards corresponding to different inspection contents can be preset based on prior knowledge or historical data.
[0130] In some embodiments, the inspection feature atom may include at least one of a construction process atom, a safety measure atom, and an inspection standard atom.
[0131] The construction process atom refers to the data obtained by dividing the contents of the construction process inspection contained in the inspection list and the inspection data step by step. In some embodiments, the construction process can be divided step by step into multiple sub-construction processes, and a construction process inspection can be performed for each sub-construction process.
[0132] In some embodiments, Figure 4 As shown, by dividing the construction process level by level, multiple levels of construction process atoms can be obtained. For example, the upper-level construction process atom can be further divided into one or more lower-level construction process atoms. When the construction process is divided into the smallest atomic level, the final-level construction process atom can be obtained. The final-level construction process atom refers to the construction process at the lowest and most detailed level after the construction process is decomposed. The final-level construction process atom cannot be divided any further.
[0133] Taking the inspection sheet of a construction project of a housing construction project as an example, the first-level construction process atom may include the "process flow of earth excavation", among which the process flow of "cutting out the groove edge contour line along the gray line" cannot be split any further, and the "cutting out the groove edge contour line along the gray line" can be regarded as the last-level construction process atom.
[0134] In some embodiments, the relevant inspection information of the construction process atom may include specifications, drawings, construction manuals, inspection contents (for example, whether the process flow is compliant, etc.), and inspection methods (for example, comparing the actual process with the standard process, etc.) corresponding to the inspection objects of the construction process inspection (for example, sub-construction processes at each level).
[0135] In some embodiments, the inspection information related to the construction process atom can be stored after being bound to the name or code of the construction process atom, and the inspection information related to the construction process atom can be obtained by searching the name or code of the construction process atom. The name of the construction process atom can be preset. For more information about the code, see the following description.
[0136] The safety measure atom refers to the data obtained by dividing the contents of the safety measure inspection contained in the inspection list and the inspection data into different levels. In some embodiments, the safety measure can be divided into multiple sub-safety measures, and the safety measure inspection can be performed for each sub-safety measure.
[0137] In some embodiments, Figure 4As shown, by dividing the security measures level by level, multiple levels of security measure atoms can be obtained. For example, the upper-level security measure atom can be further divided into one or more lower-level security measure atoms. When the security measures are divided into the smallest atomic level, the final-level security measure atom can be obtained. The final-level security measure atom refers to the security measure at the lowest and most detailed level after the security measures are decomposed. The final-level security measure atom cannot be divided any further.
[0138] In some embodiments, the relevant inspection content of the safety measure atom may include specifications, drawings, construction manuals, inspection content (for example, whether the safety measures are compliant, etc.), and inspection methods (for example, comparing actual safety measures with standard safety measures, etc.) corresponding to the inspection objects of the safety measures inspection (for example, sub-safety measures at each level).
[0139] In some embodiments, the inspection information related to the security measure atom can be stored after being bound to the name or code of the security measure atom, and the inspection information related to the security measure atom can be obtained by searching the name or code of the security measure atom. The name of the security measure atom can be preset. For more information about the code, see the following description.
[0140] The inspection criterion atom refers to data containing relevant information of the inspection criterion. In some embodiments, the inspection criterion can be divided into multiple sub-inspection criteria step by step.
[0141] In some embodiments, Figure 4 As shown, by dividing the inspection standard level by level, multiple levels of inspection standard atoms can be obtained. For example, the upper inspection standard atom can be further divided into one or more lower inspection standard atoms. When the inspection standard is divided into the smallest atomic level, the final inspection standard atom can be obtained. The final inspection standard atom refers to the inspection standard at the lowest and most detailed level after the inspection standard is decomposed. The final inspection standard atom cannot be divided any further.
[0142] In some embodiments, the inspection information related to the inspection standard atom may include the inspection object or inspection content corresponding to the inspection standard. In some embodiments, the inspection information related to the inspection standard atom may be stored after being bound to the name or code of the inspection standard atom, and the inspection information related to the inspection standard atom may be obtained by retrieving the name or code of the inspection standard atom. The name of the inspection standard atom may be preset. For more information about the coding, see the following description.
[0143] In some embodiments, the processor may decompose the construction process, safety measures, and inspection standards contained in the inspection list step by step to the smallest atomic level based on prior knowledge, thereby determining multiple inspection feature atoms and storing them in the inspection feature atom database.
[0144] In some embodiments, the processor may obtain multiple historical inspection lists, and extract at least one inspection feature point from each of the multiple historical inspection lists; determine at least one corresponding inspection feature atom based on the at least one inspection feature point to construct an inspection feature atom library.
[0145] A patrol feature point is a node used to classify patrol feature atoms contained in a patrol feature atom library. For example, a patrol feature atom library may include one or more types of patrol feature atoms, and patrol feature atoms of the same type may be classified under a patrol feature point. This is equivalent to a patrol feature point being the highest-level general node of a type of patrol feature atoms.
[0146] Just as an example, the multiple construction process atoms contained in the inspection feature atom library can be classified into the feature points corresponding to the construction process. Construction process atoms at different levels can be classified into the feature points corresponding to the construction process in turn to obtain a tree structure. Among them, the total node of the highest level of the tree structure is the feature point corresponding to the construction process, the first-level construction process atom is the child node of the total node, the second-level construction process atom is the child node of the first-level task item atom, and so on.
[0147] In some embodiments, the inspection feature points may include at least one of construction process feature points, safety measures feature points, and inspection standard feature points.
[0148] The construction process feature point refers to the total node corresponding to the construction process atoms at each level after the inspection sheet is split according to the level of the construction process. In some embodiments, the processor can split the inspection sheet level by level to the smallest atomic level according to the construction process feature point to obtain construction process atoms at multiple levels. Figure 4 As shown, the construction process feature point can be a total node of the highest level including multiple levels of sub-nodes. A sub-node of one level corresponds to a construction process atom of one level. For more description of construction process atoms of multiple levels, please refer to the relevant description above.
[0149] The safety measure characteristic point refers to the total node corresponding to the safety measure atoms at each level when the inspection list is split according to the level of the safety measure. In some embodiments, the processor can split the inspection list level by level to the smallest atomic level according to the safety measure characteristic point to obtain safety measure atoms at multiple levels. Figure 4 As shown, the security measure feature point can be a total node of the highest level including multiple levels of sub-nodes. A sub-node of one level corresponds to a security measure atom of one level. For more information about security measure atoms of multiple levels, please refer to the relevant description above.
[0150] Inspection standard feature points refer to the total nodes corresponding to inspection standard atoms at each level after the inspection list is split according to the level of the inspection standard. In some embodiments, the processor can split the inspection list level by level to the smallest atomic level according to the inspection standard feature points to obtain inspection standard atoms at multiple levels. Figure 4 As shown, the inspection standard feature point can be a total node of the highest level including multiple levels of sub-nodes. A sub-node of one level corresponds to an inspection standard atom of one level. For more description of multiple levels of inspection standard atoms, please refer to the relevant description above.
[0151] In some embodiments, the processor may determine at least one corresponding inspection feature atom based on at least one inspection feature point to construct an inspection feature atom library. For example, the processor may split the current inspection list based on at least one inspection feature point, determine the inspection feature atom corresponding to each inspection feature point, and then construct the inspection feature atom library.
[0152] In some embodiments, the processor may further bind at least one inspection feature atom with corresponding related inspection information and store the result in the inspection feature atom library.
[0153] In some embodiments of the present specification, by splitting the inspection list into inspection feature atoms, the inspection information can be deconstructed into highly flexible and easy-to-manage atomic-level data, which helps to flexibly assemble the inspection feature atoms according to different working conditions to obtain inspection lists under different working conditions.
[0154] In some embodiments, the processor may further encode each patrol feature atom in the patrol feature atom library. The manner of encoding the patrol feature atom is similar to the manner of encoding the task feature atom, and will not be described in detail here.
[0155] In some embodiments, the patrol feature atom library may include multiple patrol feature atoms and their corresponding codes.
[0156] In some embodiments, the codes of different inspection feature points and their corresponding multiple levels of inspection feature atoms in the inspection feature atom library can be stored separately. For example, the codes of construction process feature points and their corresponding multiple levels of construction process atoms can be combined into a coding table and stored independently. For another example, the codes of safety measure feature points and their corresponding multiple levels of safety measure atoms can be combined into a coding table and stored independently, and so on. The structure of the coding table can be a tree structure.
[0157] In some embodiments, the coding tables corresponding to different inspection feature points can be superimposed.
[0158] In some embodiments of the present specification, the information contained in the inspection sheet can be converted into a computer-readable form based on coding technology, and assembled quickly and accurately by a computer, thereby improving the efficiency of searching and assembling information and reducing the time and labor costs of manual recording and sorting of data.
[0159] S220, establishing an association relationship between the task feature atoms in the task feature atom library and the inspection feature atoms in the inspection feature atom library.
[0160] In some embodiments, for each task feature atom included in the task feature atom library, the processor may match at least one patrol feature atom in the patrol feature atom library and establish an association relationship between the task feature atom and the at least one patrol feature atom.
[0161] In some embodiments, the association relationship between the task feature atom in the task feature atom library and the inspection feature atom in the inspection feature atom library can be manually established. For example, for the task item atom of building a concrete column, the association relationship between it and the inspection standard atom of the concrete construction specification can be manually established.
[0162] In some embodiments, the processor can establish an association relationship between the task feature atom in the task feature atom library and the inspection feature atom in the inspection feature atom library by using a preset matching model. Figure 5 and its related description.
[0163] In some embodiments, the processor may also establish association information between the code corresponding to the task feature atom and the code corresponding to the patrol feature atom.
[0164] In some embodiments, after establishing an association relationship between task feature atoms and inspection feature atoms, the correspondence between the feature classification corresponding to each task characteristic atom in the task feature atom library (for example, task item, project category, construction stage, construction site, construction progress, construction cost or construction material) and the inspection items and inspection standards corresponding to the inspection feature atom can be determined. For example, after an engineering category atom is associated with an inspection feature atom, the correspondence between the engineering category corresponding to the engineering category atom and the inspection items and inspection standards can be determined. For another example, after an assignment item atom is associated with an inspection feature atom, the correspondence between the task item corresponding to the task item atom and the inspection items and inspection standards can be determined.
[0165] S230, obtaining a task list, and determining the target construction site to be inspected and the target task feature atoms based on the task list.
[0166] A task list is a list of tasks for building or engineering construction. A task list can contain multiple task items. Taking the task list of a construction project of a house building as an example, it can include tasks such as building foundations, building main structures (e.g., walls, columns, ceilings, etc.), building elevators, building drainage structures, building electrical structures, and decoration.
[0167] In some embodiments, the processor may obtain the task list according to the user's input. For example, the user may upload the task list of the current construction project through the terminal device.
[0168] The target construction site refers to the construction site to be inspected. For example, when the construction site to be inspected is a foundation, the foundation can be determined as the target construction site.
[0169] The target task feature atom refers to the task feature atom to be inspected.
[0170] In some embodiments, the target task feature atom may include one or any combination of a target task item atom, a target engineering category atom, a target construction progress atom, a target construction cost atom, and a target construction material atom.
[0171] The target task item atom may be a task item atom of a task item corresponding to the target construction site. The task item corresponding to the target construction site may include at least one, and the target task item atom may include at least one.
[0172] The target engineering category atom may be an engineering category atom corresponding to the engineering category to which the target construction site belongs.
[0173] The target construction progress atom may be a construction progress atom corresponding to the construction progress management mode corresponding to the target task item. The task item corresponding to the target construction site may include at least one, and the target construction progress atom may include at least one.
[0174] The target construction cost atom may be a construction cost atom corresponding to the construction cost corresponding to the target task item. The task item corresponding to the target construction location may include at least one, and the target construction cost atom may include at least one.
[0175] The target construction material atom may be a construction material atom corresponding to the construction material corresponding to the target task item. The task item corresponding to the target construction site may include at least one, and the target construction material atom may include at least one.
[0176] In some embodiments, the processor can extract the target construction site to be inspected from the task list through an extraction algorithm. Exemplary extraction algorithms include, but are not limited to, traditional keyword extraction algorithms such as word frequency-based extraction algorithms, text feature-based extraction algorithms, and linguistics-based extraction algorithms, and convolutional neural networks (CNN) and recurrent neural networks (RNN) applied to keyword extraction tasks.
[0177] In some embodiments, the processor may traverse all the information contained in the task list, and match all the information contained in the task list with the feature classification corresponding to the task feature atom in the task feature atom library to obtain the target task feature atom. The processor may determine the construction site corresponding to the target construction site atom as the target construction site. For example, when the task list only involves task items and construction sites, the task items and construction sites may be matched in the task feature atom library respectively to determine the target task item atom and the target construction site atom.
[0178] S240, based on the target task feature atom and the association relationship, determine the target inspection feature atom corresponding to the target task feature atom.
[0179] The target inspection feature atom refers to the inspection feature atom determined in the inspection feature atom library based on the target task feature atom. There is an association relationship between the target inspection feature atom and the target task feature atom.
[0180] In some embodiments, the processor may determine, based on the target task feature atom and the association relationship, a patrol feature atom in the patrol feature atom library that has an association relationship with the target task feature atom as the target patrol feature atom.
[0181] S250, determining target inspection personnel and target inspection frequency based on the target construction site.
[0182] The target inspection personnel refer to personnel related to the inspection. In some embodiments, the target inspection personnel may include personnel who perform inspections on the target construction site. In some embodiments, the target inspection personnel may also include inspected personnel. The inspected personnel may include personnel who perform production and construction tasks at the target construction site.
[0183] In some embodiments, the target inspection frequency may include the frequency of inspecting the target construction site. In some embodiments, the target inspection frequency may also include the frequency of inspecting the inspected personnel.
[0184] In some embodiments, the processor may determine the target inspection personnel and the target inspection frequency based on the target construction site by querying a preset comparison table.
[0185] In some embodiments, the preset comparison table includes a plurality of different reference construction sites and reference inspectors and reference inspection frequencies corresponding to each reference construction site. In some embodiments, the preset comparison table can be constructed based on prior knowledge or historical data. Exemplarily, the processor can search the preset comparison table based on the target construction site, determine the reference construction site similar or close to the target construction site in the preset comparison table, and then determine the reference inspector and reference inspection frequency corresponding to the reference construction site as the target inspector and target inspection frequency corresponding to the target construction site.
[0186] In some embodiments, the processor may determine the inspection type based on the target construction site; based on the inspection type, determine the target inspection personnel and the target inspection frequency.
[0187] The inspection type refers to the type of construction inspection. In some embodiments, the inspection type may include regular inspection and special inspection.
[0188] Routine inspections refer to regular inspections of the construction site at a specified frequency. Comprehensive inspections include inspections of personnel, equipment, materials, construction technology, safety, etc.
[0189] Special inspection refers to special inspections of a specific area or project at the construction site. For example, special inspections are conducted on scaffolding, temporary power facilities, etc. For another example, special inspections are required to strengthen monitoring and management of construction areas and links with major safety hazards or high risks.
[0190] In some embodiments, the processor may determine the inspection type corresponding to the target construction location based on the target construction location, the corresponding relationship between the construction location and the inspection type. In some embodiments, the corresponding relationship between the construction location and the inspection type may be preset based on prior knowledge or historical data.
[0191] In some embodiments, the processor may obtain acceptance information of similar construction sites outside the task list based on the target construction site; in response to the acceptance information satisfying the first preset condition, determine the inspection type as a regular inspection; in response to the acceptance information not satisfying the first preset condition, determine the inspection type as a special inspection. In this embodiment, the special inspection may include inspecting the construction quality of the target construction site.
[0192] In some embodiments, the same type of construction site may be a construction site in the same construction project that is in the same type as the target construction site and in an accepted task order other than the current task order.
[0193] All task items included in the accepted task list have been accepted and completed.
[0194] Acceptance information refers to information related to the completion status of the construction site.
[0195] In some embodiments, the acceptance information of the same type of construction sites may include the actual progress of the same type of construction sites (eg, accepted or not accepted, etc.), acceptance quality, etc. When the same type of construction sites have been accepted, it means that the same type of construction sites have been completed.
[0196] The acceptance quality refers to the acceptance result obtained by quality acceptance of the construction process and construction results of multiple task items corresponding to the construction site. In some embodiments, when the construction process and construction results of the construction site meet the qualified standards, the acceptance quality can be determined to be qualified. When the construction process and / or construction results of the construction site do not meet the qualified standards, the acceptance quality can be determined to be unqualified. Among them, the qualified standards can be preset by the acceptance personnel or the system.
[0197] In some embodiments, the construction process and construction results of the multiple task items corresponding to the construction site meet the qualified standards, including: the quality of the inspection items in the construction process and the construction results is qualified, the inspection items have complete construction operation basis and quality inspection records, and the visual quality meets the requirements. The visual quality can be determined by the acceptance personnel based on the visual content.
[0198] The first preset condition is a judgment condition related to the acceptance information.
[0199] In some embodiments, the first preset condition may include that the proportion of task items with unqualified acceptance quality is less than a first proportion threshold. For example, the first proportion threshold may be 2%, 4%, etc. The proportion of task items with unqualified acceptance quality may be the ratio between the number of task items with unqualified acceptance quality and the total number of task items corresponding to the same construction site.
[0200] In some embodiments, the first proportion threshold and the first preset condition may be preset by the system or manually.
[0201] In some embodiments, the processor may also obtain construction safety information of similar construction sites outside the task list based on the target construction site; in response to the construction safety information satisfying the second preset condition, determine the inspection type as a regular inspection; in response to the construction safety information not satisfying the second preset condition, determine the inspection type as a special inspection. In this embodiment, the special inspection may include inspecting the construction quality of the target construction site.
[0202] Construction safety information refers to information related to construction safety of multiple task items corresponding to the same type of construction sites. In some embodiments, the construction safety information may include whether a safety accident has occurred and related information about the safety accident (e.g., the occurrence, type, and number of occurrences of the safety accident). In some embodiments, the construction safety information may also include related information about penalties for unsafe operations (e.g., penalty content, number of penalties, etc.).
[0203] The second preset condition is a judgment condition related to construction safety information.
[0204] In some embodiments, the second preset condition may include no safety accident. When no safety accident occurs in multiple task items corresponding to the same construction site, the inspection type may be determined to be a regular inspection; otherwise, the inspection type may be determined to be a special inspection.
[0205] In some embodiments, the second preset condition may include that the proportion of task items with safety accidents is less than a second proportion threshold. For example, the second proportion threshold may be 2%, 3%, etc. When the proportion of task items with safety accidents in multiple task items corresponding to the same type of construction site is less than the second proportion threshold, the inspection type may be determined to be a regular inspection; otherwise, the inspection type may be determined to be a special inspection. Among them, the proportion of task items with safety accidents may be the ratio between the number of task items with safety accidents and the total number of task items corresponding to the same type of construction site.
[0206] In some embodiments, the second proportion threshold and the second preset condition may be preset by the system or manually.
[0207] In some embodiments, the processor can determine the target patrol personnel and target patrol frequency corresponding to the patrol type based on the patrol type and the patrol table. In some embodiments, the patrol table includes multiple different reference patrol types and reference patrol personnel and reference patrol frequencies corresponding to each reference patrol type. In some embodiments, the patrol table can be constructed based on prior knowledge or historical data. Exemplarily, the processor can search in the patrol table based on the patrol type, determine in the patrol table a reference patrol type that is similar or close to the patrol type, and then determine the reference patrol personnel and reference patrol frequency corresponding to the reference patrol type as the target patrol personnel and target patrol frequency corresponding to the current patrol type.
[0208] In some embodiments, the processor can determine a reference inspection frequency in response to the inspection type being a routine inspection by querying the inspection orders of the task orders corresponding to the same type of construction sites, and determine a target inspection frequency corresponding to the routine inspection based on the reference inspection frequency; and query the management personnel of the target construction site and determine the management personnel as the target inspection personnel corresponding to the routine inspection.
[0209] The reference patrol frequency refers to a patrol frequency to be determined as a target patrol frequency. The reference patrol frequency may include at least one.
[0210] In some embodiments, the processor may query the inspection list of the task order corresponding to the same construction site, and determine at least one historical inspection frequency for inspecting the same construction site in the inspection list as at least one reference inspection frequency.
[0211] In some embodiments, the processor may determine the target patrol frequency corresponding to the regular patrol based on the reference patrol frequency in various ways. For example, the processor may determine the median, mode or mean of at least one reference patrol frequency as the target patrol frequency corresponding to the regular patrol.
[0212] Management personnel are those who manage the production and construction process of the construction site.
[0213] In some embodiments, the processor may query the management personnel of the target construction site from the management manual. In some embodiments, the management manual may include the correspondence between different construction sites and different management personnel. The management manual may be pre-entered by the system or manually and stored in a storage device.
[0214] In some embodiments, the processor can query the construction cycle of the target construction site in response to the inspection type being a special inspection, and determine the target inspection frequency corresponding to the special inspection based on the construction cycle; and query the acceptance personnel of the target construction site, and determine the acceptance personnel as the target inspection personnel corresponding to the special inspection.
[0215] The construction period may include a planned duration of at least one task item corresponding to the construction site.
[0216] In some embodiments, the planned duration of each task item may be input and determined in advance by the construction party or the management party. In some embodiments, the processor may query at least one task item corresponding to the target construction site, query and obtain the planned duration of the at least one task item as the construction period of the target construction site.
[0217] In some embodiments, the processor can determine the target inspection frequency corresponding to the special inspection based on the construction cycle in a variety of ways. For example, the processor can set a special inspection in the planned construction period of each task item corresponding to the target construction site to obtain the number of special inspections in the entire construction period. For another example, the processor can determine the ratio of the number of planned construction periods included in the construction cycle to the time length of the construction cycle as the target inspection frequency corresponding to the special inspection. Among them, the time length of the construction cycle can be determined based on the start time of the first planned construction period and the end time of the last planned construction period.
[0218] Acceptance personnel refers to the personnel who accept the production and construction results of the construction site.
[0219] In some embodiments, the processor may query the acceptance personnel of the target construction site from the acceptance manual. In some embodiments, the acceptance manual may include the correspondence between different construction sites and different acceptance personnel. The acceptance manual may be pre-entered by the system or manually and stored in a storage device.
[0220] In some embodiments of this specification, when the inspection type is a regular inspection, the target inspection frequency is determined according to the inspection list corresponding to the same type of construction site, which helps to accurately and efficiently determine the inspection frequency of the current regular inspection based on the historical construction and historical inspection conditions. When the inspection type is a special inspection, the target inspection frequency is determined according to the construction period of the target construction site, which helps to conduct a special inspection within the planned construction period of each task item corresponding to the target construction site.
[0221] Compared with the acceptance personnel, the management personnel have a better understanding of the execution process of the task items, while the acceptance personnel are more professional in the assessment of the construction quality. In some embodiments of this specification, when the inspection type is a regular inspection, the management personnel of the target construction site are determined as the target inspection personnel, which helps to use the management personnel who are more familiar with the execution process of the task items to conduct inspections in the case of regular inspections, so as to improve the inspection efficiency. When the inspection type is a special inspection, the acceptance personnel of the target construction site are determined as the target inspection personnel, which helps to use the acceptance personnel who are more professional in the assessment of construction quality to conduct inspections in the case of special inspections, so as to improve the accuracy and professionalism of the inspection.
[0222] In some embodiments, the processor can determine the inspection intensity based on construction safety information in response to the inspection type being a special inspection, and determine the target inspection frequency corresponding to the special inspection based on the inspection intensity; and query the management personnel of the target construction site and determine the management personnel as the target inspection personnel corresponding to the special inspection.
[0223] Inspection intensity refers to the intensity of inspections on target construction sites. The higher the inspection intensity, the higher the frequency and more detailed the inspections on target construction sites.
[0224] In some embodiments, the processor can determine the proportion of task items with safety accidents based on the construction safety information of similar construction sites, and determine the patrol intensity based on the proportion of task items with safety accidents. In some embodiments, the corresponding relationship between the proportion of task items with safety accidents and the patrol intensity can be determined based on prior knowledge or historical data. The processor can determine the patrol intensity based on the proportion of task items with safety accidents and the aforementioned corresponding relationship.
[0225] In some embodiments, the processor may determine the target inspection frequency corresponding to the special inspection based on the inspection intensity and the corresponding relationship between the inspection intensity and the inspection frequency. In some embodiments, the corresponding relationship between the inspection intensity and the inspection frequency may be determined based on prior knowledge or historical data.
[0226] In some embodiments of this specification, when the inspection type is a special inspection, the inspection intensity is determined according to the construction safety information, and then the target inspection frequency is determined. The impact of safety accidents in task items of similar construction sites on the inspection frequency of special inspections can be considered to determine a more accurate target inspection frequency. At the same time, when the construction safety information meets the second preset condition, the management personnel of the target construction site are determined as target inspection personnel, which helps to use the management personnel's understanding of the execution process of the task items to conduct more detailed inspections of the target construction site, so as to improve the efficiency and accuracy of the inspection.
[0227] In some embodiments, the processor may determine a special inspection task item based on a target inspection frequency and a target construction site in response to the inspection type being a special inspection, and configure inspection standard atoms and construction process atoms for the special inspection based on the special inspection task type.
[0228] Special inspection task items refer to the task items when conducting special inspections.
[0229] In some embodiments, the processor may match similar historical inspection frequencies and historical construction sites in historical inspection data based on the target inspection frequency and the target construction site, and determine the historical inspection tasks corresponding to the historical inspection frequencies and historical construction sites as special inspection task items.
[0230] In some embodiments, the processor can match task feature atoms in the task feature atom library based on special inspection task items, and determine corresponding inspection standard atoms and construction process atoms based on the association between task feature atoms and inspection feature atoms, and then configure the corresponding inspection standard atoms and construction process atoms for the special inspection.
[0231] In some embodiments of the present specification, based on the task items corresponding to special inspections, at least one type of inspection feature atom can be matched in the inspection feature atom library, and at least one type of matched construction process atom and inspection standard atom can be flexibly assembled with the task item atom to improve the efficiency of searching and assembling data and reduce the time and labor cost of manual recording and sorting of data.
[0232] In some embodiments, the processor may also, in response to the inspection type being a special inspection, obtain a special inspection task item corresponding to each special inspection item, and configure safety measure atoms for the special inspection according to the special inspection task item.
[0233] Special inspection projects refer to specific projects for special inspections. Special inspection projects can be determined through user input, data query and other methods.
[0234] In some embodiments, the processor can match task feature atoms in the task feature atom library based on special inspection task items, and determine the corresponding safety measure atoms based on the association between the task feature atoms and the inspection feature atoms, and then configure the corresponding safety measure atoms for the special inspection.
[0235] In some embodiments of the present specification, based on the task items corresponding to special inspections, at least one type of inspection feature atom can be matched in the inspection feature atom library, and the matched at least one type of safety measure atom can be flexibly assembled with the task item atom to improve the efficiency of searching and assembling data and reduce the time and labor cost of manual recording and sorting of data.
[0236] S260, generating a target inspection list based on the target inspection feature atoms, target inspection personnel and target inspection frequency.
[0237] The target inspection form refers to a record form related to construction inspection. In some embodiments, the target inspection form may include one or more elements of inspection type, target inspection location, target inspection frequency, target inspection personnel, inspection items (including construction technology or safety measures, etc.), inspection standards, inspection conclusions, inspection opinions, etc.
[0238] In some embodiments, the processor may generate a target inspection list based on target inspection feature atoms, target inspection personnel, and target inspection frequency in a variety of ways.
[0239] In some embodiments, the processor can obtain a patrol order template; generate an initial patrol order based on the target patrol feature atoms and the patrol order template; and in response to receiving a user's confirmation feedback on the initial patrol order, generate the target patrol order based on the initial patrol order, the target patrol personnel and the target patrol frequency.
[0240] The inspection list template is a template framework for generating an inspection list. In some embodiments, the inspection list template can be in various forms such as a table and a list.
[0241] In some embodiments, the inspection form template may include a header part and a body part. In some embodiments, the header part of the inspection form template may include column headings such as target inspection location, inspection type, target inspection frequency, target inspection personnel, inspection items, and inspection standards. The body part of the inspection form template may include the specific content of each column heading.
[0242] In some embodiments, the header part of the inspection form template may also include column headings such as inspection conclusion, inspection opinion, etc. The specific contents of these column headings may be filled in and determined by the user during the actual inspection process.
[0243] In some embodiments, the inspection list template may be determined by the system or by human pre-input.
[0244] The initial inspection list refers to the inspection list that is initially determined. The format, content, layout and other information of the initial inspection list are subject to user confirmation.
[0245] In some embodiments, the processor may fill in the information corresponding to the target inspection feature atom into the corresponding table body according to the corresponding column title to obtain an initial inspection list.
[0246] In some embodiments, the processor can also query and obtain relevant inspection information of the target inspection feature atom based on the target inspection feature atom; fill the relevant inspection information of the target inspection feature atom into the corresponding table body according to the corresponding column title to obtain the initial inspection form. For example, the processor can query and obtain the specifications, drawings, construction manuals, inspection contents (for example, whether the process flow is compliant, etc.), inspection methods (for example, comparing the actual process with the standard process, etc.) of the inspection objects (for example, sub-construction processes at each level) corresponding to the construction process atom, the specifications, drawings, construction manuals, inspection contents (for example, whether the safety measures are compliant, etc.), inspection methods (for example, comparing the actual safety measures with the standard safety measures, etc.) of the inspection objects (for example, sub-safety measures at each level) corresponding to the safety measures atom, and the inspection objects or inspection contents corresponding to the inspection standard atom.
[0247] Just as an example, for the formwork project of the 1st floor of unit 1, building 1 of a project in Chengdu, Sichuan Province, the processor can obtain relevant information such as Article 6.3 of the "Certain Formwork Construction Process", Article 3.2.4 of the "Certain Formwork Safety Measures", and Article 5.3.7 of the "Certain Formwork Inspection Standards", and flexibly assemble the corresponding inspection list based on this information.
[0248] In some embodiments, the confirmation feedback may include confirmation information of the format and content of the initial inspection list by the user (eg, the target inspection personnel). In some embodiments, the confirmation feedback may be determined by user input.
[0249] In some embodiments, in response to receiving confirmation feedback from the user on the initial inspection form, the processor may fill in the target inspection personnel and the target inspection frequency into the initial inspection form to generate a target inspection form.
[0250] In some embodiments, the user can modify the initial inspection list and determine whether the modification meets the corresponding specified requirements. For example, the user can modify at least one of the target inspection location, inspection type, target inspection frequency, target inspection personnel, inspection items, inspection standards, etc. in the initial inspection list. For example, a professional technician determines whether the modification meets the requirements or multiple users jointly determine whether the modification meets the requirements.
[0251] In some embodiments, the processor may receive correction feedback from the user, and correct at least one patrol feature atom in the patrol feature atom library based on the correction feedback.
[0252] In some embodiments, the user's correction feedback may include correction content made by the user (eg, the target inspector) to the initial inspection form, where the correction content complies with corresponding prescribed requirements.
[0253] In some embodiments, the processor may determine the inspection feature atom to be corrected based on the correction feedback, and correct the inspection feature atom to be corrected based on the correction feedback. For example, the correction feedback includes correction content for a certain inspection item (for example, a construction process inspection or a safety measures inspection), and / or correction content for a certain inspection item. The processor may determine the inspection feature atom to be corrected based on keyword extraction and other methods, and determine a new inspection feature atom based on the content of the correction feedback. The determination method is similar to the method of determining the inspection feature atom based on the historical task list in the previous text, and will not be repeated here.
[0254] In some embodiments of this specification, by assembling inspection feature atoms and filling the assembled inspection feature atoms and related inspection information into a pre-built inspection form template, an inspection form can be quickly and accurately generated, improving the efficiency of searching and assembling data, and reducing the time and labor cost of manually recording and collating data. The inspection feature atom library can be modified according to the user's correction feedback on the initial inspection form, and the inspection feature atom library can be synchronized in real time according to new changes or instructions to ensure the real-time and accuracy of the inspection information.
[0255] In some embodiments, after generating the target inspection form, the processor may distribute the target inspection form to the target inspection personnel. The embodiments of this specification do not specifically limit the method of distributing the target inspection form, and operations familiar to those skilled in the art may be used.
[0256] Some embodiments of this specification include at least the following beneficial effects: (1) Flexible assembly of inspection sheets based on task feature atoms and inspection feature atoms can ensure the consistency and accuracy of inspection information, reduce the impact of human factors on inspections, and improve efficiency; (2) The complete inspection content cannot be reused, but the inspection information at the atomic level can be reused. Flexible assembly of inspection feature atoms according to different working conditions can construct inspection sheets more flexibly; (3) The human brain cannot remember such a large amount of information, but computers can. The flexible assembly of inspection sheets based on feature atoms or codes can ensure the consistency and accuracy of inspection information, reduce the impact of human factors on inspections, and improve efficiency.
[0257] In some embodiments, the processor may also obtain the inspection results corresponding to the target inspection sheet; and generate a rectification sheet based on the inspection results.
[0258] The inspection result refers to the result of the inspection based on the target inspection list. In some embodiments, the inspection result may include not meeting the inspection standard and meeting the inspection standard. In some embodiments, the inspection result may be determined by user input.
[0259] The rectification sheet can be used to rectify the target inspection part that does not meet the inspection standard. In some embodiments, the rectification sheet can include the rectification target (for example, the target inspection part that does not meet the inspection standard) and the rectification content.
[0260] In some embodiments, the rectification content may include rectification of the construction technology and safety measures of the target inspection area.
[0261] In some embodiments, in response to an inspection result that does not meet the inspection standards, the processor can determine the target inspection part that does not meet the inspection standards as a rectification target; using the inspection standards as the rectification targets, determine the rectification content of the construction process and safety measures of the target inspection part; finally, generate a rectification order based on the rectification targets and rectification content.
[0262] In some embodiments of this specification, a rectification sheet is generated based on the inspection results, which can record and track the transmission process and results of the inspection information, facilitate subsequent query and analysis, and facilitate pre-control and preventive maintenance, and trace and analyze the construction process in the later stage. Through rectification, the construction process and safety measures of the target inspection site can meet the inspection standards.
[0263] It should be noted that the above description of the process 200 is only for example and illustration, and does not limit the scope of application of this specification. For those skilled in the art, various modifications and changes can be made to the process 200 under the guidance of this specification. However, these modifications and changes are still within the scope of this specification.
[0264] Figure 5 It is an exemplary schematic diagram of establishing an association relationship according to some embodiments of this specification.
[0265] In some embodiments, the processor can arbitrarily select a task feature atom in the task feature atom library as a query item, match it one by one in the patrol feature atom library based on a preset matching model, and determine the matching item; establish an association relationship between the query item and the matching item, and obtain the association relationship between the task feature atom in the task feature atom library and the patrol feature atom in the patrol feature atom library.
[0266] A query item is an information item used to search for other information in information retrieval. A match item is an information item that is searched using a query item in information retrieval.
[0267] The preset matching model may be a model for information retrieval. In some embodiments, the preset matching model may be a natural language processing (NLP) model. For example, the preset matching model may include a neural network language model (NNLM), Word2vec, FastText, etc.
[0268] In some embodiments, for each query item, the processor may match each patrol feature atom in the patrol feature atom library in turn based on the query item through a preset matching model to determine one or more matching items corresponding to the query item. The processor may establish an association relationship between the query item and the corresponding one or more matching items.
[0269] In some embodiments, the processor may use each task feature atom in the task feature atom library as a query item, determine one or more matching items corresponding to each task feature atom in the task feature atom library as a query item, and establish an association relationship between each task feature atom in the task feature atom library and the inspection feature atom in the inspection feature atom library.
[0270] In some embodiments, in response to the matching item being a parent atom including multiple patrol feature atoms, the processor may establish an association relationship between the multiple patrol feature atoms included in the parent atom and the query item.
[0271] like Figure 5As shown, the task feature atom library 510 includes multiple levels of task feature atoms, and the multiple levels of task feature atoms form a tree structure. Among them, atom A1 in the tree structure is the parent atom including atom A1.1 and atom A1.2, and atom A1.2 is the parent atom including atom A1.2.1 and atom A1.2.2; atom B1 in the tree structure is the parent atom including atom B1.1 and atom B1.2, and atom B1.2 is the parent atom including atom B1.2.1 and atom B1.2.2. The inspection feature atom library 520 includes multiple levels of inspection feature atoms, and the multiple levels of task feature atoms form a tree structure. Among them, atom C1 in the tree structure is the parent atom including atom C1.1 and atom C1.2, and atom C1.2 is the parent atom including atom C1.2.1 and atom C1.2.2.
[0272] As an example only, if the query item is atom A1.1, and the matching item determined by matching one by one in the patrol feature atom library 520 through the preset matching model is atom C1.2, then the association relationship between atom A1.1 and atom C1.2 can be established, as well as the association relationship between atom A1.1 and atoms C1.2.1 and atom C1.2.2.
[0273] In some embodiments, in response to the query term being a parent atom including multiple task feature atoms, the processor may establish an association relationship between the multiple task feature atoms included in the parent atom and the matching term.
[0274] Just as an example, if the query item is atom A1.2, and the matching item determined by matching one by one in the patrol feature atom library 520 through the preset matching model is atom C1.1, then the association relationship between atom A1.2 and atom C1.1 can be established, as well as the association relationship between atom A1.2.1 and atom A1.2.2 and atom C1.1. If the query item is atom A1.2, and the matching item determined by matching one by one in the patrol feature atom library 520 through the preset matching model is atom C1.2, then the association relationship between atom A1.2 and atom C1.2 can be established, as can the association relationship between atom A1.2.1, atom A1.2.2 and atom C1.2, the association relationship between atom A1.2.1, atom A1.2.2 and the parent atom of atom C1.2.1 and atom C1.2.2, and the association relationship between atom A1.2 and the parent atom of atom C1.2.1 and atom C1.2.2.
[0275] In some embodiments of the present specification, by matching one by one through a preset matching model to determine the association relationship between the query item and the matching item, the matching efficiency can be improved, and the association relationship between the task feature atoms in the task feature atom library and the inspection feature atoms in the inspection feature atom library can be efficiently established. Since both the task feature atoms and the inspection feature atoms are data obtained at the minimum atomic level of the step-by-step split value, by constructing a tree structure and making the child atoms inherit the association relationship of the parent atom, it is helpful to quickly determine the association relationship of the child atoms.
[0276] The basic concepts have been described above. Obviously, for those skilled in the art, the above detailed disclosure is only for example and does not constitute a limitation of this specification. Although not explicitly stated here, those skilled in the art may make various modifications, improvements and corrections to this specification. Such modifications, improvements and corrections are suggested in this specification, so such modifications, improvements and corrections still belong to the spirit and scope of the exemplary embodiments of this specification.
[0277] At the same time, this specification uses specific words to describe the embodiments of this specification. For example, "one embodiment", "an embodiment", and / or "some embodiments" refer to a certain feature, structure or characteristic related to at least one embodiment of this specification. Therefore, it should be emphasized and noted that "one embodiment" or "an embodiment" or "an alternative embodiment" mentioned twice or more in different positions in this specification does not necessarily refer to the same embodiment. In addition, certain features, structures or characteristics in one or more embodiments of this specification can be appropriately combined.
[0278] In addition, unless explicitly stated in the claims, the order of the processing elements and sequences described in this specification, the use of alphanumeric characters, or the use of other names are not intended to limit the order of the processes and methods of this specification. Although the above disclosure discusses some invention embodiments that are currently considered useful through various examples, it should be understood that such details are only for illustrative purposes, and the attached claims are not limited to the disclosed embodiments. On the contrary, the claims are intended to cover all modifications and equivalent combinations that are consistent with the essence and scope of the embodiments of this specification. For example, although the system components described above can be implemented by hardware devices, they can also be implemented only by software solutions, such as installing the described system on an existing server or mobile device.
[0279] Similarly, it should be noted that in order to simplify the description disclosed in this specification and thus help understand one or more embodiments of the invention, in the above description of the embodiments of this specification, multiple features are sometimes combined into one embodiment, figure or description thereof. However, this disclosure method does not mean that the features required by the subject matter of this specification are more than the features mentioned in the claims. In fact, the features of the embodiments are less than all the features of the single embodiment disclosed above.
[0280] In some embodiments, numbers describing the number of components and attributes are used. It should be understood that such numbers used in the description of the embodiments are modified by the modifiers "about", "approximately" or "substantially" in some examples. Unless otherwise specified, "about", "approximately" or "substantially" indicate that the numbers are allowed to vary by ±20%. Accordingly, in some embodiments, the numerical parameters used in the specification and claims are approximate values, which may change according to the required features of individual embodiments. In some embodiments, the numerical parameters should take into account the specified significant digits and adopt the general method of retaining the digits. Although the numerical domains and parameters used to confirm the breadth of the range in some embodiments of this specification are approximate values, in specific embodiments, the setting of such numerical values is as accurate as possible within the feasible range.
[0281] Each patent, patent application, patent application publication, and other materials, such as articles, books, specifications, publications, documents, etc., cited in this specification is hereby incorporated by reference in its entirety. Except for application history documents that are inconsistent with or conflicting with the contents of this specification, documents that limit the broadest scope of the claims of this specification (currently or later attached to this specification) are also excluded. It should be noted that if the descriptions, definitions, and / or use of terms in the materials attached to this specification are inconsistent or conflicting with the contents described in this specification, the descriptions, definitions, and / or use of terms in this specification shall prevail.
[0282] Finally, it should be understood that the embodiments described in this specification are only used to illustrate the principles of the embodiments of this specification. Other variations may also fall within the scope of this specification. Therefore, as an example and not a limitation, alternative configurations of the embodiments of this specification may be considered consistent with the teachings of this specification. Accordingly, the embodiments of this specification are not limited to the embodiments explicitly introduced and described in this specification.
Claims
1. A method for generating a construction inspection form, characterized in that: include: Obtain the task feature atomic library and the inspection feature atomic library; By presetting a matching model, establishing an association relationship between the task feature atoms in the task feature atom library and the inspection feature atoms in the inspection feature atom library; Obtaining a task list, and determining the target construction site to be inspected and the target task feature atoms based on the task list; Based on the target task feature atom and the association relationship, determining the target inspection feature atom corresponding to the target task feature atom; Determining target inspection personnel and target inspection frequency based on the target construction site; and Generate a target inspection list based on the target inspection feature atoms, the target inspection personnel and the target inspection frequency; Wherein, the task feature atom library acquisition includes: Acquire multiple historical task orders, and extract at least one construction feature point from each of the multiple historical task orders; Determine at least one corresponding task feature atom based on the at least one construction feature point to construct the task feature atom library; the construction feature point includes at least one of a task item feature point, a project category feature point, a construction site feature point, a construction cost feature point, a construction material feature point, a construction phase feature point, and a construction progress feature point; the task feature atom includes at least one of a task item atom, a project category atom, a construction site atom, a construction cost atom, a construction material atom, a construction phase atom, and a construction progress atom; The determining of at least one corresponding task feature atom based on the at least one construction feature point comprises: According to the construction feature points, the historical task list is split into the smallest atomic level step by step to obtain the task feature atoms corresponding to multiple levels; The obtaining of the patrol feature atom library comprises: Acquire multiple historical inspection lists, and extract at least one inspection feature point from each of the multiple historical inspection lists; Determine at least one corresponding inspection feature atom based on the at least one inspection feature point to construct the inspection feature atom library; the inspection feature point includes at least one of a construction process feature point, a safety measure feature point and an inspection standard feature point, and the inspection feature atom includes at least one of a construction process atom, a safety measure atom and an inspection standard atom; The determining of at least one corresponding patrol feature atom based on the at least one patrol feature point comprises: The historical inspection list is split into the smallest atomic level step by step according to the inspection feature points, so as to obtain the inspection feature atoms corresponding to multiple levels.
2. The method according to claim 1, characterized in that The establishing of the association relationship between the task feature atoms in the task feature atom library and the inspection feature atoms in the inspection feature atom library by using the preset matching model includes: Randomly select a task feature atom in the task feature atom library as a query item, match one by one in the patrol feature atom library based on the preset matching model, and determine the matching item, wherein the preset matching model is a machine learning model; An association relationship between the query item and the matching item is established, and an association relationship between the task feature atom in the task feature atom library and the inspection feature atom in the inspection feature atom library is obtained.
3. The method according to claim 2, characterized in that The method further comprises: In response to the matching item being a parent atom including a plurality of the patrol feature atoms, an association relationship between the plurality of the patrol feature atoms included in the parent atom and the query item is established.
4. The method according to claim 1, characterized in that The generating a target inspection list based on the target inspection feature atom, the target inspection personnel and the target inspection frequency includes: Get the inspection form template; Generate an initial inspection list based on the target inspection feature atom and the inspection list template; In response to receiving a confirmation feedback from a user on the initial inspection list, the target inspection list is generated based on the initial inspection list, the target inspection personnel and the target inspection frequency.
5. The method according to claim 1, characterized in that Determining target inspection personnel and target inspection frequency based on the target construction site includes: Determine the inspection type based on the target construction site; Based on the inspection type, the target inspection personnel and the target inspection frequency are determined.
6. The method according to claim 5, characterized in that Determining the inspection type based on the target construction site includes: Based on the target construction site, obtaining acceptance information of similar construction sites outside the task list; In response to the acceptance information satisfying a first preset condition, determining the inspection type as a regular inspection; In response to the acceptance information not satisfying the first preset condition, determining the inspection type as a special inspection, wherein the special inspection includes inspecting the construction quality of the target construction site; The determining the target inspection personnel and the target inspection frequency based on the inspection type includes: In response to the inspection type being the conventional inspection, a reference inspection frequency is determined by querying the inspection sheet of the task sheet corresponding to the same type of construction site, and the target inspection frequency corresponding to the conventional inspection is determined based on the reference inspection frequency; and, a manager of the target construction site is queried to determine the manager as the target inspector corresponding to the conventional inspection; In response to the inspection type being the special inspection, the construction period of the target construction site is queried, and the target inspection frequency corresponding to the special inspection is determined based on the construction period; and, the acceptance personnel of the target construction site are queried, and the acceptance personnel are determined as the target inspection personnel corresponding to the special inspection.
7. The method according to claim 5, characterized in that Determining the inspection type based on the target construction site includes: Based on the target construction site, obtaining construction safety information of similar construction sites outside the task list; In response to the construction safety information satisfying a second preset condition, determining the inspection type as a regular inspection; In response to the construction safety information not satisfying the second preset condition, determining the inspection type as a special inspection, wherein the special inspection includes inspecting the construction quality of the target construction site; The determining the target inspection personnel and the target inspection frequency based on the inspection type includes: In response to the inspection type being the conventional inspection, a reference inspection frequency is determined by querying the inspection sheet of the task sheet corresponding to the same type of construction site, and the target inspection frequency corresponding to the conventional inspection is determined based on the reference inspection frequency; and, a manager of the target construction site is queried to determine the manager as the target inspector corresponding to the conventional inspection; In response to the inspection type being the special inspection, the inspection intensity is determined based on the construction safety information, and the target inspection frequency corresponding to the special inspection is determined based on the inspection intensity; and, the management personnel of the target construction site are queried, and the management personnel are determined as the target inspection personnel corresponding to the special inspection.
8. The method according to claim 1, characterized in that The method further comprises: Obtaining the inspection result corresponding to the target inspection list; Based on the inspection results, a rectification sheet is generated.
9. A system for generating a construction inspection form, characterized in that: The system comprises: An acquisition module is used to acquire a task feature atom library and an inspection feature atom library; An establishing module, used to establish an association relationship between the task feature atoms in the task feature atom library and the patrol feature atoms in the patrol feature atom library through a preset matching model; Identify modules for: Obtaining a task list, and determining the target construction site to be inspected and the target task feature atoms based on the task list; Based on the target task feature atom and the association relationship, determining the target inspection feature atom corresponding to the target task feature atom; and Based on the target construction site, determine the target inspection personnel and the target inspection frequency; A generation module, used for generating a target inspection list based on the target inspection feature atom, the target inspection personnel and the target inspection frequency; Wherein, the task feature atom library acquisition includes: Acquire multiple historical task orders, and extract at least one construction feature point from each of the multiple historical task orders; Determine at least one corresponding task feature atom based on the at least one construction feature point to construct the task feature atom library; the construction feature point includes at least one of a task item feature point, a project category feature point, a construction site feature point, a construction cost feature point, a construction material feature point, a construction phase feature point, and a construction progress feature point; the task feature atom includes at least one of a task item atom, a project category atom, a construction site atom, a construction cost atom, a construction material atom, a construction phase atom, and a construction progress atom; The determining of at least one corresponding task feature atom based on the at least one construction feature point comprises: According to the construction feature points, the historical task list is split into the smallest atomic level step by step to obtain the task feature atoms corresponding to multiple levels; The obtaining of the patrol feature atom library comprises: Acquire multiple historical inspection lists, and extract at least one inspection feature point from each of the multiple historical inspection lists; Determine at least one corresponding inspection feature atom based on the at least one inspection feature point to construct the inspection feature atom library; the inspection feature point includes at least one of a construction process feature point, a safety measure feature point and an inspection standard feature point, and the inspection feature atom includes at least one of a construction process atom, a safety measure atom and an inspection standard atom; The determining of at least one corresponding patrol feature atom based on the at least one patrol feature point comprises: The historical inspection list is split into the smallest atomic level step by step according to the inspection feature points, so as to obtain the inspection feature atoms corresponding to multiple levels.
10. A computer-readable storage medium storing computer instructions, characterized in that: After the computer reads the computer instructions in the storage medium, the computer executes the method for generating a construction inspection sheet as described in any one of claims 1 to 8.