Method for determining auxiliary tunnel centerline based on group optimization
By acquiring tunnel engineering data, determining the number of construction zones, and optimizing the center mileage, the problem of relying on experience in auxiliary tunnel design was solved, enabling rapid and accurate auxiliary tunnel design and improving design efficiency.
Patent Information
- Application Number
- CN202410646800.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2025-11-25
- Estimated Expiration
- 2044-05-23
AI Technical Summary
In existing technologies, auxiliary tunnel design relies on design experience and lacks objective data support, resulting in low design efficiency, inability to update quickly, and inability to meet the rapid drawing requirements of tunnel construction.
By acquiring tunnel engineering data, determining the number of construction work areas, calculating the reference construction period of the tunnel based on the number of construction work areas, optimizing the initial center mileage to obtain the target center mileage, and using the acquisition module, determination module, and optimization module to achieve rapid and accurate design of auxiliary tunnels.
It improves the design efficiency of auxiliary tunnel schemes, enables the rapid and accurate positioning of the center mileage of auxiliary tunnels, overcomes the technical defects of low design efficiency, and meets the requirements of rapid drawing production in tunnel construction.
Smart Images

Figure CN118427942B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of tunnel design, in particular to an auxiliary tunnel center mileage determination method based on group optimization. BACKGROUND
[0002] In the process of railway mountain tunnel construction, construction period and engineering cost affect the selection of tunnel scheme. For a super-long tunnel, if only one-way or opposite construction of the tunnel is considered, the construction period generally cannot meet the overall project demand, so an auxiliary tunnel needs to be set in the middle of the tunnel to shorten the construction period. Because tunnel excavation is carried out in different grades of rock, the excavation construction speed is not the same, which affects the overall construction period of the auxiliary tunnel, and the number of auxiliary tunnels also affects the engineering cost, so determining the number and layout position of auxiliary tunnels is an important factor to be considered in the process of optimizing construction period and cost.
[0003] At present, the design of auxiliary tunnels by designers often relies on inherent design experience. Whether the design experience is rich or poor determines whether the auxiliary tunnel scheme is accurate. Whether there is an optimization space for the auxiliary tunnel scheme cannot be known from objective data calculation, which does not meet the requirement of refined design. Moreover, in actual scheme design, the tunnel line scheme is often adjusted and changed, and the geological information is also updated continuously in the process of drilling. The conventional auxiliary tunnel design idea cannot be quickly updated, and the auxiliary tunnel scheme cannot be adjusted accordingly. The adjustment of upstream data requires designers to re-study and draw the auxiliary tunnel scheme, which is low in efficiency and cannot be updated accordingly, and cannot meet the requirement of rapid drawing.
[0004] Therefore, how to effectively improve the design efficiency of the auxiliary tunnel scheme is a problem to be solved at present.
[0005] The above content is only used to assist in understanding the technical scheme of the present application, and does not represent the acknowledgement of the above content as prior art. SUMMARY
[0006] The main purpose of the present application is to provide an auxiliary tunnel center mileage determination method based on group optimization, which aims to solve the technical problem of how to effectively improve the design efficiency of the auxiliary tunnel scheme.
[0007] To achieve the above purpose, the present application provides an auxiliary tunnel center mileage determination method based on group optimization, which comprises:
[0008] Obtain tunnel engineering data, and determine the number of construction work areas according to the tunnel engineering data;
[0009] Determine the tunnel reference construction period under the auxiliary tunnel based on the number of construction work areas;
[0010] determine an initial center mileage of the auxiliary tunnel based on the tunnel reference construction period;
[0011] obtain an actual construction period of the tunnel under the auxiliary tunnel, and optimize the initial center mileage based on the actual construction period of the tunnel to obtain a target center mileage of the auxiliary tunnel.
[0012] In an embodiment, the determining the number of construction work zones according to the tunnel engineering data comprises:
[0013] determining a tunnel overall construction period, a construction speed of each stratum within the tunnel, and a construction length of each stratum according to the tunnel engineering data;
[0014] determining a construction time of each stratum according to the construction speed of each stratum and the construction length of each stratum;
[0015] determining the number of construction work zones according to the construction time of each stratum and the tunnel overall construction period.
[0016] In an embodiment, the determining the number of construction work zones according to the construction time of each stratum and the tunnel overall construction period comprises:
[0017] determining a number of strata within the tunnel and a tunnel length according to the tunnel engineering data;
[0018] determining a one-way construction period according to the number of strata and the construction time of each stratum;
[0019] determining the number of construction work zones according to the one-way construction period and the tunnel overall construction period.
[0020] In an embodiment, the determining the number of construction work zones according to the one-way construction period and the tunnel length comprises:
[0021] when the one-way construction period is greater than the tunnel overall construction period, determining a two-way construction period according to the number of strata and the construction time of each stratum;
[0022] when the two-way construction period is greater than the tunnel overall construction period, determining a construction work zone boundary position and a number of construction work zone boundary positions according to the construction time of each stratum, the construction speed of each stratum, the construction length of each stratum, and a preset construction period of a single auxiliary tunnel;
[0023] comparing a target position in the construction work zone boundary position with the tunnel length;
[0024] when the target position in the construction work zone boundary position reaches the tunnel length, taking the number of construction work zone boundary positions as the number of construction work zones.
[0025] In an embodiment, the tunnel reference construction period under the auxiliary tunnel is determined based on the number of construction sections, and the method comprises:
[0026] The number of auxiliary tunnels is determined based on the number of construction sections.
[0027] The construction time of each construction section is determined according to the number of auxiliary tunnels.
[0028] The tunnel reference construction period under the auxiliary tunnel is determined according to the construction time of each construction section.
[0029] In an embodiment, the initial center mileage of the auxiliary tunnel is determined based on the tunnel reference construction period, and the method comprises:
[0030] The demarcation mileage of each construction section is determined according to the tunnel reference construction period.
[0031] An index number at the demarcation mileage is obtained, and an odd-even judgment is performed according to the index number.
[0032] When the index number is odd, the demarcation mileage is taken as the initial center mileage of the auxiliary tunnel.
[0033] In an embodiment, the initial center mileage is optimized based on the tunnel actual construction period to obtain the target center mileage of the auxiliary tunnel, and the method comprises:
[0034] The tunnel actual construction period is compared with the tunnel reference construction period.
[0035] When the tunnel reference construction period is greater than the tunnel actual construction period, the number of auxiliary tunnels is updated until the tunnel reference construction period corresponding to the updated number of auxiliary tunnels is less than or equal to the tunnel actual construction period, and the target number of auxiliary tunnels is obtained.
[0036] The tunnel target construction period is determined according to the target number of auxiliary tunnels.
[0037] The target center mileage of the auxiliary tunnel is determined according to the tunnel target construction period.
[0038] In addition, to achieve the above-mentioned purpose, the application further provides an auxiliary tunnel center mileage determination device based on construction optimization, which comprises:
[0039] An acquisition module is configured to acquire tunnel engineering data and determine the number of construction sections according to the tunnel engineering data.
[0040] A determination module is configured to determine the tunnel reference construction period under the auxiliary tunnel based on the number of construction sections.
[0041] The determination module is further configured to determine an initial center mileage of the auxiliary tunnel based on the tunnel reference construction period;
[0042] The optimization module is configured to obtain an actual construction period of the tunnel under the auxiliary tunnel, and optimize the initial center mileage based on the actual construction period of the tunnel to obtain a target center mileage of the auxiliary tunnel.
[0043] In addition, to achieve the above object, the present application further provides an auxiliary tunnel center mileage determination device based on group optimization, which comprises a memory, a processor and a computer program stored in the memory and executable on the processor, and the computer program is configured to implement the steps of the auxiliary tunnel center mileage determination method based on group optimization as described above.
[0044] In addition, to achieve the above object, the present application further provides a storage medium, which is a computer readable storage medium, and a computer program is stored on the storage medium, and the computer program is executed by a processor to implement the steps of the auxiliary tunnel center mileage determination method based on group optimization as described above.
[0045] In addition, to achieve the above object, the present application further provides a computer program product, which comprises a computer program, and the computer program is executed by a processor to implement the steps of the auxiliary tunnel center mileage determination method based on group optimization as described above.
[0046] The present application provides an auxiliary tunnel center mileage determination method based on group optimization. The present application firstly obtains tunnel engineering data, and determines the number of construction work areas according to the tunnel engineering data to improve the accuracy of the number of construction work areas. The tunnel reference construction period under the auxiliary tunnel is determined based on the number of construction work areas, which can quickly and accurately determine the tunnel reference construction period. The initial center mileage of the auxiliary tunnel is determined based on the tunnel reference construction period to improve the optimization efficiency. The actual construction period of the tunnel under the auxiliary tunnel is obtained, and the initial center mileage is optimized based on the actual construction period of the tunnel to obtain the target center mileage of the auxiliary tunnel. The center mileage of the auxiliary tunnel can be quickly and accurately positioned, thereby effectively improving the auxiliary tunnel scheme design efficiency.
[0047] In summary, the present application determines the initial center mileage by determining the number of construction work areas to obtain the reference construction period, and then optimizes the initial center mileage to obtain the target center mileage. The initial center mileage is quickly determined based on the number of construction work areas and continuously optimized, which can quickly and accurately position the center mileage of the auxiliary tunnel, overcome the technical defect of low auxiliary tunnel scheme design efficiency, and effectively improve the auxiliary tunnel scheme design efficiency. BRIEF DESCRIPTION OF DRAWINGS
[0048] The accompanying drawings, which are incorporated herein and constitute part of this specification, illustrate embodiments consistent with the application and, together with the description, further serve to explain the principles of the application.
[0049] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the accompanying drawings needed to be used in the embodiments or prior art description will be briefly introduced as follows. Obviously, those skilled in the art can obtain other drawings according to these drawings without any creative effort.
[0050] Figure 1 A flowchart provided by the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 1 of the present application;
[0051] Figure 2 A diagram for the case that the number of construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 1 of the present application is odd;
[0052] Figure 3 A diagram for the case that the number of construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 1 of the present application is even;
[0053] Figure 4 A diagram for auxiliary drifts and construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 1 of the present application;
[0054] Figure 5 A flowchart provided by the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 2 of the present application;
[0055] Figure 6 A diagram for the case that the number of construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 2 of the present application is odd;
[0056] Figure 7 A diagram for the case that the number of construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 2 of the present application is odd;
[0057] Figure 8 A diagram for auxiliary drifts and construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 2 of the present application;
[0058] Figure 9 A diagram for auxiliary drifts and construction work areas of the method for determining auxiliary drift center mileage based on optimization of construction groups according to Embodiment 2 of the present application;
[0059] Figure 10A module structure schematic diagram of an auxiliary tunnel center mileage determination device based on optimization of a construction team according to an embodiment of the present application;
[0060] Figure 11 A device structure schematic diagram of a hardware running environment involved in an auxiliary tunnel center mileage determination method based on optimization of a construction team according to an embodiment of the present application.
[0061] The object implementation, functional features and advantages of the present application will be further described with reference to the embodiments and the accompanying drawings. DETAILED DESCRIPTION
[0062] It should be understood that the specific embodiments described herein are merely intended to explain the technical solutions of the present application, and are not intended to limit the present application.
[0063] In order to better understand the technical solutions of the present application, the specific embodiments will be described in detail below with reference to the accompanying drawings and specific embodiments.
[0064] The main solution of the embodiment of the present application is: acquiring tunnel engineering data, and determining the number of construction work areas according to the tunnel engineering data; determining a tunnel reference construction period under the auxiliary tunnel based on the number of construction work areas; determining an initial center mileage of the auxiliary tunnel based on the tunnel reference construction period; acquiring a tunnel actual construction period under the auxiliary tunnel, and optimizing the initial center mileage based on the tunnel actual construction period to obtain a target center mileage of the auxiliary tunnel.
[0065] At present, the design of the auxiliary tunnel by the designer often relies on inherent design experience, and whether the auxiliary tunnel scheme is accurate depends on the richness and scarcity of the design experience. Whether there is an optimization space for the auxiliary tunnel scheme cannot be known from objective data calculation, which does not meet the requirement of refined design. Moreover, in actual scheme design, the tunnel line scheme is often adjusted and changed, and the geological information is also updated constantly in the drilling process. The conventional auxiliary tunnel design idea cannot be quickly updated, and the auxiliary tunnel scheme cannot be adjusted specifically. The adjustment of the upstream data causes the designer to re-study and draw the auxiliary tunnel scheme, the auxiliary tunnel scheme design efficiency is low, the auxiliary tunnel scheme cannot be updated specifically, and cannot adapt to the requirement of rapid drawing. Therefore, how to effectively improve the auxiliary tunnel scheme design efficiency is a problem to be solved at present.
[0066] The present application determines the reference construction period by determining the number of construction work areas, thereby determining the initial center mileage and optimizing it to obtain the target center mileage. The initial center mileage is quickly determined by the number of construction work areas and is constantly optimized, which can quickly and accurately locate the auxiliary tunnel center mileage, overcomes the technical defect of low auxiliary tunnel scheme design efficiency, and can effectively improve the auxiliary tunnel scheme design efficiency.
[0067] It should be noted that the execution subject of the embodiment can be a computing service device with data processing, network communication and program running functions, such as a tablet computer, a personal computer, a mobile phone, or an electronic device capable of realizing the above functions, an auxiliary tunnel center mileage determination device based on group optimization, etc. The following will take the auxiliary tunnel center mileage determination device based on group optimization as an example to describe the embodiment and the following embodiments.
[0068] Based on this, the embodiment of the application provides an auxiliary tunnel center mileage determination method based on group optimization, which refers to Figure 1 , Figure 1 The flowchart of the first embodiment of the auxiliary tunnel center mileage determination method based on group optimization of the application is shown in the figure.
[0069] In the embodiment, the auxiliary tunnel center mileage determination method based on group optimization comprises steps S10-S40:
[0070] Step S10, acquiring tunnel engineering data and determining the number of construction work areas according to the tunnel engineering data.
[0071] It should be noted that the tunnel engineering data refers to various data generated in the design and construction process of the tunnel project, including the overall duration of the tunnel, the length of the tunnel, the construction speed and length of each stratum within the tunnel range, and the construction duration of a single auxiliary tunnel, etc., which are not specifically limited in the embodiment.
[0072] It can be understood that the tunnel engineering data can be obtained in various ways, such as from design drawings, construction records, geological survey reports, etc., and the tunnel engineering data is crucial for determining the number of construction work areas, because the division of construction work areas will directly affect the efficiency and quality of tunnel construction. When determining the number of construction work areas, factors such as the overall duration of the tunnel, the length of the tunnel, and the stratum construction speed should be considered comprehensively to ensure that the division of construction work areas is reasonable and efficient.
[0073] Step S20, determining the tunnel reference construction duration under the auxiliary tunnel based on the number of construction work areas.
[0074] It should be noted that the tunnel reference construction duration refers to the theoretical duration required for tunnel construction obtained by the first recalculation duration under the condition of setting an auxiliary tunnel. When determining the tunnel reference construction duration, factors such as the number of construction work areas, the length of the tunnel, and the stratum construction speed can be considered comprehensively.
[0075] It can be understood that when the construction duration of tunnel unidirectional construction and bidirectional construction both do not meet the demand of the overall duration, an auxiliary tunnel needs to be set in the middle of the tunnel to shorten the construction duration, and the construction time of each construction work area after setting the auxiliary tunnel is the construction duration of a single construction work area minus the construction duration of a single auxiliary tunnel.
[0076] In one feasible implementation, step S20 may include: determining the number of auxiliary tunnels based on the number of construction work areas; determining the construction time of each construction work area based on the number of auxiliary tunnels; and determining the reference construction period of the tunnel under the auxiliary tunnels based on the construction time of each construction work area.
[0077] It should be noted that the number of auxiliary tunnels is determined based on the number of construction work areas. That is, if the number of construction work areas is even, the number of auxiliary tunnels N = number of construction work areas / 2 - 1; if the number of construction work areas is odd, the number of auxiliary tunnels N = (number of construction work areas + 1) / 2 - 1.
[0078] like Figure 2 As shown, Figure 2 The diagram illustrates a construction zone with an odd number of sections. The tunnel length is divided into three sections based on the construction zones, meaning there are three construction zones. The connection point between two construction zones is the boundary between adjacent construction zones. When there are three construction zones, there are two connection points between them.
[0079] like Figure 3 As shown, Figure 3 The diagram shows a construction zone with an even number of sections. The tunnel length is divided into 4 sections based on the construction zones, meaning there are 4 construction zones. The connection point between construction zones is the boundary between adjacent construction zones. When there are 4 construction zones, there are 3 connection points between construction zones.
[0080] It is understandable that the construction time of each construction section can be obtained based on the number of auxiliary tunnels and the sum of the construction time of all strata within the tunnel area. This is the tunnel construction period under the auxiliary tunnels with a quantity of N, i.e., the reference construction period of the tunnel under the auxiliary tunnels.
[0081] Step S30: Determine the initial center mileage of the auxiliary tunnel based on the reference construction period of the tunnel.
[0082] It should be noted that the initial center mileage is determined based on a comprehensive analysis of the tunnel's reference construction period and tunnel engineering data. After determining the initial center mileage, the center mileage of the auxiliary tunnels needs to be optimized based on the actual conditions of the tunnel engineering data to ensure it meets the actual construction requirements. The optimization process may include multiple iterations and adjustments until the optimal target center mileage is obtained.
[0083] Understandably, the center mileage of an auxiliary tunnel refers to its position during tunnel construction, specifically the location of the intersection of the auxiliary tunnel's centerline and the tunnel axis along the tunnel's length. Determining the center mileage of the auxiliary tunnel is crucial for the smooth progress of tunnel construction, directly impacting construction efficiency and project costs.
[0084] It is worth noting that the initial center mileage of the auxiliary tunnel is determined based on the tunnel's reference construction period and the distribution of the construction area. When determining the initial center mileage, the connection point of the construction area and the impact of the auxiliary tunnel on the construction area need to be considered.
[0085] In one feasible implementation, step S30 may include: determining the boundary mileage of each construction zone according to the tunnel reference construction period; obtaining the index number at the boundary mileage and performing parity judgment based on the index number; when the index number is odd, using the boundary mileage as the initial center mileage of the auxiliary tunnel.
[0086] It should be noted that the boundary mileage of each construction section is calculated based on the tunnel's reference construction period, tunnel stratum velocity, and distance, and this boundary mileage is added to the set. The parity of the index number at the boundary mileage is used to determine whether the mileage is the initial mileage of the construction section or the initial mileage of the auxiliary tunnel. If the number is even, it is the initial mileage of the construction section; if the number is odd, it is the initial center mileage of the auxiliary tunnel.
[0087] like Figure 4 As shown, Figure 4 To illustrate the auxiliary tunnel and construction area diagram, the tunnel length is divided into multiple construction areas based on the overall tunnel construction period, the construction speed Vi of each stratum within the tunnel, and the length li. The first and last construction areas are located at the tunnel entrance. The boundary between adjacent construction areas is the connection point of the construction area. The boundary between adjacent construction areas can also be the location of the auxiliary tunnel. The auxiliary tunnel is the starting point of the construction area, and the connection point is the ending point of the construction area.
[0088] Step S40: Obtain the actual construction period of the tunnel under the auxiliary tunnel, and optimize the initial center mileage based on the actual construction period of the tunnel to obtain the target center mileage of the auxiliary tunnel.
[0089] It should be noted that the actual construction period of the tunnel under the auxiliary tunnel, i.e. the required construction period, must conform to the overall progress of the tunnel project.
[0090] It is understandable that, due to changes in the tunnel's route and geological information, there may be some discrepancies between the reference construction period and the actual construction period. To ensure that the design of the auxiliary tunnel meets the actual construction requirements, it is necessary to obtain the actual construction period of the tunnel under the auxiliary tunnel and optimize the initial center mileage based on this actual construction period. This will allow for data adjustment and updates, adapting to the requirements of rapid drawing production for the auxiliary tunnel design, thereby improving engineering design efficiency.
[0091] In a feasible implementation, step S40 can include: comparing the actual tunnel construction period with the reference tunnel construction period; updating the number of auxiliary tunnels until the reference tunnel construction period corresponding to the updated number of auxiliary tunnels is less than or equal to the actual tunnel construction period, to obtain a target number of auxiliary tunnels; determining a target tunnel construction period according to the target number of auxiliary tunnels; and determining a target center mileage of the auxiliary tunnel according to the target tunnel construction period.
[0092] It should be noted that the target tunnel construction period is a theoretical period required for tunnel construction obtained by recalculating the period under the target number of auxiliary tunnels. By comparing the actual tunnel construction period with the reference tunnel construction period, the deviation between the two can be found in time, so that appropriate measures can be taken for adjustment. When the reference tunnel construction period is greater than the actual tunnel construction period, it indicates that the current number of auxiliary tunnels can be too small, and the number of auxiliary tunnels needs to be increased to shorten the period. In the process of increasing the number of auxiliary tunnels, the number of auxiliary tunnels needs to be updated constantly, and the reference tunnel construction period needs to be recalculated until the reference tunnel construction period is less than or equal to the actual tunnel construction period.
[0093] In a specific implementation, if the reference tunnel construction period is greater than the actual tunnel construction period, one auxiliary tunnel is added, the reference tunnel construction period is recalculated according to the updated number of auxiliary tunnels until the reference tunnel construction period is less than the actual tunnel construction period, and if the reference tunnel construction period is less than the actual tunnel construction period, a new initial center mileage of the auxiliary tunnel is calculated according to the current number of auxiliary tunnels, and the new initial center mileage of the auxiliary tunnel is taken as the target center mileage.
[0094] It should be noted that the basic principle of the auxiliary tunnel center mileage determination method based on optimization in the embodiment is as follows: before the auxiliary tunnel is arranged, the overall tunnel construction period, the tunnel length, the construction speed and length of each stratum within the tunnel range, and the construction period of a single auxiliary tunnel are determined; the tunnel is processed by slicing according to the period by using the greedy algorithm, and the number of construction work areas is preliminarily obtained; the number of auxiliary tunnels is determined according to the number of construction work areas and the parity characteristics thereof; the overall tunnel construction period is recalculated according to the determined number of construction work areas; the length of the construction work area is calculated according to the new tunnel construction period; the preliminary center mileage of the auxiliary tunnel is determined according to the length of the construction work area and the period boundary position thereof; the construction period of the auxiliary tunnel is determined, the tunnel construction period is recalculated until it is less than the required period, and the steps of “recalculating the overall tunnel construction period according to the determined number of construction work areas” to “determining the preliminary center mileage of the auxiliary tunnel according to the length of the construction work area and the period boundary position thereof” are repeated to calculate the final center mileage of the auxiliary tunnel.
[0095] The embodiment provides a method for determining an auxiliary tunnel center mileage based on optimization, and the method comprises the following steps: acquiring tunnel engineering data, and determining the number of construction work areas according to the tunnel engineering data, so as to improve the accuracy of the number of construction work areas; determining a tunnel reference construction period under the auxiliary tunnel based on the number of construction work areas, so as to quickly and accurately determine the tunnel reference construction period; determining an initial center mileage of the auxiliary tunnel based on the tunnel reference construction period, so as to improve the optimization efficiency; acquiring an actual tunnel construction period under the auxiliary tunnel, and optimizing the initial center mileage based on the actual tunnel construction period, so as to obtain a target center mileage of the auxiliary tunnel, and the target center mileage can be used to quickly and accurately locate the center mileage of the auxiliary tunnel, thereby effectively improving the auxiliary tunnel scheme design efficiency.
[0096] In conclusion, the reference construction period is determined by determining the number of construction work areas, the initial center mileage is determined and optimized to obtain the target center mileage, the initial center mileage is quickly determined based on the number of construction work areas and is continuously optimized, the center mileage of the auxiliary tunnel can be quickly and accurately located, the technical defect of low auxiliary tunnel scheme design efficiency is overcome, and the auxiliary tunnel scheme design efficiency can be effectively improved.
[0097] Based on the first embodiment of the application, in the second embodiment of the application, the same or similar contents as the above-mentioned first embodiment can be referred to the above description, and the subsequent description will not be repeated. On this basis, please refer to Figure 5 , the step S10 further comprises steps S101-S103:
[0098] In step S101, the tunnel overall construction period, the construction speed of each stratum in the tunnel range and the construction length of each stratum are determined according to the tunnel engineering data.
[0099] It should be noted that the tunnel engineering data at least comprises a tunnel overall construction period T s , a tunnel length L s , a construction speed V i of each stratum in the tunnel range, a length l i and a single auxiliary tunnel construction period T f , and the embodiment does not make specific limitation on this.
[0100] It can be understood that according to the tunnel overall construction period, in combination with the construction speed V i of each stratum in the tunnel range and the length l i , the entire tunnel is processed by slicing according to the tunnel overall construction period T s , a local optimal solution of the number of construction work areas under this construction period is obtained according to the number of slices, and the number of construction work areas is preliminarily obtained.
[0101] Step S102: Determine the construction time for each stratum based on the construction speed and construction length of each stratum.
[0102] It should be noted that, based on the construction speed V of each stratum within the tunnel area... i and length l i The construction time t for each stratum can be obtained. i , t i =V i / l i .
[0103] Step S103: Determine the number of construction zones based on the construction time of each stratum and the overall tunnel construction period.
[0104] It should be noted that, depending on the construction time t of each stratum, i And the overall construction period of the tunnel T s This allows us to determine the number of construction zones.
[0105] In practical implementation, the overall tunnel construction period T can be... s According to the construction time of each stratum t i The project is divided into sections, and the construction period for each section is determined. This determines the number of construction sections, and the time allotted for each section is the total construction period T. s It is the sum of the construction times Ti of each stratum according to the overall construction period T. s The number of work zones is obtained by dividing the area into zones. The number of work zones can also be determined by other methods, but this embodiment does not impose specific restrictions on this.
[0106] In one feasible implementation, step S103 may include: determining the number of strata and the tunnel length based on the tunnel engineering data; determining the one-way construction period based on the number of strata and the construction time of each stratum; and determining the number of construction zones based on the one-way construction period and the tunnel length.
[0107] It should be noted that the one-way construction period refers to the time required to start construction from one end of the tunnel and reach the other end. If the one-way construction period is less than or equal to the overall tunnel construction period, then one-way construction can meet the requirements of the overall tunnel construction period, and there is no need to increase the number of construction work areas. However, if the one-way construction period is greater than the overall tunnel construction period, then one-way construction cannot meet the requirements of the overall tunnel construction period, and it is necessary to consider increasing the number of construction work areas. In this case, two-way construction can be considered, that is, starting construction simultaneously from both ends of the tunnel, which can shorten the construction period.
[0108] It can be understood that if the two-way construction period is less than or equal to the overall tunnel construction period, the two-way construction can meet the requirement of the overall tunnel construction period, and in this case, the auxiliary tunnel does not need to be added. However, if the two-way construction period is still greater than the overall tunnel construction period, the auxiliary tunnel needs to be added in order to further shorten the construction period.
[0109] In a specific implementation, only the one-way construction is considered, if wherein, is the one-way construction period, the one-way construction can meet the overall tunnel construction period; if the one-way construction does not meet the overall construction period, the two-way construction is considered, if the two-way construction can meet the overall tunnel construction period, in this case, the auxiliary tunnel does not need to be added, if the auxiliary tunnel needs to be added.
[0110] In a feasible implementation, the construction work area quantity is determined according to the one-way construction period and the tunnel length, including: when the one-way construction period is greater than the overall tunnel construction period, the two-way construction period is determined according to the number of strata and the construction time of each stratum; when the two-way construction period is greater than the overall tunnel construction period, the construction work area boundary position and the construction work area boundary position quantity are determined according to the construction time of each stratum, the construction speed of each stratum, the construction length of each stratum and the preset construction period of a single auxiliary tunnel; the target position in the construction work area boundary position is compared with the tunnel length; when the target position in the construction work area boundary position reaches the tunnel length, the construction work area boundary position quantity is taken as the construction work area quantity.
[0111] It should be noted that the work area quantity is obtained by dividing the tunnel according to a certain period of time, and the position calculation is the tunnel length / work area quantity. In the calculation arrangement, the tunnel length can be certainly reached.
[0112] If the two-way construction does not meet the overall construction period, the auxiliary tunnel is considered to be constructed, when the first or last construction work area is calculated, the construction work area boundary position f(w) is as follows:
[0113]
[0114] In formula 1, f(w) is the current construction work area boundary position, f(w+1) is the next construction work area boundary position, t i is the construction time of stratum i, T s is the overall tunnel construction period, V i , l i are respectively the construction speed and length of each stratum in the tunnel range.
[0115] When calculating the remaining construction areas, the construction time of auxiliary tunnels must be taken into account, and the construction period T for each auxiliary tunnel should be set in advance. f If the construction time of the stratum is t i <T s -T f Then compare the construction time t of the next stratum. i+1 and The relationship between them. If the construction time t of the stratum... i >T s -T f Then it can be determined that there is a construction zone interface at the location of the i-th stratum, and its specific location is... The formula for calculating the location of the work area is as follows:
[0116]
[0117] In Equation 2, f(w) represents the current construction zone boundary position, f(w+1) represents the next construction zone boundary position, and t i T is the construction time for stratum i. s For the overall construction period of the tunnel, T f For the construction period of a single auxiliary tunnel, V i l i These represent the construction speed and length of each stratum within the tunnel area.
[0118] like Figure 6 As shown, Figure 6 This is a schematic diagram showing the connection point of the construction work area. The tunnel is divided into multiple construction work areas, and the construction period for each work area is t. The boundary of the construction work area is the connection point of the construction work area.
[0119] By traversing all geological strata within the tunnel, the number of iterations w (i.e., the number of construction work zone boundaries) and the value of f(w) can be obtained. The maximum value of f(w) can then be determined in relation to the tunnel length L. s Relationship, if f(w) < L s If the condition is met, the next iteration of the loop is required; otherwise, the loop is stopped. In this case, w represents the number of construction zones.
[0120] In a specific implementation, a certain tunnel is 14.116 km long, and the tunnel construction control period is 39 months. There are 8 strata in the tunnel range, and the tunnel construction speed and length in each strata are shown in Table 1. Table 1 is a table of construction information of each strata in the tunnel range, which includes the surrounding rock grade, construction speed (m / month), length (m), and event (month). For example, when the surrounding rock grade is 5, the construction speed is 65, the length is 512, and the time is 7.88. The initial construction period of the auxiliary tunnel is about 1.5 months, the starting mileage of the entrance is DK279+314, and after calculation, the preliminary construction work area is obtained, the number of which is 3, and the number of preliminary construction work area boundaries is 2, as shown in Figure 7 Figure 7 which is a schematic diagram of the number of preliminary construction work areas. The number of preliminary work areas is odd, so the number of auxiliary tunnels is 1, and the optimized construction work area is 28.8 months, which is less than the construction period of 39 months and meets the requirements. According to the number of auxiliary tunnels and the recalculated construction period, the position of the auxiliary tunnel is obtained, as shown in Figure 8 Figure 8 which is a schematic diagram of the position of the auxiliary tunnel and the construction work area. According to the calculation, the distance between the auxiliary tunnel and the starting entrance is 6.581Km, the mileage is DK285+895, and the positions of the two construction work areas are 2.755Km and 10.36Km, respectively, and the mileages are DK282+069 and DK289+674, respectively. The above data are all less than the total length of the tunnel 14.116Km, which meets the design requirements. The actual auxiliary tunnel construction period of 4.5 months is input at the position, and the updated auxiliary tunnel position is updated, as shown in Figure 9 Figure 9 which is a schematic diagram of the updated auxiliary tunnel and the position of the construction work area. After calculation, the actual construction period is 30.3 months, which is less than the required construction period of 39 months. The distance between the auxiliary tunnel and the starting entrance is 6.581Km, the mileage is DK285+895, and the positions of the two construction work areas are 2.98Km and 10.22Km, respectively, and the mileages are DK282+294 and DK289+534, respectively. The above data are all less than the total length of the tunnel 14.116Km, which meets the design requirements.
[0121] Table 1
[0122]
[0123] In this embodiment, the construction time of each strata is determined according to the tunnel engineering data, so as to determine whether an auxiliary tunnel needs to be set, and then the number of construction work areas is determined, which improves the accuracy of the number of construction work areas and further improves the design efficiency of the auxiliary tunnel scheme.
[0124] It should be noted that the above examples are only used for understanding the present application and do not constitute a limitation on the auxiliary tunnel center mileage determination method based on group optimization of the present application. More forms of simple transformation based on this technical concept are within the protection scope of the present application.
[0125] The present application also provides an auxiliary tunnel center mileage determination device based on group optimization, which refers to Figure 10 , and the auxiliary tunnel center mileage determination device based on group optimization comprises:
[0126] An acquisition module 10 is configured to acquire tunnel engineering data and determine the number of construction work areas according to the tunnel engineering data.
[0127] A determination module 20 is configured to determine a tunnel reference construction period under an auxiliary tunnel based on the number of construction work areas.
[0128] The determination module 20 is further configured to determine an initial center mileage of the auxiliary tunnel based on the tunnel reference construction period.
[0129] An optimization module 30 is configured to acquire a tunnel actual construction period under the auxiliary tunnel and optimize the initial center mileage based on the tunnel actual construction period to obtain a target center mileage of the auxiliary tunnel.
[0130] The present embodiment provides an auxiliary tunnel center mileage determination device based on group optimization. The present embodiment first acquires tunnel engineering data and determines the number of construction work areas according to the tunnel engineering data to improve the accuracy of the number of construction work areas. The tunnel reference construction period under the auxiliary tunnel is determined based on the number of construction work areas, which can quickly and accurately determine the tunnel reference construction period. The initial center mileage of the auxiliary tunnel is determined based on the tunnel reference construction period to improve the optimization efficiency. The tunnel actual construction period under the auxiliary tunnel is acquired, and the initial center mileage is optimized based on the tunnel actual construction period to obtain the target center mileage of the auxiliary tunnel, which can quickly and accurately locate the center mileage of the auxiliary tunnel, thereby effectively improving the auxiliary tunnel scheme design efficiency.
[0131] As can be seen from the above, the present embodiment determines the reference construction period by determining the number of construction work areas, thereby determining the initial center mileage and optimizing it to obtain the target center mileage. The initial center mileage is quickly determined based on the number of construction work areas and is continuously optimized, which can quickly and accurately locate the center mileage of the auxiliary tunnel, overcomes the technical defect of low auxiliary tunnel scheme design efficiency, and can effectively improve the auxiliary tunnel scheme design efficiency.
[0132] Optionally, the acquisition module 10 is further configured to determine a tunnel overall construction period, a construction speed of each stratum within the tunnel, and a construction length of each stratum according to the tunnel engineering data; determine a construction time of each stratum according to the construction speed of each stratum and the construction length of each stratum; and determine a construction work area quantity according to the construction time of each stratum and the tunnel overall construction period.
[0133] Optionally, the acquisition module 10 is further configured to determine a stratum quantity within the tunnel and a tunnel length according to the tunnel engineering data; determine a one-way construction period according to the stratum quantity and the construction time of each stratum; and determine a construction work area quantity according to the one-way construction period and the tunnel length.
[0134] Optionally, the acquisition module 10 is further configured to, when the one-way construction period is greater than the tunnel overall construction period, determine a two-way construction period according to the stratum quantity and the construction time of each stratum; when the two-way construction period is greater than the tunnel overall construction period, determine a construction work area boundary position and a construction work area boundary position quantity according to the construction time of each stratum, the construction speed of each stratum, the construction length of each stratum, and a preset construction period of a single auxiliary tunnel; compare a target position in the construction work area boundary position with the tunnel length; and when the target position in the construction work area boundary position reaches the tunnel length, take the construction work area boundary position quantity as the construction work area quantity.
[0135] Optionally, the determination module 20 is further configured to determine an auxiliary tunnel quantity based on the construction work area quantity; determine a construction time of each construction work area according to the auxiliary tunnel quantity; and determine a tunnel reference construction period under the auxiliary tunnel according to the construction time of each construction work area.
[0136] Optionally, the determination module 20 is further configured to determine a boundary mileage of each construction work area according to the tunnel reference construction period; acquire an index number at the boundary mileage and perform an odd-even judgment according to the index number; and when the index number is odd, take the boundary mileage as an initial center mileage of the auxiliary tunnel.
[0137] Optionally, the optimization module 30 is further configured to compare the tunnel actual construction period with the tunnel reference construction period; when the tunnel reference construction period is greater than the tunnel actual construction period, update the auxiliary tunnel quantity until a tunnel reference construction period corresponding to an updated auxiliary tunnel quantity is less than or equal to the tunnel actual construction period, to obtain a target auxiliary tunnel quantity; determine a tunnel target construction period according to the target auxiliary tunnel quantity; and determine a target center mileage of the auxiliary tunnel according to the tunnel target construction period.
[0138] The application provides an auxiliary tunnel center mileage determination device based on group optimization. The auxiliary tunnel center mileage determination device based on group optimization can solve the technical problem of auxiliary tunnel center mileage determination based on group optimization. Compared with the prior art, the auxiliary tunnel center mileage determination device based on group optimization has the same beneficial effects as the auxiliary tunnel center mileage determination method based on group optimization, and other technical features of the auxiliary tunnel center mileage determination device based on group optimization are the same as those of the auxiliary tunnel center mileage determination method based on group optimization. Details are not repeated here.
[0139] The application provides an auxiliary tunnel center mileage determination device based on group optimization. The auxiliary tunnel center mileage determination device based on group optimization can solve the technical problem of auxiliary tunnel center mileage determination based on group optimization. Compared with the prior art, the auxiliary tunnel center mileage determination device based on group optimization has the same beneficial effects as the auxiliary tunnel center mileage determination method based on group optimization, and other technical features of the auxiliary tunnel center mileage determination device based on group optimization are the same as those of the auxiliary tunnel center mileage determination method based on group optimization. Details are not repeated here.
[0140] Reference is made below to Figure 11 The auxiliary tunnel center mileage determination device based on group optimization shown in the drawing is only an example and should not limit the functions and use range of the application. Figure 11 The auxiliary tunnel center mileage determination device based on group optimization shown in the drawing is only an example and should not limit the functions and use range of the application.
[0141] As Figure 11As shown, the tunnel centerline determination device based on the application of optimization can include a processing device 1001 (e.g., a central processing unit, a graphics processing unit, etc.) that can perform various appropriate actions and processes according to programs stored in a read-only memory (ROM) 1002 or loaded from a storage device 1003 into a random access memory (RAM) 1004. In the RAM 1004, various programs and data required for the operation of the tunnel centerline determination device based on the application of optimization are also stored. The processing device 1001, the ROM 1002, and the RAM 1004 are connected to each other through a bus 1005. An input / output (I / O) interface 1006 is also connected to the bus. Generally, the following systems can be connected to the I / O interface 1006: input devices 1007 including, for example, a touch screen, a touch pad, a keyboard, a mouse, an image sensor, a microphone, an accelerometer, a gyroscope, etc.; output devices 1008 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; the storage device 1003 including, for example, a magnetic tape, a hard disk, etc.; and a communication device 1009. The communication device 1009 can allow the tunnel centerline determination device based on the application of optimization to communicate wirelessly or by wire with other devices to exchange data. Although the tunnel centerline determination device based on the application of optimization is shown with various systems, it should be understood that all of the shown systems are not required to be implemented or possessed. More or fewer systems can be alternatively implemented or possessed.
[0142] In particular, according to embodiments of the present disclosure, the processes described above with reference to the flowcharts can be implemented as a computer software program. For example, embodiments of the present disclosure include a computer program product comprising a computer program carrying out the program codes for performing the methods shown in the flowcharts carried on a computer readable medium. In such embodiments, the computer program can be downloaded and installed from a network through a communication device, or installed from the storage device 1003, or installed from the ROM 1002. When the computer program is executed by the processing device 1001, the above-mentioned functions defined in the methods of the embodiments of the present disclosure are performed.
[0143] The auxiliary tunnel center mileage determination device based on group optimization provided in the application adopts the auxiliary tunnel center mileage determination method based on group optimization in the above embodiment, and can solve the technical problem of auxiliary tunnel center mileage determination based on group optimization. Compared with the prior art, the auxiliary tunnel center mileage determination device based on group optimization provided in the application has the same beneficial effects as the auxiliary tunnel center mileage determination method based on group optimization provided in the above embodiment, and other technical features in the auxiliary tunnel center mileage determination device based on group optimization are the same as the features disclosed in the previous embodiment method, which will not be repeated here.
[0144] It should be understood that parts of the present application can be realized by hardware, software, firmware or a combination thereof. In the description of the above embodiments, specific features, structures, materials or characteristics can be combined in any one or more embodiments or examples in a suitable manner.
[0145] The above is merely specific implementation of the present application, but the protection scope of the present application is not limited thereto, any person skilled in the art can easily think of changes or replacements within the technical scope disclosed in the present application, which should be covered in the protection scope of the present application. Therefore, the protection scope of the present application should be subject to the protection scope of the claims.
[0146] The present application provides a computer readable storage medium having computer readable program instructions (i.e. computer programs) stored thereon, the computer readable program instructions being used to execute the auxiliary tunnel center mileage determination method based on group optimization in the above embodiment.
[0147] The computer readable storage medium provided in the application may, for example, be a U disk, but is not limited to an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, system, or device, or any combination of the above. More specific examples of the computer readable storage medium may include, but are not limited to, an electrical connection with one or more conductive wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present embodiment, the computer readable storage medium may be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, system, or device. The program code contained on the computer readable storage medium can be transmitted by any suitable medium, including but not limited to an electrical wire, an optical cable, an RF (Radio Frequency), and the like, or any suitable combination of the above.
[0148] The computer readable storage medium described above can be included in the auxiliary tunnel center line determination device based on group optimization, or can exist separately and not be assembled into the auxiliary tunnel center line determination device based on group optimization.
[0149] The computer readable storage medium described above carries one or more programs, which, when executed by the auxiliary tunnel center line determination device based on group optimization, cause the auxiliary tunnel center line determination device based on group optimization to: acquire tunnel engineering data, and determine the number of construction work areas according to the tunnel engineering data; determine the tunnel reference construction period under the auxiliary tunnel based on the number of construction work areas; determine the initial center line of the auxiliary tunnel based on the tunnel reference construction period; acquire the actual tunnel construction period under the auxiliary tunnel, and optimize the initial center line based on the actual tunnel construction period to obtain the target center line of the auxiliary tunnel.
[0150] Computer program code for carrying out operations of the present application can be written in any combination of one or more programming languages, including an object oriented programming language such as Java, Smalltalk, C++ or the like and conventional procedural programming languages, such as the "C" programming language or similar programming languages. The program code can execute entirely on the user's computer, partly on the user's computer, as a stand-alone software package, partly on the user's computer and partly on a remote computer or entirely on the remote computer or server. In the latter scenario, the remote computer can be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or the connection can be made to an external computer (for example, through the Internet using an Internet Service Provider).
[0151] The flow diagrams and the block diagrams in the drawings are illustrations of architectures, functionalities, and operations of possible implementations of systems, methods, and computer program products according to various embodiments of the present application. In this regard, each block in the flow diagrams or block diagrams can represent a module, a segment, or a portion of code, which comprises one or more executable instructions for implementing the specified logical function(s). It should also be noted that in some alternative implementations, the functions noted in the blocks can occur out of the order noted in the figures. For example, two blocks shown in succession may, in fact, be executed substantially concurrently or the blocks may
[0152] The modules involved in the embodiments of the present application can be implemented in the form of software or in the form of hardware. In some cases, the name of the module does not constitute a limitation on the module itself.
[0153] The readable storage medium provided by the present application is a computer readable storage medium, which stores computer readable program instructions (i.e., a computer program) for executing the above-mentioned auxiliary tunnel center mileage determination method based on group optimization. The computer readable program instructions can solve the technical problem of auxiliary tunnel center mileage determination based on group optimization. Compared with the prior art, the computer readable storage medium provided by the present application has the same beneficial effects as the auxiliary tunnel center mileage determination method based on group optimization provided by the above-mentioned embodiments. Details are not repeated here.
[0154] The application also provides a computer program product comprising a computer program which, when executed by a processor, implements the steps of the method for determining the auxiliary tunnel centerline mileage based on group optimization as described above.
[0155] The computer program product provided by the application can solve the technical problem of determining the auxiliary tunnel centerline mileage based on group optimization. Compared with the prior art, the beneficial effects of the computer program product provided by the application are the same as those of the method for determining the auxiliary tunnel centerline mileage based on group optimization provided by the above-mentioned embodiments, and are not described here.
[0156] The above only describes some embodiments of the application, and does not limit the patent scope of the application. Any equivalent structural transformation made by using the content of the application specification and drawings, or direct / indirect application in other related technical fields is included in the patent protection scope of the application.
Claims
1. A method for determining the centerline of a tunnel based on the optimization of the application of a group, characterized in that, The method comprises: acquiring tunnel engineering data and determining a construction work area quantity according to the tunnel engineering data; determining a tunnel reference construction period under an auxiliary tunnel based on the construction work area quantity; determining an initial center mileage of the auxiliary tunnel based on the tunnel reference construction period; the determination of the initial center mileage of the auxiliary tunnel based on the tunnel reference construction period comprises: determining a demarcation mileage of each construction work area according to the tunnel reference construction period; acquiring an index number at the demarcation mileage and performing an odd-even judgment according to the index number; when the index number is odd, taking the demarcation mileage as the initial center mileage of the auxiliary tunnel; acquiring a tunnel actual construction period under the auxiliary tunnel and optimizing the initial center mileage based on the tunnel actual construction period to obtain a target center mileage of the auxiliary tunnel; the optimization of the initial center mileage based on the tunnel actual construction period to obtain the target center mileage of the auxiliary tunnel comprises: comparing the tunnel actual construction period with the tunnel reference construction period; when the tunnel reference construction period is greater than the tunnel actual construction period, updating the auxiliary tunnel quantity until a tunnel reference construction period corresponding to an updated auxiliary tunnel quantity is less than or equal to the tunnel actual construction period to obtain a target auxiliary tunnel quantity; determining a tunnel target construction period according to the target auxiliary tunnel quantity; determining a target center mileage of the auxiliary tunnel according to the tunnel target construction period.
2. The method of claim 1, wherein, the determination of the construction work area quantity according to the tunnel engineering data comprises: determining a tunnel overall period, a construction speed of each stratum within a tunnel range and a construction length of each stratum according to the tunnel engineering data; determining a construction time of each stratum according to the construction speed of each stratum and the construction length of each stratum; determining the construction work area quantity according to the construction time of each stratum and the tunnel overall period.
3. The method of claim 2, wherein, the determination of the construction work area quantity according to the construction time of each stratum and the tunnel overall period comprises: determining a stratum quantity within the tunnel and a tunnel length according to the tunnel engineering data; determining a one-way construction period according to the stratum quantity and the construction time of each stratum; determining the construction work area quantity according to the one-way construction period and the tunnel overall period.
4. The method of claim 3, wherein, the determination of the construction work area quantity according to the one-way construction period and the tunnel length comprises: when the one-way construction period is greater than the tunnel overall period, determining a two-way construction period according to the stratum quantity and the construction time of each stratum; when the two-way construction period is greater than the tunnel overall period, determining a construction work area demarcation position and a construction work area demarcation position quantity according to the construction time of each stratum, the construction speed of each stratum, the construction length of each stratum and a preset construction period of a single auxiliary tunnel; comparing a target position in the construction work area demarcation position with the tunnel length; when the target position in the construction work area demarcation position reaches the tunnel length, taking the construction work area demarcation position quantity as the construction work area quantity.
5. The method of claim 1, wherein, the determination of the tunnel reference construction period under the auxiliary tunnel based on the construction work area quantity comprises: determine the number of auxiliary tunnels based on the number of construction areas; determine the construction time of each construction area according to the number of auxiliary tunnels; determine the tunnel reference construction period under the auxiliary tunnel according to the construction time of each construction area.
6. A device for determining the center mileage of an auxiliary tunnel based on construction organization optimization, characterized in that, The auxiliary tunnel center mileage determination device based on construction optimization comprises: an acquisition module configured to acquire tunnel engineering data and determine the number of construction areas according to the tunnel engineering data; a determination module configured to determine the tunnel reference construction period under the auxiliary tunnel based on the number of construction areas; The determination module is further configured to determine the initial center mileage of the auxiliary tunnel based on the tunnel reference construction period. The determination module is further configured to determine the demarcation mileage of each construction area according to the tunnel reference construction period, acquire the index number at the demarcation mileage, and perform odd-even judgment according to the index number; when the index number is odd, the demarcation mileage is taken as the initial center mileage of the auxiliary tunnel. An optimization module configured to acquire the actual construction period of the tunnel under the auxiliary tunnel, and optimize the initial center mileage based on the actual construction period of the tunnel to obtain the target center mileage of the auxiliary tunnel. The optimization module is further configured to compare the actual construction period of the tunnel with the tunnel reference construction period; when the tunnel reference construction period is greater than the actual construction period of the tunnel, update the number of auxiliary tunnels until the tunnel reference construction period corresponding to the updated number of auxiliary tunnels is less than or equal to the actual construction period of the tunnel to obtain the target number of auxiliary tunnels; determine the tunnel target construction period according to the target number of auxiliary tunnels; and determine the target center mileage of the auxiliary tunnel according to the tunnel target construction period.
7. A device for assisting in the determination of the centerline distance of a tunnel based on the optimization of the application of a group, characterized in that, The auxiliary tunnel center mileage determination device based on construction optimization comprises a memory, a processor, and an auxiliary tunnel center mileage determination program based on construction optimization stored on the memory and executable on the processor, which is configured to implement the auxiliary tunnel center mileage determination method based on construction optimization according to any one of claims 1 to 5.
8. A storage medium, characterized by The storage medium stores an auxiliary tunnel center mileage determination program based on construction optimization, which is executed by the processor to implement the auxiliary tunnel center mileage determination method based on construction optimization according to any one of claims 1 to 5.
Citation Information
Patent Citations
Method and system for evaluating main tunnel construction efficiency of tunnel auxiliary tunnel
CN116703653A
Tunnel excavation wall face development display, display method and display program
JP2011001698A