A three-dimensional survey and design method and system for water conservancy and hydropower projects based on GGB
By integrating GIS, GIM, and BIM data, we build a GGB data center, establish 3D real scenes and geological models, combine BIM technology to design hydraulic buildings, and dynamically update them to solve the data fusion and collaborative design of 3D survey and design in water conservancy and hydropower projects. It has realized the deep integration design of underground, surface and above ground, and improved the design accuracy and efficiency.
Patent Information
- Application Number
- CN202410855399.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-28
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-06-28
AI Technical Summary
There is a lack of comprehensive analysis and utilization of three-dimensional geological models in the existing water conservancy and hydropower engineering survey and design. The barriers between GIM, GIS, and BIM data structures have not been broken down, resulting in survey and design only staying at the model level without realizing deep integration and dynamic update of data. , it is impossible to build a full-process three-dimensional collaborative design technology system.
By building a GGB data center, integrating GIS, GIM, and BIM data, using GIS data to build a three-dimensional real-life model, building a three-dimensional geological model based on GIM data, combining BIM technology for hydraulic building model design, and dynamically updating the three-dimensional geological model through geological survey and optimize the design plan to form a three-dimensional survey and design technology system for underground, surface and above ground.
It realizes a three-dimensional survey and design that integrates underground, surface and above-ground depth, and is suitable for three-dimensional collaborative design of water conservancy and hydropower projects. The ideas are clear and the operation is simple, which improves the accuracy and efficiency of the design.
Smart Images

Figure CN118427946B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of geological three-dimensional modeling, and in particular to a three-dimensional survey and design method and system for water conservancy and hydropower engineering based on GGB. Background Art
[0002] Geological survey of water conservancy and hydropower engineering is the foundation of engineering design. The three-dimensional geological model established based on GIM (Geotechnical Information Model) technology, combined with the engineering experience of designers, fully adapts to and utilizes natural engineering geological conditions to design hydraulic structures, which is the underlying logic of forward design of water conservancy and hydropower engineering. However, in the current three-dimensional collaborative design of the entire process of water conservancy and hydropower engineering survey and design, most disciplines still focus on reverse modeling or "re-modeling", and forward three-dimensional design lacks comprehensive analysis and utilization of three-dimensional geological models.
[0003] There are four main reasons for this problem: there is a lack of unified management and application of multi-source heterogeneous and polymorphic data from multiple survey and design disciplines, and the transmission of data streams for the entire professional process has not been fully realized from data collection, storage, management, analysis, and mining; the deep integration of three-dimensional geological models (GIM models), GIS data, and hydraulic three-dimensional building models (BIM models) lacks the comprehensive utilization of GIM models and engineering exploration data; the barriers between the three data structures of GIM, GIS, and BIM have not been broken, and the spatial topological relationship between models is weakly correlated; the technical route and process of three-dimensional forward design for all disciplines and the entire process, which uses GIS to provide three-dimensional design scenarios, GIM to provide basic data for design, and BIM design as the core, has not been perfected.
[0004] In addition, in the current 3D collaborative design of water conservancy and hydropower projects, the 3D designs of GIM, GIS, and BIM are basically completed independently, and then through coordinate transformation and coordinate registration, the models of the three are assembled, collision checked, excavation volume calculated, and 3D visualized in the same coordinate system, which is essentially a collaborative design at the model level. Therefore, the existing 3D collaborative design of the entire survey and design process only stays at the model level, and the GIM, GIS, and BIM models cannot be dynamically updated in linkage. The GIM, GIS, and BIM data centers have not yet been built to complete the deep integration, analysis, and mining of survey and design data, and the GGB technology system of "data-technology-model-scenario application" of GIM, GIS, and BIM has not yet been formed to serve the survey and design work throughout the process.
[0005] The reason for this problem is that the design of water conservancy and hydropower projects is different from that of other industries and is strongly restricted by engineering geological conditions. In three-dimensional collaborative design, the basic supporting role of GIM model data in BIM three-dimensional design has not been fully utilized, and the GIM information in GIS data has not been fully mined. The multi-temporal data of GIM, GIS, and BIM have not yet been formed into a data center serving three-dimensional survey and design.
[0006] Therefore, there is an urgent need for a three-dimensional survey and design method and system for water conservancy and hydropower projects based on GGB, which can deeply integrate the underground, surface and ground to construct a three-dimensional survey and design technology system of underground, surface and ground. It is suitable for the three-dimensional collaborative design of water conservancy and hydropower project survey and design, with clear ideas and easy operation. Summary of the invention
[0007] In order to solve the above technical problems, the present invention provides a three-dimensional survey and design method and system for water conservancy and hydropower projects based on GGB, which can deeply integrate underground, surface and ground to construct a three-dimensional survey and design technical system of underground, surface and ground, and is suitable for three-dimensional collaborative design of survey and design of water conservancy and hydropower projects, with clear ideas and easy operation.
[0008] The present invention provides a three-dimensional survey and design method for water conservancy and hydropower projects based on GGB, comprising the following steps:
[0009] S1. Determine the research area and engineering stage for the survey and design of water conservancy and hydropower engineering projects;
[0010] S2. Build a GGB data center, obtain engineering data in the study area, and store the engineering data in the GGB data center after data preprocessing; engineering data includes GIS data, GIM data, BIM data and public data;
[0011] S3, using the three-dimensional real scene model in the GIS data to plot geological boundaries and extract geological occurrence information, and store the geological boundaries and geological occurrence information in the GGB data center;
[0012] S4, extract the geological boundary and geological occurrence information of the GGB data center, and establish a three-dimensional geological model through GIM technology data drive;
[0013] S5. Based on the 3D real scene model and 3D geological model, the 3D hydraulic building model is arranged through BIM technology to obtain preliminary design results;
[0014] S6. Conduct geological surveys in the study area, dynamically update the three-dimensional geological model through GIM technology based on the survey results, optimize the design plan through BIM technology, and obtain the final design results.
[0015] Further, S1, the modeling content and modeling accuracy are determined according to the research area and engineering stage of the construction project, including:
[0016] S11. Determine the research area: The research area is divided into regional scope, project area scope and building scope according to the size of the scope;
[0017] S12. Determine the engineering stages: The engineering stages from the shallowest to the most advanced are planning stage, project proposal stage, feasibility study stage, preliminary design stage, bidding design stage, and construction detailed design stage;
[0018] S13. Determine the target modeling accuracy based on the study area and engineering stage. The smaller the study area, the higher the target modeling accuracy. The deeper the engineering stage, the higher the target modeling accuracy.
[0019] Furthermore, in S2,
[0020] GIS data includes: UAV oblique photography pictures, 3D real scene models, digital elevation models, digital orthophotos, and geological remote sensing images;
[0021] GIM data includes: regional geological maps, point data, line data, surface data, and volume data for building three-dimensional geological models;
[0022] BIM data includes: BIM component library, BIM structural parameters;
[0023] Public data includes: metadata and project management data.
[0024] Furthermore, in S2, data preprocessing includes: vectorization, coordinate registration, and coordinate transformation.
[0025] Furthermore, in S3, the three-dimensional real scene model in the GIS data is used to map geological boundaries and extract geological occurrence information, including:
[0026] S31. Establish a 3D real scene model through GIS technology based on engineering data and target modeling accuracy;
[0027] S32, judging whether the modeling accuracy of the 3D real scene model reaches the target modeling accuracy according to the spatial position, geometric shape, size and topological relationship of the 3D real scene model; if so, continuing to step S33, otherwise readjusting the 3D real scene model;
[0028] S33. Mark geological boundaries in the three-dimensional real-scene model and extract geological occurrence information; wherein the geological boundaries include cover boundary, fault boundary, and stratum boundary, and the geological occurrence information includes the strike, dip, and inclination of the rock strata.
[0029] Furthermore, S5, based on the 3D real scene model and 3D geological model, arranged the hydraulic 3D building model through BIM technology, and obtained the preliminary design results including:
[0030] S51, analyzing the geological condition information displayed by the three-dimensional real scene model and the three-dimensional geological model, and determining a preliminary design scheme in combination with the engineering design scale; wherein the preliminary design scheme includes the type, design parameters, layout method and layout location of the hydraulic three-dimensional building model;
[0031] S52. Based on the preliminary design plan, use BIM technology to design the hydraulic three-dimensional building model;
[0032] If the hydraulic 3D building model is an existing 3D building model in the BIM component library, it can be directly selected from the BIM component library;
[0033] If the hydraulic 3D building model is a 3D building model that is not in the BIM component library, a 3D building model corresponding to the hydraulic building is generated according to the type and design parameters in the preliminary design plan;
[0034] S53. The hydraulic three-dimensional building model is placed at the target location through layout to obtain preliminary design results.
[0035] Further, S6, geological surveys were conducted in the study area, and the three-dimensional geological model was dynamically updated through GIM technology based on the survey results. The design scheme was optimized through BIM technology, and the final design results included:
[0036] S61. Carry out geological survey work according to the research area and engineering stage, obtain geological survey data, and dynamically update the three-dimensional geological model using GIM technology in combination with geological survey data; the means of geological survey include geological mapping, drilling exploration, physical detection, and geological test analysis;
[0037] S62, extracting updated geological condition information according to the dynamically updated three-dimensional geological model, and analyzing and determining the engineering parts that need to be adjusted in the preliminary layout plan according to the updated geological condition information;
[0038] S63. Based on the analysis and judgment results of S62, use BIM technology to adjust the type, design parameters, layout method and layout position of the hydraulic three-dimensional building model to obtain the final design results.
[0039] The present invention also provides a three-dimensional survey and design system for water conservancy and hydropower engineering based on GGB, which is used to execute any one of the three-dimensional survey and design methods for water conservancy and hydropower engineering based on GGB described above, and the system includes the following modules:
[0040] The survey and design determination module is used to determine the research area and engineering stage of the survey and design of water conservancy and hydropower engineering projects;
[0041] The data acquisition module is connected to the survey and design determination module to build the GGB data center, obtain the engineering data of the study area, and store it in the GGB data center after data preprocessing; the engineering data includes GIS data, GIM data, BIM data and public data;
[0042] The 3D real scene model processing module is connected to the data acquisition module and is used to use the 3D real scene model in the GIS data to plot geological boundaries and extract geological occurrence information, and store the geological boundaries and geological occurrence information in the GGB data center;
[0043] The 3D geological model processing module is connected to the data acquisition module to extract the geological boundaries and geological occurrence information of the GGB data center and establish a 3D geological model through GIM technology data drive;
[0044] The three-dimensional building model processing module is connected with the three-dimensional real scene model processing module and the three-dimensional geological model processing module, and is used to arrange the hydraulic three-dimensional building model through BIM technology based on the three-dimensional real scene model and the three-dimensional geological model to obtain preliminary design results;
[0045] The dynamic adjustment module is connected with the 3D geological model processing module and the 3D building model processing module, and is used to conduct geological surveys on the study area, dynamically update the 3D geological model through GIM technology according to the survey results, and optimize the design scheme through BIM technology to obtain the final design scheme.
[0046] The embodiments of the present invention have the following technical effects:
[0047] A GGB data center is built based on GIS data, GIM data and BIM data, a 3D real-life model is established through GIS data, a 3D geological model is established based on the 3D real-life model and GIM data, a preliminary layout plan is generated based on the 3D geological model and BIM data, and the preliminary layout results are dynamically adjusted according to the actual exploration results to obtain the final layout results. This method constructs a three-in-one 3D survey and design technology system for underground, surface and aboveground, deeply integrates underground, surface and aboveground, and is suitable for 3D collaborative design of water conservancy and hydropower engineering survey and design, with clear ideas and easy operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0049] Figure 1 It is a flow chart of a three-dimensional survey and design method for water conservancy and hydropower projects based on GGB provided by an embodiment of the present invention;
[0050] Figure 2 It is a structural schematic diagram of a three-dimensional survey and design system for water conservancy and hydropower engineering based on GGB provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0051] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.
[0052] Figure 1 is a flow chart of a three-dimensional survey and design method for water conservancy and hydropower projects based on GGB provided by an embodiment of the present invention, see Figure 1 , including:
[0053] S1. Determine the research area and engineering phase for survey and design of water conservancy and hydropower engineering projects.
[0054] S11. Determine the study area: The study area is divided into regional scope, project area scope and building scope according to its size.
[0055] S12. Determine the engineering stages: The engineering stages from shallow to deep are planning stage, project proposal stage, feasibility study stage, preliminary design stage, bidding design stage, and construction detailed design stage.
[0056] S13. Determine the target modeling accuracy based on the study area and project stage.
[0057] Specifically, the smaller the scope of the study area, the higher the target modeling accuracy; the deeper the engineering stage, the higher the target modeling accuracy.
[0058] S2. Build the GGB data center, obtain the engineering data of the study area, pre-process the engineering data, and store it in the GGB data center.
[0059] Specifically, the GGB (GIS+GIM+BIM) data center is the core link of the entire business process of three-dimensional survey and design of water conservancy and hydropower projects based on GGB. It stores GIS, GIM, and BIM data and realizes the interaction between GIS, GIM, and BIM data: by developing professional modules, data is read from the GGB data center and processed into GIS, GIM, and BIM models and returned to the GGB data center. The GGB data center establishes a globally unique identifier (GUID) for each project and each model, which is used for the association of the corresponding project and model's own data and the integrated application of the interactive model, realizing horizontal and vertical access to various professional data and models in survey and design, and meeting the work needs of various professions at all stages of the project.
[0060] Furthermore, engineering data includes GIS data, GIM data, BIM data and public data.
[0061] Among them, GIS data include: UAV oblique photography pictures, 3D real scene models, digital elevation models (DEM), digital orthophoto maps (DOM), geological remote sensing images;
[0062] GIM data includes: regional geological maps, point data, line data, surface data, and volume data for building three-dimensional geological models;
[0063] BIM data includes: BIM component library, BIM structural parameters;
[0064] Public data includes: metadata and project management data.
[0065] Furthermore, the engineering data is preprocessed, wherein the data preprocessing includes operations such as vectorization, coordinate alignment, and coordinate transformation.
[0066] S3. Use the three-dimensional real-scene model in the GIS data to mark geological boundaries and extract geological occurrence information, and store the geological boundaries and geological occurrence information in the GGB data center.
[0067] S31. According to the engineering data and target modeling accuracy, a three-dimensional real-scene model is established through GIS technology.
[0068] S32: judging whether the modeling accuracy of the three-dimensional real scene model reaches the target modeling accuracy according to the spatial position, geometric shape, size and topological relationship of the three-dimensional real scene model.
[0069] Specifically, if the target modeling accuracy is achieved, S33 is continued to be executed; if the target modeling accuracy is not achieved, the three-dimensional real scene model is readjusted.
[0070] S33. Mark geological boundaries in the three-dimensional real-scene model and extract geological occurrence information.
[0071] Among them, geological boundaries include cover boundaries, fault boundaries, stratum boundaries, etc., and geological occurrence information includes the strike, dip, and inclination of rock strata.
[0072] Furthermore, other important positions in the three-dimensional real scene model can be annotated with text according to actual conditions.
[0073] For example, such as the lower reservoir in the three-dimensional real-scene model, the purpose of text annotation of other important locations in the three-dimensional real-scene model is to improve the readability of the three-dimensional real-scene model, so that users can easily and accurately obtain information and understand the content expressed by the model when viewing or using the three-dimensional real-scene model.
[0074] S4. Extract the geological boundaries and geological occurrence information of the GGB data center, and establish a three-dimensional geological model through GIM technology data drive.
[0075] Specifically, the geological boundaries, geological occurrence information and other geological data are processed and integrated, and a three-dimensional geological model is established based on the integrated data. Data processing may include operations such as data format conversion, coordinate system one, and data matching to ensure the accuracy and consistency of various data.
[0076] S5. Based on the 3D real-scene model and the 3D geological model, the 3D hydraulic building model is arranged through BIM technology to obtain preliminary design results.
[0077] Among them, the three-dimensional real-scene model can display the terrain and landform features more intuitively. Therefore, combining the three-dimensional real-scene model and the three-dimensional geological model for preliminary design is more efficient and reasonable, and can reduce the number of subsequent optimization and adjustment.
[0078] S51. Analyze the geological condition information displayed by the 3D real-life model and the 3D geological model, and determine the preliminary design plan in combination with the engineering design scale.
[0079] Among them, the preliminary design plan includes the type, design parameters, layout method and layout position of the hydraulic three-dimensional building model; among them, the layout method refers to how the various hydraulic three-dimensional building models are coordinated and arranged.
[0080] S52. Based on the preliminary design plan, use BIM technology to design the three-dimensional model of hydraulic structures.
[0081] Specifically, if the hydraulic three-dimensional building model is a three-dimensional building model already in the BIM component library, it is directly selected from the BIM component library; if the hydraulic three-dimensional building model is a three-dimensional building model not in the BIM component library, the three-dimensional building model corresponding to the hydraulic structure is generated according to the type and design parameters of the hydraulic three-dimensional building model in the preliminary design plan.
[0082] For example, the type of hydraulic three-dimensional building model in the preliminary design plan is a dam, and the design parameters include: the total length of the dam crest is 708m, the dam crest width is 15m, the dam crest elevation is 1381.5m, the maximum dam height is 161.5m, the lowest elevation of the toe plate foundation is 1220.0m, etc.
[0083] S53. The hydraulic three-dimensional building model is placed at the target location through layout to obtain preliminary design results.
[0084] Specifically, based on the preliminary design plan, the three-dimensional building model is rotated, scaled, moved, and placed at a target location to obtain a preliminary design result.
[0085] S6. Conduct geological surveys in the study area, dynamically update the three-dimensional geological model through GIM technology based on the survey results, optimize the design plan through BIM technology, and obtain the final design results.
[0086] S61. Carry out geological survey work according to the study area and engineering stage, obtain geological survey data, and use GIM technology to dynamically update the three-dimensional geological model based on the geological survey data.
[0087] Specifically, the means of geological survey include geological mapping, drilling exploration, physical detection, geological test analysis, etc.
[0088] S62. Extract updated geological condition information based on the dynamically updated three-dimensional geological model, and analyze and determine the engineering parts that need to be adjusted in the preliminary layout plan based on the updated geological condition information.
[0089] For example, when the geological rock mass classification and the physical and mechanical parameters of the rock mass change, the primary support and secondary lining of underground projects such as tunnels need to be adjusted accordingly: rock mass classification and physical and mechanical parameters directly affect the stability and support requirements of underground projects. For example, higher-grade rock mass may require less support, while lower-grade rock mass may require more anchors, shotcrete or other support measures. Different rock mass classifications correspond to different design standards and construction specifications, and the support and lining design needs to be adjusted according to these standards. To ensure safety during construction, support measures must be adjusted according to changes in rock mass conditions to prevent collapse or other accidents.
[0090] When the hydrogeological grid surface is adjusted, the anti-seepage and drainage design of the foundation or building needs to be changed accordingly: changes in hydrogeological conditions will affect groundwater pressure, and the anti-seepage and drainage design needs to be adjusted to adapt to the new water pressure conditions. Adjustments to the hydrogeological grid may change the permeability assessment of soil and rock, affecting the anti-seepage design; changes in groundwater conditions may lead to changes in drainage requirements, and the drainage system needs to be redesigned to ensure effective drainage. Improper anti-seepage and drainage design may cause water damage to the foundation or building, and adjusting the design can prevent water damage from occurring.
[0091] When the geological structure changes, the foundation treatment measures need to be adjusted accordingly: geological structure changes may introduce new geological risks, such as faults and landslides, and the foundation treatment measures need to be adjusted to reduce the risks. Changes in geological structure may lead to uneven settlement, and the settlement differences need to be controlled by adjusting the foundation treatment measures. Changes in geological structure may affect the propagation characteristics of seismic waves, and the foundation design needs to be adjusted to adapt to the earthquake response. The complexity of the geological structure may increase the difficulty of construction, and the foundation treatment measures need to be adjusted to adapt to the construction conditions.
[0092] S63. Based on the analysis and judgment results of S62, use BIM technology to adjust the type, design parameters, layout method and layout position of the hydraulic three-dimensional building model to obtain the final design results.
[0093] In the embodiment of the present invention, a GGB data center is constructed based on GIS data, GIM data and BIM data, a 3D real-life model is established through GIS data, a 3D geological model is established based on the 3D real-life model and GIM data, a preliminary layout plan is generated based on the 3D geological model and BIM data, and the preliminary layout results are dynamically adjusted according to the actual exploration results to obtain the final layout results. The method constructs a three-in-one 3D survey and design technical system for underground, surface and aboveground, deeply integrates underground, surface and aboveground, is suitable for 3D collaborative design of water conservancy and hydropower engineering survey and design, has clear ideas and is easy to operate.
[0094] Figure 2 is a schematic diagram of the structure of a three-dimensional survey and design system for water conservancy and hydropower engineering based on GGB provided by an embodiment of the present invention. The system is used to execute a three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB described in the above embodiment. Figure 2 As shown, the system includes the following modules:
[0095] The survey and design determination module is used to determine the research area and engineering stage of the survey and design of water conservancy and hydropower engineering projects;
[0096] The data acquisition module is connected to the survey and design determination module to build the GGB data center, obtain the engineering data of the study area, and store it in the GGB data center after data preprocessing; the engineering data includes GIS data, GIM data, BIM data and public data;
[0097] The 3D real scene model processing module is connected to the data acquisition module and is used to use the 3D real scene model in the GIS data to plot geological boundaries and extract geological occurrence information, and store the geological boundaries and geological occurrence information in the GGB data center;
[0098] The 3D geological model processing module is connected to the data acquisition module to extract the geological boundaries and geological occurrence information of the GGB data center and establish a 3D geological model through GIM technology data drive;
[0099] The three-dimensional building model processing module is connected with the three-dimensional real scene model processing module and the three-dimensional geological model processing module, and is used to arrange the hydraulic three-dimensional building model through BIM technology based on the three-dimensional real scene model and the three-dimensional geological model to obtain preliminary design results;
[0100] The dynamic adjustment module is connected with the 3D geological model processing module and the 3D building model processing module, and is used to conduct geological surveys on the study area, dynamically update the 3D geological model through GIM technology according to the survey results, and optimize the design scheme through BIM technology to obtain the final design scheme.
[0101] It should be noted that the terms used in the present invention are only for describing specific embodiments, rather than limiting the scope of the present application. As shown in the present specification, unless the context clearly indicates an exception, the words "one", "a", "a kind of" and / or "the" do not specifically refer to the singular, but may also include the plural. The terms "include", "comprise" or any other variant thereof are intended to cover non-exclusive inclusion, so that the process, method or device including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method or device. In the absence of more restrictions, the elements defined by the sentence "include one..." do not exclude the presence of other identical elements in the process, method or device including the elements.
[0102] It should also be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. Unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0103] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the technical solutions of the embodiments of the present invention.
Claims
1. A three-dimensional survey and design method for water conservancy and hydropower projects based on GGB, characterized in that: The steps include: S1. Determine the research area and engineering stage for the survey and design of water conservancy and hydropower engineering projects; S2. Build a GGB data center, obtain engineering data of the study area, perform data preprocessing on the engineering data, and store them in the GGB data center; the engineering data includes GIS data, GIM data, BIM data, and public data; S3, using the three-dimensional real scene model in the GIS data to plot geological boundaries and extract geological occurrence information, and storing the geological boundaries and geological occurrence information in the GGB data center; S4, extracting the geological boundary and geological occurrence information of the GGB data center, and establishing a three-dimensional geological model through GIM technology data drive; S5. Based on the three-dimensional real scene model and the three-dimensional geological model, a hydraulic three-dimensional building model is arranged by using BIM technology to obtain a preliminary design result; S6. Conduct geological survey on the study area, dynamically update the three-dimensional geological model through GIM technology according to the survey results, optimize the design scheme through BIM technology, and obtain the final design results; S61. Conduct geological survey work according to the research area and engineering stage, obtain geological survey data, and dynamically update the three-dimensional geological model using GIM technology in combination with the geological survey data; the means of geological survey include geological mapping, drilling exploration, physical detection, and geological test analysis; S62, extracting updated geological condition information according to the dynamically updated three-dimensional geological model, and analyzing and determining the engineering parts that need to be adjusted in the preliminary layout plan according to the updated geological condition information; S63. Based on the analysis and judgment results of S62, the type, design parameters, layout method and layout position of the hydraulic three-dimensional building model are adjusted using BIM technology to obtain the final design results.
2. The three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB according to claim 1 is characterized in that: S1, determining the modeling content and modeling accuracy according to the research area and engineering stage of the construction project includes: S11. Determine the research area: the research area is divided into regional scope, engineering area scope and building scope according to the scope size; S12. Determine the engineering stages: the engineering stages are, from the shallowest to the most advanced, planning stage, project proposal stage, feasibility study stage, preliminary design stage, bidding design stage, and construction detailed design stage; S13. Determine the target modeling accuracy according to the study area and the engineering stage; the smaller the scope of the study area, the higher the target modeling accuracy; the deeper the engineering stage, the higher the target modeling accuracy.
3. The three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB according to claim 1 is characterized in that: In S2, The GIS data includes: UAV oblique photography pictures, three-dimensional real scene models, digital elevation models, digital orthophotos, and geological remote sensing images; The GIM data includes: regional geological maps, point data, line data, surface data, and volume data for constructing a three-dimensional geological model; The BIM data includes: BIM component library and BIM structural parameters; The public data includes: metadata and project management data.
4. The three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB according to claim 3 is characterized in that: In S2, data preprocessing includes: vectorization, coordinate registration, and coordinate transformation.
5. The three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB according to claim 2 is characterized in that: In S3, the three-dimensional real scene model in the GIS data is used to map geological boundaries and extract geological occurrence information, including: S31, establishing a three-dimensional real scene model through GIS technology according to the engineering data and the target modeling accuracy; S32, judging whether the modeling accuracy of the 3D real scene model reaches the target modeling accuracy according to the spatial position, geometric shape, size and topological relationship of the 3D real scene model; if so, continue to execute S33, otherwise readjust the 3D real scene model; S33, marking geological boundaries in the three-dimensional real-scene model and extracting geological occurrence information; wherein the geological boundaries include cover boundary, fault boundary, and stratum boundary, and the geological occurrence information includes the strike, dip, and inclination of the rock strata.
6. The three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB according to claim 1 is characterized in that: S5, based on the three-dimensional real scene model and the three-dimensional geological model, arranges the hydraulic three-dimensional building model through BIM technology, and obtains preliminary design results including: S51, analyzing the geological condition information displayed by the three-dimensional real scene model and the three-dimensional geological model, and determining a preliminary design scheme in combination with the engineering design scale; wherein the preliminary design scheme includes the type, design parameters, layout method and layout location of the hydraulic three-dimensional building model; S52. Based on the preliminary design plan, use BIM technology to design the hydraulic three-dimensional building model; If the hydraulic three-dimensional building model is a three-dimensional building model already in the BIM component library, it is directly selected from the BIM component library; If the hydraulic three-dimensional building model is a three-dimensional building model not in the BIM component library, a three-dimensional building model corresponding to the hydraulic structure is generated according to the type and design parameters in the preliminary design plan; S53, placing the hydraulic three-dimensional building model at the target position by means of the arrangement method, and obtaining a preliminary design result.
7. A three-dimensional survey and design system for water conservancy and hydropower engineering based on GGB, used to execute a three-dimensional survey and design method for water conservancy and hydropower engineering based on GGB as described in any one of claims 1 to 6, characterized in that: The system includes the following modules: The survey and design determination module is used to determine the research area and engineering stage of the survey and design of water conservancy and hydropower engineering projects; A data acquisition module, connected to the survey and design determination module, is used to build a GGB data center, acquire the engineering data of the study area, and store the engineering data in the GGB data center after data preprocessing; the engineering data includes GIS data, GIM data, BIM data and public data; A three-dimensional real scene model processing module, connected to the data acquisition module, is used to use the three-dimensional real scene model in the GIS data to plot geological boundaries and extract geological occurrence information, and store the geological boundaries and geological occurrence information in the GGB data center; A three-dimensional geological model processing module, connected to the data acquisition module, is used to extract the geological boundary and geological occurrence information of the GGB data center, and establish a three-dimensional geological model through GIM technology data drive; A three-dimensional building model processing module is connected to the three-dimensional real scene model processing module and the three-dimensional geological model processing module, and is used to arrange a hydraulic three-dimensional building model through BIM technology based on the three-dimensional real scene model and the three-dimensional geological model to obtain a preliminary design result; The dynamic adjustment module is connected to the three-dimensional geological model processing module and the three-dimensional building model processing module, and is used to conduct geological surveys on the study area, dynamically update the three-dimensional geological model through GIM technology according to the survey results, and optimize the design scheme through BIM technology to obtain the final design scheme.
Citation Information
Patent Citations
Long tunnel digital twin system and method based on BIM + GIS technology
CN114201798A
Forward planning method, device and equipment for bridge engineering and storage medium
CN115758530A