A method for arranging pressure gauges based on pipe burst analysis in drainage network
By vectorizing the drainage pipe network data and constructing the SWMM model, combined with the burst pipe data and the position of the exhaust valve, the pressure gauge distribution was optimized, solving the problem of unreasonable distribution in the existing technology and achieving more efficient pipe network monitoring. and resource conservation.
Patent Information
- Application Number
- CN202410929556.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2044-07-11
AI Technical Summary
The existing drainage pipe network pressure gauges lack scientific and reasonable methods, resulting in too dense or too sparse distribution, unable to effectively monitor the operation of the pipe network, resulting in a waste of resources and potential safety hazards.
By vectorizing the drainage pipe network data, a SWMM model is constructed, and the pressure gauge point layout is preset and simulated based on the pipe burst data. Combined with the positions of the exhaust valve and small area leakage points, the point layout plan is adjusted to ensure that the pressure gauge can effectively monitor explosions. Manage events.
It improves the intelligent management level of the drainage pipe network, avoids waste of resources, ensures the rationality and accuracy of the pressure gauge layout, can effectively monitor the operation of the pipe network, and enhances safety.
Smart Images

Figure CN118468497B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pressure gauge placement in drainage pipe networks, and in particular to a method for placing pressure gauges based on pipe burst analysis in drainage pipe networks. Background Art
[0002] In recent years, with the accelerating pace of urbanization and the continuous expansion of urban areas, the city's supporting drainage network has also been expanding, and old areas need to update and improve the existing network to adapt to the growing urban scale; the drainage network is also affected by extreme weather, which is prone to cause pipe ruptures, leaks and other hazardous events. This complexity requires the drainage network to be more intelligent and applicable. Real-time monitoring of the network operation enables managers to quickly obtain key information and take necessary measures to reduce the impact of disasters.
[0003] With the development of technology, drainage companies have begun to pay attention to the informatization, digitization and intelligence of drainage pipe networks. The installation of pipe network monitoring meters is the basis for pipe network management. Commonly installed instruments include flow meters, liquid level gauges, water level gauges and pressure gauges. Among them, pressure gauges are indispensable instruments in drainage systems. Pressure gauges have the advantages of high accuracy, easy reading and wide range of use. They can help managers to understand the pressure conditions in the drainage system in a timely manner, realize fine adjustment and optimization of the drainage system, and ensure the normal operation of the system. However, the design and installation positions of pressure gauges are mostly based on manual experience. There is no reasonable and complete distribution plan, which can easily cause the pressure gauges to be distributed too densely, resulting in waste of resources, and the pressure gauges to be distributed too sparsely, resulting in the inability to reasonably monitor the operation of the pipe network.
[0004] Therefore, the existing technology urgently needs a more reasonable method to support the design of the pressure gauge distribution in the drainage network, so as to maximize the use of the pressure gauge and improve the level of safe operation of the network.
[0005] The applicant conducted a detailed search of the prior art and did not find any technical solutions in the prior art related to the drainage network and pressure gauge layout related to the present application.
[0006] Therefore, it is necessary to provide a new technical solution to solve the above technical problems. Summary of the invention
[0007] The present application provides a method for arranging pressure gauges based on drainage pipe network burst analysis, comprising the following steps:
[0008] S1, vectorize the drainage network data to form drainage network vector data; extract pipe burst data from historical pipe burst events, where the pipe burst data includes pipe burst time, pipe burst point location, pipe diameter, and pipe burst area; collect and process the drainage network monitoring data;
[0009] S2, based on the drainage network vector data and drainage network monitoring data in S1, build the SWMM model of the current drainage network operation;
[0010] S3, based on the burst data, calls the SWMM model of the drainage network to simulate the burst, uses the SWMM model to output the pressure value on the node before the burst and the pressure value on the node after the burst, outputs the pressure difference, and arranges and displays it according to the distance from the burst point;
[0011] S4, based on the position of the burst point, the position of the exhaust valve around the burst point, and the pressure difference in S3, the pressure gauge is preset.
[0012] S5, based on the exhaust valve and pipe burst data in S1, pipe burst simulation is performed at different locations and small leakage points in the pipe network to verify the rationality of the preset pressure gauge layout;
[0013] S6, output or adjust the pressure gauge distribution plan according to the pipe burst simulation with different parameters in S5.
[0014] As a preferred solution, the drainage network vector data in S1 includes sewage pipelines, nodes, valves, and pumping stations.
[0015] As a preferred solution, the S1 drainage network monitoring data includes pump station flow, network flow and network liquid level.
[0016] As a preferred solution, the pipe network monitoring data before the pipe burst occurs is processed in S1; and S21 is included between S2 and S3 to correct the SWMM model based on the pipe network monitoring data before the pipe burst occurs.
[0017] As a preferred solution, S3 comprises the following steps:
[0018] S31: Use the pump station flow corresponding to the pipe burst time in S1 to simulate the pipe network operation on the SWMM model, and output the pressure value on the pipe network node when no pipe burst event occurs;
[0019] S32: Use the pipe diameter and pipe area in S1 to simulate pipe bursting and output the node pressure value after pipe bursting;
[0020] S33: Differences are taken between the node pressure values before and after the pipe burst, and a list of pressure differences is outputted from near to far for the surrounding nodes with the pipe burst point as the center.
[0021] As a preferred solution, in S32 , where K is the injection coefficient, is the pipe diameter, A is the pipe area, g is the gravitational acceleration g=9.81 m / s²; the injection coefficient K is input into the SWMM model to simulate the pipe burst, and the SWMM model outputs the node pressure value after the pipe burst.
[0022] As a preferred solution, in S5, when performing pipe burst simulation based on the exhaust valve, according to the formula , calculate the injection coefficient K, where is the exhaust valve diameter, A1 is the leakage area, g is the gravitational acceleration g=9.81 m / s²; the calculated injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the pressure difference before and after the pipe burst to verify the response of the preset pressure gauge points to the pipe burst event.
[0023] As a preferred solution, in S5, when pipe burst simulation is performed at different locations of the pipe network based on the pipe burst data in S1, according to the formula , calculate the injection coefficient K, where K is the injection coefficient, is the pipe diameter, A is the pipe area, g is the gravitational acceleration g=9.81 m / s²; the injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the node pressure value after the pipe burst to verify the response of the preset pressure gauge points to the pipe burst event.
[0024] As a preferred solution, in S5, when simulating a pipe burst based on a small area leak, according to the formula , calculate the injection coefficient K, where K is the injection coefficient, where is the diameter of the small leak, A2 is the area of the small leak, and g is the gravitational acceleration g=9.81 m / s². The injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the node pressure value after the pipe burst to verify the response of the preset pressure gauge points to the pipe burst event.
[0025] As a preferred solution, in S6, when the difference of the pressure gauges output by S5 is greater than 0.5m, it is determined that the pipe burst event can be monitored, and the pressure gauge layout plan is output; when the difference of any pressure gauge output by S5 is less than or equal to 0.5m, it is determined that the pipe burst event cannot be monitored, and the position of the preset pressure gauge layout is adjusted. After the adjustment is completed, S5 is executed in a loop until the difference of the pressure gauges output by S5 is greater than 0.5m.
[0026] As a preferred solution, in S2, the SWMM model includes: pipeline attributes, node attributes, valve attributes, and pump station attributes.
[0027] As a preferred solution, the pipeline attributes include pipeline number, length, pipe diameter, pipeline coordinates, starting node, ending node, starting node bottom elevation, and ending node bottom elevation.
[0028] As a preferred solution, the node attributes include node number, node coordinates, node ground elevation, and node bottom elevation.
[0029] As a preferred solution, the valve attributes include the valve number, the node corresponding to the valve, and the valve diameter.
[0030] As a preferred solution, the pump station attributes include the pump station number, the node corresponding to the pump station, and the water outflow of the pump station.
[0031] The present application constructs a SWMM model of the current operation of the drainage network through drainage network vector data and drainage network monitoring data, simulates the pipe burst of the SWMM model through the pipe burst data, completes the pressure gauge layout, and simulates the pipe burst at different locations and small leakage points in the network through the exhaust valve and the pipe burst data in S1 to verify the rationality of the preset pressure gauges, and finally outputs a reasonable pressure gauge layout. The pipe burst monitoring is performed using the pressure gauges with reasonable layout, which improves the intelligent management level of the drainage network, avoids the waste of resources caused by too many pressure gauges and the inability to reasonably monitor the operation of the network due to too sparse distribution of pressure gauges; ensures the optimal layout, saves resources, and can accurately monitor the pipe burst; preferably, the present application also verifies the SWMM model through the network monitoring data before the pipe burst occurs, so as to improve the accuracy of SWMM model modeling. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a schematic diagram of the method for distributing pressure gauges of the present invention;
[0033] Figure 2 It is a logical schematic diagram of the pressure gauge arrangement of the present invention; DETAILED DESCRIPTION
[0034] The following is combined with Figure 1 and attached Figure 2 The specific implementation of the present invention is described in detail. It should be noted that the specific implementation described here is only used to illustrate and explain the present invention, and is not used to limit the present invention. Embodiment 1
[0035] This embodiment provides a method for arranging pressure gauges based on drainage pipe network burst analysis, including the following steps:
[0036] S1, vectorize the drainage network data to form drainage network vector data; wherein the drainage network vector data includes sewage pipelines, nodes, valves, and pumping stations, and the sewage pipelines include pipeline plan layout CAD drawings and pipeline longitudinal section CAD drawings; specifically, vectorize the CAD drawings of the pipeline network data, extract the data of sewage pipelines, nodes, valves, pumping stations, etc., and supplement and improve the basic data such as node elevation and pipe diameter; extract pipe burst data from historical pipe burst events, wherein the pipe burst data includes pipe burst time, pipe burst point location, pipe burst diameter, and pipe burst area; collect and process the drainage network monitoring data, specifically the pump station flow, pipe network flow, and pipe network liquid level in the drainage network; the drainage network monitoring data involved above The frequency of the time series data is every minute; preferably, in order to train and correct the subsequent SWMM model and improve the accuracy of the model, the drainage network monitoring data before the pipe burst is collected in S1, and the drainage network monitoring data before the pipe burst is processed. Specifically, the sampling frequency of the drainage network monitoring data before the pipe burst is every minute, and the drainage network monitoring data before the pipe burst collected every minute is processed, and the processing includes data cleaning, removal of outliers, smoothing and interpolation, etc. After processing, the data of the fixed time period is taken as a sample, such as: the fixed time period is 24 hours, and the model is subsequently trained and corrected through the monitoring data collected 24 hours before the pipe burst, and the monitoring data includes flow data and liquid level data.
[0037] S2, based on the drainage network vector data and drainage network monitoring data in S1, construct a SWMM model of the current drainage network operation; the main fields used to establish the SWMM model include: pipeline attributes, node attributes, valve attributes, and pump station attributes; wherein, pipeline attributes include pipeline number, length, pipe diameter, pipeline coordinates, starting node, ending node, starting node bottom elevation, and ending node bottom elevation; node attributes include node number, node coordinates, node ground elevation, and node bottom elevation; valve attributes include valve number, valve corresponding node, and valve diameter; pump station attributes include pump station number, pump station corresponding node, pump station water outlet flow, etc.; preferably, S21 is included between S2 and S3, and the SWMM model is corrected based on the network monitoring data before the pipe burst in S1.
[0038] S3, based on the burst data in S1, calls the SWMM model of the drainage network to simulate the burst, uses the SWMM model to output the pressure value on the node before the burst and the pressure value on the node after the burst, outputs the pressure difference, and arranges and displays it according to the distance from the burst point;
[0039] Specifically, S3 includes:
[0040] S31: Use the pump station flow corresponding to the pipe burst time in S1 to simulate the pipe network operation on the SWMM model, and output the pressure value on the pipe network node when no pipe burst event occurs;
[0041] S32: Use the pipe diameter and pipe area in S1 to simulate pipe bursting and output the node pressure value after pipe bursting; more specifically, , where K is the injection coefficient, is the pipe diameter, A is the pipe area, g is the acceleration of gravity g=9.81 m / s², through the pipe diameter , burst area A, gravity acceleration g calculate injection coefficient K, then input injection coefficient K into SWMM model to simulate burst, SWMM model outputs node pressure value after burst;
[0042] S33: Taking the difference of the node pressure values before and after the pipe burst, and outputting a list of pressure difference values of the surrounding nodes from near to far with the pipe burst point as the center;
[0043] S4, based on the position of the pipe burst point in S1, the position of the exhaust valve around the pipe burst point, and the pressure difference in S3, the pressure gauge is preset and arranged; specifically, the preset pressure gauge is placed at a position upstream of the pipe burst point and the exhaust valve and the pressure difference is within the average range; the upstream position is the common upstream of the pipe burst point and the exhaust valve;
[0044] S5, based on the exhaust valve and pipe burst data in S1, pipe burst simulation is performed at different locations and small leakage points in the pipe network to verify the rationality of the preset pressure gauge layout;
[0045] When simulating pipe burst based on the exhaust valve, according to the formula , calculate the injection coefficient K, where, is the exhaust valve diameter, A1 is the leakage area, and g is the gravity acceleration g=9.81 m / s²; the calculated injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the pressure difference before and after the pipe burst to test the response of the preset pressure gauge points to the pipe burst event and determine whether the preset pressure gauge can monitor the pipe burst event.
[0046] When simulating pipe bursts at different locations in the pipe network based on the pipe burst data in S1, according to the formula , calculate the injection coefficient K, where K is the injection coefficient, is the pipe diameter, A is the pipe area, and g is the gravity acceleration g=9.81 m / s²; the injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the node pressure value after the pipe burst to test the response of the preset pressure gauge points to the pipe burst event and determine whether the preset pressure gauge can monitor the pipe burst event.
[0047] When simulating a pipe burst based on a small leak, according to the formula , calculate the injection coefficient K, where K is the injection coefficient, where is the diameter of the small leak, A2 is the area of the small leak, and g is the gravity acceleration g=9.81 m / s²; the injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the node pressure value after the pipe burst to test the response of the preset pressure gauge points to the pipe burst event and determine whether the preset pressure gauge can monitor the pipe burst event.
[0048] S6, according to the pipe burst simulation of different parameters in S5, output or adjust the pressure gauge layout plan; specifically: when the difference values of the pressure gauges output by S5 are all greater than 0.5m, it is determined that the pressure difference values of the preset pressure gauges have an obvious response, and it is determined that the pipe burst event can be monitored, and the pressure gauge layout plan is output; when any difference value of the pressure gauges output by S5 is less than or equal to 0.5m, it is determined that the pressure difference values of the preset pressure gauges do not have an obvious response, and it is determined that the pipe burst event cannot be monitored, and the position of the preset pressure gauge is adjusted. After the adjustment is completed, S5 is executed repeatedly until the difference values of the pressure gauges output by S5 are all greater than 0.5m. Embodiment 2
[0049] This embodiment provides a specific application scenario:
[0050] S1, vector conversion is performed on the drainage network data CAD drawing, and data such as sewage pipelines, nodes, valves, pump stations, etc. are extracted, and basic data such as node elevation and pipe diameter are supplemented and improved; in this embodiment, the node elevation is supplemented according to the elevation data in the pipeline longitudinal section CAD drawing, and the pipe diameter is supplemented according to the pipe diameter data in the pipeline plane layout CAD drawing; the drainage network monitoring data with a sampling frequency of every minute before the pipe burst occurs is processed, and the processing includes data cleaning, removal of outliers, smoothing and interpolation, etc. After pre-processing, the data of a fixed time period is taken as a sample, and the fixed time period in this embodiment is 24 hours; that is, the training and correction of the SWMM model is subsequently performed through the drainage network monitoring data 24 hours before the pipe burst; for extracting pipe burst data in historical pipe burst events, the pipe burst data includes pipe burst time, pipe burst point location, pipe burst diameter, and pipe burst area; the drainage network monitoring data includes pump station flow, pipe network flow, and pipe network liquid level;
[0051] S2, based on the drainage network vector data and drainage network monitoring data in S1, build a SWMM model of the current drainage network operation; the main fields used to build the SWMM model include: pipeline attributes, node attributes, valve attributes, and pump station attributes; among them, pipeline attributes include pipeline number, length, pipe diameter, pipeline coordinates, starting node, ending node, starting node bottom elevation, and ending node bottom elevation; node attributes include node number, node coordinates, node ground elevation, and node bottom elevation; valve attributes include valve number, valve corresponding node, and valve diameter; pump station attributes include pump station number, pump station corresponding node, and pump station water flow;
[0052] S21, correcting the SWMM model based on the drainage network monitoring data before the pipe burst in S1;
[0053] S31: Locate the pump station flow at that time according to the pipe burst time extracted in S1, simulate the pipe network operation on the SWMM model, and output the pressure value on the pipe network node when no pipe burst event occurs;
[0054] S32: Output the node pressure value after the pipe burst according to the pipe burst diameter and pipe burst area extracted in S1; in this embodiment, the pipe burst diameter is 1200mm and the area is 0.0114㎡; according to the formula Calculate the ejection coefficient, i.e. the diameter of the burst tube =1200mm, A=0.0114㎡, gravitational acceleration g=9.81 m / s², the injection coefficient K=125 is calculated; the injection coefficient is input into the SWMM model to simulate the pipe burst, and the node pressure value after the pipe burst is output;
[0055] S33: Calculate the difference between the node pressure values output by the SWMM model before and after the pipe burst, and output a list of pressure differences for the surrounding nodes from near to far with the pipe burst point as the center.
[0056] S4, based on the list output by S33, it can be known that in this embodiment, the node pressure difference after the pipe burst is greater than 4m, and there is an exhaust valve upstream of the pipe burst point. Combined with the distribution of the node pressure difference after the pipe burst, the preset pressure gauge point is placed at the common upstream position of the pipe burst point and the exhaust valve, and the pressure difference is within the mean range;
[0057] S5, pipe burst simulation based on the exhaust valve. In this embodiment, the exhaust valve on the drainage network can drain water to simulate the pipe burst on site and check the response of the preset pressure gauge to the pipe burst event. The diameter of the exhaust valve is known. =200mm, the leakage area is A1=0.1256㎡, according to the formula , calculate the injection coefficient K=343.08, perform pipe burst simulation in the SWMM model, and output the pressure difference before and after the pipe burst. In this embodiment, the output pressure difference is 8.75m;
[0058] Based on the historical pipe burst data, pipe burst simulations were performed at different locations of the pipe network. In this embodiment, the injection coefficient of the historical pipe burst was calculated to be K=125. This injection coefficient value was used to simulate pipe bursts at different locations of the drainage pipe network to obtain the pressure difference of the pressure gauge before and after the pipe burst. The results showed that except for the location 1km away from the sewage treatment plant, the pressure difference at the distribution point was less than 2m when the pipe burst occurred on the pipeline, and when the pipe burst occurred at other locations, the pressure value changes at the distribution points were all greater than 2m.
[0059] A small area leak point burst simulation is performed. In this embodiment, the diameter of the small and medium area leak point is =60mm, the area of the small leakage point is A2=0.0028㎡, through the formula , calculated the injection coefficient K = 30.58, carried out pipe burst simulation at different locations on the pipe network, and output the pressure difference of the pressure gauge, the pressure difference was greater than 0.5m,
[0060] S6, output or adjust the pressure gauge layout plan according to the pipe burst simulation with different parameters in S5; specifically: if the difference of the pressure gauges output by S5 is greater than 0.5m, it is determined that the pipe burst event can be monitored, and the pressure gauge layout plan is output; if any difference of the pressure gauges output by S5 is less than or equal to 0.5m, it is determined that the pipe burst event cannot be monitored, and the position of the preset pressure gauge is adjusted. After the adjustment is completed, S5 is executed repeatedly until the difference of the pressure gauges output by S5 is greater than 0.5m; combined with S5, it can be seen that in this embodiment, the pipe burst simulation is performed based on the exhaust valve, and the preset pressure gauge layout can monitor the occurrence of the pipe burst event in the pipeline; when the pipe burst simulation is performed at different locations of the pipeline network based on the historical pipe burst data, the preset pressure gauge layout can monitor the occurrence of the pipe burst event in the pipeline; when the small area leakage point pipe burst simulation is performed, the preset pressure gauge layout can monitor the occurrence of the pipe burst event in the pipeline, therefore, the pressure gauge layout plan in S4 is directly output, and the workers can install the pressure gauges at the layout locations.
[0061] To sum up, due to the adoption of the above technical scheme, the present application constructs a SWMM model of the current drainage network operation through the network vector data and the drainage network monitoring data, simulates the pipe burst of the SWMM model through the pipe burst data, completes the pressure gauge layout, and simulates the pipe burst at different positions and small leakage points of the network through the exhaust valve and the pipe burst data in S1 to verify the rationality of the preset pressure gauges, and finally outputs a reasonable pressure gauge layout. The pipe burst monitoring is performed using the pressure gauges with reasonable layout, which improves the intelligent management level of the drainage network, avoids the waste of resources caused by too many pressure gauges and the inability to reasonably monitor the operation of the network due to too sparse distribution of pressure gauges; ensures the optimal layout, saves resources, and can accurately monitor the pipe burst; preferably, the present application also verifies the SWMM model through the network monitoring data before the pipe burst occurs, so as to improve the accuracy of SWMM model modeling.
[0062] The various implementation modes of the present application may be arbitrarily combined, and as long as they do not violate the concept of the present application, they should also be regarded as the contents disclosed in the present application.
[0063] A person skilled in the art should understand that the discussion of any of the above embodiments is only exemplary and is not intended to imply that the scope of the disclosure of the embodiments of the present invention (including the claims) is limited to these examples; under the concept of the embodiments of the present invention, the technical features in the above embodiments or different embodiments can also be combined, and there are many other changes in different aspects of the embodiments of the present invention as described above, which are not provided in detail for the sake of simplicity. Therefore, any omissions, modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the embodiments of the present invention should be included in the protection scope of the embodiments of the present invention.
Claims
1. A method for arranging pressure gauges based on drainage pipe network burst analysis, characterized in that: The steps include: S1, vectorize the drainage network data to form drainage network vector data, the drainage network vector data includes sewage pipelines, nodes, valves, pumping stations, sewage pipelines include pipeline plane layout CAD drawings, pipeline longitudinal section CAD drawings; extract pipe burst data from historical pipe burst events, wherein the pipe burst data includes pipe burst time, pipe burst point location, pipe diameter, and pipe burst area; collect and process the drainage network monitoring data, the drainage network monitoring data includes pump station flow, pipe network flow, and pipe network liquid level in the drainage network; S2, based on the drainage network vector data and drainage network monitoring data in S1, build the SWMM model of the current drainage network operation; S3, based on the burst data in S1, calls the SWMM model of the drainage network to simulate the burst, uses the SWMM model to output the pressure value on the node before the burst and the pressure value on the node after the burst, outputs the pressure difference, and arranges and displays it according to the distance from the burst point; S4, based on the position of the pipe burst point in S1, the position of the exhaust valve around the pipe burst point, and the pressure difference in S3, the pressure gauge is preset and arranged; the preset pressure gauge is placed at a position upstream of the pipe burst point and the exhaust valve and where the pressure difference is within the average range; the upstream position is the common upstream of the pipe burst point and the exhaust valve; S5, based on the exhaust valve and pipe burst data, pipe burst simulation is performed at different locations and small leakage points in the pipe network to verify the rationality of the preset pressure gauge layout; When simulating pipe burst based on the exhaust valve, according to the formula , calculate the injection coefficient ,in, is the exhaust valve diameter, is the leak area, g is the gravitational acceleration g=9.81 m / s²; the calculated injection coefficient K is input into the SWMM model to simulate the pipe burst. The SWMM model outputs the pressure difference before and after the pipe burst to test the response of the preset pressure gauge points to the pipe burst event and determine whether the preset pressure gauge can monitor the pipe burst event. When simulating a pipe burst based on a small leak, according to the formula , calculate the injection coefficient ,in, is the injection coefficient, where is the diameter of a small leak. is the area of the small leak, g is the acceleration of gravity g=9.81 m / s²; enter the injection coefficient in the SWMM model Conduct pipe burst simulation, and the SWMM model outputs the node pressure value after the pipe burst, and verifies the response of the preset pressure gauge points to the pipe burst event, and determines whether the preset pressure gauge can monitor the pipe burst event; S6, output or adjust the pressure gauge distribution plan according to the pipe burst simulation with different parameters in S5.
2. The method for arranging pressure gauges based on pipe burst analysis of a drainage network according to claim 1 is characterized in that: The drainage network vector data in S1 includes sewage pipelines, nodes, valves, and pumping stations.
3. The method for arranging pressure gauges based on drainage pipe network burst analysis according to claim 1 is characterized in that: In the S1, the pipe network monitoring data before the pipe burst occurs is processed; between the S2 and S3, there is S21, which corrects the SWMM model based on the pipe network monitoring data before the pipe burst occurs.
4. The method for arranging pressure gauges based on drainage pipe network burst analysis according to claim 1 is characterized in that: The S3 comprises the following steps: S31: Perform pipe network operation simulation on the SWMM model using the pump station flow corresponding to the pipe burst time, and output the pressure value on the pipe network node when no pipe burst event occurs; S32: Perform pipe burst simulation based on pipe burst diameter and pipe burst area, and output node pressure value after pipe burst; S33: Calculate the difference between the node pressure values before and after the pipe burst, and output a list of pressure difference values of the surrounding nodes from near to far with the pipe burst point as the center.
5. The method for arranging pressure gauges based on drainage pipe network burst analysis according to claim 4 is characterized in that: In the S32 ,in, is the injection coefficient, is the burst pipe diameter, is the burst area, g is the gravitational acceleration g=9.81 m / s²; enter the injection coefficient in the SWMM model Perform pipe burst simulation, and the SWMM model outputs the node pressure value after the pipe burst.
6. The method for arranging pressure gauges based on drainage pipe network burst analysis according to claim 1 is characterized in that: In S5, when pipe burst simulation is performed at different locations of the pipe network based on the pipe burst data in S1, according to the formula , calculate the injection coefficient ,in, is the injection coefficient, is the burst pipe diameter, is the burst area, g is the gravitational acceleration g=9.81 m / s²; enter the injection coefficient in the SWMM model The pipe burst simulation is carried out, and the SWMM model outputs the node pressure value after the pipe burst to verify the response of the preset pressure gauge points to the pipe burst event.
7. The method for arranging pressure gauges based on drainage pipe network burst analysis according to claim 1 is characterized in that: In S6, when the difference of the pressure gauges output by S5 is greater than 0.5m, it is determined that the pipe burst event can be monitored, and the pressure gauge layout plan is output; when the difference of any pressure gauge output by S5 is less than or equal to 0.5m, it is determined that the pipe burst event cannot be monitored, and the position of the preset pressure gauge layout is adjusted. After the adjustment is completed, S5 is executed repeatedly until the difference of the pressure gauges output by S5 is greater than 0.5m.