A welding platform for assembling port cranes
By designing flexible welding platform components, the problem of cumbersome operation of existing welding platforms has been solved, enabling efficient and safe welding operations and adapting to crane assembly requirements.
Patent Information
- Application Number
- CN202410944619.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-15
AI Technical Summary
The existing port crane welding platforms are time-consuming and labor-intensive to set up, and cannot flexibly adapt to the needs of the cranes. They are also cumbersome to operate, affecting welding efficiency and safety.
A welding platform was designed, which includes components such as a frame, support plate, guiding mechanism, lifting mechanism, connecting components, and meshing mechanism. By combining the moving components and the lifting mechanism, the platform can be moved flexibly and its height can be adjusted, thereby enhancing the flexibility and safety of the welding platform. A safety net is used to prevent objects from falling from heights.
It improves welding efficiency and safety, can flexibly adapt to the assembly needs of cranes, prevents objects from falling from heights, and simplifies the operation process.
Smart Images

Figure CN118478334B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field related to welding platforms, and in particular provides a welding platform for assembling a port crane. Background Art
[0002] Port cranes are heavy machinery used to load and unload cargo at ports. They are usually located on docks and are used to unload cargo from ships to land, or load cargo from land to ships. These cranes usually have strong lifting capacity and long arms, and can handle various types and weights of cargo, including containers, bulk cargo, and heavy equipment. The design and operation of port cranes need to take into account factors such as safety, efficiency and reliability to ensure smooth cargo flow and port operations.
[0003] The port crane welding platform is a working platform used for welding and repair work on port cranes, enabling workers to perform welding, repair and inspection work safely.
[0004] The existing welding platform is generally built with a tower body set on one side of the crane, and then the crane needs to constantly cooperate and adjust to weld it. After the construction is completed, it is placed there, or directly dismantled later. The construction not only wastes time, but also cannot meet the needs of the crane for assembly. The operation is cumbersome, time-consuming and laborious. Therefore, we need to improve the above problems. Summary of the invention
[0005] The purpose of the present invention is to solve the problems existing in the background technology and to propose a welding platform for assembling a port crane.
[0006] To achieve the above purpose, the present invention provides a welding platform for assembling port cranes, including: two groups of frames, the lower surfaces of the two groups of frames are provided with moving components, the outer sides of the two groups of frames are provided with support plates, the upper surfaces of the two sides of the two support plates are provided with guide mechanisms, the upper surfaces of the two support plates and near the middle are fixedly installed with bar racks, the lower sides of the two groups of frames are provided with lifting mechanisms, the sides of the two groups of frames are provided with beams, the outer sides of the corresponding beams are connected to the lifting mechanism through the provided connecting components, a connecting frame is commonly provided between the two beams, the inner sides of the two ends of the connecting frame are rotatably connected to the corresponding beams through the inserted reinforcement rods, the tops of the two beams are provided with meshing mechanisms, the outer walls of one side of the two beams are correspondingly connected with pedestals through the provided mounting components, the inner sides of the two pedestals are slidably provided with lifting frames, the outer sides of one ends of the two pedestals are provided with opening and closing mechanisms, and the inner sides of the frames are fixedly installed with control boxes.
[0007] In the above scheme, further, the guiding mechanism includes sleeve rods installed on the upper surface of one side of the support plate, a strip groove is opened on the inner side of the sleeve rod, and multiple sets of sleeve seats are mounted on the outer side of the frame beam, and extension rods are fixedly installed on the edges of one side of multiple sleeve seats, and clamping plates are fixedly installed on the inner sides of two extension rods, and multiple sets of running wheels are installed on the inner sides of the two clamping plates, and the multiple sets of running wheels pass through the strip groove and roll and fit on the inner wall of the sleeve rod.
[0008] In the above scheme, further, the lifting mechanism includes a fixed seat fixedly installed on the outside of the frame, a first hydraulic cylinder is fixedly installed on the upper surface of the fixed seat, and the telescopic end of the first hydraulic cylinder is connected to the connecting assembly.
[0009] In the above scheme, further, the connecting assembly includes a dowel seat fixedly mounted on the lower surface of the frame beam, and the telescopic end of the first hydraulic cylinder is connected to the lower surface of the dowel seat.
[0010] In the above scheme, further, the meshing mechanism includes bearing sleeves fixedly mounted on the upper surfaces of both ends of the frame beam, and shafts are inserted and rotated together inside the two bearing sleeves. A first gear is fixedly mounted on the outer side of one end of the shaft, and the first gear meshes with a bar rack.
[0011] In the above scheme, further, the installation components include installation frames that are fixedly installed on the outer wall of one side of the frame beam, a fixed beam is fixedly installed on one end of the installation frame, connecting seats are fixedly inserted inside both ends of the fixed beam, one end of the two connecting seats is connected to the pedestal, a fixing plate is fixedly installed on the lower surface of the fixed beam, cables are fixedly installed on the outer walls at both ends of the fixing plate, positioning rods are fixedly installed on the outer sides of the two cables away from the fixing plate, a net is installed on the inner side of the fixing plate, and the two positioning rods are fixedly connected to the net.
[0012] In the above scheme, further, two second hydraulic cylinders are symmetrically arranged on both sides of the two groups of fixed beams, wherein the distance between the two second hydraulic cylinders located on one side of the fixed beam is smaller than the distance between the two second hydraulic cylinders located on the other side of the fixed beam, and the telescopic ends of the second hydraulic cylinders are fixedly installed with moving seats, and an L-shaped rack is fixedly installed on one side of the moving seat, a second gear is meshed with the upper part of the L-shaped rack, a rod shaft is embedded in the inside of the second gear, and the end of the rod shaft is fixed to the lifting frame.
[0013] In the above scheme, further, the opening and closing mechanism includes an arc-shaped railing mounted rotatably on the outside of one end of the pedestal, an arc-shaped platform extends from one end of the pedestal, a support rod is fixedly mounted on the upper surface of one side of the arc-shaped platform, a latch pin is movably inserted on the upper inner side of the arc-shaped railing, and one end of the latch pin extends to the inside of the support rod.
[0014] In the above scheme, further, a fixed block is fixedly installed on the outer side of one end of the pedestal away from the arc-shaped railing, a clamping rod is rotatably installed on the inner side of one end of the fixed block, and two clamping columns are symmetrically installed on the upper outer side of the other pedestal, and one end of the clamping rod is movably clamped between the two clamping columns.
[0015] Compared with the prior art, the present invention has the following beneficial effects:
[0016] By setting a connecting frame and a fixing rod between the two sets of frames, the corresponding frames can rotate automatically, so that they can be more flexibly moved outside the base when assembling the crane, and the corresponding workers can carry the welding machine directly through the drive of the lifting mechanism. As the base moves up, the efficiency of crane welding can be improved. When the two sets of frames are close to each other, the corresponding second hydraulic cylinder can move the lifting frame to the bottom by itself, thereby forming a larger welding platform, which is more convenient to operate and the safety factor is also guaranteed. The net connected by cables under the fixed plate can catch objects during high-altitude operations, thereby preventing the danger of falling objects from high altitudes in the construction site area. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0018] Figure 2 It is a connection schematic diagram of the overall structure of the present invention from another angle;
[0019] Figure 3 It is a schematic diagram of the connection structure between the pedestal and the arc-shaped guardrail of the present invention;
[0020] Figure 4 It is a schematic diagram of the lower surface structure of the pedestal of the present invention;
[0021] Figure 5 It is a schematic diagram of the connection structure between the fixing plate and the bag net of the present invention;
[0022] Figure 6 For the present invention Figure 1 Schematic diagram of the structure at A in the middle;
[0023] Figure 7 For the present invention Figure 2 Schematic diagram of the structure at B in the middle;
[0024] Figure 8 For the present invention Figure 4 Schematic diagram of the structure at point C in the middle.
[0025] In the figure: 1, frame; 2, support seat; 3, beam; 4, mounting frame; 5, fixed beam; 6, connecting frame; 7, reinforcement rod; 8, bearing sleeve; 9, shaft rod; 10, fixed plate; 11, net; 12, first hydraulic cylinder; 13, fixed seat; 14, control box; 15, bar rack; 16, pedestal; 17, fixed block; 18, clamping rod; 19, clamping column; 20, connecting seat; 21, arc guardrail; 22, arc platform; 23, L-shaped rack; 24, moving seat; 25, lifting frame; 26, second hydraulic cylinder; 27, positioning rod; 28, cable; 29, extension rod; 30, sleeve seat; 31, clamping plate; 32, walking wheel; 33, support plate; 34, first gear; 35, sleeve rod; 36, rod shaft; 37, second gear; 38, support rod; 39, bayonet pin. DETAILED DESCRIPTION
[0026] In order to more clearly understand the above-mentioned objects, features and advantages of the present invention, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0027] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0028] like Figure 1-Figure 8 The welding platform for assembling a port crane shown in the figure comprises: two groups of frames 1, the lower surfaces of the two groups of frames 1 are provided with moving components, the outer sides of the two groups of frames 1 close to each other are provided with support plates 33, the upper surfaces of the two sides of the two support plates 33 are provided with guiding mechanisms, the upper surfaces of the two support plates 33 and near the middle thereof are fixedly installed with bar racks 15, the outer lower sides of the two groups of frames 1 are provided with lifting mechanisms, the two groups of frames 1 are provided with frame beams 3 on the sides close to each other, the outer sides of the corresponding frame beams 3 are connected to the lifting mechanisms through the provided connecting components, a connecting frame 6 is provided between the two frame beams 3, the inner sides of the two ends of the connecting frame 6 are rotatably connected to the corresponding frame beams 3 through the inserted reinforcing rods 7, the tops of the two frame beams 3 are provided with meshing mechanisms, the outer walls of one side of the two frame beams 3 are correspondingly connected with pedestals 16 through the provided mounting components, the inner sides of the two pedestals 16 are slidably provided with lifting frames 25, the outer sides of one ends of the two pedestals 16 are provided with opening and closing mechanisms, and the inner sides of the frames 1 are fixedly installed with a control box 14.
[0029] The frame 1 and the beam 3 are both composed of steel structures. The moving components include wear-resistant steel wheels with brake mechanisms, which are more convenient to move. The height can be gradually increased through the set lifting mechanism when welding the crane, making the welding work more convenient. The control box 14 can be connected to the driving components and electrical components on the device and controlled and used from the bottom.
[0030] The guiding mechanism includes sleeve rods 35 which are all installed on the upper surface of one side of the support plate 33. A strip groove is opened on the inner side of the sleeve rod 35. Multiple sets of sleeve seats 30 are mounted on the outer side of the frame beam 3. Extension rods 29 are fixedly installed on the edge of one side of the multiple sleeve seats 30. A clamping plate 31 is fixedly installed on the inner side of the two extension rods 29. Multiple sets of running wheels 32 are installed on the inner side of the two clamping plates 31. The multiple sets of running wheels 32 pass through the strip groove and roll and fit on the inner wall of the sleeve rod 35.
[0031] The clamping plate 31 rolls inside the sleeve rod 35 along with the running wheel 32, which can ensure stability during the subsequent lifting and lowering, and can prevent deviation during the lifting and lowering.
[0032] The lifting mechanism includes a fixed seat 13 fixedly installed on the outside of the frame 1, a first hydraulic cylinder 12 is fixedly installed on the upper surface of the fixed seat 13, the telescopic end of the first hydraulic cylinder 12 is connected to the connecting component, the connecting component includes a retaining seat 2 fixedly sleeved on the lower surface of the frame beam 3, the telescopic end of the first hydraulic cylinder 12 is connected to the lower surface of the retaining seat 2, the meshing mechanism includes bearing sleeves 8 fixedly installed on the upper surfaces of both ends of the frame beam 3, a shaft rod 9 is inserted and rotated together inside the two bearing sleeves 8, a first gear 34 is fixedly sleeved on the outer side of one end of the shaft rod 9, and the first gear 34 is meshed with the bar rack 15.
[0033] The first hydraulic cylinder 12 drives the stop 2 to rise, and the shaft rod 9 on the corresponding frame beam 3 is driven by the first gear 34, and one end rotates inside the two bearing sleeves 8, thereby enabling the frame beam 3 to be raised and lowered. In this way, the driving contact area can be increased to ensure the stability of the frame beam 3.
[0034] The installation components include installation frames 4 fixedly installed on the outer wall of one side of the frame beam 3, a fixed beam 5 is fixedly installed on one end of the installation frame 4, connecting seats 20 are fixedly inserted inside both ends of the fixed beam 5, one end of the two connecting seats 20 is connected to the pedestal 16, a fixing plate 10 is fixedly installed on the lower surface of the fixed beam 5, cables 28 are fixedly installed on the outer walls of both ends of the fixing plate 10, positioning rods 27 are fixedly installed on the outer sides of the two cables 28 away from the fixing plate 10, a net 11 is installed on the inner side of the fixing plate 10, and the two positioning rods 27 are fixedly connected to the net 11.
[0035] The mounting frame 4 and the fixing beam 5 can allow the fixing plate 10 to be set on one side for installing the pedestal 16;
[0036] Under the connection of the positioning rod 27 and the cable 28, the net 11 can catch objects or slag during high-altitude operations, thereby preventing the danger of falling objects from high altitudes in the construction site area. The net 11 can be made of a metal net.
[0037] Two second hydraulic cylinders 26 are symmetrically arranged on both sides of the two groups of fixed beams 5, wherein the spacing between the two second hydraulic cylinders 26 on one side of the fixed beam 5 is smaller than the spacing between the two second hydraulic cylinders 26 on the other side of the fixed beam 5, and the telescopic ends of the second hydraulic cylinders 26 are fixedly installed with moving seats 24, and an L-shaped rack 23 is fixedly installed on one side of the moving seat 24, a second gear 37 is meshed with the upper part of the L-shaped rack 23, a rod shaft 36 is embedded in the second gear 37, and the end of the rod shaft 36 is fixed to the lifting frame 25.
[0038] The two sets of second hydraulic cylinders 26 can correspondingly drive the moving seat 24 and the L-shaped rack 23 to move to the lifting frame 25, and then lift the lifting frame 25, and then move the L-shaped rack 23, so that the second gear 37 outside the rod shaft 36 is engaged with the L-shaped rack 23, thereby the position of the lifting frame 25 can be firmly fixed, otherwise the L-shaped rack 23 is retracted to allow the corresponding lifting frame 25 to move down, and the two sets of pedestals 16 are used in conjunction with each other on the same side;
[0039] The second hydraulic cylinders 26 of the two groups of pedestals 16 are arranged at a distance from each other to avoid collision during telescopic driving.
[0040] The extension of the movable seat 24 and the L-shaped rack 23 strengthens the supporting force at the bottom of the pedestal 16 , which helps to improve the bearing capacity of the pedestal 16 .
[0041] The opening and closing mechanism includes an arc-shaped railing 21 rotatably mounted on the outside of one end of the pedestal 16, an arc-shaped platform 22 extends from one end of the pedestal 16, a support rod 38 is fixedly mounted on the upper surface of one side of the arc-shaped platform 22, a latch 39 is movably inserted on the upper inner side of the arc-shaped railing 21, and one end of the latch 39 extends to the inside of the support rod 38.
[0042] The purpose of setting the arc-shaped guardrail 21 is to provide protection at an open side during high-altitude operations. Then, when a worker stands on the inner side of the pedestal 16, the latch 39 is inserted from the upper inner side of the arc-shaped guardrail 21 into the support rod 38, thereby fixing the arc-shaped guardrail 21 on the arc-shaped platform 22.
[0043] A fixed block 17 is fixedly installed on the outer side of one end of the pedestal 16 away from the arc-shaped guardrail 21, and a clamping rod 18 is rotatably installed on the inner side of one end of the fixed block 17. Two clamping columns 19 are symmetrically installed on the upper side of the other pedestal 16, and one end of the clamping rod 18 is movably clamped between the two clamping columns 19.
[0044] When the two sets of pedestals 16 are close to each other, the corresponding clamping rods 18 can be rotated to one side of the two clamping columns 19. The ends of the clamping rods 18 adopt flexible components, which can improve the connection strength when connected, and under the premise that the frame 1 itself has a certain weight, the connection between the two is tighter.
[0045] Working principle: When assembling and welding the crane, the device can drive the entire structure close to the base of the crane through the moving components at the bottom of the frame 1. In order to cooperate with higher assembly and welding efficiency, the two sets of frames 1 can be rotated correspondingly through the connecting frame 6 and the reinforcing rod 7, thereby flexibly adjusting according to the welding position, and when the frame beam 3 and the frame 1 are rotated, the corresponding pedestals 16 also move away from each other. The two pedestals 16 can carry workers and welding mechanisms on top, thereby respectively and simultaneously carrying out welding operations. Driven by the second hydraulic cylinder 26, the L-shaped rack 23 is driven to move to the lifting frame 25, and then the lifting frame 25 is lifted, and then the L-shaped rack 2 is moved. 3 moves, causing the second gear 37 outside the rod shaft 36 to engage with the L-shaped rack 23, thereby the position of the lifting frame 25 can be firmly fixed, and the safety factor is higher when the two sets of frames 1 are close to each other, and the corresponding two sets of pedestals 16 are also close to each other. Through the clamping of the clamping rod 18, the two sets of pedestals 16 are connected together, thereby forming a welding platform with a larger area, which is more convenient during operation. In addition, the net 11 is located below the pedestal 16 through the connection of the cable 28 under the fixing plate 10, so that the object or slag can be caught during high-altitude operation, thereby preventing the danger of falling objects from high altitude in the construction site area.
[0046] As described above, in order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
Claims
1. A welding platform for assembling a port crane, comprising: Two groups of building frames (1), characterized in that: the lower surfaces of the two groups of building frames (1) are both provided with moving components, the outer sides of the two groups of building frames (1) close to each other are both provided with support plates (33), the upper surfaces of both sides of the two support plates (33) are both provided with guiding mechanisms, the upper surfaces of the two support plates (33) are fixedly installed with bar-shaped racks (15) near the middle, the lower parts of the outer sides of the two groups of building frames (1) are both provided with lifting mechanisms, the sides of the two groups of building frames (1) close to each other are both provided with frame beams (3), and the corresponding outer sides of the frame beams (3) are connected to the lifting mechanisms by connecting components. The two beams (3) are connected to each other by a lowering mechanism, a connecting frame (6) is provided between the two beams (3), the inner sides of the two ends of the connecting frame (6) are rotatably connected to the corresponding beams (3) through inserted reinforcement rods (7), the tops of the two beams (3) are provided with a meshing mechanism, the outer walls of one side of the two beams (3) are connected to a pedestal (16) through a set mounting assembly, the inner sides of the two pedestals (16) are slidably provided with a lifting frame (25), the outer sides of one end of the two pedestals (16) are provided with an opening and closing mechanism, and the inner side of the building frame (1) is fixedly provided with a control box (14); The opening and closing mechanism comprises an arc-shaped guard bar (21) rotatably mounted on the outside of one end of a pedestal (16); an arc-shaped platform (22) extends from one end of the pedestal (16); a stopper (38) is fixedly mounted on the upper surface of one side of the arc-shaped platform (22); a latch (39) is movably inserted through the upper inner side of the arc-shaped guard bar (21), and one end of the latch (39) extends into the interior of the stopper (38); The guide mechanism comprises sleeve rods (35) which are all mounted on the upper surface of one side of the support plate (33), the sleeve rods (35) are provided with strip grooves on the inner side, a plurality of sleeve seats (30) are sleeved on the outer side of the frame beam (3), an extension rod (29) is fixedly mounted on the edge of one side of the plurality of sleeve seats (30), a clamping plate (31) is fixedly mounted on the inner side of two extension rods (29), a plurality of running wheels (32) are installed on the inner side of the two clamping plates (31), and the plurality of running wheels (32) pass through the strip grooves and roll to fit on the inner wall of the sleeve rod (35); The lifting mechanism comprises a fixed seat (13) fixedly mounted on the outside of the frame (1), a first hydraulic cylinder (12) being fixedly mounted on the upper surface of the fixed seat (13), and a telescopic end of the first hydraulic cylinder (12) being connected to a connecting assembly; The connection assembly comprises a stopper (2) fixedly sleeved on the lower surface of the frame beam (3), and the telescopic end of the first hydraulic cylinder (12) is connected to the lower surface of the stopper (2); The meshing mechanism comprises bearing sleeves (8) respectively fixedly mounted on the upper surfaces of both ends of the frame beam (3), a shaft (9) being inserted and rotatably mounted inside the two bearing sleeves (8), a first gear (34) being fixedly mounted on the outer side of one end of the shaft (9), and the first gear (34) meshing with a bar-shaped rack (15); The mounting assembly comprises a mounting frame (4) which is fixedly mounted on the outer wall of one side of the frame beam (3); a fixed beam (5) is fixedly mounted on one end of the mounting frame (4); connecting seats (20) are fixedly inserted into the interior of both ends of the fixed beam (5); one end of the two connecting seats (20) is connected to the pedestal (16); a fixing plate (10) is fixedly mounted on the lower surface of the fixed beam (5); cables (28) are fixedly mounted on the outer walls of both ends of the fixing plate (10); positioning rods (27) are fixedly mounted on the outer sides of the two cables (28) away from the fixing plate (10); a sack net (11) is mounted on the inner side of the fixing plate (10); and the two positioning rods (27) are fixedly connected to the sack net (11); Two second hydraulic cylinders (26) are symmetrically arranged on both sides of the two groups of fixed beams (5), wherein the distance between the two second hydraulic cylinders (26) located on one side of the fixed beam (5) is smaller than the distance between the two second hydraulic cylinders (26) located on the other side of the fixed beam (5), the telescopic ends of the second hydraulic cylinders (26) are fixedly mounted with a moving seat (24), and an L-shaped rack (23) is fixedly mounted on one side of the moving seat (24), a second gear (37) is meshed on the upper part of the L-shaped rack (23), a rod shaft (36) is embedded in the interior of the second gear (37), and the end of the rod shaft (36) is fixed to the lifting frame (25); A fixing block (17) is fixedly mounted on the outer side of one end of the pedestal (16) away from the arc-shaped guardrail (21); a clamping rod (18) is rotatably mounted on the inner side of one end of the fixing block (17); and two clamping columns (19) are symmetrically mounted on the upper side of the outer side of the other pedestal (16); one end of the clamping rod (18) is movably clamped between the two clamping columns (19).