Power resource sharing control method for distributed charging pile
By establishing a virtual power module in the charging station, power resource sharing and optimal allocation between charging piles are realized, which solves the problem of low utilization rate of power resources in existing charging stations, improves charging speed and utilization rate, and reduces the cost of upgrades. cost.
Patent Information
- Application Number
- CN202410903423.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-08
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-08
AI Technical Summary
The power resource utilization rate of charging piles in existing charging stations is low, which cannot meet the increasing demand for charging speed of electric vehicles, and the upgrade cost is high, resulting in slow charging speed and affecting user experience.
Using the power resource sharing control method of distributed charging piles, multiple charging piles are connected through communication lines and power lines, a virtual power module is established, and the output capacity of the charging piles is monitored and scheduled in real time to realize the sharing and optimal allocation of power resources to meet the needs of users. electrical equipment needs.
It improves the output capacity and power usage of charging stations, reduces upgrade costs, achieves faster charging speeds, saves the cost of building new charging piles, and improves user charging experience.
Smart Images

Figure CN118478738B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of charging piles, and in particular to a power resource sharing control method for a distributed charging pile. Background Art
[0002] With the continuous improvement of electric vehicle technology, the driving range of electric vehicles is constantly increasing, the battery capacity is constantly increasing, and the charging speed allowed by electric vehicles is also constantly increasing, while the time that charging users expect the battery to be fully charged is getting shorter and shorter. The output capacity of the existing charging stations can no longer meet the increasing demand for charging speed of electric vehicles. The low power resource utilization rate and slow charging speed of the existing charging piles have become the problems that most charging users want to solve.
[0003] After research, it was found that for the existing charging stations, the charging output capacity of the charging piles in the stations is generally low due to the low battery capacity of the vehicles and low charging speed requirements during construction. Due to the limitations of the input power line specifications and the structural design of the charging piles, it is impossible to support the addition of power modules to increase the output capacity of the charging piles. Rebuilding new charging piles that meet faster charging speeds requires replacing basic power distribution facilities, and the upgrade cost is relatively high. For new charging stations, under the premise of limited distribution network capacity and the pursuit of faster charging speeds, charging piles with higher output capacity need to be built, which will lead to a reduction in the number of charging piles that can be built in the station, and the low demand charging stage of electric vehicles during the peak charging period will greatly waste the power resource allocation of the charging piles; and under the premise of pursuing the number of piles to be built, the output capacity of a single charging pile will be low, which will greatly extend the user's charging time and affect the user's charging experience. Summary of the invention
[0004] Based on this, it is necessary to provide a power resource sharing control method for distributed charging piles that can improve the output capacity of the built charging stations in response to the above technical problems.
[0005] A power resource sharing control method for a distributed charging pile, the power resource sharing control method is applied to a distributed charging pile, the distributed charging pile includes N charging piles, the N charging piles are connected according to a preset rule, and the charging piles are connected through a communication line and a power line; the power resource sharing control method includes the following steps:
[0006] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line. The current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information; the power resource status information at least includes the maximum available charging power and usage status of the charging pile; the current charging pile is the charging pile that is starting to charge the power-consuming device among the charging piles;
[0007] When the current charging pile starts to charge the electric device, the current required power of the electric device is obtained, and a local power module is allocated to the electric device based on the current required power; the local power module is the power module carried by the current charging pile itself;
[0008] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, a virtual power module is searched based on the power shortage, and a target virtual power module is allocated to the power-consuming equipment; the target virtual power module is one or more virtual power modules whose maximum available charging power meets the power shortage; the power shortage is the difference between the required power and the maximum available charging power of the local power module.
[0009] In one of the embodiments, the power resource sharing control method further comprises the steps of:
[0010] The current charging pile checks the current power demand of the electrical equipment in real time or periodically;
[0011] When the current charging pile determines that the current required power is less than the maximum available charging power of the local power module and the overflow power is greater than or equal to the maximum available charging power of the target virtual power module, the charging power of the corresponding target virtual power module is controlled to be released;
[0012] When the current charging pile determines that the current required power is equal to zero, it controls the release of the charging power of the local power module and the charging power of the target virtual power module.
[0013] In one of the embodiments, the power resource status information also includes a charging strategy configured for the charging pile; the charging strategy is a high-power priority charging strategy or a local priority charging strategy; a virtual power module configured as a high-power priority charging strategy is defined as a first-class virtual power module; a virtual power module configured as a local priority charging strategy is defined as a second-class virtual power module;
[0014] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the step of searching for a virtual power module based on the power shortage and allocating a target virtual power module to the power-consuming device includes the following steps:
[0015] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, searching for the first type of virtual power module and the second type of virtual power module in an idle state from the virtual power modules;
[0016] The current charging pile searches for the first type of virtual power module and the second type of virtual power module in an idle state based on the power shortage, and allocates a target virtual power module to the power-consuming device.
[0017] In one of the embodiments, the power resource sharing control method further comprises the steps of:
[0018] If the target virtual power module is a first type virtual power module, when the charging pile corresponding to the target virtual power module is connected to the power-consuming device, the charging pile corresponding to the target virtual power module sends a prompt message to the power-consuming device connected to the charging pile corresponding to the target virtual power module to prompt that the charging power of the charging pile corresponding to the target virtual power module is occupied; or
[0019] If the target virtual power module is a first-class virtual power module, and the charging pile corresponding to the target virtual power module is already charging the power-consuming equipment, the current charging pile controls the charging pile corresponding to the target virtual power module to stop charging the power-consuming equipment, and controls the charging pile corresponding to the target virtual power module to switch the charging power to the current charging pile.
[0020] In one of the embodiments, the power resource sharing control method further comprises the steps of:
[0021] If the target virtual power module is a second-type virtual power module in an idle state, when the charging pile corresponding to the target virtual power module is connected to an electrical device, the charging pile corresponding to the target virtual power module sends a power release request to the current charging pile, and the current charging pile responds to the power release request and releases the charging power of the target virtual power module.
[0022] In one of the embodiments, the power resource status information further includes the charging strategy configured for the charging pile in different time periods, and the distributed charging pile further includes a charging operation platform, and the charging operation platform is communicatively connected with the charging pile;
[0023] The charging pile receives the charging strategies for different time periods sent by the charging operation platform;
[0024] The charging pile reports the current maximum available charging power and usage status of the charging pile to the charging operation platform.
[0025] In one of the embodiments, the usage state is an idle state, a fault state, or an occupied state;
[0026] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the step of searching for a virtual power module based on the power shortage and allocating a target virtual power module to the power-consuming device includes the following steps:
[0027] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the power shortage is compared with the maximum available charging power of the virtual power module;
[0028] If there is a virtual power module whose maximum available charging power is equal to the power shortage, the virtual power module whose maximum available charging power is equal to the power shortage is used as the target virtual power module;
[0029] If there is no virtual power module whose maximum available charging power is equal to the power shortfall, but there is a virtual power module whose maximum available charging power is greater than the power shortfall, the virtual power module whose maximum available charging power is greater than the power shortfall is used as the target virtual power module;
[0030] If there is no virtual power module whose maximum available charging power is greater than or equal to the power shortage, two or more virtual power modules whose sum of maximum available charging power is equal to or greater than the power shortage are used as target virtual power modules;
[0031] The current charging pile sends a control instruction to the charging pile corresponding to the target virtual power module, controls the charging pile corresponding to the target virtual power module to switch the charging power equal to the power shortage, and controls the charging pile corresponding to the target virtual power module to switch the use state to the occupied state.
[0032] In one of the embodiments, the preset rule is to connect in sequence, and N charging piles are connected in sequence to form a linear distributed charging pile;
[0033] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information:
[0034] The current charging pile obtains the power resource status information of the charging pile directly connected to the current charging pile; if the current charging pile is located at the head or tail of the linear distributed charging pile, a virtual power module is established in the current charging pile; if the current charging pile is located in the middle of the linear distributed charging pile, two virtual power modules are established in the current charging pile.
[0035] In one embodiment, the preset rule is to connect end to end in sequence, and N charging piles are connected end to end in sequence to form a ring-shaped distributed charging pile; the local power module includes M local power submodules;
[0036] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information:
[0037] The current charging pile obtains power resource status information of a charging pile directly connected to the current charging pile, and establishes two virtual power modules in the current charging pile.
[0038] In one embodiment, the preset rule is to connect end to end in sequence, and N charging piles are connected end to end in sequence to form a ring-shaped distributed charging pile; the local power module includes M local power submodules;
[0039] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information:
[0040] The current charging pile obtains other charging piles except the current charging pile, and establishes N-1 virtual power modules in the current charging pile.
[0041] One of the above technical solutions has the following advantages and beneficial effects:
[0042] The power resource sharing control method of the distributed charging pile of the present application includes the following steps: the current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information; when the current charging pile starts to charge the power-consuming device, the current required power of the power-consuming device is obtained, and a local power module is allocated to the power-consuming device based on the current required power; when the maximum available charging power of the local power module of the current charging pile is less than the current required power, the virtual power module is searched based on the power shortage, and the target virtual power module is allocated to the power-consuming device. The method of the present application establishes a virtual mirror (i.e., a virtual power module) of the output capacity of other charging piles in the charging pile, so that the charging pile can monitor the status of other charging piles at any time. When the power-consuming device connected to the charging pile has a high-power charging demand and it cannot meet the power demand of the power-consuming device by itself, the charging pile that meets the conditions for switching can be quickly queried in other charging piles through the virtual mirror to supplement the output to meet the charging demand of the power-consuming device. This application method does not require the construction of new high-power charging piles. Instead, existing charging stations that have already been built can be renovated and upgraded to achieve high-power output, saving costs and improving the power utilization rate of existing charging stations. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 It is a schematic diagram of the structure of a distributed charging stack in an embodiment of the present application.
[0044] Figure 2 It is a flow chart of the power resource sharing control method of the distributed charging stack in the embodiment of the present application.
[0045] Figure 3 This is a schematic diagram of the virtual structure of the charging pile in the embodiment of the present application.
[0046] Figure 4 This is a schematic diagram of a type of structure of a distributed charging stack in an embodiment of the present application.
[0047] Figure 5 This is a schematic diagram of another type of structure of a distributed charging stack in an embodiment of the present application.
[0048] Figure 6 This is a schematic diagram of another type of structure of a distributed charging stack in an embodiment of the present application.
[0049] Figure 7 Schematic diagram of the process of releasing power in an embodiment of the present application. DETAILED DESCRIPTION
[0050] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0051] Traditional charging technology has at least the following disadvantages:
[0052] Traditional integrated DC charging piles have fixed power and cannot fully meet the charging needs of vehicles with a demand power greater than the rated power of the charging pile. They cannot adapt to the needs of the rapid development of battery technology. When the charging pile is idle, the power resources in the pile cannot be used by other charging piles that are in a charging state and cannot meet the charging needs. The power resource utilization rate of the entire charging station is low.
[0053] The charging speed of existing charging stations is too slow, and it is too expensive to use traditional DC charging pile technology to improve the charging speed. The original infrastructure and electrical facilities of existing charging stations cannot be directly applied to high-power DC charging piles that exceed their original specifications after replacement. The cost of technical transformation is no less than building a new charging station, and the cost of upgrading and transformation is too high.
[0054] In order to solve the above problems, a power resource sharing control method for a distributed charging pile is provided. The power resource sharing control method is applied to a distributed charging pile. The distributed charging pile includes N charging piles. The N charging piles are connected according to preset rules, and the charging piles are connected through communication lines and power lines. In one example, N can be a positive integer greater than or equal to 3. N charging piles are connected to form a distributed charging pile. The preset rule can be a sequential connection or a head-to-tail connection. Different connection methods form different types of distributed charging piles. For example, a sequential connection can form a linear distributed charging pile, and a head-to-tail connection can form a ring-shaped distributed charging pile. The communication line is used to transmit information data, and the power control module of the charging pile is connected via the communication line. The power line is used to transmit electric energy, and the power module of the charging pile is connected via the power line (such as Figure 1 as shown).
[0055] like Figure 2 As shown, the power resource sharing control method includes the following steps:
[0056] Step S210, the current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information. From the time when the current charging pile starts to charge the power-consuming device (the power-consuming device can be an electric car, an electric ship, etc. that uses a power battery) to the end of charging the power-consuming device, the current charging pile obtains the power resource status information of the corresponding charging pile (the corresponding charging pile can include a charging pile directly connected to the current charging pile, and can also include a charging pile indirectly connected to the current charging pile) in real time or periodically. The acquisition process can be that the current charging pile actively inquires the corresponding charging pile, and the corresponding charging pile responds to the inquiry of the current charging pile and sends the power resource status information to the current charging pile, or the corresponding charging pile actively and continuously sends it when monitoring that the current charging pile starts charging, or the corresponding charging pile periodically sends it out. The current charging pile grasps the current status of the corresponding charging pile through the power resource status. The power resource status information includes at least the maximum available charging power and the use status of the charging pile. The use status is an idle state, an occupied state, or a fault state. The idle state means that the charging pile can be searched and occupied. The occupied state means that the charging pile has been occupied by a charging gun of the distributed charging pile, receives the power control of the charging gun, and provides power output for the charging gun. The fault state means that the power resources in the charging pile are abnormal, such as abnormal communication of the charging module, fault of the charging module, etc. The power resources in the charging pile in the faulty state cannot be searched and occupied (some unimportant faults of the charging pile itself do not affect its power resources being shared by adjacent piles). It should be noted that the current charging pile is the charging pile that is starting to charge the electrical equipment. In a distributed charging pile, there can be two or more current charging piles at the same time.
[0057] In one example, the power resource status information also includes the charging strategy configured for the charging pile in different time periods. The charging strategy refers to the way in which the charging pile is charged, for example, the charging strategy is a high-power priority charging strategy or a local priority charging strategy. It should be noted that the charging pile may have different charging strategies in different time periods, wherein different time periods refer to dividing a day into several sections. In one example, the distributed charging pile also includes a charging operation platform, which is connected to the charging pile in communication. The charging pile receives the charging strategies for different time periods sent by the charging operation platform. The charging pile reports the maximum available charging power and usage status of the current charging pile to the charging operation platform. It should be noted that the charging operation platform is a comprehensive management platform for the charging pile. The charging operation platform divides a day into multiple different time periods and formulates a charging strategy for each time period. The charging strategies for different time periods may be the same or different. The charging operation platform sends the charging strategies for different time periods to the charging pile. The charging pile saves the charging strategies for different time periods in the local storage. During the operation of the charging pile, the corresponding charging strategy is obtained according to the current time, and the power sharing process is performed according to the charging strategy. After the charging pile is offline from the charging operation platform, the charging pile can still read the most recent charging strategy from the local storage. During operation, in order for the charging operation platform to manage the charging pile according to the latest situation of the charging pile at any time, the charging pile reports the current maximum available charging power and usage status of the charging pile to the charging operation platform. It should be noted that in addition to reporting the maximum available charging power and usage status, other information can also be reported, such as the actual output voltage, current, power, operating time, etc., and the connected vehicle model, etc.
[0058] The current charging pile establishes a virtual power module based on the power resource status information, such as Figure 3 As shown, it is equivalent to the current charging pile establishing a virtual image corresponding to the resource status information in its memory, that is, a virtual image corresponding to other charging piles. The virtual power module can reflect the maximum available charging power and usage status of the corresponding charging pile, and change in real time with the maximum available charging power and usage status of the charging pile. The current charging pile can conveniently check the current status of other charging piles through the virtual power module to facilitate power switching scheduling.
[0059] Depending on the structure of the distributed charging pile, the current charging pile can establish different amounts of virtual power:
[0060] In the first example, Figure 4 As shown, the preset rule is to connect in sequence, and N charging piles are connected in sequence to form a linear distributed charging pile.
[0061] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information:
[0062] The current charging pile obtains the power resource status information of the charging pile directly connected to the current charging pile; if the current charging pile is located at the head or tail of the linear distributed charging pile, a virtual power module is established in the current charging pile; if the current charging pile is located in the middle of the linear distributed charging pile, two virtual power modules are established in the current charging pile. In this example, the current charging pile only establishes the virtual power module of the charging pile directly connected to it.
[0063] In the second example, Figure 5 As shown, the preset rule is to connect the N charging piles end to end in sequence to form a ring-shaped distributed charging pile; the local power module includes M local power submodules. Wherein, M is a positive integer greater than 1.
[0064] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information:
[0065] The current charging pile obtains the power resource status information of the charging pile directly connected to the current charging pile, and establishes two virtual power modules in the current charging pile. In this example, since the distributed charging pile is a ring-shaped distributed charging pile, each charging pile can establish two virtual power modules therein.
[0066] In the third example, Figure 6 As shown, the preset rule is to connect end to end in sequence, and N charging piles are connected end to end in sequence to form a ring-shaped distributed charging pile; the local power module includes M local power sub-modules.
[0067] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information:
[0068] The current charging pile obtains other charging piles except the current charging pile, and establishes N-1 virtual power modules in the current charging pile. In this example, in order to further improve the resource power utilization rate of the charging pile, the current charging pile establishes virtual power modules corresponding to all other charging piles in it, so that the current charging pile can schedule the charging power of all other charging piles in the distributed charging pile.
[0069] Step S220, when the current charging pile starts to charge the electric device, the current power demand of the electric device is obtained, and a local power module is allocated to the electric device based on the current power demand. The electric device is connected to the current charging pile, and the current charging pile immediately starts to charge the electric device. In the preparation stage before charging, the current charging pile obtains the current power demand of the electric device. The current charging pile gives priority to matching the local power module for the electric device, that is, the charging power of the local power module is input into the electric device to charge it. It should be noted that the local power module is the power module carried by the current charging pile itself.
[0070] Step S230, when the maximum available charging power of the local power module of the current charging pile is less than the current required power, the virtual power module is searched based on the power shortage, and the target virtual power module is allocated to the power-consuming equipment. The maximum available charging power of the local power module of the current charging pile is less than the current required power, indicating that the charging power of the current charging pile cannot meet the charging demand of the power-consuming equipment. In order to meet the charging demand of the power-consuming equipment, the current charging pile searches for a target virtual power module that meets the demand from the virtual power modules, that is, the target virtual power module is one or more virtual power modules whose charging power meets the power shortage. It should be noted that the charging power of the charging pile corresponding to the target virtual power module is in a schedulable state, that is, the charging pile corresponding to the target virtual power module contains at least idle charging power, and the idle charging power is not occupied. Among them, the power shortage is the difference between the required power and the maximum available charging power of the local power module.
[0071] In one example, a method for allocating a target virtual power module is provided. Specifically, when the maximum available charging power of the local power module of the current charging pile is less than the current required power, the virtual power module is searched based on the power shortage, and the step of allocating the target virtual power module to the power-consuming device includes the following steps:
[0072] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the power shortage is compared with the maximum available charging power of the virtual power module.
[0073] If there is a virtual power module whose maximum available charging power is equal to the power shortage, the virtual power module whose maximum available charging power is equal to the power shortage is used as the target virtual power module.
[0074] If there is no virtual power module whose maximum available charging power is equal to the power shortage, but there is a virtual power module whose maximum available charging power is greater than the power shortage, the virtual power module whose maximum available charging power is greater than the power shortage is used as the target virtual power module.
[0075] If there is no virtual power module whose maximum available charging power is greater than or equal to the power shortage, two or more virtual power modules whose sum of maximum available charging powers is equal to or greater than the power shortage are used as target virtual power modules.
[0076] It should be noted that in order to save charging resources and improve the utilization rate of power resources in the charging pile, priority is given to allocating virtual power modules with a maximum available charging power equal to the power shortage, followed by allocating virtual power modules with a maximum available charging power greater than the power shortage, and finally, the charging needs of the power-consuming equipment are met through a combination of two or more virtual power modules. The current charging pile allocates a target virtual power module to the power-consuming equipment, that is, the current charging pile sends a control instruction to the charging pile corresponding to the target virtual power module, controls the charging pile corresponding to the target virtual power module to switch the charging power equal to the power shortage, and controls the charging pile corresponding to the target virtual power module to switch the use state to the occupied state.
[0077] In order to meet a larger charging scenario, the following charging strategies are provided:
[0078] In one example, the power resource status information also includes the charging strategy configured for the charging pile; the charging strategy is a high-power priority charging strategy or a local priority charging strategy; the virtual power module configured as the high-power priority charging strategy is defined as a first-class virtual power module; the virtual power module configured as the local priority charging strategy is defined as a second-class virtual power module. It should be noted that the high-power priority charging strategy means that high-power charging is given priority to the power-consuming device. Even if the charging pile is charging the power-consuming device, when the current charging pile sends a switching request to the charging pile, the charging pile will still suspend charging the power-consuming device and switch its charging power to the current charging pile. The local priority charging strategy means that the power-consuming device connected to itself is charged first, and when the switching request of the current charging pile is received, the charging power will not be switched for the current charging pile. The virtual power module configured as the high-power priority charging strategy can always be regarded as being in an idle state relative to the current charging pile. The virtual power module configured as the local priority charging strategy is regarded as being in an idle state relative to the current charging pile only if it contains idle charging power.
[0079] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the step of searching for a virtual power module based on the power shortage and allocating a target virtual power module to the power-consuming device includes the following steps:
[0080] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, searching for the first type of virtual power module and the second type of virtual power module in an idle state from the virtual power modules;
[0081] The current charging pile searches for the first type of virtual power module and the second type of virtual power module in an idle state based on the power shortage, and allocates a target virtual power module to the power-consuming device.
[0082] In this example, specifically, the power resource sharing control method further includes the steps of:
[0083] If the target virtual power module is a first type virtual power module, when the charging pile corresponding to the target virtual power module is connected to the power-consuming device, the charging pile corresponding to the target virtual power module sends a prompt message to the power-consuming device connected to the charging pile corresponding to the target virtual power module to prompt that the charging power of the charging pile corresponding to the target virtual power module is occupied; or
[0084] If the target virtual power module is a first-class virtual power module, and the charging pile corresponding to the target virtual power module is already charging the power-consuming equipment, the current charging pile controls the charging pile corresponding to the target virtual power module to stop charging the power-consuming equipment, and controls the charging pile corresponding to the target virtual power module to switch the charging power to the current charging pile.
[0085] It should be noted that the first type of virtual power module is first assigned to the current charging pile, and the charging pile corresponding to the first type of virtual power module will not provide charging for the connected power device until the current charging pile is fully charged. The first type of virtual power module first charges the connected power device, but upon receiving the switching request of the current charging pile, the first type of virtual power module immediately stops charging the connected power device.
[0086] In this example, specifically, the power resource sharing control method further includes the steps of:
[0087] If the target virtual power module is a second-type virtual power module in an idle state, when the charging pile corresponding to the target virtual power module is connected to an electrical device, the charging pile corresponding to the target virtual power module sends a power release request to the current charging pile, and the current charging pile responds to the power release request and releases the charging power of the target virtual power module.
[0088] It should be noted that the second-type virtual power module in the idle state is first allocated to the target virtual power module, and then the charging pile corresponding to the second-type virtual power module in the idle state is connected to the electrical equipment itself, and the charging pile corresponding to the second-type virtual power module stops switching charging power to the current charging pile and turns to charging the electrical equipment connected to itself.
[0089] In order to improve the efficiency of power resource utilization in the charging pile, the excess charging power is released as soon as possible after the power demand of the current power-consuming equipment of the charging pile is reduced. In an example, Figure 7 As shown, the power resource sharing control method also includes the steps of:
[0090] Step S710: The current charging pile checks the current power demand of the electrical equipment in real time or periodically.
[0091] Step S720, when the current charging pile determines that the current demand power is less than the maximum available charging power of the local power module, and the overflow power is equal to the maximum available charging power of the target virtual power module, it controls the release of the charging power of the corresponding target virtual power module. It should be noted that the corresponding target virtual power module refers to the target virtual power module whose maximum available charging power is equal to the overflow power. As charging progresses, the demand of the electrical equipment connected to the current charging pile gradually decreases, and the sum of the maximum available charging power of the local power module and the maximum available charging power of the target virtual power module gradually exceeds the demand power, that is, overflow power is formed. When the overflow power is equal to a target virtual power module, the target virtual power module is released, thereby improving the efficiency of the use of power resources in the charging pile.
[0092] Step S730 , when the current charging pile determines that the current required power is equal to zero, it controls the release of the charging power of the local power module and the charging power of the target virtual power module.
[0093] The power resource sharing control method of the distributed charging pile of the present application comprises the following steps: the current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information; when the current charging pile starts to charge the power-consuming device, the current required power of the power-consuming device is obtained, and a local power module is allocated to the power-consuming device based on the current required power; when the maximum available charging power of the local power module of the current charging pile is less than the current required power, the virtual power module is searched based on the power shortage, and the target virtual power module is allocated to the power-consuming device. The method of the present application establishes a virtual mirror (i.e., a virtual power module) of the output capacity of other charging piles in the charging pile, so that the charging pile can monitor the status of other charging piles at any time. When the power-consuming device connected to the charging pile has a high-power charging demand and it cannot meet the power demand of the power-consuming device by itself, the power resources in the charging pile that meet the conditions for switching are quickly queried in other charging piles through the virtual mirror to supplement the output to meet the charging demand of the power-consuming device. This application method does not require the construction of new high-power charging piles. Instead, existing charging stations that have already been built can be renovated and upgraded to achieve high-power output, saving costs and increasing the utilization rate of existing charging stations.
[0094] It should be understood that although Figure 2 and Figure 7The steps in the flowchart are shown in sequence as indicated by the arrows, but these steps are not necessarily executed in the order indicated by the arrows. Unless otherwise specified in this document, there is no strict order restriction for the execution of these steps, and these steps can be executed in other orders. Moreover, Figure 2 and Figure 7 At least part of the steps may include multiple sub-steps or multiple stages. These sub-steps or stages are not necessarily executed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least part of the sub-steps or stages of other steps.
[0095] In one embodiment, Figure 1 As shown, the distributed charging stack includes N charging piles, which are connected according to preset rules, the power control modules of the charging piles are connected through communication lines, the local power modules of the charging piles are connected through power lines, and the local power modules of the charging piles are also connected to the charging guns of the charging piles through power lines;
[0096] The distributed charging stack performs the following steps:
[0097] The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line. The current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information; the power resource status information at least includes the maximum available charging power and usage status of the charging pile; the current charging pile is the charging pile that is starting to charge the power-consuming device among the charging piles;
[0098] When the current charging pile starts to charge the electric device, the current required power of the electric device is obtained, and a local power module is allocated to the electric device based on the current required power; the local power module is the power module carried by the current charging pile itself;
[0099] When the maximum available charging power of the local power module of the current charging pile is less than the current required power, a virtual power module is searched based on the power shortage, and a target virtual power module is allocated to the power-consuming equipment; the target virtual power module is one or more virtual power modules whose charging power meets the power shortage; the power shortage is the difference between the required power and the maximum available charging power of the local power module.
[0100] The distributed charging pile power sharing method of the present application greatly improves the power utilization rate of the charging pile equipment in the charging station and can effectively improve the charging speed of the charging gun, especially for the current new energy vehicles with long cruising range and large battery capacity. When there are few charging vehicles during the day, the idle power can be switched to the adjacent charging guns with larger power demand, thereby increasing the vehicle charging speed and reducing the vehicle charging time; when there are many charging vehicles at night, multiple guns can output at the same time to meet the charging needs of multiple users at the same time.
[0101] The renovation of old stations will greatly reduce the investment costs of operators. Distributed charging piles can be built directly without changing the original power distribution electrical infrastructure. Newly built charging piles with power sharing functions will also meet customers' requirements for increased charging speeds.
[0102] Those of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be implemented by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), etc.
[0103] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0104] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.
Claims
1. A power resource sharing control method for a distributed charging pile, characterized in that: The power resource sharing control method is applied to a distributed charging pile, wherein the distributed charging pile includes N charging piles, the N charging piles are connected according to a preset rule, and the charging piles are connected through a communication line and a power line; the power resource sharing control method includes the following steps: The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information; the power resource status information at least includes the maximum available charging power and usage status of the charging pile; the current charging pile is the charging pile that is being started to charge the electrical equipment among the charging piles; the virtual power module establishes a virtual image corresponding to the power resource status information in its memory for the current charging pile, and changes in real time with the maximum available charging power and usage status of the charging pile; When the current charging pile starts to charge the electric device, the current required power of the electric device is obtained, and a local power module is allocated to the electric device based on the current required power; the local power module is a power module carried by the current charging pile itself; When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the virtual power module is searched based on the power shortage, and a target virtual power module is allocated to the power-consuming device; the target virtual power module is one or more virtual power modules whose maximum available charging power satisfies the power shortage; the power shortage is the difference between the required power and the maximum available charging power of the local power module; The current charging pile checks the current required power of the electric equipment in real time or periodically; When the current charging pile determines that the current required power is less than the maximum available charging power of the local power module, and the overflow power is greater than or equal to the maximum available charging power of the target virtual power module, controlling the release of the corresponding charging power of the target virtual power module; When the current charging pile determines that the current required power is equal to zero, controlling the release of the charging power of the local power module and the charging power of the target virtual power module; The power resource status information also includes the charging strategy configured for the charging pile; the charging strategy is a high-power priority charging strategy or a local priority charging strategy; the virtual power module configured for the high-power priority charging strategy is defined as a first-class virtual power module; the virtual power module configured for the local priority charging strategy is defined as a second-class virtual power module; When the maximum available charging power of the local power module is less than the current required power, the current charging pile searches for the virtual power module based on the power shortage and allocates a target virtual power module to the power-consuming device, including the following steps: When the maximum available charging power of the local power module of the current charging pile is less than the current required power, searching the first type of virtual power module and the second type of virtual power module in an idle state from the virtual power modules; The current charging pile searches for the first type of virtual power module and the second type of virtual power module in an idle state based on the power shortage, and allocates a target virtual power module to the power-consuming device; If the target virtual power module is the first type of virtual power module, when the charging pile corresponding to the target virtual power module is connected to an electric device, the charging pile corresponding to the target virtual power module sends a prompt message to the electric device connected to the charging pile corresponding to the target virtual power module to prompt that the charging power of the charging pile corresponding to the target virtual power module is occupied; or If the target virtual power module is the first type of virtual power module, and the charging pile corresponding to the target virtual power module is already charging the electrical equipment, the current charging pile controls the charging pile corresponding to the target virtual power module to stop charging the electrical equipment, and controls the charging pile corresponding to the target virtual power module to switch the charging power to the current charging pile.
2. The power resource sharing control method of a distributed charging stack according to claim 1, characterized in that: The power resource sharing control method further comprises the steps of: If the target virtual power module is the second type of virtual power module in an idle state, when the charging pile corresponding to the target virtual power module is connected to an electrical equipment, the charging pile corresponding to the target virtual power module sends a power release request to the current charging pile, and the current charging pile responds to the power release request and releases the charging power of the target virtual power module.
3. The power resource sharing control method of a distributed charging stack according to claim 1 or 2, characterized in that: The use state is an idle state, a fault state or an occupied state; When the maximum available charging power of the local power module is less than the current required power, the current charging pile searches for the virtual power module based on the power shortage and allocates a target virtual power module to the power-consuming device, including the following steps: When the maximum available charging power of the local power module is less than the current required power, the current charging pile compares the power shortage with the maximum available charging power of the virtual power module; If there is a virtual power module whose maximum available charging power is equal to the power shortage, taking the virtual power module whose maximum available charging power is equal to the power shortage as the target virtual power module; If there is no virtual power module whose maximum available charging power is equal to the power shortage, but there is a virtual power module whose maximum available charging power is greater than the power shortage, the virtual power module whose maximum available charging power is greater than the power shortage is used as the target virtual power module; If there is no virtual power module whose maximum available charging power is greater than or equal to the power shortage, two or more virtual power modules whose sum of maximum available charging power is equal to or greater than the power shortage are used as target virtual power modules; The current charging pile sends a control instruction to the charging pile corresponding to the target virtual power module, controls the charging pile corresponding to the target virtual power module to switch to a charging power equal to the power shortage, and controls the charging pile corresponding to the target virtual power module to switch the use state to the occupied state.
4. The power resource sharing control method of a distributed charging stack according to claim 1 or 2, characterized in that: The preset rule is to connect in sequence, and the N charging piles are connected in sequence to form a linear distributed charging pile; In the step of the current charging pile acquiring the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishing a virtual power module corresponding to the power resource status information one by one according to the power resource status information: The current charging pile obtains the power resource status information of the charging pile directly connected to the current charging pile; if the current charging pile is located at the head or tail of the linear distributed charging pile, a virtual power module is established in the current charging pile; if the current charging pile is located in the middle of the linear distributed charging pile, two virtual power modules are established in the current charging pile.
5. The power resource sharing control method of a distributed charging stack according to claim 1 or 2, characterized in that: The preset rule is to connect the N charging piles end to end in sequence, and the N charging piles are connected end to end in sequence to form a ring-shaped distributed charging pile; the local power module includes M local power submodules; In the step of the current charging pile acquiring the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishing a virtual power module corresponding to the power resource status information one by one according to the power resource status information: The current charging pile obtains power resource status information of a charging pile directly connected to the current charging pile, and two virtual power modules are established in the current charging pile.
6. The power resource sharing control method of a distributed charging stack according to claim 1 or 2, characterized in that: The preset rule is to connect the N charging piles end to end in sequence, and the N charging piles are connected end to end in sequence to form a ring-shaped distributed charging pile; the local power module includes M local power submodules; In the step of the current charging pile acquiring the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishing a virtual power module corresponding to the power resource status information one by one according to the power resource status information: The current charging pile obtains the other charging piles except the current charging pile, and N-1 virtual power modules are established in the current charging pile.
7. A distributed charging stack, characterized in that: The distributed charging pile includes N charging piles, the N charging piles are connected according to a preset rule, the power control modules of the charging piles are connected via a communication line, the local power modules of the charging piles are connected via a power line, and the local power modules of the charging piles are also connected to the charging guns of the charging piles via a power line; The distributed charging stack performs the following steps: The current charging pile obtains the power resource status information sent by the corresponding charging pile through the communication line, and the current charging pile establishes a virtual power module corresponding to the power resource status information according to the power resource status information; the power resource status information at least includes the maximum available charging power and usage status of the charging pile; the current charging pile is the charging pile that is being started to charge the electrical equipment among the charging piles; the virtual power module establishes a virtual image corresponding to the power resource status information in its memory for the current charging pile, and changes in real time with the maximum available charging power and usage status of the charging pile; When the current charging pile starts to charge the electric device, the current required power of the electric device is obtained, and a local power module is allocated to the electric device based on the current required power; the local power module is a power module carried by the current charging pile itself; When the maximum available charging power of the local power module of the current charging pile is less than the current required power, the virtual power module is searched based on the power shortage, and a target virtual power module is allocated to the power-consuming device; the target virtual power module is one or more virtual power modules whose maximum available charging power satisfies the power shortage; the power shortage is the difference between the required power and the maximum available charging power of the local power module; The current charging pile checks the current required power of the electric equipment in real time or periodically; When the current charging pile determines that the current required power is less than the maximum available charging power of the local power module, and the overflow power is greater than or equal to the maximum available charging power of the target virtual power module, controlling the release of the corresponding charging power of the target virtual power module; When the current charging pile determines that the current required power is equal to zero, controlling the release of the charging power of the local power module and the charging power of the target virtual power module; The power resource status information also includes the charging strategy configured for the charging pile; the charging strategy is a high-power priority charging strategy or a local priority charging strategy; the virtual power module configured for the high-power priority charging strategy is defined as a first-class virtual power module; the virtual power module configured for the local priority charging strategy is defined as a second-class virtual power module; When the maximum available charging power of the local power module is less than the current required power, the current charging pile searches for the virtual power module based on the power shortage and allocates a target virtual power module to the power-consuming device, including the following steps: When the maximum available charging power of the local power module of the current charging pile is less than the current required power, searching the first type of virtual power module and the second type of virtual power module in an idle state from the virtual power modules; The current charging pile searches for the first type of virtual power module and the second type of virtual power module in an idle state based on the power shortage, and allocates a target virtual power module to the power-consuming device; If the target virtual power module is the first type of virtual power module, when the charging pile corresponding to the target virtual power module is connected to an electric device, the charging pile corresponding to the target virtual power module sends a prompt message to the electric device connected to the charging pile corresponding to the target virtual power module to prompt that the charging power of the charging pile corresponding to the target virtual power module is occupied; or If the target virtual power module is the first type of virtual power module, and the charging pile corresponding to the target virtual power module is already charging the electrical equipment, the current charging pile controls the charging pile corresponding to the target virtual power module to stop charging the electrical equipment, and controls the charging pile corresponding to the target virtual power module to switch the charging power to the current charging pile.
Citation Information
Patent Citations
Intelligent dynamic power allocating charging method
CN109606180A
Control method for autonomous coordination power between charging piles
CN112319293A
System and method for dynamically adjusting power of charging pile based on field bus
CN114248657A
Virtual power plant-oriented large-scale charging pile energy optimization management method and system
CN114784896A
Power sharing charging system and charging station
CN118124441A