A method for joint dispatching of park equipment

By building a three-dimensional model and real-time positioning technology, combined with production plan analysis, intelligent scheduling of mining park equipment is realized, which solves the problem of equipment scheduling lag in existing technologies and improves production efficiency and cost control.

CN118504949BActive Publication Date: 2024-10-29ZIJIN ZHIXIN (XIAMEN) TECH CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410963098.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-18
Publication Date
2024-10-29
Estimated Expiration
2044-07-18

AI Technical Summary

Technical Problem

The existing monitoring methods and equipment joint dispatching in mining parks are lagging behind and lack flexibility, resulting in the failure to achieve automation, informatization and intelligence in management, affecting production efficiency and cost control.

Method used

By using remote sensing radar images, mine design drawings and laser scanning technology to build a three-dimensional model, combined with the positioning module, inertial navigation module and visual positioning module, the location and attribute information of personnel and equipment are collected and displayed in real time, and based on the production plan and actual progress. Equipment scheduling planning, calculation of equipment saving or supplementary man-hours.

Benefits of technology

Real-time grasp of the precise location and attribute information of the park is achieved, timely discovery of early, on-time or lagging situations in the production process, reasonable arrangement of equipment and personnel, improved equipment utilization efficiency and production efficiency, and reduced cost investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118504949B_ABST
    Figure CN118504949B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of equipment scheduling in mining areas, and in particular to a method for joint scheduling of equipment in a park. The present invention constructs a park model by integrating remote sensing radar images, mine design drawings, laser scanning and other data collection and processing methods, which can present the real situation of the park more comprehensively and accurately, install positioning and attribute marking modules for personnel wearable devices and mining equipment, and can grasp the position and attribute information of personnel and equipment in real time. The wearable device is also provided with a visual positioning module, which can determine the real-time position according to the acquisition screen when the signal is missing to establish a workload calculation model for each mining equipment, and can accurately calculate the saved working hours or required working hours of the equipment according to the changes in the production progress. When the production progress is ahead of schedule, idle equipment can be reasonably arranged to avoid idle resources; when the production progress lags behind, idle equipment can be deployed in time to make up for the working hours, thereby greatly improving the utilization efficiency and production efficiency of the equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mining equipment scheduling, and in particular to a method for joint scheduling of park equipment. Background Art

[0002] In a mining park, the safety management of personnel is crucial to production efficiency and cost control. However, the existing monitoring methods and joint scheduling are relatively backward and not flexible enough. The park's floor plan display is relatively simple, the positioning of personnel is quite dependent on the environment, and the connection between various equipment is not smooth enough, resulting in the failure to achieve automation, informatization, and intelligence in the park's management;

[0003] Therefore, a method for joint scheduling of park equipment is proposed to address the above problems. Summary of the invention

[0004] The purpose of the present invention is to provide a method for joint scheduling of park equipment to solve the problems raised in the above background technology.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] A method for joint scheduling of park equipment includes the following steps:

[0007] Step S1, establishing a park model; first, using remote sensing radar images to establish a ground three-dimensional model of the park, then constructing a three-dimensional model according to the mine design drawings, and then using laser scanning to obtain high-precision data of key areas of the mine to improve the fuzzy areas in the three-dimensional model to obtain a three-dimensional model of the mine, and finally integrating the ground three-dimensional model and the mine three-dimensional model to obtain a park model;

[0008] Step S2, collecting the attributes and positions of equipment and personnel; installing the positioning module, inertial navigation module and visual positioning module on the wearable device, locating the personnel position, and marking the attributes of the personnel wearable device; installing the identity authentication module, equipment location determination module and equipment status monitoring module on the mining area equipment, locating the mining area equipment position, and marking the attributes of the mining area equipment; displaying the personnel position and mining area equipment position on the park model in real time;

[0009] Step S3, production progress analysis: receiving the production plan of the park, formulating a time schedule for each task according to the production plan, collecting the actual production progress of each task in the park in real time, estimating the actual completion time of the task based on the actual production progress, obtaining an estimated time schedule, and comparing it with the time schedule;

[0010] Step S4, carry out equipment scheduling planning according to the production schedule; establish a workload calculation model for each mining area equipment, receive comparison data of the estimated time schedule and the time schedule, when the estimated time schedule is earlier than the time threshold of the time schedule, determine the time difference between the estimated time schedule and the time schedule, calculate the saved working hours of the corresponding mining area equipment according to the time difference combined with the daily workload calculation model of the mining area equipment, determine the working hours saved by the mining area equipment in each task and the corresponding mining area equipment for statistics, and obtain idle equipment data; when the estimated time schedule exceeds the time threshold of the time schedule, determine the overtime value of the estimated time schedule and the time schedule, calculate the required working hours of the corresponding mining area equipment according to the overtime value combined with the daily workload calculation model of the mining area equipment, retrieve the corresponding mining area equipment in the idle equipment data for deployment, and make up for the required working hours of the corresponding mining area equipment.

[0011] As a preferred solution, when using remote sensing radar images to establish a ground three-dimensional model of the park, satellite remote sensing and unmanned aerial vehicle radar are first used to collect remote sensing radar image data of the park in all directions, and the collected remote sensing radar image data are subjected to radiation correction, geometric correction, and filtering and denoising operations to obtain pre-processed remote sensing radar image data, and point cloud data of feature objects in the pre-processed remote sensing radar image data are extracted, and the point cloud data are classified and filtered. A triangulated network is constructed based on the classified and filtered point cloud data, and on the basis of the triangulated network, a ground three-dimensional model of the park is generated through interpolation and fitting methods.

[0012] As a preferred solution, when constructing a three-dimensional model of a mine, the mine design drawings are first analyzed to obtain the layout, structure, and size data of the mine in the mine design drawings, and the tunnels, mining faces, ventilation facilities, and transportation systems in the mine design drawings are marked. A three-dimensional model is established based on the layout, structure, and size data of the mine in the mine design drawings. A laser scanner is used to scan the key areas of the mine along the scanning route to obtain point cloud data of the laser scan, and noise points and abnormal points in the point cloud data are removed. The point cloud data excluding the noise points and abnormal points is integrated into the three-dimensional model to obtain a three-dimensional model of the mine.

[0013] As a preferred solution, when constructing the park model, the ground 3D model and the mine 3D model are converted into a compatible format, a unified coordinate system is determined, the coordinates of the ground 3D model and the mine 3D model are converted into a unified coordinate system, the ground 3D model and the mine 3D model are respectively imported into the same scene for fusion, the overlapping parts of the ground 3D model and the mine 3D model are smoothed to obtain the park model.

[0014] As a preferred solution, when marking the attributes of personnel wearable devices, the marking content includes the type of personnel and the type of task; when marking the attributes of mining equipment, the marking content includes the equipment type, equipment model, maintenance information and task type.

[0015] As a preferred solution, the specific steps of production progress analysis are:

[0016] Decompose each task in the production plan and clarify the order and dependencies of the tasks;

[0017] Allocate time resources, mine equipment configuration and personnel arrangements for each task;

[0018] Real-time collection of actual production progress, including manual reporting and automatic collection by sensors;

[0019] Analyze the completion ratio and remaining workload of tasks based on the actual production progress data collected;

[0020] Based on the current work efficiency and resource input, estimate the time required for the remaining work;

[0021] Compare the estimated time schedule with the original time schedule one by one, find out the tasks that are completed ahead of schedule, on time and behind schedule, and calculate the degree of deviation.

[0022] As a preferred solution, when establishing a workload calculation model for each mining equipment, first collect the basic information of each mining equipment, the basic information includes equipment model, specifications, purchase time, collect daily working time data of mining equipment over a period of time, record the workload completed by mining equipment every day, collect maintenance and servicing records of mining equipment, the maintenance records include maintenance time, maintenance interval and time used, first calculate the workload completed per hour of the mining equipment based on the daily working time data of the mining equipment and the workload completed every day, count the workload completed in multiple hours and calculate the average workload, determine the average workload as the standard workload per hour of the mining equipment, take time as the axis, take the purchase time as the starting point of mining equipment maintenance, synchronize the time of each maintenance of the mining equipment and the time used for maintenance to the time axis according to the maintenance interval, synchronize the standard workload per hour of the mining equipment to the time axis, and obtain the workload calculation model of the mining equipment.

[0023] It can be seen from the technical solution provided by the present invention that the method for joint scheduling of park equipment provided by the present invention has the following beneficial effects:

[0024] 1. The park model constructed by integrating remote sensing radar images, mine design drawings, laser scanning and other data collection and processing methods can present the real situation of the park more comprehensively and accurately. Positioning and attribute marking modules are installed for personnel wearable devices and mining equipment to grasp the location and attribute information of personnel and equipment in real time. The visual positioning module is also set on the wearable device to determine the real-time position based on the collected picture when the signal is missing;

[0025] 2. By formulating detailed production plans and time schedules, and collecting and analyzing the actual production progress in real time, it is possible to timely discover the advance, on-time or delayed situations in the production process, and make corresponding adjustment strategies;

[0026] 3. Establish a workload calculation model for equipment in each mining area, which can accurately calculate the equipment's saved working hours or required working hours according to changes in production progress. When the production progress is ahead of schedule, idle equipment can be reasonably arranged to avoid idle resources; when the production progress lags behind, idle equipment can be deployed in time to make up for the working hours and ensure that production tasks are completed on time, thereby greatly improving the utilization efficiency and production efficiency of equipment. Accurate equipment scheduling planning and personnel allocation can avoid losses caused by excessive use or idleness of equipment, as well as ineffective labor of personnel, thereby reducing cost investment in the production process. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the overall structure of a method for joint scheduling of park equipment according to the present invention;

[0028] Figure 2 It is a schematic diagram of the scheduling system structure in the present invention. DETAILED DESCRIPTION

[0029] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0030] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0031] like Figure 1 As shown, an embodiment of the present invention provides a method for joint scheduling of campus equipment, including the following steps:

[0032] Step S1, establishing a park model; first, using remote sensing radar images to establish a ground three-dimensional model of the park, then constructing a three-dimensional model according to the mine design drawings, and then using laser scanning to obtain high-precision data of key areas of the mine to improve the fuzzy areas in the three-dimensional model to obtain a three-dimensional model of the mine, and finally integrating the ground three-dimensional model and the mine three-dimensional model to obtain a park model;

[0033] When using remote sensing radar images to establish a ground three-dimensional model of the park, first use satellite remote sensing and drone-mounted radar to collect all-round remote sensing radar image data of the park, perform radiation correction, geometric correction, and filtering and denoising operations on the collected remote sensing radar image data to obtain pre-processed remote sensing radar image data, extract point cloud data of feature objects in the pre-processed remote sensing radar image data, classify and filter the point cloud data, and construct a triangulated network based on the classified and filtered point cloud data. On the basis of the triangulated network, generate a ground three-dimensional model of the park through interpolation and fitting methods;

[0034] Furthermore, when constructing the three-dimensional model of the mine, the mine design drawings are first analyzed to obtain the layout, structure, and size data of the mine in the mine design drawings, and the tunnels, mining faces, ventilation facilities, and transportation systems in the mine design drawings are marked. A three-dimensional model is established based on the layout, structure, and size data of the mine in the mine design drawings. A laser scanner is used to scan the key areas of the mine according to the scanning route to obtain point cloud data of the laser scan, and noise points and abnormal points in the point cloud data are removed. The point cloud data except for the noise points and abnormal points is integrated into the three-dimensional model to obtain the three-dimensional model of the mine;

[0035] When constructing the park model, the ground 3D model and the mine 3D model are converted into a compatible format, a unified coordinate system is determined, the coordinates of the ground 3D model and the mine 3D model are converted into the unified coordinate system, the ground 3D model and the mine 3D model are respectively imported into the same scene for fusion, and the overlapping parts of the ground 3D model and the mine 3D model are smoothed to obtain the park model;

[0036] Step S2, collecting the attributes and positions of equipment and personnel; installing the positioning module, inertial navigation module and visual positioning module on the wearable device, locating the personnel position, and marking the attributes of the personnel wearable device; installing the identity authentication module, equipment location determination module and equipment status monitoring module on the mining area equipment, locating the mining area equipment position, and marking the attributes of the mining area equipment; displaying the personnel position and mining area equipment position on the park model in real time;

[0037] Furthermore, when the attributes of personnel wearable devices are marked, the marking content includes the type of personnel and the type of task; when the attributes of mining equipment are marked, the marking content includes the equipment type, equipment model, maintenance information and task type;

[0038] Step S3, production progress analysis: receiving the production plan of the park, formulating a time schedule for each task according to the production plan, collecting the actual production progress of each task in the park in real time, estimating the actual completion time of the task based on the actual production progress, obtaining an estimated time schedule, and comparing it with the time schedule; the specific steps of production progress analysis are:

[0039] Decompose each task in the production plan and clarify the order and dependencies of the tasks;

[0040] Allocate time resources, mine equipment configuration and personnel arrangements for each task;

[0041] Real-time collection of actual production progress, including manual reporting and automatic collection by sensors;

[0042] Analyze the completion ratio and remaining workload of tasks based on the actual production progress data collected;

[0043] Based on the current work efficiency and resource input, estimate the time required for the remaining work;

[0044] Compare the estimated time schedule with the original time schedule one by one, find out the tasks that are completed ahead of schedule, on time and behind schedule, and calculate the degree of deviation;

[0045] Step S4, carry out equipment scheduling planning according to the production schedule; establish a workload calculation model for each mining area equipment, receive comparison data of the estimated time schedule and the time schedule, when the estimated time schedule is earlier than the time threshold of the time schedule, determine the time difference between the estimated time schedule and the time schedule, calculate the saved working hours of the corresponding mining area equipment according to the time difference combined with the daily workload calculation model of the mining area equipment, determine the working hours saved by the mining area equipment in each task and the corresponding mining area equipment for statistics, obtain idle equipment data, when the estimated time schedule exceeds the time threshold of the time schedule, determine the overtime value of the estimated time schedule and the time schedule, calculate the required working hours of the corresponding mining area equipment according to the overtime value combined with the daily workload calculation model of the mining area equipment, call the corresponding mining area equipment in the idle equipment data for deployment, and make up for the required working hours of the corresponding mining area equipment;

[0046] Furthermore, when establishing a workload calculation model for each mining equipment, first collect the basic information of each mining equipment, the basic information includes equipment model, specifications, and purchase time, collect daily working time data of mining equipment over a period of time, record the workload completed by mining equipment every day, and collect maintenance and servicing records of mining equipment. The maintenance records include maintenance time, maintenance intervals, and time used. First, calculate the workload completed per hour of the mining equipment based on the daily working time data of the mining equipment and the workload completed every day, count the workload completed in multiple hours and calculate the average workload, determine the average workload as the standard workload per hour of the mining equipment, take time as the axis, take the purchase time as the starting point of mining equipment maintenance, synchronize the time of each maintenance of the mining equipment and the time used for maintenance to the time axis according to the maintenance interval, synchronize the standard workload per hour of the mining equipment to the time axis, and obtain the workload calculation model of the mining equipment.

[0047] The above-mentioned method of joint dispatching of park equipment is based on the dispatching system. Figure 2 , the scheduling system includes:

[0048] Collection end: The collection end includes:

[0049] The positioning module, inertial navigation module and visual positioning module are installed on the wearable device. The positioning module is used to locate the real-time position of the wearable device. The inertial navigation module includes an accelerometer and a gyroscope. In an environment where satellite signals cannot be received, the inertial navigation module can autonomously provide accurate position, speed and attitude information to ensure the continuity and reliability of navigation. The working principle of the visual positioning module usually involves the following steps: First, the image or video of the scene is obtained through a camera or other image acquisition device; then, the image processing algorithm is used to analyze and extract features from these images, such as identifying the edge, shape, color and other features of the object; then, the extracted features are matched and compared with the park model to determine the location of the wearable device;

[0050] The identity authentication module, equipment location determination module and equipment status monitoring module installed on the mining equipment. The identity authentication module includes a face recognition camera to recognize the face of the person and determine the driver's information. The equipment location determination module is a Beidou positioning module or GPS positioning module integrated with inertial navigation to locate the equipment in real time. The equipment status monitoring module collects the operating computer of the mining equipment and collects the operating data of the operating computer;

[0051] The dispatch center includes:

[0052] The park model building module uses remote sensing radar images to build a ground 3D model of the park, then builds a 3D model based on the mine design drawings, and then uses laser scanning to obtain high-precision data of key areas of the mine to improve the fuzzy areas in the 3D model to obtain a 3D model of the mine. Finally, the ground 3D model and the mine 3D model are integrated to obtain the park model;

[0053] Equipment attribute classification module: The equipment attribute classification module is used to mark the attributes of mining equipment. When marking the attributes of personnel wearable equipment, the marking content includes the type of personnel and the type of task; when marking the attributes of mining equipment, the marking content includes the equipment type, equipment model, maintenance information and task type;

[0054] The production progress analysis module receives the production plan of the park, formulates a time schedule for each task according to the production plan, collects the actual production progress of each task in the park in real time, estimates the actual completion time of the task based on the actual production progress, obtains the estimated time schedule, and compares it with the time schedule; the specific steps of production progress analysis are:

[0055] Decompose each task in the production plan and clarify the order and dependencies of the tasks;

[0056] Allocate time resources, mine equipment configuration and personnel arrangements for each task;

[0057] Real-time collection of actual production progress, including manual reporting and automatic collection by sensors;

[0058] Analyze the completion ratio and remaining workload of tasks based on the actual production progress data collected;

[0059] Based on the current work efficiency and resource input, estimate the time required for the remaining work;

[0060] Compare the estimated time schedule with the original time schedule one by one, find out the tasks that are completed ahead of schedule, on time and behind schedule, and calculate the degree of deviation;

[0061] Equipment scheduling and planning module: The equipment scheduling and planning module establishes a workload calculation model for each mining equipment, receives comparison data of the estimated time schedule and the time schedule, and when the estimated time schedule is earlier than the time threshold of the time schedule, determines the time difference between the estimated time schedule and the time schedule, and calculates the saved working hours of the corresponding mining equipment based on the time difference combined with the daily workload calculation model of the mining equipment, determines the length of working hours saved by the mining equipment in each task and the corresponding mining equipment for statistics, and obtains idle equipment data. When the estimated time schedule exceeds the time threshold of the time schedule, determines the overtime value of the estimated time schedule and the time schedule, and calculates the required working hours of the corresponding mining equipment based on the overtime value combined with the daily workload calculation model of the mining equipment, and retrieves the corresponding mining equipment in the idle equipment data for deployment to make up for the required working hours of the corresponding mining equipment;

[0062] User interaction module, the user interaction module establishes communication connections with the user terminal, wearable devices and mining equipment. The user terminal uploads the production plan of the park. At the same time, when an unexpected situation occurs and emergency dispatch of mining equipment is required, the user terminal edits the required equipment information and construction location and uploads it to the user interaction module. The user interaction module generates scheduling information and sends it to the wearable device and mining equipment synchronously.

[0063] In this embodiment, when the user interaction module performs equipment and personnel scheduling in the mining area, the user interaction module takes the construction location as the origin and performs the scheduling of equipment and personnel in the mining area based on the principle of proximity.

[0064] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for joint scheduling of park equipment, characterized in that: The following steps are involved: Step S1, establishing a park model; first, using remote sensing radar images to establish a ground three-dimensional model of the park, then constructing a three-dimensional model according to the mine design drawings, and then using laser scanning to obtain high-precision data of key areas of the mine to improve the fuzzy areas in the three-dimensional model to obtain a three-dimensional model of the mine, and finally integrating the ground three-dimensional model and the mine three-dimensional model to obtain a park model; When using remote sensing radar images to establish a ground three-dimensional model of the park, first use satellite remote sensing and drone-mounted radar to collect all-round remote sensing radar image data of the park, perform radiation correction, geometric correction, and filtering and denoising operations on the collected remote sensing radar image data to obtain pre-processed remote sensing radar image data, extract point cloud data of feature objects in the pre-processed remote sensing radar image data, classify and filter the point cloud data, and construct a triangulated network based on the classified and filtered point cloud data. On the basis of the triangulated network, generate a ground three-dimensional model of the park through interpolation and fitting methods; When constructing a three-dimensional model of a mine, first analyze the mine design drawings, obtain the layout, structure, and size data of the mine in the mine design drawings, and mark the tunnels, mining faces, ventilation facilities, and transportation systems in the mine design drawings. A three-dimensional model is established based on the layout, structure, and size data of the mine in the mine design drawings. A laser scanner is used to scan the key areas of the mine according to the scanning route to obtain point cloud data of the laser scan, remove noise points and abnormal points in the point cloud data, and integrate the point cloud data except for the noise points and abnormal points into the three-dimensional model to obtain a three-dimensional model of the mine. When constructing the park model, the ground 3D model and the mine 3D model are converted into a compatible format, a unified coordinate system is determined, the coordinates of the ground 3D model and the mine 3D model are converted into the unified coordinate system, the ground 3D model and the mine 3D model are respectively imported into the same scene for fusion, and the overlapping parts of the ground 3D model and the mine 3D model are smoothed to obtain the park model; Step S2, collecting the attributes and positions of equipment and personnel; installing the positioning module, inertial navigation module and visual positioning module on the wearable device, locating the personnel position, and marking the attributes of the personnel wearable device; installing the identity authentication module, equipment location determination module and equipment status monitoring module on the mining area equipment, locating the mining area equipment position, and marking the attributes of the mining area equipment; displaying the personnel position and mining area equipment position on the park model in real time; When marking the attributes of personnel wearable equipment, the marking content includes the type of personnel and the type of task; when marking the attributes of mining equipment, the marking content includes the equipment type, equipment model, maintenance information and task type; Step S3, production progress analysis: receiving the production plan of the park, formulating a time schedule for each task according to the production plan, collecting the actual production progress of each task in the park in real time, estimating the actual completion time of the task based on the actual production progress, obtaining an estimated time schedule, and comparing it with the time schedule; the specific steps of production progress analysis are: Decompose each task in the production plan and clarify the order and dependencies of the tasks; Allocate time resources, mine equipment configuration and personnel arrangements for each task; Real-time collection of actual production progress, including manual reporting and automatic collection by sensors; Analyze the completion ratio and remaining workload of tasks based on the actual production progress data collected; Based on the current work efficiency and resource input, estimate the time required for the remaining work; Compare the estimated time schedule with the original time schedule one by one, find out the tasks that are completed ahead of schedule, on time and behind schedule, and calculate the degree of deviation; Step S4, carry out equipment scheduling planning according to the production schedule; establish a workload calculation model for each mining area equipment, receive comparison data of the estimated time schedule and the time schedule, when the estimated time schedule is earlier than the time threshold of the time schedule, determine the time difference between the estimated time schedule and the time schedule, calculate the saved working hours of the corresponding mining area equipment according to the time difference combined with the daily workload calculation model of the mining area equipment, determine the working hours saved by the mining area equipment in each task and the corresponding mining area equipment for statistics, obtain idle equipment data, when the estimated time schedule exceeds the time threshold of the time schedule, determine the overtime value of the estimated time schedule and the time schedule, calculate the required working hours of the corresponding mining area equipment according to the overtime value combined with the daily workload calculation model of the mining area equipment, call the corresponding mining area equipment in the idle equipment data for deployment, and make up for the required working hours of the corresponding mining area equipment; When establishing the workload calculation model of each mining area equipment, first collect the basic information of each mining area equipment, the basic information includes equipment model, specification, purchase time, collect the daily working time data of mining area equipment within a period of time, record the workload completed by mining area equipment every day, collect the maintenance and maintenance records of mining area equipment, the maintenance records include maintenance time, maintenance interval and time used, first calculate the workload completed by the mining area equipment per hour according to the daily working time data of mining area equipment and the workload completed every day, count the workload completed in multiple hours and calculate the workload mean, determine the workload mean as the standard workload per hour of the mining area equipment, take time as the axis, take the purchase time as the starting point of mining area equipment maintenance, synchronize the time of each maintenance of mining area equipment and the maintenance time to the time axis according to the maintenance interval, synchronize the standard workload per hour of the mining area equipment to the time axis, and obtain the workload calculation model of the mining area equipment; The method for joint dispatching of park equipment is completed based on a dispatching system, which includes a collection terminal and a dispatching center; The acquisition end includes: The positioning module, inertial navigation module and visual positioning module are installed on the wearable device. The positioning module is used to locate the real-time position of the wearable device. The inertial navigation module includes an accelerometer and a gyroscope. In an environment where satellite signals cannot be received, the inertial navigation module can autonomously provide accurate position, speed and attitude information to ensure the continuity and reliability of navigation. The working principle of the visual positioning module includes the following steps: Acquire images or videos of the scene through a camera or other image acquisition device; Use image processing algorithms to analyze and extract features from these images, such as identifying the edges, shapes, colors, and other features of objects; Match and compare the extracted features with the park model to determine the location of the wearable device; It also includes an identity authentication module, an equipment location determination module and an equipment status monitoring module installed on the mining equipment. The identity authentication module includes a face recognition camera to recognize the face of the person and determine the information of the driver. The equipment location determination module is a Beidou positioning module or a GPS positioning module integrated with inertial navigation to locate the equipment in real time. The equipment status monitoring module collects the operating computer of the mining equipment and collects the operating data of the operating computer; The dispatch center includes: The park model building module uses remote sensing radar images to build a ground 3D model of the park, then builds a 3D model based on the mine design drawings, and then uses laser scanning to obtain high-precision data of key areas of the mine to improve the fuzzy areas in the 3D model to obtain a 3D model of the mine. Finally, the ground 3D model and the mine 3D model are integrated to obtain the park model; Equipment attribute classification module: The equipment attribute classification module is used to mark the attributes of mining equipment. When marking the attributes of personnel wearable equipment, the marking content includes the type of personnel and the type of task; when marking the attributes of mining equipment, the marking content includes the equipment type, equipment model, maintenance information and task type; The production progress analysis module receives the production plan of the park, formulates a time schedule for each task according to the production plan, collects the actual production progress of each task in the park in real time, estimates the actual completion time of the task based on the actual production progress, obtains the estimated time schedule, and compares it with the time schedule; the specific steps of production progress analysis are: Decompose each task in the production plan and clarify the order and dependencies of the tasks; Allocate time resources, mine equipment configuration and personnel arrangements for each task; Real-time collection of actual production progress, including manual reporting and automatic collection by sensors; Analyze the completion ratio and remaining workload of tasks based on the actual production progress data collected; Based on the current work efficiency and resource input, estimate the time required for the remaining work; Compare the estimated time schedule with the original time schedule one by one, find out the tasks that are completed ahead of schedule, on time and behind schedule, and calculate the degree of deviation; Equipment scheduling and planning module: The equipment scheduling and planning module establishes a workload calculation model for each mining equipment, receives comparison data of the estimated time schedule and the time schedule, and when the estimated time schedule is earlier than the time threshold of the time schedule, determines the time difference between the estimated time schedule and the time schedule, and calculates the saved working hours of the corresponding mining equipment based on the time difference combined with the daily workload calculation model of the mining equipment, determines the length of working hours saved by the mining equipment in each task and the corresponding mining equipment for statistics, and obtains idle equipment data. When the estimated time schedule exceeds the time threshold of the time schedule, determines the overtime value of the estimated time schedule and the time schedule, and calculates the required working hours of the corresponding mining equipment based on the overtime value combined with the daily workload calculation model of the mining equipment, and retrieves the corresponding mining equipment in the idle equipment data for deployment to make up for the required working hours of the corresponding mining equipment; User interaction module: The user interaction module establishes communication connections with the user terminal, wearable devices and mining equipment. The user terminal uploads the production plan of the park. At the same time, when an unexpected situation occurs and emergency dispatch of mining equipment is required, the user terminal edits the required equipment information and construction location and uploads it to the user interaction module. The user interaction module generates dispatch information and sends it to the wearable device and mining equipment synchronously. When the user interaction module performs equipment and personnel scheduling in the mine area, it takes the construction location as the origin and schedules the equipment and personnel in the mine area based on the principle of proximity.

Citation Information

Patent Citations

  • Mine field scheduling method and system based on three-dimensional laser scanning

    CN113450019A

  • Intelligent digital mine platform construction method and platform

    CN117710133A

  • Building engineering equipment use efficiency scheduling system and method

    CN118096444A