Safety management methods, devices, equipment and media for smart highway beam yards

By generating target beam fabrication data, analyzing current beam fabrication task data and BIM twin girder field management data, predicting phase girder fabrication data, and adjusting the bridge construction plan based on planned deviation data, the problem of low safety management efficiency of the highway smart girder field is solved. problems, achieving efficient and safe management of the bridge construction process.

CN118505442BActive Publication Date: 2024-10-01CHINA RAILWAY SEVENTH BUREAU GRP XIAN RAILWAY ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410949362.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-10-01
Estimated Expiration
2044-07-16

AI Technical Summary

Technical Problem

The safety management efficiency of highway smart beam yards is low. Due to the uncertainties and unsafe factors in the highway construction process, it is difficult for the existing management methods to effectively monitor and optimize the bridge construction process.

Method used

By generating target beam fabrication data, analyzing current beam fabrication task data and BIM twin girder field management data, predicting stage beam fabrication data, and determining plan adjustment methods based on planned offset data, highway usage conditions and environmental factors to optimize the bridge Construction progress and resource allocation.

Benefits of technology

It improves the safety management efficiency of bridge construction, ensures the compliance of the bridge construction process and the efficient use of resources, detects and adjusts plan deviations in a timely manner, and improves the overall safety management efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118505442B_ABST
    Figure CN118505442B_ABST
Patent Text Reader

Abstract

The present application provides a safety management method, device, equipment and medium for a smart beam yard on a highway. The safety management method for a smart beam yard on a highway includes: generating target beam making data according to bridge construction goals and beam erection plans; determining current beam making task data according to the target beam making data; analyzing the current beam making task data and the management data of the BIM twin beam yard corresponding to the smart beam yard on the highway to determine the current beam making data, and predicting the stage beam making data for a preset management period; the current beam making data and the stage beam making data include the corresponding target preset beam body and the corresponding transportation route; determining the planned offset data according to the current beam making task data, the current beam making data, and the stage beam making data, and determining the planned adjustment method corresponding to the planned offset data based on the planned offset data, highway usage conditions, beam erection plans and environmental factors. The present application can improve the safety management efficiency of smart beam yards on highways.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of smart building technology, and in particular to a safety management method, device, equipment and medium for a smart highway beam yard. Background Art

[0002] The smart highway beam yard refers to an intelligent, digital, and automated beam yard construction and management model formed by combining the new generation of information technology with highway beam yard construction. This model realizes real-time monitoring and intelligent management of the entire process of beam production, transportation, storage, etc. by introducing Internet of Things technology, big data analysis, and intelligent control systems, so as to improve construction quality and efficiency, while improving the safety and health of the beam. The safety management of the smart highway beam yard mainly focuses on the various building materials, prefabricated beams, and various links in their production process used to build bridges on highways.

[0003] In the related technology, the production process of prefabricated beams in the smart beam yard of the highway is monitored and analyzed to determine whether there are any problems. However, highways have their own particularities. There are many uncertainties and unsafe factors in the process of building bridges on highways. Therefore, the safety management of the smart beam yard of the highway is closely related to the highway's beam construction plan. Therefore, the current safety management method has low management efficiency. Summary of the invention

[0004] The present application aims to provide a safety management method, device, equipment and medium for a smart beam yard on a highway, which can improve the safety management efficiency of the smart beam yard on the highway.

[0005] According to one aspect of the present application, a safety management method for a highway smart beam yard is proposed, comprising:

[0006] Generate target beam-making data according to bridge construction goals and beam-erecting plans;

[0007] According to the target beam-making data, determine the current beam-making task data;

[0008] Analyze the current beam-making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam-making data and predict the stage beam-making data of the preset management period; the current beam-making data and stage beam-making data include the corresponding target preset beam body and the corresponding transportation route;

[0009] The planned offset data is determined based on the current beam making task data, current beam making data and stage beam making data. The planned adjustment method corresponding to the planned offset data is determined based on the planned offset data, highway usage conditions, beam erection plan and environmental factors.

[0010] Optionally, target beam fabrication data is generated according to the bridge construction target and beam erection plan, including:

[0011] Analyze bridge construction goals to determine corresponding bridge construction needs;

[0012] Determine the corresponding bridge components according to the bridge construction requirements and the preset bridge component information;

[0013] Generate a preliminary beam-making plan based on bridge components and preset component relationships;

[0014] Based on the beam erection plan, the preliminary beam fabrication plan is updated to generate target beam fabrication data.

[0015] Optionally, according to the target beam making data, current beam making task data is determined, including:

[0016] Analyze the target beam-making data and determine the corresponding beam-making building materials, building material placement locations and transportation equipment;

[0017] According to the building material properties of the beam-making building materials, the building material placement location and the equipment properties of the transportation equipment, the target beam-making data is divided into a number of beam-making tasks; wherein the several beam-making tasks include corresponding transportation routes, task time periods and beam-making equipment;

[0018] According to the current moment, the current beam-making task data is determined from a number of beam-making tasks.

[0019] Optionally, the current beam-making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard are analyzed to determine the current beam-making data and predict the stage beam-making data of the preset management period, including:

[0020] Analyze the current beam-making task data to determine the corresponding current transportation route, current task period and current beam-making equipment;

[0021] Analyze the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam manufacturing progress at the current moment;

[0022] According to the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam making progress, the current transportation route, current task period and current beam making equipment are updated to determine the actual transportation route, actual task period and actual beam making equipment;

[0023] Determine the current beam-making data based on the actual transport route, actual task period and actual beam-making equipment;

[0024] Based on the current beam-making data and management data, predict the stage beam-making data for the preset management period.

[0025] Optionally, based on the current beam making data and management data, predicting the stage beam making data of a preset management period includes:

[0026] Perform data preprocessing on the current beam manufacturing data and management data to determine the preliminary prediction sample data:

[0027] Clean and standardize the preliminary forecast sample data to determine the target forecast sample data;

[0028] The beam-making features corresponding to the beam-making progress and the equipment efficiency of the current beam-making equipment are extracted from the current beam-making data and management data.

[0029] Transform the beam making features to determine the model application features;

[0030] Select the corresponding prediction model based on the model application characteristics;

[0031] Based on the historical prediction sample data, target prediction sample data, prediction model and preset management period, the corresponding stage beam making data is predicted.

[0032] Optionally, the planned offset data is determined according to the current beam making task data, the current beam making data, and the stage beam making data, including:

[0033] Analyze the stage beam-making data to determine the completion status of the corresponding beam-making tasks and the stage beam-making tasks;

[0034] Determine the forecast plan data based on the completion status of the beam-making task, the stage beam-making task and the current beam-making task data;

[0035] Compare the predicted plan data with the current beam manufacturing data to determine the plan offset data; wherein the plan offset data includes task progress offset, resource utilization efficiency offset, and beam quality offset.

[0036] Optionally, based on the plan deviation data, the highway usage status, the bridge erection plan and environmental factors, a plan adjustment method corresponding to the plan deviation data is determined, including:

[0037] Quantify the plan deviation data and calculate the corresponding deviation value; the deviation value includes the number of days the task progress is delayed and the percentage reduction in resource utilization efficiency;

[0038] Determine the cause of the plan deviation based on the preset deviation conditions, plan deviation data and deviation values;

[0039] Determine the target plan deviation based on highway usage, girder erection plan and environmental factors;

[0040] According to the reasons for plan deviation and target plan deviation, formulate corresponding plan adjustment methods.

[0041] According to one aspect of the present application, a safety management device for a highway smart beam yard is proposed, comprising:

[0042] The target beam-making data generation module is used to generate the target beam-making data according to the bridge construction target and beam-making plan;

[0043] The current beam-making task data determination module is used to determine the current beam-making task data according to the target beam-making data;

[0044] The beam making data determination module is used to analyze the current beam making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam making data and predict the stage beam making data of the preset management period; wherein the current beam making data and the stage beam making data include the corresponding target preset beam body and the corresponding transportation route;

[0045] The planned offset data determination module is used to determine the planned offset data based on the current beam making task data, the current beam making data, and the stage beam making data, and to determine the planned adjustment method corresponding to the planned offset data based on the planned offset data, the highway usage status, the beam erection plan and environmental factors.

[0046] Optionally, the target beam making data generating module is specifically used for:

[0047] Analyze bridge construction goals to determine corresponding bridge construction needs;

[0048] Determine the corresponding bridge components according to the bridge construction requirements and the preset bridge component information;

[0049] Generate a preliminary beam-making plan based on bridge components and preset component relationships;

[0050] Based on the beam erection plan, the preliminary beam fabrication plan is updated to generate target beam fabrication data.

[0051] Optionally, the current beam-making task data determination module is specifically used for:

[0052] Analyze the target beam-making data and determine the corresponding beam-making building materials, building material placement locations and transportation equipment;

[0053] According to the building material properties of the beam-making building materials, the building material placement location and the equipment properties of the transportation equipment, the target beam-making data is divided into a number of beam-making tasks; wherein the several beam-making tasks include corresponding transportation routes, task time periods and beam-making equipment;

[0054] According to the current moment, the current beam-making task data is determined from a number of beam-making tasks.

[0055] Optionally, the beam making data determination module is specifically used for:

[0056] Analyze the current beam-making task data to determine the corresponding current transportation route, current task period and current beam-making equipment;

[0057] Analyze the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam manufacturing progress at the current moment;

[0058] According to the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam making progress, the current transportation route, current task period and current beam making equipment are updated to determine the actual transportation route, actual task period and actual beam making equipment;

[0059] Determine the current beam-making data based on the actual transport route, actual task period and actual beam-making equipment;

[0060] Based on the current beam-making data and management data, predict the stage beam-making data for the preset management period.

[0061] Optionally, when the beam making data determination module predicts the stage beam making data of a preset management period based on the current beam making data and the management data, it is specifically used to:

[0062] Perform data preprocessing on the current beam manufacturing data and management data to determine the preliminary prediction sample data:

[0063] Clean and standardize the preliminary forecast sample data to determine the target forecast sample data;

[0064] The beam-making features corresponding to the beam-making progress and the equipment efficiency of the current beam-making equipment are extracted from the current beam-making data and management data.

[0065] Transform the beam making features to determine the model application features;

[0066] Select the corresponding prediction model based on the model application characteristics;

[0067] Based on the historical prediction sample data, target prediction sample data, prediction model and preset management period, the corresponding stage beam making data is predicted.

[0068] Optionally, when the planned offset data determination module determines the planned offset data according to the current beam making task data, the current beam making data, and the stage beam making data, it is specifically used to:

[0069] Analyze the stage beam-making data to determine the completion status of the corresponding beam-making tasks and the stage beam-making tasks;

[0070] Determine the forecast plan data based on the completion status of the beam-making task, the stage beam-making task and the current beam-making task data;

[0071] Compare the predicted plan data with the current beam manufacturing data to determine the plan offset data; wherein the plan offset data includes task progress offset, resource utilization efficiency offset, and beam quality offset.

[0072] Optionally, when the plan offset data determination module determines the plan adjustment method corresponding to the plan offset data based on the plan offset data, the highway usage status, the bridge erection plan and environmental factors, it is specifically used to:

[0073] Quantify the plan deviation data and calculate the corresponding deviation value; the deviation value includes the number of days the task progress is delayed and the percentage reduction in resource utilization efficiency;

[0074] Determine the cause of the plan deviation based on the preset deviation conditions, plan deviation data and deviation values;

[0075] Determine the target plan deviation based on highway usage, girder erection plan and environmental factors;

[0076] According to the reasons for plan deviation and target plan deviation, formulate corresponding plan adjustment methods.

[0077] Through the bridge construction goals and beam erection plan, this application can generate a beam making plan with clear goals, ensure that the entire bridge construction process has rules to follow, and reduce blindness and arbitrariness. Accurate target beam making data helps to optimize resource allocation, improve production efficiency, and ensure the quality and progress of bridge construction. Using the management data of the BIM twin beam yard to analyze the current beam making task data, it is possible to accurately grasp key information such as beam making progress, resource consumption, and equipment status, providing strong support for decision-making. Predicting the stage beam making data of the preset management period can understand the demand and trend of beam making in the future in advance, and provide a scientific basis for formulating and adjusting plans. By analyzing the current beam making task data, the current beam making data, and the stage beam making data, the planned deviation data, that is, the difference between the actual progress and the planned progress, can be discovered in time. Based on multi-dimensional information such as planned deviation data, highway usage status, beam erection plan, and environmental factors, the plan adjustment method can be quickly determined to ensure flexibility and efficiency in the bridge construction process. The overall safety management efficiency is improved.

[0078] According to one aspect of the present application, an electronic device is proposed, which includes: a processor; a memory storing a computer program, and when the computer program is executed by the processor, the processor executes the safety management method of the smart beam yard of the highway as described above.

[0079] According to one aspect of the present application, a non-transitory computer-readable medium is proposed, on which readable instructions are stored. When the instructions are executed by a processor, the processor executes the safety management method for the smart beam yard of the highway as described above.

[0080] It should be understood that the foregoing general description and the following detailed description are exemplary only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0081] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without exceeding the scope of protection required by the present application.

[0082] Figure 1 A flowchart of a safety management method for a highway smart beam yard provided in one embodiment of the present application;

[0083] Figure 2 A schematic diagram of the structure of a safety management device for a highway smart beam yard provided in one embodiment of the present application;

[0084] Figure 3 A schematic diagram of the structure of an electronic device provided in one embodiment of the present application.

[0085] Explanation of the accompanying drawings: 200, safety management device for smart beam yard of highway; 201, target beam making data generation module; 202, current beam making task data determination module; 203, beam making data determination module; 204, planned offset data determination module; 300, electronic device; 301, memory; 302, processor. DETAILED DESCRIPTION

[0086] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present application.

[0087] Due to topographic factors, environmental protection needs, traffic flow needs, geological conditions and landscape needs, bridges need to be built on highways, so the safety management requirements for various bridge components and beams used to build bridges are higher. And because of the conditions of highways being put into use, there may be a situation where bridges are built on the highway while vehicles are allowed to pass. Therefore, there may be overlaps in the beam erection plan, beam manufacturing plan and highway use conditions, resulting in complex beam transportation in the highway smart beam yard, and many hidden dangers in safety management.

[0088] Based on this, the present application provides a safety management method, device, equipment and medium for a highway smart beam yard. Considering the transportation route of the beam body at different times, the occupancy of the beam making equipment, and the occupancy of the transportation equipment, the target beam making data can be planned and adjusted. The plan can also be adjusted according to the beam erection plan, highway usage status, etc.

[0089] For specific implementation methods, please refer to the following embodiments.

[0090] Figure 1 A flowchart of a safety management method for a highway smart beam yard according to an exemplary embodiment is shown. The method of this embodiment can be applied to a safety management server. Figure 1 As shown, the method includes:

[0091] S101. Generate target beam fabrication data according to the bridge construction target and beam erection plan.

[0092] Bridge construction objectives can be used to characterize the overall requirements and expected results of bridge construction projects, usually including key indicators such as bridge design standards, service life, load-bearing capacity, traffic flow, etc. The bridge construction project can be formulated according to the relevant departments of highway bridge construction, and the bridge construction objectives can be formulated by relevant documents issued by these relevant departments.

[0093] The beam erection plan is an important part of the bridge construction process. It can specify the sequence, time nodes, required equipment, etc. of bridge erection, and is the key to ensure that bridge construction proceeds in an orderly manner according to the predetermined plan. The beam erection plan can be set by relevant staff based on the specific conditions of the highway smart beam yard, documents issued by relevant departments, etc., but the beam erection plan may change due to traffic demand, weather demand, etc.

[0094] Target beam production data can be a detailed plan for guiding the production and supply of precast beams for bridges, which is formulated according to the bridge construction goals and beam erection plans. The production quantity, specifications, production time, transportation arrangements, etc. of precast beams can be specified to ensure that precast beams can be supplied to the bridge construction site in a timely and accurate manner.

[0095] The bridge construction goal provides direction and guidance for the entire bridge construction project, and the beam erection plan is the specific steps and arrangements to achieve the bridge construction goal. Therefore, the target beam production data can be formulated based on the bridge construction goal and the beam erection plan, which is a specific plan and arrangement for the production and supply of bridge prefabricated beams. The three show a progressive relationship of goal-plan-implementation, which are interdependent and mutually influential.

[0096] According to the example embodiment, the bridge construction goal can be analyzed first to determine the key points and difficulties of beam erection and the required bridge construction type, quantity, specifications and other data. Based on this, a preliminary beam manufacturing plan can be formulated, such as beam manufacturing cycle, production process and other data content. The preliminary beam erection plan is compared with the acquired beam erection plan to determine the difference between the two, and the preliminary beam manufacturing plan is adjusted and optimized according to the bridge construction goal, thereby generating target beam manufacturing data.

[0097] S102, analyzing target beam-making data and determining current beam-making task data.

[0098] The current beam-making task data may be beam-making tasks that need to be specifically executed and completed at the current stage under the guidance of the target beam-making data. These tasks may generally include the production and supply of prefabricated beams of specific specifications and quantities.

[0099] The target beam manufacturing data is a guiding document for the production and supply of precast beams (precast beam bodies) during the entire bridge construction process, which can plan the production, transportation and installation of precast beams. The current beam manufacturing task data is a specific and executable task determined based on the target beam manufacturing data and the actual situation of the current bridge construction. The target beam manufacturing data can specifically include tasks to be performed in different time periods, specific work at different times, etc.

[0100] According to an example embodiment, based on the current moment, a search and match may be performed in the target beam-making data to extract the corresponding current beam-making task data.

[0101] S103. Analyze the current beam manufacturing task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam manufacturing data and predict the stage beam manufacturing data of the preset management period.

[0102] Among them, the current beam making data and the stage beam making data include the corresponding target preset beam body and the corresponding transportation route.

[0103] The highway smart beam yard can be a place where advanced information technology and intelligent equipment are used to intelligently manage the production, transportation, and installation of prefabricated beams for highway bridges. The BIM twin beam yard can be a digital beam yard model built based on the building information model (BIM) technology, which can reflect the production status of the actual beam yard, equipment operation status and other information in real time.

[0104] Management data may be data related to beam yard management collected, processed and stored in the highway smart beam yard and BIM twin beam yard, including building material inventory, equipment status, production progress, etc. Current beam making data may be specific data related to the current beam making task data determined based on the current beam making task data and the management data of the highway smart beam yard and BIM twin beam yard, and may include the production status and transportation route of the target preset beam body.

[0105] The staged beam making data may be data related to the staged beam making task predicted within a preset management period based on the current beam making task data and beam yard management data, and may also include the production plan and transportation route of the target prefabricated beam. The target prefabricated beam may be the bridge beam that needs to be prefabricated and installed at the current moment according to the bridge design and beam making plan. The transportation route may be the beam transportation path from the beam yard to the bridge installation location.

[0106] The current beam-making task data is the basis for executing beam-making operations. It defines the target preset beams and transportation routes that need to be produced. The highway smart beam yard and BIM twin beam yard provide real-time data for beam yard management. These data include building material inventory, equipment status, production progress, etc., which are important bases for determining and predicting beam-making data. The current beam-making data is determined based on the current beam-making task data and management data, while the stage beam-making data is obtained based on the current data and prediction model, and is used to guide the beam-making work within the preset management period.

[0107] According to the example embodiment, big data analysis technology can be used to deeply mine and analyze the current beam-making task data to identify bottlenecks and potential problems in the production process. Then, based on historical data and current production conditions, a prediction model (such as time series analysis, machine learning model, etc.) can be established to preliminarily predict the stage beam-making data within the preset management period. The preliminary prediction results are evaluated using the visualization function and simulation function of the BIM twin beam yard, and the prediction data is combined with the physical structure of the entity beam yard to obtain the stage beam-making data.

[0108] S104. Determine the planned offset data according to the current beam-making task data, the current beam-making data, and the stage beam-making data, and determine the planned adjustment method corresponding to the planned offset data based on the planned offset data, the highway usage status, the beam-making plan, and environmental factors.

[0109] Planned deviation data can be used to represent the difference between current beam-making data and stage beam-making data, reflecting the deviation between actual progress and planned progress. Highway usage conditions can include current traffic flow, road conditions, maintenance plans, etc., which may affect the progress of bridge construction and transportation arrangements.

[0110] Environmental factors may include weather, geology, construction environment, etc. These factors may have an impact on bridge construction and can be taken into account in the plan adjustment. The plan adjustment method can be used to indicate the measures and methods for adjusting the current beam manufacturing task data and plan based on the plan offset data and other related factors.

[0111] The current beam-making task data is the basis of bridge construction, and the current beam-making data is a real-time reflection of the task execution status. The stage beam-making data is the future plan data derived from the current data and the prediction model. The planned deviation data is the difference between the current beam-making data and the stage beam-making data, reflecting the deviation between the actual progress and the planned progress. The highway usage status, beam erection plan and environmental factors are important factors affecting the progress and plan adjustment of bridge construction. These factors and the planned deviation data together constitute the basis for determining the plan adjustment method.

[0112] According to an example embodiment, the current beam-making data and the stage beam-making data can be compared and analyzed to identify the planned offset data, which may include the offset amount, offset direction (advance or delay), etc. Then the beam erection plan can be analyzed to obtain the time node and sequence of each task. The pre-set and stored plan adjustment strategy is obtained, which may include the influence degree values ​​of different beam erection plans under different factors, the allowable adjustment degree values ​​of different beam erection plans, and the adjustment methods of different influence degrees under different allowable adjustment degree values. The time node, the corresponding sequence, the highway usage status and the environmental factors are used as matching factors to find and obtain the corresponding influence degree value, the allowable adjustment degree value and the plan adjustment method in the plan adjustment strategy. For example, if the offset is small and the difference between the influence degree value on the beam erection plan and the allowable adjustment degree value of the beam erection plan is small, it may only be necessary to fine-tune the production plan or work overtime to catch up. If the offset is large or the difference between the influence degree value on the beam erection plan and the allowable adjustment degree value of the beam erection plan is large, it may be necessary to rearrange the production sequence, adjust resource allocation or adjust the time node of the beam erection plan.

[0113] This embodiment can generate a beam-making plan with clear goals through bridge construction goals and beam erection plans, ensuring that the entire bridge construction process has rules to follow and reducing blindness and arbitrariness. Accurate target beam-making data helps optimize resource allocation, improve production efficiency, and ensure the quality and progress of bridge construction. By using the management data of the BIM twin beam yard to analyze the current beam-making task data, key information such as beam-making progress, resource consumption, and equipment status can be accurately grasped, providing strong support for decision-making. Predicting the stage beam-making data of the preset management period can understand the demand and trend of beam-making in the future in advance, providing a scientific basis for formulating and adjusting plans. By analyzing the current beam-making task data, the current beam-making data, and the stage beam-making data, the planned deviation data, that is, the difference between the actual progress and the planned progress, can be discovered in time. Based on multi-dimensional information such as planned deviation data, highway usage status, beam erection plan, and environmental factors, the plan adjustment method can be quickly determined to ensure flexibility and efficiency during the bridge construction process. The overall safety management efficiency is improved.

[0114] In some embodiments, when generating target beam-making data based on bridge construction goals and beam-erection plans, the bridge construction goals can be specifically analyzed to determine corresponding bridge construction requirements; corresponding bridge components can be determined based on bridge construction requirements and preset bridge component information; a preliminary beam-making plan can be generated based on the relationship between bridge components and preset components; and based on the beam-erection plan, the preliminary beam-making plan can be updated to generate target beam-making data.

[0115] The bridge construction demand can be based on the bridge construction goal, specifically determining the various resources and conditions required for bridge construction, which may include the required bridge components, construction period, etc. The preset bridge component information can be the pre-set detailed information about the bridge components, which may include the type, size, quantity, material, etc. of the components. Bridge components can be used to represent the components of a bridge, such as beams, plates, columns, etc., which are the basic units of bridge construction. The preset component relationship can represent the combination and connection relationship between bridge components, and define how the components are combined into a complete bridge structure.

[0116] The preliminary beam-making plan can be a preliminary beam-making plan based on bridge construction requirements and bridge component information, including the basic beam-making sequence and time arrangement. The target beam-making data can be the final beam-making plan obtained after updating and optimizing the preliminary beam-making plan in combination with the beam-erection plan.

[0117] The bridge construction target is the core of the entire bridge construction project and can determine the bridge construction requirements. Based on the bridge construction requirements and combined with the preset bridge component information, the required bridge components can be determined. The preset relationship between bridge components defines how the components are combined into the bridge structure and is the basis for generating a preliminary beam manufacturing plan. The preliminary beam manufacturing plan is the prototype of the target beam manufacturing data, and the target beam manufacturing data is the result of updating and optimizing the preliminary beam manufacturing plan in combination with the beam erection plan.

[0118] In some implementations, the bridge construction goal can be analyzed to clarify the key requirements of the bridge, such as the structural type, bearing capacity, and service life. According to the construction goal, the basic conditions and resources required for bridge construction are determined. According to the bridge construction goal, the specific resources and conditions required for bridge construction are refined and determined, and the specific requirements such as the type, quantity, and specifications of the required bridge components are clarified. The preset bridge component information is obtained, the bridge components that match the bridge construction requirements are selected, and the specific size, material, quantity, and other detailed information of each component are determined. According to the relationship between the bridge components and the preset components, the production sequence and combination method of the bridge components are determined, and a preliminary beam making plan is formulated, including the schedule for beam making, resource allocation, etc. The beam erection plan is analyzed to understand the specific steps and time nodes of bridge erection. Then, the preliminary beam making plan can be updated and adjusted according to the beam erection plan to ensure that the production and supply of prefabricated beams match the progress and needs of bridge erection. The updated and optimized preliminary beam making plan is the target beam making data, where the target beam making data can include the specific requirements and arrangements for each link of the production, transportation, and installation of prefabricated beams.

[0119] This embodiment can accurately identify the specific needs of bridge construction, such as bridge type, bearing capacity, service life, etc., by deeply analyzing the bridge construction goals. This precise matching ensures that the beam making plan can meet the actual use needs of the bridge and avoids resource waste and project delays caused by design mismatches. Based on the bridge construction requirements and the preset bridge component information, bridge components can be reasonably selected to ensure that the specifications, models, materials, etc. of the components meet the design requirements. This can not only improve the overall performance of the bridge, but also reduce quality problems and safety hazards caused by component mismatches. Through the preset component relationship, a preliminary beam making plan can be generated. This plan generation method based on component relationships makes the beam making plan more scientific and reasonable, and reduces the interference of human factors. At the same time, it also improves the execution efficiency and feasibility of the plan. Updating the preliminary beam making plan based on the beam erection plan can ensure that the beam making plan is synchronized with the beam erection plan. When the beam erection plan changes, the beam making plan can respond in time and make corresponding adjustments. This flexibility reduces the risk of project delays and cost increases and improves the overall efficiency of bridge construction.

[0120] In some embodiments, when determining the current beam making task data based on the target beam making data, the target beam making data can be specifically analyzed to determine the corresponding beam making building materials, building material placement locations and transportation equipment; based on the building material properties of the beam making building materials, the building material placement locations and the equipment properties of the transportation equipment, the target beam making data can be split into several beam making tasks; wherein several beam making tasks include corresponding transportation routes, task time periods and beam making equipment; based on the current time, the current beam making task data is determined from several beam making tasks.

[0121] Beam-making materials can refer to raw materials used to make prefabricated bridge beams, such as steel bars and concrete. Building material placement locations can refer to the storage locations of beam-making materials in the highway smart beam yard. Transportation equipment can refer to tools or machines used to transport beam-making materials from the storage location to the beam-making equipment, or to transport them out of the smart beam yard, such as cranes and trucks.

[0122] Building material attributes may include the physical and chemical properties of beam-making materials, such as weight, size, material, etc. Equipment attributes may include the performance parameters of transportation equipment and beam-making equipment, such as load capacity, transportation speed, production efficiency, etc. Beam-making tasks may be used to represent specific execution units divided based on target beam-making data, combined with building materials, location, and equipment information. Transport routes may be used to represent the movement path of building materials from storage locations to beam-making equipment. Task time periods may be the time period required to complete beam-making tasks. Beam-making equipment may represent equipment used to produce precast bridge beams, such as formwork, concrete mixers, etc.

[0123] In some implementations, the target beam-making data can be analyzed to understand the types, quantities, specifications, and placement locations of the required building materials, and to obtain the required transportation equipment and beam-making equipment, and to understand their performance parameters. Then, the transportation method, time, and efficiency of the building materials can be determined based on the properties of the beam-making building materials and the properties of the equipment. The target beam-making data is divided into several specific beam-making tasks according to factors such as building materials, transportation routes, task periods, and beam-making equipment. Each beam-making task should have a clear start and end time, as well as the required building materials, equipment, and transportation routes. According to the current moment, one of the several beam-making tasks is selected as the beam-making task that needs to be executed currently. The selection can be based on the urgency of the task, the availability of resources, the production sequence, etc. If necessary, the priority and execution order of the tasks can be adjusted according to the actual situation. The required building materials, equipment, and human resources are allocated to the current beam-making task data, and the responsibilities and tasks of each participant are clarified to ensure that the task can be executed smoothly.

[0124] In other implementations, execution can be started according to the requirements of the current beam-making task data, and the execution status of the task can be monitored in real time to ensure that the task can proceed smoothly as planned. If deviations or problems occur during execution, the execution plan can be adjusted and optimized in a timely manner.

[0125] This embodiment splits the complex plan into several specific beam-making tasks by deeply analyzing the beam-making building materials and transportation equipment in the target beam-making data. This process ensures the rational allocation of various resources, improves resource utilization, and reduces resource waste. Each beam-making task includes a clear transportation route, task period, and beam-making equipment, making the production process clearer and more orderly. This helps to reduce waiting time and idle time in the production process, thereby improving overall production efficiency. By splitting the target beam-making data into several beam-making tasks and determining the current beam-making task data in real time, the management department can monitor the production progress and resource allocation more accurately. This helps to discover and solve problems in a timely manner and improve management efficiency.

[0126] In some embodiments, when analyzing the current beam-making task data and the management data of the BIM twin beam yard corresponding to the smart beam yard of the highway to determine the current beam-making data and predict the stage beam-making data of the preset management period, the current beam-making task data can be specifically analyzed to determine the corresponding current transportation route, current task period and current beam-making equipment; the management data of the BIM twin beam yard corresponding to the smart beam yard of the highway can be analyzed to determine the actual activated equipment, transportation equipment occupancy, transportation route occupancy data and beam-making progress at the current moment; according to the actual activated equipment, transportation equipment occupancy, transportation route occupancy data and beam-making progress, the current transportation route, current task period and current beam-making equipment are updated to determine the actual transportation route, actual task period and actual beam-making equipment; according to the actual transportation route, actual task period and actual beam-making equipment, the current beam-making data is determined; based on the current beam-making data and management data, the stage beam-making data of the preset management period is predicted.

[0127] In some implementations, the current beam-making task data can be analyzed to determine specific requirements, which may include information such as the specifications and quantity of the target preset beam body, the required transportation route, the task period, and the beam-making equipment. From the BIM twin beam yard system corresponding to the highway smart beam yard, management data such as the actual enabled equipment at the current moment, the occupancy of the transportation equipment, the occupancy data of the transportation route, and the progress of beam-making are collected. According to the occupancy data of the transportation route, the route with the lowest idle or occupancy rate is selected as the actual transportation route. According to the equipment status and the occupancy of the transportation equipment, the task period is adjusted to ensure that the beam-making task is completed within the available time of the equipment. According to the equipment status and the actual enabled equipment, the beam-making equipment most suitable for the current task is selected. According to the updated actual transportation route, the actual task period, and the actual beam-making equipment, the current beam-making data is determined. This includes specific production plans, transportation plans, and resource allocation. Based on the current beam-making data, management data, and historical data, a prediction model (such as machine learning algorithms, time series analysis, etc.) is used to predict the stage beam-making data of the preset management period. The prediction content may include the progress of beam-making, resource requirements, possible risk points, etc. at each time point in the stage.

[0128] In other implementations, the possible impact of external factors such as weather and traffic conditions on the beam manufacturing process can be considered, and necessary adjustments and optimizations can be made to the prediction results.

[0129] This embodiment combines the current beam-making task data with the management data of the BIM twin beam yard, and this solution can monitor each link in the beam-making process in real time and dynamically, including key information such as the transportation route, task period, and beam-making equipment. This real-time monitoring ensures the efficiency and accuracy of the beam-making process. According to the actual enabled equipment, the occupancy of the transportation equipment, the occupancy data of the transportation route, and the progress of beam-making, this solution can accurately allocate resources, such as optimizing the transportation route, adjusting the task period, and selecting the best beam-making equipment. This precise allocation ensures the maximum utilization of resources and reduces resource waste. By updating the current transportation route, task period, and beam-making equipment, this solution can determine the actual transportation route, the actual task period, and the actual beam-making equipment, thereby ensuring that the beam-making task is executed according to the optimal solution. This not only improves production efficiency, but also reduces production costs. Based on the current beam-making data and management data, this solution can predict the stage beam-making data of the preset management period. This prediction function provides a scientific basis for the formulation and adjustment of the beam-making plan, which helps to discover potential problems in advance and take corresponding countermeasures.

[0130] In some embodiments, when predicting the stage beam making data of a preset management period based on the current beam making data and management data, data preprocessing can be performed on the current beam making data and management data to determine preliminary prediction sample data: the preliminary prediction sample data is cleaned and standardized to determine the target prediction sample data; the beam making features corresponding to the beam making progress and the equipment efficiency of the current beam making equipment are extracted from the current beam making data and management data. The beam making features are converted to determine the model application features; based on the model application features, the corresponding prediction model is selected; and the corresponding stage beam making data is predicted based on the historical prediction sample data, the target prediction sample data, the prediction model and the preset management period.

[0131] Data preprocessing can be used to characterize the cleaning, conversion and standardization of raw data to improve data quality and the effectiveness of model input. The preliminary prediction sample data can be a sample data set that has been preliminarily cleaned and sorted for subsequent analysis. The target prediction sample data can be a sample data set that has been standardized and directly used for prediction model input. Beam manufacturing features can represent data features related to beam manufacturing progress and equipment efficiency, such as equipment status, material consumption rate, etc. Model application features can be used to represent input features that are directly used for prediction models after conversion and selection.

[0132] The prediction model can be a mathematical model built based on historical data and algorithms to predict future beam data. The historical prediction sample data can be prediction sample data within a period of time in the past, which is used to train and adjust the prediction model. The preset management period can be a specific time period for which the beam data needs to be predicted in advance, such as the next week, month, etc.

[0133] The current beam-making data and management data are the basis for the beam-making data in the forecasting stage. They are converted into preliminary forecast sample data through data preprocessing, and then further standardized to obtain the target forecast sample data. From these data, beam-making features related to beam-making progress and equipment efficiency can be extracted and converted into model application features. Based on these model application features, a suitable forecasting model can be selected to forecast the stage beam-making data. Throughout the process, historical forecast sample data can be used to train and verify the accuracy of the forecasting model.

[0134] In some implementations, data of current beam-making task data and management data of highway smart beam yards and BIM twin beam yards can be collected. These data are integrated to form an original data set containing all necessary information. The original data set is cleaned to remove duplicate, erroneous or irrelevant data. The data is standardized so that features of different dimensions and units can be compared and analyzed. After cleaning and standardization, preliminary prediction sample data is obtained. Beam-making features related to beam-making progress, equipment efficiency, etc. are extracted from the preliminary prediction sample data. These beam-making features are transformed, such as encoding and normalization, to form model application features. According to the characteristics of the problem and the nature of the data, a suitable prediction model is selected, such as linear regression, decision tree, neural network, etc. If there is historical prediction sample data, these data can be used to train and verify the accuracy of the prediction model. The target prediction sample data and model application features are input into the prediction model, and the corresponding stage beam-making data, including beam-making progress, resource requirements, etc., are predicted according to the preset management period.

[0135] In other implementations, the prediction results may be evaluated to compare the difference between the predicted value and the actual value, and the prediction model may be optimized and adjusted according to the evaluation results to improve the accuracy of the prediction.

[0136] In this embodiment, data quality is effectively improved by performing data preprocessing on the current beam manufacturing data and management data, including data cleaning and standardization. The cleaning process can remove noise and outliers, while the standardization process makes different features comparable, providing high-quality input data for subsequent data analysis and model prediction. Based on the model application characteristics, the corresponding prediction model is selected. This step can ensure the matching of the model and the data, and select the model that best suits the current data and prediction objectives. Through accurate model selection, the accuracy and reliability of the prediction results can be improved. Through accurate prediction results, managers can better understand the beam manufacturing situation in the future, so as to make decisions and adjustments in advance. This enhanced decision support capability helps to reduce production risks, improve production efficiency and resource utilization.

[0137] In some embodiments, when determining the planned offset data based on the current beam making task data, the current beam making data, and the stage beam making data, the stage beam making data can be specifically analyzed to determine the corresponding beam making task completion status and the stage beam making task; based on the beam making task completion status, the stage beam making task and the current beam making task data, the predicted plan data can be determined; the predicted plan data and the current beam making data can be compared to determine the planned offset data; wherein the planned offset data includes task progress offset, resource utilization efficiency offset, and beam quality offset.

[0138] The completion status of the beam-making task can be a specific description of the execution progress of the current beam-making task data, including indicators such as the number and quality of completed beams. The forecast plan data can be the task completion status that is expected to be achieved at a certain point in time, calculated based on the current task, historical data, and forecast models.

[0139] Task progress deviation can represent the difference between the actual task completion progress and the predicted planned progress. Resource utilization efficiency deviation can represent the difference between the actual resource utilization efficiency and the expected resource utilization efficiency. Beam quality deviation can represent the difference between the actual produced beam quality and the expected quality standard.

[0140] The current beam-making task data is the basis for formulating the forecast plan data, and is compared with the stage beam-making task to evaluate the progress of task execution. The current beam-making data and stage beam-making data are the direct basis for determining the planned deviation data. The completion of the beam-making task is an important indicator for evaluating the deviation of the task progress. Resource utilization efficiency deviation and beam quality deviation are key components of the planned deviation data, reflecting the effectiveness of resource utilization and the compliance of product quality, respectively.

[0141] In some implementations, the quantity and quality of completed beams are evaluated based on the current beam-making data. The current beam-making task data and the stage beam-making task are compared to understand the overall situation of task execution. The forecast plan data are calculated by combining the current beam-making task data, historical data and the forecast model. The forecast plan data includes the expected task progress, resource utilization efficiency and beam quality standards. The current beam-making data is compared with the forecast plan data. The task progress offset, resource utilization efficiency offset and beam quality offset are calculated.

[0142] In other implementations, problems and bottlenecks in the beam manufacturing process can be identified based on the planned offset data, and the beam manufacturing plan can be adjusted in a timely manner to optimize resource allocation and improve production efficiency and beam quality.

[0143] By comparing the current beam manufacturing data with the forecasted plan data, this embodiment can accurately calculate the planned offset data, including the offset of task progress, resource utilization efficiency and beam quality, and provide an accurate basis for management decisions. The analysis of planned offset data helps to timely identify potential problems and bottlenecks in the beam manufacturing process, so as to take preventive measures to avoid the expansion of problems or affect subsequent production. According to the offset of resource utilization efficiency, resource allocation can be optimized, production efficiency and resource utilization can be improved, and costs can be reduced.

[0144] In some embodiments, when determining the plan adjustment method corresponding to the plan offset data based on the plan offset data, highway usage conditions, current bridge erection plan and environmental factors, the plan offset data can be specifically quantified and the corresponding deviation value can be calculated; wherein the deviation value includes the number of days the task progress is delayed and the percentage reduction in resource utilization efficiency; according to the preset offset conditions, the plan offset data and the deviation value, the cause of the plan offset is determined; according to the highway usage conditions, the current bridge erection plan and environmental factors, the target plan offset is determined; and according to the cause of the plan offset and the target plan offset, a corresponding plan adjustment method is formulated.

[0145] Quantification can be the process of converting plan deviation data into specific values ​​for mathematical calculation and analysis. Deviation values ​​can be specific values ​​that represent the degree of plan deviation after quantification, such as the number of days of delay in task progress, the percentage reduction in resource utilization efficiency, etc. The preset deviation condition can be a standard or threshold set in advance for judging the cause of plan deviation. The cause of plan deviation can be the specific reason that causes the plan deviation, which may be an external factor or an internal factor. The use status of the highway can include information such as traffic flow, road conditions, and traffic control in the construction area, which affects the transportation and erection of the beam. The target plan deviation can be the allowable plan deviation range or target value set based on the current actual situation and expected goals. The plan adjustment method can be the measures and methods for adjusting the current beam manufacturing plan and beam erection plan based on the plan deviation data and other relevant factors.

[0146] The plan deviation data is the difference between the actual execution and the plan, which is quantified to form the deviation value. The preset deviation condition is the basis for judging the cause of the plan deviation, and together with the plan deviation data and the deviation value, it determines the specific cause of the deviation. The use of expressways, the current bridge erection plan and environmental factors are external factors that affect the setting of the target plan deviation, and together with the plan deviation data and the plan deviation cause, they act on the formulation of the plan adjustment method.

[0147] In some implementations, the plan deviation data is quantified to calculate deviation values ​​such as the number of days of task progress delay and the percentage reduction in resource utilization efficiency. According to the preset deviation conditions, the specific reasons for the plan deviation are analyzed and determined in combination with the plan deviation data and the deviation values. Considering the use status of the highway, the current beam erection plan and environmental factors, possible future changes are predicted. Based on the prediction results, a reasonable target plan deviation is set to ensure that the plan adjustment is neither too conservative nor too radical. According to the reasons for the plan deviation and the target plan deviation, a specific plan adjustment method is formulated. The adjustment method may include adjusting the beam manufacturing progress, optimizing resource allocation, adjusting the transportation route, strengthening quality management, etc.

[0148] This embodiment can accurately calculate the deviation value by quantifying the plan deviation data, providing an accurate basis for plan adjustment. Combined with the preset deviation conditions and deviation values, the specific reasons for the plan deviation can be accurately analyzed, providing a basis for formulating targeted adjustment methods. Based on the comprehensive consideration of the use status of the expressway, the current bridge erection plan and environmental factors, the formulated plan adjustment method is more scientific and reasonable. The plan can be flexibly adjusted according to the actual situation to ensure the smooth progress of bridge construction.

[0149] The following describes an apparatus embodiment of the present application, which can be used to execute the method embodiment of the present application. For details not disclosed in the apparatus embodiment of the present application, reference can be made to the method embodiment of the present application.

[0150] Figure 2 This is a schematic diagram of a safety management device for a highway smart beam yard provided in one embodiment of the present application. Figure 2 As shown, the safety management device 200 of the highway smart beam yard includes a target beam making data generation module 201, a current beam making task data determination module 202, a beam making data determination module 203 and a planned offset data determination module 204.

[0151] The target beam-making data generating module 201 is used to generate the target beam-making data according to the bridge construction target and the beam-making plan;

[0152] The current beam-making task data determination module 202 is used to determine the current beam-making task data according to the target beam-making data;

[0153] The beam making data determination module 203 is used to analyze the current beam making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam making data and predict the stage beam making data of the preset management period; wherein the current beam making data and the stage beam making data include the corresponding target preset beam body and the corresponding transportation route;

[0154] The planned offset data determination module 204 is used to determine the planned offset data according to the current beam making task data, the current beam making data and the stage beam making data, and to determine the planned adjustment method corresponding to the planned offset data based on the planned offset data, the highway usage status, the beam erection plan and environmental factors.

[0155] Optionally, the target beam making data generating module 201 is specifically used for:

[0156] Analyze bridge construction goals to determine corresponding bridge construction needs;

[0157] Determine the corresponding bridge components according to the bridge construction requirements and the preset bridge component information;

[0158] Generate a preliminary beam-making plan based on bridge components and preset component relationships;

[0159] Based on the beam erection plan, the preliminary beam fabrication plan is updated to generate target beam fabrication data.

[0160] Optionally, the current beam-making task data determination module 202 is specifically used for:

[0161] Analyze the target beam-making data and determine the corresponding beam-making building materials, building material placement locations and transportation equipment;

[0162] According to the building material properties of the beam-making building materials, the building material placement location and the equipment properties of the transportation equipment, the target beam-making data is divided into a number of beam-making tasks; wherein the several beam-making tasks include corresponding transportation routes, task time periods and beam-making equipment;

[0163] According to the current moment, the current beam-making task data is determined from a number of beam-making tasks.

[0164] Optionally, the beam making data determination module 203 is specifically used for:

[0165] Analyze the current beam-making task data to determine the corresponding current transportation route, current task period and current beam-making equipment;

[0166] Analyze the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam manufacturing progress at the current moment;

[0167] According to the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam making progress, the current transportation route, current task period and current beam making equipment are updated to determine the actual transportation route, actual task period and actual beam making equipment;

[0168] Determine the current beam-making data based on the actual transport route, actual task period and actual beam-making equipment;

[0169] Based on the current beam-making data and management data, predict the stage beam-making data for the preset management period.

[0170] Optionally, when the beam making data determination module 203 predicts the stage beam making data of a preset management period based on the current beam making data and the management data, it is specifically used to:

[0171] Perform data preprocessing on the current beam manufacturing data and management data to determine the preliminary prediction sample data:

[0172] Clean and standardize the preliminary forecast sample data to determine the target forecast sample data;

[0173] The beam-making features corresponding to the beam-making progress and the equipment efficiency of the current beam-making equipment are extracted from the current beam-making data and management data.

[0174] Transform the beam making features to determine the model application features;

[0175] Select the corresponding prediction model based on the model application characteristics;

[0176] Based on the historical prediction sample data, target prediction sample data, prediction model and preset management period, the corresponding stage beam making data is predicted.

[0177] Optionally, when the planned offset data determining module 204 determines the planned offset data according to the current beam making task data, the current beam making data, and the stage beam making data, it is specifically used to:

[0178] Analyze the stage beam-making data to determine the completion status of the corresponding beam-making tasks and the stage beam-making tasks;

[0179] Determine the forecast plan data based on the completion status of the beam-making task, the stage beam-making task and the current beam-making task data;

[0180] Compare the predicted plan data with the current beam manufacturing data to determine the plan offset data; wherein the plan offset data includes task progress offset, resource utilization efficiency offset, and beam quality offset.

[0181] Optionally, when determining the plan adjustment method corresponding to the plan offset data based on the plan offset data, the highway usage status, the bridge erection plan and environmental factors, the plan offset data determination module 204 is specifically used to:

[0182] Quantify the plan deviation data and calculate the corresponding deviation value; the deviation value includes the number of days the task progress is delayed and the percentage reduction in resource utilization efficiency;

[0183] Determine the cause of the plan deviation based on the preset deviation conditions, plan deviation data and deviation values;

[0184] Determine the target plan deviation based on highway usage, girder erection plan and environmental factors;

[0185] According to the reasons for plan deviation and target plan deviation, formulate corresponding plan adjustment methods.

[0186] The device performs functions similar to the method provided above. For other functions, please refer to the previous description and will not be repeated here.

[0187] Figure 3 A schematic diagram of the structure of an electronic device according to an exemplary embodiment is shown. Figure 3As shown, the electronic device 300 of this embodiment may include: a memory 301 and a processor 302 .

[0188] The memory 301 stores a computer program. When the computer program is executed by the processor 302, the processor 302 executes the method in the above embodiment.

[0189] The processor 302 and the memory 301 are connected, for example, via a bus.

[0190] Optionally, the electronic device 300 may further include a transceiver. It should be noted that in actual applications, the number of transceivers is not limited to one, and the structure of the electronic device 300 does not constitute a limitation on the embodiments of the present application.

[0191] The processor 302 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array), or other programmable logic devices, transistor logic devices, hardware components, or any combination thereof. It may implement or execute various exemplary logic blocks, modules, and circuits described in conjunction with the disclosure of this application. The processor 302 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, and the like.

[0192] The bus may include a path to transmit information between the above components. The bus may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, only one thick line is used in the figure, but it does not mean that there is only one bus or one type of bus.

[0193] The memory 301 can be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited to these.

[0194] The memory 301 is used to store the application code for executing the solution of the present application, and the execution is controlled by the processor 302. The processor 302 is used to execute the application code stored in the memory 301 to implement the contents shown in the above method embodiment.

[0195] The electronic devices include, but are not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), and fixed terminals such as digital TVs, desktop computers, etc. It can also be a server, etc. Figure 3 The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0196] The electronic device of this embodiment can be used to execute the method of any of the above embodiments, and its implementation principle and technical effect are similar, which will not be described in detail here.

[0197] The present application also provides a non-transitory computer-readable storage medium having computer-readable instructions stored thereon. When the aforementioned instructions are executed by a processor, the processor executes the method in the above embodiment.

[0198] Those skilled in the art can understand that all or part of the steps of implementing the above-mentioned method embodiments can be completed by hardware related to program instructions. The aforementioned program can be stored in a non-transient computer-readable storage medium. When the program is executed, the steps of the above-mentioned method embodiments are executed; and the aforementioned storage medium includes: ROM, RAM, disk or optical disk and other media that can store program codes.

[0199] The embodiments of the present application are described in detail above. Specific examples are used herein to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method and its core idea of ​​the present application. At the same time, changes or deformations made by those skilled in the art based on the ideas of the present application, the specific implementation methods and the scope of application of the present application, all belong to the scope of protection of the present application. In summary, the content of this specification should not be construed as a limitation on the present application.

Claims

1. A safety management method for a highway smart beam yard, characterized in that: include: Generate target beam-making data according to bridge construction goals and beam-erecting plans; Analyze the target beam-making data to determine current beam-making task data; Analyze the current beam-making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam-making data and predict the stage beam-making data of the preset management period; wherein the current beam-making data and the stage beam-making data include the corresponding target preset beam body and the corresponding transportation route; Determine the planned offset data according to the current beam-making task data, the current beam-making data, and the stage beam-making data, and determine the planned adjustment method corresponding to the planned offset data based on the planned offset data, the highway usage status, the beam-making plan, and environmental factors; The step of generating target beam-making data according to the bridge construction target and beam-laying plan includes: Analyze the bridge construction goals to determine corresponding bridge construction needs; Determining corresponding bridge components according to the bridge construction requirements and preset bridge component information; generating a preliminary beam-making plan according to the bridge components and the preset component relationships; Based on the beam erection plan, the preliminary beam fabrication plan is updated to generate the target beam fabrication data; The analysis of the current beam-making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam-making data and predict the stage beam-making data of the preset management period includes: Analyze the current beam-making task data to determine the corresponding current transport route, current task period and current beam-making equipment; Analyze the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam manufacturing progress at the current moment; According to the actually enabled equipment, the occupancy of the transport equipment, the occupancy data of the transport route and the beam making progress, the current transport route, the current task period and the current beam making equipment are updated to determine the actual transport route, the actual task period and the actual beam making equipment; Determining the current beam making data according to the actual transport route, the actual task period and the actual beam making equipment; Based on the current beam-making data and the management data, predicting the stage beam-making data of the preset management period; Wherein, the predicting the stage beam making data of the preset management period based on the current beam making data and the management data includes: The current beam making data and the management data are preprocessed to determine preliminary prediction sample data: Cleaning and standardizing the preliminary prediction sample data to determine target prediction sample data; Extracting beam making features corresponding to the beam making progress and the equipment efficiency of the current beam making equipment from the current beam making data and the management data; Converting the beam making feature to determine the model application feature; Based on the model application characteristics, select a corresponding prediction model; Predicting the corresponding stage beam making data according to the historical prediction sample data, the target prediction sample data, the prediction model and the preset management period; Wherein, determining the plan adjustment method corresponding to the plan offset data based on the plan offset data, the highway usage status, the bridge erection plan and environmental factors includes: Quantifying the plan deviation data and calculating the corresponding deviation value; wherein the deviation value includes the number of days of task progress delay and the percentage reduction of resource utilization efficiency; Determining the reason for the plan deviation according to the preset deviation condition, the plan deviation data and the deviation value; Determining a target plan deviation according to the highway usage status, the beam erection plan and the environmental factors; According to the reasons for the plan deviation and the target plan deviation, a corresponding plan adjustment method is formulated.

2. The safety management method for the highway smart beam yard according to claim 1 is characterized in that: According to the target beam making data, current beam making task data is determined, including: Analyze the target beam-making data to determine corresponding beam-making building materials, building material placement locations, and transportation equipment; According to the building material properties of the beam-making building materials, the placement location of the building materials and the equipment properties of the transportation equipment, the target beam-making data is split into a plurality of beam-making tasks; wherein the plurality of beam-making tasks include corresponding transportation routes, task time periods and beam-making equipment; According to the current moment, the current beam-making task data is determined from the plurality of beam-making tasks.

3. The safety management method for the highway smart beam yard according to claim 1 is characterized in that: The step of determining the planned offset data according to the current beam making task data, the current beam making data, and the stage beam making data includes: Analyze the beam fabrication data of the stage to determine the completion status of the corresponding beam fabrication tasks and the beam fabrication tasks of the stage; Determine forecast plan data based on the completion status of the beam making task, the stage beam making task and the current beam making task data; The predicted plan data and the current beam making data are compared to determine the plan offset data; wherein the plan offset data includes task progress offset, resource utilization efficiency offset, and beam quality offset.

4. A safety management device for a highway smart beam yard, characterized in that: include: The target beam-making data generation module is used to generate the target beam-making data according to the bridge construction target and beam-making plan; A current beam-making task data determination module is used to determine the current beam-making task data according to the target beam-making data; A beam making data determination module is used to analyze the current beam making task data and the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the current beam making data and predict the stage beam making data of the preset management period; wherein the current beam making data and the stage beam making data include the corresponding target preset beam body and the corresponding transportation route; A planned offset data determination module is used to determine the planned offset data according to the current beam-making task data, the current beam-making data, and the stage beam-making data, and determine the planned adjustment method corresponding to the planned offset data based on the planned offset data, the highway usage status, the beam-laying plan and environmental factors; Wherein, the target beam making data generation module is specifically used for: Analyze the bridge construction goals to determine corresponding bridge construction needs; Determining corresponding bridge components according to the bridge construction requirements and preset bridge component information; generating a preliminary beam-making plan according to the bridge components and the preset component relationships; Based on the beam erection plan, the preliminary beam fabrication plan is updated to generate the target beam fabrication data; Wherein, the beam making data determination module is specifically used for: Analyze the current beam-making task data to determine the corresponding current transport route, current task period and current beam-making equipment; Analyze the management data of the BIM twin beam yard corresponding to the highway smart beam yard to determine the actual enabled equipment, transportation equipment occupancy, transportation route occupancy data and beam manufacturing progress at the current moment; According to the actually enabled equipment, the occupancy of the transport equipment, the occupancy data of the transport route and the beam making progress, the current transport route, the current task period and the current beam making equipment are updated to determine the actual transport route, the actual task period and the actual beam making equipment; Determining the current beam making data according to the actual transport route, the actual task period and the actual beam making equipment; Based on the current beam-making data and the management data, predicting the stage beam-making data of the preset management period; Wherein, the beam making data determination module is specifically used to predict the stage beam making data of the preset management period based on the current beam making data and the management data: The current beam making data and the management data are preprocessed to determine preliminary prediction sample data: Cleaning and standardizing the preliminary prediction sample data to determine target prediction sample data; Extracting beam making features corresponding to the beam making progress and the equipment efficiency of the current beam making equipment from the current beam making data and the management data; Converting the beam making feature to determine the model application feature; Based on the model application characteristics, select a corresponding prediction model; Predicting the corresponding stage beam making data according to the historical prediction sample data, the target prediction sample data, the prediction model and the preset management period; Wherein, the plan offset data determination module is specifically used to determine the plan adjustment method corresponding to the plan offset data based on the plan offset data, the highway usage status, the bridge erection plan and environmental factors: Quantifying the plan deviation data and calculating the corresponding deviation value; wherein the deviation value includes the number of days of task progress delay and the percentage reduction of resource utilization efficiency; Determining the reason for the plan deviation according to the preset deviation condition, the plan deviation data and the deviation value; Determining a target plan deviation according to the highway usage status, the beam erection plan and the environmental factors; According to the reasons for the plan deviation and the target plan deviation, a corresponding plan adjustment method is formulated.

5. An electronic device, characterized in that: include: Memory and processor; The memory is used to store program instructions; The processor is used to call and execute program instructions in the memory to execute the safety management method of the smart beam yard for highways as described in any one of claims 1-3.

6. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program; when the computer program is executed by the processor, the safety management method for the smart beam yard of the highway as described in any one of claims 1-3 is implemented.