A three-dimensional automatic deformation monitoring method and system for tunnels

By constructing a three-dimensional tunnel model and a task analysis library, the monitoring points are automatically determined, which solves the problem of inconsistent monitoring results caused by manual dependence in the existing technology, and achieves accuracy and consistency in tunnel deformation monitoring.

CN118506136BActive Publication Date: 2024-10-29WUHAN ENGINEERING CO LTD OF CHINA RAILWAY SEVENTH GROUP +5
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410949002.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-10-29
Estimated Expiration
2044-07-16

AI Technical Summary

Technical Problem

Existing tunnel deformation monitoring methods rely on manual data acquisition, and the selection of monitoring data collection locations mostly relies on personnel experience, resulting in individual subjective differences in monitoring results, making it impossible to achieve objective and accurate monitoring.

Method used

By constructing a three-dimensional model of the tunnel and generating requests based on the monitoring tasks sent by the monitoring terminal, the target tunnel area is determined, and the preset task analysis library is used to generate monitoring tasks to automatically determine the monitoring points and ensure the rationality and accuracy of the monitoring points. .

Benefits of technology

It improves the accuracy and consistency of tunnel deformation monitoring, reduces manual subjective interference, and realizes automated monitoring point layout and data collection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118506136B_ABST
    Figure CN118506136B_ABST
Patent Text Reader

Abstract

The present invention provides a method and system for three-dimensional automatic deformation monitoring of tunnels, wherein the method comprises: constructing and storing a three-dimensional model of the tunnel; determining the target tunnel area of ​​the task to be generated according to a monitoring task generation request sent by a monitoring terminal; determining the target model corresponding to the target tunnel area of ​​the task to be generated from the stored three-dimensional model; generating the monitoring task according to the target model and a preset task analysis library. The method and system for three-dimensional automatic deformation monitoring of tunnels of the present invention constructs a model of the tunnel, and then analyzes the constructed model to determine the monitoring points, thereby ensuring the rationality of the layout of the monitoring points and improving the accuracy of monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of monitoring and management systems, and in particular to a three-dimensional automatic deformation monitoring method and system for a tunnel. Background Art

[0002] In order to overcome terrain obstacles, the use of tunnels in mountainous areas can improve line design, increase driving speed, shorten mileage, reduce damage to vegetation, and help protect the ecological environment.

[0003] Due to the particularity of tunnels, they are affected by geological changes, hydrological conditions, earthquakes and other factors for a long time, and the deformation of tunnel structures is inevitable. The deformation of tunnels may manifest as surface subsidence, structural cracking, cracking deformation, etc. Once it occurs, it may have a serious impact on the safety and operation of the tunnel structure. Therefore, the significance and importance of tunnel deformation monitoring are very important. It can ensure the safe operation of tunnels and reduce the risk of tunnel accidents. By monitoring the deformation of tunnel structures, safety hazards in tunnels can be discovered in time and corresponding preventive measures can be taken to reduce the risk of accidents in tunnels.

[0004] At present, the traditional method of tunnel deformation monitoring is mainly to pre-bury several deformation monitoring points in the tunnel arch and on both sides of the tunnel at intervals, use a total station or level to measure the elevation change of the arch monitoring point as the tunnel arch settlement, and use a total station or convergence meter to measure the change in the distance between the two deformation monitoring points as the tunnel convergence deformation in the direction of the line connecting the two measuring points.

[0005] 3D laser scanners can automatically and quickly obtain high-density point cloud data on the surface of target objects, with measurement accuracy reaching the millimeter level. It is an emerging method for monitoring tunnel deformation. To use 3D laser scanning technology for tunnel deformation monitoring, you must first use a 3D laser scanner to obtain the point cloud of the inner surface of the tunnel in the target mileage section, and then perform data processing and analysis on the point cloud. There are currently two main processing and analysis methods:

[0006] 1. Use data processing software to cut a point cloud of a certain thickness perpendicular to the central axis of the tunnel at a specified mileage along the tunnel depth direction, project the cut point cloud on a plane perpendicular to the central axis at the above-mentioned specified mileage, fit the obtained projection to obtain the projected contour line as the tunnel section contour line at the above-mentioned specified mileage, and calculate the difference between the tunnel section contour lines by comparing the tunnel section contour lines at different periods as the tunnel deformation at the above-mentioned specified mileage;

[0007] Second, use data processing software to construct the point cloud of the tunnel inner surface into a triangulated network model, cut a section perpendicular to the tunnel centerline at a specified mileage, and then obtain the contour line of the triangulated network model on the specified mileage section. By comparing the contour lines of the triangulated network models of different periods on the same specified mileage section, calculate the difference between the contour lines as the tunnel deformation at the specified mileage;

[0008] Existing patent CN201811529199.1 A tunnel deformation monitoring and analysis method based on grid projection point cloud processing technology is proposed to solve the above problems. It is proposed to divide the tunnel design surface model into polygonal unit grids of the same size as the projection reference surface, and then fit the point cloud within the projection range of the unit grid on the tunnel surface point cloud model into a plane quadrilateral. The point cloud fitting at different times in the same projection range obtains the difference in distance from the centroid of the plane polygon to the projection center on the tunnel central axis as the deformation of the tunnel at the projection position. The judgment results are screened according to the difference in deformation direction of the point cloud of the projection area corresponding to the above unit grid and the point cloud of the projection area corresponding to the four adjacent unit grids. Different colors are given to the unit grids according to the size of the deformation at the corresponding position to obtain a more intuitive color tunnel surface design model, thereby realizing the overall analysis of tunnel deformation monitoring.

[0009] However, its data acquisition still relies on manual labor, and the selection of the collection location of the monitoring data mostly depends on the experience of the personnel. Since the monitoring is not necessarily carried out by the same personnel each time, there are large personal subjective differences, and objective and accurate monitoring cannot be achieved. Summary of the invention

[0010] One of the purposes of the present invention is to provide a three-dimensional automatic deformation monitoring method and system for a tunnel, construct a model for the tunnel, and then analyze and determine the monitoring points based on the constructed model to ensure the rationality of the layout of the monitoring points and improve the accuracy of monitoring.

[0011] An embodiment of the present invention provides a three-dimensional automatic deformation monitoring method for a tunnel, comprising:

[0012] Build and store a 3D model of the tunnel;

[0013] Determine the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal;

[0014] Determine a target model corresponding to a target tunnel area of ​​a task to be generated from the stored three-dimensional models;

[0015] Generate monitoring tasks based on the target model and the preset task analysis library.

[0016] Preferably, determining the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal includes:

[0017] According to the target identification code in the monitoring task generation request, the preset tunnel code library is queried to determine the target tunnel area corresponding to the target identification code.

[0018] Preferably, determining the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal includes:

[0019] According to the positioning information of the monitoring terminal in the monitoring task generation request, a tunnel area closest to the positioning information is determined as the target tunnel area.

[0020] Preferably, determining the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal further includes:

[0021] When the tunnel area closest to the positioning information is in the first list restricted as the target of the generated task, and the adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list is one, the adjacent area of ​​the tunnel area closest to the positioning information is used as the target tunnel area;

[0022] The first list construction steps are as follows:

[0023] Get historical monitoring tasks whose time difference from the current moment is within the preset time threshold;

[0024] According to the target tunnel area corresponding to the historical monitoring task, a list of restrictions as targets for generating tasks is constructed.

[0025] Preferably, determining the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal further includes:

[0026] When the tunnel area closest to the positioning information is in the list restricted as the target of the generated task, and there is more than one adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list, determining the shortest distance between each adjacent area and the positioning information;

[0027] The adjacent area with the shortest distance is taken as the target tunnel area.

[0028] Preferably, the monitoring task is generated according to the target model and the preset task analysis library, including:

[0029] Segment the target model to obtain multiple model units;

[0030] Parse the task analysis library to determine the importance assessment sub-library and the interference assessment sub-library;

[0031] According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit;

[0032] According to the interference assessment sub-library, the interference value corresponding to each model unit is determined;

[0033] Determine the priority value of each model unit according to the key value and interference value corresponding to each model unit;

[0034] According to the priority value, a model unit screening list is constructed;

[0035] The monitoring points are determined based on the preset monitoring point screening rules and model unit screening list.

[0036] The present invention also provides a three-dimensional automatic deformation monitoring system for a tunnel, comprising:

[0037] A model building module, used to build and store a three-dimensional model of the tunnel;

[0038] A target determination module, used to determine a target tunnel area for a task to be generated according to a monitoring task generation request sent by a monitoring terminal;

[0039] A model retrieval module is used to determine a target model corresponding to a target tunnel area of ​​a task to be generated from a stored three-dimensional model;

[0040] The task generation module is used to generate monitoring tasks based on the target model and the preset task analysis library.

[0041] Preferably, the target determination module determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and performs the following operations:

[0042] According to the target identification code in the monitoring task generation request, the preset tunnel code library is queried to determine the target tunnel area corresponding to the target identification code.

[0043] Preferably, the target determination module determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and performs the following operations:

[0044] According to the positioning information of the monitoring terminal in the monitoring task generation request, a tunnel area closest to the positioning information is determined as the target tunnel area.

[0045] Preferably, the target determination module determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and further performs the following operations:

[0046] When the tunnel area closest to the positioning information is in the first list restricted as the target of the generated task, and the adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list is one, the adjacent area of ​​the tunnel area closest to the positioning information is used as the target tunnel area;

[0047] The first list construction steps are as follows:

[0048] Get historical monitoring tasks whose time difference from the current moment is within the preset time threshold;

[0049] According to the target tunnel area corresponding to the historical monitoring task, a list of restrictions as targets for generating tasks is constructed.

[0050] Preferably, the target determination module determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and further performs the following operations:

[0051] When the tunnel area closest to the positioning information is in the list restricted as the target of the generated task, and there is more than one adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list, determining the shortest distance between each adjacent area and the positioning information;

[0052] The adjacent area with the shortest distance is taken as the target tunnel area.

[0053] Preferably, the task generation module generates a monitoring task according to the target model and a preset task analysis library, and performs the following operations:

[0054] Segment the target model to obtain multiple model units;

[0055] Parse the task analysis library to determine the importance assessment sub-library and the interference assessment sub-library;

[0056] According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit;

[0057] According to the interference assessment sub-library, the interference value corresponding to each model unit is determined;

[0058] Determine the priority value of each model unit according to the key value and interference value corresponding to each model unit;

[0059] According to the priority value, a model unit screening list is constructed;

[0060] The monitoring points are determined based on the preset monitoring point screening rules and model unit screening list.

[0061] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description and the accompanying drawings.

[0062] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0063] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0064] Figure 1 A schematic diagram of a three-dimensional automatic deformation monitoring method for a tunnel according to an embodiment of the present invention;

[0065] Figure 2 Schematic diagram of a three-dimensional automatic deformation monitoring system for a tunnel in an embodiment of the present invention. DETAILED DESCRIPTION

[0066] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0067] The embodiment of the present invention provides a three-dimensional automatic deformation monitoring method for a tunnel, such as Figure 1 As shown, including:

[0068] Step S1: constructing and storing a three-dimensional model of the tunnel;

[0069] Step S2: determining a target tunnel area for a task to be generated according to a monitoring task generation request sent by the monitoring terminal;

[0070] Step S3: determining a target model corresponding to a target tunnel area of ​​a task to be generated from the stored three-dimensional models;

[0071] Step S4: Generate monitoring tasks based on the target model and the preset task analysis library.

[0072] The working principle and beneficial effects of the above technical solution are:

[0073] The three-dimensional automated deformation monitoring method of the tunnel of the present invention first constructs a three-dimensional model of each tunnel, and stores the constructed three-dimensional model for standby; generates a request for monitoring tasks sent by the monitoring terminal, determines the target tunnel area, and then determines the target model from the stored three-dimensional model, and then generates a monitoring task according to a preset task analysis library, and determines the monitoring task by analyzing the three-dimensional model of the tunnel; sends the monitoring task to the monitoring terminal of the staff, and the staff arranges the monitoring points, and connects the monitoring equipment to the server by installing the monitoring equipment to the monitoring points; the subsequent server can visualize the three-dimensional model of the tunnel body, and arrange the monitoring network points (working base points, monitoring points, and reference points) on the three-dimensional model of the tunnel, completes the attribute information query and spatial position visualization of the monitoring points, and the present invention performs spatial analysis on the basis of the three-dimensional model of the tunnel, judges the rationality of the arrangement of the monitoring points, and obtains the optimal position of the arrangement of the monitoring points. Based on the three-dimensional modeling technology, the tunnel is expressed in a three-dimensional manner, and the deformation monitoring network is arranged on the basis of the automated monitoring scheme. In addition, the measurement robot TM-50 can also be used as a monitoring device to realize the visualization, transparency, and manageability of the underground tunnel. The monitoring terminals include mobile terminals (mobile phones, tablets, etc.) used by various staff members.

[0074] In one embodiment, determining a target tunnel area for a task to be generated according to a monitoring task generation request sent by a monitoring terminal includes:

[0075] According to the target identification code in the monitoring task generation request, the preset tunnel code library is queried to determine the target tunnel area corresponding to the target identification code.

[0076] The working principle and beneficial effects of the above technical solution are:

[0077] The monitoring task generation request issued by the monitoring terminal can be generated by the staff by clicking on the area of ​​the tunnel that needs to be monitored in the visual tunnel distribution map on the monitoring terminal, and generating the monitoring task generation request according to the target identification code corresponding to the selected area; wherein the target identification code is a unique identification code for the identity of each pre-divided area of ​​each tunnel; one target identification code only corresponds to one divided area of ​​a tunnel.

[0078] In one embodiment, determining a target tunnel area for a task to be generated according to a monitoring task generation request sent by a monitoring terminal includes:

[0079] According to the positioning information of the monitoring terminal in the monitoring task generation request, a tunnel area closest to the positioning information is determined as the target tunnel area.

[0080] In order to improve the efficiency of the staff in the actual execution of the monitoring task, when the staff finishes the monitoring of the area, they do not need to move to the location of the next area before applying for the indication of the monitoring point, and can apply during the movement. On this basis, the method of the present invention determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and also includes:

[0081] When the tunnel area closest to the positioning information is in the first list restricted as the target of the generated task, and the adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list is one, the adjacent area of ​​the tunnel area closest to the positioning information is used as the target tunnel area;

[0082] The first list construction steps are as follows:

[0083] Obtain historical monitoring tasks whose time difference from the current moment is within a preset time threshold (for example, any one between 3 months and 1 year);

[0084] According to the target tunnel area corresponding to the historical monitoring task, a list of restrictions as targets for generating tasks is constructed.

[0085] In addition, according to the monitoring task generation request sent by the monitoring terminal, determining the target tunnel area of ​​the task to be generated also includes:

[0086] When the tunnel area closest to the positioning information is in the list restricted as the target of the generated task, and there is more than one adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list, determining the shortest distance between each adjacent area and the positioning information;

[0087] The adjacent area with the shortest distance is taken as the target tunnel area.

[0088] The working principle and beneficial effects of the above technical solution are:

[0089] When the staff uses the positioning-based target confirmation mode on the monitoring terminal, the request contains the positioning information but does not contain the target identification code corresponding to the target. The corresponding target is automatically determined through the positioning information, which improves the intelligence of the system.

[0090] In one embodiment, a monitoring task is generated according to the target model and a preset task analysis library, including:

[0091] Segment the target model to obtain multiple model units;

[0092] Parse the task analysis library to determine the importance assessment sub-library and the interference assessment sub-library;

[0093] According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit;

[0094] According to the interference assessment sub-library, the interference value corresponding to each model unit is determined;

[0095] According to the key value and interference value corresponding to each model unit, the priority value of each model unit is determined; for example, the priority value is the weighted sum of the key value and the interference value, and the weight coefficients corresponding to the key value and the interference value are pre-configured and stored;

[0096] According to the priority value, a model unit screening list is constructed; the model unit screening list is constructed in descending order of the priority value;

[0097] Based on the preset monitoring point screening rules and the model unit screening list, the monitoring points are determined. For example, the monitoring point screening rule is to extract the first N units from the list to determine the monitoring points.

[0098] The working principle and beneficial effects of the above technical solution are:

[0099] By segmenting the model and evaluating each model unit based on the importance assessment sub-library and the interference assessment sub-library, suitable monitoring points can be screened out to ensure the effectiveness and rationality of the monitoring point layout.

[0100] Among them, according to the importance assessment sub-library, the key values ​​corresponding to each model unit are determined, including:

[0101] Acquire a preset first feature extraction template associated with the importance assessment sub-library;

[0102] According to the first feature extraction template, feature extraction is performed on the model unit to obtain multiple first feature values, wherein the first feature values ​​include: feature values ​​representing the component type in the model area, feature values ​​representing the distance parameter of the model unit from the reference plane of the tunnel, feature values ​​representing the parameters of each component element in the model area, etc.; wherein the component type represents which equipment is in the model area, when only the basic structure of the tunnel exists, the component type is A, and the specific component type can be specified by a query table of numbers corresponding to the component elements and component types configured in advance; the parameters include: quantity, area size, etc.;

[0103] Constructing a keyword analysis set according to the plurality of first feature values;

[0104] Based on the keyword analysis set, the key values ​​of the corresponding keyword analysis set are retrieved from the importance evaluation sub-library; the importance evaluation sub-library is pre-configured in the system, and the key values ​​are associated with the keyword analysis set in a one-to-one correspondence in the library.

[0105] According to the interference assessment sub-library, determine the interference value corresponding to each model unit, including:

[0106] According to the second feature extraction template associated with the interference assessment sub-library, feature extraction is performed on the model unit to obtain multiple second feature values, wherein the second feature values ​​include: feature values ​​representing the component type in the model area, feature values ​​representing the distance parameter of the model unit from the reference plane of the tunnel, feature values ​​representing the parameters of each component element in the model area, etc.; wherein the component type represents which equipment is in the model area, when only the basic structure of the tunnel exists, the component type is A, and the specific component type can be specified by a pre-configured query table of component elements and numbers corresponding to the component types; parameters include: quantity, area size, etc.;

[0107] The analysis set constructed with the second characteristic value is queried through the interference evaluation sub-library to retrieve the interference value of the corresponding analysis set; the interference evaluation sub-library is pre-configured in the system, and the interference value is associated with the analysis set in a one-to-one correspondence in the library;

[0108] The analysis of interference values ​​mainly analyzes the interference of the structure and various devices in the model unit on data detection. The smaller the interference value, the closer the detection result is to the actual situation.

[0109] In one embodiment, a monitoring task is generated according to the target model and a preset task analysis library, including:

[0110] Segment the target model to obtain multiple model units;

[0111] Parse the task analysis library to determine the importance assessment sub-library and the interference assessment sub-library;

[0112] According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit;

[0113] According to the interference assessment sub-library, the interference value corresponding to each model unit is determined;

[0114] Determine the change value of each model unit based on historical monitoring data;

[0115] According to the key value, interference value and change value corresponding to each model unit, the priority value of each model unit is determined; for example, the priority value is the weighted sum of the key value, interference value and change value; the weight coefficient corresponding to the change value is also pre-configured;

[0116] According to the priority value, a model unit screening list is constructed;

[0117] The monitoring points are determined based on the preset monitoring point screening rules and model unit screening list.

[0118] Among them, according to the historical monitoring data, the change value of each model unit is determined, including:

[0119] Analyze historical monitoring data and determine the deformation data corresponding to the monitoring points in each model unit;

[0120] According to the deformation data, a deformation trend description set is constructed; the deformation trend description set is formed by arranging the parameters corresponding to the deformation data in chronological order;

[0121] The change value is determined according to the deformation trend description set and a preset change value quantization library; the change value quantization library is pre-configured, and the change amount in the library is correspondingly associated with the change trend description set.

[0122] The method provided in this embodiment comprehensively considers the importance of the unit, the interference of the internal settings and the historical deformation when constructing the task; on this basis, accurate and effective screening is carried out to provide effective guidance for the monitoring of the staff and improve the effectiveness of monitoring.

[0123] The present invention also provides a three-dimensional automatic deformation monitoring system for tunnels, such as Figure 2 As shown, including:

[0124] Model building module 1, used for building and storing a three-dimensional model of the tunnel;

[0125] A target determination module 2 is used to determine a target tunnel area for a task to be generated according to a monitoring task generation request sent by a monitoring terminal;

[0126] A model retrieval module 3 is used to determine a target model corresponding to a target tunnel area of ​​a task to be generated from a stored three-dimensional model;

[0127] The task generation module 4 is used to generate monitoring tasks according to the target model and the preset task analysis library.

[0128] In one embodiment, the target determination module 2 determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and performs the following operations:

[0129] According to the target identification code in the monitoring task generation request, the preset tunnel code library is queried to determine the target tunnel area corresponding to the target identification code.

[0130] In one embodiment, the target determination module 2 determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and performs the following operations:

[0131] According to the positioning information of the monitoring terminal in the monitoring task generation request, a tunnel area closest to the positioning information is determined as the target tunnel area.

[0132] In addition, the target determination module 2 determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and also performs the following operations:

[0133] When the tunnel area closest to the positioning information is in the first list restricted as the target of the generated task, and the adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list is one, the adjacent area of ​​the tunnel area closest to the positioning information is used as the target tunnel area;

[0134] The first list construction steps are as follows:

[0135] Get historical monitoring tasks whose time difference from the current moment is within the preset time threshold;

[0136] According to the target tunnel area corresponding to the historical monitoring task, a list of restrictions as targets for generating tasks is constructed.

[0137] In addition, the target determination module 2 determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and also performs the following operations:

[0138] When the tunnel area closest to the positioning information is in the list restricted as the target of the generated task, and there is more than one adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list, determining the shortest distance between each adjacent area and the positioning information;

[0139] The adjacent area with the shortest distance is taken as the target tunnel area.

[0140] In one embodiment, the task generation module 4 generates a monitoring task according to the target model and a preset task analysis library, and performs the following operations:

[0141] Segment the target model to obtain multiple model units;

[0142] Parse the task analysis library to determine the importance assessment sub-library and the interference assessment sub-library;

[0143] According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit;

[0144] According to the interference assessment sub-library, the interference value corresponding to each model unit is determined;

[0145] Determine the priority value of each model unit according to the key value and interference value corresponding to each model unit;

[0146] According to the priority value, a model unit screening list is constructed;

[0147] The monitoring points are determined based on the preset monitoring point screening rules and model unit screening list.

[0148] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A three-dimensional automatic deformation monitoring method for a tunnel, characterized in that: include: Build and store a 3D model of the tunnel; Determine the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal; Determine a target model corresponding to a target tunnel area of ​​a task to be generated from the stored three-dimensional model; Generate monitoring tasks according to the target model and a preset task analysis library; Wherein, generating a monitoring task according to the target model and a preset task analysis library includes: Segmenting the target model to obtain multiple model units; Parsing the task analysis library to determine an importance assessment sub-library and an interference assessment sub-library; According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit; According to the interference assessment sub-library, the interference value corresponding to each model unit is determined; Determine the priority value of each model unit according to the key value and interference value corresponding to each model unit; According to the priority value, a model unit screening list is constructed; Determine monitoring points based on preset monitoring point screening rules and model unit screening list; Wherein, according to the monitoring task generation request sent by the monitoring terminal, determining the target tunnel area of ​​the task to be generated includes: According to the location information of the monitoring terminal in the monitoring task generation request, determining the tunnel area closest to the location information as the target tunnel area; When the tunnel area closest to the positioning information is in the first list restricted as the target of generating the task, and the number of adjacent areas of the tunnel area closest to the positioning information that is not in the first list is one, the adjacent area of ​​the tunnel area closest to the positioning information is used as the target tunnel area; The first list construction steps are as follows: Get historical monitoring tasks whose time difference from the current moment is within the preset time threshold; According to the target tunnel area corresponding to the historical monitoring task, a list of restrictions as targets for generating tasks is constructed.

2. The three-dimensional automatic deformation monitoring method for tunnels according to claim 1, characterized in that: According to the monitoring task generation request sent by the monitoring terminal, the target tunnel area of ​​the task to be generated is determined, including: According to the target identification code in the monitoring task generation request, a preset tunnel code library is queried to determine the target tunnel area corresponding to the target identification code.

3. The three-dimensional automatic deformation monitoring method for tunnels according to claim 1, characterized in that: Determining a target tunnel area for a task to be generated according to a monitoring task generation request sent by the monitoring terminal, further comprising: When the tunnel area closest to the positioning information is in the list restricted as the target of generating the task, and there is more than one adjacent area of ​​the tunnel area closest to the positioning information that is not in the first list, determining the shortest distance between each adjacent area and the positioning information; The adjacent area with the shortest distance is taken as the target tunnel area.

4. A three-dimensional automatic deformation monitoring system for tunnels, characterized in that: include: A model building module, used to build and store a three-dimensional model of the tunnel; A target determination module, used to determine a target tunnel area for a task to be generated according to a monitoring task generation request sent by a monitoring terminal; A model retrieval module, used to determine a target model corresponding to a target tunnel area of ​​a task to be generated from the stored three-dimensional model; A task generation module, used to generate monitoring tasks according to the target model and a preset task analysis library; Generate monitoring tasks based on the target model and the preset task analysis library, including: Segmenting the target model to obtain multiple model units; Parsing the task analysis library to determine an importance assessment sub-library and an interference assessment sub-library; According to the importance assessment sub-library, determine the key values ​​corresponding to each model unit; According to the interference assessment sub-library, the interference value corresponding to each model unit is determined; Determine the priority value of each model unit according to the key value and interference value corresponding to each model unit; According to the priority value, a model unit screening list is constructed; Determine monitoring points based on preset monitoring point screening rules and model unit screening list; The target determination module determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and performs the following operations: According to the location information of the monitoring terminal in the monitoring task generation request, determining the tunnel area closest to the location information as the target tunnel area; When the tunnel area closest to the positioning information is in the first list restricted as the target of generating the task, and the number of adjacent areas of the tunnel area closest to the positioning information that is not in the first list is one, the adjacent area of ​​the tunnel area closest to the positioning information is used as the target tunnel area; The first list construction steps are as follows: Get historical monitoring tasks whose time difference from the current moment is within the preset time threshold; According to the target tunnel area corresponding to the historical monitoring task, a list of restrictions as targets for generating tasks is constructed.

5. The three-dimensional automatic deformation monitoring system for tunnels according to claim 4, characterized in that: The target determination module determines the target tunnel area of ​​the task to be generated according to the monitoring task generation request sent by the monitoring terminal, and performs the following operations: According to the target identification code in the monitoring task generation request, a preset tunnel code library is queried to determine the target tunnel area corresponding to the target identification code.

Citation Information

Patent Citations

  • Tunnel deformation monitoring and analysis method based on grid projection point cloud processing technology

    CN109556529A

  • Rainfall point arrangement and monitoring system and method

    CN110849415A