Rail transit BIM model integrity review method and system based on B / S architecture
Through the B/S architecture method, the problems of difficulty, low efficiency and difficult quality inspection of the information integrity of the urban rail transit BIM model are solved, and intelligent automatic review of the BIM model is realized, which improves the review efficiency and delivery quality.
Patent Information
- Application Number
- CN202411002813.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-25
AI Technical Summary
In the prior art, the BIM model information integrity review in the field of urban rail transit relies on manual methods, and there are problems such as high difficulty in review, low efficiency and difficult quality to ensure.
Using a B/S architecture-based method, the specifications of human codes are translated into a review standard library for machine codes through cross-language processing algorithms, and the information reconstruction algorithm is used to regenerate the BIM model that meets the standards, and the breadth-first traversal method is used to regenerate the BIM model that meets the standards. Construct the mapping rules between the element information database and the review standard database, calculate the integrity indicators and matching coefficients of each review element, generate information integrity evaluation indicators, and finally output the review report.
It realizes intelligent automatic alignment of BIM model specifications and information, reduces the risks of missed and missed inspections, improves review efficiency and model delivery quality, and reduces rework.
Smart Images

Figure CN118520580B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of building information modeling, and in particular to a method and system for reviewing the integrity of a rail transit BIM model based on a B / S architecture. Background Art
[0002] BIM (Building Information Model) is a three-dimensional model that integrates various relevant information of construction projects through the use of digital technology. Compared with traditional two-dimensional plane drawings, BIM models have the advantages of rich mounting information, strong three-dimensional effect expression, and the ability to present the entire life cycle of the project. Therefore, BIM technology has been increasingly applied to the design, construction, operation and maintenance of urban rail transit projects.
[0003] As a new technology, BIM currently relies heavily on manual review for its model. However, the quality of BIM model review under manual review has always been a pain point in the industry:
[0004] (1) Difficulty in review: BIM models carry a huge amount of information and have strong logic and correlation. It is extremely difficult to determine whether the model complies with the modeling specifications and whether the model information meets the delivery standards.
[0005] (2) Low review efficiency: BIM model specifications are usually different in different regions. The specifications in different regions are often different and have many items. Reviewers must fully understand the specification items and align them with the model information one by one. The review is relatively inefficient. At the same time, this places high demands on the reviewers' qualifications, experience, and comprehensive quality.
[0006] (3) Review quality is difficult to guarantee: 2D drawings are usually reviewed and co-signed by professionals from multiple units, including the design unit, consulting unit, and review unit, to ensure the quality of the drawings. However, in urban rail design, BIM models are usually only reviewed by consulting units, and the quality of model delivery is difficult to guarantee.
[0007] It can be seen that at present in the field of urban rail transit, there are many unresolved problems in the manual review of BIM model information integrity.
[0008] Therefore, it is urgent to design an urban rail transit BIM model information integrity review method and system based on B / S architecture to replace manual review and improve the intelligence level of review. Summary of the invention
[0009] According to the above problems, the present invention proposes a rail transit BIM model integrity review method and system based on B / S architecture. The specific scheme is as follows:
[0010] A rail transit BIM model integrity review method based on B / S architecture includes the following steps:
[0011] S1: Deconstruct the BIM model specifications of urban rail transit projects, use cross-language processing algorithms to translate the specification clauses in human language and compile them into a review standard library SL (rf i ), where i ≥ 1, and is stored in a relational database on the backend server;
[0012] S2: On the Web side, the initial BIM model to be reviewed is uploaded to the backend server. Using the information reconstruction algorithm, the structural information, attribute information, material information and other data formats stored in the initial BIM model are reconstructed into a multi-level organizational system that meets the review standard library SL (rf i ) regular data format and regenerate it into a lightweight BIM model that can be used for data exchange;
[0013] S3: In the regenerated BIM model, the element information library is DL (ep j ), j≥1, based on the principle of common semantic matching, based on the breadth-first traversal method BFS, construct the element information library DL (ep j ) and the Review Standard Library SL(rf i ) to calculate the integrity index I and matching coefficient M of each review element;
[0014] S4: Calculate the information integrity evaluation index E of the BIM model according to the integrity index I of each review element and its total number N1, the matching coefficient M of each review element and its total number N2 stored in the background database;
[0015] S5: Based on the review results of each review element and the calculated integrity evaluation index E, the information integrity review report of the BIM model is output in the form of a file on the Web side.
[0016] Preferably, in step S1, deconstructing the BIM model specification of the urban rail transit project includes the following steps:
[0017] S201: Fully disassemble the specification and convert the diagrams in the specification into natural sentences written in human language code;
[0018] S202: According to the article number, the natural sentences in each article are automatically segmented according to word classes and symbols. The segmented text is more machine-readable and serves as the basis for subsequent article translation;
[0019] Wherein: the word classes include nouns, verbs, pronouns or other word classes, and the symbols include commas, periods, semicolons or other symbols.
[0020] Preferably, in step S1, rf i is a data tuple in the review standard library SL, that is, a set of review factors;
[0021] The review standard library SL has i data tuples, rf i = { i , pn i , pa i , pt i , pd i , pr i ,pc i , ps i},pe i , pn i , pa i , pt i , pd i , pr i , pc i , ps i All are review factors;
[0022] Among them, pe i is the name of the subject of review, pn i To review the parameter name, pa i To review parameter values, pt i For information type, pd i For parameter grouping, pr i For the regulations, pc i is the parameter category, ps i is the parameter type;
[0023] Each rf i There must be a PC i At the same time, there may be several other types of review factors mentioned above, and the number and types of the review factors are adjusted according to specific specifications.
[0024] Preferably, in step S2, the regenerated BIM model retains all geometric and non-geometric properties of the initial BIM model, and can be displayed in three-dimensional digital form on the Web.
[0025] Further preferably, in step S3, ep j is a data tuple in the element information library DL, that is, a set of review elements;
[0026] There are j data tuples in the element information library DL, ep j = { etj , eid j , e.g. k}, k ≥ 1, et j 、eid j 、eg k All are review elements;
[0027] Among them, et j is the element name, eid j is the element id, e.g. k is the element attribute group;
[0028] eg k = { en n , ea n}, n≥1, en n is the attribute name, ea n is the attribute value;
[0029] Each ep j There must be et j and eid j , and there are k groups of element attribute groups, the value of k varies with the reference specifications during modeling; each eg k There are n sets of attribute names and attribute values, and the value of n varies with the reference specifications used during modeling.
[0030] Further preferably, in step S3, when calculating the integrity index I of each review element, the initial value of I is I=0. i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The censoring factor under the corresponding ep j If there is no corresponding review element in the background database, the ep is automatically recorded in the background database. j The element name in et j and the element's unique id value eid j , and for this ep j The completeness index I of the missing review elements is reassigned to I=1.
[0031] Further preferably, in step S3, when calculating the matching coefficient M of each review element, the initial value of M is 0. If a data tuple rf in the review standard library SL i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The target value of the review factor under the corresponding ep j The following matched element attribute group eg kMedium attribute value ea n If the value does not match, the ep is automatically recorded in the background database. j The element name in et j , the unique id value of the element eid j And element attribute groups, eg k The attribute name in en n , and for this ep j The matching coefficient M of the review element that does not match the target value of the review factor is reassigned to M=1.
[0032] Preferably, in step S4, the calculation method of the BIM model information integrity evaluation index E is:
[0033] .
[0034] Further preferably, in step S5, the information integrity review report of the BIM model outputted includes the following contents:
[0035] All review elements with integrity index I=1 and their corresponding element names et j and the element's unique id value eid j ;
[0036] All the elements with matching coefficient M=1 and their corresponding element names et j , the unique id value of the element eid j , element attribute group eg k The attribute name in en n ;
[0037] Calculation results of BIM model information integrity evaluation index E.
[0038] The second purpose of the present invention is:
[0039] A rail transit BIM model integrity review system based on B / S architecture, using a rail transit BIM model integrity review method based on B / S architecture, including the following modules:
[0040] Specification translation and storage module: deconstructs the BIM model specifications of urban rail transit projects, translates the specification clauses in human language and integrates them into a review standard library in machine language;
[0041] Model information reconstruction module: reconstructs the information of the uploaded initial BIM model and regenerates it into a lightweight BIM model that can be used for data exchange;
[0042] Review calculation processing module: constructs the mapping rules between the element information library and the review standard library, and calculates the integrity index and matching coefficient of each review element;
[0043] Evaluation index construction module: Calculate the BIM model information integrity evaluation index based on the integrity index and its total number, matching coefficient and its total number of each review element;
[0044] Review report output module: output BIM model information integrity review report in file form on the Web.
[0045] The beneficial effects of the present invention are:
[0046] (1) The present invention integrates the specification information and BIM model information through standardized translation of the urban rail transit BIM model specification with the characteristics of "one site, one specification" and reconstruction of the information consistency of multi-source BIM models, thereby realizing the fusion of multi-source heterogeneous data, establishing a unified data architecture, and laying the foundation for intelligent review.
[0047] (2) Based on the established BIM model specification review standard library and BIM model element information library, the present invention constructs a mapping rule and realizes the association between the specification and the model, so that the specification items and the BIM model information can be intelligently and automatically aligned without the need for manual item-by-item matching for review, thereby reducing the risk of missed detection and wrong detection caused by the technical gap between reviewers, improving the review efficiency and shortening the review cycle.
[0048] (3) The present invention can automatically output the information integrity review report of the BIM model on the Web. Through the BIM model integrity evaluation index results in the report, designers can quickly and intuitively evaluate the quality of the model; through the problem elements and their names and IDs output in the report, designers can quickly locate the problem components, reducing the time spent on finding problems and improving the modification speed of the BIM model.
[0049] (4) Based on the B / S architecture, the present invention fully automates the entire process of BIM model intelligent review, and can quickly replace specifications or BIM models for review, thereby improving the intelligence level of the review, ensuring the delivery quality of the model, and reducing multiple rework caused by non-compliance issues of the BIM model. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] The technical solution of the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments, but it should be understood that these drawings are designed only for explanation purposes and are not intended to limit the scope of the present invention. In addition, unless otherwise specified, these drawings are intended only to conceptually illustrate the structural configurations described herein and are not necessarily drawn to scale.
[0051] Figure 1 It is a schematic diagram of the process of the present invention;
[0052] Figure 2 It is a partial fragment of the review standard library SL established according to a certain specification in the application example of the present invention;
[0053] Figure 3 A schematic diagram of an initial BIM model and a regenerated BIM model in an application example of the present invention;
[0054] Figure 4 It is a partial fragment of the element information library DL in the BIM model regenerated in the application example of the present invention;
[0055] Figure 5 Part of the review report output in the application example of the present invention;
[0056] Figure 6 It is a schematic diagram of the system module of the present invention. DETAILED DESCRIPTION
[0057] First of all, it should be noted that the specific structure, features and advantages of the present invention will be specifically described below by way of example, but all descriptions are only for illustration and should not be understood as limiting the present invention in any way. In addition, any single technical feature described or implied in the embodiments mentioned herein, or any single technical feature displayed or implied in the drawings, can still be combined or deleted between these technical features to obtain more other embodiments of the present invention that may not be directly mentioned in this document. In addition, in order to simplify the drawings, the same or similar technical features may be marked only in one place in the same drawing.
[0058] In the present invention, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the present invention according to the specific circumstances.
[0059] The following is combined with Figure 1 -Attached Figure 6 The present invention will be described in detail. Embodiment 1:
[0060] As attached Figure 1 To the attached Figure 5 As shown, a rail transit BIM model integrity review method based on B / S architecture includes the following steps:
[0061] S1: Deconstruct the BIM model specifications of urban rail transit projects, use cross-language processing algorithms to translate the specification clauses in human language and compile them into a review standard library SL (rf i ), where i ≥ 1, and is stored in a relational database on the backend server;
[0062] S2: On the Web side, the initial BIM model to be reviewed is uploaded to the backend server side, and the structural information, attribute information, material information and other data formats stored in the initial BIM model are reconstructed into a review standard library SL (rf) with a multi-level organizational system architecture through a bottom-up, multi-loop recursive approach using an information reconstruction algorithm. i ) regular data format and regenerate it into a lightweight BIM model that can be used for data exchange;
[0063] S3: In the regenerated BIM model, the element information library is DL (ep j ), j≥1, based on the principle of common semantic matching, based on the breadth-first traversal method BFS, construct the element information library DL (ep j ) and the Review Standard Library SL(rf i ) to calculate the integrity index I and matching coefficient M of each review element;
[0064] S4: Calculate the information integrity evaluation index E of the BIM model according to the integrity index I of each review element and its total number N1, the matching coefficient M of each review element and its total number N2 stored in the background database;
[0065] S5: According to the review results of each review element and the calculated integrity evaluation index E, the information integrity review report of the initial BIM model is output in the form of a file on the Web side.
[0066] Furthermore, in the embodiment, it can also be considered that in step S1, the BIM model specification of the urban rail transit project is deconstructed, including the following steps:
[0067] S201: Fully disassemble the specification and convert the diagrams in the specification into natural sentences written in human language code;
[0068] S202: According to the article number, the natural sentences in each article are automatically segmented according to word classes and symbols. The segmented text is more machine-readable and serves as the basis for subsequent article translation;
[0069] Wherein: the word classes include nouns, verbs, pronouns or other word classes, and the symbols include commas, periods, semicolons or other symbols.
[0070] Furthermore, in the embodiment, it can also be considered that in the step S1, the data storage format of the review standard library SL is determined on the basis of in-depth analysis of the main text items in the BIM model specifications of urban rail transit in various regions across the country and mining their consistency and specificity.
[0071] Furthermore, in the embodiment, it can also be considered that in step S1, rf i is a data tuple in the review standard library SL, that is, a set of review factors;
[0072] The review standard library SL has i data tuples, rf i = { i , pn i , pa i , pt i , pd i , pr i ,pc i , ps i ,…},pe i , pn i , pa i , pt i , pd i , pr i , pc i , ps i All are review factors;
[0073] Among them, pe i is the name of the subject of review, pn i To review the parameter name, pa i To review parameter values, pt i For information type, pd i For parameter grouping, pr i For the regulations, pc i is the parameter category, ps i is the parameter type;
[0074] Each rf i There must be a PC i At the same time, there may be several other types of review factors mentioned above, and the number and types of the review factors are adjusted according to specific specifications.
[0075] Furthermore, in the embodiment, it can also be considered that in step S2, the regenerated BIM model retains all geometric and non-geometric properties of the initial BIM model, and can be displayed in three-dimensional digital form on the Web.
[0076] Furthermore, in the embodiment, it can also be considered that in the step S2, the format of the initial BIM model to be reviewed includes, but is not limited to, .rvt, .rfa, .dgn, .sat, and .stp formats.
[0077] Furthermore, in the embodiments, it can also be considered that in the step S2, the professional classifications to which the initial BIM model to be reviewed belong include but are not limited to: lines, limits, tracks, buildings, structures and waterproofing, ventilation and air conditioning, water supply and drainage and fire protection, dynamic lighting, civil air defense, power supply system, communication system, signal system, gas fire extinguishing system, integrated monitoring system, environment and equipment monitoring system, automatic fire alarm system, access control system, automatic ticket vending and checking system, shield door, security inspection system, escalator and vertical elevator, bridge, sound barrier, trackside equipment, decoration and guidance, etc.
[0078] Furthermore, in the embodiment, it can also be considered that in step S3, ep j is a data tuple in the element information library DL, that is, a set of review elements;
[0079] There are j data tuples in the element information library DL, ep j = { et j , eid j , e.g. k ,…}, k≥1, et j 、eid j 、eg k All are review elements;
[0080] Among them, et j is the element name, eid j is the element id, e.g. k is the element attribute group;
[0081] eg k = { en n , ea n}, n≥1, en n is the attribute name, ea n is the attribute value;
[0082] Each ep j There must be et j and eid j , and there are k groups of element attribute groups, the value of k varies with the reference specifications during modeling; each eg k There are n sets of attribute names and attribute values, and the value of n varies with the reference specifications used during modeling.
[0083] Furthermore, in the embodiment, it can also be considered that in step S3, when calculating the integrity index I of each review element, the initial value of I is I=0. i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The censoring factor under the corresponding ep j If there is no corresponding review element in the background database, the ep is automatically recorded in the background database. j The element name in et j and the element's unique id value eid j , and for this ep j The completeness index I of the missing review elements is reassigned to I=1.
[0084] In this embodiment, rf i The review parameter name pn i 、Information type pt i 、Parameter grouping pd i A nominal audit factor or audit parameter value pa i Such as a numerical review factor, in the corresponding ep j If there is no corresponding review element in the background database, the ep is automatically recorded in the background database. j The element name in et j and the element's unique id value eid j , and for this ep j The completeness index I of the missing review elements is reassigned to I=1.
[0085] In this embodiment, nominal data, i.e., non-numeric data, cannot be subjected to mathematical operations, and numerical data, i.e., numerical data, can be subjected to mathematical operations.
[0086] Furthermore, in the embodiment, it can be considered that in step S3, when calculating the matching coefficient M of each review element, the initial value of M is 0. If a data tuple rf in the review standard library SL i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The target value of the review factor under the corresponding ep j The following matched element attribute group eg k Medium attribute value ea n If the value does not match, the ep is automatically recorded in the background database. j The element name in et j , the unique id value of the element eid j And element attribute groups such as kThe attribute name in en n , and for this ep j The matching coefficient M of the review element that does not match the target value of the review factor is reassigned to M=1.
[0087] In this embodiment, when the rf i The review parameter value pa i The target value of a numerical review factor, such as ep j The following matched element attribute group eg k Medium attribute value ea n If the value does not match, the ep is automatically recorded in the background database. j The element name in et j , the unique id value of the element eid j And element attribute groups, eg k The attribute name in en n , and for this ep j The matching coefficient M of the review elements that do not match the review factor target value is reassigned to M=1.
[0088] Furthermore, in the embodiment, it can also be considered that in step S4, the calculation method of the BIM model information integrity evaluation index E is:
[0089] .
[0090] Furthermore, in the embodiment, it can also be considered that in the step S5, the information integrity review report of the BIM model output includes the following contents:
[0091] All review elements with integrity index I=1 and their corresponding element names et j and the element's unique id value eid j ;
[0092] All the elements with matching coefficient M=1 and their corresponding element names et j , the unique id value of the element eid j , element attribute group eg k The attribute name in en n ;
[0093] Calculation results of BIM model information integrity evaluation index E.
[0094] Furthermore, in the embodiment, it can also be considered that in the step S4, the calculation result of the BIM model information integrity evaluation index E is: the numerical range of E is 0%≤E≤100%; within this range, the closer E is to 100%, the higher the integrity of the BIM model information, the better the model delivery quality, and the less model information needs to be modified; the closer E is to 0%, the lower the integrity of the BIM model information, the worse the model delivery quality, and the more model information needs to be modified.
[0095] Furthermore, in step S5, the output BIM model information integrity review report includes: all review elements with integrity index I=1 and their corresponding element names et j and the element's unique id value eid j ; All review elements with matching coefficient M=1 and their corresponding element names et j , the unique id value of the element eid j And element attribute groups, eg k The attribute name in en n ; Calculation results of BIM model information integrity evaluation index E.
[0096] Embodiment 2:
[0097] As attached Figure 6 As shown, the present invention provides a rail transit BIM model integrity review system based on B / S architecture, using a rail transit BIM model integrity review method based on B / S architecture, including the following modules:
[0098] Specification translation and storage module: deconstructs the BIM model specifications of urban rail transit projects, translates the specification clauses in human language and integrates them into a review standard library in machine language;
[0099] Model information reconstruction module: reconstructs the information of the uploaded initial BIM model and regenerates it into a lightweight BIM model that can be used for data exchange;
[0100] Review calculation processing module: constructs the mapping rules between the element information library and the review standard library, and calculates the integrity index and matching coefficient of each review element;
[0101] Evaluation index construction module: Calculate the BIM model information integrity evaluation index based on the integrity index and its total number, matching coefficient and its total number of each review element;
[0102] Review report output module: outputs the information integrity review report of the BIM model in the form of a file on the Web.
[0103] The report content includes: (1) all reviewed elements with an integrity index of 1, the corresponding element names and the unique id values of the elements; (2) all reviewed elements with a matching coefficient of 1, the corresponding element names, the unique id values of the elements, and the attribute names in the element attribute group; (3) the calculation results of the BIM model information integrity evaluation index.
[0104] In this embodiment, the details are as follows:
[0105] Standard translation storage module: deconstructs the BIM model specifications of urban rail transit projects, and uses cross-language processing algorithms to translate and compile standard clauses in human language into a review standard library SL (rf i ), i ≥ 1, and store it in the relational database on the backend server;
[0106] Model information reconstruction module: connected to the specification translation storage module, uploads the initial BIM model to be reviewed to the backend server on the Web side, and uses the information reconstruction algorithm to reconstruct the data format of the structural information, attribute information, material information, etc. stored in the initial BIM model into a multi-level organizational system architecture that complies with the review standard library SL (rf i ) regular data format and regenerate it into a lightweight BIM model that can be used for data exchange;
[0107] Review calculation processing module: connected to the model information reconstruction module, the element information library in the regenerated BIM model is DL (ep j ), j≥1, based on the principle of common semantic matching, based on the breadth-first search method (BFS), the element information library DL (ep j ) and the Review Standard Library SL(rf i ) to calculate the integrity index I and matching coefficient M of each review element;
[0108] Evaluation index construction module: connected to the review calculation processing module, calculates the BIM model information integrity evaluation index E according to the integrity index I and the total number N1 of each review element stored in the background database, the matching coefficient M of each review element and the total number N2;
[0109] Review report output module: connected to the evaluation index construction module, outputs the BIM model information integrity review report in the form of a file on the Web side according to the review results of each review element and the calculated integrity evaluation index E.
[0110] Embodiment 3:
[0111] An embodiment of the present invention provides a computer device, which includes: at least one processor, a memory, and a computer program stored in the memory and executable on the at least one processor, wherein the processor implements the steps of any of the above-mentioned method embodiments when executing the computer program.
[0112] Embodiment 4:
[0113] An embodiment of the present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in the above-mentioned method embodiments can be implemented.
[0114] Embodiment 5:
[0115] An embodiment of the present invention further provides an information data processing terminal, which, when executed on an electronic device, provides a user input interface to implement the steps in the above method embodiments. The information data processing terminal is not limited to mobile phones, computers, and switches.
[0116] Embodiment 6:
[0117] An embodiment of the present invention further provides a server, which is used to provide a user input interface to implement the steps in the above method embodiments when executed on an electronic device.
[0118] Embodiment 7:
[0119] An embodiment of the present invention provides a computer program product. When the computer program product runs on an electronic device, the electronic device can implement the steps in the above-mentioned method embodiments when executing the computer program product.
[0120] Application Example 1:
[0121] Based on Example 1, the present invention provides an example of its application, which is as follows:
[0122] Combined with Figure 1 To Attachment Figure 5 As shown, an embodiment of the present invention provides a method for reviewing the information integrity of a BIM model of urban rail transit based on a B / S architecture, which specifically includes the following steps:
[0123] Step S1, deconstruct the BIM model specification of urban rail transit engineering, and use the cross-language processing algorithm to translate the specification clauses in human language code and compile them into the review standard library SL (rf i ), i ≥ 1, and stored in the relational database on the backend server.
[0124] Specifically, in step S1, the BIM model specification of the urban rail transit project is deconstructed, including: the full text of the specification is disassembled, the charts in the specification are first converted into natural sentences written in human language codes, and then the natural sentences in each article are automatically segmented according to the word classes such as nouns, verbs, pronouns, and symbols such as commas, periods, and semicolons according to the article sequence number. The segmented text is more machine-readable and serves as the basis for subsequent article translation.
[0125] Specifically, in step S1, the data storage format of the review standard library SL is determined on the basis of in-depth analysis of the main text items in the BIM model specifications of urban rail transit in various regions across the country and mining their consistency and specificity.
[0126] Specifically, in step S1, taking Article 4.6, paragraph 5 of the "Technical Guidance Requirements for BIM Modeling of Section Structures of a Certain City Railway Group" as an example, the natural sentence segmentation is further explained: Article 4.6, paragraph 5 of the "Technical Guidance Requirements for BIM Modeling of Section Structures of a Certain City Railway Group": "The conventional segmentation of the dark excavation section is: the primary support segmentation is 0.75m, and the secondary lining segmentation is 9m." is divided into " / *dark excavation / §ion / &conventional / &segmentation / &situation / & is / &: / &primary support / &segmentation / & is / &0.75m / &, / &secondary lining / &segmentation / & is / &9m / &. / ^".
[0127] Specifically, in step S1, rf i is the data tuple in the review standard library SL, that is, the set of review factors. There are i data tuples in the review standard library SL, rf i = { i , pn i , pa i , pt i , pd i , pr i , pc i , ps i ,…},pe i 、pn i ,pa i ,pt i 、pd i etc. are all review factors, pe i is the name of the subject of review, pn i To review the parameter name, pa i To review parameter values, pt i For information type, pd i For parameter grouping, pr i For the regulations, pc i is the parameter category, ps i Is the parameter type; each rfi There must be a PC i There may be several other types of review factors mentioned above. The number and type of review factors need to be adjusted according to specific specifications. Taking the "Technical Guidance Requirements for Modeling the Section Structure BIM Model of a Certain City Railway Group" as an example, some fragments of the review standard library SL established according to this specification are shown in the attached figure. Figure 2 shown.
[0128] Step S2: Upload the initial BIM model to be reviewed to the backend server on the Web side, and use the information reconstruction algorithm to reconstruct the data format of the structural information, attribute information, material information, etc. stored in the initial BIM model into a multi-level organizational system architecture that meets the review standard library SL (rf i ) regular data format and regenerate it into a lightweight BIM model that can be used for data exchange.
[0129] Specifically, in step S2, the format of the initial BIM model to be reviewed includes, but is not limited to, .rvt, .rfa, .dgn, .sat, and .stp formats.
[0130] Specifically, in step S2, the professional categories to which the initial BIM model to be reviewed belong include but are not limited to: lines, limits, tracks, buildings, structures and waterproofing, ventilation and air conditioning, water supply and drainage and fire protection, dynamic lighting, civil air defense, power supply system, communication system, signal system, gas fire extinguishing system, integrated monitoring system, environment and equipment monitoring system, automatic fire alarm system, access control system, automatic ticket vending and checking system, shield door, security inspection system, escalator and vertical elevator, bridge, sound barrier, trackside equipment, decoration and guidance, etc.
[0131] Specifically, in step S2, the regenerated BIM model retains all geometric and non-geometric properties of the initial BIM model, and can be displayed in three-dimensional digital form on the Web. Taking a certain urban rail transit station as an example, the initial BIM model and the regenerated BIM model are shown in the attached figure. Figure 3 shown.
[0132] Specifically, in step S2, when the initial BIM model to be reviewed is uploaded to the backend server, the data transmission uses the JSON format and the data transmission complies with the TCP / IP protocol.
[0133] Step S3: The element information library in the regenerated BIM model is DL (ep j ), j≥1, based on the principle of common semantic matching, based on the breadth-first search method (BFS), the element information library DL (ep j ) and the Review Standard Library SL(rf i) and calculate the integrity index I and matching coefficient M of each review element.
[0134] Specifically, in step S3, the element information library DL(ep j ), ep j is the data tuple in the element information library DL, that is, the set of review elements. There are j data tuples in the element information library DL, ep j = { et j , eid j , e.g. k ,…}, k≥1, et j 、eid j 、eg k etc. are all review elements, et j is the element name, eid j is the element id, e.g. k For element attribute groups, e.g. k = { en n ,ea n}, n≥1, en n is the attribute name, ea n is the attribute value; each ep j There must be et j and eid j , and there are k groups of element attribute groups, the value of k varies with the reference specifications during modeling; each eg k There are n sets of attribute names and attribute values in the model, and the value of n varies with the reference specifications used during modeling;
[0135] Taking a certain city rail transit station as an example, some fragments of the element information library DL in the regenerated BIM model are shown in the attached figure. Figure 4 shown.
[0136] Specifically, in step S3, when calculating the integrity index I of each review element, the initial value of I is I=0. If a data tuple rf in the review standard library SL i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The review parameter name pn i 、Information type pt i 、Parameter grouping pd i A nominal audit factor or audit parameter value pa i Such as a numerical review factor, in the corresponding ep j If there is no corresponding review element in the background database, the ep is automatically recorded in the background database. j The element name in et j and the element's unique id value eidj , and for this ep j The completeness index I of the missing review elements is reassigned to I=1.
[0137] Specifically, in step S3, when calculating the matching coefficient M of each review element, the initial value of M is 0. If a data tuple rf in the review standard library SL i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The review parameter value pa i The target value of a numerical review factor, such as ep j The following matched element attribute group eg k Medium attribute value ea n If the value does not match, the ep is automatically recorded in the background database. j The element name in et j , the unique id value of the element eid j And element attribute groups, eg k The attribute name in en n , and for this ep j The matching coefficient M of the review elements that do not match the review factor target value is reassigned to M=1.
[0138] Step S4, calculate the BIM model information integrity evaluation index E according to the integrity index I of each review element and its total number N1, the matching coefficient M of each review element and its total number N2 stored in the background database.
[0139] Specifically, in step S4, the calculation method of the BIM model information integrity evaluation index E is:
[0140]
[0141] Using the Technical Guidance Requirements for Modeling the Section Structure BIM Model of a Certain City Railway Group, a certain city rail transit station was reviewed, and the integrity evaluation index was obtained from step S1 to step S4:
[0142]
[0143] Specifically, in step S4, the calculation result of the BIM model information integrity evaluation index E is as follows: the numerical range of E is 0%≤E≤100%; within this range, the closer E is to 100%, the higher the integrity of the BIM model information, the better the model delivery quality, and the less model information needs to be modified; the closer E is to 0%, the lower the integrity of the BIM model information, the worse the model delivery quality, and the more model information needs to be modified.
[0144] Step S5: Output the BIM model information integrity review report in the form of a file on the Web side according to the review results of each review element and the calculated integrity evaluation index E.
[0145] Specifically, in step S5, the output BIM model information integrity review report includes: all review elements with integrity index I=1 and their corresponding element names et j and the element's unique id value eid j ; All review elements with matching coefficient M=1 and their corresponding element names et j , the unique id value of the element eid j And element attribute groups such as k The attribute name in en n ; Calculation results of BIM model information integrity evaluation index E; Using the "Technical Guidance Requirements for Modeling the Section Structure BIM Model of a Certain City Railway Group" to review a certain city rail transit station, from steps one to five, the output of the review report is as follows Figure 5 shown.
[0146] The above embodiments describe the present invention in detail, but the contents are only preferred embodiments of the present invention and cannot be considered to limit the scope of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the present invention.
Claims
1. A rail transit BIM model integrity review method based on B / S architecture, characterized in that: The following steps are involved: S1: Deconstruct the BIM model specifications of urban rail transit projects, use cross-language processing algorithms to translate the specification clauses in human language and compile them into a review standard library SL (rf i ), where i ≥ 1, and is stored in a relational database on the backend server; S2: On the Web side, the initial BIM model to be reviewed is uploaded to the backend server. Using the information reconstruction algorithm, the structural information, attribute information, material information and other data formats stored in the initial BIM model are reconstructed into a multi-level organizational system that meets the review standard library SL (rf i ) regular data format and regenerate it into a lightweight BIM model that can be used for data exchange; S3: In the regenerated BIM model, the element information library is DL (ep j ), j≥1, based on the principle of common semantic matching, based on the breadth-first traversal method BFS, construct the element information library DL (ep j ) and the Review Standard Library SL(rf i ) to calculate the integrity index I and matching coefficient M of each review element; S4: Calculate the information integrity evaluation index E of the BIM model according to the integrity index I of each review element and its total number N1, the matching coefficient M of each review element and its total number N2 stored in the background database; S5: Outputting the information integrity review report of the BIM model in the form of a file on the Web end according to the review results of each review element and the calculated integrity evaluation index E; In step S1, rf i is a data tuple in the review standard library SL, that is, a set of review factors; The review standard library SL has i data tuples, rf i = { i , pn i , pa i , pt i , pd i , pr i , pc i ,ps i },pe i , pn i , pa i , pt i , pd i , pr i , pc i , ps i All are review factors; Among them, pe i is the name of the subject of review, pn i To review the parameter name, pa i To review parameter values, pt i For information type, pd i For parameter grouping, pr i For the regulations, pc i is the parameter category, ps i is the parameter type; Each rf i There must be a PC i , and there may be several other types of review factors mentioned above, the number and types of which are adjusted according to specific specifications; In step S3, ep j is a data tuple in the element information library DL, that is, a set of review elements; There are j data tuples in the element information library DL, ep j = { et j , eid j , e.g. k }, k ≥ 1, et j 、eid j 、eg k All are review elements; Among them, et j is the element name, eid j is the element id, e.g. k is the element attribute group; eg k = { en n , ea n }, n≥1, en n is the attribute name, ea n is the attribute value; Each ep j There must be et j and eid j , and there are k groups of element attribute groups, the value of k varies with the reference specifications during modeling; each eg k There are n sets of attribute names and attribute values, and the value of n varies with the reference specifications used during modeling.
2. The rail transit BIM model integrity review method based on B / S architecture according to claim 1 is characterized by: In step S1, the BIM model specification of the urban rail transit project is deconstructed, including the following steps: S201: Fully disassemble the specification and convert the diagrams in the specification into natural sentences written in human language code; S202: According to the article number, the natural sentences in each article are automatically segmented according to word classes and symbols. The segmented text is more machine-readable and serves as the basis for subsequent article translation; Wherein: the word classes include nouns, verbs, pronouns or other word classes, and the symbols include commas, periods, semicolons or other symbols.
3. The rail transit BIM model integrity review method based on B / S architecture according to claim 1 is characterized in that: In step S2, the regenerated BIM model retains all geometric and non-geometric properties of the initial BIM model, and can be displayed in three-dimensional digital form on the Web.
4. The rail transit BIM model integrity review method based on B / S architecture according to claim 1 is characterized in that: In step S3, when calculating the integrity index I of each review element, the initial value of I is I=0. i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The censoring factor under the corresponding ep j If there is no corresponding review element in the background database, the ep is automatically recorded in the background database. j The element name in et j and the element's unique id value eid j , and for this ep j The completeness index I of the missing review elements is reassigned to I=1.
5. The rail transit BIM model integrity review method based on B / S architecture according to claim 4 is characterized in that: In step S3, when calculating the matching coefficient M of each review element, the initial value of M is 0. If a data tuple rf in the review standard library SL i and a data tuple ep in the element information library DL j Comply with the mapping rule, and when the rf i The target value of the review factor under the corresponding ep j The following matched element attribute group eg k Medium attribute value ea n If the value does not match, the ep is automatically recorded in the background database. j The element name in et j , the unique id value of the element eid j And element attribute groups, eg k The attribute name in en n , and for this ep j The matching coefficient M of the review element that does not match the target value of the review factor is reassigned to M=1.
6. The rail transit BIM model integrity review method based on B / S architecture according to claim 1 is characterized by: In step S4, the calculation method of the BIM model information integrity evaluation index E is: 。 7. The rail transit BIM model integrity review method based on B / S architecture according to claim 5 is characterized by: In step S5, the information integrity review report of the BIM model is output, including the following contents: All review elements with integrity index I=1 and their corresponding element names et j and the element's unique id value eid j ; All the elements with matching coefficient M=1 and their corresponding element names et j , the unique id value of the element eid j , element attribute group eg k The attribute name in en n ; Calculation results of BIM model information integrity evaluation index E.
8. A rail transit BIM model integrity review system based on B / S architecture, using the rail transit BIM model integrity review method based on B / S architecture as described in any one of claims 1 to 7, characterized in that: Includes the following modules: Specification translation and storage module: deconstructs the BIM model specifications of urban rail transit projects, translates the specification clauses in human language and integrates them into a review standard library in machine language; Model information reconstruction module: reconstructs the information of the uploaded initial BIM model and regenerates it into a lightweight BIM model that can be used for data exchange; Review calculation processing module: constructs the mapping rules between the element information library and the review standard library, and calculates the integrity index and matching coefficient of each review element; Evaluation index construction module: Calculate the BIM model information integrity evaluation index based on the integrity index and its total number, matching coefficient and its total number of each review element; Review report output module: output BIM model information integrity review report in file form on the Web.