A boiler waste heat recovery energy scheduling management method and system
By judging the data quality in the boiler waste heat recovery system, dividing management windows and adopting appropriate scheduling methods, the energy scheduling problem when data quality is poor is solved, energy utilization efficiency and system performance are improved, and operating costs are reduced.
Patent Information
- Application Number
- CN202411004186.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-07-25
AI Technical Summary
The existing boiler waste heat recovery energy dispatch management system is difficult to switch to rule-based dispatch management when the data quality is poor, resulting in low energy utilization efficiency and high cost, and it is difficult to screen intelligent algorithms and rule-based application scenarios.
By obtaining the information of the data transmission channel, it is judged whether there is insufficient data support in the management window, the data anomaly index and the transmission anomaly index are generated, and sent to the pre-trained machine learning model, the data quality coefficient is generated, and divided into basic management Window and fine management windows use rule-based scheduling to manage basic windows and intelligent algorithm-based scheduling to manage fine windows, and use fuzzy logic to determine optimization strategies for adaptive optimization.
It achieves the best operating status under different data quality conditions, improves energy utilization efficiency, reduces energy waste and operating costs, and ensures stable operation of the system and data quality.
Smart Images

Figure CN118521144B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of energy recovery, and more specifically, to a boiler waste heat recovery energy scheduling management method and system. Background Art
[0002] Boiler waste heat recovery energy dispatch management refers to the systematic method of recovering and reusing the waste heat generated during boiler operation, and optimizing the distribution and use of energy through an intelligent dispatch system. Specifically, a large amount of waste heat is generated during the combustion process of the boiler. If this heat is not recycled, it will cause energy waste and environmental pollution. Through waste heat recovery technology, this waste heat can be converted into usable energy forms, such as steam or hot water, for heating, industrial production or power generation.
[0003] The existing technology has the following deficiencies: The existing energy dispatching and management system based on intelligent algorithms optimizes the entire process of waste heat recovery and utilization through real-time monitoring and data analysis. The dispatching system can intelligently adjust the distribution and use of waste heat according to factors such as the operating status of the equipment to ensure efficient use of energy and minimized costs. The dispatching method based on rule-based dispatching management is suitable for situations where data quality is poor. Compared with the energy dispatching and management system based on intelligent algorithms, it reduces the requirements for the overall data quality. When the data quality is poor and is not suitable for energy dispatching management using intelligent algorithms, switching to the dispatching method based on rule-based dispatching management can ensure the management quality during actual dispatching. How to screen the application scenarios of the two is a problem that needs to be solved. Therefore, a boiler waste heat recovery energy dispatching management method and system are proposed. Summary of the invention
[0004] To achieve the above object, the present invention provides the following technical solutions:
[0005] A boiler waste heat recovery energy scheduling management method comprises the following steps:
[0006] Obtain the preset rule-based scheduling management scheduling method 1 and intelligent algorithm-based scheduling method 2, collect information on the data transmission channel for boiler waste heat recovery monitoring, and then conduct preliminary analysis to determine whether there is a hidden danger of insufficient data support in the management window;
[0007] When there is a hidden danger of insufficient data support, the recovery information in the boiler waste heat recovery process is collected, and then an abnormality analysis is performed to generate a data anomaly index and a transmission anomaly index. The data anomaly index and the transmission anomaly index are then transmitted to a pre-trained machine learning model to generate a data quality coefficient through the pre-trained machine learning model.
[0008] Based on the generated data quality coefficient, the management window is divided into a basic management window and a fine management window;
[0009] The first dispatching method is used to manage the energy dispatching of the basic management window, and the second dispatching method is used to manage the energy dispatching of the fine management window;
[0010] For the basic management window of energy dispatch management using dispatch mode 1, determine the optimization processing strategy and perform adaptive optimization.
[0011] In a preferred embodiment, the steps of determining whether there is a hidden danger of insufficient data support in the management window are as follows:
[0012] For the target management window, divide it into multiple continuous time windows, and then obtain the actual packet loss rate of each time window to obtain the time series D: , , …, ; n is the total number of divided time windows, then the actual packet loss rate average value and the actual packet loss rate standard deviation of the time series D are calculated, the actual packet loss rate average value is compared with the preset reference interval, and the actual packet loss rate standard deviation is compared with the preset reference threshold. If the actual packet loss rate average value is within the preset reference interval and the actual packet loss rate standard deviation is less than or equal to the preset reference threshold, a normal signal is generated. If the actual packet loss rate average value is within the preset reference interval and the actual packet loss rate standard deviation is less than or equal to the preset reference threshold, a hidden danger signal is generated. When the hidden danger signal is generated, it indicates that the management window has a hidden danger of insufficient data support.
[0013] Collecting the recovery information during the boiler waste heat recovery process refers to collecting the monitoring information during the boiler waste heat recovery process and collecting the transmission information during the data transmission process.
[0014] In a preferred embodiment, the logic for obtaining the data anomaly index is:
[0015] Get the data collection frequency, actual value, number of data points collected for each sensor, and then calculate the data coverage: ; CRi represents the data coverage of the i-th sensor, NCi represents the number of data points actually collected by the i-th sensor, and NQi represents the number of data points required by the i-th sensor. Then calculate the overall data gap rate: ; OGR represents the overall data gap rate, and M is the total number of sensors;
[0016] Calculate the average deviation between the measured value and the actual value of each sensor: ; MDi represents the average deviation between the measured value and the actual value of sensor i, represents the measured value of the jth data point of the i-th sensor, represents the actual value of the jth data point of the ith sensor, and then calculates the standardized deviation value for each sensor: ; SDi is the standardized deviation value of sensor i, represents the average value of the actual value of the i-th sensor; then calculate the overall standardized deviation value: ; OSD is the overall standardized deviation;
[0017] Calculate the actual acquisition frequency of each sensor: ; T is the time period value collected by the sensor, AFi is the actual collection frequency of sensor i; then calculate the frequency gap rate of each sensor: ; FRi is the acquisition frequency required by sensor i, and FGRi is the frequency gap rate of sensor i; then calculate the overall frequency gap rate: ; OFGR represents the overall frequency gap rate;
[0018] Based on the overall data gap rate OGR, the overall standardized deviation value OSD, and the overall frequency gap rate OFGR, a weighted geometric mean is calculated to obtain the data anomaly index. The specific calculation formula is: ; DAI represents data anomaly index.
[0019] In a preferred embodiment, the logic for obtaining the transmission anomaly index is:
[0020] Get the sending time, receiving time, and packet size of each data packet, and then calculate the packet loss rate. The packet loss rate is obtained by dividing the number of lost packets by the total number of sent packets.
[0021] Calculate the transmission delay time value of each data packet. The transmission delay time value is obtained by subtracting the transmission time of the data packet from the reception time of the data packet. Then calculate the sum of the transmission delay time values of all data packets to obtain the total transmission time value. Divide the total transmission time value by the total number of data packets to obtain the average transmission delay time value. Then use the standard deviation calculation formula to calculate the standard deviation value of the transmission delay time and calculate the coefficient of variation of the transmission delay: ; ATD represents the average transmission delay time value, SDTD represents the standard deviation value of the transmission delay time, and CVTD represents the coefficient of variation of the transmission delay;
[0022] Calculate the deviation value for each packet size: ; Si represents the size of the i-th data packet, represents the average size of all received data packets, SDPSi represents the deviation value of the ith data packet, the standard deviation value of the data packet size is calculated using the standard deviation calculation formula, and then the coefficient of variation of the data packet size is calculated: ; SDP represents the standard deviation value of the data packet size, and CVPS represents the coefficient of variation of the data packet size;
[0023] Based on the packet loss rate, the coefficient of variation of transmission delay CVTD, and the coefficient of variation of packet size CVPS, the Euclidean distance calculation method is used to calculate the transmission anomaly index. The specific calculation formula is: ; NPLR represents the packet loss rate, and TAI represents the transmission anomaly index.
[0024] In a preferred embodiment, based on the generated data quality coefficient, dividing the management window into a basic management window and a fine management window means:
[0025] The generated data quality coefficient is compared with the preset data adoption reference coefficient. If the generated data quality coefficient is greater than or equal to the preset data adoption reference coefficient, the management window is divided into a fine management window. If the generated data quality coefficient is less than the preset data adoption reference coefficient, the management window is divided into a basic management window.
[0026] In a preferred embodiment, for the basic management window that adopts scheduling mode 1 for energy scheduling management, the strategy for determining the optimization processing refers to: obtaining the data anomaly index, transmission anomaly index, and data quality coefficient of the basic management window, and then applying fuzzy logic for reasoning to determine the type of optimization strategy for improving data quality.
[0027] In a preferred embodiment, the logic of reasoning using fuzzy logic is:
[0028] Define the input variables as data anomaly index, transmission anomaly index, and data quality coefficient, define the output variable as the type of optimization strategy, fuzzify the input variables, and convert the values of the input variables into fuzzy sets, fuzzify the output variables, and convert the output variables into fuzzy sets, formulate fuzzy rules, describe the optimization requirements under different data type combinations, and infer the fuzzified input variables through fuzzy rules to determine the type of optimization strategy.
[0029] In a preferred embodiment, a boiler waste heat recovery energy scheduling and management system includes a scheduling mode library, a preliminary judgment module, an abnormal analysis module, a delivery module, an optimization strategy judgment module, and an adaptive optimization module;
[0030] The preliminary judgment module is used to collect information from the data transmission channel for boiler waste heat recovery monitoring, and then conduct preliminary analysis to determine whether there is a hidden danger of insufficient data support in the management window;
[0031] The abnormal analysis module is used to collect the recovery information in the boiler waste heat recovery process when there is a hidden danger of insufficient data support, and then perform abnormal analysis to generate a data abnormality index and a transmission abnormality index, and then transmit the data abnormality index and the transmission abnormality index to a pre-trained machine learning model to generate a data quality coefficient through the pre-trained machine learning model;
[0032] The dispatch method library has preset dispatch method 1 based on rule-based dispatch management and dispatch method 2 based on intelligent algorithm;
[0033] The delivery module divides the management window into a basic management window and a fine management window based on the generated data quality coefficient, and then delivers the basic management window to the dispatch mode 1 for energy dispatch management, and delivers the fine management window to the dispatch mode 2 for energy dispatch management;
[0034] The optimization strategy judgment module is used to judge the optimization processing strategy for the basic management window that adopts the scheduling mode 1 for energy scheduling management;
[0035] The adaptive optimization module adaptively optimizes and improves data quality based on the optimization processing strategy determined by the optimization strategy determination module.
[0036] Technical effects and advantages of the present invention:
[0037] Through data collection and preliminary analysis, the present invention can timely determine whether there is a hidden danger of insufficient data support in the management window, and can quickly discover and solve potential problems to ensure the stable operation of the system. Based on the data anomaly index and the transmission anomaly index, a data quality coefficient (DQC) is generated, and then the management window is divided into a basic management window and a fine management window. Through this refined management, different scheduling strategies can be adopted for different data quality conditions to optimize resource allocation and improve management efficiency. Basic management window: adopts a rule-based scheduling management method (scheduling method one), which is suitable for situations with poor data quality. Through a simple and efficient management method, resource consumption is reduced. Fine management window: adopts a scheduling management method based on an intelligent algorithm (scheduling method two), which is suitable for situations with good data quality. Through intelligent and refined scheduling management, energy use is further optimized and system performance is improved.
[0038] The method and system of the present invention have strong scalability and adaptability, and can be adjusted and optimized according to specific application requirements. Whether it is a boiler waste heat recovery system or other energy management systems, the method and technology of the present invention can be applied through corresponding adjustments to improve system performance and data quality. In the basic management window, the optimization processing strategy is judged and adaptive optimization is performed. Through the adaptive optimization module, the data collection and transmission strategies are dynamically adjusted to further improve data quality and system performance. By optimizing energy scheduling management, the energy utilization efficiency in the boiler waste heat recovery process is improved. The combination of rule-based scheduling management methods and intelligent algorithms ensures the optimal operating state of the system under different data quality conditions, reduces energy waste, and reduces operating costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] In order to facilitate understanding by those skilled in the art, the present invention is further described below in conjunction with the accompanying drawings;
[0040] Figure 1 This is a schematic diagram of a boiler waste heat recovery energy scheduling management method in the present invention.
[0041] Figure 2 This is a schematic diagram of a boiler waste heat recovery energy dispatching and management system in the present invention. DETAILED DESCRIPTION
[0042] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0043] Reference Figure 1 - Figure 2 The following embodiments are obtained:
[0044] Embodiment 1: A boiler waste heat recovery energy scheduling management method comprises the following steps:
[0045] Obtain the preset rule-based scheduling management scheduling method 1 and intelligent algorithm-based scheduling method 2, collect information on the data transmission channel for boiler waste heat recovery monitoring, and then conduct preliminary analysis to determine whether there is a hidden danger of insufficient data support in the management window;
[0046] The scheduling method mentioned in the present invention is illustrated as follows: determine the key parameters that need to be monitored and scheduled in the system, such as temperature, pressure, flow, etc. Set thresholds and rules: temperature threshold: upper limit temperature: 90°C, lower limit temperature: 60°C; pressure threshold: upper limit pressure: 15bar, lower limit pressure: 10bar; flow threshold: upper limit flow: 1000L / h, lower limit flow: 500L / h. Scheduling rules:
[0047] If the temperature exceeds 90°C, activate the cooling system to reduce the temperature to below 85°C.
[0048] If the temperature is below 60°C, start the heating system to raise the temperature to above 65°C.
[0049] If the pressure exceeds 15 bar, open the pressure relief valve and reduce the pressure to below 14 bar.
[0050] If the pressure is lower than 10 bar, start the booster system to increase the pressure to above 11 bar.
[0051] If the flow rate exceeds 1000 L / h, reduce supply or increase storage to reduce the flow rate to below 900 L / h.
[0052] If the flow rate is less than 500 L / h, increase supply or reduce consumption to increase the flow rate to more than 600 L / h.
[0053] The rule-based scheduling management method relies on pre-set thresholds and rules, and is suitable for scenarios with relatively simple system structures and relatively stable operating parameters. This method is simple, reliable, and easy to implement, but it has low flexibility and is difficult to cope with complex and changing situations.
[0054] The second scheduling method based on the intelligent algorithm is an intelligent algorithm mentioned in an intelligent chemical flue gas recovery and regulation device disclosed in the existing patent. The intelligent chemical flue gas recovery and regulation device includes a smoking device, a flue gas storage device, a smoke water diversion device, an insulated gas storage tank, an insulated water storage tank, an air heat exchange device, a water heat exchange device, and control valves on each pipeline. The spray pipeline replaces part of the flue gas heat with water to achieve the diversion of flue gas and water heat, thereby more efficiently absorbing the heat load carried by the corresponding medium. It can also store excess flue gas or water in an adiabatic manner and perform heat conversion when the system demand is large. Using the Tianniu group algorithm, the opening and closing size of the control valves of each pipeline is optimized and controlled to achieve the optimal waste heat recovery efficiency of the regulation equipment. Compared with the prior art, the equipment has a higher chemical flue gas waste heat recovery efficiency, and can effectively replace heat recovery equipment such as waste heat boilers in the integrated energy system, and can also store and release heat energy, and realize the heat load scheduling inside the regulator together with the control valve. When using intelligent algorithms, higher requirements are placed on the reliability and stability of data. For example, in the monitoring and acquisition of valve recovery heat data in the Tianniu swarm algorithm, it is necessary to ensure the high quality of the data. When there is no hidden danger of insufficient data support, intelligent algorithms are generally used for scheduling.
[0055] The steps to determine whether there is a risk of insufficient data support in the management window are as follows:
[0056] For the target management window, divide it into multiple continuous time windows, each of which has the same length. Then obtain the actual packet loss rate of each time window to obtain the time series D: , , …, ; n is the total number of divided time windows, then the actual packet loss rate average value and the actual packet loss rate standard deviation of the time series D are calculated, the actual packet loss rate average value is compared with the preset reference interval, and the actual packet loss rate standard deviation is compared with the preset reference threshold. If the actual packet loss rate average value is within the preset reference interval and the actual packet loss rate standard deviation is less than or equal to the preset reference threshold, a normal signal is generated. If the actual packet loss rate average value is within the preset reference interval and the actual packet loss rate standard deviation is less than or equal to the preset reference threshold, a hidden danger signal is generated. When the hidden danger signal is generated, it indicates that there is a hidden danger of insufficient data support in the management window; by monitoring and analyzing the actual packet loss rate, the stability of the data transmission process is judged to ensure the integrity and accuracy of the data. A high packet loss rate or large fluctuation may result in insufficient data to support the normal operation of the system. By generating hidden danger signals, problems with insufficient data support can be discovered in advance, avoiding data loss or errors at critical moments, which would lead to performance degradation of intelligent algorithms. This is conducive to taking measures in advance to optimize data or adjust transmission, and ensure the stability and reliability of intelligent algorithms. Insufficient data support will directly affect the accuracy and reliability of data-based decisions. Ensuring sufficient data support can improve the accuracy of intelligent algorithms in the data-driven decision-making process and reduce erroneous decisions caused by data problems.
[0057] When there is a hidden danger of insufficient data support, the recovery information in the boiler waste heat recovery process is collected, and then anomaly analysis is performed to generate a data anomaly index and a transmission anomaly index, and then the data anomaly index and the transmission anomaly index are transmitted to a pre-trained machine learning model to generate a data quality coefficient through the pre-trained machine learning model; collecting recovery information in the boiler waste heat recovery process refers to collecting monitoring information in the boiler waste heat recovery process and collecting transmission information in the data transmission process.
[0058] The logic for obtaining the data anomaly index is:
[0059] Collect monitoring information: including key parameters such as temperature, pressure, flow, etc., obtain the data collection frequency, actual value, and number of data points collected for each sensor, and then calculate the data coverage: ; CRi represents the data coverage rate of the i-th sensor, reflecting the ratio of the number of data points actually collected by the sensor to the number of required data points, NCi represents the number of data points actually collected by the i-th sensor, and NQi represents the number of data points required by the i-th sensor. Then the overall data gap rate is calculated: ; OGR represents the overall data gap rate, reflecting the data coverage of all sensors, and M is the total number of sensors;
[0060] Calculate the average deviation between the measured value and the actual value of each sensor: ; MDi represents the average deviation between the measured value and the actual value of sensor i, reflecting the degree of deviation between the measured value and the actual value of the sensor. represents the measured value of the jth data point of the i-th sensor, represents the actual value of the jth data point of the ith sensor, and then calculates the standardized deviation value for each sensor: ; SDi is the standardized deviation value of sensor i, and the standardized average deviation value is convenient for comparison between different sensors. represents the average value of the actual value of the i-th sensor; then calculate the overall standardized deviation value: ; OSD is the overall standardized deviation value, reflecting the overall deviation of all sensors;
[0061] Calculate the actual acquisition frequency of each sensor: ; T is the time period value collected by the sensor, AFi is the actual collection frequency of sensor i, reflecting the actual data frequency collected by the sensor in a certain period of time; then calculate the frequency gap rate of each sensor: ; FRi is the acquisition frequency required by sensor i, and FGRi is the frequency gap rate of sensor i, which reflects the difference between the actual acquisition frequency and the required acquisition frequency; then calculate the overall frequency gap rate: ; OFGR represents the overall frequency gap rate, reflecting the acquisition frequency of all sensors;
[0062] Based on the overall data gap rate OGR, the overall standardized deviation value OSD, and the overall frequency gap rate OFGR, a weighted geometric mean is calculated to obtain the data anomaly index. The specific calculation formula is: ; DAI represents the data anomaly index, which comprehensively reflects the overall data quality indicator of data coverage, deviation and collection frequency. w1, w2 and w3 are the weights of each factor, which can be adjusted according to actual needs.
[0063] The data anomaly index comprehensively considers data coverage, standardized deviation value and frequency gap rate, and is used to evaluate the data quality of each sensor in the system. The size of DAI directly reflects the degree of data anomaly. DAI is close to 0: The closer the data anomaly index is to 0, the lower the degree of data anomaly in the system. At this time, the data coverage is high, the deviation between the measured value and the actual value is small, and the difference between the data collection frequency and the required frequency is small. Moderate DAI (greater than 0 and less than 1): The data anomaly index is between 0 and 1, indicating that there is a certain degree of data anomaly in the system. At this time, some sensors may have slight insufficient data coverage, deviation or collection frequency difference. There are some problems with the data collection of the sensor, but the overall impact is not significant, and the data collection quality is basically acceptable. High DAI (greater than or equal to 1): The data anomaly index is greater than or equal to 1, indicating that there is a significant data anomaly in the system. At this time, one or more factors in the data coverage, deviation and collection frequency difference are seriously deviated from the normal range. The data collection condition of the sensor is poor, and the data collection quality is low, which may affect the normal operation and decision accuracy of the intelligent algorithm in the second scheduling method.
[0064] The logic for obtaining the transmission anomaly index is:
[0065] Collect data transmission information: record the sending time, receiving time, and packet size of each data packet, obtain the sending time, receiving time, and packet size of each data packet, and then calculate the packet loss rate. The packet loss rate is obtained by dividing the number of lost packets by the total number of sent packets, which reflects the loss of data packets during the transmission process;
[0066] Calculate the transmission delay time value of each data packet. The transmission delay time value is obtained by subtracting the transmission time of the data packet from the reception time of the data packet, reflecting the time difference from the transmission to the reception of the data packet. Then calculate the sum of the transmission delay time values of all data packets to obtain the total transmission time value. Divide the total transmission time value by the total number of data packets to obtain the average transmission delay time value, reflecting the overall delay level of data packet transmission. Then use the standard deviation calculation formula to calculate the standard deviation value of the transmission delay time, reflecting the fluctuation of the transmission delay, and calculate the coefficient of variation of the transmission delay: ; ATD represents the average transmission delay time value, SDTD represents the standard deviation value of the transmission delay time, and CVTD represents the coefficient of variation of the transmission delay, which is a standardized delay fluctuation measure;
[0067] Calculate the deviation value for each packet size: ; Si represents the size of the i-th data packet, represents the average size of all received data packets, SDPSi represents the deviation value of the ith data packet, the standard deviation value of the data packet size is calculated using the standard deviation calculation formula, and then the coefficient of variation of the data packet size is calculated: ; SDP represents the standard deviation value of the packet size, reflecting the fluctuation of the packet size, and CVPS represents the coefficient of variation of the packet size, which is a standardized measure of packet size fluctuation;
[0068] Based on the packet loss rate, the coefficient of variation of transmission delay CVTD, and the coefficient of variation of packet size CVPS, the Euclidean distance calculation method is used to calculate the transmission anomaly index. The specific calculation formula is: NPLR represents the packet loss rate, and TAI represents the transmission anomaly index, which comprehensively reflects the degree of anomaly of the packet loss rate, transmission delay coefficient of variation, and packet size coefficient of variation. By monitoring TAI, anomalies in data transmission can be discovered in advance, and timely measures can be taken to avoid the impact of data loss and delay on the performance of the intelligent algorithm in scheduling method 2. The transmission anomaly index is close to 0, indicating that the packet loss rate is low, the delay is stable, the packet size consistency is high, and the data transmission quality is high during the data transmission process. The transmission anomaly index is between 0 and 1, indicating that there are certain problems with the packet loss rate, delay, and packet size fluctuations during the data transmission process, and there are some problems with the data transmission quality, but the overall impact is not significant. The transmission anomaly index is greater than or equal to 1, indicating that the packet loss rate is high, the delay fluctuation is large, the packet size inconsistency is serious, and the data transmission quality is low during the data transmission process, which may affect the normal operation of the intelligent algorithm in scheduling method 2.
[0069] The machine learning model is not specifically limited here. Any model that can perform comprehensive analysis of the data anomaly index and the transmission anomaly index to generate a data quality coefficient can be used. In order to implement the technical solution of the present invention, the present invention provides a specific implementation method: the data anomaly index and the transmission anomaly index are standardized so that their data range is within the same scale, and then substituted into the pre-trained machine learning model. In the present invention, Min-Max standardization is adopted to scale the data anomaly index (DAI) and the transmission anomaly index (TAI) to the range of [0,1]. Assuming that the machine learning model is a simple linear regression model, its coefficient vector is w=[w1,w2] and the bias term is b, then the calculation formula of the data quality coefficient is: ; and They respectively represent the data anomaly index and transmission anomaly index after standardization. DQC is the data quality coefficient. The size of the data quality coefficient can intuitively reflect the overall quality of the data in the system. The larger the value, the higher the overall data quality, and the more suitable it is for use with the intelligent algorithm in scheduling method 2.
[0070] Based on the generated data quality coefficient, the management window is divided into a basic management window and a fine management window; the generated data quality coefficient is compared with the preset data reference coefficient. If the generated data quality coefficient is greater than or equal to the preset data reference coefficient, the management window is divided into a fine management window. If the generated data quality coefficient is less than the preset data reference coefficient, the management window is divided into a basic management window. The basic management window is energy dispatched and managed using scheduling method one, and the fine management window is energy dispatched and managed using scheduling method two: Scheduling method one (basic management window): a scheduling management method based on rules, which is suitable for windows with poor data quality, where the system operation is relatively unstable and requires a simple and efficient management method. Scheduling method two (fine management window): a scheduling management method based on intelligent algorithms, which is suitable for windows with good data quality, where the system operation is stable and allows for more refined and dynamic scheduling management.
[0071] For the basic management window that adopts scheduling method one for energy scheduling management, the optimization processing strategy is determined and adaptive optimization is performed. For the basic management window that adopts scheduling method one for energy scheduling management, the optimization processing strategy is determined by obtaining the data anomaly index, transmission anomaly index, and data quality coefficient of the basic management window, and then applying fuzzy logic for reasoning to determine the type of optimization strategy for improving data quality.
[0072] The logic of applying fuzzy logic for reasoning is:
[0073] Define the input variables as data anomaly index, transmission anomaly index, and data quality coefficient, define the output variable as the type of optimization strategy, fuzzify the input variables, and convert the values of the input variables into fuzzy sets, fuzzify the output variables, and convert the output variables into fuzzy sets, formulate fuzzy rules, describe the optimization requirements under different data type combinations, and infer the fuzzified input variables through fuzzy rules to determine the type of optimization strategy.
[0074] Define input variables and output variables, input variables: data anomaly index (DAI), transmission anomaly index (TAI), data quality coefficient (DQC); output variables: optimization strategy type (OPT); fuzzy processing of input variables, define fuzzy sets: data anomaly index (DAI): low (Low, L), medium (Medium, M), high (High, H); transmission anomaly index (TAI): low (Low, L), medium (Medium, M), high (High, H); data quality coefficient (DQC): low (Low, L), medium (Medium, M), high (High, H), fuzzy processing of output variables, optimization strategy type (OPT): data collection optimization ( The optimization strategy type is finally obtained by applying fuzzy logic for reasoning. The system status can be comprehensively evaluated and the most appropriate optimization strategy type can be determined based on the data anomaly index, transmission anomaly index and data quality coefficient. This method can flexibly handle different data situations, provide targeted optimization suggestions, and ensure the stability and efficiency of system operation.
[0075] Embodiment 2: A boiler waste heat recovery energy dispatching and management system, comprising a dispatching mode library, a preliminary judgment module, an abnormality analysis module, a delivery module, an optimization strategy judgment module, and an adaptive optimization module;
[0076] The preliminary judgment module is used to collect information from the data transmission channel for boiler waste heat recovery monitoring, and then conduct preliminary analysis to determine whether there is a hidden danger of insufficient data support in the management window;
[0077] The abnormal analysis module is used to collect the recovery information in the boiler waste heat recovery process when there is a hidden danger of insufficient data support, and then perform abnormal analysis to generate a data abnormality index and a transmission abnormality index, and then transmit the data abnormality index and the transmission abnormality index to a pre-trained machine learning model to generate a data quality coefficient through the pre-trained machine learning model;
[0078] The dispatch method library has preset dispatch method 1 based on rule-based dispatch management and dispatch method 2 based on intelligent algorithm;
[0079] The delivery module divides the management window into a basic management window and a fine management window based on the generated data quality coefficient, and then delivers the basic management window to the dispatch mode 1 for energy dispatch management, and delivers the fine management window to the dispatch mode 2 for energy dispatch management;
[0080] The optimization strategy judgment module is used to judge the optimization processing strategy for the basic management window that adopts the scheduling mode 1 for energy scheduling management;
[0081] The adaptive optimization module adaptively optimizes and improves the data quality based on the optimization processing strategy determined by the optimization strategy judgment module. The adaptive optimization module receives the optimization strategy provided by the optimization strategy judgment module. The optimization strategies include: data collection optimization (DCO), data transmission optimization (DTO), and both optimization (BO). According to the received optimization strategy, the adaptive optimization module executes corresponding optimization measures, such as optimizing the problems existing in the data collection process during data collection optimization. Specific measures include but are not limited to: increasing the acquisition frequency, increasing the frequency of data collection to ensure the real-time and integrity of the data, dynamically adjusting the acquisition frequency of the sensor, and adapting according to data requirements and actual conditions. Calibrate sensors: Calibrate sensors regularly to improve data accuracy, and recalibrate or replace sensors with large deviations. Expand collection points: Increase the number of data collection points to cover more monitoring areas, ensure comprehensive monitoring of key parameters, and reduce data gaps.
[0082] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0083] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0084] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0085] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0086] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A boiler waste heat recovery energy scheduling management method, It is characterized in that The following steps are involved: Obtain the preset rule-based scheduling management scheduling method 1 and intelligent algorithm-based scheduling method 2, collect information on the data transmission channel for boiler waste heat recovery monitoring, and then conduct preliminary analysis to determine whether there is a hidden danger of insufficient data support in the management window; When there is a hidden danger of insufficient data support, the recovery information in the boiler waste heat recovery process is collected, and then an abnormality analysis is performed to generate a data anomaly index and a transmission anomaly index. The data anomaly index and the transmission anomaly index are then transmitted to a pre-trained machine learning model to generate a data quality coefficient through the pre-trained machine learning model. Based on the generated data quality coefficient, the management window is divided into a basic management window and a fine management window; The first dispatching method is used to manage the energy dispatching of the basic management window, and the second dispatching method is used to manage the energy dispatching of the fine management window; For the basic management window of energy dispatch management using dispatch mode 1, determine the optimization processing strategy and perform adaptive optimization; The steps to determine whether there is a risk of insufficient data support in the management window are as follows: For the target management window, it is divided into multiple continuous time windows, and then the actual packet loss rate of each time window is obtained respectively to obtain the time series D: D1, D2, ..., Dn; n is the total number of divided time windows, and then the actual packet loss rate average value and the actual packet loss rate standard deviation of the time series D are calculated, and the actual packet loss rate average value is compared with the preset reference interval, and the actual packet loss rate standard deviation is compared with the preset reference threshold. If the actual packet loss rate average value is within the preset reference interval and the actual packet loss rate standard deviation is less than or equal to the preset reference threshold, a normal signal is generated. If the actual packet loss rate average value is within the preset reference interval and the actual packet loss rate standard deviation is less than or equal to the preset reference threshold, a hidden danger signal is generated. When the hidden danger signal is generated, it indicates that the management window has a hidden danger of insufficient data support; Collecting the recovery information during the boiler waste heat recovery process refers to collecting the monitoring information during the boiler waste heat recovery process and collecting the transmission information during the data transmission process; The logic for obtaining the data anomaly index is: Get the data collection frequency, actual value, number of data points collected for each sensor, and then calculate the data coverage: CRi represents the data coverage of the i-th sensor, NCi represents the number of data points actually collected by the i-th sensor, and NQi represents the number of data points required by the i-th sensor. Then the overall data gap rate is calculated: OGR represents the overall data gap rate, and M is the total number of sensors; Calculate the average deviation between the measured value and the actual value of each sensor: MDi represents the average deviation between the measured value and the actual value of sensor i, Vij represents the measured value of the jth data point of the i-th sensor, and Vij' represents the actual value of the jth data point of the i-th sensor. Then the standardized deviation value of each sensor is calculated: SDi is the standardized deviation value of sensor i, and Vi represents the average value of the actual value of the i-th sensor; then the overall standardized deviation value is calculated: OSD is the overall standardized deviation value; Calculate the actual acquisition frequency of each sensor: T is the time period value collected by the sensor, and AFi is the actual collection frequency of sensor i; then the frequency gap rate of each sensor is calculated: FRi is the acquisition frequency required by sensor i, and FGRi is the frequency gap rate of sensor i; then calculate the overall frequency gap rate: OFGR represents the overall frequency gap ratio; Based on the overall data gap rate OGR, the overall standardized deviation value OSD, and the overall frequency gap rate OFGR, a weighted geometric mean is calculated to obtain the data anomaly index; The logic for obtaining the transmission anomaly index is: Get the sending time, receiving time, and packet size of each data packet, and then calculate the packet loss rate. The packet loss rate is obtained by dividing the number of lost packets by the total number of sent packets. Calculate the transmission delay time value of each data packet. The transmission delay time value is obtained by subtracting the transmission time of the data packet from the reception time of the data packet. Then calculate the sum of the transmission delay time values of all data packets to obtain the total transmission time value. Divide the total transmission time value by the total number of data packets to obtain the average transmission delay time value. Then use the standard deviation calculation formula to calculate the standard deviation value of the transmission delay time and calculate the coefficient of variation of the transmission delay: ATD represents the average transmission delay time value, SDTD represents the standard deviation value of the transmission delay time, and CVTD represents the coefficient of variation of the transmission delay; Calculate the deviation value for each packet size: Si represents the size of the ith data packet, S represents the average size of all received data packets, SDPSi represents the deviation value of the ith data packet, and the standard deviation value of the data packet size is calculated using the standard deviation calculation formula, and then the coefficient of variation of the data packet size is calculated: SDP represents the standard deviation value of the packet size, and CVPS represents the coefficient of variation of the packet size; Based on the packet loss rate, the coefficient of variation of transmission delay CVTD, and the coefficient of variation of packet size CVPS, the transmission anomaly index is obtained by using the Euclidean distance calculation method; Based on the generated data quality coefficient, the management window is divided into a basic management window and a fine management window, which means: The generated data quality coefficient is compared with the preset data adoption reference coefficient. If the generated data quality coefficient is greater than or equal to the preset data adoption reference coefficient, the management window is divided into a fine management window. If the generated data quality coefficient is less than the preset data adoption reference coefficient, the management window is divided into a basic management window. For the basic management window that uses the first scheduling mode for energy scheduling management, the strategy for determining the optimization processing refers to: obtaining the data anomaly index, transmission anomaly index, and data quality coefficient of the basic management window, and then applying fuzzy logic for reasoning to determine the type of optimization strategy for improving data quality; The logic of applying fuzzy logic for reasoning is: Define the input variables as data anomaly index, transmission anomaly index, and data quality coefficient, define the output variable as the type of optimization strategy, fuzzify the input variables, and convert the values of the input variables into fuzzy sets, fuzzify the output variables, and convert the output variables into fuzzy sets, formulate fuzzy rules, describe the optimization requirements under different data type combinations, and infer the fuzzified input variables through fuzzy rules to determine the type of optimization strategy.
2. A boiler waste heat recovery energy scheduling and management system, based on the boiler waste heat recovery energy scheduling and management method according to claim 1, It is characterized in that It includes scheduling method library, preliminary judgment module, abnormal analysis module, delivery module, optimization strategy judgment module and adaptive optimization module; The preliminary judgment module is used to collect information from the data transmission channel for boiler waste heat recovery monitoring, and then conduct preliminary analysis to determine whether there is a hidden danger of insufficient data support in the management window; The abnormal analysis module is used to collect the recovery information in the boiler waste heat recovery process when there is a hidden danger of insufficient data support, and then perform abnormal analysis to generate a data abnormality index and a transmission abnormality index, and then transmit the data abnormality index and the transmission abnormality index to a pre-trained machine learning model to generate a data quality coefficient through the pre-trained machine learning model; The dispatch method library has preset dispatch method 1 based on rule-based dispatch management and dispatch method 2 based on intelligent algorithm; The delivery module divides the management window into a basic management window and a fine management window based on the generated data quality coefficient, and then delivers the basic management window to the dispatch mode 1 for energy dispatch management, and delivers the fine management window to the dispatch mode 2 for energy dispatch management; The optimization strategy judgment module is used to judge the optimization processing strategy for the basic management window that adopts the scheduling mode 1 for energy scheduling management; The adaptive optimization module adaptively optimizes and improves data quality based on the optimization processing strategy determined by the optimization strategy determination module.