A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery

By integrating membrane distillation, renewable energy and waste heat recovery, the sewage treatment system solves the problems of high heat energy consumption and easy clogging of microporous membranes in traditional technology, achieves efficient sewage treatment and clean reuse, and reduces heat loss and water waste. .

CN118561376BActive Publication Date: 2024-10-25INST OF WATER RESOURCES FOR PASTERAL AREA MINIST OF WATER RESOURCES P R C
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411035455.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-10-25
Estimated Expiration
2044-07-31

AI Technical Summary

Technical Problem

Traditional membrane distillation technology has problems such as high heat energy consumption, low flux, high process heat loss, difficulty in equipment modification and easy clogging of microporous membranes when treating wastewater from energy industries such as coal chemical industry. It is difficult to meet the requirements of efficient sewage treatment and clean reuse. need.

Method used

A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery is designed. It adopts a modular structure and integrated distillation tower, combined with solar power supply and waste heat recovery, to keep the microporous membrane components clean through the cleaning stage, reducing heat loss and Water wastage.

Benefits of technology

It realizes multi-stage distillation function, reduces heat loss, improves processing efficiency, is clean and environmentally friendly, avoids microporous membrane clogging, and reduces water waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118561376B_ABST
    Figure CN118561376B_ABST
Patent Text Reader

Abstract

The present invention belongs to the field of sewage treatment, and provides a sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery, comprising a cooling water tank, a particle separator, a distilled water tank, a sewage tank, a top seat, an insulating shell, an intermediate seat, a base, a fixed seat, a microporous membrane assembly, a cooling plate and a supporting plate; the present invention adopts the structure of an integrated distillation tower, in which sewage, distilled water and cooling water flow, which can reduce heat loss during medium flow, and the present invention adopts renewable energy solar energy to power a heating device, which is cleaner and more environmentally friendly; the heat exchange medium of the present invention fully absorbs the waste heat of cooling water and sewage in the entire system, which can effectively reduce heat loss in the system; the present invention is designed with a cleaning stage, which can flush both sides of the microporous membrane assembly to keep the microporous membrane assembly clean and avoid clogging that affects membrane separation efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of sewage treatment, and in particular relates to a sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery. Background Art

[0002] Coal chemical and other energy industries generate a large amount of toxic and harmful wastewater every year, which needs to be treated urgently. However, traditional wastewater treatment processes often have many difficulties, such as low treatment efficiency, complex processes, and high operation and maintenance costs. Improper treatment may also bring multiple hidden dangers to the water environment, atmosphere, soil and human health. Moreover, for areas with water shortages, efficient treatment and clean reuse of wastewater from coal chemical and other energy industries are crucial to the sustainable development of the energy industry.

[0003] At present, membrane distillation technology is commonly used to treat wastewater from energy industries such as coal chemical industry. Membrane distillation is a membrane technology that uses hydrophobic microporous membranes to separate aqueous solutions containing non-volatile solutes. Due to the surface tension of water, liquid water cannot pass through the micropores of the membrane under normal pressure, but water vapor can. When there is a certain temperature difference on both sides of the membrane, due to the difference in vapor pressure, water vapor molecules pass through the micropores and condense on the other side, causing the solution to gradually concentrate. However, when heating sewage, the current membrane distillation treatment equipment consumes a lot of heat energy, has a small flux, and has a high process heat loss; different processes require the use of different membrane distillation processes, and the equipment is difficult to transform and difficult to adapt to the needs of multiple treatment processes; when treating wastewater containing particles, the microporous membrane is easily blocked, affecting the treatment efficiency. At present, the equipment often needs to be disassembled for manual cleaning, which is difficult to clean. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery to solve the problems in the prior art. The technical solution adopted by the present invention is:

[0005] A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery, comprising a cooling water tank, a particle separator, a distilled water tank, a sewage tank, a top seat, a heat-insulating shell, an intermediate seat, a base, a fixing seat, a microporous membrane assembly, a cooling plate and a bearing plate;

[0006] The heat-insulating shell is a hollow structure, and a plurality of the heat-insulating shells are stacked vertically, and the middle seat is detachably connected between two adjacent heat-insulating shells, the top of the uppermost heat-insulating shell is detachably connected to the top seat, and the bottom of the lowermost heat-insulating shell is detachably connected to the base, and the bottom of the base is fixedly connected to the fixed seat;

[0007] The bearing plate is inserted into the interior of the plurality of heat-insulating shells, the middle seat is provided with a through hole through which the bearing plate passes, and the microporous membrane assembly is fixedly arranged on the bearing plate;

[0008] The cooling plate is fixedly arranged inside the thermal insulation shell, and the cooling plate and the bearing plate are both arranged vertically and spaced apart, and the cooling plate and the microporous membrane assembly divide the interior of the thermal insulation shell into three chambers arranged horizontally, a distilled water chamber is between the cooling plate and the microporous membrane assembly, a cooling water chamber is between the cooling plate and the wall of the thermal insulation shell, and a sewage chamber is between the microporous membrane assembly and the wall of the thermal insulation shell; the sewage chambers, cooling water chambers and distilled water chambers in the plurality of thermal insulation shells are connected end to end in sequence;

[0009] Cooling water is arranged in the cooling water tank and is circulated and connected with the cooling water cavity; the sewage tank, the sewage cavity and the particle separator are connected in sequence, and a heating device is arranged in the sewage tank; the heating device is powered by solar energy, and the distilled water cavity is connected with the distilled water tank.

[0010] Furthermore, the top of the bearing plate is connected to a lifting device through a rope, the lifting device is installed on the top seat, the microporous membrane assembly is not arranged in the uppermost heat-insulating shell, and the top of the bearing plate and the top seat form a reserved space for lifting the bearing plate;

[0011] The cooling plate is provided with a nozzle connected to the cooling water cavity, the nozzle faces the microporous membrane assembly, and the cooling plates in the two upper and lower adjacent heat preservation shells are alternately distributed on both sides of the bearing plate;

[0012] During the cleaning stage, the lifting device is used to move the supporting plate up and down, so that the nozzle sprays the liquid medium to both sides of the microporous membrane assembly.

[0013] Furthermore, a plurality of protrusions are fixedly connected to one side of the cooling plate facing the microporous membrane assembly, and the plurality of protrusions are vertically arranged side by side. The protrusions are in the structure of a "V"-shaped plate, and a "V"-shaped cavity is formed between the protrusions and the cooling plate. The "V"-shaped cavity is connected to the cooling water cavity via a guide hole. The end of the protrusion away from the cooling plate is rotatably connected to the cleaning roller via a bracket. The nozzle is installed at the end of the protrusion away from the cooling plate, and the nozzle is connected to the "V"-shaped cavity. The spraying direction of the nozzle is toward the cleaning roller, and is used to spray liquid medium to the side of the cleaning roller away from the microporous membrane assembly.

[0014] Furthermore, the cleaning roller and the microporous membrane assembly are spaced apart, one end of a return spring is fixedly connected to the side of the cooling plate away from the cleaning roller, the other end of the return spring is fixedly connected to the inner wall of the heat preservation shell, and a sealing plug is sleeved on the cooling plate;

[0015] During the cleaning stage, the cooling plate moves toward the microporous membrane assembly under the action of the water pressure in the cooling water chamber, so that the cleaning roller contacts the microporous membrane assembly.

[0016] Furthermore, the middle seat and the base are both provided with installation cavities, and the middle seat is provided with a sewage conducting pipe, a cooling water conducting pipe, and a distillation and cleaning water conducting pipe, wherein the two ends of the sewage conducting pipe are connected to two adjacent sewage cavities, the two ends of the cooling water conducting pipe are connected to two adjacent cooling water cavities, and the two ends of the distillation and cleaning water conducting pipe are connected to two adjacent distillation water cavities;

[0017] The base is provided with a sewage chamber outlet pipe, a distilled water chamber outlet pipe and a cooling water chamber outlet pipe, which are used to outlet the liquid medium in the sewage chamber, the distilled water chamber and the cooling water chamber respectively.

[0018] Furthermore, a reflux chamber is provided in the fixed seat, an overflow seat is fixedly provided in the reflux chamber, an overflow chamber is provided in the overflow seat, the liquid medium in the overflow chamber enters the reflux chamber through overflow, the reflux chamber is connected to the cooling water tank through a cooling water return pipe, and the cooling water tank is connected to the uppermost cooling water chamber through a cooling water output pipe;

[0019] One end of the sewage chamber outlet pipe is connected to the lowermost sewage chamber, and the other end is connected to the particle separator through a sewage discharge pipe;

[0020] One end of the distilled water chamber outlet pipe is connected to the bottom distilled water chamber, and the other end is connected to the overflow chamber. A second three-way valve is provided on the distilled water chamber outlet pipe, and the second three-way valve is connected to the distilled water tank through a distilled water discharge pipe.

[0021] One end of the cooling water chamber outlet pipe is connected to the lowermost cooling water chamber, and the other end is connected to the reflux chamber. A control valve is provided on the cooling water chamber outlet pipe;

[0022] During the membrane distillation stage, after the conversion of the second three-way valve, the distilled water chamber outlet pipe is connected to the distilled water chamber and the distilled water tank, so as to transport the distilled water to the distilled water tank;

[0023] During the cleaning stage, after the conversion of the second three-way valve, the distilled water chamber outlet pipe is connected to the overflow chamber to transport the clean wastewater to the overflow chamber.

[0024] Furthermore, a heat exchange tube is provided in the reflux chamber, a heat exchange device is provided in the sewage tank, one end of the heat exchange tube is connected to a waste heat recovery device through a waste heat input pipe, the waste heat recovery device is connected to the heat exchange device through a waste heat output pipe, the waste heat recovery device is installed on the sewage discharge pipe, and the heat exchange device is connected to the other end of the heat exchange tube through a low-temperature water pipe, and a pump body and a cooling device are provided on the low-temperature water pipe.

[0025] Furthermore, the overflow chamber is connected to the particle separator via a sedimentation water output pipe, and the sedimentation water output pipe is connected in parallel with the sewage discharge pipe and is connected to the particle separator via a first three-way valve.

[0026] Furthermore, a sealing frame is provided in the overflow seat, and the sealing frame is a hollow structure. An extension part is fixedly provided at the bottom of the supporting plate, and the extension part can be slidably inserted in the sealing frame. A tension spring is provided in the sealing frame, and a blind hole is provided at the bottom of the extension part. The tension spring is located in the blind hole, and the top of the tension spring is fixedly connected to the top of the blind hole, and the bottom of the tension spring is fixedly connected to the bottom of the overflow seat.

[0027] Further, the heat exchange device includes a cover plate, a plug-in tube, a heat exchange box and a heat conducting pipe. The heat exchange box is fixedly connected to the sewage tank, a heat exchange chamber is arranged in the heat exchange box, one end of the heat exchange chamber is connected to the low-temperature water pipe, and the other end of the heat exchange chamber is connected to the waste heat output pipe. Both ends of the heat conducting pipe are fixedly connected to the top surface and the bottom surface of the heat exchange box, the plug-in tube is plugged into the heat conducting pipe, the plug-in tube is fixedly connected to the cover plate, and the cover plate is slidably arranged in the sewage tank;

[0028] The heat exchange box divides the interior of the sewage tank into an upper chamber and a lower chamber, and the plug-in pipe connects the upper chamber and the lower chamber.

[0029] The present invention has the following beneficial effects:

[0030] (1) The present invention adopts a modular design. Through the modular structure formed by multiple insulation shells and intermediate seats, the system can be modified in time to form a three-pass or multi-pass membrane distillation process, thereby forming a multi-stage distillation function;

[0031] (2) The present invention adopts an integrated distillation tower structure, in which sewage, distilled water and cooling water flow, which can reduce the heat loss when the medium flows. The present invention uses renewable energy solar energy to power the heating device, which is cleaner and more environmentally friendly;

[0032] (3) The heat exchange medium of the present invention fully absorbs the waste heat of cooling water and sewage in the entire system, which can effectively reduce the heat loss in the system;

[0033] (4) The present invention is designed with a cleaning stage, which can flush both sides of the microporous membrane assembly to keep the microporous membrane assembly clean and avoid clogging that affects the membrane separation efficiency;

[0034] (5) The cooling water of the present invention not only serves as a condensation function in membrane distillation, but can also be used as cleaning water in the cleaning stage. After the cleaning is completed, the clear liquid can be precipitated and recovered, thereby reducing the waste of water resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0036] Figure 2 It is a schematic diagram when the load-bearing plate is lifted to the highest height;

[0037] Figure 3 yes Figure 1 The enlarged schematic diagram at A in the middle;

[0038] Figure 4 It is a schematic diagram of the position relationship of the cooling plates during the cleaning stage;

[0039] Figure 5 yes Figure 1 The enlarged schematic diagram of point B in the middle;

[0040] Figure 6 It is a schematic diagram of a sewage tank;

[0041] Figure 7 This is a top view of the middle seat;

[0042] In the figure: 1 cooling water tank, 2 particle separator, 3 recovery water tank, 4 distilled water tank, 5 sewage tank, 6 top seat, 7 insulation shell, 8 middle seat, 82 base, 9 fixed seat, 10 lifting device, 11 microporous membrane assembly, 12 waste heat recovery device, 13 cooling device, 14 rope body, 15 cooling plate, 16 bearing plate, 17 temporary storage insulation warehouse, 18 heat exchange device, 19 heating device, 101 cooling water output pipe, 102 sedimentation water output pipe, 103 sewage discharge pipe, 104 sewage feed pipe, 105 waste heat input pipe, 106 distilled water discharge pipe, 107 waste heat output pipe, 108 heat exchange pipe, 109 cooling water return pipe, 110 low temperature water pipe, 111 first three-way valve, 161 hollow part , 162 solid part, 163 extension part, 164 tension spring, 801 sewage conducting pipe, 802 cooling water conducting pipe, 803 distillation and cleaning water conducting pipe, 821 sewage chamber outlet pipe, 822 distillation water chamber outlet pipe, 823 cooling water chamber outlet pipe, 824 second three-way valve, 825 control valve, 151 guide hole, 152 protrusion, 153 nozzle, 154 cleaning roller, 701 sewage chamber, 702 cooling water chamber, 703 distillation water chamber, 901 sealing frame, 902 overflow seat, 903 overflow chamber, 904 reflux chamber, 181 cover plate, 182 plug-in tube, 183 heat exchange box, 184 heat conduction pipe, 501 middle plate, 502 middle tube, 503 feed hopper. DETAILED DESCRIPTION

[0043] The following will be combined with the embodiments of the present invention Figure 1-Figure 7 , the technical solutions in the embodiments of the present invention are described clearly and completely. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Unless otherwise specified, the technical means used in the embodiments are conventional means well known to those skilled in the art.

[0044] like Figure 1 , a sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery, comprising a cooling water tank 1, a particle separator 2, a distilled water tank 4, a sewage tank 5, a top seat 6, a heat-insulating shell 7, an intermediate seat 8, a base 82, a fixing seat 9, a microporous membrane assembly 11, a cooling plate 15 and a bearing plate 16;

[0045] The heat-insulating shell 7 is a hollow structure, and a plurality of the heat-insulating shells 7 are stacked vertically. Two adjacent heat-insulating shells 7 are detachably connected to the middle seat 8, the top of the uppermost heat-insulating shell 7 is detachably connected to the top seat 6, and the bottom of the lowermost heat-insulating shell 7 is detachably connected to the base 82, and the bottom of the base 82 is fixedly connected to the fixed seat 9;

[0046] The bearing plate 16 is inserted into the plurality of heat-insulating shells 7, the middle seat 8 is provided with a through hole through which the bearing plate 16 passes, and the microporous membrane assembly 11 is fixedly arranged on the bearing plate 16;

[0047] The cooling plate 15 is fixedly arranged inside the thermal insulation shell 7. The cooling plate 15 and the supporting plate 16 are both arranged vertically and spaced apart. The cooling plate 15 and the microporous membrane assembly 11 divide the interior of the thermal insulation shell 7 into three chambers arranged horizontally. A distilled water chamber 703 is between the cooling plate 15 and the microporous membrane assembly 11, a cooling water chamber 702 is between the cooling plate 15 and the wall of the thermal insulation shell 7, and a sewage chamber 701 is between the microporous membrane assembly 11 and the wall of the thermal insulation shell 7; the sewage chambers 701, cooling water chambers 702 and distilled water chambers 703 in the plurality of thermal insulation shells 7 are connected end to end in sequence;

[0048] Cooling water is arranged in the cooling water tank 1 and is circulated and connected with the cooling water chamber 702; the sewage tank 5, the sewage chamber 701 and the particle separator 2 are connected in sequence, and a heating device 19 is arranged in the sewage tank 5; the heating device 19 is powered by solar energy, and the distilled water chamber 703 is connected with the distilled water tank 4.

[0049] Specifically, multiple insulation shells 7 are of the same size and together with the middle seat 8 form a modular structure. During specific implementation, the number of insulation shells 7 and middle seats 8 can be increased or decreased according to demand. For example, in this embodiment, 4 insulation shells 7, 3 middle seats 8, and 3 microporous membrane assemblies 11 are provided, so the sewage is sequentially distilled through three microporous membrane assemblies 11. In the vertical direction, from top to bottom, there are the modular structure composed of the top seat 6, insulation shell 7 and middle seat 8, the base 82 and the fixed seat 9. The various components are detachably connected by bolts. The top seat 6, insulation shell 7, middle seat 8, base 82 and fixed seat 9 together constitute the structure of an integrated distillation tower, in which sewage, distilled water and cooling water flow, which can reduce heat loss during medium flow.

[0050] The cooling water tank 1 stores cooling water, which can be tap water. The cooling water tank 1 and the multiple cooling water chambers 702 form a water cooling cycle to provide the temperature environment required for the condensation of steam in the cooling water chambers 702. The sewage tank 5 stores raw sewage. The heating device 19 heats the raw sewage to a predetermined temperature (water vapor can be evaporated). Then the raw sewage enters the multiple sewage chambers 701 in sequence. The raw sewage evaporates in the sewage chamber 701 to form water vapor. The water vapor enters the distilled water chamber 703 through the microporous membrane assembly 11. Then the water vapor repeatedly contacts the cooling plate 15 to form a condensation effect to produce condensed distilled water. The distilled water is output to the distilled water tank 4 through the multiple distilled water chambers 703. The distilled water tank 4 stores clean distilled water, which is the sewage treatment product of the present invention and can be used in other process links of the plant. After the raw sewage is distilled, it is full of particulate matter. It enters the particle separator 2 from the bottom sewage chamber 701 for particle separation to separate the particles (such as salt particles, etc.) in the raw sewage. The output end of the particle separator 2 is connected to the recovery water tank 3, and the sewage discharge end of the particle separator 2 can be connected to facilities such as a sedimentation tank and a sewage discharge tank. The sewage after the particles are separated by the particle separator 2 enters the recovery water tank 3, and the recovery water tank 3 stores the wastewater after the particles are removed. The wastewater can be used for cleaning, flushing, washing, etc. in the plant area.

[0051] It should be noted that the heating device 19, the particle separator 2, the microporous membrane assembly 11, and the solar power supply are all prior art. The particle separator 2 can be a cyclone separator, and the microporous membrane assembly 11 can be an assembly composed of multiple microporous membranes made of various materials such as PTFE, PP, and PVDF. The solar power supply can be a solar photovoltaic panel, which concentrates solar energy into a battery, and the battery is connected to the heating device 19 to provide electrical energy for the heating device 19. The heating device 19 can be an electric heater.

[0052] Compared with the prior art, the present invention adopts a modular design. Through the modular structure formed by multiple heat-insulating shells 7 and intermediate seats 8, the system can be modified in time to form a three-pass or multi-pass membrane distillation process, thereby forming a multi-stage distillation function. The present invention adopts an integrated distillation tower structure, in which sewage, distilled water and cooling water flow, which can reduce heat loss during medium flow. The present invention uses renewable energy solar energy to power the heating device 19, which is cleaner and more environmentally friendly.

[0053] like Figure 1-Figure 4 The present invention also designs a cleaning stage to clean particles and impurities attached to the microporous membrane assembly 11 to avoid clogging thereof. Specifically:

[0054] The top of the carrying plate 16 is connected to the lifting device 10 through the rope body 14, and the lifting device 10 is installed on the top seat 6. The microporous membrane assembly 11 is not arranged in the uppermost heat-insulating shell 7, and the top of the carrying plate 16 and the top seat 6 form a reserved space for lifting the carrying plate 16;

[0055] The cooling plate 15 is provided with a nozzle 153 connected to the cooling water chamber 702, and the nozzle 153 faces the microporous membrane assembly 11. The cooling plates 15 in the upper and lower adjacent heat preservation shells 7 are alternately distributed on both sides of the carrier plate 16;

[0056] During the cleaning stage, the lifting device 10 is used to move the supporting plate 16 up and down, so that the nozzle 153 sprays the liquid medium to both sides of the microporous membrane assembly 11 .

[0057] The lifting device 10 is a prior art, such as a hoist, a winch, etc. The rope body 14 can be a steel wire rope. Since the number of microporous membrane components 11 is one less, only the cooling plate 15 and its related components are arranged in the uppermost heat-insulating shell 7. The advantage of such a design is that the two sides of the microporous membrane components 11 can alternately pass through the nozzle 153, so as to be washed by the nozzle 153.

[0058] A temporary insulation bin 17 is arranged in the uppermost insulation shell 7. The temporary insulation bin 17 is arranged on the side of the supporting plate 16 away from the cooling plate 15. The temporary insulation bin 17 is connected to the sewage tank 5 through the sewage feed pipe 104. The sewage tank 5 outputs the sewage to the temporary insulation bin 17. The temporary insulation bin 17 outputs the sewage downward to the sewage cavity 701 in the insulation shell 7 below.

[0059] The nozzles 153 on the two adjacent cooling plates 15 are symmetrically arranged, so that the sewage chambers 701, cooling water chambers 702 and distilled water chambers 703 in the two adjacent insulation shells 7 are arranged in opposite directions; for example, in the second-to-last insulation shell 7 at the top, the sewage chamber 701, cooling water chamber 702 and distilled water chamber 703 are arranged in sequence from left to right in the figure. In another insulation shell 7 below the insulation shell 7, the distilled water chamber 703, cooling water chamber 702 and sewage chamber 701 are arranged in sequence from left to right in the figure.

[0060] Furthermore, the cooling plate 15 is fixedly connected to a side facing the microporous membrane assembly 11 with a plurality of protrusions 152, and the plurality of protrusions 152 are vertically arranged side by side. The protrusions 152 are in the structure of a "V"-shaped plate, and a "V"-shaped cavity is formed between the protrusions 152 and the cooling plate 15, and the "V"-shaped cavity is connected to the cooling water cavity 702 through the guide hole 151, and the end of the protrusion 152 away from the cooling plate 15 is rotatably connected to the cleaning roller 154 through a bracket, and the nozzle 153 is installed on the end of the protrusion 152 away from the cooling plate 15, and the nozzle 153 is connected to the "V"-shaped cavity, and the spraying direction of the nozzle 153 is toward the cleaning roller 154, and is used to spray the liquid medium to the side of the cleaning roller 154 away from the microporous membrane assembly 11.

[0061] like Figure 3 , in a direction perpendicular to the plane of the drawing, the protrusion 152 covers the microporous membrane assembly 11, and a plurality of nozzles 153 are provided. The nozzle 153 is opened and closed by a solenoid valve. In the membrane distillation stage, the nozzle 153 is closed, and the cooling water in the cooling water chamber 702 enters the "V"-shaped cavity. Therefore, the "V"-shaped wall surface of the protrusion 152 can increase the contact area with the water vapor in the distilled water chamber 703, which is beneficial to improve the condensation effect of the water vapor. In the cleaning stage, the cooling water sprayed by the nozzle 153 can clean the cleaning roller 154.

[0062] Furthermore, the cleaning roller 154 and the microporous membrane assembly 11 are spaced apart, one end of a return spring is fixedly connected to the side of the cooling plate 15 away from the cleaning roller 154, the other end of the return spring is fixedly connected to the inner wall of the heat preservation shell 7, and a sealing plug is sleeved on the cooling plate 15;

[0063] During the cleaning stage, the cooling plate 15 moves toward the microporous membrane assembly 11 under the action of the water pressure in the cooling water chamber 702 , so that the cleaning roller 154 contacts the microporous membrane assembly 11 .

[0064] Cleaning stage Figure 1 , Figure 3 In the state, the clean water used is the cooling water in the cooling water tank 1. During the membrane distillation stage, the cooling water in the multiple cooling water chambers 702 circulates, so the water pressure in the cooling water chambers 702 is low. At this time, under the action of the return spring, the cooling plate 15 is reset to form Figure 1 , Figure 3 status in .

[0065] Furthermore, the middle seat 8 and the base 82 are both provided with installation cavities, and the middle seat 8 is provided with a sewage conducting pipe 801, a cooling water conducting pipe 802 and a distilled and clean water conducting pipe 803. The two ends of the sewage conducting pipe 801 are connected to the two adjacent sewage cavities 701 above and below, the two ends of the cooling water conducting pipe 802 are connected to the two adjacent cooling water cavities 702 above and below, and the two ends of the distilled and clean water conducting pipe 803 are connected to the two adjacent distilled water cavities 703 above and below;

[0066] The base 82 is provided with a sewage chamber outlet pipe 821 , a distilled water chamber outlet pipe 822 and a cooling water chamber outlet pipe 823 , which are used to respectively outlet the liquid medium in the sewage chamber 701 , the distilled water chamber 703 and the cooling water chamber 702 .

[0067] The liquid medium in the distilled water chamber 703, the cooling water chamber 702 and the sewage chamber 701 all flows downward and flows into the corresponding chambers through the sewage chamber outlet pipe 821, the distilled water chamber outlet pipe 822 and the cooling water chamber outlet pipe 823. The installation chamber is preferably a vacuum chamber to improve the thermal insulation performance.

[0068] like Figure 7 The sewage chamber outlet pipe 821 , the distilled water chamber outlet pipe 822 and the cooling water chamber outlet pipe 823 are distributed on both sides of the bearing plate 16 and avoid the bearing plate 16 to avoid interfering with the movement of the bearing plate 16 .

[0069] In addition, the middle seat 8 is a square hollow structure, wherein the hollow part is a square through hole, and the size is adapted to the carrying plate 16. The carrying plate 16 is provided with a hollow part 161 and a solid part 162, wherein the solid part 162 is the integral plate part of the carrying plate 16, and the hollow part 161 is the part for fixing and installing the microporous membrane assembly 11. Figure 1 During the membrane distillation stage, the solid portion 162 blocks the through hole of the intermediate seat 8 to form a seal. A sealing ring may be provided in the through hole.

[0070] Further, a reflux chamber 904 is provided in the fixed seat 9, an overflow seat 902 is fixedly provided in the reflux chamber 904, an overflow chamber 903 is provided in the overflow seat 902, the liquid medium in the overflow chamber 903 enters the reflux chamber 904 through the overflow effect, the reflux chamber 904 is connected to the cooling water tank 1 through the cooling water return pipe 109, and the cooling water tank 1 is connected to the uppermost cooling water chamber 702 through the cooling water output pipe 101;

[0071] One end of the sewage chamber outlet pipe 821 is connected to the sewage chamber 701 at the bottom, and the other end thereof is connected to the particle separator 2 through the sewage discharge pipe 103;

[0072] One end of the distilled water chamber outlet pipe 822 is connected to the distilled water chamber 703 at the bottom, and the other end thereof is connected to the overflow chamber 903. A second three-way valve 824 is provided on the distilled water chamber outlet pipe 822. The second three-way valve 824 is connected to the distilled water tank 4 through the distilled water discharge pipe 106.

[0073] One end of the cooling water chamber outlet pipe 823 is connected to the cooling water chamber 702 at the bottom, and the other end thereof is connected to the reflux chamber 904. A control valve 825 is provided on the cooling water chamber outlet pipe 823.

[0074] During the membrane distillation stage, after the conversion of the second three-way valve 824, the distilled water chamber outlet pipe 822 is connected to the distilled water chamber 703 and the distilled water tank 4, so as to transport the distilled water to the distilled water tank 4;

[0075] During the cleaning stage, after the conversion of the second three-way valve 824 , the distilled water chamber outlet pipe 822 is connected to the overflow chamber 903 to transport the clean wastewater to the overflow chamber 903 .

[0076] The distilled water chamber outlet pipe 822 includes an upper section and a lower section, and a second three-way valve 824 is disposed between the upper section and the lower section. During the cleaning stage, the second three-way valve 824 connects the upper section and the lower section of the distilled water chamber outlet pipe 822. During the membrane distillation stage, the second three-way valve 824 connects the upper section of the distilled water chamber outlet pipe 822 and the distilled water discharge pipe 106.

[0077] Furthermore, a heat exchange tube 108 is provided in the reflux chamber 904, and a heat exchange device 18 is provided in the sewage tank 5. One end of the heat exchange tube 108 is connected to the waste heat recovery device 12 through the waste heat input pipe 105, and the waste heat recovery device 12 is connected to the heat exchange device 18 through the waste heat output pipe 107. The waste heat recovery device 12 is installed on the sewage discharge pipe 103, and the heat exchange device 18 is connected to the other end of the heat exchange tube 108 through a low-temperature water pipe 110. A pump body and a cooling device 13 are provided on the low-temperature water pipe 110.

[0078] The heat exchange tube 108 is preferably a spiral tube, which is arranged around the overflow seat 902. The reflux chamber 904 is an annular chamber structure, surrounding the overflow seat 902. The waste heat recovery device 12 and the cooling device 13 are prior art, the waste heat recovery device 12 can be a pipeline waste heat recovery device, and the cooling device 13 can be a fan, a radiator and other components. A heat exchange medium is arranged in the heat exchange tube 108, such as a liquid or gas medium such as a refrigerant and tap water.

[0079] Furthermore, the overflow chamber 903 is connected to the particle separator 2 via a sedimentation water output pipe 102 , and the sedimentation water output pipe 102 is connected in parallel with the sewage discharge pipe 103 and is connected to the particle separator 2 via a first three-way valve 111 .

[0080] Furthermore, a sealing frame 901 is provided in the overflow seat 902, and the sealing frame 901 is a hollow structure. An extension part 163 is fixedly provided at the bottom of the supporting plate 16, and the extension part 163 can be slidably inserted in the sealing frame 901. A tension spring 164 is provided in the sealing frame 901, and a blind hole is provided at the bottom of the extension part 163. The tension spring 164 is located in the blind hole, and the top of the tension spring 164 is fixedly connected to the top of the blind hole, and the bottom of the tension spring 164 is fixedly connected to the bottom of the overflow seat 902.

[0081] The sealing frame 901 may be a hollow structure or a closed structure at the bottom. Its function is to provide a travel range for the support plate 16 to move up and down, so that when the support plate 16 is at the highest position, the extension part 163 is still in the sealing frame 901 or the base 82. Figure 2 In addition, the sealing frame 901 and the extension portion 163 together form a sealing structure to prevent the medium in the overflow seat 902 from entering the sealing frame 901. The tension spring 164 provides a reset function for the support plate 16, which pulls the support plate 16 downward to return it to its original position. Figure 1 The initial state of .

[0082] like Figure 5 The heat exchange device 18 includes a cover plate 181, a plug-in tube 182, a heat exchange box 183 and a heat conduction pipe 184. The heat exchange box 183 is fixedly connected to the sewage tank 5. A heat exchange chamber is arranged in the heat exchange box 183. One end of the heat exchange chamber is connected to the low-temperature water pipe 110, and the other end of the heat exchange chamber is connected to the waste heat output pipe 107. Both ends of the heat conduction pipe 184 are fixedly connected to the top surface and the bottom surface of the heat exchange box 183. The plug-in tube 182 is plugged into the heat conduction pipe 184. The plug-in tube 182 is fixedly connected to the cover plate 181, and the cover plate 181 is slidably arranged in the sewage tank 5; the heat exchange box 183 divides the interior of the sewage tank 5 into an upper chamber and a lower chamber, and the plug-in tube 182 connects the upper chamber and the lower chamber.

[0083] The heat exchange medium in the heat exchange tube 108 circulates in the heat exchange box 183 , and the heat exchange medium fully wraps the heat conducting tube 184 , and the heat conducting tube 184 transfers the heat to the raw sewage in the sewage tank 5 through the plug tube 182 .

[0084] In addition, multiple plug-in tubes 182 and heat-conducting tubes 184 are provided, and the plug-in tubes 182 can also achieve filtering. The raw sewage enters the upper chamber through the feed hopper 503 at the top of the sewage tank 5, and the raw sewage is filtered by the plug-in tubes 182 and enters the bottom of the heat exchange box 183. In this process, the raw sewage in the upper chamber exchanges heat with the heat exchange medium, and the heat exchange medium increases the initial temperature of the raw sewage.

[0085] An intermediate plate 501 and an intermediate pipe 502 may also be provided in the sewage tank 5. The intermediate plate 501 is located below the heat exchange box 183. The intermediate pipe 502 is fixedly provided on the intermediate plate 501. The intermediate pipe 502 connects the upper and lower spaces. A control valve is provided on the intermediate pipe 502. The heating device 19 is provided below the intermediate plate 501. After the raw sewage is preliminarily heated by the heat exchange medium and reaches a preset temperature value, it enters the space below the intermediate plate 501 through the intermediate pipe 502. Then, the raw sewage is heated again by the heating device 19 to the temperature required for membrane distillation. The advantage of such a design is that the raw sewage can be preliminarily heated, the power consumption of the heating device 19 can be reduced, and the heat of the heating device 19 can be prevented from being transferred to the heat exchange medium, thereby preventing the initial cooling effect of the heat exchange medium from being affected.

[0086] When the present invention is implemented, the raw sewage is put into the sewage tank 5. The cooling water is preset in the cooling water tank 1. The heat exchange medium is preset in the heat exchange tube 108. The present invention as a whole includes a membrane distillation stage and a cleaning stage. The two are different according to the different working conditions of the whole system and the different flow directions of the medium. The specific working process is as follows:

[0087] Membrane distillation stage: Figure 1 , Figure 3 , Figure 5 When sewage is treated normally, it is the initial state of the present invention, that is, the membrane distillation stage. In the membrane distillation stage, the nozzle 153 is closed, the control valve 825 is opened, and the lifting device 10 is closed.

[0088] The raw sewage in the sewage tank 5 is first heated to the required temperature for distillation by the heating device 19, and then transported to the temporary storage and insulation warehouse 17 through the waste heat output pipe 107 and the pump body on the waste heat output pipe 107. Then the sewage in the temporary storage and insulation warehouse 17 enters the sewage cavity 701 in the lower insulation shell 7 through the sewage conducting pipe 801, and is transported downward through multiple sewage cavities 701 and sewage conducting pipes 801 alternately, and enters the sewage cavity outlet pipe 821 in the base 82. The sewage cavity outlet pipe 821 transports the distilled sewage to the sewage discharge pipe 103. The first three-way valve 111 connects the particle separator 2 and the sewage discharge pipe 103. The pump body on the sewage discharge pipe 103 transports the sewage to the particle separator 2. After particle separation, it finally enters the recovery water tank 3 for recovery, thereby completing the sewage treatment.

[0089] During the flow of sewage, sewage evaporates in the sewage chamber 701, forms water vapor and passes through the microporous membrane assembly 11 into the distilled water chamber 703, and distilled water is formed in the distilled water chamber 703. The distilled water is alternately transported downward through the plurality of distilled water chambers 703. At this time, the second three-way valve 824 connects the upper section of the distilled water chamber outlet pipe 822 and the distilled water discharge pipe 106, and the distilled water enters the distilled water discharge pipe 106 through the upper section of the distilled water chamber outlet pipe 822, and is finally transported to the distilled water tank 4 through the pump body on the distilled water discharge pipe 106.

[0090] The cooling water is output from the cooling water tank 1 to the cooling water output pipe 101, and is transported to the cooling water chamber 702 in the topmost insulation shell 7 through the pump body on the cooling water output pipe 101. Then, it is transported downward alternately through multiple cooling water chambers 702 in sequence, and enters the cooling water chamber outlet pipe 823 in the base 82, and enters the reflux chamber 904 through the cooling water chamber outlet pipe 823. The cooling water in the reflux chamber 904 returns to the cooling water tank 1 through the cooling water return pipe 109, forming a circulating flow of cooling water.

[0091] During the membrane distillation stage, the heat exchange medium needs to circulate to absorb residual heat (waste heat): the heat exchange medium is transported from one end of the heat exchange tube 108 to the residual heat input tube 105, and is transported to the residual heat recovery device 12 through the pump body on the residual heat input tube 105. The residual heat recovery device 12 transports the heat exchange medium to the heat exchange device 18 through the residual heat output tube 107, and then is transported from the heat exchange device 18 to the low-temperature water pipe 110, cooled by the pump body on the low-temperature water pipe 110, and returns to the other end of the heat exchange tube 108 through the pump body on the low-temperature water pipe 110.

[0092] During the cooling water flow, when passing through the cooling water chamber 702, the cooling plate 15 and the protrusion 152 absorb the heat of the water vapor in the distilled water chamber 703, so the cooling water in the return chamber 904 just conveyed is high-temperature cooling water. The high-temperature cooling water is cooled to low-temperature cooling water through the heat exchange tube 108 and then returns to the cooling water tank 1, and then re-enters the cooling water chamber 702 to condense the water vapor.

[0093] Since the raw sewage is heated to high-temperature sewage by the heating device 19, the high-temperature sewage still contains heat after passing through multiple sewage chambers 701, and it is medium-temperature sewage. The medium-temperature sewage recovers waste heat through the waste heat recovery device 12, becomes low-temperature sewage, and then enters the particle separator 2. During the flow of the heat exchange medium, it first absorbs the heat of the high-temperature cooling water from the heat exchange tube 108, and then absorbs the heat of the medium-temperature sewage through the waste heat recovery device 12. At this time, the heat of the high-temperature cooling water and the medium-temperature sewage has been fully absorbed, and the temperature of the medium-temperature sewage is higher than that of the high-temperature cooling water. Therefore, when the heat exchange medium enters the heat exchange device 18, it can fully and preliminarily heat the raw sewage. The heat exchange medium of the present invention fully absorbs the waste heat of the cooling water and sewage in the entire system.

[0094] Cleaning stage: Figure 1 , Figure 2 , Figure 4 After a long period of sewage treatment, particles are easily attached to the microporous membrane assembly 11, causing blockage, which affects the efficiency of membrane distillation. Therefore, a cleaning stage can be performed. During the cleaning stage, the nozzle 153 is opened, the control valve 825 is closed, the pump body on the sewage feed pipe 104 is closed, the sewage does not enter the system, and the heating device 19 is closed. The pump body on the waste heat input pipe 105 is closed, and the heat exchange medium does not flow.

[0095] The cooling water tank 1 outputs cooling water as clean water to the cooling water output pipe 101, which is transported to the cooling water chamber 702 in the top insulation shell 7 through the pump body on the cooling water output pipe 101, and then transported downward through multiple cooling water chambers 702 alternately. Since the control valve 825 is closed, water pressure is formed in multiple cooling water chambers 702, so that the cooling plate 15 moves under the action of water pressure, and the cleaning roller 154 contacts the microporous membrane assembly 11. Then the lifting device 10 works, and the supporting plate 16 reciprocates up and down. The cleaning roller 154 fully cleans both sides of the microporous membrane assembly 11, adsorbs the particulate matter, and is flushed by the nozzle 153. The particulate waste water passes through multiple distilled water chambers 703 and enters the distilled water chamber outlet pipe 822. At this time, the second three-way valve 824 connects the upper and lower sections of the distilled water chamber outlet pipe 822, and the particulate waste water passes through the distilled water chamber outlet pipe 822 and enters the overflow chamber 903. The particulate wastewater in the overflow chamber 903 is precipitated, and the upper clear liquid enters the reflux chamber 904 under the overflow effect, completing the precipitation and recovery of the particulate wastewater.

[0096] During the cleaning stage, the first three-way valve 111 connects the particle separator 2 and the sedimentation water output pipe 102. The sedimentation water output pipe 102 transports the lower layer of particle wastewater in the overflow chamber 903 to the particle separator 2 for separation, and enters the recovery water tank 3 after treatment.

[0097] The cleaning phase is complete and returns to Figure 1 The initial state of .

[0098] Compared with the prior art, the heat exchange medium of the present invention fully absorbs the waste heat of the cooling water and sewage in the entire system, which can effectively reduce the heat loss in the system. The present invention is designed with a cleaning stage, which can flush both sides of the microporous membrane assembly 11 to keep the microporous membrane assembly 11 clean and avoid clogging that affects the membrane separation efficiency. The cooling water of the present invention not only serves as a condensation function in membrane distillation, but also can be used as cleaning water in the cleaning stage, and after the cleaning is completed, the clear liquid can be precipitated and recovered, which can reduce the waste of water resources.

[0099] In addition, each pump body of the present invention can be powered by solar energy.

[0100] The embodiments described above are only descriptions of the preferred modes of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various deformations, modifications, and substitutions made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery, It is characterized in that It comprises a cooling water tank (1), a particle separator (2), a distilled water tank (4), a sewage tank (5), a top seat (6), a heat-insulating shell (7), an intermediate seat (8), a base (82), a fixing seat (9), a microporous membrane assembly (11), a cooling plate (15) and a bearing plate (16); The heat-insulating shell (7) is a hollow structure, and a plurality of the heat-insulating shells (7) are stacked in a vertical direction. Two adjacent heat-insulating shells (7) are detachably connected to the middle seat (8), the top of the uppermost heat-insulating shell (7) is detachably connected to the top seat (6), and the bottom of the lowermost heat-insulating shell (7) is detachably connected to the base (82), and the bottom of the base (82) is fixedly connected to the fixed seat (9); The bearing plate (16) is inserted into the interior of the plurality of heat-insulating shells (7); the intermediate seat (8) is provided with a through hole through which the bearing plate (16) passes; and the microporous membrane assembly (11) is fixedly mounted on the bearing plate (16); The cooling plate (15) is fixedly arranged inside the thermal insulation shell (7); the cooling plate (15) and the supporting plate (16) are both arranged vertically and spaced apart; the cooling plate (15) and the microporous membrane assembly (11) divide the interior of the thermal insulation shell (7) into three chambers arranged horizontally; a distilled water chamber (703) is located between the cooling plate (15) and the microporous membrane assembly (11); a cooling water chamber (702) is located between the cooling plate (15) and the wall surface of the thermal insulation shell (7); and a sewage chamber (701) is located between the microporous membrane assembly (11) and the wall surface of the thermal insulation shell (7); the sewage chambers (701), cooling water chambers (702) and distilled water chambers (703) in the plurality of thermal insulation shells (7) are connected in sequence end to end; Cooling water is provided in the cooling water tank (1) and is circulated and connected to the cooling water chamber (702); the sewage tank (5), the sewage chamber (701) and the particle separator (2) are connected in sequence, and a heating device (19) is provided in the sewage tank (5); the heating device (19) is powered by solar energy, and the distilled water chamber (703) is connected to the distilled water tank (4); The top of the bearing plate (16) is connected to the lifting device (10) via a rope (14); the lifting device (10) is installed on the top seat (6); the microporous membrane assembly (11) is not arranged in the uppermost heat-insulating shell (7); the top of the bearing plate (16) and the top seat (6) form a reserved space for lifting the bearing plate (16); The cooling plate (15) is provided with a nozzle (153) connected to the cooling water chamber (702), the nozzle (153) is directed toward the microporous membrane assembly (11), and the cooling plates (15) in the two upper and lower adjacent heat-insulating shells (7) are alternately distributed on both sides of the supporting plate (16); During the cleaning phase, the lifting device (10) is used to move the supporting plate (16) up and down, so that the nozzle (153) sprays the liquid medium to both sides of the microporous membrane assembly (11).

2. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 1, It is characterized in that A plurality of protrusions (152) are fixedly connected to one side of the cooling plate (15) facing the microporous membrane assembly (11); the plurality of protrusions (152) are vertically arranged side by side; the protrusions (152) are in the structure of a "V"-shaped plate; a "V"-shaped cavity is formed between the protrusions and the cooling plate (15); the "V"-shaped cavity is connected to the cooling water cavity (702) via a guide hole (151); one end of the protrusion (152) away from the cooling plate (15) is rotatably connected to a cleaning roller (154) via a bracket; the nozzle (153) is installed at one end of the protrusion (152) away from the cooling plate (15); the nozzle (153) is connected to the "V"-shaped cavity; the spraying direction of the nozzle (153) is toward the cleaning roller (154), and is used to spray a liquid medium to the side of the cleaning roller (154) away from the microporous membrane assembly (11).

3. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 2, It is characterized in that The cleaning roller (154) and the microporous membrane assembly (11) are spaced apart from each other; the side of the cooling plate (15) away from the cleaning roller (154) is fixedly connected to one end of a return spring; the other end of the return spring is fixedly connected to the inner wall surface of the heat-insulating shell (7); and a sealing plug is sleeved on the cooling plate (15); During the cleaning phase, the cooling plate (15) moves toward the microporous membrane assembly (11) under the action of the water pressure in the cooling water chamber (702), so that the cleaning roller (154) contacts the microporous membrane assembly (11).

4. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 1, It is characterized in that The intermediate seat (8) and the base (82) are both provided with mounting cavities, and the interior of the intermediate seat (8) is provided with a sewage conducting pipe (801), a cooling water conducting pipe (802) and a distilled and clean water conducting pipe (803), wherein the sewage conducting pipe (801) has two ends connected to two upper and lower adjacent sewage cavities (701), the cooling water conducting pipe (802) has two ends connected to two upper and lower adjacent cooling water cavities (702), and the distilled and clean water conducting pipe (803) has two ends connected to two upper and lower adjacent distilled water cavities (703); The base (82) is provided with a sewage chamber outlet pipe (821), a distilled water chamber outlet pipe (822) and a cooling water chamber outlet pipe (823), which are used to respectively outlet the liquid medium in the sewage chamber (701), the distilled water chamber (703) and the cooling water chamber (702).

5. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 4, It is characterized in that A reflux chamber (904) is arranged in the fixed seat (9), an overflow seat (902) is fixedly arranged in the reflux chamber (904), an overflow chamber (903) is arranged in the overflow seat (902), liquid medium in the overflow chamber (903) enters the reflux chamber (904) through overflow, the reflux chamber (904) is connected to the cooling water tank (1) through a cooling water return pipe (109), and the cooling water tank (1) is connected to the uppermost cooling water chamber (702) through a cooling water output pipe (101); One end of the sewage chamber outlet pipe (821) is connected to the sewage chamber (701) at the bottom, and the other end is connected to the particle separator (2) via a sewage discharge pipe (103); One end of the distilled water chamber outlet pipe (822) is connected to the distilled water chamber (703) at the bottom, and the other end is connected to the overflow chamber (903). A second three-way valve (824) is provided on the distilled water chamber outlet pipe (822). The second three-way valve (824) is connected to the distilled water tank (4) via a distilled water discharge pipe (106); One end of the cooling water chamber outlet pipe (823) is connected to the cooling water chamber (702) at the bottom, and the other end is connected to the reflux chamber (904); a control valve (825) is provided on the cooling water chamber outlet pipe (823); During the membrane distillation stage, after the conversion of the second three-way valve (824), the distilled water chamber outlet pipe (822) is connected to the distilled water chamber (703) and the distilled water tank (4) so ​​as to transport the distilled water to the distilled water tank (4); During the cleaning stage, after the conversion of the second three-way valve (824), the distilled water chamber outlet pipe (822) is connected to the overflow chamber (903) to transport the clean wastewater to the overflow chamber (903).

6. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 5, It is characterized in that A heat exchange tube (108) is provided in the reflux chamber (904), a heat exchange device (18) is provided in the sewage tank (5), one end of the heat exchange tube (108) is connected to a waste heat recovery device (12) via a waste heat input tube (105), the waste heat recovery device (12) is connected to the heat exchange device (18) via a waste heat output tube (107), the waste heat recovery device (12) is installed on the sewage discharge pipe (103), the heat exchange device (18) is connected to the other end of the heat exchange tube (108) via a low-temperature water pipe (110), and a pump body and a cooling device (13) are provided on the low-temperature water pipe (110).

7. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 5, It is characterized in that The overflow chamber (903) is connected to the particle separator (2) via a sedimentation water output pipe (102); the sedimentation water output pipe (102) is connected in parallel with the sewage discharge pipe (103) and is connected to the particle separator (2) via a first three-way valve (111).

8. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 5, It is characterized in that A sealing frame (901) is arranged in the overflow seat (902), and the sealing frame (901) is a hollow structure. An extension part (163) is fixedly arranged at the bottom of the bearing plate (16), and the extension part (163) is slidably inserted in the sealing frame (901). A tension spring (164) is arranged in the sealing frame (901), and a blind hole is arranged at the bottom of the extension part (163). The tension spring (164) is located in the blind hole. The top of the tension spring (164) is fixedly connected to the top of the blind hole, and the bottom of the tension spring (164) is fixedly connected to the bottom of the overflow seat (902).

9. A sewage treatment system integrating membrane distillation, renewable energy and waste heat recovery according to claim 6, It is characterized in that The heat exchange device (18) comprises a cover plate (181), a plug-in tube (182), a heat exchange box (183) and a heat conduction pipe (184); the heat exchange box (183) is fixedly connected to the sewage tank (5); a heat exchange chamber is provided in the heat exchange box (183); one end of the heat exchange chamber is connected to the low-temperature water pipe (110); the other end of the heat exchange chamber is connected to the waste heat output pipe (107); two ends of the heat conduction pipe (184) are fixedly connected to the top surface and the bottom surface of the heat exchange box (183); the plug-in tube (182) is plugged into the heat conduction pipe (184); the plug-in tube (182) is fixedly connected to the cover plate (181); and the cover plate (181) is slidably provided in the sewage tank (5); The heat exchange box (183) divides the interior of the sewage tank (5) into an upper chamber and a lower chamber, and the plug-in pipe (182) connects the upper chamber and the lower chamber.