A method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall

By planning cross-layer doors and windows on the exterior walls of old buildings and setting reliable layers, the problem of load-bearing exterior wall interference is solved, and the stable construction and load bearing of new floor slabs inside the building is achieved, ensuring waterproofing effect and reducing the old building structure destruction.

CN118564105BActive Publication Date: 2024-11-12BEIJING FOURTH CONSTR & ENG +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411049995.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-12
Estimated Expiration
2044-08-01

AI Technical Summary

Technical Problem

The load-bearing exterior walls of old buildings have interfered with, which hinders the construction of new floor slabs inside the building and cannot effectively carry or connect large-sized components, especially when the old building structure is aging and waterproofing is unreliable.

Method used

By planning span-layer doors and windows on the exterior walls of the old building, setting up lintels and hidden columns, chiseling the inner wall of the exterior wall and attaching new reliable layers to the exterior wall construction, reserving interfaces and waterproof layers, and installing new floor slabs layer by layer , and implant steel bars on the exterior wall to form a new load-bearing structure.

Benefits of technology

Overcoming exterior wall interference, providing stable load-bearing and connection interfaces, reducing damage to old building structures, ensuring waterproofing, and achieving reliable installation and load-bearing of floor slabs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118564105B_ABST
    Figure CN118564105B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of construction measures for existing buildings, and discloses a method for rebuilding a new floor slab when interference exists in an original load-bearing outer wall. In the invention, all the door and window holes required for rebuilding an old building are gathered together to form vertical cross-layer door and window holes, thereby providing the construction holes required for the construction of each layer and minimizing the damage to the bearing capacity of the outer wall of the old building. A small amount of lintels and hidden columns can be used to overcome the influence caused by the opening of the holes, thereby overcoming the interference caused by the outer wall of the old building on the major internal reconstruction construction. A new reliable layer is constructed close to the outer wall of the old building as a new load-bearing wall, the new reliable layer can reliably bear the new floor slab, has an interface that can be reliably connected to the new floor slab, and also holds the old load-bearing wall to prevent it from collapsing, and at the same time, the waterproof structure of the old load-bearing wall does not need to be renovated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction measures for existing buildings, and in particular to a method for rebuilding a new floor slab when interference exists in an original load-bearing exterior wall. Background Art

[0002] The fate of most old buildings is to be demolished to make way for the construction of new buildings, but there are some old buildings with special significance that need to be changed in use while retaining their original appearance, which requires in-depth renovation of the buildings.

[0003] Considering that the old building itself has been seriously aged, its structural strength has seriously declined, and its appearance has become very dilapidated. These problems are difficult to solve without deep transformation of the building itself. Therefore, the transformation of old buildings often needs to be carried out in the form of dismantling into parts and reassembling. During the dismantling process, the building parts can be tested separately and the parts that do not meet the strength standards or are seriously damaged can be replaced. The internal reinforcement treatment can be carried out or the internal layout of the building can be changed to adapt to the changes in the use of the building.

[0004] However, if the old building mainly relies on load-bearing walls to bear the load, this construction method is not applicable. Whether it is a load-bearing wall made of reinforced concrete or a load-bearing wall of masonry structure, it cannot be dismantled into parts without causing damage. At this time, the load-bearing wall of the old building is no longer a resource that can be used for the reconstruction of the interior of the building, but a heavy burden. Because the reconstruction of the interior of the building will inevitably involve changes in layout and load. However, due to the relationship of time, this load-bearing wall itself has various defects. It is not only unreliable in force, but also unreliable in waterproofing. Therefore, not only can the new load not be carried by the old load-bearing wall, but the old load-bearing wall also needs to be repaired. Secondly, even if you do not want to rely on the old load-bearing wall, but also set up other load-bearing components in the building to bear the new load in the building, these old load-bearing walls will also block large-sized building components (beams, columns, steel, steel bars, plates, etc.) including load-bearing components from entering and exiting the building. If the old building itself is a storage building type, the problem will be even more serious (there are few and small holes in this kind of building).

[0005] Taking the Jinyu Xingfa Science Park project in the northern area of ​​Beijing Huairou Science City as an example, the project site is the Xingfa Cement Factory, which was built in the early 1990s and contributed a large amount of building materials to Beijing's urban construction. It is an important industrial heritage site. Therefore, the buildings there need to be transformed into research facilities of the nearby Beijing Yanqi Lake Institute of Applied Mathematics while retaining their appearance. The cement silo needs to be transformed into an expert residential building. The floor height of the cement silo is too large for a residence (close to 20 meters high, which will make it impossible for residents to decorate the ceiling) and is too wasteful, so several floors need to be added inside. The original material opening of the cement silo does not allow the large-sized building components that are probably needed inside the building to be transported in, nor does it allow the concrete pump pipe to enter the casting surface nearby. It cannot reliably carry the newly added floor slabs, and there is no interface that can be reliably connected to the newly added floor slabs. Summary of the invention

[0006] The invention provides a method for rebuilding a new floor slab when interference exists in an original load-bearing exterior wall.

[0007] The technical problem to be solved is: when the exterior walls of an old building are load-bearing walls, major renovations such as new floor slabs inside the building will be interfered with by the exterior walls. At the same time, the exterior walls of the old building can neither effectively bear the newly added components nor effectively connect with the newly added components.

[0008] In order to solve the above technical problems, the present invention adopts the following technical solutions: a method for rebuilding a new floor slab when there is interference with the original load-bearing external walls, which is used to overcome the interference of the external walls on the construction and add a new floor slab in the old building when the external walls of the old building are all load-bearing walls, comprising the following steps:

[0009] Step 1: Plan the doors and windows positions after the renovation of the old building, and concentrate the doors and windows in the cross-layer door and window openings, which meet the following conditions:

[0010] Condition 1.1: Set up on the unobstructed side of the old building;

[0011] Condition 1.2: The top is higher than the highest new floor slab, and the gap between the top and the highest new floor slab can accommodate at least one door and one window; the bottom is lower than the lowest new floor slab, and the gap between the bottom and the lowest new floor slab can accommodate at least one concrete pump pipe;

[0012] Step 2: A lintel is constructed by cutting a groove at the top of the cross-layer door and window opening, and the two ends of the lintel fall on the newly added hidden columns after the grooves are cut on the left and right sides of the cross-layer door and window opening;

[0013] Step 3: Cut out cross-layer door and window holes on the exterior wall of the old building;

[0014] Step 4: Chisel the inner wall of the exterior wall of the old building; then construct a new reliable layer close to the exterior wall. The new reliable layer is a load-bearing wall that meets the following conditions:

[0015] Condition 4.1: Fixedly connected to the exterior wall of the old building;

[0016] Condition 4.2: An interface is reserved for installing the new floor slab;

[0017] Condition 4.3: Can be stable without the existing exterior wall of the old building;

[0018] Condition 4.4: Waterproof;

[0019] Step 5: Install new floor slabs on the newly added reliable layer layer by layer from bottom to top.

[0020] Furthermore, if there are multiple old buildings arranged in a row, before the construction of step 4 begins, an externally projected construction corridor is installed on one side of the row of old buildings in advance, and among the cross-layer door and window openings planned in step 1, each old building has at least one cross-layer door and window opening leading to the externally projected construction corridor; during the decoration stage after the renovation of the old buildings is completed, the externally projected construction corridor is covered with glass curtain walls and ceilings to form a corridor for residents to use.

[0021] Furthermore, the steel bars of the newly added floor slab penetrate the newly added reliable layer and are implanted into the outer wall of the old building.

[0022] Further, step 4 includes the following sub-steps:

[0023] Step 4.1: Chisel the inner wall of the old building's exterior wall;

[0024] Step 4.2: implanting the reinforcement of the newly added floor slab on the inner wall surface of the outer wall of the old building, wherein the reinforcement passes through the newly added reliable layer and extends to the interior of the old building;

[0025] Step 4.3: Tie up the steel cage of the newly added reliable layer, and install embedded parts for connecting with the beams of the newly added floor below the position of the newly added floor, wherein the beams of the newly added floor are connected to each other in a grid shape;

[0026] Step 4.4: Pour the concrete of the newly added reliable layer, and reserve a groove with a rough inner surface at the location of the newly added floor slab during pouring;

[0027] Step 5 The construction process of each new floor slab is as follows:

[0028] Install the beams of the new floor slab - tie the reinforcement cage of the new floor slab and fix it with the reinforcement in step 4.2 - pour concrete.

[0029] Furthermore, the newly added reliable layer is a reinforced concrete shear wall, and a ring beam is protruded outward from the bottom of the newly added floor to support the edge of the newly added floor. Continuous steel bars or steel sections are arranged in the ring beam and the edge of the new floor, which surround the entire old building.

[0030] Furthermore, in the cross-layer door and window openings, all doors and windows are arranged in the vertical direction; and in the doors and windows on the same floor, from top to bottom, there are shutters for ventilation, glass windows for lighting, and doors for passage.

[0031] Furthermore, before the construction of step 2, defects in the concrete on the exterior wall surface of the old building are inspected and repaired; cracks are repaired by grouting, and defects other than cracks are repaired by chiseling the defective parts to form V-shaped grooves and then filling them with new concrete.

[0032] Compared with the prior art, the method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall of the present invention has the following beneficial effects:

[0033] In the present invention, by gathering all the door and window holes needed for the reconstruction of the old building together, vertical strip-shaped cross-layer door and window holes are formed (such holes allow various large-sized beams / slabs / columns to enter, and the pump pipe for pouring concrete inside can also slide up and down along the holes to any position), the construction holes required for the construction of each floor are provided while minimizing the damage to the bearing capacity of the outer wall of the old building, and a small number of lintels and hidden columns can be used to overcome the impact of the opening, thereby overcoming the interference of the outer wall of the old building on the internal major reconstruction construction;

[0034] By constructing a new reliable layer against the outer wall of the old building as a new load-bearing wall, the new reliable layer can reliably bear the new floor slab and has an interface that can be reliably connected to the new floor slab. It also holds the old load-bearing wall to prevent it from collapsing, and at the same time makes it unnecessary to renovate the waterproof structure of the old load-bearing wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a floor plan of the building after renovation using the present invention;

[0036] Figure 2 This is a elevation view of a building after renovation using the present invention, in which doors and windows have been installed in the cross-story door and window openings;

[0037] In the figure, 1-old building, 2-cross-story door and window openings, 3-lintel, 4-newly added reliable floor, 5-externally projecting construction corridor. DETAILED DESCRIPTION

[0038] Take the cement silo of the Jinyuxingfa Science Park project in the northern area of ​​Huairou Science City, Beijing, as an example. Figure 1-2 As shown, a method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall is used to overcome the interference of the exterior wall on the construction and add a new floor slab in the old building 1 when the exterior wall of the old building 1 is a load-bearing wall, including the following steps:

[0039] Step 1: Plan the doors and windows positions of the renovated old building 1, and concentrate the doors and windows in the cross-layer door and window opening 2. The cross-layer door and window opening 2 meets the following conditions:

[0040] Condition 1.1: Set up on the unobstructed side of the old building 1;

[0041] This condition is to meet the needs of transporting building materials into the building along the cross-layer door and window openings 2 during the building reconstruction process and the ventilation and lighting needs of the reconstructed building. If there are obstructions, it will affect the hoisting and ventilation and lighting.

[0042] Condition 1.2: The top is higher than the highest new floor slab, and the gap between the top and the highest new floor slab can accommodate at least one door and one window; the bottom is lower than the lowest new floor slab, and the gap between the bottom and the lowest new floor slab can accommodate at least one concrete pump pipe;

[0043] That is to say, the cross-layer door and window hole 2 in the present application is a very long strip-shaped hole, which can not only take into account the construction of all floors, but also various large beams / columns / slabs can be directly hoisted in, including the composite slabs and templates used in the concrete pouring process. At the same time, the concrete pump pipe can slide up and down along the cross-layer door and window hole 2 to various positions on the floor. In addition to the convenience of construction, this structure also causes minimal damage to the old building 1, there is no danger during the hole opening process, and only a small number of hidden columns and lintels 3 are needed to complete the reinforcement.

[0044] At the same time, this structure has advantages in appearance. Compared with the existing door and window layout, this layout of doors and windows is more beautiful. Its beauty and comfort have been recognized by the experts and professors of the Beijing Yanqi Lake Institute of Applied Mathematics who have stayed there.

[0045] Step 2: groove the top of the cross-layer door and window opening 2 to construct the lintel 3, and the two ends of the lintel 3 fall on the newly added hidden columns after the grooves are cut on the left and right sides of the cross-layer door and window opening 2;

[0046] That is to say, the construction of the hidden column and the lintel 3 is completed before the opening, and the hidden column is constructed first, and then the lintel 3 is constructed. While compensating for the adverse effect of the opening on the vertical bearing capacity of the old building 1, the construction safety is guaranteed. Here, when the groove is opened, a part of the horizontal steel bars in the groove can be retained for connection with the horizontal steel bars of the hidden column and the lintel 3 to increase the strength. The specific method is to leave a part of the under-excavated wall on the left and right sides of the groove when the groove is opened, and then chisel out the concrete in the under-excavated wall.

[0047] Step 3: Cut out cross-layer door and window holes 2 on the exterior wall of the old building 1;

[0048] Here, a water saw is used to cut the door and window holes, which makes the holes regular and convenient for the subsequent installation of doors and windows, while avoiding additional damage to the walls of the old building 1.

[0049] Step 4: Chisel the inner wall of the exterior wall of the old building 1; then construct a new reliable layer 4 close to the exterior wall. The new reliable layer 4 is a load-bearing wall that meets the following conditions:

[0050] Condition 4.1: Fixedly connected to the outer wall of the old building 1;

[0051] The purpose here is to hold the outer wall of the old building 1 so that it does not collapse after the hole is opened.

[0052] Condition 4.2: An interface is reserved for installing the new floor slab;

[0053] The interfaces here refer to the embedded parts used to install beams, the rebars used to connect the floor slabs, and the rough surfaces and grooves used to connect to the concrete of the floor slabs.

[0054] Even if the outer wall of the old building 1 has a qualified bearing capacity, it is impossible to install the floor slab without large-scale demolition, and the demolition is horizontal, which is equivalent to directly interrupting the old building 1, which is completely unfeasible in terms of safety. Therefore, it is chosen here to install the new floor slab on the new reliable layer 4.

[0055] Condition 4.3: It can be stable without the existence of the exterior wall of the old building 1;

[0056] That is to say, the outer wall of the old building 1 does not bear the newly added building components, and the newly added reliable layer 4 can be separated from the outer wall of the old building 1 and stably bear the newly added floor slab thereon, and meet various requirements of building specifications.

[0057] Condition 4.4: Waterproof;

[0058] The waterproofing on the outer wall of the old building 1 is no longer reliable, and the location of the leak is unknown, so the renovation cannot guarantee the effect. Here, the newly added reliable layer 4 is chosen to be waterproof, so that no additional work is required to ensure reliable waterproofing after the building reconstruction.

[0059] Step 5: Install new floor slabs on the newly added reliable layer 4 layer by layer from bottom to top.

[0060] If there are multiple old buildings 1 and they are arranged in a row, then before the construction of step 4 begins, an externally projecting construction corridor 5 is installed in advance on one side of the row of old buildings 1, and among the cross-layer door and window openings 2 planned in step 1, each old building 1 has at least one cross-layer door and window opening 2 leading to the externally projecting construction corridor 5; in the decoration stage after the renovation of the old building 1 is completed, the externally projecting construction corridor 5 is covered with a glass curtain wall and a ceiling to form a corridor for residents to use.

[0061] If the old buildings 1 are arranged in a row, it may be difficult to connect them, and there may be a need to exchange materials / personnel between different old buildings 1 during construction. Therefore, a construction platform is cantilevered here (cantilevering can avoid interference with the ground), which can meet the needs of material / personnel exchange between different old buildings 1 during construction and the need to connect different old buildings 1 after construction.

[0062] The reinforcement of the newly added floor slab penetrates the newly added reliable layer 4 and is implanted into the outer wall of the old building 1.

[0063] The operation of planting reinforcement can be carried out without damaging the exterior wall of the old building 1, while improving the pull-out resistance of the rebar. If the rebar is not planted in the exterior wall of the old building 1, the rebar needs additional fixing measures to ensure that it does not tilt when the concrete of the newly added reliable layer 4 is poured. At the same time, considering that the newly added reliable layer 4 is thin, additional structures need to be added to the rebar if the pull-out resistance is to meet the standard.

[0064] Step 4 includes the following sub-steps:

[0065] Step 4.1: Chisel the inner wall surface of the outer wall of the old building 1;

[0066] In order to ensure that the outer wall of the old building 1 is effectively connected with the newly added reliable layer 4, it is necessary not only to roughen the surface, but also to chisel away until the outer wall of the old building 1 exposes the steel bars, that is, to chisel away a layer of concrete protective layer. This layer of concrete mainly serves to protect the internal steel bars and is basically not subjected to stress, so it will not affect safety.

[0067] Step 4.2: implant the reinforcement of the newly added floor slab on the inner wall surface of the outer wall of the old building 1, and the reinforcement passes through the newly added reliable layer 4 and extends to the interior of the old building 1;

[0068] The steel bars of the newly added floor slabs need to be connected with the loose bars when binding.

[0069] Step 4.3: Tie up the steel cage of the newly added reliable layer 4, and install embedded parts for connecting with the beams of the newly added floor below the position of the newly added floor, wherein the beams of the newly added floor are connected to each other in a grid shape;

[0070] The embedded parts here can be the connecting plates needed for steel beams, or the rebars used for the construction of reinforced concrete columns. The beams here are connected in a grid shape to hold the outer wall.

[0071] Step 4.4: pouring concrete for the newly added reliable layer 4, and reserving a groove with a rough inner surface at the location of the newly added floor slab during pouring;

[0072] Step 5 The construction process of each new floor slab is as follows:

[0073] Install the beams of the new floor slab - tie the reinforcement cage of the new floor slab and fix it with the reinforcement in step 4.2 - pour concrete.

[0074] The newly added reliable layer 4 is a reinforced concrete shear wall, and protrudes outward from the bottom of the newly added floor to form a ring beam for supporting the edge of the newly added floor. Continuous steel bars or steel sections are arranged in the ring beam and the edge of the newly added floor, which surround the entire old building 1.

[0075] This structure in the newly added reliable layer 4, in addition to improving the effect of the load-bearing floor, also has another function of making the newly added reliable layer 4 more continuous and complete, so that it can bear stress better like the lining of a tunnel.

[0076] In the cross-layer door and window openings 2 , all doors and windows are arranged in the vertical direction; this is to make the cross-layer door and window openings as narrow as possible, thereby reducing the impact on the strength of the old building 1 .

[0077] The doors and windows on the same floor are arranged from top to bottom, including blinds for ventilation, glass windows for lighting, and doors for passage. This arrangement is to meet the needs of use. The blinds do not need to be opened or closed at ordinary times in order to meet the needs of range hoods and fresh air air conditioners, so they are set at the highest position. The door is set at the lowest position to ensure normal use. The glass window for lighting is set above the door and can be opened and closed with the help of an auxiliary handle.

[0078] Before the construction of step 2, the defects of the concrete on the outer wall surface of the old building 1 are checked and repaired; cracks are repaired by grouting, and defects other than cracks are repaired by chiseling the defective parts to form V-shaped grooves and then filling with new concrete.

[0079] The purpose of repairing defects here is mainly to meet the requirements of appearance, and the impact on strength is only reflected in avoiding the impact of defects on the concrete on the exterior wall of the old building 1 on the connection with the newly added reliable layer 4. Of course, repairing defects here can also improve the strength of the exterior wall of the old building 1 to a certain extent, but this is not required here.

[0080] The embodiments described above are merely descriptions of preferred implementation modes of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A method for rebuilding a new floor slab when there is interference with the original load-bearing external walls, used to overcome the interference of the external walls on the construction and add a new floor slab in the old building (1) when the external walls of the old building (1) are all load-bearing walls, characterized in that: The following steps are involved: Step 1: Plan the doors and windows positions of the renovated old building (1), and concentrate the doors and windows in the cross-layer door and window openings (2). The cross-layer door and window openings (2) meet the following conditions: Condition 1.1: Set up on the unobstructed side of the old building (1); Condition 1.2: The top is higher than the highest new floor slab, and the gap between the top and the highest new floor slab can accommodate at least one door and one window; The bottom is lower than the lowest newly added floor slab, and the gap between the bottom and the lowest newly added floor slab can accommodate at least one concrete pump pipe; Step 2: A lintel (3) is constructed by cutting a groove at the top of the cross-layer door and window opening (2), and the two ends of the lintel (3) fall on the newly added hidden columns after the grooves are cut on the left and right sides of the cross-layer door and window opening (2); Step 3: cutting out cross-layer door and window holes (2) on the exterior wall of the old building (1); Step 4: Chisel the inner wall surface of the outer wall of the old building (1); then construct a new reliable layer (4) close to the outer wall, wherein the new reliable layer (4) is a load-bearing wall that meets the following conditions: Condition 4.1: Fixedly connected to the exterior wall of the old building (1); Condition 4.2: An interface is reserved for installing the new floor slab; Condition 4.3: Can be stable without the existence of the exterior wall of the old building (1); Condition 4.4: Waterproof; Step 5: Install the new floor slabs on the new reliable layer (4) layer by layer from bottom to top.

2. The method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall according to claim 1, characterized in that: If there are multiple old buildings (1) arranged in a row, before the construction of step 4 begins, an externally projecting construction corridor (5) is pre-installed on one side of the row of old buildings (1), and among the cross-layer door and window openings (2) planned in step 1, each old building (1) has at least one cross-layer door and window opening (2) leading to the externally projecting construction corridor (5); during the decoration stage after the renovation of the old buildings (1), the externally projecting construction corridor (5) is covered with a glass curtain wall and a ceiling to form a corridor for residents to use.

3. The method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall according to claim 1, characterized in that: The steel bars of the newly added floor slab penetrate the newly added reliable layer (4) and are implanted into the outer wall of the old building (1).

4. The method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall according to claim 3, characterized in that: Step 4 includes the following sub-steps: Step 4.1: Chisel the inner surface of the exterior wall of the old building (1); Step 4.2: implanting the reinforcing bars of the newly added floor slab on the inner wall surface of the outer wall of the old building (1), wherein the reinforcing bars pass through the newly added reliable layer (4) and extend into the interior of the old building (1); Step 4.3: Tie up the steel cage of the newly added reliable layer (4), and install embedded parts for connecting with the beams of the newly added floor below the position of the newly added floor, wherein the beams of the newly added floor are connected to each other in a grid shape; Step 4.4: pouring concrete for the newly added reliable layer (4), and during pouring, leaving a groove with a rough inner surface at the location of the newly added floor slab; Step 5 The construction process of each new floor slab is as follows: Install the beams of the new floor slab - tie the reinforcement cage of the new floor slab and fix it with the reinforcement in step 4.2 - pour concrete.

5. The method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall according to claim 4, characterized in that: The newly added reliable layer (4) is a reinforced concrete shear wall and protrudes outwards from the bottom of the newly added floor slab to form a ring beam for supporting the edge of the newly added floor slab. Continuous steel bars or steel sections are arranged in the ring beam and in the edge of the newly added floor slab, which surround the entire old building (1).

6. The method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall according to claim 1, characterized in that: In the cross-floor door and window openings (2), all doors and windows are arranged in a vertical direction; and the doors and windows on the same floor are, from top to bottom, shutters for ventilation, glass windows for lighting, and doors for passage.

7. The method for rebuilding a new floor slab when there is interference with the original load-bearing exterior wall according to claim 1, characterized in that: Before the construction of step 2, the defects of the concrete on the outer wall surface of the old building (1) are inspected and repaired; cracks are repaired by grouting, and defects other than cracks are repaired by chiseling the defective parts to form V-shaped grooves and then filling with new concrete.