Intelligent tensile testing machine and testing method

By introducing mechanisms such as heat conductivity utilization, insulation and preheating, pre-filtration and air pressure adjustment in the intelligent tensile tester, the problem of high-temperature gas cannot be reused is solved, and the testing efficiency and resource utilization are improved.

CN118566019BActive Publication Date: 2024-11-15江西优尔检测认证股份有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410659089.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-27
Publication Date
2024-11-15
Estimated Expiration
2044-05-27

AI Technical Summary

Technical Problem

When the high-temperature tensile tester is in use, the high-temperature gas cannot be reused, resulting in waste of resources and low test efficiency.

Method used

An intelligent tensile testing machine is designed, including a cavity heat conduction utilization mechanism, a heat insulation preheating mechanism, a pre-filter mechanism, a negative pressure one-way communication mechanism and a pneumatic pressure adjustment mechanism, through which the reuse and preheat of temperature are realized.

Benefits of technology

It effectively reduces resource waste, shortens the time for reheating the box, improves the test efficiency, and achieves more convenient intelligent tensile tests.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118566019B_ABST
    Figure CN118566019B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of intelligent tensile testing machines, and specifically relates to an intelligent tensile testing machine and a test method, wherein an intelligent tensile testing machine comprises a tensile testing machine body, a chamber heat conduction utilization mechanism, a heat preservation preheating mechanism, a pre-filtering mechanism, a negative pressure one-way connection mechanism and an air pressure regulating mechanism, and a chamber heat conduction utilization mechanism is fixedly installed on the tensile testing machine body, and the chamber heat conduction utilization mechanism comprises a chamber heat conduction chamber, and a plurality of evenly distributed chamber vacuum tubes are arranged in the chamber heat conduction chamber, and a chamber delivery pipeline is fixedly installed between the chamber heat conduction chamber and the tensile testing machine body. The intelligent tensile testing machine and the test method of the present invention enable the temperature in the tensile testing machine to be repeatedly utilized through the setting of corresponding mechanisms, thereby reducing the waste of resources, and at the same time, can preheat the box body, shortening the time for the box body to be reheated, thereby improving the test efficiency of the tensile testing machine, and being more convenient and intelligent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of intelligent tensile testing machines, and in particular relates to an intelligent tensile testing machine and a testing method. Background Art

[0002] The tensile testing machine is also known as the universal material testing machine. The universal testing machine is a mechanical force testing machine used to perform static load, stretching, compression, bending, shearing, tearing, peeling and other mechanical property tests on various materials. It is suitable for various physical and mechanical property tests of plastic plates, pipes, special-shaped materials, plastic films, rubber, wires and cables, steel, glass fiber and other materials for material development, physical property testing, teaching research, quality control and other indispensable testing equipment. The tensile machine fixture is an important part of the instrument. Different materials require different fixtures. It is also an important factor in whether the test can be carried out smoothly and the accuracy of the test results.

[0003] Some materials need to simulate tensile tests in high temperature environments, and a high temperature tensile testing machine is usually used. When the door of this high temperature tensile testing machine is opened to replace materials, in order to prevent the high temperature gas from scalding the staff, an exhaust device is usually installed on the wall of the box to discharge the high temperature gas out of the box before the staff opens the door.

[0004] At present, when the high-temperature tensile testing machine is used, there is no corresponding waste heat utilization mechanism, and the temperature inside the box cannot be reused, resulting in a waste of resources. At the same time, after the high-temperature gas is discharged, the inside of the box needs to be reheated, which consumes a lot of time and affects the test efficiency of the tensile testing machine. It is not convenient and intelligent enough.

[0005] The information disclosed in this background technology section is only intended to enhance the understanding of the overall background of the invention and should not be regarded as an acknowledgment or any form of suggestion that the information constitutes the prior art already known to a person skilled in the art. Summary of the invention

[0006] The object of the present invention is to provide an intelligent tensile testing machine and a testing method, which can solve the problem that high-temperature gas in a high-temperature tensile testing machine cannot be reused, causing waste and affecting the test efficiency.

[0007] In order to achieve the above object, a technical solution provided by a specific embodiment of the present invention is as follows:

[0008] An intelligent tensile testing machine, comprising: a tensile testing machine body, a chamber heat conduction utilization mechanism, a heat preservation preheating mechanism, a pre-filtering mechanism, a negative pressure one-way connection mechanism and an air pressure regulating mechanism;

[0009] A cavity heat conduction utilization mechanism is fixedly installed on the tensile testing machine body, and the cavity heat conduction utilization mechanism includes a cavity heat conduction chamber, and a plurality of evenly distributed cavity vacuum tubes are arranged in the cavity heat conduction chamber, and a cavity delivery pipeline is fixedly installed between the cavity heat conduction chamber and the tensile testing machine body, and a cavity sealing plate is arranged on one side of the cavity delivery pipeline, and a cavity heat conduction plate is fixedly installed in the cavity heat conduction chamber, and a cavity sealing pad is fixedly installed on the side of the cavity sealing plate close to the cavity delivery pipeline;

[0010] A heat preservation preheating mechanism is installed on the outer side of the chamber heat transfer bin, and the heat preservation preheating mechanism includes a heat preservation preheating bin, a heat preservation filtrate is arranged in the heat preservation preheating bin, a heat preservation dispersion filter is rotatably installed in the heat preservation preheating bin, a heat preservation motor is fixedly installed in the heat preservation preheating bin, a heat preservation support bearing is installed between the heat preservation dispersion filter and the heat preservation preheating bin, a heat preservation gear is fixedly installed on the heat preservation motor, and a heat preservation gear ring is fixedly installed on the heat preservation dispersion filter;

[0011] A pre-filtering mechanism is installed between the tensile testing machine body and the sub-chamber heat transfer chamber, for simply filtering the air in the tensile testing machine body;

[0012] A negative pressure one-way communication mechanism is installed between the sub-chamber heat transfer bin and the heat preservation preheating bin to prevent the heat preservation filtrate from entering the sub-chamber heat transfer bin;

[0013] An air pressure regulating mechanism is installed in the divided-chamber heat-conducting chamber to regulate the air pressure in the divided-chamber heat-conducting chamber.

[0014] In one or more embodiments of the present invention, the split-chamber vacuum tube is arranged through the split-chamber heat-conducting plate, and the split-chamber heat-conducting plate separates the split-chamber heat-conducting chamber to form two independent spaces, and the split-chamber vacuum tube can conduct the temperatures of the two spaces to each other;

[0015] The sub-cavity delivery pipeline runs through the tensile testing machine body, the heat preservation preheating chamber and the sub-cavity heat transfer chamber, connecting the tensile testing machine body and the sub-cavity heat transfer chamber, so that the air with temperature in the sub-cavity heat transfer chamber can enter the tensile testing machine body to preheat the tensile testing machine body;

[0016] The sub-cavity sealing plate is rotatably mounted on the tensile testing machine body, so that air can push the sub-cavity sealing plate open, and when the air pressure in the sub-cavity heat transfer chamber becomes low, the sub-cavity delivery pipeline can be closed;

[0017] A plurality of sub-cavity heat-conducting fins are fixedly mounted on the plurality of sub-cavity vacuum tubes, which improves the efficiency of temperature conduction, increases the contact area between the air and the sub-cavity vacuum tubes, and enables better temperature conduction.

[0018] In one or more embodiments of the present invention, the heat preservation gear is meshed with the heat preservation gear ring, which can drive the heat preservation gear ring to rotate, so that the heat preservation dispersion filter can be driven by the heat preservation gear ring to rotate, making the rotation of the heat preservation dispersion filter more controllable;

[0019] A capped filter is fixedly installed in the thermal insulation preheating chamber, which can reduce the possibility of impurities floating on the surface of the thermal insulation filtrate entering the equalization and pressure pipeline, making the air entering the equalization and pressure pipeline cleaner;

[0020] A flat-pressure pipe is arranged in the thermal insulation preheating chamber, connecting the thermal insulation preheating chamber and the sub-cavity heat transfer chamber, so that the air in the thermal insulation preheating chamber can better enter the sub-cavity heat transfer chamber, and the flat-pressure pipe runs through the sub-cavity heat transfer chamber.

[0021] In one or more embodiments of the present invention, the pre-filter mechanism includes a pre-filter bin, which facilitates the sliding of the pre-filter drawer, improves the stability of the pre-filter drawer, and facilitates cleaning by the user;

[0022] Pre-filter connecting pipes are installed on both sides of the pre-filtering bin, connecting the sub-cavity heat transfer bin, the pre-filtering bin and the tensile testing machine body, so that the air in the tensile testing machine body can enter the pre-filtering bin and finally enter the sub-cavity heat transfer bin. A pair of pre-filter connecting pipes are respectively set to penetrate the tensile testing machine body and the sub-cavity heat transfer bin;

[0023] A pre-filter drawer is slidably installed in the pre-filter bin to collect impurities. The test materials are uncertain and may produce debris or impurities. These impurities will be blocked by the self-cleaning filter and fall into the pre-filter drawer. The pre-filter drawer and the pre-filter connecting pipe are both set through the pre-filter bin.

[0024] In one or more embodiments of the present invention, a pair of balancing shafts are fixedly installed in the pre-filter bin, which improves the balance of the self-cleaning filter and reduces the probability of the self-cleaning filter tilting;

[0025] A pair of the balancing shafts are slidably mounted with self-cleaning filters, which can block impurities and make them fall into the pre-filter drawer without affecting the circulation of air;

[0026] The self-cleaning filter is fixedly installed with a wind blocking plate to block the air, so that the thrust generated by the air can make the self-cleaning filter fit with the pre-filter connecting pipe, reducing the possibility of impurities entering the sub-cavity heat transfer bin. At the same time, when the self-cleaning filter and the pre-filter connecting pipe collide with each other, vibration can be generated to loosen the stuck impurities, reducing the probability of clogging of the self-cleaning filter;

[0027] A pair of positioning springs are provided on both sides of the self-cleaning filter, which can locate the position of the self-cleaning filter so that the self-cleaning filter can indirectly collide with the pre-filtration connecting pipe. The positioning spring is sleeved on the balance support shaft, which facilitates the installation of the positioning spring and improves the stability of the positioning spring.

[0028] In one or more embodiments of the present invention, the negative pressure one-way connecting mechanism includes a negative pressure one-way pipe, which connects the sub-cavity heat transfer bin and the heat preservation preheating bin, so that the air in the sub-cavity heat transfer bin can enter the heat preservation preheating bin, and the heat preservation filtrate is heated while being filtered, and the negative pressure one-way pipe runs through the sub-cavity heat transfer bin and the heat preservation preheating bin;

[0029] A negative pressure matching ring is fixedly installed in the negative pressure one-way pipe, which can cooperate with the negative pressure sealing ball to seal the negative pressure one-way pipe, thereby reducing the possibility of the thermal insulation filter liquid flowing into the sub-chamber heat transfer bin, thereby extending the use time of the thermal insulation filter liquid;

[0030] A negative pressure guide frame is fixedly installed in the negative pressure one-way pipe, which facilitates the sliding of the negative pressure sealing ball, allowing the air to lift the negative pressure sealing ball and pass through the negative pressure one-way pipe.

[0031] In one or more embodiments of the present invention, a negative pressure sealing ball is slidably mounted on the negative pressure guide frame, which can seal the negative pressure one-way pipeline, and the negative pressure sealing ball matches the negative pressure matching ring;

[0032] A negative pressure sealing spring is installed between the negative pressure sealing ball and the negative pressure guide frame, which can squeeze the negative pressure sealing ball so that the negative pressure sealing ball can better cooperate with the negative pressure matching ring to close the negative pressure one-way pipeline. The negative pressure sealing spring is sleeved on the negative pressure guide frame.

[0033] In one or more embodiments of the present invention, the air pressure regulating mechanism includes an air pressure lifting plate, which can adjust the air pressure in the sub-cavity heat transfer bin by lifting and lowering, and the air circulation can be controlled by lifting and lowering the air pressure lifting plate;

[0034] An air pressure sealing pad is installed between the air pressure lifting plate and the sub-cavity heat transfer chamber, which improves the sealing between the air pressure lifting plate and the sub-cavity heat transfer chamber and reduces the possibility of air leakage from the gap between the air pressure lifting plate and the sub-cavity heat transfer chamber;

[0035] A pneumatic motor is fixedly installed on the chamber heat transfer bin, which can drive the rotation of the pneumatic threaded rod and provide corresponding power for the rotation of the pneumatic threaded rod;

[0036] A pneumatic threaded rod is fixedly installed on the pneumatic motor, which can drive the lifting and lowering of the pneumatic lifting plate and control the lifting and lowering of the pneumatic lifting plate. The pneumatic threaded rod and the chamber heat transfer bin are installed on a pneumatic support frame, which improves the balance of the pneumatic threaded rod and facilitates the installation of the pneumatic balance rod.

[0037] In one or more embodiments of the present invention, the pneumatic threaded rod passes through the pneumatic lifting plate and the pneumatic support frame, the pneumatic threaded rod matches the pneumatic lifting plate, and a pair of pneumatic balance rods are installed between the pneumatic support frame and the chamber heat conduction bin, which can improve the balance of the pneumatic lifting plate and the sealing performance while guiding the pneumatic lifting plate. The pneumatic balance rod passes through the pneumatic lifting plate.

[0038] A testing method of an intelligent tensile testing machine comprises the following steps:

[0039] S1. After the tensile test is completed, start the pneumatic motor, so that the pneumatic threaded rod drives the pneumatic lifting plate to rise upward, and the air pressure in the heat transfer chamber of the divided chamber becomes lower;

[0040] S2. At this time, the air in the tensile testing machine will carry heat into the pre-filter chamber, and will be simply filtered by the self-cleaning filter and flow into the heat transfer chamber;

[0041] S3. After the air enters the heat transfer chamber, the heat will be conducted by the heat transfer fins and vacuum tubes, so that the water in the vacuum tubes will be heated up. Since the vacuum tubes are in a vacuum state, the water will be converted into water vapor more quickly.

[0042] S4, the air with residual temperature will enter the heat preservation and preheating chamber through the negative pressure one-way connecting mechanism, and heat the heat preservation filtrate, so that the heat preservation and preheating chamber can keep the air in the heat conduction chamber warm;

[0043] S5. At the same time, the thermal insulation filter liquid can filter out harmful substances carried in the air, and the thermal insulation dispersion filter will disperse the bubbles formed by the air through rotation, thereby improving the filtering effect of the thermal insulation filter liquid;

[0044] S6. Then, the air will enter the sub-cavity heat transfer chamber through the flat pressure pipe, and be heated by the temperature in the sub-cavity vacuum tube, and will be squeezed into the tensile testing machine body through the descent of the air pressure lifting plate, so as to utilize the residual heat to achieve the purpose of preheating the tensile testing machine body.

[0045] Compared with the prior art, the intelligent tensile testing machine and testing method of the present invention enable the temperature inside the tensile testing machine to be reused through the setting of corresponding mechanisms, thereby reducing the waste of resources. At the same time, it can preheat the box, shorten the time for reheating the box, improve the testing efficiency of the tensile testing machine, and be more convenient and intelligent. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0047] Figure 1 It is a front cross-sectional view of an intelligent tensile testing machine and a testing method in one embodiment of the present invention;

[0048] Figure 2 for Figure 1 Schematic diagram at A in the middle;

[0049] Figure 3 for Figure 1 Schematic diagram at point B in the middle;

[0050] Figure 4 for Figure 1 Schematic diagram at C in the middle;

[0051] Figure 5 for Figure 1 Schematic diagram at D in the middle;

[0052] Figure 6 for Figure 1 Schematic diagram at E in the middle;

[0053] Figure 7 for Figure 1 Schematic diagram of point F in the middle;

[0054] Figure 8 for Figure 1 Schematic diagram at G in the middle;

[0055] Fig. 9 for Figure 1 Schematic diagram of H in the middle;

[0056] Fig.10 It is a three-dimensional diagram of an intelligent tensile testing machine and a testing method in one embodiment of the present invention.

[0057] Description of main reference numerals:

[0058] 1- tensile testing machine body, 2- chamber heat conduction utilization mechanism, 201- chamber heat conduction chamber, 202- chamber vacuum tube, 203- chamber delivery pipeline, 204- chamber closing plate, 205- chamber heat conduction plate, 206- chamber closing pad, 207- chamber heat conduction fin, 3- insulation preheating mechanism, 301- insulation preheating chamber, 302- insulation filtrate, 303- insulation dispersion filter, 304- insulation motor, 305- insulation support bearing, 306- insulation gear, 307- insulation gear ring, 308- capping filter, 309- flat pressure pipeline, 4- pre-filtration mechanism, 401-pre-filter bin, 402-pre-filter connecting pipe, 403-pre-filter drawer, 404-balance support shaft, 405-self-cleaning filter, 406-wind baffle, 407-positioning spring, 5-negative pressure one-way connecting mechanism, 501-negative pressure one-way pipe, 502-negative pressure matching ring, 503-negative pressure guide frame, 504-negative pressure closing ball, 505-negative pressure closing spring, 6-air pressure regulating mechanism, 601-air pressure lifting plate, 602-air pressure sealing pad, 603-air pressure motor, 604-air pressure threaded rod, 605-air pressure support frame, 606-air pressure balance rod. DETAILED DESCRIPTION

[0059] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0060] like Figures 1 to 10 As shown, the intelligent tensile testing machine and testing method in one embodiment of the present invention include: a tensile testing machine body 1, a chamber heat conduction utilization mechanism 2, a heat preservation and preheating mechanism 3, a pre-filtration mechanism 4, a negative pressure one-way connection mechanism 5 and an air pressure adjustment mechanism 6.

[0061] like Figures 1 to 5 As shown, a divided-chamber heat-conducting utilization mechanism 2 is fixedly installed on the tensile testing machine body 1. The divided-chamber heat-conducting utilization mechanism 2 includes a divided-chamber heat-conducting chamber 201, which can accommodate air and can also achieve the purpose of delivering or extracting air for the tensile testing machine body 1 by lifting and lowering the air pressure lifting plate 601.

[0062] Among them, a number of evenly distributed sub-cavity vacuum tubes 202 are provided in the sub-cavity heat transfer chamber 201. The interior of the sub-cavity vacuum tube 202 is vacuum and filled with water. The sub-cavity vacuum tube 202 can absorb heat and heat the water, converting the water into water vapor, raising the water vapor, and transferring the heat again.

[0063] In addition, a sub-cavity delivery pipeline 203 is fixedly installed between the sub-cavity heat transfer chamber 201 and the tensile testing machine body 1, connecting the sub-cavity heat transfer chamber 201 and the tensile testing machine body 1, so that the air in the sub-cavity heat transfer chamber 201 can be injected into the tensile testing machine body 1.

[0064] In addition, a chamber closing plate 204 is provided on one side of the chamber delivery pipeline 203, which can close the chamber delivery pipeline 203 so that when the air pressure lifting plate 601 rises, the upper cavity formed by the chamber heat conduction chamber 201 and the chamber heat conduction plate 205 will not draw air from the tensile testing machine body 1.

[0065] Among them, a partition heat conduction plate 205 is fixedly installed in the partition heat conduction chamber 201, which can separate the partition heat conduction chamber 201 so that the partition heat conduction chamber 201 forms two cavities, and a partition sealing pad 206 is fixedly installed on the side of the partition closing plate 204 close to the partition delivery pipe 203, which improves the sealing performance of the partition closing plate 204 to the partition delivery pipe 203, and further reduces the possibility that the partition delivery pipe 203 absorbs air in the tensile testing machine body 1.

[0066] like Figures 1 to 5 As shown, the divided-chamber vacuum tube 202 is arranged through the divided-chamber heat-conducting plate 205, and the divided-chamber heat-conducting plate 205 separates the divided-chamber heat-conducting chamber 201 to form two independent spaces. The divided-chamber vacuum tube 202 can conduct the temperatures of the two spaces to each other.

[0067] Among them, the sub-chamber conveying pipeline 203 runs through the tensile testing machine body 1, the thermal insulation preheating chamber 301 and the sub-chamber heat transfer chamber 201, connecting the tensile testing machine body 1 and the sub-chamber heat transfer chamber 201, so that the air carrying the temperature in the sub-chamber heat transfer chamber 201 can enter the tensile testing machine body 1 to preheat the tensile testing machine body 1.

[0068] In addition, the chamber sealing plate 204 is rotatably installed with the tensile testing machine body 1, so that the air can push open the chamber sealing plate 204, and when the air pressure in the chamber heat transfer chamber 201 becomes low, the chamber delivery pipeline 203 can be closed.

[0069] In addition, a plurality of sub-cavity heat-conducting fins 207 are fixedly mounted on the plurality of sub-cavity vacuum tubes 202 , which improves the efficiency of temperature conduction, increases the contact area between air and the sub-cavity vacuum tubes 202 , and enables better temperature conduction.

[0070] like Figures 1 to 8 As shown, a heat preservation and preheating mechanism 3 is installed on the outer side of the divided-chamber heat transfer chamber 201. The heat preservation and preheating mechanism 3 includes a heat preservation and preheating chamber 301, which can accommodate the heat preservation filtrate 302 and provide corresponding space for air filtration.

[0071] In addition, the heat preservation preheating chamber 301 is provided with a heat preservation filtrate 302 which can be heated to achieve the purpose of heat preservation of the sub-chamber heat transfer chamber 201 and slow down the dissipation speed of the air temperature in the sub-chamber heat transfer chamber 201 .

[0072] Among them, a heat preservation dispersion filter 303 is rotatably installed in the heat preservation preheating chamber 301, which can disperse the bubbles formed by the air, so that the heat preservation filter liquid 302 can better absorb impurities and harmful substances in the air.

[0073] In addition, an insulation motor 304 is fixedly installed in the insulation preheating chamber 301, which can drive the rotation of the insulation gear 306 and provide corresponding power for the rotation of the insulation gear 306. An insulation support bearing 305 is installed between the insulation dispersion filter 303 and the insulation preheating chamber 301, which facilitates the rotation of the insulation dispersion filter 303 and reduces the friction between the insulation dispersion filter 303 and the insulation preheating chamber 301.

[0074] In addition, a heat preservation gear 306 is fixedly installed on the heat preservation motor 304 , which can drive the rotation of the heat preservation gear ring 307 and provide power for the rotation of the heat preservation gear ring 307 . The heat preservation dispersion filter 303 is fixedly installed with a heat preservation gear ring 307 .

[0075] like Figures 1 to 6 As shown, the heat preservation gear 306 is meshed with the heat preservation gear ring 307, which can drive the rotation of the heat preservation gear ring 307, so that the heat preservation dispersion filter 303 can be driven by the heat preservation gear ring 307 to rotate, making the rotation of the heat preservation dispersion filter 303 more controllable.

[0076] Among them, a capping filter 308 is fixedly installed in the insulation preheating chamber 301, which can reduce the possibility of impurities floating on the surface of the insulation filtrate 302 entering the equalization and pressure pipe 309, making the air entering the equalization and pressure pipe 309 cleaner.

[0077] In addition, a flat-pressure pipe 309 is provided in the thermal insulation preheating chamber 301, connecting the thermal insulation preheating chamber 301 and the sub-cavity heat transfer chamber 201, so that the air in the thermal insulation preheating chamber 301 can better enter the sub-cavity heat transfer chamber 201, and the flat-pressure pipe 309 is set through the sub-cavity heat transfer chamber 201.

[0078] like Figures 1 to 3 As shown, a pre-filter mechanism 4 is installed between the tensile testing machine body 1 and the divided-chamber heat-conducting chamber 201, which is used to simply filter the air in the tensile testing machine body 1. The pre-filter mechanism 4 includes a pre-filter chamber 401, which facilitates the sliding of the pre-filter drawer 403, improves the stability of the pre-filter drawer 403, and facilitates cleaning by the user.

[0079] Among them, pre-filter connecting pipes 402 are installed on both sides of the pre-filter bin 401, connecting the divided-chamber heat-conducting bin 201, the pre-filter bin 401 and the tensile testing machine body 1, so that the air in the tensile testing machine body 1 can enter the pre-filter bin 401 and finally enter the divided-chamber heat-conducting bin 201. A pair of pre-filter connecting pipes 402 are respectively set through the tensile testing machine body 1 and the divided-chamber heat-conducting bin 201.

[0080] In addition, a pre-filter drawer 403 is slidably installed in the pre-filter bin 401 to collect impurities. The test materials are uncertain and may produce debris or impurities. These impurities will be blocked by the self-cleaning filter 405 and fall into the pre-filter drawer 403. The pre-filter drawer 403 and the pre-filter connecting pipe 402 are both set throughout the pre-filter bin 401.

[0081] like Figures 1 to 3 As shown, a pair of balancing support shafts 404 are fixedly installed in the pre-filter chamber 401, which improves the balance of the self-cleaning filter 405 and reduces the probability of the self-cleaning filter 405 tilting.

[0082] A self-cleaning filter 405 is slidably mounted on a pair of balancing shafts 404, which can block impurities and make them finally fall into the pre-filter drawer 403 without affecting the circulation of air.

[0083] In addition, a wind blocking plate 406 is fixedly installed in the self-cleaning filter 405 to block the air so that the thrust generated by the air can fit the self-cleaning filter 405 and the pre-filter connecting pipe 402, thereby reducing the possibility of impurities entering the sub-chamber heat transfer chamber 201. At the same time, when the self-cleaning filter 405 and the pre-filter connecting pipe 402 collide with each other, vibrations can be generated to loosen the stuck impurities, thereby reducing the chance of blockage of the self-cleaning filter 405.

[0084] In addition, a pair of positioning springs 407 are provided on both sides of the self-cleaning filter 405, which can locate the position of the self-cleaning filter 405 so that the self-cleaning filter 405 can indirectly collide with the pre-filtration connecting pipe 402. The positioning spring 407 is sleeved on the balance support shaft 404, which facilitates the installation of the positioning spring 407 and improves the stability of the positioning spring 407.

[0085] like Figures 1 to 6As shown, a negative pressure one-way connecting mechanism 5 is installed between the divided-chamber heat transfer bin 201 and the thermal insulation preheating bin 301, which is used to prevent the thermal insulation filtered liquid 302 from entering the divided-chamber heat transfer bin 201. The negative pressure one-way connecting mechanism 5 includes a negative pressure one-way pipe 501, which connects the divided-chamber heat transfer bin 201 and the thermal insulation preheating bin 301, so that the air in the divided-chamber heat transfer bin 201 can enter the thermal insulation preheating bin 301, and the thermal insulation filtered liquid 302 is heated while being filtered. The negative pressure one-way pipe 501 is set through the divided-chamber heat transfer bin 201 and the thermal insulation preheating bin 301.

[0086] Among them, a negative pressure matching ring 502 is fixedly installed in the negative pressure one-way pipe 501, which can cooperate with the negative pressure sealing ball 504 to seal the negative pressure one-way pipe 501, thereby reducing the possibility of the insulation filter liquid 302 flowing into the sub-chamber heat transfer chamber 201, and extending the use time of the insulation filter liquid 302.

[0087] In addition, a negative pressure guide frame 503 is fixedly installed in the negative pressure one-way pipe 501 to facilitate the sliding of the negative pressure sealing ball 504, so that the air can lift the negative pressure sealing ball 504 and pass through the negative pressure one-way pipe 501.

[0088] like Figures 1 to 6 As shown, a negative pressure sealing ball 504 is slidably mounted on the negative pressure guide frame 503 , which can seal the negative pressure one-way pipe 501 , and the negative pressure sealing ball 504 matches the negative pressure matching ring 502 .

[0089] Among them, a negative pressure sealing spring 505 is installed between the negative pressure sealing ball 504 and the negative pressure guide frame 503, which can squeeze the negative pressure sealing ball 504 so that the negative pressure sealing ball 504 can better cooperate with the negative pressure matching ring 502 to close the negative pressure one-way pipe 501. The negative pressure sealing spring 505 is sleeved on the negative pressure guide frame 503.

[0090] like Figures 1 to 8 As shown, an air pressure regulating mechanism 6 is installed in the divided-chamber heat-conducting chamber 201 for regulating the air pressure in the divided-chamber heat-conducting chamber 201. The air pressure regulating mechanism 6 includes an air pressure lifting plate 601, which can regulate the air pressure in the divided-chamber heat-conducting chamber 201 by lifting. By lifting and lowering the air pressure lifting plate 601, the air circulation can be controlled.

[0091] Among them, an air pressure sealing pad 602 is installed between the air pressure lifting plate 601 and the divided chamber heat transfer chamber 201, which improves the sealing between the air pressure lifting plate 601 and the divided chamber heat transfer chamber 201 and reduces the possibility of air leakage from the gap between the air pressure lifting plate 601 and the divided chamber heat transfer chamber 201.

[0092] In addition, a pneumatic motor 603 is fixedly installed on the chamber heat transfer chamber 201 , which can drive the rotation of the pneumatic threaded rod 604 and provide corresponding power for the rotation of the pneumatic threaded rod 604 .

[0093] In addition, a pneumatic threaded rod 604 is fixedly installed on the pneumatic motor 603, which can drive the lifting and lowering of the pneumatic lifting plate 601 and control the lifting and lowering of the pneumatic lifting plate 601. The pneumatic threaded rod 604 and the chamber heat transfer chamber 201 are installed on a pneumatic support frame 605, which improves the balance of the pneumatic threaded rod 604 and facilitates the installation of the pneumatic balance rod 606.

[0094] like Figures 1 to 10 As shown, the pneumatic threaded rod 604 passes through the pneumatic lifting plate 601 and the pneumatic support frame 605, the pneumatic threaded rod 604 matches the pneumatic lifting plate 601, and a pair of pneumatic balance rods 606 are installed between the pneumatic support frame 605 and the chamber heat transfer chamber 201, which can improve the balance of the pneumatic lifting plate 601 and the sealing performance, and can guide the pneumatic lifting plate 601. The pneumatic balance rod 606 passes through the pneumatic lifting plate 601.

[0095] A testing method for an intelligent tensile testing machine, characterized in that it comprises the following steps:

[0096] S1. After the tension test is completed, the pneumatic motor 603 is started, so that the pneumatic threaded rod 604 drives the pneumatic lifting plate 601 to rise upward, and the air pressure in the divided-chamber heat transfer chamber 201 becomes lower.

[0097] S2. At this time, the air in the tensile testing machine body 1 will carry heat into the pre-filter chamber 401 and be simply filtered by the self-cleaning filter 405 and flow into the sub-chamber heat transfer chamber 201.

[0098] S3. After the air enters the divided-chamber heat transfer chamber 201, the heat will be conducted by the divided-chamber heat transfer fins 207 and the divided-chamber vacuum tube 202, so that the water in the divided-chamber vacuum tube 202 will be heated up. Since the divided-chamber vacuum tube 202 is in a vacuum state, the water will be converted into water vapor more quickly.

[0099] S4. The air with residual temperature will enter the heat preservation and preheating chamber 301 through the negative pressure one-way connecting mechanism 5 and heat the heat preservation filtrate 302, so that the heat preservation and preheating chamber 301 can keep the air in the divided chamber heat transfer chamber 201 warm.

[0100] S5. At the same time, the thermal insulation filter liquid 302 can filter harmful substances carried in the air, and the thermal insulation dispersion filter 303 will disperse the bubbles formed by the air through rotation, thereby improving the filtering effect of the thermal insulation filter liquid 302.

[0101] S6. Then, the air will enter the divided-chamber heat transfer chamber 201 through the equalizing pipe 309, and be heated by the temperature in the divided-chamber vacuum tube 202, and will be squeezed into the tensile testing machine body 1 through the descent of the air pressure lifting plate 601, so as to utilize the residual heat to achieve the purpose of preheating the tensile testing machine body 1.

[0102] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

[0103] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. An intelligent tensile testing machine, characterized in that: include: Tensile testing machine body; The sub-cavity heat conduction utilization mechanism is fixedly installed on the tensile testing machine body, the sub-cavity heat conduction utilization mechanism includes a sub-cavity heat conduction bin, a plurality of evenly distributed sub-cavity vacuum tubes are arranged in the sub-cavity heat conduction bin, a sub-cavity delivery pipeline is fixedly installed between the sub-cavity heat conduction bin and the tensile testing machine body, a sub-cavity closing plate is arranged on one side of the sub-cavity delivery pipeline, a sub-cavity heat conduction plate is fixedly installed in the sub-cavity heat conduction bin, a sub-cavity closing pad is fixedly installed on the side of the sub-cavity closing plate close to the sub-cavity delivery pipeline, the sub-cavity vacuum tube is arranged through the sub-cavity heat conduction plate, the sub-cavity delivery pipeline is arranged through the tensile testing machine body, the thermal insulation preheating bin and the sub-cavity heat conduction bin, the sub-cavity closing plate is rotatably installed with the tensile testing machine body, and a plurality of sub-cavity heat conduction fins are fixedly installed on the plurality of sub-cavity vacuum tubes; A heat preservation and preheating mechanism is installed on the outside of the sub-cavity heat transfer bin, the heat preservation and preheating mechanism includes a heat preservation and preheating bin, a heat preservation filtrate is arranged in the heat preservation and preheating bin, a heat preservation and dispersion filter is rotatably installed in the heat preservation and preheating bin, a heat preservation motor is fixedly installed in the heat preservation and preheating bin, a heat preservation support bearing is installed between the heat preservation and dispersion filter and the heat preservation and preheating bin, a heat preservation gear is fixedly installed on the heat preservation and preheating motor, a heat preservation gear ring is fixedly installed on the heat preservation and dispersion filter, the heat preservation gear is meshed with the heat preservation gear ring, a capping filter is fixedly installed in the heat preservation and preheating bin, a flat pressure pipe is arranged in the heat preservation and preheating bin, and the flat pressure pipe runs through the sub-cavity heat transfer bin; A pre-filter mechanism is installed between the tensile testing machine body and the sub-cavity heat-conducting chamber, and is used for simply filtering the air in the tensile testing machine body. The pre-filter mechanism includes a pre-filtering chamber, and both sides of the pre-filtering chamber are provided with pre-filtering communication pipes. A pair of the pre-filtering communication pipes respectively penetrate the tensile testing machine body and the sub-cavity heat-conducting chamber. A pre-filtering drawer is slidably installed in the pre-filtering chamber, and the pre-filtering drawer and the pre-filtering communication pipe are both provided through the pre-filtering chamber; A negative pressure one-way communication mechanism is installed between the heat preservation and preheating chamber and the heat conduction chamber of the sub-chamber, and is used to prevent the heat preservation filtrate from entering the heat conduction chamber of the sub-chamber; The air pressure regulating mechanism is installed in the divided-chamber heat-conducting chamber and is used to regulate the air pressure in the divided-chamber heat-conducting chamber.

2. The intelligent tensile testing machine according to claim 1, characterized in that: A pair of balancing shafts are fixedly installed in the pre-filter bin, a self-cleaning filter is slidably installed on the pair of balancing shafts, a wind blocking plate is fixedly installed in the self-cleaning filter, a pair of positioning springs are provided on both sides of the self-cleaning filter, and the positioning springs are sleeved on the balancing shafts.

3. The intelligent tensile testing machine according to claim 1, characterized in that: The negative pressure one-way connecting mechanism includes a negative pressure one-way pipe, which runs through the sub-cavity heat conduction bin and the thermal insulation preheating bin. A negative pressure matching ring is fixedly installed in the negative pressure one-way pipe, and a negative pressure guide frame is fixedly installed in the negative pressure one-way pipe.

4. The intelligent tensile testing machine according to claim 3, characterized in that: A negative pressure sealing ball is slidably mounted on the negative pressure guide frame, the negative pressure sealing ball matches the negative pressure matching ring, a negative pressure sealing spring is mounted between the negative pressure sealing ball and the negative pressure guide frame, and the negative pressure sealing spring is sleeved on the negative pressure guide frame.

5. The intelligent tensile testing machine according to claim 1, characterized in that: The air pressure regulating mechanism includes an air pressure lifting plate, an air pressure sealing pad is installed between the air pressure lifting plate and the divided chamber heat conducting bin, an air pressure motor is fixedly installed on the divided chamber heat conducting bin, an air pressure threaded rod is fixedly installed on the air pressure motor, and an air pressure support frame is installed between the air pressure threaded rod and the divided chamber heat conducting bin.

6. The intelligent tensile testing machine according to claim 5, characterized in that: The pneumatic threaded rod passes through the pneumatic lifting plate and the pneumatic support frame, the pneumatic threaded rod matches the pneumatic lifting plate, a pair of pneumatic balance rods are installed between the pneumatic support frame and the chamber heat conduction bin, and the pneumatic balance rods pass through the pneumatic lifting plate.

7. A testing method of the intelligent tensile testing machine according to any one of claims 1 to 6, characterized in that: The following steps are involved: S1. After the tensile test is completed, start the pneumatic motor, so that the pneumatic threaded rod drives the pneumatic lifting plate to rise upward, and the air pressure in the heat transfer chamber of the divided chamber becomes lower; S2. At this time, the air in the tensile testing machine will carry heat into the pre-filter compartment, and will be simply filtered by the self-cleaning filter and flow into the heat transfer compartment; S3. After the air enters the heat transfer chamber, the heat will be conducted by the heat transfer fins and vacuum tubes, so that the water in the vacuum tubes will be heated up. Since the vacuum tubes are in a vacuum state, the water will be converted into water vapor more quickly. S4, the air with residual temperature will enter the heat preservation and preheating chamber through the negative pressure one-way connecting mechanism, and heat the heat preservation filtrate, so that the heat preservation and preheating chamber can keep the air in the heat conduction chamber warm; S5. At the same time, the thermal insulation filter liquid can filter out harmful substances carried in the air, and the thermal insulation dispersion filter will disperse the bubbles formed by the air through rotation, thereby improving the filtering effect of the thermal insulation filter liquid; S6. Then, the air will enter the sub-cavity heat transfer chamber through the flat pressure pipe, and be heated by the temperature in the sub-cavity vacuum tube, and will be squeezed into the tensile testing machine body through the descent of the air pressure lifting plate, so as to utilize the residual heat to achieve the purpose of preheating the tensile testing machine body.