A construction control system for prestressed concrete cast-in-place continuous beam hanging basket
By constructing a three-dimensional model and benchmark point fitting technology, the complex problem of linear control during the bridge construction stage was solved, and accurate linear monitoring and control of the cantilever cast-in-place box girder was achieved, ensuring construction quality.
Patent Information
- Application Number
- CN202411057753.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-08-02
AI Technical Summary
During the bridge construction stage, alignment control is complex, especially the deflection monitoring of cantilever cast-in-place box girders is difficult. Existing technology is mainly used for alignment monitoring of completed bridges, and lacks alignment monitoring methods during the construction stage, which affects construction quality.
Provides a construction control system for prestressed concrete cast-in-situ continuous beam hanging baskets. It obtains bridge image information through the image acquisition module, builds a three-dimensional model, sets reference points to determine the reference straight line, and the image processing module fits edge information and optimizes the simulation based on threshold settings. When combined, the control system issues instructions to adjust the position of the pouring formwork to ensure the linear requirements.
It realizes linear monitoring and control of the hanging basket process during the construction stage, improves the precise positioning of the pouring formwork, and ensures the beauty and safety of the bridge.
Smart Images

Figure CN118567245B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a prestressed concrete cast-in-place continuous beam hanging basket construction control system. Background Art
[0002] Linear control has a vital impact on the appearance, service life and operation status of cantilever cast-in-place box girders. The main contents of linear monitoring include elevation, axis and deflection. The control of plane curve linearity can meet the requirements through precise measurement and strict control during construction; the linear control of bridge longitudinal variable cross-section curve has many influencing factors, complex calculations, and the difficulty of monitoring is the key to linear control. The main factors affecting deflection are the elastic deformation of the hanging basket caused by the deadweight of the box girder section, construction load, construction technology, foundation settlement, compression deformation of the main pier, concrete shrinkage and creep, sunshine and temperature changes, etc., so it is necessary to adopt dynamic monitoring.
[0003] The Chinese patent with publication number CN113192063B discloses a bridge alignment monitoring system and bridge alignment monitoring method, which sets multiple targets with different heights and spacings under the bridge, uses image acquisition equipment to collect images of the targets from two different perspectives at different times, performs real-time data processing, and fits the alignment curve of the bridge. However, in this scheme, it is mainly used for alignment monitoring of built bridges, and once the bridge is built, the alignment is basically finalized. Therefore, the alignment monitoring of the hanging basket process should also be carried out in advance during the construction stage to ensure that the cast beams at each stage meet the alignment requirements of the bridge. Summary of the invention
[0004] The purpose of the present invention is to overcome the defects in the prior art and provide a prestressed concrete cast-in-place continuous beam hanging basket construction control system.
[0005] The present invention provides a prestressed concrete cast-in-place continuous beam hanging basket construction control system, the control system is connected to at least two prestressed concrete cast-in-place continuous beam hanging basket construction equipment, the two prestressed concrete cast-in-place continuous beam hanging basket construction equipment are respectively located on both sides of the bridge block No. 0, and are used to simultaneously perform hanging basket construction at both ends of the bridge block No. 0, the prestressed concrete cast-in-place continuous beam hanging basket construction equipment at least includes:
[0006] The movable main truss located at the top of the bridge block No. 0, the lower crossbeams located at both ends of the bridge block No. 0, the casting template located on the lower crossbeam, and the external grouting pump; the lower crossbeam is connected to the movable main truss through a hoisting device, one end of the grouting pump is connected to an external concrete mixing device for providing mixing concrete, and the other end of the grouting pump can be extended to the inside of the casting area formed by the casting template to complete the concrete pouring;
[0007] The control system comprises:
[0008] An image acquisition module, used to obtain image information of bridge block 0, wherein the image information at least includes a top view image and a side view image;
[0009] A coordinate construction module, connected to the image acquisition module, constructs a construction scene and constructs a three-dimensional model of bridge block No. 0 based on the image information, and constructs three-dimensional coordinates and two-dimensional coordinates of the upper surface and end surface of bridge block No. 0 based on the three-dimensional model;
[0010] A linear reference module is used to set at least two reference points on both side edges of the upper surface of bridge block No. 0, so that the reference straight line where the line connecting at least two of the reference points on the same side coincides with the straight line where one side edge of bridge block No. 0 is located, and to set at least two reference points on the top of the facade of the casting template, so that the reference straight line where the line connecting at least two of the reference points on the top of the facade of the casting template coincides with the straight line where the top edge of the facade of the casting template is located;
[0011] An image processing module, connected to the image acquisition module, for acquiring at least one frame of overhead image information and side image information of bridge block 0, and fitting the overhead image information to the two-dimensional coordinate system of the upper surface of bridge block 0 after preprocessing the image, and fitting the side image information to the two-dimensional coordinate system of the end face of bridge block 0, and acquiring the two-dimensional coordinates of each reference point of the image information;
[0012] A coordinate determination module calculates the equation of a reference line located on the same side based on the two-dimensional coordinates of the reference point; draws a reference line on the three-dimensional model based on the equation of the reference line, and determines the coordinates of key points of the casting template in the three-dimensional coordinates;
[0013] The control system is connected to the prestressed concrete cast-in-place continuous beam hanging basket construction equipment, and issues control instructions based on the key point coordinates of the hanging basket. The prestressed concrete cast-in-place continuous beam hanging basket construction equipment responds to the control instructions to adjust the three-dimensional position of the casting template.
[0014] A further solution is that the image processing module includes:
[0015] A grayscale processing unit, used for performing grayscale processing on the image information to obtain a first grayscale image;
[0016] A smoothing processing unit, used for performing smoothing processing on the first grayscale image to obtain a second grayscale image;
[0017] An edge detection unit, used to perform edge detection on the second grayscale image to obtain an edge information image;
[0018] An image fitting unit is used to optimize and fit the straight lines with similar slopes in the edge information graph using the corresponding reference straight lines, retaining two parallel first reference straight lines and a third reference straight line perpendicular to the first reference straight line and the second reference straight line; the first reference straight line and the second reference straight line are the edge straight lines in the length direction of block 0 of the bridge, and the third reference straight line is the top edge straight line of the facade of the casting formwork.
[0019] A further solution is that the image fitting unit is also connected to a threshold setting unit, which is used to set a slope threshold of the edge straight line in the edge information map, and send the edge straight line in the edge information map whose slope is within the slope threshold to the image fitting unit for fitting.
[0020] A further solution is that the coordinate construction module further includes a task tracking unit, a load applying unit and a coordinate optimization unit, wherein the task tracking unit sequentially draws a set number of casting template models on the three-dimensional model based on the construction task or the construction progress, and the position of the latter casting template model is set based on the position of the previous casting template model;
[0021] The load applying unit is used to apply load on each casting formwork model in turn based on construction requirements;
[0022] The coordinate optimization unit optimizes the coordinates of the casting template model based on the settlement value of each casting template model after the load is applied.
[0023] A further solution is that the coordinate construction module further includes a straight line construction unit, which constructs a fourth reference straight line based on a line connecting a key point of the casting template model after each settlement, and a mirror straight line based on the fourth reference straight line and the first reference straight line and / or the second reference straight line;
[0024] The coordinate optimization unit optimizes the coordinates of each of the casting template models based on the mirror line of the fourth reference line, calibrates the casting template based on the optimized coordinates of each of the casting template models, determines the key point coordinates of the casting template in the three-dimensional coordinates, and completes the hoisting positioning of the lower beam based on the main truss control model.
[0025] A further solution is that the main truss control model has a built-in coordinate conversion unit for obtaining the different coordinates of the same key points of several casting templates in the three-dimensional coordinates, and recording the position coordinates of each lower beam corresponding to the casting template, determining the mapping relationship between the key point coordinates of the casting template and the position coordinates of the lower beam, and completing the conversion of the casting template coordinates and the lower beam coordinates based on the mapping relationship.
[0026] A further solution is that the construction process of the main truss control model is: obtaining a large number of lower beam coordinates and the horizontal displacement values of the main truss and the working parameters of the lifting equipment at the coordinates and performing manual expert marking to obtain a number of groups of lower beam coordinate-horizontal displacement value pairs and lower beam coordinate-lifting equipment working parameter pairs; after marking, the lower beam coordinate-horizontal displacement value pairs and the lower beam coordinate-lifting equipment working parameter pairs are sequentially input into the first neural network unit and the second neural network unit for iterative training, and the horizontal displacement value of the main truss and the working parameters of the lifting equipment are output respectively, so as to obtain the main truss control model for inputting the lower beam coordinates and outputting the horizontal displacement value of the main truss and the working parameters of the lifting equipment;
[0027] The control system issues control instructions based on the main truss control model to adjust the horizontal displacement value of the main truss and the operating parameters of the lifting equipment.
[0028] A further solution is that the coordinate construction module also includes a collision simulation unit, which issues control instructions based on the main truss control model to place the casting template models in the virtual scene in sequence according to the key point coordinates and determines whether there is a collision between adjacent casting template models. If there is a collision between adjacent casting template models, the horizontal displacement value of the main truss and the working parameters of the lifting equipment are re-obtained.
[0029] A further solution is that the reference point is an RFID tag, and the image acquisition module also includes a radio frequency identifier for identifying the RFID tag of block 0 of the bridge.
[0030] Compared with the prior art, the present invention has the following beneficial effects:
[0031] The present invention records a prestressed concrete cast-in-place continuous beam hanging basket construction control system, which connects the control system with the prestressed concrete cast-in-place continuous beam hanging basket construction equipment, issues control instructions based on the key point coordinates of the hanging basket, and controls the prestressed concrete cast-in-place continuous beam hanging basket construction equipment to adjust the three-dimensional position of the casting template, thereby ensuring the linear requirements of the concrete cast-in-place continuous beam hanging basket construction.
[0032] The present invention constructs a construction scene and a three-dimensional model of bridge block No. 0, and determines a reference straight line by setting a reference point, so as to fit an edge information graph. When fitting lines, a slope threshold of an edge straight line in the edge information graph is set by a threshold setting unit, and edge straight lines in the edge information graph whose slopes are within the slope threshold are sent to an image fitting unit for fitting, thereby improving the accuracy of the reference straight line.
[0033] Since pouring concrete may cause settlement of the casting formwork during the hanging basket construction process, in the present invention, the position of the already determined casting formwork is also optimized by a coordinate optimization unit. Specifically, a reference straight line is constructed based on a connecting line of a key point of each casting formwork model after settlement, and a mirror line of the reference straight line. The coordinates of each casting formwork model are optimized by the mirror line, and the casting formwork is calibrated based on the optimized coordinates of each casting formwork model, the key point coordinates of the casting formwork in the three-dimensional coordinates are determined, and the hoisting positioning of the lower beam is completed based on the main truss control model.
[0034] The present invention adopts the main truss control model to complete the hoisting and positioning of the lower crossbeam. By inputting the coordinates of the lower crossbeam, the horizontal displacement value of the main truss and the working parameters of the hoisting equipment are output respectively. The main truss control model is iteratively trained to improve the precise positioning of the lower crossbeam, and then the position of the casting formwork is accurately controlled, further ensuring the overall beauty and safety of the bridge. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] The following drawings are only used to illustrate and explain the present invention, and are not used to limit the scope of the present invention, wherein:
[0036] Figure 1 : Schematic diagram of bridge block 0;
[0037] Figure 2 : Schematic diagram of three-dimensional coordinate construction;
[0038] Figure 3 : Schematic diagram of two-dimensional coordinate construction;
[0039] Figure 4 : Schematic diagram of the coordinate optimization of the casting template model;
[0040] Figure 5 : Schematic diagram of system connection of the present invention;
[0041] Figure 6 : Schematic diagram of the image processing module structure;
[0042] Figure 7 : Schematic diagram of the structure of the coordinate building module;
[0043] In the figure: 1. Bridge pier; 2. Bridge block No. 0; 3. Main truss; 4. Casting formwork; 5. External facade; 6. Lower crossbeam; 7. Lifting equipment. DETAILED DESCRIPTION
[0044] In order to make the purpose, technical solution, design method and advantages of the present invention clearer, the present invention is further described in detail by specific embodiments in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0045] like Figure 1 As shown, the present invention provides a prestressed concrete cast-in-place continuous beam hanging basket construction control system, wherein the control system is connected to two prestressed concrete cast-in-place continuous beam hanging basket construction equipment. In order to ensure that the forces on both sides of the bridge block No. 0 2 located on the top of the pier 1 are balanced during the construction process, in this embodiment, the control system simultaneously controls the two prestressed concrete cast-in-place continuous beam hanging basket construction equipment, and the two prestressed concrete cast-in-place continuous beam hanging basket construction equipment are respectively located on both sides of the bridge block No. 0 2, and the hanging basket construction at both ends of the bridge block No. 0 2 is carried out simultaneously. The prestressed concrete cast-in-place continuous beam hanging basket construction equipment comprises: a main truss 3 located on the top of the bridge block No. 0 2 and capable of sliding along the base, a lower crossbeam 6 located at both ends of the bridge block No. 0 2, a casting template 4 located on the lower crossbeam 6, and an external grouting pump; the lower crossbeam 6 is connected to the main truss 3 by a hoisting device 7, one end of the grouting pump is connected to an external concrete mixing device for providing mixing concrete, and the other end of the grouting pump can extend to the inside of the casting area formed by the casting template 4 to complete the concrete casting;
[0046] like Figure 5 As shown, the control system includes:
[0047] An image acquisition module is used to obtain image information of bridge block 0 2, wherein the image information includes at least a top view image and a side view image, wherein the image acquisition process can be completed by shooting with the aid of a drone, the top view image is used to obtain a surface image of bridge block 0 2, and the side view image is used to obtain an end face image of bridge block 0 2;
[0048] The coordinate construction module is connected to the image acquisition module, constructs the construction scene and constructs the three-dimensional model of the bridge block 0 2 based on the image information, and can place the three-dimensional model in the construction scene, and construct the three-dimensional coordinates and the two-dimensional coordinates of the upper surface and end surface of the bridge block 0 2 based on the three-dimensional model, such as Figure 2 The xyz three-dimensional coordinate system shown in Figure 3 The x shown 1 y 1 Coordinate system and x 2 y 2 Coordinate system;
[0049] A linear reference module is used to set at least two reference points on both side edges of the upper surface of bridge block 0 2, so that the reference straight line where the line connecting at least two of the reference points on the same side coincides with the straight line where one side edge of bridge block 0 2 is located, and to set at least two reference points on the top of the facade 5 of the casting template 4, so that the reference straight line where the line connecting at least two of the reference points on the top of the facade 5 coincides with the straight line where the top edge of the facade 5 is located; in this embodiment, at least three groups of reference points need to be set, and the three groups of reference points can constitute three reference straight lines, wherein the reference points are RFID tags, and the image acquisition module also includes a radio frequency identifier for identifying the RFID tag of bridge block 0 2;
[0050] An image processing module, connected to the image acquisition module, is used to obtain at least one frame of overhead image information and side image information of bridge block 0 2, and fit the overhead image information to the two-dimensional coordinate system of the upper surface of bridge block 0 2 after preprocessing the image, and fit the side image information to the two-dimensional coordinate system of the end face of bridge block 0 2, and obtain the two-dimensional coordinates of each reference point of the image information;
[0051] The coordinate determination module calculates the reference straight line equation located on the same side based on the two-dimensional coordinates of the reference point; draws the reference straight line on the three-dimensional model based on the reference straight line equation, and determines the key point coordinates of the casting template 4 in the three-dimensional coordinates; in this embodiment, the key point coordinates are the coordinates of the vertices on both sides of the top of the facade 5, such as Figure 2 As shown, the three reference straight lines are straight line L 1 , straight line L 2 and the straight line L 3 , then the coordinates of the vertices on both sides of the top of the facade 5 are K1 (m, n, h) and K2 (m, 0, h), where m is the product of the number of hanging baskets and the width of the casting template 4. For example, if the width of the casting template 4 is 5 meters, then when the basket is hung for the second time, m is 10, n is the width of the facade 5, and h is the elevation of the bridge block 2 No. 0;
[0052] The control system is connected to the prestressed concrete cast-in-place continuous beam hanging basket construction equipment, and issues control instructions based on the key point coordinates of the hanging basket. The prestressed concrete cast-in-place continuous beam hanging basket construction equipment responds to the control instructions to adjust the three-dimensional position of the casting template 4. Since the casting template 4 is fixed on the lower crossbeam 6, the position of the casting template 4 can be determined by intervening in the position of the lower crossbeam 6 through the control system.
[0053] like Figure 6As shown, the image processing module includes: a grayscale processing unit, which is used to perform grayscale processing on the image information to obtain a first grayscale image; a smoothing processing unit, which is used to perform smoothing on the first grayscale image to obtain a second grayscale image; an edge detection unit, which is used to perform edge detection on the second grayscale image to obtain an edge information image; an image fitting unit, which is used to optimize the fitting of straight lines with similar slopes in the edge information image using the corresponding reference straight lines, retaining two parallel first reference straight lines and second reference straight lines and a third reference straight line perpendicular to the first reference straight line and the second reference straight line; the first reference straight line and the second reference straight line are edge straight lines in the length direction of the bridge block 0 2, and the third reference straight line is the top edge straight line of the facade 5 of the casting formwork 4. The first reference straight line and the second reference straight line are respectively aligned with the straight line L 1 , straight line L 2 Coincident, the third reference straight line and straight line L 3 In the above, the corresponding reference straight line refers to the edge information of the image retained after edge extraction of the image. In this embodiment, the edge information mainly refers to the edge line of bridge block 0 2 or the edge line of facade 5, and the straight line corresponding to the edge line of bridge block 0 2 is straight line L. 1 , straight line L 2 , the straight line corresponding to the edge line of the facade 5 is the straight line L 3 .
[0054] like Figure 6 As shown, the image fitting unit is also connected to a threshold setting unit for setting a slope threshold of the edge straight line in the edge information graph, and sending the edge straight line whose slope is within the slope threshold in the edge information graph to the image fitting unit for fitting. Figure 7 As shown, the coordinate construction module also includes a task tracking unit, a load applying unit and a coordinate optimization unit. The task tracking unit sequentially draws a set number of casting template models on the three-dimensional model based on the construction task or construction progress, and the position of the latter casting template model is set based on the position of the previous casting template model; the load applying unit is used to sequentially apply loads to each casting template model based on construction requirements; the coordinate optimization unit optimizes the coordinates of the casting template model based on the settlement value after the load is applied to each casting template model. The coordinate construction module also includes a straight line construction unit, such as Figure 4 As shown, a fourth reference straight line L is constructed based on a line connecting a key point of the casting template model after each settlement. 4 , and the fourth reference straight line L 4 The coordinate optimization unit is based on the fourth reference straight line L 4The coordinates of each casting template model are optimized by the mirror line, and the casting template 4 is calibrated based on the optimized coordinates of each casting template model, the key point coordinates of the casting template 4 in the three-dimensional coordinates are determined, and the hoisting positioning of the lower cross beam 6 is completed based on the main truss control model. Figure 4 An example of the coordinate optimization process: Assume that four pouring operations are required on one side of bridge block 0, and define the coordinates of a vertex at the top of the first pouring template 4 as (0, -h 1 ), then the coordinates of a vertex on the top of the second casting template 4 are (m, -h 1 ), the coordinates of a vertex on the top of the third casting template 4 are (2m, -h 1 ), where h 1 is the settlement amount after the external load is applied to the casting formwork 4. Since the external load applied by each casting formwork 4 is the same, its settlement amount h 1 The same is true, so the fourth reference straight line L 4 Parallel to the first reference straight line and / or the second reference straight line, since the fourth reference straight line L is used in this embodiment 4 The coordinates of the mirror image of the first reference straight line and / or the second reference straight line are optimized, so that the coordinates of a vertex on the top of the first casting template 4 are optimized to (0, h 1 ), the coordinates of a vertex on the top of the second casting template 4 are optimized as (m, h 1 ), the coordinates of a vertex on the top of the third casting template 4 are optimized to (2m, h 1 ).
[0055] like Figure 1 and Figure 7As shown, the main truss control model has a built-in coordinate conversion unit for obtaining different coordinates of the same key points of several casting templates 4 in the three-dimensional coordinates, and recording the position coordinates of each lower beam 6 corresponding to the casting template 4, determining the mapping relationship between the key point coordinates of the casting template 4 and the position coordinates of the lower beam 6, and completing the conversion of the coordinates of the casting template 4 and the coordinates of the lower beam 6 based on the mapping relationship. The construction process of the main truss control model is as follows: a large number of coordinates of the lower beam 6 and the horizontal displacement values of the main truss 3 and the working parameters of the lifting equipment under the coordinates are obtained and marked by artificial experts to obtain a number of pairs of lower beam coordinates-horizontal displacement values and pairs of lower beam coordinates-working parameters of the lifting equipment; after marking, the pairs of lower beam coordinates-horizontal displacement values and the pairs of lower beam coordinates-working parameters of the lifting equipment are sequentially input into the first neural network unit and the second neural network unit for iterative training, and the horizontal displacement values of the main truss 3 and the working parameters of the lifting equipment 7 are output respectively, so as to obtain a main truss control model for inputting the coordinates of the lower beam 6 and outputting the horizontal displacement values of the main truss 3 and the working parameters of the lifting equipment 7; the control system issues a control instruction based on the main truss control model to adjust the horizontal displacement value of the main truss 3 and the working parameters of the lifting equipment 7. Among them, the first neural network unit and the second neural network unit are both deep learning models, and in this embodiment, they are DBN network structures based on RBM, which are stacked by two RBMs, and an input layer is added to the second RBM. For the first neural network unit and the second neural network unit, during model training, each RBM is trained separately; the hidden layer output of the previous RBM is connected to the input layer input and used as the input of the next RBM. For example, the previous RBM inputs the coordinates of the lower beam 6 and outputs the horizontal displacement value of the main truss 3. Then the horizontal displacement value of the main truss 3 is input again as the hidden layer output of the previous RBM into the next RBM, and finally the next RBM outputs the horizontal displacement value and the working parameters of the hoisting equipment 7. In this embodiment, the working parameters of the hoisting equipment 7 refer to the number of turns of the hoisting machine of the hoisting equipment 7, etc. The coordinate construction module also includes a collision simulation unit, which issues a control instruction based on the main truss control model to place the casting template model in the virtual scene in accordance with the coordinates of the key points and judge whether there is a collision between adjacent casting template models. If there is a collision between adjacent casting template models, the horizontal displacement value of the main truss 3 and the working parameters of the hoisting equipment 7 are re-acquired.
[0056] The embodiments of the present invention have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and changes will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The selection of terms used herein is intended to best explain the principles of the embodiments, practical applications, or technical improvements in the market, or to enable other persons of ordinary skill in the art to understand the embodiments disclosed herein.
Claims
1. A prestressed concrete cast-in-place continuous beam hanging basket construction control system, characterized in that: The control system is connected to at least two prestressed concrete cast-in-place continuous beam hanging basket construction devices, which are respectively located on both sides of the bridge block No. 0 and are used to simultaneously perform hanging basket construction at both ends of the bridge block No.
0. The prestressed concrete cast-in-place continuous beam hanging basket construction devices at least include: The movable main truss located at the top of the bridge block No. 0, the lower crossbeams located at both ends of the bridge block No. 0, the casting template located on the lower crossbeam, and the external grouting pump; the lower crossbeam is connected to the movable main truss through a hoisting device, one end of the grouting pump is connected to an external concrete mixing device for providing mixing concrete, and the other end of the grouting pump can be extended to the inside of the casting area formed by the casting template to complete the concrete pouring; The control system comprises: An image acquisition module, used to obtain image information of bridge block 0, wherein the image information at least includes a top view image and a side view image; A coordinate construction module, connected to the image acquisition module, constructs a construction scene and constructs a three-dimensional model of bridge block No. 0 based on the image information, and constructs three-dimensional coordinates and two-dimensional coordinates of the upper surface and end surface of bridge block No. 0 based on the three-dimensional model; A linear reference module is used to set at least two reference points on both side edges of the upper surface of bridge block No. 0, so that the reference straight line where the line connecting at least two of the reference points on the same side coincides with the straight line where one side edge of bridge block No. 0 is located, and to set at least two reference points on the top of the facade of the casting template, so that the reference straight line where the line connecting at least two of the reference points on the top of the facade of the casting template coincides with the straight line where the top edge of the facade of the casting template is located; An image processing module, connected to the image acquisition module, for acquiring at least one frame of overhead image information and side image information of bridge block 0, and fitting the overhead image information to the two-dimensional coordinate system of the upper surface of bridge block 0 after preprocessing the image, and fitting the side image information to the two-dimensional coordinate system of the end face of bridge block 0, and acquiring the two-dimensional coordinates of each reference point of the image information; A coordinate determination module calculates the equation of a reference line located on the same side based on the two-dimensional coordinates of the reference point; draws a reference line on the three-dimensional model based on the equation of the reference line, and determines the coordinates of key points of the casting template in the three-dimensional coordinates; The control system is connected to the prestressed concrete cast-in-place continuous beam hanging basket construction equipment, and issues control instructions based on the key point coordinates of the hanging basket. The prestressed concrete cast-in-place continuous beam hanging basket construction equipment responds to the control instructions to adjust the three-dimensional position of the casting template.
2. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 1, characterized in that: The image processing module comprises: A grayscale processing unit, used for performing grayscale processing on the image information to obtain a first grayscale image; A smoothing processing unit, used for performing smoothing processing on the first grayscale image to obtain a second grayscale image; An edge detection unit, used to perform edge detection on the second grayscale image to obtain an edge information image; An image fitting unit is used to optimize and fit the straight lines with similar slopes in the edge information graph using the corresponding reference straight lines, retaining two parallel first reference straight lines and a third reference straight line perpendicular to the first reference straight line and the second reference straight line; the first reference straight line and the second reference straight line are the edge straight lines in the length direction of block 0 of the bridge, and the third reference straight line is the top edge straight line of the facade of the casting formwork.
3. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 2, characterized in that: The image fitting unit is also connected to a threshold setting unit for setting a slope threshold of the edge straight line in the edge information graph, and sending the edge straight line in the edge information graph whose slope is within the slope threshold to the image fitting unit for fitting.
4. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 3, characterized in that: The coordinate construction module also includes a task tracking unit, a load applying unit and a coordinate optimization unit. The task tracking unit sequentially draws a set number of casting template models on the three-dimensional model based on the construction task or construction progress, and the position of the latter casting template model is set based on the position of the previous casting template model. The load applying unit is used to apply load on each casting formwork model in turn based on construction requirements; The coordinate optimization unit optimizes the coordinates of the casting template model based on the settlement value of each casting template model after the load is applied.
5. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 4, characterized in that: The coordinate construction module further comprises a straight line construction unit, which constructs a fourth reference straight line and a mirror straight line of the fourth reference straight line and the first reference straight line and / or the second reference straight line based on a line connecting a key point of each settled casting template model; The coordinate optimization unit optimizes the coordinates of each of the casting template models based on the mirror line of the fourth reference line, calibrates the casting template based on the optimized coordinates of each of the casting template models, determines the key point coordinates of the casting template in the three-dimensional coordinates, and completes the hoisting positioning of the lower beam based on the main truss control model.
6. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 5, characterized in that: The main truss control model has a built-in coordinate conversion unit, which is used to obtain the different coordinates of the same key points of several casting templates in the three-dimensional coordinates, and record the position coordinates of each lower beam corresponding to the casting template, determine the mapping relationship between the key point coordinates of the casting template and the position coordinates of the lower beam, and complete the conversion of the casting template coordinates and the lower beam coordinates based on the mapping relationship.
7. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 6, characterized in that: The construction process of the main truss control model is as follows: a large number of lower beam coordinates and the horizontal displacement values of the main truss and the working parameters of the lifting equipment at the coordinates are obtained and marked by manual experts to obtain a number of pairs of lower beam coordinates-horizontal displacement values and pairs of lower beam coordinates-working parameters of the lifting equipment; after marking, the pairs of lower beam coordinates-horizontal displacement values and the pairs of lower beam coordinates-working parameters of the lifting equipment are sequentially input into the first neural network unit and the second neural network unit for iterative training, and the horizontal displacement values of the main truss and the working parameters of the lifting equipment are output respectively, so as to obtain the main truss control model for inputting the lower beam coordinates and outputting the horizontal displacement values of the main truss and the working parameters of the lifting equipment; The control system issues control instructions based on the main truss control model to adjust the horizontal displacement value of the main truss and the operating parameters of the lifting equipment.
8. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 7, characterized in that: The coordinate construction module also includes a collision simulation unit, which issues control instructions based on the main truss control model to place the casting template models in the virtual scene in sequence according to the key point coordinates and determines whether there is a collision between adjacent casting template models. If there is a collision between adjacent casting template models, the horizontal displacement value of the main truss and the working condition parameters of the lifting equipment are re-obtained.
9. A prestressed concrete cast-in-place continuous beam hanging basket construction control system according to claim 1, characterized in that: The reference point is an RFID tag, and the image acquisition module also includes a radio frequency identifier for identifying the RFID tag of bridge block 0.