A crane operation path planning method with dynamic aisle yard

By dynamically adjusting the aisle spacing in the yard and optimizing the path planning of the crane, the problem of low dynamic aisle utilization in the yard is solved, the picking efficiency and space utilization are improved, and the intelligence level of the yard is improved.

CN118569467BActive Publication Date: 2024-10-25SHENZHEN CHANGYU IND OF DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411064699.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-25
Estimated Expiration
2044-08-05

AI Technical Summary

Technical Problem

The low utilization rate of dynamic aisles in the yard affects space utilization and crane picking efficiency.

Method used

A crane operation path planning method with a dynamic aisle yard is used to optimize the crane's picking path and time by adjusting the aisle spacing, setting up a buffer zone for items entering and exiting the warehouse, determining the optimal aisle, and controlling the movement paths of the crane trolley and hook.

Benefits of technology

It improves the space utilization rate of the yard and the picking efficiency of the crane, significantly reduces the picking time, and improves the intelligence level of the yard.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118569467B_ABST
    Figure CN118569467B_ABST
Patent Text Reader

Abstract

The present invention relates to a crane operation path planning method with a dynamic aisle yard in the field of intelligent lifting and picking technology, comprising the following steps: S1, setting a yard with a dynamic aisle; S2, determining the current picking position and the optimal aisle according to the order of items listed in the customer order; S3, adjusting the current dynamic aisle to the optimal aisle; S4, controlling the crane to complete the picking of an item from the in-and-out buffer zone via the current optimal aisle from the current picking position, return to the in-and-out buffer zone, and calculate the time taken by the crane to complete the current item picking; S5, updating the number of items and customer orders at the current picking position, updating the picking path and the time taken; S6, if the customer order is empty, outputting the picking path and the time taken; if the customer order is not empty, returning to S2 to continue picking. The crane operation path planning method improves the picking efficiency of the yard crane while ensuring the saving of yard space.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of intelligent lifting and picking, and in particular to a method for planning a crane operation path with a dynamic aisle yard. Background Art

[0002] It is well known that existing storage devices such as document cabinets and shelves can place shelves close to each other side by side to save space. When a row of shelves needs to be picked up or placed, the shelves on both sides of the shelves only need to be moved outward to free up aisles. However, in actual applications of yard cranes, aisles are rarely used in yards, especially dynamic aisles, which is bound to affect the space utilization of the yard and the picking efficiency of the yard crane. Therefore, it is urgent to find a crane operation path planning method with a dynamic aisle yard. Summary of the invention

[0003] In order to overcome the deficiencies in the background technology and solve the existing technical problems, the present invention discloses a crane operation path planning method with a dynamic aisle yard, which improves the picking efficiency of the yard crane while ensuring the saving of yard space.

[0004] In order to achieve the above-mentioned invention object, the present invention adopts the following technical scheme:

[0005] A crane operation path planning method for a yard with dynamic aisles includes the following steps: S1, setting a dynamic aisle capable of adjusting any aisle spacing to adapt to the crane hook hoisting through the yard, and setting a corner of the yard as an item in-and-out buffer zone; S2, determining the current picking bay and the optimal aisle for the crane to reach the bay according to the order of items listed in the customer order; S3, adjusting the current dynamic aisle to the optimal aisle, and controlling the crane trolley to move to the outer end of the dynamic aisle accordingly; S4, controlling the crane to complete the picking of an item from the in-and-out buffer zone via the current optimal aisle, from the current picking bay, and return to the in-and-out buffer zone, and calculating the time taken by the crane to complete the picking of the current item; S5, updating the number of items and customer orders at the current picking bay, and updating the picking path and the time taken; S6, if the customer order is empty, outputting the picking path and the time taken; if the customer order is not empty, returning to S2 to continue picking.

[0006] Furthermore, in S1, a supporting trolley is provided at the bottom of each bay in the yard to support all goods stacked vertically above, and the supporting trolley can be moved and positioned in a direction perpendicular to the aisle.

[0007] Further, in S2, a bay is randomly selected from the bays where items are currently to be picked as the current picking bay, and its coordinates are used to update the coordinates of the current picking bay. At the same time, the row number of the current picking bay is the row number of the optimal aisle.

[0008] Further, in S3, the current dynamic aisle is adjusted to the optimal aisle, and the row number Aisle_current of the current dynamic aisle is updated; it is determined whether the current aisle is at the optimal aisle. If the current aisle is at the optimal aisle, the current aisle is no longer adjusted, and the row number Aisle_current of the current aisle is no longer changed; otherwise, if the row number of the current aisle is less than the row number of the optimal aisle, all rows between the current aisle and the row number of the optimal aisle plus 1 are added, and only the first row to the current picking position minus 1 in these rows The bay position is moved to the current aisle by the distance between adjacent rows; if the row number of the current aisle is greater than the row number of the optimal aisle, then all rows between the row number of the optimal aisle minus 1 and the current aisle, and only the bays from the 1st column to the column number minus 1 of the current picking bay are moved to the current aisle by the distance between adjacent rows; finally, the row number of the optimal aisle, Aisle_current, is updated with the row number of the optimal aisle, Aisle_optimal, that is, Aisle_current=Aisle_optimal.

[0009] Further, in S4, the adjusted dynamic aisle enables the hook to directly reach the current picking position in the direction of the trolley's movement, and enables the hook to run at a height one level above the item layer height of the current picking position.

[0010] Further, the inspection of the crane operation path planning method comprises the following steps:

[0011] The first step is to establish a mathematical model of the time it takes for a crane with a dynamic aisle yard to complete order item picking, as follows;

[0012] (1)

[0013] (2)

[0014] (3)

[0015] (4)

[0016] Among them, formula (1) is the time it takes for the crane to complete the order item picking; formula (3) and formula (4) are constraint conditions, specifically: formula (3) represents the quantity constraint of the items to be picked; formula (4) is the value range constraint of the decision variable;

[0017] j represents the number assigned to the picked item, j∈{1,2,…, Sn 1 + Sn 2 +…+ Sn m}; t j represents the time taken to complete the picking of the jth item; pjx 、p jy and p jz represents the three-dimensional coordinates of the jth item; v x 、v y and v z They represent the average operating speed of the crane trolley, the average operating speed of the crane trolley and the average operating speed of the crane hook respectively; s j Indicates whether the jth item is picked, if yes, s j =1, otherwise s j =0;

[0018] The second step is to initialize the parameters: the height of a single item in the yard Hgi, where m is the category number of the item to be picked, the coordinates of the item outbound buffer P0 (0, 0, 0), the horizontal and vertical distances between the item in the first row and the outbound buffer are Dx and Dy respectively, the distance between adjacent rows is Dh, the distance between two adjacent bays in the same row and the same layer is Dv, the row number of the current aisle Aisle_current, the width of the dynamic aisle Daisle, the name Goodname, category Goodsort and quantity N of the items stored in each bay in the yard, the customer orders to be picked Customerorders, the picking route Route_total and its time Time_total;

[0019] The third step is to determine the current picking position coordinates Location_current and the optimal aisle number Aisle_optimal where the crane can reach the position;

[0020] Step 4: Adjust the current aisle to the optimal aisle and update the row number Aisle_current of the current aisle.

[0021] Step 5: The crane completes the picking of an item from the current picking position via the current aisle;

[0022] Step 6: Update the number of items in the current picking position, Item_num;

[0023] Step 7: Update customer orders Customerorders;

[0024] Step 8: Update the picking route Route_total and its time Time_total;

[0025] Step 9. If the customer order Customerorders is not empty, return to step 3; otherwise, output the picking route Route_total and its time Time_total.

[0026] Furthermore, in the sixth step, after completing the picking of the items at the current picking position, the number of items at this position should be updated to Item_num=Item_num-1.

[0027] Furthermore, in the seventh step, after completing the picking of the item at the current picking position, the customer order Customerorders should be updated, that is, the first picked item in the customer order Customerorders should be deleted.

[0028] Due to the adoption of the above-mentioned technical solution, the present invention has the following beneficial effects:

[0029] The crane operation path planning method for a stockpile with dynamic aisles disclosed in the present invention introduces dynamic aisles into the stockpile, which not only improves the space utilization rate of the stockpile, but also effectively overcomes the disadvantage of low picking efficiency, greatly improves the efficiency of stockpile cranes in picking items, and further improves the intelligence level of stockpile cranes in a digital way. It is a vivid example of digital empowerment of the traditional lifting equipment industry, and has a good demonstration and leading role in the digital transformation and upgrading of lifting equipment in related fields. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a schematic diagram of the planning process of the present invention;

[0031] Figure 2 is a layout diagram of items in a yard with dynamic aisles before picking in an embodiment;

[0032] Figure 3 It is a dynamic aisle layout diagram when an item is picked according to the method of the present invention in an embodiment. DETAILED DESCRIPTION

[0033] The technical solution of the present invention will be described below in conjunction with the accompanying drawings in the embodiments of the present invention:

[0034] Combined with Figure 1 The crane operation path planning method with a dynamic aisle yard comprises the following steps:

[0035] S1. Set up a dynamic aisle that can adjust the distance between any aisles to adapt to the yard where the crane hook passes through, and set a corner of the yard as a buffer zone for goods entering and leaving the warehouse; according to needs, a supporting trolley is set at the bottom of each bay in the yard to support all the goods piled vertically above. The supporting trolley can move and position in a direction perpendicular to the aisle. By controlling the approach and distance of the supporting trolleys in adjacent rows, dynamic aisles can be eliminated and generated, so that only one dynamic aisle spacing can be reserved for picking and selecting goods. Compared with the traditional method of setting a picking aisle between each row of goods, it greatly saves space;

[0036] S2. Determine the current picking position and the optimal aisle that the crane can reach the position according to the order of the items listed in the customer order; if multiple picking positions have the listed items to be picked, then a position can be randomly selected from the positions with items to be picked as the current picking position, and its coordinates are used to update the coordinates of the current picking position. At the same time, the row number of the current picking position is the row number of the optimal aisle;

[0037] S3. Adjust the current dynamic aisle to the optimal aisle, and control the crane trolley to move to the outer end of the dynamic aisle to ensure synchronization, or the optimal aisle adjustment time is less than the crane trolley movement time to prevent the aisle adjustment from affecting the picking efficiency; adjust the current dynamic aisle to the optimal aisle, and update the row number Aisle_current where the current dynamic aisle is located; determine whether the current aisle is at the optimal aisle. If the current aisle is at the optimal aisle, the current aisle will no longer be adjusted, and the row number Aisle_current where the current aisle is located will no longer be changed; otherwise, if the row number of the current aisle is less than the row number of the optimal aisle, all rows between the current aisle and the row number of the optimal aisle plus 1, and only the first row to the current picking row among these rows The pick position at the column number minus 1 is moved to the current aisle by the distance of the adjacent row spacing; if the row number of the current aisle is greater than the row number of the optimal aisle, all rows between the optimal aisle number minus 1 and the current aisle, and only the pick positions from the first column to the column number minus 1 of the current picking position are moved to the current aisle by the distance of the adjacent row spacing; in this way, it is not necessary to move the entire row to form a complete channel, but only the aisle needs to be able to reach the pick position from one end, thereby reducing the number of movement controls of the supporting trolley. Finally, the row number Aisle_current of the current aisle is updated with the row number Aisle_optimal of the optimal aisle, that is, Aisle_current=Aisle_optimal;

[0038] S4, control the crane to complete the picking of an item from the in-and-out buffer through the current optimal aisle, from the current picking position, and return to the in-and-out buffer, and calculate the time it takes for the crane to complete the picking of the current item; the adjusted dynamic aisle enables the hook to directly reach the current picking position in the direction of the trolley movement, and enables the hook to operate at a height one level higher than the item layer height of the current picking position, thereby saving the time of the hook moving vertically;

[0039] S5. Update the number of items and customer orders at the current picking location, and update the picking path and its duration;

[0040] S6. If the customer order is empty, output the picking path and its duration; if the customer order is not empty, return to S2 to continue picking.

[0041] In order to verify the effect of the present invention, the inspection of the crane operation path planning method is designed to include the following steps:

[0042] The first step is to establish a mathematical model of the time it takes for a crane with a dynamic aisle yard to complete order item picking, as follows;

[0043] (1)

[0044] (2)

[0045] (3)

[0046] (4)

[0047] Among them, formula (1) is the time it takes for the crane to pick the order items; formula (3) and formula (4) are constraint conditions, specifically: formula (3) represents the quantity constraint of the items to be picked; formula (4) is the range constraint of the decision variable;

[0048] j represents the number assigned to the picked item, j∈{1,2,…, Sn 1 + Sn 2 +…+ Sn m}; t j represents the time taken to complete the picking of the jth item; p jx 、p jy and p jz represents the three-dimensional coordinates of the jth item; v x 、v y and v z They represent the average operating speed of the crane trolley, the average operating speed of the crane trolley and the average operating speed of the crane hook respectively; s j Indicates whether the jth item is picked, if yes, s j =1, otherwise s j =0;

[0049] The second step is to initialize the parameters: the height of a single item in the yard Hgi, where m is the category number of the item to be picked, the coordinates of the item outbound buffer P0 (0, 0, 0), the horizontal and vertical distances between the item in the first row and the outbound buffer are Dx and Dy respectively, the distance between adjacent rows is Dh, the distance between two adjacent bays in the same row and the same layer is Dv, the row number of the current aisle Aisle_current, the width of the dynamic aisle Daisle, the name Goodname, category Goodsort and quantity N of the items stored in each bay in the yard, the customer orders to be picked Customerorders, the picking route Route_total and its time Time_total;

[0050] The third step is to determine the current picking position coordinates Location_current and the optimal aisle number Aisle_optimal where the crane can reach the position;

[0051] Step 4: Adjust the current aisle to the optimal aisle and update the row number Aisle_current of the current aisle.

[0052] Step 5: The crane completes the picking of an item from the current picking position via the current aisle;

[0053] Step 6: Update the number of items in the current picking position, Item_num; specifically, after completing the picking of the items in the current picking position, the number of items in the position should be updated to Item_num=Item_num-1;

[0054] Step 7: Update the customer order Customerorders; specifically, after completing the picking of the current picking position, the first picked item in the customer order Customerorders1 should be deleted;

[0055] Step 8: Update the picking route Route_total and its time Time_total;

[0056] Step 9. If the customer order Customerorders is not empty, return to step 3; otherwise, output the picking route Route_total and its time Time_total.

[0057] Implement the method of the present invention to solve practical problems, and use the above method to find the optimal solution or suboptimal solution that meets the constraints;

[0058] According to the above technical solution, an example is given with the order picking of yard items in a manufacturing enterprise as the application background. The experiment is carried out on the Win10 system platform, a 3.7GHz Intel processor, 4GB memory and Matlab R2014b development environment. The yard and crane related parameters are: the yard specifications are 30 rows and 40 columns, and the initial layout of the yard items is as follows: Figure 2 As shown in the figure; the coordinates of the outbound buffer area are P0 (0, 0, 0). In order to take into account the picking efficiency of each item, the items in the yard are placed in an alternating mixed mode, that is, each item occupies a separate bay in each row, and different types of items are stacked in two adjacent bays, and the size of each bay is the same;

[0059] There are currently 8 types of items stored in the yard, and the height of each item is shown in Table 1 below:

[0060] type A B C D E F G H Height (m) 0.30 0.90 0.70 0.80 0.46 0.34 0.68 0.26

[0061] The horizontal and vertical distances between the first row and the first column of the first row and the outbound buffer are Dx = 0.4m and Dy = 0.5m respectively. The distance between two adjacent rows is Dh = 1.4m. The row number of the current aisle is Aisle_current = 1. The width of the dynamic aisle is equal to Dh. The distance between two adjacent bays in the same row and the same floor is Dv = 0.2m. The average operating speed of the crane trolley is v x Average running speed of crane trolley v y and the average operating speed of the crane hook v z They are 30m / min, 40m / min and 8m / min respectively;

[0062] The quantity information of the items to be picked is shown in Table 2 below:

[0063] type A B D F G H quantity 69 57 87 50 210 360

[0064] The results are shown in Table 3 below:

[0065] method Picking time (h) Method of the present invention 56.41 Traditional methods 61.96

[0066] Regarding the yard item picking embodiment, Figure 3 The change of the dynamic aisle in the picking process of the yard with dynamic aisles is shown, that is, when picking items at a certain position, the controller drives the actuator, that is, drives the supporting trolley, and dynamically adjusts the aisle to the optimal aisle, so that the hook of the yard crane can reach the position to be picked directly with the minimum lifting distance through the optimal aisle located in the running direction of the trolley, thereby achieving the purpose of reducing the time consumption of picking; further, it can be seen from the comparison table 3 that the traditional picking method without dynamic aisles is significantly lower than the method of the present invention in picking efficiency. The reason for this is that the dynamic aisle makes it unnecessary for the hook of the yard crane to rise to the highest height of the yard during the picking process, thereby saving precious time for it to reach the position to be picked as soon as possible; in summary, the reason why the method of the present invention performs superiorly is that: the dynamic aisle is introduced into the yard, and the hook of the yard crane can use the dynamic aisle to reach the position to be picked without obstacles without unnecessary lifting, which plays a key role in improving the picking efficiency of the yard crane.

[0067] The parts of the present invention that are not described in detail are prior art. It is obvious to those skilled in the art that the present invention is not limited to the details of the above-mentioned exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or basic characteristics of the present invention. Therefore, no matter from which point of view, the above-mentioned embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is limited by the attached claims rather than the above description. Therefore, it is intended to include all changes within the meaning and scope of the equivalent elements of the claims in the present invention, and any figure marks in the claims should not be regarded as limiting the content of the claims involved.

Claims

1. A crane operation path planning method with a dynamic aisle yard, characterized by: The following steps are involved: S1. Set up a dynamic aisle that can adjust the spacing of any aisles to accommodate the yard through which the crane hook passes, and set a corner of the yard as a buffer zone for goods entering and leaving the warehouse; set a supporting trolley at the bottom of each bay in the yard to support all the goods piled vertically above. The supporting trolley can move and position in a direction perpendicular to the aisle. By controlling the approach and distance of the supporting trolleys in adjacent rows, dynamic aisles can be eliminated and generated, so that only one dynamic aisle spacing can be reserved for picking and selecting goods; S2. Determine the current picking position and the optimal aisle that the crane can reach the position according to the order of the items listed in the customer order; randomly select a position from the positions of the items to be picked as the current picking position, and use its coordinates to update the coordinates of the current picking position. At the same time, the row number of the current picking position is the row number of the optimal aisle; S3. Adjust the current dynamic aisle to the optimal aisle, and control the crane trolley to move to the outer end of the dynamic aisle accordingly; adjust the current dynamic aisle to the optimal aisle, and update the row number Aisle_current where the current dynamic aisle is located; determine whether the current aisle is at the optimal aisle. If the current aisle is at the optimal aisle, the current aisle will no longer be adjusted, and the row number Aisle_current where the current aisle is located will no longer be changed; otherwise, if the row number where the current aisle is located is less than the row number where the optimal aisle is located, all rows between the current aisle and the row number where the optimal aisle is located plus 1, and only the bays from the 1st column to the column number minus 1 where the current picking bay is located in these rows are moved one relative position to the current aisle. The distance between adjacent rows; if the row number of the current aisle is greater than the row number of the optimal aisle, then all rows between the row number of the optimal aisle minus 1 and the current aisle, and only the cells from the first column to the column number minus 1 of the current picking position, are moved to the current aisle by the distance between adjacent rows; in this way, it is not necessary to move the entire row to form a complete channel, but only the aisle needs to be able to reach the picking position from one end, thereby reducing the number of movement controls of the supporting trolley; finally, the row number of the optimal aisle, Aisle_current, is updated with the row number of the optimal aisle, Aisle_optimal, that is, Aisle_current=Aisle_optimal; S4, control the crane to pick an item from the inbound and outbound buffer through the current optimal aisle, from the current picking position, return to the inbound and outbound buffer, and calculate the time it takes for the crane to complete the current item picking; S5. Update the number of items and customer orders at the current picking location, and update the picking path and its duration; S6. If the customer order is empty, output the picking path and its duration; if the customer order is not empty, return to S2 to continue picking.

2. The crane operation path planning method with a dynamic aisle yard according to claim 1 is characterized by: In S4, the adjusted dynamic aisle enables the hook to reach the current picking position directly in the direction of the trolley's movement, and enables the hook to run at a height one level above the item layer height of the current picking position.

3. The crane operation path planning method with a dynamic aisle yard according to claim 1 is characterized by: The inspection of the crane operation path planning method comprises the following steps: The first step is to establish a mathematical model of the time it takes for a crane with a dynamic aisle yard to complete order item picking, as follows; (1) (2) (3) (4) Among them, formula (1) is the time it takes for the crane to complete the order item picking; formula (3) and formula (4) are constraint conditions, specifically: formula (3) represents the quantity constraint of the items to be picked; formula (4) is the value range constraint of the decision variable; j represents the number assigned to the picked item, j∈{1,2,…, Sn1+ Sn2+…+ Sn m };t j represents the time taken to complete the picking of the jth item; p jx 、p jy and p jz represents the three-dimensional coordinates of the jth item; v x 、v y and v z They represent the average operating speed of the crane trolley, the average operating speed of the crane trolley and the average operating speed of the crane hook respectively; s j Indicates whether the jth item is picked, if yes, s j =1, otherwise s j =0; The second step is to initialize the parameters: the height of a single item in the yard Hgi, where m is the category number of the item to be picked, the coordinates of the item outbound buffer P0 (0, 0, 0), the horizontal and vertical distances between the item in the first row and the outbound buffer are Dx and Dy respectively, the distance between adjacent rows is Dh, the distance between two adjacent bays in the same row and the same layer is Dv, the row number of the current aisle Aisle_current, the width of the dynamic aisle Daisle, the name Goodname, category Goodsort and quantity N of the items stored in each bay in the yard, the customer orders to be picked Customerorders, the picking route Route_total and its time Time_total; The third step is to determine the current picking position coordinates Location_current and the optimal aisle number Aisle_optimal where the crane can reach the position; Step 4: Adjust the current aisle to the optimal aisle and update the row number Aisle_current of the current aisle. Step 5: The crane completes the picking of an item from the current picking position via the current aisle; Step 6: Update the number of items in the current picking position, Item_num; Step 7: Update customer orders Customerorders; Step 8: Update the picking route Route_total and its time Time_total; Step 9. If the customer order Customerorders is not empty, return to step 3; otherwise, output the picking route Route_total and its time Time_total.

4. The crane operation path planning method with dynamic aisle yard according to claim 3 is characterized in that: In the sixth step, after completing the picking of the items in the current picking bay, the number of items at this bay should be updated to Item_num=Item_num-1.

5. The crane operation path planning method with dynamic aisle yard according to claim 3 is characterized in that: In the seventh step, after completing the picking of the items in the current picking position, the customer order Customerorders should be updated, that is, the first picked item in the customer order Customerorders should be deleted.