A BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless railway

Using BIM technology to automatically create a steel bar model for the railway ballastless track turnout area solves the problems of slow modeling speed and low accuracy in the existing technology, and achieves efficient and accurate steel bar modeling, which is suitable for complex track bed structures.

CN118586090BActive Publication Date: 2024-10-01CHINA RAILWAY DESIGN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411067702.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-10-01
Estimated Expiration
2044-08-06

AI Technical Summary

Technical Problem

The existing technology cannot effectively automate the modeling of steel bars in the railway ballastless track turnout area, resulting in slow modeling speed, low accuracy and error-prone, especially under complex geometric structures.

Method used

Using BIM-based intelligent modeling methods, by establishing a spatial coordinate system, generating a three-dimensional model of the track bed, constructing the distribution of lower, middle and upper reinforcements, and combining the geometric information of the switch machine and sleepers, the steel bar model is automatically created to support a variety of track bed units. type.

Benefits of technology

It improves modeling efficiency, avoids manual errors, dynamically adjusts modeling results, is suitable for complex track bed structures, simplifies the operation process, and is suitable for rapid reinforcement of right-angled polygonal track beds.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118586090B_ABST
    Figure CN118586090B_ABST
Patent Text Reader

Abstract

The present invention discloses a BIM-based intelligent modeling method for steel bars in a turnout area of ​​a ballastless railway track, comprising the following steps: S1, establishing a spatial coordinate system and placing a generated three-dimensional model of a ballast bed unit; S2, constructing the distribution of the lower reinforcement of the ballast bed in the ballast bed unit; S3, grouping the sleepers of different tracks, and sorting the obtained sleeper groups to obtain a sequential sleeper group; S4, calculating the distribution of the middle reinforcement of the ballast bed; S5, calculating the distribution of the upper reinforcement of the ballast bed; S6, judging the type of the ballast bed unit again, and constructing the distribution of steel bars of the ballast bed without a base; S7, constructing the distribution of steel bars of the base and the distribution of steel bars of the combined structure. The present invention can make full use of the information and three-dimensional form in the BIM model, and intelligently create a steel bar model according to the actual structure of the ballast bed and the base. The present invention solves the problems of cumbersome operation, difficulty in modification, and complex logic of the existing method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of modeling, and in particular to a BIM-based intelligent modeling method for steel bars in a turnout area of ​​a ballastless railway track. Background Art

[0002] Railway turnout is a track device with a switch and a frog with a guide rail, through which railway locomotives can switch from one track to another. Railway turnout is an important part of the railway and plays a very important role in the railway. Railway turnout is the weak link on the line, the focus and difficulty of maintenance, the key equipment that affects the speed and safety of trains, and one of the key technologies in the construction of high-speed railways.

[0003] The railway turnout area is the area where different types of railway turnouts or turnout groups are located. Due to the complex structure and numerous types of railway turnouts, the structure of the turnout area is also very complex and diverse, so the steel bar modeling for the turnout area of ​​ballastless railway is very complex and difficult.

[0004] Building Information Modeling (BIM) refers to the methods and technologies of information management by applying models and digital technology throughout the life cycle of construction project assets. The core concept of BIM is to use digital technology to provide a complete and actual construction project information library for the model. With the help of this three-dimensional model containing construction project information, the degree of information integration of construction projects can be effectively improved, thereby providing a platform for engineering information exchange and sharing for stakeholders in construction projects.

[0005] Ballastless track switch area often uses sleeper embedded ballastless track, which is composed of rails, fasteners, sleepers, ballast bed, base (concrete support layer) and other parts in order from top to bottom. The steel bar modeling of the ballastless track switch area is mainly for the steel bar modeling inside the ballast bed and base.

[0006] Since the track switch area is often composed of a combination of different types of turnouts and crossovers, the geometric forms of the main ballast bed in the track structure are often different; in addition, considering the track equipment such as switch machines, it is necessary to reserve several grooves on the ballast bed. However, the existing technical means can only complete the creation of steel bars by manually creating steel bars. Faced with the complex geometric forms of the switch area ballast bed, manual drawing of steel bars is not only difficult and slow, but also prone to errors. At present, there is no automated modeling method for steel bar modeling in the switch area of ​​railway ballastless track. Summary of the invention

[0007] In order to solve the problems existing in the prior art, the present invention provides a BIM-based railway ballastless track switch area steel bar intelligent modeling method which has fast modeling speed and high accuracy and supports multiple roadbed unit types.

[0008] To this end, the present invention adopts the following technical solutions:

[0009] A BIM-based intelligent modeling method for steel bars in a turnout area of ​​a ballastless railway includes the following steps:

[0010] S1, establish a spatial coordinate system and put in the generated 3D model of the track bed unit:

[0011] S11, establish the spatial coordinate system:

[0012] Based on the imported CAD turnout layout drawing, draw the outer contour of a ballast unit including at least one right angle.

[0013] Select a right angle of the outer contour, and use the side of the right angle along the railway line as the X-axis, the other side of the right angle as the Y-axis, and set a Z-axis perpendicular to the XY plane formed by the X-axis and the Y-axis;

[0014] The outer contour of the ballast unit includes the ballast contour and the base contour; if there is a switch machine in the ballast unit, the switch machine base contour is also drawn;

[0015] S12, generating a three-dimensional model of the ballast bed containing relevant geometric information: the three-dimensional model includes a limit groove, a switch groove and a sleeper; placing the generated three-dimensional model of the ballast bed unit into the spatial coordinate system established in S11; the XY plane is above the three-dimensional model of the ballast bed unit;

[0016] S2, constructing the lower reinforcement distribution of the ballast in the ballast unit, including the following steps:

[0017] Firstly, the projection distribution of the lower layer reinforcement of the roadbed is established on the XY plane; then the type of the roadbed unit is determined, and the projection distribution of the lower layer reinforcement is adjusted according to the different types; finally, the adjusted projection distribution of the lower layer reinforcement is translated along the Z axis to obtain different types of distribution of the lower layer reinforcement of the roadbed;

[0018] The different types of ballast lower layer reinforcement distribution include ballast lower layer reinforcement distribution of a combined structure of a base + ballast and ballast lower layer reinforcement distribution of a ballast without a base;

[0019] S3, grouping the sleepers of different tracks, and sorting the obtained sleeper groups to obtain sequential sleeper groups;

[0020] S31, classifying the sleepers in the track unit according to their track numbers, storing them into different sets, and sorting each set according to the track numbers;

[0021] S32, randomly selecting an ungrouped sleeper from the set with the smallest track number, and projecting the center point of the sleeper onto the X-axis to obtain its first projection point on the X-axis;

[0022] S33, selecting a set that has not been selected from other sets, cyclically selecting a sleeper from the set as the second sleeper, projecting the center point of the second sleeper onto the X-axis to obtain its second projection point on the X-axis, and calculating the distance between the second projection point and the first projection point, if the distance is less than a threshold, the second sleeper is grouped with the first sleeper; if there is no distance less than the threshold, the algorithm process is terminated, and manual inspection and correction are performed; the threshold is set by surveying the railway site;

[0023] S34, repeating step S33 until all the sleepers in the same group as the first sleeper are screened out and put into the same group as the first sleeper;

[0024] S35, repeating steps S32-S34 until all sleepers of different sets are grouped to obtain a set of sleeper groups;

[0025] S36, sort the sleeper groups:

[0026] The sleeper groups are sorted in order of the distance from the projection of the center point of the sleeper with the smallest track number on the X-axis to the origin from small to large, to obtain a sequential sleeper group;

[0027] S4, calculate the distribution of the middle reinforcement of the ballast bed;

[0028] S5, calculate the distribution of reinforcement in the upper layer of the ballast;

[0029] S6, determining the type of the ballast unit again, and constructing the steel bar distribution of the ballast without a base:

[0030] When the ballast unit does not include a base, the distribution of the lower reinforcement of the ballast without a base obtained by S2, the distribution of the middle reinforcement of the ballast obtained by S4, and the distribution of the upper reinforcement of the ballast obtained by S5 are combined according to whether there is a switch or not, and the distribution of the reinforcement of the ballast without a base is obtained and output;

[0031] Otherwise, go to S7;

[0032] S7, reinforcement distribution of the construction base and reinforcement distribution of the composite structure:

[0033] The reinforcement distribution of the base is constructed and combined with the lower reinforcement distribution of the combined structure ballast obtained in S2, the middle reinforcement distribution of the ballast obtained in S4, and the upper reinforcement distribution of the ballast obtained in S5 according to the presence or absence of a switch, to obtain the reinforcement distribution of the combined structure and output it.

[0034] Preferably, S2 comprises the following steps:

[0035] S21, projection distribution of steel bars for ballast bed:

[0036] On the XY plane, the X-axis is translated in the direction indicated by the Y-axis to obtain a plurality of equidistant X-axis parallel lines, and the line connecting the intersection points of each X-axis parallel line and the ballast bed contour is the preliminary projection distribution of the X-ribs in the lower layer of the ballast bed;

[0037] Similarly, the Y axis is translated in the direction indicated by the X axis, and the above method is used to obtain the preliminary projection distribution of the Y reinforcement in the lower layer of the ballast bed;

[0038] S22, determine the type of track bed unit:

[0039] When the ballast unit is a combination structure of a base and a ballast, execute S23; otherwise, execute S24;

[0040] S23, constructing the projection distribution of the lower layer reinforcement of the composite structure ballast bed:

[0041] When the ballast unit does not include a switch machine, the projection distribution of the lower layer reinforcement of the combined structure ballast is the preliminary projection distribution of the X reinforcement and Y reinforcement of the lower layer of the ballast obtained in S21, and S28 is executed;

[0042] Otherwise, the preliminary projection distribution of the X and Y ribs of the lower layer of the ballast is interrupted at the portion where the ballast contour overlaps with the switch machine cap contour to obtain the projection distribution of the ribs of the lower layer of the combined structure ballast, and S28 is executed;

[0043] S24, construct the projection distribution of the lower reinforcement of the subgrade without base:

[0044] When the ballast unit does not include a switch machine, the projection distribution of the lower layer reinforcement of the ballast without a base is the preliminary projection distribution of the X reinforcement and Y reinforcement of the lower layer of the ballast obtained in S21, and S27 is executed;

[0045] Otherwise, for the preliminary projection distribution of the X-bar and Y-bar of the lower layer of the ballast at the part where the contour of the ballast coincides with the contour of the switch machine cap, the preliminary projection distribution of the X-bar of the lower layer of the ballast is interrupted to obtain the projection distribution of the X-bar of the lower layer of the ballast without a base;

[0046] The preliminary projection distribution of the Y reinforcement of the lower layer of the ballast is extended to the outermost edge of the switch machine cap contour to obtain the projection distribution of the Y reinforcement of the lower layer of the ballast without a base; the projection distribution of the Y reinforcement of the lower layer of the ballast without a base is combined with the projection distribution of the X reinforcement of the lower layer of the ballast without a base to obtain the preliminary projection distribution of the reinforcement of the lower layer of the ballast without a base;

[0047] S25, calculating the distribution of the X-reinforcement of the lower layer of the switch machine cap: translating the parallel lines of the X-axis toward the Y-axis direction, and the lines connecting the intersections of each parallel line and the contour of the switch machine cap are the projections of the X-reinforcement on the XY plane; obtaining the projection distribution of the X-reinforcement of the lower layer of the switch machine;

[0048] S26, combining the projection distribution of the lower X-bar of the switch machine with the projection distribution of the lower bar of the preliminary subgrade-free ballast, and executing S27;

[0049] S27, translating the obtained projection distribution downward in the Z-axis direction to obtain the distribution of the reinforcement in the lower layer of the ballast without a base, and executing S3;

[0050] S28, translating the obtained projection distribution downward in the Z-axis direction to obtain the reinforcement distribution of the lower layer of the composite structure roadbed.

[0051] Preferably, the translation distance in S21 and S25 is 100 mm-250 mm; the translation distance in S27 and S28 is 200-400 mm.

[0052] Preferably, S4 comprises the following steps:

[0053] S41, calculating the projection distribution of the middle layer reinforcement, including the following sub-steps:

[0054] S411, on the XY plane, translate the X axis in the direction indicated by the Y axis to obtain a plurality of equidistant X axis parallel lines, and the line connecting the intersection points of each of the obtained X axis parallel lines and the ballast bed contour is the projection distribution of the X-ribs in the middle layer of the ballast bed;

[0055] Similarly, the Y axis is translated in the direction indicated by the X axis, and the projection distribution of the Y reinforcement in the middle layer of the track bed is obtained using the above method;

[0056] When the ballast unit does not include a switch, S412 is executed; otherwise, the projection distribution of the ballast middle layer X ribs and the ballast middle layer Y ribs is adjusted using the switch groove;

[0057] First, the switch machine groove is projected onto the XY plane to obtain a switch machine groove projection frame;

[0058] When the projection distribution of the middle layer X-bars intersects with the switch machine groove projection frame, the projection distribution of the middle layer X-bars of the ballast in the switch machine groove projection frame is interrupted;

[0059] When the projection distribution of the middle layer Y reinforcement has an intersection with the switch machine groove projection frame, the projection distribution of the middle layer Y reinforcement of the ballast in the switch machine groove projection frame is removed; and S412 is executed;

[0060] S412, if the ballast unit includes a double-block sleeper, execute S42; otherwise, proceed to S43;

[0061] S42, adjusting the projection of the middle layer reinforcement, including the following steps:

[0062] S421, projecting the outline of the sleeper onto the XY plane to obtain a rectangular projection set based on the sequential sleeper group obtained in S36 and the position of the double-block sleeper in the CAD turnout layout diagram;

[0063] S422, comparing the projection of each steel bar in the projection distribution of the middle layer X bars and the projection distribution of the middle layer Y bars obtained in S411 with each rectangular projection in S421,

[0064] If the projection of this middle layer X-bar intersects with the rectangular projection, it will be sunk 50mm-100mm;

[0065] If the projection of the middle Y reinforcement intersects with the rectangular projection, it will be bent so that it is in the same plane as the projection of the sunken X reinforcement;

[0066] If there is no intersection, it remains unchanged;

[0067] Through the above operations, the adjusted projection distribution of the middle layer X reinforcement and the adjusted projection distribution of the middle layer Y reinforcement are obtained;

[0068] S43, translating the projection distribution of the middle layer X reinforcement and the projection distribution of the middle layer Y reinforcement obtained in S422 downward in the Z axis direction to obtain the middle layer reinforcement distribution of the roadbed.

[0069] Preferably, the translation distance in S43 is 100 mm-300 mm.

[0070] Preferably, S5 comprises the following steps:

[0071] S5, calculation of the distribution of the upper reinforcement of the ballast bed, including the following sub-steps:

[0072] S51, generating steel bars on both sides of the sleeper, including the following steps:

[0073] S511, selecting a sleeper group whose steel bars distribution on both sides is not calculated from the sequential sleeper groups obtained in S36, and translating the center line distribution of all sleepers in the sleeper group to the left and right sides by a certain distance to obtain two groups of line segments;

[0074] S512, for the two groups of line segments generated in S511, connect the line segments on the same side of the sleeper across the track number tails and then extend both ends thereof until they intersect with the edge of the ballast bed, thereby obtaining the steel bars on both sides of the sleeper of the group;

[0075] S513, repeating steps 511 to 512 until all sleeper groups have calculated the corresponding steel bar distribution on both sides, and using it as the upper layer Y bar distribution;

[0076] S52, translating the oblique side of the ballast in the ballast unit inward several times to obtain a partial upper layer X-rebar distribution;

[0077] S53, when the track in the ballast unit does not include a double-block sleeper, proceed to S6, otherwise constructing the X-bar distribution at the bottom of the double-block sleeper, specifically including the following steps:

[0078] S531, select a track with a double-block sleeper and no X-ribs generated at the bottom of the double-block sleeper, and connect the midpoints of the first double-block sleeper and the last double-block sleeper on the track to obtain a center line;

[0079] S532, translating the center line obtained in S531 to both sides for several times to obtain the X-bar distribution at the lower part of the double-block sleeper of the track;

[0080] S533, repeating steps S531 to S532, obtaining the lower X-reinforcement distribution of the double-block sleepers of all tracks containing double-block sleepers in the ballast unit, and combining the lower X-reinforcement distribution with the upper X-reinforcement distribution obtained in S52 as the upper X-reinforcement distribution of the ballast;

[0081] S54, combining the upper X-reinforcement distribution of the ballast bed with the upper Y-reinforcement distribution obtained in S513 to obtain the upper Y-reinforcement distribution of the ballast bed.

[0082] Preferably, in S52, the oblique side of the ballast in the ballast unit is translated inward 1-3 times at a distance of 100 mm-250 mm to obtain a partial upper layer X-rib distribution.

[0083] Preferably, in S532, the center line obtained in S531 is translated to both sides by a distance of 200 mm-250 mm 1-3 times to obtain the X-bar distribution at the lower part of the double-block sleeper of the track.

[0084] Preferably, S7 comprises the following steps:

[0085] S71, on the XY plane, translate the X-axis in the direction indicated by the Y-axis to obtain a plurality of equidistant X-axis parallel lines, and the lines connecting the intersections of each of the X-axis parallel lines and the base contour are the preliminary projection distribution of the base X-ribs;

[0086] Similarly, translate the Y axis in the direction indicated by the X axis, and use the above method to obtain the preliminary projection distribution of the Y ribs of the base;

[0087] S72, when the track bed unit includes a switch machine, execute S73; otherwise, execute S74;

[0088] S73, constructing a base reinforcement distribution including a switch machine, comprising the following steps;

[0089] S731, for the part where the base contour coincides with the switch machine cap contour, the preliminary projection distribution of the base X reinforcement and the preliminary projection distribution of the base Y reinforcement are interrupted to obtain the projection distribution of the base lower layer X reinforcement;

[0090] The preliminary projection distribution of the Y reinforcement of the base is extended to the outermost edge of the switch machine cap contour to obtain the projection distribution of the Y reinforcement of the lower layer of the base; it is combined with the projection distribution of the X reinforcement of the lower layer of the base to obtain the preliminary projection distribution of the reinforcement of the lower layer of the base;

[0091] S732, combining the preliminary projection distribution of the lower layer reinforcement of the base with the projection distribution of the lower layer X reinforcement of the switch obtained in S25; translating the combined projection distribution downward in the Z-axis direction to obtain the distribution of the lower layer reinforcement of the base including the switch;

[0092] S733, projecting the limiting groove onto the XY plane to obtain a limiting groove projection set, first interrupting the preliminary projection distribution of the base X ribs and the preliminary projection distribution of the base Y ribs obtained in S71 at the projection of the limiting groove; then interrupting them at the point where the base contour coincides with the contour of the switch machine cap, and finally obtaining the projection distribution of the upper ribs of the base including the switch machine; translating them downward in the Z-axis direction to obtain the distribution of the upper ribs of the base including the switch machine;

[0093] S74, construction excluding the distribution of base reinforcement of the switch machine:

[0094] S741, translating the preliminary projection distribution obtained in S71 downward in the Z-axis direction to obtain the distribution of the lower reinforcement of the base excluding the switch machine;

[0095] S742, projecting the limiting groove onto the XY plane to obtain a limiting groove projection set, firstly interrupting the projections of the base X ribs and Y ribs obtained in S71 at the limiting groove projections; then translating the interrupted projection distribution downward in the Z axis direction to obtain the upper rib distribution of the base excluding the switch machine; executing S75;

[0096] S75, combining the upper reinforcement distribution of the base and the lower reinforcement distribution of the base to obtain the reinforcement distribution of the base;

[0097] S76, reinforcement distribution for composite structures:

[0098] The reinforcement distribution of the base obtained by S75, the lower reinforcement distribution of the combined structure ballast obtained by S2, the middle reinforcement distribution of the ballast obtained by S4 and the upper reinforcement distribution of the ballast obtained by S5 are combined according to whether there is a switch machine, and the reinforcement distribution of the combined structure is obtained and output.

[0099] Preferably, the translation in S732 and S741 is 400 mm-600 mm along the Z-axis direction; and the translation in S733 and S742 is 300 mm-500 mm along the Z-axis direction.

[0100] Compared with the prior art, the present invention has the following beneficial effects:

[0101] 1. The present invention uses BIM technology to realize intelligent modeling of steel bars in the turnout area of ​​ballastless railway, thereby improving modeling efficiency;

[0102] 2. The method of the present invention avoids the errors caused by manual reinforcement and can dynamically adjust the modeling results through parameter settings;

[0103] 3. The method of the present invention solves the problems of cumbersome operation, difficult modification, and complex logic of the existing method, and has a reference effect on the intelligent reinforcement of other subjects;

[0104] 4. The present invention is suitable for rapid reinforcement of any polygonal roadbed structure containing a right angle. Different from the previous method of manually reading parameters and manually creating steel bars, the present invention can make full use of the information and three-dimensional form in the BIM model and intelligently create a steel bar model according to the actual structure of the roadbed and the base. BRIEF DESCRIPTION OF THE DRAWINGS

[0105] Figure 1 is a flow chart of the present invention;

[0106] Figure 2 The schematic diagram of the model of the baseless track bed with the switch machine cap is shown in FIG.

[0107] Figure 3 It is a schematic diagram of the steel bar structure at the groove of the switch machine;

[0108] Figure 4 Schematic diagram of the sunken middle layer X-bar and the Y-bar that adapts to it by bending;

[0109] Figure 5 Schematic diagram of the upper Y-ribs on both sides of the sleeper;

[0110] Figure 6 Schematic diagram of the upper reinforcement of the lower part of the embedded sleeper (left side) and the lower part of the double-block sleeper (right side);

[0111] Figure 7 It is a schematic diagram of the upper X-ribs and upper Y-ribs of the base interrupted at the limiting groove;

[0112] Figure 8 It is a schematic diagram of the process of S2 of the present invention.

[0113] In the figure:

[0114] 1. Roadbed without base, 2. Switch machine support, 3. Switch machine groove, 4. Limit groove. DETAILED DESCRIPTION

[0115] The technical solution of the present invention is described in detail below in conjunction with the accompanying drawings and embodiments.

[0116] The "certain interval" (the distance between adjacent steel bars) and "specified number of times" mentioned below are manually set parameters, which are specified values ​​set based on actual conditions.

[0117] As described in the background art, the steel bar modeling of the turnout area of ​​ballastless track is mainly aimed at the steel bar modeling inside the track bed and the base.

[0118] The sleepers involved in the present invention include two types: double-block sleepers and embedded sleepers. Unless otherwise specified, both types of sleepers are applicable.

[0119] The "tracks" mentioned below are numbered railway lanes used for parking in station platforms.

[0120] The track bed involved in the method of the present invention includes a track bed without a base and a combined structure of a base + track bed.

[0121] The method of the present invention takes into account the steel bar modeling at the switch machine groove, the switch machine cap and the limit groove.

[0122] like Figure 1 As shown, the BIM-based railway ballastless track turnout area steel bar intelligent modeling method of the present invention comprises the following steps:

[0123] S1, establish a spatial coordinate system and put in the generated 3D model of the track bed unit:

[0124] S11, establish the spatial coordinate system:

[0125] Import the CAD turnout layout drawing into BIMBase. The turnout area of ​​ballastless railway includes multiple ballast units, each of which is usually 7-10m long. Since the reinforcement modeling method of each ballast unit is the same, only one ballast unit is used as an example for explanation below.

[0126] Based on the imported CAD turnout layout drawing, draw the outer contour of a ballast unit including at least one right angle, the outer contour includes the ballast contour (when there is no base) or the ballast contour and the base contour (when there is a base). If there is a switch machine in the ballast unit, it is also necessary to draw the pedestal contour of the switch machine and record the parameters of the groove of the switch machine. When drawing the outer contour of the ballast unit, it is necessary to determine the drawing direction of the contour in order to obtain the positions of each vertex of the contour.

[0127] Select a right angle of the outer contour (usually the upper left corner), and use the two sides of the right angle as the X-axis and Y-axis of the spatial coordinate system, and set the XY plane composed of the X-axis and Y-axis at the top of the track bed unit.

[0128] Specifically, the side of the right angle along the railway line is taken as the X-axis, the other side of the right angle is taken as the Y-axis, and the upward direction perpendicular to the XY plane is taken as the direction of the Z-axis. All longitudinal steel bars in the X direction are referred to as X bars, and all transverse steel bars in the Y direction (perpendicular to the railway line) are referred to as Y bars.

[0129] S12, generating a three-dimensional model of the track bed unit including relevant geometric information:

[0130] Based on the center line of the sleeper, the limit groove (i.e., the groove on the base), and the outer contour of the ballast unit and the contour of the switch machine cap drawn in S11, the 3D model is instantiated to obtain the 3D model of the ballast unit. The 3D model of the ballast unit records the geometric design information of the ballast, limit groove, switch machine, and sleeper, which is used for automatic steel bar layout. The generated 3D model of the ballast unit is placed in the spatial coordinate system established in S11.

[0131] S2, construct the lower reinforcement distribution of the ballast in the ballast unit. Figure 8 , which step includes the following sub-steps:

[0132] S21, projection distribution of steel bars for ballast bed:

[0133] On the XY plane, the X-axis is translated in the direction indicated by the Y-axis at a certain interval (e.g., 100 mm-250 mm) to obtain multiple parallel lines, and the intersection points of each parallel line and the track bed contour are obtained. The two intersection points are connected to obtain the preliminary projection distribution of the X-ribs in the lower layer of the track bed.

[0134] Similarly, the Y-axis is translated in the direction of the X-axis at a certain interval (100mm-250mm) to obtain multiple lines. The intersection points of each parallel line and the trackbed contour are connected to obtain the preliminary projection distribution of the Y-bars in the lower layer of the trackbed.

[0135] S22, determine the type of track bed unit:

[0136] When the ballast unit is a combination structure of a base and a ballast, execute S23; otherwise, execute S24;

[0137] S23, construct the projection distribution of the lower reinforcement of the composite structure roadbed:

[0138] When the track bed unit does not include a switch machine, the projection distribution of the lower layer reinforcement of the combined structure track bed is the preliminary projection distribution of the X reinforcement and Y reinforcement of the lower layer of the track bed obtained in S21, and S28 is executed;

[0139] Otherwise, the preliminary projection distribution of the X and Y reinforcements in the lower layer of the ballast is interrupted at the part where the ballast contour overlaps with the switch machine cap contour to obtain the projection distribution of the reinforcements in the lower layer of the combined structure ballast, and S28 is executed;

[0140] S24, construct the projection distribution of the lower reinforcement of the subgrade without base:

[0141] When the ballast unit does not include a switch machine, the projection distribution of the lower layer reinforcement of the ballast without a base is the preliminary projection distribution of the X reinforcement and Y reinforcement of the lower layer of the ballast obtained in S21, and S27 is executed;

[0142] Otherwise, it is necessary to interrupt the preliminary projection distribution of the X-bars in the lower layer of the ballast bed at the part where the contour of the ballast bed and the contour of the switch machine cap coincide on the XY plane, so as to obtain the projection distribution of the X-bars in the lower layer of the ballast bed without a base;

[0143] When calculating the Y reinforcement at the part where the contour of the ballast bed and the contour of the switch machine cap overlap, it is necessary to extend the projection of the Y reinforcement to the outermost edge of the contour of the switch machine cap to obtain the projection distribution of the Y reinforcement of the lower layer of the ballast bed without a base; the projection distribution of the Y reinforcement of the lower layer of the ballast bed without a base is combined with the projection distribution of the X reinforcement of the lower layer of the ballast bed without a base to obtain the preliminary projection distribution of the reinforcement of the lower layer of the ballast bed without a base; the intersection of the ballast bed without a base and the switch machine cap is as follows Figure 2 As shown;

[0144] S25, calculate the distribution of the lower X-ribs of the switch machine cap: translate the parallel line of the X-axis toward the Y-axis at a certain interval (100mm-250mm), and the line connecting the intersection of each translation line and the contour of the switch machine cap is the projection of the X-rib on the XY plane, and the projection distribution of the lower X-ribs of the switch machine is obtained.

[0145] S26, combining the projection distribution of the lower X-bar of the switch machine with the projection distribution of the lower bar of the preliminary subgrade-free ballast, and executing S27;

[0146] S27, translate the obtained projection distribution downward in the Z-axis direction by a set value (e.g., 200-400 mm) to obtain the reinforcement distribution of the lower layer of the subgrade without a base, and execute S3;

[0147] S28, the projection distribution obtained in S23 is translated downward in the Z-axis direction by a set value (e.g., 200-400 mm) to obtain the reinforcement distribution of the lower layer of the composite structure track bed.

[0148] S3, grouping the sleepers of different tracks and sorting the sleeper groups, including the following steps:

[0149] S31, classifying the sleepers in the track bed unit according to the track number and storing them into different sets, and sorting each set according to the track number;

[0150] S32, randomly selecting an ungrouped sleeper from the set with the smallest track number, projecting the center point of the sleeper onto the X-axis, and obtaining its projection point on the X-axis;

[0151] S33, select a set that has not been selected from other sets, cyclically select sleepers from the set, project the center point of the selected sleeper onto the X-axis, and obtain its projection point on the X-axis; calculate the distance between the projection point and the projection point obtained in step S32, if the distance is less than a preset value, the sleeper is grouped with the sleeper selected in step S32, and the preset value is set according to the actual situation; if there is no distance less than the preset value, it means that there is a problem with the model or classification, and the algorithm process is terminated, and manual inspection and correction are performed;

[0152] S34, repeating step S33 until all sleepers in the same group as the sleepers selected in step S32 are screened out and put into the same group;

[0153] S35, repeating steps S32-S34 until all sleepers in different sets are grouped to obtain a set of sleeper groups;

[0154] S36, sort the sleeper groups:

[0155] The sleeper groups are sorted in order of the distance from the projection of the center point of the sleeper with the smallest track number in each sleeper group on the X-axis to the origin from small to large, so as to obtain a sequential sleeper group.

[0156] S4, calculating the distribution of the middle reinforcement of the ballast bed, includes the following sub-steps:

[0157] S41, calculate the projection distribution of the reinforcement in the middle layer of the ballast bed, including:

[0158] S411, using the method in S21 to generate the projection distribution of the X reinforcement in the middle layer of the ballast and the projection distribution of the Y reinforcement in the middle layer of the ballast;

[0159] When the track bed unit does not include a switch machine, S412 is executed, otherwise the projection distribution of the X-rib and the Y-rib is adjusted using the switch machine groove.

[0160] First, project the switch machine groove onto the XY plane to obtain the switch machine groove projection frame;

[0161] When the projection of the middle layer X-bar intersects with the switch machine groove projection frame, the projection of the middle layer X-bar of the ballast in the switch machine groove projection frame is interrupted;

[0162] When the projection of the middle layer Y reinforcement has an intersection with the switch machine groove projection frame, the projection of the middle layer Y reinforcement of the ballast in the switch machine groove projection frame is removed; S412 is executed;

[0163] S412, if the ballast unit includes a double-block sleeper, execute S42; otherwise, proceed to S43;

[0164] S42, adjusting the projection of the middle layer reinforcement, including the following steps:

[0165] S421, projecting the outline of the sleeper onto the XY plane to obtain a rectangular projection set based on the sequential sleeper group obtained in S36 and the position of the double-block sleeper in the CAD turnout layout diagram.

[0166] S422, comparing the projection of each steel bar in the projection distribution of the X-bar in the middle layer of the ballast obtained in S411 and the projection distribution of the Y-bar in the middle layer of the ballast with each rectangular projection in S421;

[0167] If the projection of this middle layer X-bar intersects with the rectangular projection, it will be sunk by a specified distance (e.g. 50mm-100mm).

[0168] If the projection of the middle Y reinforcement intersects with the rectangular projection, it is bent so that it is in the same plane as the projection of the sunken X reinforcement;

[0169] If there is no intersection, it remains unchanged;

[0170] Through the above operations, the adjusted projection distribution of the middle layer X reinforcement and the adjusted projection distribution of the middle layer Y reinforcement are obtained;

[0171] S43, the projection distribution of the middle layer X reinforcement and the projection distribution of the middle layer Y reinforcement obtained in S422 are translated downward in the Z-axis direction by a set value (e.g., 100 mm-300 mm) to obtain the distribution of the middle layer reinforcement of the ballast; Figure 3 and Figure 4 shown.

[0172] S5, calculation of the distribution of the upper reinforcement of the ballast bed, including the following sub-steps:

[0173] S51, generates the reinforcement on both sides of the sleeper, as follows:

[0174] S511, select a sleeper group without calculating the distribution of steel bars on both sides from the sequential sleeper groups obtained in S36, and translate the center lines of all sleepers in the sleeper group to the left and right sides by a specified distance (e.g., 200 mm-250 mm) to obtain two groups of line segments, and the number of line segments in each group is the same as the number of center lines of the sleeper group. There are two center lines of sleepers, and in the method of the present invention, a center line whose angle with the Y axis is within the range of positive and negative 90 degrees is selected.

[0175] S512, for the two groups of line segments generated in S511, connect the line segments on the same side of the sleeper across the track number tail, and then extend both ends until they intersect with the edge of the ballast bed to obtain the steel bars on both sides of the sleeper.

[0176] S513, repeating steps 511 and 512 until all sleeper groups have calculated the corresponding steel bar distribution on both sides, and using it as the upper Y-bar distribution; Figure 5 shown.

[0177] S52, the inclined side of the ballast is translated inwardly at a specified interval (e.g., 100 mm-250 mm) for a specified number of times (e.g., 1-3 times) to obtain a distribution of a portion of the upper X-rebars;

[0178] S53, when the track in the ballast unit does not include a double-block sleeper, enter S6, otherwise construct the X-bar distribution at the bottom of the double-block sleeper, specifically including the following steps:

[0179] S531, select a track with a double-block sleeper and no X-ribs generated at the bottom of the double-block sleeper, and connect the midpoints of the first double-block sleeper and the last double-block sleeper on the track to obtain a center line;

[0180] S532, the center line obtained in S531 is translated to both sides for a specified number of times (e.g., 1-3 times) at a specified interval (e.g., 200 mm-250 mm) to obtain the X-bar distribution at the lower part of the double-block sleeper of the track;

[0181] S533, repeating steps S531 to S532, obtaining the lower X-reinforcement distribution of the double-block sleepers of all tracks containing double-block sleepers in the ballast unit, and combining the lower X-reinforcement distribution with the upper X-reinforcement distribution obtained in S52 as the upper X-reinforcement distribution of the ballast;

[0182] S54, the upper layer X reinforcement distribution of the ballast is combined with the upper layer Y reinforcement distribution obtained in S513 to obtain the upper layer reinforcement distribution of the ballast, such as Figure 6 shown.

[0183] S6, determine the type of ballast unit again and construct the steel bar distribution of the ballast without base:

[0184] When the ballast unit does not include a base, the lower layer reinforcement distribution of the ballast without a base obtained in S2, the middle layer reinforcement distribution of the ballast obtained in S4, and the upper layer reinforcement distribution of the ballast obtained in S5 are combined according to whether there is a switch machine, and the steel bar distribution of the ballast without a base is obtained and output; otherwise, enter S7.

[0185] S7, constructing the steel bar distribution of the base and the steel bar distribution of the composite structure, including the following steps:

[0186] S71, using the method of S21, obtaining the preliminary projection distribution of the base X ribs and the preliminary projection distribution of the base Y ribs through the base contour;

[0187] S72, when the track bed unit includes a switch machine, execute S73; otherwise, execute S74;

[0188] S73, constructing a base reinforcement distribution including a switch machine, comprising the following steps;

[0189] S731, on the XY plane, interrupting the preliminary projection distribution of the X-bars of the base at the portion where the contour of the base coincides with the contour of the switch machine cap, to obtain the projection distribution of the X-bars of the lower layer of the base;

[0190] When calculating the Y reinforcement, it is necessary to extend the projection of the Y reinforcement to the outermost edge of the switch machine cap contour to obtain the projection distribution of the Y reinforcement in the lower layer of the base; combine it with the projection distribution of the X reinforcement in the lower layer of the base to obtain the preliminary projection distribution of the reinforcement in the lower layer of the base including the switch machine;

[0191] S732, combining the preliminary projection distribution of the lower layer reinforcement of the base including the switch machine and the projection distribution of the lower layer X reinforcement of the switch machine obtained in S25; translating the combined projection distribution downward in the Z-axis direction by a set value (e.g., 400-600 mm) to obtain the distribution of the lower layer reinforcement of the base including the switch machine;

[0192] S733, projecting the limiting groove onto the XY plane to obtain a limiting groove projection set, firstly interrupting the projection of the base X rib and Y rib obtained in S71 at the limiting groove projection; then interrupting it at the point where the base contour coincides with the switch machine cap contour, and finally obtaining the projection distribution of the upper ribs of the base including the switch machine; Figure 7 Then, the projection distribution of the upper ribs of the base including the switch machine is translated downward by a set value (for example, 300-500 mm) in the Z-axis direction to obtain the distribution of the upper ribs of the base including the switch machine; execute S75;

[0193] S74, construction excluding the distribution of base reinforcement of the switch machine:

[0194] S741, the preliminary projection distribution obtained in S71 is translated downward in the Z-axis direction by a set value (e.g., 400-600 mm) to obtain the distribution of the lower layer reinforcement of the base excluding the switch machine;

[0195] S742, projecting the limiting groove onto the XY plane to obtain a limiting groove projection set, firstly interrupting the projections of the base X ribs and Y ribs obtained in S71 at the limiting groove projections; then translating the interrupted projection distribution downward in the Z-axis direction by a set value (e.g., 300-500 mm) to obtain the upper rib distribution of the base excluding the switch machine; executing S75;

[0196] S75, the upper reinforcement distribution of the base and the lower reinforcement distribution of the base are combined to obtain the reinforcement distribution of the base.

[0197] At this time, the steel bar distribution of the base includes the steel bar distribution of the base including the switch machine and the steel bar distribution of the base not including the switch machine.

[0198] S76, reinforcement distribution for composite structures:

[0199] The reinforcement distribution of the base obtained by S75, the lower reinforcement distribution of the combined structure ballast obtained by S2, the middle reinforcement distribution of the ballast obtained by S4 and the upper reinforcement distribution of the ballast obtained by S5 are combined according to whether there is a switch machine, and the reinforcement distribution of the combined structure is obtained and output.

[0200] The above method is to perform reinforcement modeling operation on a single ballast bed unit. After completion, the above method needs to be performed on all other ballast bed units to obtain the final reinforcement distribution of the ballastless track turnout area.

Claims

1. A BIM-based intelligent modeling method for steel bars in the turnout area of ​​railway ballastless track, characterized in that: The following steps are involved: S1, establish a spatial coordinate system and put in the generated 3D model of the track bed unit: S11, establish the spatial coordinate system: Based on the imported CAD turnout layout drawing, draw the outer contour of a ballast unit including at least one right angle. Select a right angle of the outer contour, and use the side of the right angle along the railway line as the X-axis, the other side of the right angle as the Y-axis, and set a Z-axis perpendicular to the XY plane formed by the X-axis and the Y-axis; The outer contour of the ballast unit includes the ballast contour and the base contour; if the ballast unit has a switch machine, the switch machine base contour is also drawn; S12, generating a three-dimensional model of the ballast bed containing relevant geometric information: the three-dimensional model includes a limit groove, a switch groove and a sleeper; placing the generated three-dimensional model of the ballast bed unit into the spatial coordinate system established in S11; the XY plane is above the three-dimensional model of the ballast bed unit; S2, constructing the lower reinforcement distribution of the ballast in the ballast unit, including the following steps: Firstly, the projection distribution of the lower layer reinforcement of the roadbed is established on the XY plane; then the type of the roadbed unit is determined, and the projection distribution of the lower layer reinforcement is adjusted according to the different types; finally, the adjusted projection distribution of the lower layer reinforcement is translated along the Z axis to obtain different types of distribution of the lower layer reinforcement of the roadbed; The different types of ballast lower layer reinforcement distribution include ballast lower layer reinforcement distribution of a combined structure of a base + ballast and ballast lower layer reinforcement distribution of a ballast without a base; S3, grouping the sleepers of different tracks, and sorting the obtained sleeper groups to obtain sequential sleeper groups; S31, classifying the sleepers in the track unit according to their track numbers, storing them into different sets, and sorting each set according to the track numbers; S32, randomly selecting an ungrouped sleeper from the set with the smallest track number, and projecting the center point of the sleeper onto the X-axis to obtain its first projection point on the X-axis; S33, selecting a set that has not been selected from other sets, cyclically selecting a sleeper from the set as the second sleeper, projecting the center point of the second sleeper onto the X-axis to obtain its second projection point on the X-axis, and calculating the distance between the second projection point and the first projection point, if the distance is less than a threshold, the second sleeper is grouped with the first sleeper; if there is no distance less than the threshold, the algorithm process is terminated, and manual inspection and correction are performed; the threshold is set by surveying the railway site; S34, repeating step S33 until all the sleepers in the same group as the first sleeper are screened out and put into the same group as the first sleeper; S35, repeating steps S32-S34 until all sleepers of different sets are grouped to obtain a set of sleeper groups; S36, sort the sleeper groups: The sleeper groups are sorted in order of the distance from the projection of the center point of the sleeper with the smallest track number on the X-axis to the origin from small to large, to obtain a sequential sleeper group; S4, calculate the distribution of the middle reinforcement of the ballast bed; S5, calculate the distribution of reinforcement in the upper layer of the ballast; S6, determining the type of the ballast unit again, and constructing the steel bar distribution of the ballast without a base: When the ballast unit does not include a base, the distribution of the lower reinforcement of the ballast without a base obtained by S2, the distribution of the middle reinforcement of the ballast obtained by S4, and the distribution of the upper reinforcement of the ballast obtained by S5 are combined according to whether there is a switch or not, and the distribution of the reinforcement of the ballast without a base is obtained and output; Otherwise, go to S7; S7, reinforcement distribution of the construction base and reinforcement distribution of the composite structure: The reinforcement distribution of the base is constructed and combined with the lower reinforcement distribution of the combined structure ballast obtained in S2, the middle reinforcement distribution of the ballast obtained in S4, and the upper reinforcement distribution of the ballast obtained in S5 according to the presence or absence of a switch, to obtain the reinforcement distribution of the combined structure and output it.

2. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 1 is characterized in that: S2 includes the following steps: S21, projection distribution of steel bars for ballast bed: On the XY plane, the X-axis is translated in the direction indicated by the Y-axis to obtain a plurality of equidistant X-axis parallel lines, and the line connecting the intersection points of each X-axis parallel line and the ballast bed contour is the preliminary projection distribution of the X-ribs in the lower layer of the ballast bed; Similarly, the Y axis is translated in the direction indicated by the X axis, and the above method is used to obtain the preliminary projection distribution of the Y reinforcement in the lower layer of the ballast bed; S22, determine the type of track bed unit: When the ballast unit is a combination structure of a base and a ballast, execute S23; otherwise, execute S24; S23, constructing the projection distribution of the lower layer reinforcement of the composite structure ballast bed: When the ballast unit does not include a switch machine, the projection distribution of the lower layer reinforcement of the combined structure ballast is the preliminary projection distribution of the X reinforcement and Y reinforcement of the lower layer of the ballast obtained in S21, and S28 is executed; Otherwise, the preliminary projection distribution of the X and Y ribs of the lower layer of the ballast is interrupted at the portion where the ballast contour overlaps with the switch machine cap contour to obtain the projection distribution of the ribs of the lower layer of the combined structure ballast, and S28 is executed; S24, construct the projection distribution of the lower reinforcement of the subgrade without base: When the ballast unit does not include a switch machine, the projection distribution of the lower layer reinforcement of the ballast without a base is the preliminary projection distribution of the X reinforcement and Y reinforcement of the lower layer of the ballast obtained in S21, and S27 is executed; Otherwise, for the preliminary projection distribution of the X-bar and Y-bar of the lower layer of the ballast at the part where the contour of the ballast coincides with the contour of the switch machine cap, the preliminary projection distribution of the X-bar of the lower layer of the ballast is interrupted to obtain the projection distribution of the X-bar of the lower layer of the ballast without a base; The preliminary projection distribution of the Y reinforcement of the lower layer of the ballast is extended to the outermost edge of the switch machine cap contour to obtain the projection distribution of the Y reinforcement of the lower layer of the ballast without a base; the projection distribution of the Y reinforcement of the lower layer of the ballast without a base is combined with the projection distribution of the X reinforcement of the lower layer of the ballast without a base to obtain the preliminary projection distribution of the reinforcement of the lower layer of the ballast without a base; S25, calculating the distribution of the X-reinforcement of the lower layer of the switch machine cap: translating the parallel lines of the X-axis toward the Y-axis direction, and the lines connecting the intersections of each parallel line and the contour of the switch machine cap are the projections of the X-reinforcement on the XY plane; obtaining the projection distribution of the X-reinforcement of the lower layer of the switch machine; S26, combining the projection distribution of the lower X-bar of the switch machine with the projection distribution of the lower bar of the preliminary subgrade-free ballast, and executing S27; S27, translating the obtained projection distribution downward in the Z-axis direction to obtain the distribution of the reinforcement in the lower layer of the ballast without a base, and executing S3; S28, translating the obtained projection distribution downward in the Z-axis direction to obtain the reinforcement distribution of the lower layer of the composite structure roadbed.

3. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 2 is characterized in that: The translation distance in S21 and S25 is 100mm-250mm; the translation distance in S27 and S28 is 200-400mm.

4. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 1 is characterized in that: S4 includes the following steps: S41, calculate the projection distribution of the middle layer reinforcement, The following steps are included: S411, on the XY plane, translate the X axis in the direction indicated by the Y axis to obtain a plurality of equidistant X axis parallel lines, and the line connecting the intersection points of each of the obtained X axis parallel lines and the ballast bed contour is the projection distribution of the X-ribs in the middle layer of the ballast bed; Similarly, the Y axis is translated in the direction indicated by the X axis, and the projection distribution of the Y reinforcement in the middle layer of the ballast bed is obtained using the above method; When the ballast unit does not include a switch, S412 is executed; otherwise, the projection distribution of the ballast middle layer X ribs and the ballast middle layer Y ribs is adjusted using the switch groove; First, the switch machine groove is projected onto the XY plane to obtain a switch machine groove projection frame; When the projection distribution of the middle layer X-bars intersects with the switch machine groove projection frame, the projection distribution of the middle layer X-bars of the ballast in the switch machine groove projection frame is interrupted; When the projection distribution of the middle layer Y reinforcement has an intersection with the switch machine groove projection frame, the projection distribution of the middle layer Y reinforcement of the ballast in the switch machine groove projection frame is removed; and S412 is executed; S412, if the ballast unit includes a double-block sleeper, execute S42; otherwise, proceed to S43; S42, adjusting the projection of the middle layer reinforcement, including the following steps: S421, projecting the outline of the sleeper onto the XY plane to obtain a rectangular projection set based on the sequential sleeper group obtained in S36 and the position of the double-block sleeper in the CAD turnout layout diagram; S422, comparing the projection of each steel bar in the projection distribution of the middle layer X bars and the projection distribution of the middle layer Y bars obtained in S411 with each rectangular projection in S421, If the projection of this middle layer X-bar intersects with the rectangular projection, it will be sunk 50mm-100mm; If the projection of the middle Y reinforcement intersects with the rectangular projection, it will be bent so that it is in the same plane as the projection of the sunken X reinforcement; If there is no intersection, it remains unchanged; Obtaining the adjusted projection distribution of the middle layer X reinforcement and the adjusted projection distribution of the middle layer Y reinforcement; S43, translating the projection distribution of the middle layer X reinforcement and the projection distribution of the middle layer Y reinforcement obtained in S422 downward in the Z axis direction to obtain the middle layer reinforcement distribution of the roadbed.

5. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 4 is characterized in that: The translation distance in S43 is 100 mm-300 mm.

6. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 1 is characterized in that: S5 includes the following steps: S5, calculation of the distribution of the upper reinforcement of the ballast bed, including the following sub-steps: S51, generating steel bars on both sides of the sleeper, including the following steps: S511, selecting a sleeper group whose steel bars distribution on both sides is not calculated from the sequential sleeper groups obtained in S36, and translating the center line distribution of all sleepers in the sleeper group to the left and right sides by a certain distance to obtain two groups of line segments; S512, for the two groups of line segments generated in S511, connect the line segments on the same side of the sleeper across the track number tails, and then extend both ends until they intersect with the edge of the ballast bed, to obtain the steel bars on both sides of the sleeper; S513, repeating steps 511 to 512 until all sleeper groups have calculated the corresponding steel bar distribution on both sides, and using it as the upper layer Y bar distribution; S52, translating the oblique side of the ballast in the ballast unit inward several times to obtain a partial upper layer X-rebar distribution; S53, when the track in the ballast unit does not include a double-block sleeper, proceed to S6, otherwise constructing the X-bar distribution at the bottom of the double-block sleeper, specifically including the following steps: S531, select a track with a double-block sleeper and no X-ribs generated at the bottom of the double-block sleeper, and connect the midpoints of the first double-block sleeper and the last double-block sleeper on the track to obtain a center line; S532, translating the center line obtained in S531 to both sides for several times to obtain the X-bar distribution at the lower part of the double-block sleeper of the track; S533, repeating steps S531 to S532, obtaining the lower X-reinforcement distribution of the double-block sleepers of all tracks containing double-block sleepers in the ballast unit, and combining the lower X-reinforcement distribution with the upper X-reinforcement distribution obtained in S52 as the upper X-reinforcement distribution of the ballast; S54, combining the upper X-reinforcement distribution of the ballast bed with the upper Y-reinforcement distribution obtained in S513 to obtain the upper reinforcement distribution of the ballast bed.

7. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​railway ballastless track according to claim 6 is characterized by: In S52, the oblique side of the ballast in the ballast unit is translated inward 1-3 times at a distance of 100 mm-250 mm to obtain a partial upper layer X-rib distribution.

8. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 6 is characterized by: In S532, the center line obtained in S531 is translated to both sides by a distance of 200mm-250mm 1-3 times to obtain the X-bar distribution at the lower part of the double-block sleeper of the track.

9. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 2 is characterized in that: S7 includes the following steps: S71, on the XY plane, translate the X-axis in the direction indicated by the Y-axis to obtain a plurality of equidistant X-axis parallel lines, and the lines connecting the intersections of each of the X-axis parallel lines and the base contour are the preliminary projection distribution of the base X-ribs; Similarly, translate the Y axis in the direction indicated by the X axis, and use the above method to obtain the preliminary projection distribution of the Y ribs of the base; S72, when the track bed unit includes a switch machine, execute S73; otherwise, execute S74; S73, constructing a base reinforcement distribution including a switch machine, comprising the following steps; S731, for the part where the base contour coincides with the switch machine cap contour, the preliminary projection distribution of the base X reinforcement and the preliminary projection distribution of the base Y reinforcement are interrupted to obtain the projection distribution of the base lower layer X reinforcement; The preliminary projection distribution of the Y reinforcement of the base is extended to the outermost edge of the switch machine cap contour to obtain the projection distribution of the Y reinforcement of the lower layer of the base; it is combined with the projection distribution of the X reinforcement of the lower layer of the base to obtain the preliminary projection distribution of the reinforcement of the lower layer of the base; S732, combining the preliminary projection distribution of the lower layer reinforcement of the base with the projection distribution of the lower layer X reinforcement of the switch obtained in S25; translating the combined projection distribution downward in the Z-axis direction to obtain the distribution of the lower layer reinforcement of the base including the switch; S733, projecting the limiting groove onto the XY plane to obtain a limiting groove projection set, first interrupting the preliminary projection distribution of the base X ribs and the preliminary projection distribution of the base Y ribs obtained in S71 at the projection of the limiting groove; then interrupting them at the point where the base contour coincides with the contour of the switch machine cap, and finally obtaining the projection distribution of the upper ribs of the base including the switch machine; translating them downward in the Z-axis direction to obtain the distribution of the upper ribs of the base including the switch machine; S74, construction excluding the distribution of base reinforcement of the switch machine: S741, translating the preliminary projection distribution obtained in S71 downward in the Z-axis direction to obtain the distribution of the lower reinforcement of the base excluding the switch machine; S742, projecting the limiting groove onto the XY plane to obtain a limiting groove projection set, firstly interrupting the projections of the base X ribs and Y ribs obtained in S71 at the limiting groove projections; then translating the interrupted projection distribution downward in the Z axis direction to obtain the upper rib distribution of the base excluding the switch machine; executing S75; S75, combining the upper reinforcement distribution of the base and the lower reinforcement distribution of the base to obtain the reinforcement distribution of the base; S76, reinforcement distribution for composite structures: The reinforcement distribution of the base obtained by S75, the lower reinforcement distribution of the combined structure ballast obtained by S2, the middle reinforcement distribution of the ballast obtained by S4 and the upper reinforcement distribution of the ballast obtained by S5 are combined according to whether there is a switch machine, and the reinforcement distribution of the combined structure is obtained and output.

10. The BIM-based intelligent modeling method for steel bars in the turnout area of ​​ballastless track according to claim 9 is characterized in that: In S732 and S741, the translation is 400mm-600mm along the Z axis; in S733 and S742, the translation is 300mm-500mm along the Z axis.