A water conservancy construction interception device and interception method
By designing a gate device with a push plate and an adjustment mechanism during water conservancy construction, the problem of the gate not being able to fit well with the gate pier was solved and a better interception effect was achieved.
Patent Information
- Application Number
- CN202411110031.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The sediment carried by the gate when opening the water flow stays directly below the gate, causing the gate to be unable to fit the bottom of the gate pier, affecting the interception effect and causing water seepage.
A water conservancy construction interception device is designed, including a gate pier, a push plate and an adjustment mechanism. The drive motor drives the push plate and gate plate to move, cleans the sediment under the gate plate, and uses a bevel gear and threaded sleeve mechanism to The bottom of the gate plate is in contact with the bottom of the gate pier to ensure the interception effect.
Effectively clean the sediment under the gate, improve the fit between the gate and the bottom of the gate pier, ensure the water flow interception effect, and avoid the impact of sediment accumulation on the interception.
Smart Images

Figure CN118621751B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water conservancy construction, and in particular to a water conservancy construction interception device and an interception method. Background Art
[0002] At present, when the gate is opened and water flows, part of the mud and sand carried by the gate will remain directly below the gate. When the gate needs to be closed to cut off the water flow, the bottom of the gate cannot contact the bottom of the gate pier due to the obstruction of the mud and sand. The cutting effect of the gate will be affected, and water will seep out from the bottom of the gate, thus failing to ensure the interception effect of the gate.
[0003] Therefore, it is necessary to provide a water conservancy construction interception device and interception method to solve the above technical problems. Summary of the invention
[0004] The object of the present invention is to provide a hydraulic construction interception device and interception method which can better clean the silt accumulated directly below the gate plate, prevent the bottom of the gate plate from failing to fit with the bottom of the gate pier, and improve the interception effect of the gate plate.
[0005] In order to solve the above technical problems, the water conservancy construction interception device provided by the present invention comprises: a gate pier, wherein a plurality of adjustment mechanisms are arranged on the gate pier, and the plurality of adjustment mechanisms all comprise: a cylinder 1, a threaded sleeve, a bevel gear 1, a bevel gear 2, a ball screw 1, two connecting blocks, a gate plate and four limit blocks, wherein the cylinder 1 is fixedly mounted on the top of the gate pier, the threaded sleeve is rotatably mounted on the cylinder 1, the bevel gear 1 is fixedly sleeved on the threaded sleeve, the bevel gear 2 is arranged on one side of the cylinder 1, the bevel gear 2 is meshed with the bevel gear 1, the ball screw 1 is threadedly mounted on the threaded sleeve, the two connecting blocks are respectively fixedly mounted on both sides of the ball screw 1, the gate plate is fixedly mounted on the bottom of the two connecting blocks, the four limit blocks are respectively fixedly mounted on the inner walls on both sides of the gate pier, and the four limit blocks are all slidably connected with the gate plate, a driving motor 1 is fixedly mounted on the top of the gate pier, and a driving motor 1 is fixedly mounted on the inner wall of the top of the gate pier. The transmission gear of the present invention is a gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of a first gear and a second gear selected from the group consisting of
[0006] Preferably, an adjustment mechanism is provided on the gate pier, the second bevel gear is fixedly sleeved on the output rod of the first driving motor, and a round block is fixedly installed on the top end of the first ball screw.
[0007] Preferably, two transverse rods are fixedly installed between the inner walls on both sides of the box body, the two transverse rods are slidably connected to the moving block, and reinforcement arms are fixedly installed on the two connecting rods.
[0008] Preferably, a accommodating cavity is provided on the gate plate, a strip groove is provided at the bottom of the accommodating cavity, the top inner wall of the strip groove is connected to the bottom inner wall of the accommodating cavity, insertion grooves are provided on both sides of the strip groove, and a placement groove is provided at the bottom of the gate pier. A ball screw three is rotatably installed on the gate plate, a driving motor four is fixedly installed on the top of the gate plate, a bevel gear three is fixedly installed on the output shafts of the ball screw three and the driving motor four, a sliding block one is threadedly installed on the ball screw three, and a recessed groove is provided at the bottom of the sliding block one, the same reinforcement plate is fixedly installed between the inner walls of both sides of the accommodating cavity, the reinforcement plate is adapted to the recessed groove, a circular long rod is fixedly installed at the bottom of the sliding block one, a linkage block is fixedly installed at the bottom end of the circular long rod, the linkage block is slidably installed in the strip groove, scrapers are fixedly installed on both sides of the linkage block, and two scrapers are respectively slidably installed in the two insertion grooves.
[0009] Preferably, rolling balls are embedded on both sides of the sliding block 1, and the two rolling balls are in contact with the inner walls on both sides of the accommodating cavity respectively.
[0010] Preferably, a circular through hole is opened on the top inner wall of the accommodating cavity, and the inner wall of the circular through hole is in three-way rotational contact with the ball screw.
[0011] Preferably, two adjustment mechanisms are provided on the gate pier, two support blocks 1 are fixedly installed on the top of the gate pier, and transfer rods 2 are rotatably installed on the two support blocks 1, and the two bevel gears 2 are respectively fixedly sleeved on one end of the two transfer rods 2, and the ends of the two transfer rods 2 away from the two bevel gears 2 are fixedly sleeved with bevel gears 4, and two support blocks 2 are fixedly installed on the top of the gate pier, and cylinders 2 are rotatably installed on the two support blocks 2, and bevel gears 5 are fixedly sleeved on the two cylinders 2, and the two bevel gears 5 are respectively connected to the two bevel gears The four wheels are meshed with each other, and the same mounting rod is rotatably installed on the two cylinders. The output shaft of the driving motor one is fixedly connected to one end of the mounting rod. Rectangular grooves are provided on the top and bottom of the mounting rod. A ball screw four is rotatably installed on the mounting rod, and two sliding blocks two are threadedly installed on the ball screw four. A rectangular clamping block is fixedly installed on the side where the two sliding blocks two are close to each other, and the two rectangular clamping blocks are respectively aligned with the two rectangular grooves. Brake rods are fixedly installed on the top and bottom of the mounting rod, and the two brake rods are respectively slidably connected to the two sliding blocks two.
[0012] Preferably, the two cylinders are each provided with a connecting hole, the two connecting holes are respectively connected to the two rectangular grooves, and the two connecting holes are adapted to the two rectangular blocks.
[0013] Preferably, positioning blocks are fixedly installed on the top and bottom ends of the ball screw rod 4, pointing blocks 1 are fixedly installed on the top and bottom of the mounting rod, pointing blocks 2 are fixedly installed on the two cylinders 2, and the two pointing blocks 1 and the two pointing blocks 2 are aligned.
[0014] The present invention also provides a water conservancy construction interception method, comprising the following steps:
[0015] S1. First, the drive motor 3 needs to be started. The output shaft of the drive motor 3 will drive the transfer rod 1 fixedly connected thereto to rotate. The transfer rod 1 drives two circular gears. The two circular gears drive the two connecting rods to gradually move downward through multiple tooth grooves. The two connecting rods drive the push plate to move downward until the bottom of the push plate is flush with the inner wall of the bottom of the gate pier. The drive motor 3 will automatically shut down and the push plate will remain at the height at that time.
[0016] S2, then start the driving motor 2, the output shaft of the driving motor 2 will drive the ball screw 2 fixedly connected thereto to rotate, during the rotation of the ball screw 2, restricted by the cooperation of the two transverse rods, the moving block will gradually move on the ball screw 2 to the position of the gate plate, because the bottom of the push plate is already flush with the bottom inner wall of the gate pier, so the push plate will generate a driving force on the sediment gathered under the gate plate during the movement, so that the sediment is pushed to one side, and the movement of the push plate follows the direction of the water flow, so that the sediment can be better taken away, until the moving block moves to contact the inner wall of the other side of the box body, at this time the push plate reaches the predetermined position, after the sediment is cleaned up, the driving motor 2 starts to rotate in the opposite direction, and drives the push plate to rotate in the opposite direction through the moving block and the two connecting rods, until the push plate is moved to the initial position;
[0017] S3. Finally, start the driving motor 1. The output shaft of the driving motor 1 will drive the bevel gear 2 fixedly connected thereto. The bevel gear 2 will drive the threaded sleeve to rotate on the cylinder 1 through the bevel gear 1. During the rotation of the cylinder 1, due to the cooperation of the four limit blocks, the ball screw 1 will drive the gate plate to move downward gradually until the bottom of the gate plate contacts the bottom inner wall of the gate pier.
[0018] Compared with the related art, the water conservancy construction interception device and interception method provided by the present invention have the following beneficial effects:
[0019] The present invention provides a water conservancy construction interception device and interception method. A push plate is arranged on one side of a gate plate. The push plate is usually suspended at a higher position. Once the gate plate is lowered to intercept the water flow, it is only necessary to start the drive motor three and the drive motor two in sequence to adjust the height and position of the push plate. The push plate is used to clean the silt at the bottom of the gate plate, provide assistance for the downward movement of the gate plate, and clean the space that the bottom of the gate plate is about to contact, so as to improve the fit between the gate plate and the inner wall of the bottom of the gate pier, thereby avoiding the accumulation of silt to affect the interception effect of the gate plate. After the push plate is used, the drive motor three and the drive motor two are started in the opposite direction to adjust the push plate to the initial position, thereby preventing the push plate from interfering with the use of the gate plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A three-dimensional schematic diagram of a first embodiment of a water conservancy construction interception device provided by the present invention;
[0021] Figure 2 for Figure 1 An enlarged schematic diagram of the frame block shown in;
[0022] Figure 3 A schematic diagram of the front cross-sectional structure of a gate pier in the first embodiment of the water conservancy construction interception device provided by the present invention;
[0023] Figure 4 for Figure 3 An enlarged schematic diagram of the gate shown in;
[0024] Figure 5 A schematic diagram of the side cross-sectional structure of the gate pier shown in the first embodiment of the water conservancy construction interception device provided by the present invention;
[0025] Figure 6 for Figure 5 An enlarged schematic diagram of the box shown in;
[0026] Figure 7 A schematic diagram of the cross-sectional structure of the cylinder 1 shown in the first embodiment of the water conservancy construction interception device provided by the present invention;
[0027] Figure 8 for Figure 7 An enlarged schematic diagram of the box shown in;
[0028] Fig. 9 A schematic diagram of a top view and cross-section structure of a frame block shown in the first embodiment of the water conservancy construction interception device provided by the present invention;
[0029] Fig.10 for Fig. 9 An enlarged schematic diagram of the frame block shown in;
[0030] Fig.11A schematic diagram of the three-dimensional structure of the second embodiment of the water conservancy construction interception device provided by the present invention;
[0031] Fig.12 A schematic diagram of the front cross-sectional structure of a gate plate shown in the second embodiment of the water conservancy construction interception device provided by the present invention;
[0032] Fig.13 for Fig.12 An enlarged schematic diagram of the gate shown in;
[0033] Fig.14 A schematic diagram of a cross-sectional structure of a gate plate in a second embodiment of a water conservancy construction interception device provided by the present invention, viewed from above;
[0034] Fig.15 for Fig.14 An enlarged schematic diagram of the gate shown in;
[0035] Fig.16 for Fig.15 The assembly diagram of the gate shown in FIG.
[0036] Fig.17 A schematic diagram of the three-dimensional structure of the third embodiment of the water conservancy construction interception device provided by the present invention;
[0037] Fig.18 for Fig.17 An enlarged schematic diagram of a ball screw 1 is shown in FIG.
[0038] Fig.19 A schematic diagram of a front cross-sectional structure of a ball screw rod 1 shown in the third embodiment of the water conservancy construction interception device provided by the present invention;
[0039] Fig. 20 for Fig.19 An enlarged schematic diagram of a ball screw 1 is shown in FIG.
[0040] Fig.21 A schematic diagram of the top view of the structure of the third embodiment of the water conservancy construction interception device provided by the present invention;
[0041] Fig. 22 for Fig.21 An enlarged schematic diagram of a ball screw 1 is shown in FIG.
[0042] Fig.23 A side cross-sectional structural schematic diagram of the support block 2 shown in the third embodiment of the water conservancy construction interception device provided by the present invention;
[0043] Fig.24 for Fig.23 An enlarged schematic diagram of support block 2 is shown in FIG.
[0044] Fig.25 for Fig.24 An enlarged view of the mounting rod is shown in FIG.
[0045] Numbers in the figure: 1, gate pier; 2, cylinder 1; 3, threaded sleeve; 4, bevel gear 1; 5, drive motor 1; 6, bevel gear 2; 7, ball screw 1; 8, connecting block; 9, gate; 10, limit block; 11, connecting block; 12, box body; 13, ball screw 2; 14, drive motor 2; 15, moving block; 16, frame block; 17, transfer rod 1; 18, circular gear; 19, drive motor 3; 20, side groove; 21, connecting rod; 22, tooth groove; 23, rectangular block; 24, push plate; 25, accommodating chamber; 2 6. Strip groove; 27. Insertion groove; 28. Placement groove; 29. Ball screw three; 30. Drive motor four; 31. Bevel gear three; 32. Recessed groove; 33. Slide block one; 34. Reinforcement plate; 35. Round long rod; 36. Linkage block; 37. Scraper; 38. Support block one; 39. Adapter rod two; 40. Bevel gear four; 41. Support block two; 42. Cylinder two; 43. Bevel gear five; 44. Mounting rod; 45. Rectangular groove; 46. Ball screw four; 47. Slide block two; 48. Rectangular clamping block; 49. Brake rod. DETAILED DESCRIPTION
[0046] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.
[0047] First embodiment:
[0048] Please refer to Figure 1-Figure 10In the first embodiment of the present invention, the water conservancy construction interception device includes: a gate pier 1, a plurality of adjustment mechanisms are arranged on the gate pier 1, and the plurality of adjustment mechanisms include: a cylinder 2, a threaded sleeve 3, a bevel gear 4, a bevel gear 6, a ball screw 7, two connecting blocks 8, a gate plate 9 and four limit blocks 10. The cylinder 2 is fixedly installed on the top of the gate pier 1, the threaded sleeve 3 is rotatably installed on the cylinder 2, the bevel gear 4 is fixedly sleeved on the threaded sleeve 3, the bevel gear 6 is arranged on one side of the cylinder 2, the bevel gear 6 is meshed with the bevel gear 4, the ball screw 7 is threadedly installed on the threaded sleeve 3, and a through hole is opened on the gate pier 1, and the through hole and the ball screw 7 are threadedly installed. The ball screw 17 is adapted, and the inner wall of the through hole does not contact the ball screw 17, so as to ensure the normal rotation of the ball screw 17 and provide sufficient activity space for the ball screw 17. The two connecting blocks 8 are respectively fixedly installed on both sides of the ball screw 17, and the gate plate 9 is fixedly installed at the bottom of the two connecting blocks 8. The top of the gate plate 9 is fixedly connected to the bottom end of the ball screw 17. The four limit blocks 10 are respectively fixedly installed on the inner walls of both sides of the gate pier 1. The four limit blocks 10 are all slidably connected with the gate plate 9. The four limit blocks 10 are distributed in a rectangular array. The gate plate 9 is slidably installed between the four limit blocks 10. The four limit blocks 10 can determine the stability of the position of the gate plate 9 and ensure the stability of the gate plate 9 and the gate pier 1, and also limits the activity tendency of the gate plate 9. A driving motor 15 is fixedly installed on the top of the gate pier 1, and two connecting blocks 11 are fixedly installed on the top inner wall of the gate pier 1. The bottom of the two connecting blocks 11 is fixedly installed with the same box body 12, and the opening of the box body 12 faces downward. A ball screw 13 is rotatably installed on the box body 12, and a driving motor 14 is fixedly installed on one side of the box body 12. The output shaft of the driving motor 14 is fixedly connected to one end of the ball screw 13, and a moving block 15 is threadedly installed on the ball screw 13. A frame block 16 is fixedly installed on the bottom of the moving block 15, and a transfer rod 17 is rotatably installed on the frame block 16. The transfer rod 17 The upper fixed sleeve is provided with two circular gears 18, and a driving motor three 19 is fixedly installed on one side of the frame block 16. The output shaft of the driving motor three 19 is fixedly connected to one end of the transfer rod one 17. Two side grooves 20 are provided on the inner wall of one side of the frame block 16, and connecting rods 21 are slidably installed in the two side grooves 20. One side of the two connecting rods 21 is provided with a plurality of tooth grooves 22, and the plurality of tooth grooves 22 are linearly distributed. The teeth on the two circular gears 18 are adapted to the plurality of tooth grooves 22. Rectangular blocks 23 are fixedly installed on the top ends of the two connecting rods 21. The rectangular blocks 23 can limit the sliding range of the connecting rods 21, and the same pushing plate 24 is fixedly installed on the bottom ends of the two connecting rods 21.
[0049] In this embodiment, an adjustment mechanism is provided on the gate pier 1, a bevel gear 26 is fixedly mounted on the output rod of the driving motor 15, a round block is fixedly installed on the top of the ball screw 17, and the round block is used to limit the moving range of the ball screw 17. In order to limit the movement trend of the moving block 15 and increase the stability of the moving block 15, two transverse rods are fixedly installed between the inner walls on both sides of the box body 12, and the two transverse rods are both slidably connected to the moving block 15, and reinforcement arms are fixedly installed on the two connecting rods 21.
[0050] In this embodiment, a water conservancy construction interception method is also provided, which is as follows:
[0051] The water flows from front to back. In the initial state, the gate plate 9 is in an ascending state, and the water flow under the gate pier 1 will flow normally. When the water flow needs to be cut off, the drive motor 3 19 needs to be started first. The output shaft of the drive motor 3 19 will drive the transfer rod 17 fixedly connected thereto to rotate, and the transfer rod 17 drives the two circular gears 18. The two circular gears 18 will drive the two connecting rods 21 to gradually move downward through a plurality of tooth grooves 22. The two connecting rods 21 drive the push plate 24 to move downward until the bottom of the push plate 24 is flush with the inner wall of the bottom of the gate pier 1. The drive motor 3 19 will be automatically closed, and the push plate 24 will remain at the height at this time.
[0052] Then, the driving motor 2 14 is started again, and the output shaft of the driving motor 2 14 will drive the ball screw 2 13 fixedly connected thereto to rotate. During the rotation of the ball screw 2 13, the moving block 15 will gradually move toward the position of the gate plate 9 on the ball screw 2 13 under the cooperation restriction of the two transverse rods. Since the bottom of the pushing plate 24 is already flush with the bottom inner wall of the gate pier 1, the pushing plate 24 will generate a driving force for the silt gathered under the gate plate 9 during the movement, so that the silt is pushed to one side. The movement of the pushing plate 24 conforms to the direction of the water flow, so that the silt can be better taken away, until the moving block 15 moves to contact the inner wall of the other side of the box body 12. At this time, the pushing plate 24 reaches the predetermined position. After the silt is cleaned up, the driving motor 2 14 starts to rotate in the opposite direction, and drives the pushing plate 24 to rotate in the opposite direction through the moving block 15 and the two connecting rods 21, until the pushing plate 24 is moved to the initial position, so as to prevent the activity space of the gate plate 9 from being blocked by the pushing plate 24.
[0053] Finally, start the driving motor 5, the output shaft of the driving motor 5 will drive the bevel gear 2 6 fixedly connected thereto, and the bevel gear 2 6 will drive the threaded sleeve 3 to rotate on the cylinder 2 through the bevel gear 4. During the rotation of the cylinder 2, due to the cooperation of the four limit blocks 10, the ball screw 7 will drive the gate plate 9 to move downward gradually until the bottom of the gate plate 9 contacts the bottom inner wall of the gate pier 1. With the shielding of the gate plate 9, the water flowing under the gate pier 1 will be cut off, thereby completing the interception.
[0054] Compared with the related art, the water conservancy construction interception device and interception method provided by the present invention have the following beneficial effects:
[0055] In the present invention, a push plate 24 is provided on one side of the gate plate 9, and the push plate 24 is usually suspended at a higher position. Once the gate plate 9 is lowered to cut off the water flow, it is only necessary to start the drive motor three 19 and the drive motor two 14 in sequence to adjust the height and position of the push plate 24. The push plate 24 is used to clean the silt at the bottom of the gate plate 9, to provide assistance for the downward movement of the gate plate 9, and to clean the space that the bottom of the gate plate 9 is about to contact, so as to improve the fit between the gate plate 9 and the inner wall of the bottom of the gate pier 1, thereby avoiding the accumulation of silt to affect the interception effect of the gate plate 9. After the push plate 24 is used, the drive motor three 19 and the drive motor two 14 are started in the opposite direction, so that the push plate 24 can be adjusted to the initial position, thereby preventing the push plate 24 from interfering with the use of the gate plate 9.
[0056] Second embodiment:
[0057] Based on the water conservancy construction interception device and interception method provided in the first embodiment of the present application, the second embodiment of the present application proposes another water conservancy construction interception device and interception method. The second embodiment is only a preferred embodiment of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.
[0058] The second embodiment of the present invention is further described below in conjunction with the accompanying drawings and implementation modes.
[0059] Please refer to Figure 11-Figure 16, in the water conservancy construction interception device: a accommodating chamber 25 is provided on the gate plate 9, a strip groove 26 is provided at the bottom of the accommodating chamber 25, the top inner wall of the strip groove 26 is connected to the bottom inner wall of the accommodating chamber 25, and insertion grooves 27 are provided on both sides of the strip groove 26, and a placement groove 28 is provided at the bottom of the gate pier 1, and the placement groove 28 is used to accommodate the driving motor four 30 and two bevel gears three 31 mentioned below, a ball screw three 29 is rotatably installed on the gate plate 9, a driving motor four 30 is fixedly installed on the top of the gate plate 9, and a bevel gear three 31 is fixedly installed on the top of the ball screw three 29 and the output shaft of the driving motor four 30, and the two bevel gears three 31 are meshed with each other, and a sliding block one 33 is threadedly installed on the ball screw three 29, and the sliding block one 33 is slidably installed in the accommodating chamber 25, and the accommodating chamber 2 5 is adapted to the sliding block 1 33, so that the movement of the sliding block 1 33 can be restricted by the accommodating chamber 25, so that the sliding block 1 33 can only slide back and forth up and down in the accommodating chamber 25, and a recessed groove 32 is provided at the bottom of the sliding block 1 33. A same reinforcing plate 34 is fixedly installed between the inner walls of both sides of the accommodating chamber 25, and the reinforcing plate 34 is rotatably connected to the ball screw 3 29. The reinforcing plate 34 is adapted to the recessed groove 32 to ensure that the reinforcing plate 34 can slide into the recessed groove 32. A round long rod 35 is fixedly installed at the bottom of the sliding block 1 33, and a linkage block 36 is fixedly installed at the bottom of the round long rod 35. The linkage block 36 is slidably installed in the strip groove 26, and scrapers 37 are fixedly installed on both sides of the linkage block 36. The two scrapers 37 are respectively slidably installed in the two insertion grooves 27.
[0060] In order to increase the stability of the sliding block 33 and reserve sufficient movable space for the ball screw 3 29, in the present embodiment, rolling balls are embedded on both sides of the sliding block 33, and the two rolling balls are respectively in contact with the inner walls on both sides of the accommodating cavity 25. A circular through hole is opened on the top inner wall of the accommodating cavity 25, and the inner wall of the circular through hole is in rotational contact with the ball screw 3 29.
[0061] In this embodiment
[0062] The bottom of the gate pier 1 is in contact with water for a long time, and some aquatic plants and animals are easily attached. These attachments will affect the subsequent downward movement of the gate plate 9. In order to reduce the impact on the gate plate 9, before the gate plate 9 moves down to intercept the flow, it is necessary to start the drive motor 4 30. The output shaft of the drive motor 4 30 will drive the bevel gear 3 31 fixedly connected thereto, and drive the ball screw 3 29 with the cooperation of the two bevel gears 31. During the rotation of the ball screw 3 29, the sliding block 1 33 will be restricted by the accommodating cavity 25 and will gradually move downward on the ball screw 3 29. The sliding block 1 33 will then drive the linkage block 36 through the circular long rod 35, and the linkage block 36 will drive the two scrapers 37. During the movement, the two scrapers 37 will contact the inner walls on both sides of the gate pier 1. The attachments on the inner walls on both sides of the gate pier 1 are gradually scraped off until the top inner wall of the recessed groove 32 contacts the reinforcing plate 34. At this time, the sliding block 33 has been moved to the predetermined position. At this time, the two scrapers 37 contact the bottom inner wall of the gate pier 1, completing the cleaning of the gate pier 1. Then the driving motor 4 30 will start in the opposite direction, and then move the linkage block 36 together with the two scrapers 37 into the gate plate 9. Then start the driving motor 1 5 to lower the gate plate 9. After cleaning the gate pier 1, the gate plate 9 will not be stuck during the downward movement, so that the sliding of the gate plate 9 is smoother, which can prevent the movement of the gate plate 9 from being affected by the bottom mud and sand, and can also avoid the gate plate 9 from being hindered by the attachments, thereby facilitating the movement of the gate plate 9.
[0063] Third embodiment:
[0064] Based on the water conservancy construction interception device and interception method provided in the first and second embodiments of the present application, the third embodiment of the present application proposes another water conservancy construction interception device and interception method. The third embodiment is only a preferred mode of the first or second embodiment, and the implementation of the third embodiment will not affect the independent implementation of the first or second embodiment.
[0065] The third embodiment of the present invention is further described below in conjunction with the accompanying drawings and implementation modes.
[0066] Please refer to Figure 17-Figure 25In the water conservancy construction interception device: two adjustment mechanisms are arranged on the gate pier 1, two support blocks 38 are fixedly installed on the top of the gate pier 1, and transfer rods 39 are rotatably installed on the two support blocks 38, two bevel gears 26 are respectively fixedly sleeved on the left ends of the two transfer rods 29, and the two bevel gears 26 are respectively meshed with the two bevel gears 4, and the ends of the two transfer rods 29 away from the two bevel gears 26 are fixedly sleeved with bevel gears 40, and two support blocks 241 are fixedly installed on the top of the gate pier 1, and cylinders 242 are rotatably installed on the two support blocks 241, and bevel gears 543 are fixedly sleeved on the two cylinders 242, and the two bevel gears 543 are respectively meshed with the two bevel gears 40, and the same mounting rod 44 is rotatably installed on the two cylinders 242, driving the horse The output shaft of the lever 45 is fixedly connected to one end of the mounting rod 44, and rectangular grooves 45 are provided at the top and bottom of the mounting rod 44. A ball screw 46 is rotatably installed on the mounting rod 44, and the ball screw 46 is provided with two sections of threads with the same rotation direction. Two sliding blocks 2 47 are threadedly installed on the ball screw 46, and rectangular clamping blocks 48 are fixedly installed on the sides of the two sliding blocks 2 47 close to each other. The two rectangular clamping blocks 48 are respectively aligned with the two rectangular grooves 45, and the rectangular clamping block 48 located on the top is slidably installed in the corresponding rectangular groove 45. Braking rods 49 are fixedly installed on the top and bottom of the mounting rod 44, and the two brake rods 49 are respectively slidably connected to the two sliding blocks 2 47. The two brake rods 49 can limit the movement tendency of the two sliding blocks 2 47 and increase the stability of the two sliding blocks 2 47.
[0067] In order to provide sliding space for the two rectangular blocks 48 and ensure that the two rectangular blocks 48 can slide smoothly into the two rectangular grooves 45, in this method, connecting holes are opened on the two cylinders 42, and the two connecting holes are respectively connected to the two rectangular grooves 45, and the two connecting holes are adapted to the two rectangular blocks 48.
[0068] In this embodiment, positioning blocks are fixedly installed on the top and bottom ends of the ball screw four 46. The two positioning blocks can facilitate the rotation of the ball screw four 46 and prevent the two sliding blocks two 47 from slipping off the ball screw four 46. Pointing blocks one are fixedly installed on the top and bottom of the mounting rod 44, and pointing blocks two are fixedly installed on the two cylinders two 42. The two pointing blocks one and the two pointing blocks two are aligned with each other. The two pointing blocks one and the two pointing blocks two can be used to conveniently determine whether the two rectangular grooves 45 are aligned with the two connecting holes, thereby facilitating the two rectangular clamping blocks 48 to pass through the two connecting holes and accurately insert into the two rectangular grooves 45.
[0069] In this embodiment
[0070] Due to the long-term use of the gate plate 9, cracks or other damages are prone to appear on the gate plate 9. In order to ensure the normal use of the gate plate 9 and reserve time for repairing or replacing the gate plate 9, two gate plates 9 can usually be set on the gate pier 1, one of which is used daily, and the other gate plate 9 is usually suspended on the gate pier 1 as a spare, and the parts set on the two gate plates 9 are the same.
[0071] When the gate plate 9 in use is damaged and needs to be replaced, first ensure that the gate plate 9 in use is in a raised state. At this time, the rectangular block 48 located at the top is stuck in the rectangular groove 45 located at the top, and the rectangular block 48 located at the bottom is outside the rectangular groove 45. Therefore, at this time, the mounting rod 44 has no driving effect on the cylinder 2 42 close to the drive motor 1 5.
[0072] At this time, it is necessary to rotate the ball screw four 46. During the rotation of the ball screw four 46, the two sliding blocks 2 47 will be restricted by the cooperation of the two brake rods 49, which will make the two sliding blocks 2 47 move on the ball screw four 46 at the same time. The two sliding blocks 2 47 drive the two rectangular blocks 48, so that the rectangular block 48 located on the upper side will gradually move out of the corresponding rectangular groove 45, and the rectangular block 48 located on the lower side will gradually move into the corresponding rectangular groove 45. At this time, the cylinder two 42 close to the driving motor one 5 will be connected to the mounting rod 44, conversely, the other cylinder two 42 away from the driving motor one 5 will release the connection with the mounting rod 44, and then the driving motor one 5 will be started again, and the driving motor one 5 will drive the mounting rod 44. The mounting rod 44 will drive the cylinder two 42 close to the driving motor one 5 through the rectangular block 48 connected thereto, and the cylinder two 42 will drive the bevel gear five 43 connected thereto, and the bevel gear five 43 will be connected to the bevel gear five 43 through the transfer rod two 39 and the cooperation of bevel gear four 40 and bevel gear one 4 will drive the corresponding threaded sleeve 3. The cylinder two 42 close to the driving motor one 5 corresponds to the gate plate 9 located at the rear and in a standby state. Therefore, at this time, the threaded sleeve 3 will drive the spare gate plate 9 to gradually move downward to replace the previously used gate plate 9 for intercepting flow. Since the connection between the cylinder two 42 far away from the driving motor one 5 and the mounting rod 44 has been gradually released, the mounting rod 44 will not cause any impact on the cylinder two 42 during its rotation. Therefore, the gate plate 9 that is located in the front and needs to be repaired and replaced and has been raised in advance will maintain its height unchanged and be exposed above the water surface, thereby facilitating its maintenance. In addition, as mentioned above, sufficient activity space is reserved for the moving block 15 in the box body 12. Therefore, when the spare gate plate 9 is used in a timely manner, the push plate 24 can also clean up the mud and sand at the bottom of the spare gate plate 9 during the movement, thereby solving the worries about the use of the gate plate 9.
[0073] The above are only embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A water conservancy construction interception device, comprising a gate pier (1), characterized in that: The gate pier (1) is provided with a plurality of adjustment mechanisms, each of which comprises: a cylinder (2), a threaded sleeve (3), a bevel gear (4), a bevel gear (6), a ball screw (7), two connecting blocks (8), a gate plate (9) and four limit blocks (10), wherein the cylinder (2) is fixedly mounted on the top of the gate pier (1), the threaded sleeve (3) is rotatably mounted on the cylinder (2), the bevel gear (4) is fixedly sleeved on the threaded sleeve (3), the bevel gear (6) is arranged on one side of the cylinder (2), and the bevel gear (6) and the bevel gear (4) are rotatably mounted on the cylinder (2). ), the ball screw rod (7) is threadedly mounted on the threaded sleeve (3), the two connecting blocks (8) are respectively fixedly mounted on both sides of the ball screw rod (7), the gate plate (9) is fixedly mounted on the bottom of the two connecting blocks (8), the four limit blocks (10) are respectively fixedly mounted on the inner walls on both sides of the gate pier (1), and the four limit blocks (10) are all slidably connected to the gate plate (9), a driving motor (5) is fixedly mounted on the top of the gate pier (1), two connecting blocks (11) are fixedly mounted on the inner wall of the top of the gate pier (1), and the bottoms of the two connecting blocks (11) are fixedly mounted with The same box body (12) has a second ball screw (13) rotatably mounted on the box body (12), a second drive motor (14) is fixedly mounted on one side of the box body (12), an output shaft of the second drive motor (14) is fixedly connected to one end of the second ball screw (13), a moving block (15) is threadedly mounted on the second ball screw (13), a frame block (16) is fixedly mounted on the bottom of the moving block (15), a transfer rod (17) is rotatably mounted on the frame block (16), two circular gears (18) are fixedly sleeved on the transfer rod (17), and one side of the frame block (16) is fixedly mounted A driving motor 3 (19) is installed, the output shaft of the driving motor 3 (19) is fixedly connected to one end of the transfer rod 1 (17), two side grooves (20) are provided on the inner wall of one side of the frame block (16), connecting rods (21) are slidably installed in the two side grooves (20), one side of the two connecting rods (21) is provided with a plurality of tooth grooves (22), the two circular gears (18) are adapted to the plurality of tooth grooves (22), the top ends of the two connecting rods (21) are fixedly installed with rectangular blocks (23), and the bottom ends of the two connecting rods (21) are fixedly installed with the same push plate (24).
2. The water conservancy construction intercepting device according to claim 1, characterized in that: The gate pier (1) is provided with an adjustment mechanism, the bevel gear 2 (6) is fixedly sleeved on the output rod of the drive motor 1 (5), and a round block is fixedly mounted on the top end of the ball screw 1 (7).
3. The water conservancy construction interception device according to claim 2, characterized in that: Two transverse rods are fixedly mounted between the inner walls on both sides of the box body (12), the two transverse rods are slidably connected to the moving block (15), and reinforcement arms are fixedly mounted on the two connecting rods (21).
4. The water conservancy construction interception device according to claim 1, characterized in that: The gate plate (9) is provided with a receiving chamber (25), the bottom of the receiving chamber (25) is provided with a strip groove (26), the top inner wall of the strip groove (26) is connected to the bottom inner wall of the receiving chamber (25), both sides of the strip groove (26) are provided with insertion grooves (27), the bottom of the gate pier (1) is provided with a placement groove (28), a ball screw rod 3 (29) is rotatably mounted on the gate plate (9), a drive motor 4 (30) is fixedly mounted on the top of the gate plate (9), a bevel gear 3 (31) is fixedly mounted on the output shafts of the ball screw rod 3 (29) and the drive motor 4 (30), and the ball screw rod 3 (29) is provided with a screw rod 4 (29) on the top of the ball screw rod 3 (29). A sliding block (33) is installed on the groove, and a recessed groove (32) is opened at the bottom of the sliding block (33). A same reinforcing plate (34) is fixedly installed between the inner walls of both sides of the accommodating cavity (25), and the reinforcing plate (34) is adapted to the recessed groove (32). A round long rod (35) is fixedly installed on the bottom of the sliding block (33), and a linkage block (36) is fixedly installed at the bottom end of the round long rod (35). The linkage block (36) is slidably installed in the strip groove (26). Scrapers (37) are fixedly installed on both sides of the linkage block (36), and the two scrapers (37) are respectively slidably installed in the two insertion grooves (27).
5. The water conservancy construction interception device according to claim 4, characterized in that: Rolling balls are inlaid on both sides of the sliding block 1 (33), and the two rolling balls are in contact with the inner walls on both sides of the accommodating cavity (25) respectively.
6. The water conservancy construction interception device according to claim 4, characterized in that: A circular through hole is provided on the top inner wall of the accommodating cavity (25), and the inner wall of the circular through hole is in rotational contact with the ball screw rod 3 (29).
7. The water conservancy construction intercepting device according to claim 4, characterized in that: The gate pier (1) is provided with two adjustment mechanisms. Two support blocks (38) are fixedly mounted on the top of the gate pier (1). Transfer rods (39) are rotatably mounted on the two support blocks (38). The two bevel gears (6) are respectively fixedly sleeved on one end of the two transfer rods (39). The ends of the two transfer rods (39) away from the two bevel gears (6) are fixedly sleeved with bevel gears (40). The top of the gate pier (1) is fixedly mounted with two support blocks (41). The two support blocks (41) are rotatably mounted with cylinders (42). The two cylinders (42) are fixedly sleeved with bevel gears (5) (43). The two bevel gears (5) (43) are respectively meshed with the two bevel gears (40). The two cylinders (42) are rotatably mounted with a same mounting rod (44), the output shaft of the driving motor (5) is fixedly connected to one end of the mounting rod (44), the top and bottom of the mounting rod (44) are both provided with rectangular grooves (45), the mounting rod (44) is rotatably mounted with a ball screw (46), the ball screw (46) is threadedly mounted with two sliding blocks (47), the two sliding blocks (47) are fixedly mounted with a rectangular clamping block (48) on one side close to each other, the two rectangular clamping blocks (48) are respectively aligned with the two rectangular grooves (45), the top and bottom of the mounting rod (44) are fixedly mounted with a brake rod (49), the two brake rods (49) are respectively slidably connected with the two sliding blocks (47).
8. The water conservancy construction intercepting device according to claim 7, characterized in that: The two cylinders (42) are each provided with a communicating hole, the two communicating holes are respectively connected to the two rectangular grooves (45), and the two communicating holes are adapted to the two rectangular blocks (48).
9. The water conservancy construction intercepting device according to claim 7, characterized in that: Positioning blocks are fixedly mounted on the top and bottom ends of the ball screw rod 4 (46), pointing blocks 1 are fixedly mounted on the top and bottom ends of the mounting rod (44), and pointing blocks 2 are fixedly mounted on the two cylinders 2 (42), and the two pointing blocks 1 and the two pointing blocks 2 are aligned with each other.
10. A method for intercepting flow in water conservancy construction using the water conservancy construction intercepting device according to claim 3, characterized in that: The following steps are involved: S1. First, the drive motor 3 (19) needs to be started. The output shaft of the drive motor 3 (19) will drive the transfer rod 1 (17) fixedly connected thereto to rotate. The transfer rod 1 (17) drives the two circular gears (18). The two circular gears (18) drive the two connecting rods (21) to gradually move downward through a plurality of tooth grooves (22). The two connecting rods (21) then drive the push plate (24) to move downward until the bottom of the push plate (24) is flush with the bottom inner wall of the gate pier (1). The drive motor 3 (19) will automatically shut down and the push plate (24) will remain at the height at that time. S2. Then, the second drive motor (14) is started. The output shaft of the second drive motor (14) drives the second ball screw (13) fixedly connected thereto to rotate. During the rotation of the second ball screw (13), the moving block (15) is restricted by the cooperation of the two transverse rods and gradually moves on the second ball screw (13) toward the position of the gate plate (9). Since the bottom of the push plate (24) is flush with the bottom inner wall of the gate pier (1), the push plate (24) will push the mud accumulated under the gate plate (9) during the movement. The sand generates a driving force, so that the silt is pushed to one side, and the movement of the push plate (24) follows the direction of the water flow, so that the silt can be better taken away, until the moving block (15) moves to contact the inner wall of the other side of the box body (12), at which time the push plate (24) reaches a predetermined position. After the silt is cleaned, the second drive motor (14) starts to rotate in the opposite direction, and drives the push plate (24) to rotate in the opposite direction through the moving block (15) and the two connecting rods (21), until the push plate (24) is moved to the initial position; S3. Finally, the drive motor 1 (5) is started. The output shaft of the drive motor 1 (5) drives the bevel gear 2 (6) fixedly connected thereto. The bevel gear 2 (6) drives the threaded sleeve (3) to rotate on the cylinder 1 (2) through the bevel gear 1 (4). During the rotation of the cylinder 1 (2), the four limit blocks (10) cooperate to cause the ball screw 1 (7) to drive the gate plate (9) to gradually move downward until the bottom of the gate plate (9) contacts the bottom inner wall of the gate pier (1).