A method for installing a super large floating crane herringbone frame

Through hinge pin connection and precise positioning technology, the rapid overall lifting and welding of the super-large floating crane herringbone is achieved, which solves the problems of complex installation and tedious operation, and improves the installation efficiency and accuracy.

CN118637505BActive Publication Date: 2024-10-22NANTONG ZHENHUA HEAVY EQUIP MFG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411110368.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-22
Estimated Expiration
2044-08-14

AI Technical Summary

Technical Problem

The installation process of the super-large floating crane herringbone is complicated and the operation is cumbersome. The conventional method requires lifting the diagonal brace and front legs in two times, resulting in low installation efficiency and troublesome assembly and welding.

Method used

A hinged pin connection is used to set up diagonal braces at the pier, and the whole body is hoisted onto the ship. The angle and position are adjusted through the limit plate, total station and Kama to achieve rapid installation and welding of the diagonal braces and front legs.

Benefits of technology

Through integral hoisting and precise positioning, the installation efficiency is improved, the complexity of split hoisting is reduced, and the accurate installation and welding of the diagonal brace and front legs is ensured, saving time and manpower.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118637505B_ABST
    Figure CN118637505B_ABST
Patent Text Reader

Abstract

The invention relates to a method for installing a super-large floating crane herringbone frame, which is characterized by: S1: marking a floating ship; S2: installing a diagonal brace; S3: putting a front leg assembly on board; S4: welding a front leg assembly; S5: putting a rear leg of the herringbone frame on board; S6: welding a rear leg of the herringbone frame; by adopting a hinged arrangement mode of the diagonal brace and the front leg, the diagonal brace is firstly hinged to the front leg at a dock, and then hoisted onto the floating ship, the angle between the diagonal brace and the front leg is adjusted on the floating ship, and the angle between the front leg and the diagonal brace is locked and limited by a pin shaft; then the diagonal brace is welded and assembled together with the front leg on the floating ship, and in this assembly mode, the front leg and the diagonal brace are hoisted in an integral manner, which saves the hoisting time, and the diagonal brace and the front leg are firstly hinged and positioned, and then locked and limited in a manner, so that the installation of the diagonal brace can be quickly realized, thereby avoiding the problem of low efficiency of split hoisting positioning connection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ships, and in particular to a method for installing a super-large floating crane herringbone frame. Background Art

[0002] The herringbone frame on the super-large floating crane is a structure used to fix the boom through wire ropes. Due to the large size of the herringbone frame and the inconvenience of installation, the herringbone frame is usually divided into the front leg segment and the rear leg segment for separate hoisting, and finally welded on the floating ship;

[0003] However, the front legs of conventional A-frames need to be supported by diagonal braces during hoisting. A common method is to hoist the A-frame onto a floating vessel, then preliminarily weld the diagonal braces to the front legs, and then remove the diagonal braces after the rear legs are welded. This diagonal brace structure is separated from the front legs, and at least two hoisting operations are required to achieve the installation of the diagonal brace and the front legs on the floating vessel, which has low installation efficiency and troublesome welding. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a method for installing a super-large floating crane herringbone frame, which can solve the problems of complex installation procedures and cumbersome operations of the general traditional super-large floating crane herringbone frame.

[0005] In order to solve the above technical problems, the technical solution of the present invention is: a method for installing a super large floating crane herringbone frame, and its innovation lies in: the specific installation method is as follows:

[0006] S1: Floating boat marking: re-measure the size and level of the overtime surface structure where the hull A-frame is installed; take the center line of the floating boat as the reference, mark the positioning cross center line of the front leg, diagonal brace and rear leg;

[0007] S2: Installation of diagonal braces: The front legs of the herringbone frame are transferred to the dock, and the front legs of the herringbone frame are hoisted by a floating crane. The diagonal braces are connected to the outer contour of the front legs of the herringbone frame through a hinge pin, and the diagonal braces are fixed by another pin shaft to form the angle between the front legs of the herringbone frame and the diagonal braces. Finally, the front leg assembly is turned over by a floating crane and waits for hoisting onto the ship.

[0008] S3: Front leg assembly on board: draw lines on the floating boat to arrange the front leg limit plates, which are used to limit the front leg when adjusting the position. The limit plates need to be arranged in line with the hull strong structure; use floating crane to hoist the front leg assembly on board; after hoisting the front leg assembly on board, position it according to the ground sample line. After the angle is adjusted to the right position, use the total station to measure the size from the upper end of the front leg to the deck surface, and use this as a basis to draw lines to trim the margin of the lower end of the front leg, and make a bevel;

[0009] S4: Welding of front leg assembly: After the pre-welding dimension inspection is completed, the left and right chords are welded symmetrically according to the welding requirements, and the flaw detection inspection is carried out; the bottom welding of the lower end of the front leg and the deck surface is completed, and the upper end of the product diagonal brace and the lower end of the diagonal brace are welded to the deck surface, and the floating crane is unhooked; after the welding inspection is completed, the process hinge point and scaffolding platform at the diagonal brace closing mouth are removed, and 3mm grinding allowance is reserved when cutting, and the parent material must not be damaged. After cutting, the paint is repaired and the main lifting ear of the front leg is retained;

[0010] S5: Loading the rear legs of the herringbone frame onto the ship: Transfer the rear legs of the herringbone frame to the dock, re-measure the size of the longitudinal node plate opening at the rear leg rib position of the floating ship, take multiple points of measurement up and down, and adjust the deviation in advance in combination with the size of the lower notch of the rear legs of the herringbone frame; install the positioning block frame at the rear legs, and use the original shipping triangular block frame; use the floating crane to hoist the rear legs of the herringbone frame onto the ship; and when hoisting onto the ship, turn the horizontal rear legs of the herringbone frame over to an inclined state; hoist the rear leg assembly onto the ship at an inclined state of 17°; slowly insert the rear legs into the longitudinal node plate at the rear leg rib position of the floating ship, and then slowly lower the hook head, The lower end of the rear leg is placed on the deck surface, and the deck surface is padded with wooden boards in advance; the left hook of the floating crane is slowly de-stressed, and the right hook is simultaneously increased in force, until the right hook carries no less weight than the front leg, and the left hook is completely unhooked; the floating crane is slowly moved upward as a whole, and the movement of the floating crane drives the inclination angle of the rear leg from 17° to 2°-3° and then stops; while moving, the wire rope of the right hook is simultaneously tightened to ensure that the right hook remains stressed and the lower end of the rear leg remains on the ground; after the right leg is erected to an angle of 2°-3°, the right hook is slowly lifted until the rear leg is fully erected, at which time the right hook is fully loaded and the rear leg is completely off the ground;

[0011] S6: Welding of the rear legs of the A-frame: Use a floating crane to adjust the rear legs of the A-frame, position the lower end according to the ground sample line, and position the upper closing mouth using the process guide plate; position the dimensions of the ship width and length direction on the lower deck surface, adjust the staggered sides and gaps of the upper closing mouth to the theoretical dimensions, and after the overall verticality of the rear legs is ≤20mm, use a card to fix them; install the transverse node plate at the lower end of the rear legs; and weld according to welding requirements.

[0012] Furthermore, when the S3 front leg assembly is on board and the front leg is positioned and adjusted, in order to prevent the diagonal brace from affecting its angle, the lower end of the diagonal brace needs to be raised first; the margin of the lower end of the front leg is trimmed and cut into place, and it is fixed with a cama after it is adjusted to the theoretical size; pay attention to fine-tuning the node plate of the lower end of the front leg so that it is aligned with the hull structure and the misalignment deviation is ≤3mm; adjust the angle of the diagonal brace, open the two sides, mark and trim the margin of the lower end of the diagonal brace, and make a bevel according to the requirements of the drawing; trim the margin of the diagonal brace into place, adjust the size to the theoretical size, and then fix it with a cama; report the size before welding.

[0013] Furthermore, in the welding of the S4 front leg assembly: welding dimension inspection requirements: the height from the deck surface to the upper end of the front leg is required to be 46964±5mm; the front leg positioning deviation is ≤5mm, and the node plate and hull structure reinforcement misalignment deviation is ≤3mm; the diagonal brace and front leg installation angle deviation must be ≤0.01°, and the deviation between the tube center and the corresponding rib position is ≤10mm.

[0014] Furthermore, in the welding of the rear legs of the S6 A-frame: the hook can be removed after 1 / 3 of the base welding of the upper and lower closing mouths of the rear legs is completed; the three process supports at the upper and lower parts of the front and rear legs can be removed using the auxiliary hook of the gantry crane after the base welding is completed; the scaffolding platform at the closing mouth of the front leg needs to be removed after the welding and flaw detection of the closing mouth are completed, the sealing and flaw detection of the process holes are completed, and the paint repair is in place; when dismantling, pay attention to protecting the paint; the height requirement from the deck surface to the upper plane of the upper end beam is 53646±15mm; the positioning deviation of the rear leg is ≤10mm, and the misalignment deviation of the node plate and the hull structure is ≤3mm; the overall verticality deviation of the rear leg is required to be ≤20mm.

[0015] The advantages of the present invention are:

[0016] 1) In the present invention, the diagonal brace and the front leg are hingedly arranged, the diagonal brace is first hinged to the front leg at the dock, and then hoisted onto the floating boat, the angle between the diagonal brace and the front leg is adjusted on the floating boat, and the angle between the front leg and the diagonal brace is locked and limited by a pin shaft; then the diagonal brace and the front leg are welded and assembled together on the floating boat. This assembly method hoists the front leg and the diagonal brace in an integral manner, saving the hoisting work, and the diagonal brace and the front leg are first hinged and positioned, and then locked and limited, so that the diagonal brace can be quickly installed, avoiding the problem of low efficiency of split hoisting positioning connection. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0018] Figure 1 The present invention is a flow chart of a method for installing a super-large floating crane herringbone frame.

[0019] Figures 2 to 7 The present invention is a diagram showing the installation state of a super-large floating crane herringbone frame. DETAILED DESCRIPTION

[0020] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0021] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0022] like Figures 1 to 7 The installation method of a super large floating crane herringbone frame is shown in the figure. The specific installation method is as follows:

[0023] S1: Floating boat marking: re-measure the size and level of the overtime surface structure where the hull A-frame is installed; take the center line of the floating boat as the reference, mark the positioning cross center line of the front leg, diagonal brace and rear leg;

[0024] S2: Installation of diagonal braces: The front legs of the herringbone frame are transferred to the dock, and the front legs of the herringbone frame are hoisted by a floating crane. The diagonal braces are connected to the outer contour of the front legs of the herringbone frame through a hinge pin, and the diagonal braces are fixed by another pin shaft to form the angle between the front legs of the herringbone frame and the diagonal braces. Finally, the front leg assembly is turned over by a floating crane and waits for hoisting onto the ship.

[0025] S3: Front leg assembly on board: draw lines on the floating boat to arrange the front leg limit plates, which are used to limit the front leg when adjusting the position. The limit plates need to be arranged in line with the hull strong structure; use floating crane to hoist the front leg assembly on board; after hoisting the front leg assembly on board, position it according to the ground sample line. After the angle is adjusted to the right position, use the total station to measure the size from the upper end of the front leg to the deck surface, and use this as a basis to draw lines to trim the margin of the lower end of the front leg, and make a bevel;

[0026] S4: Welding of front leg assembly: After the pre-welding dimension inspection is completed, the left and right chords are welded symmetrically according to the welding requirements, and the flaw detection inspection is carried out; the bottom welding of the lower end of the front leg and the deck surface is completed, and the upper end of the product diagonal brace and the lower end of the diagonal brace are welded to the deck surface, and the floating crane is unhooked; after the welding inspection is completed, the process hinge point and scaffolding platform at the diagonal brace closing mouth are removed, and 3mm grinding allowance is reserved when cutting, and the parent material must not be damaged. After cutting, the paint is repaired and the main lifting ear of the front leg is retained;

[0027] S5: Loading the rear legs of the herringbone frame onto the ship: Transfer the rear legs of the herringbone frame to the dock, re-measure the size of the longitudinal node plate opening at the rear leg rib position of the floating ship, take multiple points of measurement up and down, and adjust the deviation in advance in combination with the size of the lower notch of the rear legs of the herringbone frame; install the positioning block frame at the rear legs, and use the original shipping triangular block frame; use the floating crane to hoist the rear legs of the herringbone frame onto the ship; and when hoisting onto the ship, turn the horizontal rear legs of the herringbone frame over to an inclined state; hoist the rear leg assembly onto the ship at an inclined state of 17°; slowly insert the rear legs into the longitudinal node plate at the rear leg rib position of the floating ship, and then slowly lower the hook head, The lower end of the rear leg is placed on the deck surface, and the deck surface is padded with wooden boards in advance; the left hook of the floating crane is slowly de-stressed, and the right hook is simultaneously increased in force, until the right hook carries no less weight than the front leg, and the left hook is completely unhooked; the floating crane is slowly moved upward as a whole, and the movement of the floating crane drives the inclination angle of the rear leg from 17° to 2°-3° and then stops; while moving, the wire rope of the right hook is simultaneously tightened to ensure that the right hook remains stressed and the lower end of the rear leg remains on the ground; after the right leg is erected to an angle of 2°-3°, the right hook is slowly lifted until the rear leg is fully erected, at which time the right hook is fully loaded and the rear leg is completely off the ground;

[0028] S6: Welding of the rear legs of the A-frame: Use a floating crane to adjust the rear legs of the A-frame, position the lower end according to the ground sample line, and position the upper closing mouth using the process guide plate; position the dimensions of the ship width and length direction on the lower deck surface, adjust the staggered sides and gaps of the upper closing mouth to the theoretical dimensions, and after the overall verticality of the rear legs is ≤20mm, use a card to fix them; install the transverse node plate at the lower end of the rear legs; and weld according to welding requirements.

[0029] When the S3 front leg assembly is on board, in order to prevent the diagonal brace from affecting its angle during positioning and adjustment of the front leg, the lower end of the diagonal brace needs to be raised first; the margin of the lower end of the front leg is trimmed and cut into place, and it is fixed with a cama after adjusting it to the theoretical size; pay attention to fine-tuning the node plate at the lower end of the front leg so that it is aligned with the hull structure, and the misalignment deviation is ≤3mm; adjust the diagonal brace angle, open the two sides, mark and trim the margin of the lower end of the diagonal brace, and make a bevel according to the requirements of the drawing; trim the margin of the diagonal brace into place, adjust the size to the theoretical size, and fix it with a cama; report the size before welding.

[0030] During the welding of S4 front leg assembly: welding dimension inspection requirements: the height from the deck surface to the upper end of the front leg is required to be 46964±5mm; the positioning deviation of the front leg is ≤5mm, and the misalignment deviation of the node plate and the hull structure is ≤3mm; the installation angle deviation of the diagonal brace and the front leg must be ≤0.01°, and the deviation between the center of the pipe and the corresponding rib position is ≤10mm.

[0031] During the welding of the rear legs of the S6 A-frame: the hook can be removed after 1 / 3 of the base welding of the upper and lower closing mouths of the rear legs is completed; the three process supports at the upper and lower parts of the front and rear legs can be removed using the auxiliary hook of the gantry crane after the base welding is completed; the scaffolding platform at the closing mouth of the front leg needs to be removed after the welding and flaw detection of the closing mouth are completed, the sealing and flaw detection of the process holes are completed, and the paint repair is in place; when removing, pay attention to protecting the paint; the height from the deck surface to the upper plane of the upper end beam is required to be 53646±15mm; the positioning deviation of the rear leg is ≤10mm, and the misalignment deviation of the node plate and the hull structure is ≤3mm; the overall verticality deviation of the rear leg is required to be ≤20mm.

[0032] Those skilled in the art should understand that the present invention is not limited to the above-mentioned embodiments. The above-mentioned embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may be subject to various changes and improvements, and these changes and improvements shall all fall within the scope of the present invention claimed for protection.

Claims

1. A method for installing a super large floating crane herringbone frame, characterized in that: The specific installation method is as follows: S1: Floating boat marking: Re-measure the size and level of the deck surface structure where the hull A-frame is installed; take the center line of the floating boat as the reference, mark the positioning cross center line of the front leg, diagonal brace and rear leg; S2: Installation of diagonal braces: The front legs of the herringbone frame are transferred to the dock, and the front legs of the herringbone frame are hoisted by a floating crane. The diagonal braces are connected to the outer contour of the front legs of the herringbone frame through a hinge pin, and the diagonal braces are fixed by another pin shaft to form the angle between the front legs of the herringbone frame and the diagonal braces. Finally, the front leg assembly is turned over by a floating crane and waits for hoisting onto the ship. S3: Front leg assembly on board: draw lines on the floating boat to arrange the front leg limit plates, which are used to limit the front leg when adjusting the position. The limit plates need to be arranged in line with the hull strong structure; use floating crane to hoist the front leg assembly on board; after hoisting the front leg assembly on board, position it according to the ground sample line. After the angle is adjusted to the right position, use the total station to measure the size from the upper end of the front leg to the deck surface, and use this as a basis to draw lines to trim the margin of the lower end of the front leg, and make a bevel; S4: Welding of front leg assembly: After the pre-welding dimension inspection is completed, the left and right chords are welded symmetrically according to the welding requirements, and the flaw detection inspection is carried out; the bottom welding of the lower end of the front leg and the deck surface is completed, and the upper end of the product diagonal brace and the lower end of the diagonal brace are welded to the deck surface, and the floating crane is unhooked; after the welding inspection is completed, the process hinge point and scaffolding platform at the diagonal brace closing mouth are removed, and 3mm grinding allowance is reserved when cutting, and the parent material must not be damaged. After cutting, the paint is repaired and the main lifting ear of the front leg is retained; S5: Loading the rear legs of the herringbone frame onto the ship: Move the rear legs of the herringbone frame to the dock, re-measure the size of the longitudinal node plate opening at the rear leg rib position of the floating ship, take multiple points of measurement up and down, and adjust the deviation in advance in combination with the size of the lower notch of the rear legs of the herringbone frame; install the positioning stopper at the rear leg, and use the original triangular stopper; use the floating crane to hoist the rear legs of the herringbone frame onto the ship; and when hoisting onto the ship, turn the horizontal rear legs of the herringbone frame over to an inclined state; hoist the rear legs onto the ship at an inclined state of 17°; slowly insert the rear legs into the longitudinal node plate at the rear leg rib position of the floating ship, and then slowly lower the hook head to make it The lower end of the rear leg is placed on the deck surface, and the deck surface is padded with wooden boards in advance; the left hook of the floating crane is slowly de-stressed, and the right hook is simultaneously increased in force, until the right hook carries no less weight than the front leg, and the left hook is completely unhooked; the floating crane is slowly moved upward as a whole, and the movement of the floating crane drives the inclination angle of the rear leg to change from 17° to 2°-3° and then stops; while moving, the steel wire rope of the right hook is simultaneously tightened to ensure that the right hook remains stressed and the lower end of the rear leg remains on the ground; after the right leg is erected to an angle of 2°-3°, the right hook is slowly lifted until the rear leg is fully erected, at which time the right hook is fully loaded and the rear leg is completely off the ground; S6: Welding of the rear legs of the herringbone frame: Use a floating crane to adjust the rear legs of the herringbone frame, position the lower end according to the ground sample line, and position the upper closing mouth using a process guide plate; position the dimensions of the ship width and length direction on the deck surface at the lower end, adjust the staggered sides and gaps of the upper closing mouth to the theoretical dimensions, and use a card to fix the rear legs after the overall verticality is ≤20mm; install the transverse node plate at the lower end of the rear legs; and weld according to welding requirements; When the S3 front leg assembly is on board, when the front leg is positioned and adjusted, in order to prevent the diagonal brace from affecting its angle, the lower end of the diagonal brace needs to be raised first; the margin of the lower end of the front leg is trimmed and cut into place, and it is fixed with a cama after adjusting it to the theoretical size; pay attention to fine-tuning the node plate at the lower end of the front leg so that it is aligned with the hull structure, and the misalignment deviation is ≤3mm; adjust the diagonal brace angle, open the two sides, mark and trim the margin of the lower end of the diagonal brace, and make a bevel according to the requirements of the drawing; trim the margin of the diagonal brace into place, adjust the size to the theoretical size, and fix it with a cama; report the size before welding.

2. The method for installing a super large floating crane herringbone frame according to claim 1, characterized in that: During the welding of the S4 front leg assembly: welding dimension inspection requirements: the height from the deck surface to the upper end of the front leg is required to be 46964±5mm; the front leg positioning deviation is ≤5mm, and the node plate and hull structure reinforcement misalignment deviation is ≤3mm; the diagonal brace and front leg installation angle deviation must be ≤0.01°, and the deviation between the pipe center and the corresponding rib position is ≤10mm.

3. The method for installing a super large floating crane herringbone frame according to claim 1, characterized in that: During the welding of the rear legs of the S6 A-frame: the hook can be removed after 1 / 3 of the base welding of the upper and lower closing mouths of the rear legs is completed; the three process supports at the upper and lower parts of the front and rear legs can be removed using the auxiliary hook of the gantry crane after the base welding is completed; the scaffolding platform at the closing mouth of the front leg needs to be removed after the welding and flaw detection of the closing mouth are completed, the sealing and flaw detection of the process holes are completed, and the paint repair is in place; when removing, pay attention to protecting the paint; the height requirement from the deck surface to the upper plane of the upper end beam is 53646±15mm; the positioning deviation of the rear leg is ≤10mm, and the misalignment deviation of the node plate and the hull structure is ≤3mm; the overall verticality deviation of the rear leg is required to be ≤20mm.